+ All Categories
Home > Documents > Project Modul

Project Modul

Date post: 03-Apr-2018
Category:
Upload: nabil-benchakroune
View: 218 times
Download: 0 times
Share this document with a friend

of 51

Transcript
  • 7/28/2019 Project Modul

    1/51

    0

    Expedited Permit Process

    for PV Systems

    with Detailed Explanationto Help Guide Thru the Process

    Preparedfor:

    NewMexicoStateUniversity

    SolarAmericaBoardforCodesandStandards

    (availableatwww.SolarABCS.org)

    Preparedby:

    BrooksEngineering

    873KellsCircle

    Vacaville,CA95688

    www.brooksolar.com

    Version4

    May2009

  • 7/28/2019 Project Modul

    2/51

    1

    Dedication:

    Thisdocumentisdedicatedtotwokeyindividualsthatrepresenttheverybestofthosewho

    haveworkedonthecodesandstandardsprocessesastheyrelatetoPVsystems.Thesetwo

    amazingpeople,TimOwens,ofSantaClaraBuildingDepartment,andChuckWhitaker,ofBEW

    Engineering,passed

    away

    in

    the

    months

    prior

    to

    the

    release

    of

    this

    standardized

    permitting

    process.

    TimOwens:

    TimOwenspassedawayinDecemberof2008attheageof??inthemidstofadistinguished

    careerintheelectricaltradesandcodeenforcement.WhileworkingasChiefElectrical

    InspectorfortheCityofSanDiegoin1999,Timwasthefirstjurisdictionalofficertoput

    togetherasimplifiedpermittingprocessforPVsystems.Hisdesiretoseesuchaprocess

    becomecommonplaceiswhathasdriventhisauthortoworkonimprovingpermittingand

    approvalprocessesforPVsystemsforthepastdecade.Thesolarcommunity,lostatruefriend

    andpartnerwhowasdedicatedtothesuccessofsolarphotovoltaicsystemsinCaliforniaand

    therestoftheU.S.

    ChuckWhitaker:

    ChuckWhitakerpassedawayinearlyMayof2009attheageof50inthemidstofa

    distinguishedcareersupportingthedevelopmentandimplementationofmostofthecodesand

    standardsthegovernandsupportPVsystemsbothnationallyandinternationally.Hispassing

    coincidedwiththeinitialreleaseofthisstandardizedpermittingprocess.Theauthorhadthe

    privilegeofknowingChuckfortwodecadesandworkingcloselywithhimforover8yearsashis

    employeeand

    colleague.

    It

    is

    difficult

    to

    overstate

    Chucks

    contribution

    to

    the

    PV

    industry

    since

    hisinfluenceisfoundinnearlyeverycodeandstandardthathasbeendevelopedforPV

    equipmentandsystemsoverthepast25years.Itisonlyfittingthatthisdocument,which

    includeshisinfluence,bededicatedtohismemory.AhugeholeisleftinthePVindustrywith

    Chuckspassing,anditisthehopeofmanyofusinthecodesandstandardsarenatobeableto

    carryonhistirelessworkwithasemblanceoftheskill,whit,andhumorthatwasthehallmark

    ofthisamazingindividual.

  • 7/28/2019 Project Modul

    3/51

    2

    INTRODUCTION:............................................................................................................................. 3

    ExpeditedPermitProcessforSmallScalePVSystems................................................................. 4

    ExpeditedPermitGuidelinesforSmallScalePVSystems............................................................ 8

    Section1. RequiredInformationforPermit:........................................................................... 8

    Section2.

    Step

    1:

    Structural

    Review

    of

    PV

    Array

    Mounting

    System

    .......................................

