Date post: | 31-Dec-2015 |
Category: |
Documents |
Upload: | cuthbert-blake |
View: | 216 times |
Download: | 1 times |
What is a Project Temporary – A project has a beginning and an end
Unique – A project is outside of routine work
Sponsored – A project has a sponsor that provides resources for the work
Why is Project Management Important?
On time (T
ime)
Delivering what was promised (scope)
On budget (Cost)Triple Constraints
Challenged and Failing Software Projects
Successful39%
Challenged43%
Failed18%
Chaos Resolution
SuccessfulChallengedFailed
Chaos Manifesto 2013, The Standish Group
Myers-Briggs Personality Test A test designed to discover how a person sees things and makes decisions
Click on the MBTI link on your desktop
Balanced Teams Activity
Find four people who do NOT have your personality type and sit with them. This is your new team.
Teams that have a variety of personality types tend to perform better because Different personality types tend to see problems differently
One personality type may be better at a task than another
Critical Path Activity – Part 1
Lay the cards end to end in the correct order to make a sandwich
Step1
Step8
Step2
Step3
Step4
Step5
Step6
Step7
The Critical Path
Start
The longest sequence of activities in a project to be completed on time for the project to complete on the due date.
Finish
4 days
1 day 1 day1 day
3 days
1 day
2 days2 days
9 Days
How long does it take to make the sandwich
21 minutes
How can you shorten the time?
Do things in parallel (at the same time)
Remove/change the requirements
Add resources
Shorten the duration to complete a task
Critical Path Activity – Part 2
Card 1
Card 8
Card 2
Card 3
Card4
Card 5
Card 6
Card 7
Repeat the previous activity – this time put the cards in an order that will shorten the time it takes to make the sandwich
Making A Sandwich
Toast
bread
Gather
ingredients
Cook
bacon
EndAssemble
sandwich
Wash
lettuce
Start
Slice
cheese
Cut
tomato
Butter
bread