Project Management of Rooppur NPP BANGLADESH Md. Hasinur Rahman Principal Scientific Officer Construction of Rooppur NPP Project Bangladesh Atomic Energy Commission 18 December 2014, IAEA Headquarters, Vienna, Austria
Transcript
Page 1: Project Management of Rooppur NPP · PDF fileProject Management of Rooppur NPP BANGLADESH Md. Hasinur Rahman Principal Scientific Officer Construction of Rooppur NPP Project Bangladesh

Project Management of

Rooppur NPP

BANGLADESH

Md. Hasinur Rahman Principal Scientific Officer

Construction of Rooppur NPP Project

Bangladesh Atomic Energy Commission

18 December 2014, IAEA Headquarters, Vienna, Austria

Page 2: Project Management of Rooppur NPP · PDF fileProject Management of Rooppur NPP BANGLADESH Md. Hasinur Rahman Principal Scientific Officer Construction of Rooppur NPP Project Bangladesh

Outline

Introduction

Major Milestones in the Development of

National Nuclear Power Programme

Management System of Rooppur NPP

Conclusion

Page 3: Project Management of Rooppur NPP · PDF fileProject Management of Rooppur NPP BANGLADESH Md. Hasinur Rahman Principal Scientific Officer Construction of Rooppur NPP Project Bangladesh

A Brief Introduction

Page 4: Project Management of Rooppur NPP · PDF fileProject Management of Rooppur NPP BANGLADESH Md. Hasinur Rahman Principal Scientific Officer Construction of Rooppur NPP Project Bangladesh

Full name: People's Republic of Bangladesh Population: 160 million Area: 143,998 sq km (55,598 sq miles) Population Density: 1034 per sq km Major language: Bengali Educaction Rate: 60% Major Profession: Agriculture, 50% GDP Major religions: Islam Main exports: Garments, fish, jute goods, leather products

Page 5: Project Management of Rooppur NPP · PDF fileProject Management of Rooppur NPP BANGLADESH Md. Hasinur Rahman Principal Scientific Officer Construction of Rooppur NPP Project Bangladesh

Major Milestones in the Development of National

Nuclear Power Programme

Page 6: Project Management of Rooppur NPP · PDF fileProject Management of Rooppur NPP BANGLADESH Md. Hasinur Rahman Principal Scientific Officer Construction of Rooppur NPP Project Bangladesh

The Perspective Plan of Bangladesh: 2010 – 2021, the National Development Policy Document established the sector-wise development strategy for materializing “the Vision 2021” of Bangladesh government;

The power sector has given the top priority, a target of 20,000 MW electricity generation has been set up by 2021 to achieve the objectives of the Vision 2021;

The Perspective Plan and ‘Power System Master Plan 2010’ includes diversified energy options: an addition of 2000 MW(e) Nuclear Capacity by 2021 and 4000 MW(e) by 2030;

The National Parliament passed a resolution in 2010 : “In order to overcome the increasing power crisis in the country nuclear power plant shall be established immediately”;

Page 7: Project Management of Rooppur NPP · PDF fileProject Management of Rooppur NPP BANGLADESH Md. Hasinur Rahman Principal Scientific Officer Construction of Rooppur NPP Project Bangladesh

A Framework Agreement on Peaceful Uses of Atomic Energy between the government of Bangladesh and the Russian Federation signed on 21st May 2010;

A Cooperation Agreement concerning the construction of a nuclear power plant in Bangladesh between the Government of Bangladesh and the Russian Federation signed on 2nd November 2011;

An Agreement on State Export Credit between the Government of Bangladesh and the Russian Federation for financing the preparatory stage of Rooppur NPP construction and an MOU on Financing the Main stage of construction for Rooppur NPP signed on 15 January, 2013;

Under the State Export Credit Agreement 3 (three) separate Contracts already have been signed with vendor for preparatory stage of activities up to FCD.

