BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS
1
COURSE / WORKSHOP
PROJECT MANAGEMENT TOOLS FOR SHIPYARD PROJECT MANAGERS
6th March 2017
BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS
2
COURSE / WORKSHOP OBJECTIVE
To provide Shipyard Project Managers and Shipyard personnel with project management tools for planning and controlling projects, using recognized project management standards applied on ship repair industry. Through this course learning experience will be improved by practicing concepts through a real-world ship repair project.
“This will increase the chance of success on your projects”
6th March 2017
BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS
3
• Module 0. Project Management Standards and overview (1 hour): Definition of Project Management. Project Management Standards, Knowledge Areas and Process groups. Project Management in Shipyard industry overview.
• Module 1. WBS for Ship Repair Projects – (4 hours): What is a WBS?. Components of a WBS. Steps to create a WBS for a ship repair project. WBS top 4 Benefits in Ship Repair industry. WBS Manual exercise. Create the WBS for project QUEEN ANDREA using a WBS software.
• Module 2. Critical Path / Ms Project for Ship Repair Projects – (4 to 5 hours): Basic concepts for project scheduling. What is critical path? How to use it in Ship Repair Projects. Critical path Top 5 benefits. Aspects on which the Ship Repair Project Manager should focus in project scheduling. Critical Path Exercise. Steps to Create a project schedule in Ms Project. How to monitor the schedule in Ms Project. Schedule Accuracy level in ship repair projects based on uncertainty. Create the project schedule for project QUEEN ANDREA using Ms Project.
COURSE / WORKSHOP CONTENT
6th March 2017
BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS
4
• Module 3. Time and Cost Control with EVM Ship Repair Projects – (4 to 5 hours): What is EVM?. EVM formulas (Variance, KPIs and Forecast). How to use EVM in Ship Repair Projects to control cost and time (calculations and reports). Relationship between the WBS, Project Schedule (Ms Project) and EVM. Use EVM calculations and reports for the project QUEEN ANDREA.
• Module 4. Risk Management in Ship Repair Projects – (4 hours): What is Risk Management?. Steps for risk management in ship repair projects. Understanding the Risk Register and Risk Assessment Matrix for Ship Repair Projects. Apply Risk Management for project QUEEN ANDREA.
• Module 5. Stakeholders Management in Ship Repair Projects – (4 hours): What is Stakeholder Management?. Identify and analyze ship repair stakeholders. Manage ship repair stakeholders engagement. Identify and analyze stakeholders for project QUEEN ANDREA.
COURSE / WORKSHOP CONTENT
6th March 2017
BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS
5
• Module 6. Ship Repair Project Manager Soft Skills (1 to 2 hours): The 3 propeller blades of knowledge for the Ship Repair Project Manager. Recognized Project Management Certifications. Coordination skills. Overview on negotiation skills.
• Module 7. Multi-Projects (Program) Control using Ms-Project and EVM (3 to 4 hours): What is Multi-Project / Program Management in the ship repair industry. Planning the Program. Controlling the Program. The benefits of controlling the program. Then need of a Program or Project Management Manager in the ship repair industry. Practical exercise using Ms Project and EVM
COURSE / WORKSHOP CONTENT
6th March 2017
BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS
6
COURSE / WORKSHOP METHODOLOGY
The course / workshop methodology is based on “experiential learning”.
Theory + subject specific exercise + real-world ship repair project practice
MV “QUEEN ANDREA”
IMO number: 0000000Length Overall: 250 mBreadth: 40.06 mGross Tonnage: 120.000 Vessel Type: Tanker
6th March 2017
BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS
7
COURSE / WORKSHOP FOUNDATION
• PMBOK guide from PMI• My upcoming book “Shipyard Project
Management”
Coming soon May 2017
BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS
8
EDUCATIONAL BACKGROUND
• Industrial Engineer• Post Graduate - Diploma in Project Management• Project Management for Engineering projects course from Delft
University• Certified as Project Management Professional - PMP by the Project
Management Institute (PMI) since 2011.
EXPERIENCE
• 10 years of experience in the industry• Positions held: Project Manager, Risk Engineer, Production
Superintendent (Shipbuilding), Marine Maintenance Supervisor.• 6 years of experience using PMI Standard in Ship Repair Projects
• Author and speaker about Project Management focused on Ship Repair
6th March [email protected]
BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS
9
…… based on PMI Standard
MODULE 0
PROJECT MANAGEMENT
STANDARDS AND OVERVIEW
“….What is Project Management about? Project Management is about how to organize yourself, your team and your project….”