    8

    Section3. Step2:ElectricalReviewofPVSystem(CalculationsforElectricalDiagram)......10

    Section4. InverterInformation............................................................................................. 11

    Section5. ModuleInformation.............................................................................................. 12

    Section6. Arrayinformation................................................................................................. 13

    a) NUMBEROFMODULESINSERIES................................................................................. 13

    b) NUMBEROFPARALLELCIRCUITS.................................................................................. 13

    c) LOWESTEXPECTEDAMBIENTTEMP............................................................................. 13

    d) HIGHESTCONTINUOUSTEMP(ambient)...................................................................... 13

    Section7. SIGNS..................................................................................................................... 14

    a) PVPOWERSOURCE....................................................................................................... 14

    b) WARNINGSIGNREQUIREDBYNEC690.17.................................................................. 15

    c) PointofConnectionSign[NEC690.54]......................................................................... 15

    Section8. WiringandOvercurrentProtection...................................................................... 16

    a) DCWiringSystems:....................................................................................................... 16

    b) ACWiringSystems........................................................................................................ 18

    Section9. ACPointofConnection......................................................................................... 18

    Section10. Grounding......................................................................................................... 19

    a) SystemGrounding......................................................................................................... 19

    b) EquipmentGrounding................................................................................................... 19

    c) SizingofGroundingConductors................................................................................... 20

    APPENDIX.....................................................................................................................................

    21

    APPENDIXA:EXAMPLESUBMITTAL............................................................................................ 22

    APPENDIXB:STRUCTURAL.......................................................................................................... 26

    STRUCTUREWORKSHEETWKS1................................................................................................... 26

    B.2 SPANTABLES..................................................................................................................... 27

    SpanTableR802.5.1(1),........................................................................................................ 27

    SpanTableR802.5.1(2),........................................................................................................ 28

    APPENDIXC:SPECIALELECTRICALTOPICS.................................................................................. 29

    ModuleFrameGrounding:........................................................................................................... 29

    ACConnectiontoBuildingElectricalSystems.............................................................................. 30

    AC

    Connection

    to

    Load

    Side

    of

    Main

    Service

    Panel

    ......................................................................

    30

    ACConnectiontoSubpanel:......................................................................................................... 31

    ACSupplySideConnection:.......................................................................................................... 32

    SourceCircuitOvercurrentProtection:........................................................................................ 33

    DisconnectingMeans:................................................................................................................... 34

    Provisionsforthephotovoltaicpowersourcedisconnectingmeans:.........................................35

    APPENDIXD:COSTSOFPERMITS................................................................................................ 36

    APPENDIXE:TEMPERATURETABLES........................................................................................... 37

  • 7/28/2019 Project Modul

    4/51

    3

    INTRODUCTION:

    Theonepageexpeditedpermitprocess,andtheaccompanyingdocumentexplainingeachstep,

    providesameanstodifferentiatesystemsthatcanbepermittedquicklyandeasilyduetotheir

    similaritywiththemajorityofsmallscalePVsystems.Asmostsystemshaveunique

    characteristics,they

    may

    be

    handled

    with

    small

    additions

    to

    this

    expedited

    process

    or

    may

    requiremuchmoreinformation,dependingontheuniquenessoftheinstallation.

    ThediagramsshownintheExpeditedPermitProcessareavailableonlineatwww.solarabcs.org

    inaninteractivePDFformatsothatthediagramscanbefilledoutelectronicallyandsubmitted

    eitherinprintedformorviaemailtothelocaljurisdiction.Anelectronicformatisusedsothat

    thesuppliedinformationisstandardizedandlegibleforthelocaljurisdiction.Additional

    drawingswillbeaddedtothewebsiteastheybecomeavailable.

    Theexpeditedprocessdoesprovideforflexibilityinthestructuralreviewincludingspantables

    and

    additional

    information

    found

    in

    Appendix

    B

    of

    this

    explanatory

    document.

    PV

    systems

    with

    batterybackupmaybeabletouseaportionofthisinformationtoassistthepermitting

    process,butarrayconfigurationsandthebatterysystemrequireamoredetailedelectrical

    drawingthanthisprocessprovides.