Page 8: Project Management of Rooppur NPP · PDF fileProject Management of Rooppur NPP BANGLADESH Md. Hasinur Rahman Principal Scientific Officer Construction of Rooppur NPP Project Bangladesh

National Committee headed by the Hon'able Prime Minister (June 2010) formed to provide directives to the relevant ministries/agencies on the activities/ interventions to be carried out and the policy decisions on issues related to RNPP implementation;

Technical Committee headed by the Minister of MOST, formed to coordinate and monitor the development of nuclear infrastructure and the progress of project activities and provide recommendations for consideration of National Committee (2010);

A Working Group and Eight Sub-Groups, headed by the Secretary, MOST, formed to initiate and coordinate activities of different Organizations/Ministries for establishing required infrastructures as outlined in the IAEA Milestone documents (June 2010) – The NEPIO;

Page 9: Project Management of Rooppur NPP · PDF fileProject Management of Rooppur NPP BANGLADESH Md. Hasinur Rahman Principal Scientific Officer Construction of Rooppur NPP Project Bangladesh

Prime Minister

Working Group

Secretary MOST

Technical Committee

Working Sub-Groups (Ministry)

Development of Human Resources

Funding and Financing

National Participation

Nuclear Fuel Cycle, Waste Management and

Environ Monitoring

BAEC

Coordination Committee

Nuclear Power and Energy Division (NPED)

Ownership, Project

execution & Management

Legal and Regulatory

International Obligations

Development of Human

Resources

Grid System

Development

Funding and Financing

Nuclear FC, WM and Environ

Monitoring

National Participation & Procurement

NEPIO

Minister MOST

National Committee

Sub-Committees on RNPP (BAEC)

Legal and Regulatory Aspects, International

Obligations

Heavy Equipment Transportation Planning

Ownership, Project execution and Project

Management

Grid System Nuclear Safety and Radiation Control Division (NSRCD)

The NEPIO - Nuclear Power Programme of Bangladesh

Page 10: Project Management of Rooppur NPP · PDF fileProject Management of Rooppur NPP BANGLADESH Md. Hasinur Rahman Principal Scientific Officer Construction of Rooppur NPP Project Bangladesh

The “Bangladesh Atomic Energy Regulatory Authority (BAER) Act-2012” passed by the government on 31 May 2012;

An independent nuclear regulatory authority - Bangladesh Atomic Energy Regulatory Authority established on 12 February, 2013;

The BAER Authority is establishing and adopting necessary regulations, standards, codes and guides, systems or processes for its regulatory function of all kinds of nuclear installations and radiation practices in the country.

An Agreement on cooperation in the field of nuclear and radiation safety in the use of nuclear energy for peaceful purposes between the Nuclear Regulatory Authority, Russian Federation and the Ministry of Science and Technology, Bangladesh signed in February 2012;

Page 11: Project Management of Rooppur NPP · PDF fileProject Management of Rooppur NPP BANGLADESH Md. Hasinur Rahman Principal Scientific Officer Construction of Rooppur NPP Project Bangladesh

Management System of Rooppur NPP

Page 12: Project Management of Rooppur NPP · PDF fileProject Management of Rooppur NPP BANGLADESH Md. Hasinur Rahman Principal Scientific Officer Construction of Rooppur NPP Project Bangladesh

The government approved a project - Construction of Rooppur Nuclear Power Plant (First Phase) on 2 April, 2013 for the period FY 2013 - 2017;

• The project document (DPP) prepared based on the guidelines of the Annual Development Program of Bangladesh Government;

• DPP - The Project Definition Document approved by the highest level of the government;

• A project Management Structure has been approved with brief description of responsibilities;

• A general guideline for HR recruitment and development plan has been incorporated in the DPP;

• Project monitoring, reviewing and auditing system has also been established;

Page 13: Project Management of Rooppur NPP · PDF fileProject Management of Rooppur NPP BANGLADESH Md. Hasinur Rahman Principal Scientific Officer Construction of Rooppur NPP Project Bangladesh

Based on national guideline-

Project Implementation Committee (PIC), comprising different stakeholders, sit once in a month for smooth implementation of the project.

Project Steering Committee (PSC), comprising high officials from different ministries, usually sits in two months interval to provide overall guidance and co-ordination of the project activities.

