+ All Categories
Home > Documents > Project Manager: Tim Brown Project Editor: Tabatha Doughty Project Engineer: Drew Furry Project...

Project Manager: Tim Brown Project Editor: Tabatha Doughty Project Engineer: Drew Furry Project...

Date post: 22-Dec-2015
Category:
View: 220 times
Download: 1 times
Share this document with a friend
Popular Tags:
36
Project Manager: Tim Brown Project Editor: Tabatha Doughty Project Engineer: Drew Furry Project Engineer: Jim Walter
Transcript
Page 1: Project Manager: Tim Brown Project Editor: Tabatha Doughty Project Engineer: Drew Furry Project Engineer: Jim Walter.

Project Manager: Tim BrownProject Editor: Tabatha Doughty

Project Engineer: Drew FurryProject Engineer: Jim Walter

Page 2: Project Manager: Tim Brown Project Editor: Tabatha Doughty Project Engineer: Drew Furry Project Engineer: Jim Walter.

Today’s Agenda

• Project Description & Approach• Alternative Solutions• Final Design Results

– Proposed Roadway– Horizontal & Vertical Alignment– Pavement Design– Hydraulic Design– Construction Plan– Cost Analysis

• Summary - Q & A

Page 3: Project Manager: Tim Brown Project Editor: Tabatha Doughty Project Engineer: Drew Furry Project Engineer: Jim Walter.

Project Description

• 13-acres of land • Multiple curves in the road, storage buildings,

railroad tracks and other outdoor storage• 0.6-mile road connects the main access highway

to the storage facility• Recent changes in ordinance transport have

brought up this issue

Page 4: Project Manager: Tim Brown Project Editor: Tabatha Doughty Project Engineer: Drew Furry Project Engineer: Jim Walter.

Project Description

• Challenges– Railroad crossings must be limited– Crossing can not be over a “frog” – Road must meet Navy, INDOT, and

AASHTO codes and regulations

Page 5: Project Manager: Tim Brown Project Editor: Tabatha Doughty Project Engineer: Drew Furry Project Engineer: Jim Walter.
Page 6: Project Manager: Tim Brown Project Editor: Tabatha Doughty Project Engineer: Drew Furry Project Engineer: Jim Walter.

Project Approach

• Site Assessment

- walkthrough, site survey, map overview• Existing Subsurface Conditions

- Soil assessment

- Boring samples from ATC Associates• Codes and Regulations

- challenges- must comply with Navy, AASHTO and INDOT codes and regulations

Page 7: Project Manager: Tim Brown Project Editor: Tabatha Doughty Project Engineer: Drew Furry Project Engineer: Jim Walter.

Project Approach

• Assessment of Design Constraints– Wildlife protection, subgrade conditions,

hydrological issues• Design

– Consider possible alternatives– Design appropriate solution based on criteria

Page 8: Project Manager: Tim Brown Project Editor: Tabatha Doughty Project Engineer: Drew Furry Project Engineer: Jim Walter.

Alternative Solutions

• Five alternative solutions• Developed by RH Roadways with suggestions

from client & faculty• Created Evaluation Matrix• Design of best alternative

Page 9: Project Manager: Tim Brown Project Editor: Tabatha Doughty Project Engineer: Drew Furry Project Engineer: Jim Walter.

Alternative 1 – Existing Road

Page 10: Project Manager: Tim Brown Project Editor: Tabatha Doughty Project Engineer: Drew Furry Project Engineer: Jim Walter.

Alternative 2 – Modify Existing Road

Page 11: Project Manager: Tim Brown Project Editor: Tabatha Doughty Project Engineer: Drew Furry Project Engineer: Jim Walter.

Alternative 3 – New Alignment South

Page 12: Project Manager: Tim Brown Project Editor: Tabatha Doughty Project Engineer: Drew Furry Project Engineer: Jim Walter.

Alternative 4 – New Alignment North A

Page 13: Project Manager: Tim Brown Project Editor: Tabatha Doughty Project Engineer: Drew Furry Project Engineer: Jim Walter.

Alternative 5 – New Alignment North B

Page 14: Project Manager: Tim Brown Project Editor: Tabatha Doughty Project Engineer: Drew Furry Project Engineer: Jim Walter.

Evaluation Matrix

Page 15: Project Manager: Tim Brown Project Editor: Tabatha Doughty Project Engineer: Drew Furry Project Engineer: Jim Walter.

Comparison

Existing Roadway• Roadway conditions

fair/poor• 7 RR crossings• 85-feet radius of

curvature• 10% maximum

vertical grade • Little signage

Proposed Roadway• Excellent roadway

conditions• 5 RR Crossings• 500-feet minimum

radius of curvature• 3% maximum vertical

grade• Proper signage

(posted 25mph)

Page 16: Project Manager: Tim Brown Project Editor: Tabatha Doughty Project Engineer: Drew Furry Project Engineer: Jim Walter.

Comparison

Existing Roadway• Lack of pavement

markings

• Width of 16-feet

• Average thickness of 4-inches

Proposed Roadway• Adequate markings

(centerline, edges, etc.)

• Width of Road 24-feet with shoulders and ditches

• Pavement total thickness of 10-inches

Page 17: Project Manager: Tim Brown Project Editor: Tabatha Doughty Project Engineer: Drew Furry Project Engineer: Jim Walter.

Horizontal Alignment

• Plan View Map

Page 18: Project Manager: Tim Brown Project Editor: Tabatha Doughty Project Engineer: Drew Furry Project Engineer: Jim Walter.