    TheappendixtothisexplanatorydocumenthasanexamplesubmittalinAppendixAalsohasa

    varietyofspecialelectricaltopicsinAppendixC.ItalsoincludestemperaturetablesinAppendix

    DthatareusedinapplyingtheNationalElectricalCodestemperaturedependentcriteria.This

    documentisintendedtobeusablethroughouttheUnitedStatesandcanprovidestandard

    installationdesigndocumentationformostlocationswithintheU.S.andotherregionsthatuse

    theNationalElectricalCode.

  • 7/28/2019 Project Modul

    5/51

    4

    ExpeditedPermitProcessforSmallScalePVSystemsTheinformationinthisguidelineisintendedtohelplocaljurisdictionsandcontractorsidentifywhenPVsystem

    installationsaresimple,needingonlyabasicreview,andwhenaninstallationismorecomplex.Itislikelythat

    50%75%ofallresidentialsystemswillcomplywiththesesimplecriteria.Forprojectsthatfailtomeetthe

    simplecriteria,aresolutionstepsmaybesuggestedtoprovideapathtopermitapproval.

    RequiredInformation

    for

    Permit:

    1. Siteplanshowinglocationofmajorcomponentsontheproperty.Thisdrawingneednotbeexactlytoscale,butitshouldrepresentrelativelocationofcomponentsatsite(seesuppliedexamplesiteplan).

    PVarraysondwellingswitha3perimeterspaceatridgeandsidesmaynotneedseparatefireservice

    review.

    2. ElectricaldiagramshowingPVarrayconfiguration,wiringsystem,overcurrentprotection,inverter,disconnects,requiredsigns,andacconnectiontobuilding(seesuppliedstandardelectricaldiagram).

    3. Specificationsheetsandinstallationmanuals(ifavailable)forallmanufacturedcomponentsincluding,butnotlimitedto,PVmodules,inverter(s),combinerbox,disconnects,andmountingsystem.

    Step1:StructuralReviewofPVArrayMountingSystemIsthearraytobemountedonadefined,permittedroofstructure? Yes NoIfNoduetononcompliantrooforagroundmount,submitcompletedworksheetforthestructureWKS1.

    RoofInformation:

    1. Istheroofingtypelightweight(Yes=composition,lightweightmasonry,metal,etc)_____________If No,submitcompletedworksheetforroofstructureWKS1(No=heavymasonry,slate,etc).

    2. Doestheroofhaveasingleroofcovering? Yes NoIfNo,submitcompletedworksheetforroofstructureWKS1.

    3. Providemethodandtypeofweatherproofingroofpenetrations(e.g.flashing,caulk).____________MountingSystemInformation:

    1. ThemountingstructureisanengineeredproductdesignedtomountPVmodules? Yes NoIfNo,providedetailsofstructuralattachmentcertifiedbyadesignprofessional.

    2. Formanufacturedmountingsystems,filloutinformationonthemountingsystembelow:a. MountingSystemManufacturer ___________ProductNameandModel#_____________b. TotalWeightofPVModulesandRails___________lbsc. TotalNumberofAttachmentPoints____________d. WeightperAttachmentPoint(bc)_________________lbs(ifgreaterthan40lbs,seeWKS1)e. MaximumSpacingBetweenAttachmentPointsonaRail______________inches(seeproduct

    manualformaximumspacingallowedbasedonmaximumdesignwindspeed)

    f. TotalSurfaceAreaofPVModules(squarefeet)_________________ft2g. DistributedWeightofPVModuleonRoof(bf)_______________lbs/ft2

    IfdistributedweightofthePVsystemisgreaterthan5lbs/ft2,seeWKS1.

    Step2:ElectricalReviewofPVSystem(CalculationsforElectricalDiagram)InorderforaPVsystemtobeconsideredforanexpeditedpermitprocess,thefollowingmustapply:

    1. PVmodules,utilityinteractiveinverters,andcombinerboxesareidentifiedforuseinPVsystems.2. ThePVarrayiscomposedof4seriesstringsorlessperinverter,and15kWSTCorless.3. Thetotalinvertercapacityhasacontinuouspoweroutput13,440Wattsorless4. Theacinterconnectionpointisontheloadsideofservicedisconnectingmeans(690.64(B)).5. Theelectricaldiagram(E1.1)canbeusedtoaccuratelyrepresentthePVsystem.