Some other monitoring instruments-

Prime Minister level Monitoring: The Rooppur Nuclear Power Plant (First Phase) Project is considered as the Fast-Track Project of the government under supervision of the Hon’ble Prime Minister;

Ministerial Level Monitoring: A High Level Project Monitoring Team on Rooppur NPP formed (January 2013) comprising members at senior level decision makers for initiating and coordinating activities for implementing Rooppur NPP project;

Page 14: Project Management of Rooppur NPP · PDF fileProject Management of Rooppur NPP BANGLADESH Md. Hasinur Rahman Principal Scientific Officer Construction of Rooppur NPP Project Bangladesh

According to IGA, a Joint Coordination Committee (JCC) has been formed to exercise control and adopt proper measure for successful implementation of the project, which used to sit twice in a year in alternate country.

3 (three) Joint Working Groups (JWG) have been established in the field of

◦ i) Nuclear Infrastructure Development;

◦ ii) Industry Information; and

◦ iii) Nuclear Industry Education (HRD).

Page 15: Project Management of Rooppur NPP · PDF fileProject Management of Rooppur NPP BANGLADESH Md. Hasinur Rahman Principal Scientific Officer Construction of Rooppur NPP Project Bangladesh

• The Project Management Office for Rooppur NPP has been established;

• As approved, total Manpower for the Project Management Office would be 130. Out of this, Govt has already sanctioned 97 posts for recruitment. Now a days, around 55 persons are working in our project office.

• A draft Act “Rooppur Nuclear Power Plant Act-

2014” has been prepared and submitted for government approval.

• Initiatives have been taken to establish an Operator Organization (“Rooppur Nuclear Power Company Limited”, a state own company of BAEC);

Page 16: Project Management of Rooppur NPP · PDF fileProject Management of Rooppur NPP BANGLADESH Md. Hasinur Rahman Principal Scientific Officer Construction of Rooppur NPP Project Bangladesh

Project Organization Structure

Page 17: Project Management of Rooppur NPP · PDF fileProject Management of Rooppur NPP BANGLADESH Md. Hasinur Rahman Principal Scientific Officer Construction of Rooppur NPP Project Bangladesh

A Two-Stages Construction Approach for Construction of Rooppur NPP has been adopted, taking into consideration of the country’s NPP licensing procedure, industrial base to support NPP construction, availability and competence of its human resources for managing the NPP construction, national resources as well as its social and economic condition.

Preparatory Stage of Rooppur NPP Construction

Main Stage of Rooppur NPP Construction

Project Implementation Modality

Page 18: Project Management of Rooppur NPP · PDF fileProject Management of Rooppur NPP BANGLADESH Md. Hasinur Rahman Principal Scientific Officer Construction of Rooppur NPP Project Bangladesh

Preparatory Stage of Construction

Construction and Commissioning

Reports on FE, EIA and Site confirmation for Rooppur NPP

Tech. Docs., Design and Working Docs for Rooppur NPP

Construction and erection works of preparatory stage

Rooppur NPP Acceptance

FE Evaluation, EIA and Site Engineering Survey

and Environmental studies

Site License

General Contract for Construction of NPP

Performance of First Priority Construction,

erection works

Construction

License

Development of NPP Tech. & Working Docs

PSAR, QA

Operational

License

Rooppur NPP Main Stage of Construction

2013 -

2016

2017 –

2021-2

2

Page 19: Project Management of Rooppur NPP · PDF fileProject Management of Rooppur NPP BANGLADESH Md. Hasinur Rahman Principal Scientific Officer Construction of Rooppur NPP Project Bangladesh

Activities related to preparatory stage of construction up to 2016 will be carried out under following Contracts:

Feasibility evaluation, environment impact assessment and site engineering survey and environmental studies for Rooppur NPP – the documentation and materials obtained through these activities will be used for getting Site License;

Development of design documentation, first-priority working documentation and engineering survey for the Design stage of Rooppur NPP – the documentation and materials obtained through these activities will be used for getting Construction License;

First-priority construction and erection works of Rooppur NPP at preparatory stage of construction till to the “first concrete pouring” is in progress;

Page 20: Project Management of Rooppur NPP · PDF fileProject Management of Rooppur NPP BANGLADESH Md. Hasinur Rahman Principal Scientific Officer Construction of Rooppur NPP Project Bangladesh