Typical Cross Section

Page 19: Project Manager: Tim Brown Project Editor: Tabatha Doughty Project Engineer: Drew Furry Project Engineer: Jim Walter.

Vertical Alignment

• Profile View Map

Page 20: Project Manager: Tim Brown Project Editor: Tabatha Doughty Project Engineer: Drew Furry Project Engineer: Jim Walter.

Pavement Design

•Computed an Equivalent Axel Load (EAL)– Traffic Study – 200 trucks per day each way– Used traffic data and tractor trailer dimensions

and weight for EAL design - 2.9 Million EAL– Calculated Stacker EAL – insignificant• Pavement Thickness – CBR value from ATC Associates + EAL– Asphalt Institute Manual to design 4 options

Page 21: Project Manager: Tim Brown Project Editor: Tabatha Doughty Project Engineer: Drew Furry Project Engineer: Jim Walter.

Pavement Options

Option1:• 2” Asphalt Concrete

Surface• 9” Asphalt Concrete Base

Option 3:• 2” Asphalt Concrete

Surface• 8” Asphalt Concrete Base• 6” Untreated Aggregate

Subbase

Option2:• 2” Asphalt Concrete

Surface• 15” Type III Emulsified

Asphalt Base

Option 4:• 2” Asphalt Concrete

Surface• 13.5” Type III Emulsified

Asphalt Base• 6” Untreated Aggregate

Subbase

Page 22: Project Manager: Tim Brown Project Editor: Tabatha Doughty Project Engineer: Drew Furry Project Engineer: Jim Walter.

Pavement Cost

• Data collected from INDOT website detailing their project costs for 2003.

• HMA costs include labor and equipment.

Page 23: Project Manager: Tim Brown Project Editor: Tabatha Doughty Project Engineer: Drew Furry Project Engineer: Jim Walter.

Final Pavement Design

2” Asphalt Concrete Surface 8” Asphalt Concrete Base 6” Untreated Aggregate Subbase

Page 24: Project Manager: Tim Brown Project Editor: Tabatha Doughty Project Engineer: Drew Furry Project Engineer: Jim Walter.

Hydraulic Design

• Place 3 culverts – Corrugated Metal Pipe – 12” Diameter

• Ditches– Flow of 1.27 cubic feet per second– Depth = 0.5 feet – Slope = 3:1

Page 25: Project Manager: Tim Brown Project Editor: Tabatha Doughty Project Engineer: Drew Furry Project Engineer: Jim Walter.

Culvert Locations

Page 26: Project Manager: Tim Brown Project Editor: Tabatha Doughty Project Engineer: Drew Furry Project Engineer: Jim Walter.

Construction Alternatives

• Traffic Control - Three Options• Method 1:

– Complete shutdown of road with a detour to divert traffic during construction

• Method 2:– Shut down one lane while remaining lane stays

open for traffic flow• Method 3:

– Same as method 2, save an added detour to ease traffic flow through the project area.

Page 27: Project Manager: Tim Brown Project Editor: Tabatha Doughty Project Engineer: Drew Furry Project Engineer: Jim Walter.

Traffic Detour Method Matrix

Page 28: Project Manager: Tim Brown Project Editor: Tabatha Doughty Project Engineer: Drew Furry Project Engineer: Jim Walter.

Traffic Control Method 3

Page 29: Project Manager: Tim Brown Project Editor: Tabatha Doughty Project Engineer: Drew Furry Project Engineer: Jim Walter.

Traffic Detour Route

Page 30: Project Manager: Tim Brown Project Editor: Tabatha Doughty Project Engineer: Drew Furry Project Engineer: Jim Walter.

Erosion & Sediment Control Plan

• Erosion control points of interest:– Minimum clearing and grading– Minimum erosion due to short project time– Runoff is non-existent – no present streams– After bare soil removed, silt fences will be

needed along sloped areas– Upon project completion, areas must be

seeded and slopes protected with erosion control blankets in place

Page 31: Project Manager: Tim Brown Project Editor: Tabatha Doughty Project Engineer: Drew Furry Project Engineer: Jim Walter.

Erosion Control Map

• Insert 11x17 erosion control map

Page 32: Project Manager: Tim Brown Project Editor: Tabatha Doughty Project Engineer: Drew Furry Project Engineer: Jim Walter.

Soil Management

• Borrow location• Location for cut soil to be stored• “Phase-construction”• Topsoil stockpiles• Soil testing required according to AASHTO and

INDOT Specifications

Page 33: Project Manager: Tim Brown Project Editor: Tabatha Doughty Project Engineer: Drew Furry Project Engineer: Jim Walter.

Waste Management

• Large capacity worksite dumpsters• Construction fencing• Planned stockpiling• Pavement removal

~2500 yd^2

Page 34: Project Manager: Tim Brown Project Editor: Tabatha Doughty Project Engineer: Drew Furry Project Engineer: Jim Walter.

Cost Analysis

Page 35: Project Manager: Tim Brown Project Editor: Tabatha Doughty Project Engineer: Drew Furry Project Engineer: Jim Walter.

Summary

• Project Description & Approach• Alternative Solutions• Final Design Results

– Proposed Roadway– Horizontal & Vertical Alignment– Pavement Design– Hydraulic Design– Construction Plan– Soil & Waste Management– Cost Analysis

Page 36: Project Manager: Tim Brown Project Editor: Tabatha Doughty Project Engineer: Drew Furry Project Engineer: Jim Walter.

Questions???


Recommended