    Filloutthestandardelectricaldiagramcompletely.Aguidetotheelectricaldiagramisprovidedtohelpthe

    applicantunderstandeachblanktofillin.Iftheelectricalsystemismorecomplexthanthestandardelectrical

    diagramcaneffectivelycommunicate,provideanalternativediagramwithappropriatedetail.

  • 7/28/2019 Project Modul

    6/51

    ContractorName,

    AddressandPhone:

    _____

    ____________

    _____

    ____________

    _____

    ____________

    _____

    ____________

    S

    ampleSitePlan

    forSmall-Scale,Single-PhasePVSystems

    SiteName:___

    ________________________

    SiteAddress:_

    ________________________

    SystemACSize:______________________

    SIZE

    FSCMNO

    DWGNO

    REV

    S1.1

    SCALE

    NTS

    Date:

    SHEET

    DrawnBy:

    CheckedBy:

    INVERTERWITH

    SUPPLIED

    COMBINERAND

    DCDISCONNECT

    3'-0"

    3'-0"

    3'-0"

    J

    EXISTINGALL-IN-ONE

    SERVICEEQUIPMENT

    W

    ITH40-AMPPV

    B

    REAKERASAC

    DISCONNECT

    24SOLARWORLDSW175

    MODULESIN2SERIESSTRINGS

    OF12MODULESEACHON

    EXISTINGROOFSTRUCTURE

    ROOFTOPJ-BOXTO

    TRANSITIONEXPOSED

    USE-2TOTHWN-2

    CONDUCTORSIN"EMT

    10'-8"

    11'-3"

    12'-7"

    EXISTINGFENCE

    24SOLARWORLDSW175

    MODULESIN2SERIESSTRINGS

    OF12MODULESEACHON

    EXISTINGSHADESTRUCTURE

    J

  • 7/28/2019 Project Modul

    7/51

    ContractorName,

    Address

    andPhone:

    _______

    __________

    _______

    __________

    _______

    __________

    _______

    __________

    One-LineStan

    dardElectricalDiagramfor

    Small-Scale,Single-PhasePVSystems

    SiteName:_

    ________________________

    SiteAddress

    :_______________________

    SystemACS

    ize:____________________

    SIZE

    FSCMNO

    DWGNO

    REV

    E1.1

    SCALE

    NTS

    Date:

    SHEET

    DrawnBy:

    CheckedBy:

    DESCRIPTIONORCO

    NDUCTORTYPE

    USE-2

    orPVWIRE

    BARECOPPEREQ.G

    RD.COND.(EGC)

    THWN-2

    orXHHW

    -2

    orRHW-2

    THWN-2

    orXHHW

    -2

    orRHW-2

    INSULATEDEGC

    DCGROUNDINGELE

    CTRODECOND.

    THWN-2

    orXHHW

    -2

    orRHW-2

    INSULATEDEGC

    TAG

    12345

    CONDUITANDCONDUCTORSCHEDULE

    COND.

    GAUGE

    NUMBEROF

    CONDUCTORS

    CONDUIT

    TYPE

    N/A

    N/A

    CONDUIT

    SIZE

    N/A

    N/A

    DESCRIPTION

    SOLARPVMODULE

    PVARRAY

    J-BOX(IFUSED)

    COMBINER(IFUSED

    )

    DCDISCONNECT

    DC/ACINVERTER

    GENMETER(IFUSE

    D)

    ACDISCONNECT(IF

    USED)

    SERVICEPANEL

    TAG

    123456789

    PARTNUMBER

    NOTES

    _____VAC,_

    _____AMAIN,______ABUS,______AINVE

    RTEROCPD

    (SEENOTE5FORINVERTEROCPDs,ALSOSEEGUIDESECTION9)