Development of pre-design & design

documentation and construction activities of

Rooppur NPP will be carried out based on

standards, codes and techno normative

documents of Russian Federation as well as

applicable domestic regulations and observing

IAEA guidelines;

The Quality Assurance Program for Rooppur

NPP is being developed in accordance with

Nuclear Quality Assurance Program of Russian

Federation;

Page 21: Project Management of Rooppur NPP · PDF fileProject Management of Rooppur NPP BANGLADESH Md. Hasinur Rahman Principal Scientific Officer Construction of Rooppur NPP Project Bangladesh

For effective management of the preparatory stage of

activites of Rooppur NPP Project Microsoft Project is

being implemented in the project office. The major

facilities of this Project Management System:

Project scheduling (task based time bound),

Dissemination of works (responsible personnel/ sections),

Daily monitoring of progress (progress monitoring and reviewing the progress by person and by task),

Risk and obstacle of execution finding and mitigation (through project meeting and consultation).

Establishment of Management System

Page 22: Project Management of Rooppur NPP · PDF fileProject Management of Rooppur NPP BANGLADESH Md. Hasinur Rahman Principal Scientific Officer Construction of Rooppur NPP Project Bangladesh

Snapshot of MS Project Management for Rooppur NPP (User Interface)

Page 23: Project Management of Rooppur NPP · PDF fileProject Management of Rooppur NPP BANGLADESH Md. Hasinur Rahman Principal Scientific Officer Construction of Rooppur NPP Project Bangladesh

Snapshot of MS Project Management for Rooppur NPP (Task Breakdown)

Page 24: Project Management of Rooppur NPP · PDF fileProject Management of Rooppur NPP BANGLADESH Md. Hasinur Rahman Principal Scientific Officer Construction of Rooppur NPP Project Bangladesh

Snapshot of MS Project Management for Rooppur NPP (Task Breakdown)

Page 25: Project Management of Rooppur NPP · PDF fileProject Management of Rooppur NPP BANGLADESH Md. Hasinur Rahman Principal Scientific Officer Construction of Rooppur NPP Project Bangladesh

A document control process has been developed and

approved. It is written in generic form. It does not

contain security classification.

We are also developing computer based Electronic

Document Control System.

The main feature of this EDCS:

Track record of the documents;

Maintain track record for reviewing and approval

process;

User access, records;

Store and keep recording of the documents;

Document Control System

Page 26: Project Management of Rooppur NPP · PDF fileProject Management of Rooppur NPP BANGLADESH Md. Hasinur Rahman Principal Scientific Officer Construction of Rooppur NPP Project Bangladesh

Document acceptance procedure as well as Work

acceptance procedure have been finalized;

Document review process starting with QA-check and

re-check has been established;

Document approval procedure has been developed and

approved;

Graded approach to be developed based on IAEA Safety

Guide;

Page 27: Project Management of Rooppur NPP · PDF fileProject Management of Rooppur NPP BANGLADESH Md. Hasinur Rahman Principal Scientific Officer Construction of Rooppur NPP Project Bangladesh
Page 28: Project Management of Rooppur NPP · PDF fileProject Management of Rooppur NPP BANGLADESH Md. Hasinur Rahman Principal Scientific Officer Construction of Rooppur NPP Project Bangladesh

Conclusion

Page 29: Project Management of Rooppur NPP · PDF fileProject Management of Rooppur NPP BANGLADESH Md. Hasinur Rahman Principal Scientific Officer Construction of Rooppur NPP Project Bangladesh

Bangladesh has started implementing it’s first Nuclear Power

Plant as well as started developing necessary infrastructure at

the same time with it’s limited resources.

In every steps of this development, Bangladesh is following IAEA

Guidelines to efficiently manage the country’s NPP project.

Bangladesh also trying to develop the Integrated Management

System, before starting the main stage of construction focusing

on proposed ‘Operator Organization’, that are being used in

world’s Nuclear Industry for the Safe and effective operation of

Country’s first NPP.

In this regard, we are seeking assistance from vendor country.

Strong support and wider cooperation from IAEA also need.

Conclusion