PMBOK - PMI
APMBOK - APM PRINCE2 - AXELOS
BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS
10
…… based on PMI Standard
MODULE 0
PROJECT MANAGEMENT
STANDARDS AND OVERVIEW
EXISTING PROJECT MANAGEMENT WAY
OF THINKING IN SHIPREPAIR INDUSTRY
OLD FASHIONED MANAGEMENT
STYLE
QUA
LITY
MAN
AGEM
ENT
HU
MAN
RES
OU
RCE
MAN
AGEM
ENT
COM
MU
NIC
ATIO
N M
ANAG
EMEN
T
RISK
MAN
AGEM
ENT
PRO
CURE
MEN
T M
ANAG
EMEN
T
STAK
EHO
LDER
MAN
AGEM
ENT
Cost
ScopeTime
SHIPS TECHNICAL
KNOWLEDGE
PROJECT MANAGEMENT STANDARDS
SUST
AIN
IBIL
ITY
THE CORRECT WAY TO MANAGE SHIPREPAIR PROJECTS
BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS
11
…… based on PMI Standard
IF YOU ARE INTERESTED TO KNOW MORE AND LEARN ABOUT THIS MODULE PLEASE CONTACT ME [email protected]
MODULE 0
PROJECT MANAGEMENT
STANDARDS AND OVERVIEW
BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS
12
…… based on PMI Standard
MODULE 1
WBS – WORK BREAKDOWN STRUCTURE
APPLIED TO SHIP REPAIR
PROJECTS
BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS
13
…… based on PMI Standard
MODULE 1
WBS – WORK BREAKDOWN STRUCTURE
APPLIED TO SHIP REPAIR
PROJECTSVessel Location /
Deliverable
Work Packages
Main Deliverable or Project
Figure 13. WBS example
1
1.1
1.1.1
1.2
1.1.2 1.2.1
LEVEL 1
LEVEL 2
LEVEL 3
WBS COMPONENTS
• Deliverable: is what we are going to deliver, either a service or a product requested by the client.• Work package: is the lowest level of decomposition. As from the work packages you can define the activities• ID number: is the number located on each component for easy identification• Level of decomposition: is related how deep you decompose each element
BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS
14
…… based on PMI Standard
MODULE 1
WBS – WORK BREAKDOWN STRUCTURE
APPLIED TO SHIP REPAIR
PROJECTS
HOW TO CREATE AND USE A WBS FOR SHIP REPAIR PROJECTS
STEP 1. Collect input
documents
STEP 2. Divide ship
per locations
and systems
STEP 3. Define the software to
be used
STEP 4.Create the
WBS
BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS
15
…… based on PMI Standard
MODULE 1
WBS – WORK BREAKDOWN STRUCTURE
APPLIED TO SHIP REPAIR
PROJECTS
IF YOU ARE INTERESTED TO KNOW MORE AND LEARN ABOUT THIS MODULE PLEASE CONTACT ME [email protected]
BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS
16
…… based on PMI Standard
MODULE 2
CRITICAL PATH – MS PROJECT
CRITICAL PATH – MS PROJECT
BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS
17
…… based on PMI Standard
MODULE 2
CRITICAL PATH – MS PROJECT
CRITICAL PATH METHOD
Critical Path is the longest path from the beginning to the end of the project. A path is a sequence of activities in a certain time frame and the longest path is the one leading the finish of the project
BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS
18
…… based on PMI Standard
MODULE 2
CRITICAL PATH – MS PROJECT
IN WHAT ASPECTS THE SHIPREPAIR PROJECT MANAGER SHOULD FOCUS WHILE PLANNING AND CONTROLLING THE PROJECT SCHEDULE?
BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS
19
…… based on PMI Standard
MODULE 2
CRITICAL PATH – MS PROJECT
STEPS TO CREATE A SCHEDULE IN MS-PROJECT
Transfer WBS information into MS PROJECT
Adjust initial settings: Calendar and Project start date
Define activities and milestones
Define activity duration and sequence the activities
Calculate the critical path
Save baseline
1
2
3
5
6
4
BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS
20
…… based on PMI Standard
MODULE 2
CRITICAL PATH – MS PROJECT
STEPS TO CREATE A SCHEDULE IN MS-PROJECT
Define activity duration and sequence the activities4
BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS
21
…… based on PMI Standard
MODULE 2
CRITICAL PATH – MS PROJECT
IF YOU ARE INTERESTED TO KNOW MORE AND LEARN ABOUT THIS MODULE PLEASE CONTACT ME [email protected]
BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS
22
…… based on PMI Standard
MODULE 3
TIME AND COST CONTROL WITH
EVM
BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS
23
…… based on PMI Standard
MODULE 3
TIME AND COST CONTROL WITH
EVM
Project information
Project estimates: Price / MH / Materials / Contractor invoice price /
Contractor prices / SC % margin
Monitoring dates: PV, EV, AC, Variance for Man hours and
Materials
Jobs description + Control account
Totals: Revenues, MH, Materials, Subcontractors
Totals per date: PV, EV, AC, Variance for MH and Materials
BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS
24
…… based on PMI Standard
MODULE 3
TIME AND COST CONTROL WITH
EVM
BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS
25
…… based on PMI Standard
MODULE 3
TIME AND COST CONTROL WITH
EVM
IF YOU ARE INTERESTED TO KNOW MORE AND LEARN ABOUT THIS MODULE PLEASE CONTACT ME [email protected]
BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS
26
…… based on PMI Standard
MODULE 4
RISK MANAGEMENT
FOR SHIP REPAIR
PROJECTS
BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS
27
…… based on PMI Standard
MODULE 4
RISK MANAGEMENT
FOR SHIP REPAIR
PROJECTS
STEPS FOR PROJECT RISK MANAGEMENT IN SHIP REPAIR PROJECTS 1. Identify Risks: Once the scope is known a risk identification can be performed. Risk can be identified during project
initiation till the end.
This are the most important aspects to consider when you are identifying Risk and Causes:
• The Risks must be identified based on the Project Objectives• The Risks cannot be a constraint (a constraint is something that already exists and should be responded with
a contingency plan)• When the risk is going to be identified you should ask yourself: What can go wrong that can impact the
project objectives?• The cause of the risk could be a constraint, an assumption, requirement or condition that originates the
unwanted or wished event.
Example 1: Lack of man power, due to interference with other projects, impacting undocking date and departure date.Example 2: To not finish Hull blasting on planned date, due to extreme weather conditions on April, impacting dry-docking time of the vessel
BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS
28
…… based on PMI Standard
MODULE 4
RISK MANAGEMENT
FOR SHIP REPAIR
PROJECTS
BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS
29
…… based on PMI Standard
MODULE 4
RISK MANAGEMENT
FOR SHIP REPAIR
PROJECTS
IF YOU ARE INTERESTED TO KNOW MORE AND LEARN ABOUT THIS MODULE PLEASE CONTACT ME [email protected]
BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS
30
…… based on PMI Standard
MODULE 5
STAKEHOLDER MANAGEMENT
FOR SHIP REPAIR
PROJECTS
STAKEHOLDER MANAGEMENT FOR
SHIP REPAIR PROJECTS
BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS
31
…… based on PMI Standard
MODULE 5
STAKEHOLDER MANAGEMENT
FOR SHIP REPAIR
PROJECTS
Stakeholder Identification
BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS
32
…… based on PMI Standard
MODULE 5
STAKEHOLDER MANAGEMENT
FOR SHIP REPAIR
PROJECTS
Figure 12. Stakeholders Analysis Matrix
Stakeholder Analysis Matrix
BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS
33
…… based on PMI Standard
MODULE 5
STAKEHOLDER MANAGEMENT
FOR SHIP REPAIR
PROJECTS
IF YOU ARE INTERESTED TO KNOW MORE AND LEARN ABOUT THIS MODULE PLEASE CONTACT ME [email protected]
BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS
34
…… based on PMI Standard
MODULE 6
SOFT SKILLS FOR SHIPREPAIR
PROJECT MANAGERS
Project Management
Technical Business
BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS
35
…… based on PMI Standard
MODULE 6
SOFT SKILLS FOR SHIPREPAIR
PROJECT MANAGERS
BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS
36
…… based on PMI Standard
MODULE 6
SOFT SKILLS FOR SHIPREPAIR
PROJECT MANAGERS
IF YOU ARE INTERESTED TO KNOW MORE AND LEARN ABOUT THIS MODULE PLEASE CONTACT ME [email protected]
BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS
37
…… based on PMI Standard
MODULE 7
MULTI-PROJECTS CONTROL
USING EVM
BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS
38
…… based on PMI Standard
MODULE 7
MULTI-PROJECTS CONTROL
USING EVM
Figure 26. Program planning in MS Project
BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS
39
…… based on PMI Standard
MODULE 7
MULTI-PROJECTS CONTROL
USING EVM
1 765432 1098 1211
13
Figure 27. Program EVM report
BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS
40