    FORUNUSEDSERIESSTRINGS

    PUT"N/AinBLANKABO

    VE

    SEEGUIDEAPPENDIXB

    FOR

    INFORMATIONONMODUL

    EAND

    ARRAYGROUNDING

    ________MODULES

    IN

    SERIESSOURCE-CIRC

    UIT

    ________MODULES

    IN

    SERIESSOURCE-CIRC

    UIT

    ________MODULESIN

    SERIESSOURCE-CIRC

    UIT

    ________MODULESIN

    SERIESSOURCE-CIRC

    UIT

    DC

    DISCO

    INVERTER

    A

    C

    DIS

    CO

    AC

    DC

    M

    BUILDING

    GROUNDING

    ELECTRODE

    G

    Disrega

    rdif

    providedwith

    inverter

    COMBINER

    MUTILITY

    SERVICE

    MAINSERVICE

    PANEL

    MAIN

    OCPD

    INVERTER

    OCPD

    J-BOX

    1

    1

    3

    4

    5

    6

    7

    9

    2

    3

    4

    5

    8

    2

    EQUIPMENTSCH

    EDULE

  • 7/28/2019 Project Modul

    8/51

  • 7/28/2019 Project Modul

    9/51

    8

    ExpeditedPermitGuidelinesforSmallScalePVSystems

    Section1. RequiredInformationforPermit:

    1. Siteplanshowinglocationofmajorcomponentsontheproperty.Thisdrawingneednotbe

    toscale,butitshouldrepresentrelativelocationofcomponentsatsite.(seesupplied

    examplesite

    plan).

    Explanation:Thisisasimplediagramtoshowwheretheequipmentislocatedontheproperty.

    Thiscanbeazoneclearanceplotplanwiththeequipmentclearlyshownandidentifiedontheplan.If

    PVarrayisgroundmounted,clearlyshowthatsystemwillbemountedwithinallowablezoned

    setbacks. Seesiteplanexampledrawinginpermitprocessforreference.

    2. ElectricaldiagramshowingPVarrayconfiguration,wiringsystem,overcurrentprotection,

    inverter,disconnects,requiredsigns,andacconnectiontobuilding(seesuppliedstandard

    electricaldiagram).

    Explanation:Thecornerstoneofasimplifiedpermitprocessistheabilitytoexpresstheelectrical

    designwithagenericelectricaldiagram.Thisdiagramhasbeendesignedtoaccuratelyrepresentthe

    majorityofsinglephase,residentialsized,PVsystems.PVsystemsmayvarydramaticallyinPVarray

    layoutandinverterselection.However,themajorityofsmallscale,residentialsizedPVsystemscanbeaccuratelyrepresentedbythisdiagram.Thisdiagrammustbefullycompletedfilledoutinorder

    forthepermitpackagetobesubmitted.

    3. Specificationsheetsandinstallationmanuals(ifavailable)forallmanufacturedcomponents

    including,butnotlimitedto,PVmodules,inverter(s),combinerbox,disconnects,and

    mountingsystem.

    Explanation:Ataminimum,specificationsheetsmustbeprovidedforallmajorcomponents.In

    additiontothecomponentslisted,otherimportantcomponentsmaybespecialtyfuses,circuit

    breakers,oranyotheruniqueproductthatmayneedtobereviewedbythelocaljurisdiction.

    Installationmanualsarealsolistedinthisitem.Thisisreferringtothebriefversionsofmanualsthat

    arereviewedbythelistingagencycertifyingtheproduct.Somedetailedinstallationmanualscanbe

    severaldozensorhundredsofpages.Ifthelocaljurisdictionfeelsitisnecessarytoreviewtheselargedocuments,agoodalternativewouldbeforthedocumentstobesuppliedelectronically,ratherthan

    inprint.ItisworthconsiderationthatPDFsofthesecomprehensivemanualsbekeptelectronicallyby

    thelocaljurisdiction.

    Section2. Step1:StructuralReviewofPVArrayMountingSystem

    Isthearraytobemountedonadefined,permittedroofstructure? Yes No(structure

    meetsmoderncodes)

    IfNo,submitcompletedworksheetforroofstructureWKS1.Explanation:Thereferencetoadefined,permittedroofstructurereferstostructuresthathavea

    clearinspectionhistorysothatverificationofstructuralelementsisunnecessary.Ifstructural

    modificationshavebeenmadeduetoremodeling,thosechangesshouldbedocumentedthroughthe

    permitandreviewprocess.Italsorecognizesthefactthatthecodeenforcementofroofstructural

    elementshasbeenmuchmoreconsistentacrosstheUnitedStatesinthelast35years.However,there

    maybemanylocaljurisdictionswhohavebeencarefullyreviewingroofstructuresforamuchlonger

    periodoftime.Thelocaljurisdictionshouldconsiderextendingthislimitbasedontheperiodthatroofs

    havebeenconsistentlyinspected.Inareaswherejurisdictionalreviewshavenotextended35yearsinto

  • 7/28/2019 Project Modul

    10/51

    9

    thepast,thejurisdictionmayneedtogettheinformationfromWKS1tobesurewhetherornotthe

    proposedPVsystemisbeinginstalledonatypicalroofstructureornot.

    RoofInformation:

    1. Istheroofingtypelightweight(Yes=composition,lightweightmasonry,metal,wood

    shake,etc)_____________

    If No,submitcompletedworksheetforroofstructureWKS1(No=heavymasonry,slate,

    etc).

    Explanation:Thereisaneedtodistinguishifaroofhasalightweightproduct.Heavier

    roofingmaterials(e.g.slate,heavymasonry,maynothavetheassumeddeadloadingandlive

    loadingcapacitiesthatarefoundwithlighterweightroofingmaterials.Thesearemuchless

    commonrooftypesandoftenjustifyafurtherreviewtoclarifythattheroofstructureiseitherin

    complianceorneedsenhancement.

    2. Doestheroofhaveasingleroofcovering? Yes No

    IfNo,submitcompletedworksheetforroofstructureWKS1.Explanation:Multiplecompositionrooflayersaretakingaportionoralloftheassumed

    additionalweightallowancefoundinthe5lbs/ft2allowanceattheendofthemountingsystem

    section.

    3. Providemethodandtypeofweatherproofingroofpenetrations(e.g.flashing,

    caulk).____________

    Explanation:Theweatherproofingmethodneedstobespecificallyidentifiedsothatplan

    checkersandfieldinspectorsarenotifiedaheadoftimeofthemethodbeingused.Some

    jurisdictionsmayconstrainweatherproofingmethodsandmaterials.

    MountingSystem

    Information:

    1. ThemountingstructureisanengineeredproductdesignedtomountPVmodules?Yes No

    IfNo,providedetailsofstructuralattachmentcertifiedbyadesignprofessional.Explanation:Nonengineeredrackingsystemshaveundefinedcapabilities.PVsystems

    shouldonlybemountedusingsystemsthatareengineeredanddesignedforthatpurpose.

    However,ifaninstallerchoosestouseahybridmountingsystem,thenthesystemcannotbe

    consideredforexpeditedpermitting.

    2. Formanufacturedmountingsystems,filloutinformationonthemountingsystem

    below:

    a. MountingSystem

    Manufacturer

    ___________Product

    Name

    and

    Model#_____________(selfexplanatory)

    b. TotalWeightofPVModulesandRails___________lbs(includetotalweightofall

    hardwareusedalongwithmoduleweight)

    c. TotalNumberofAttachmentPoints____________(selfexplanatory)

    d. WeightperAttachmentPoint(bc)_________________lbs(ifgreaterthan40

    lbs,seeWKS1)

  • 7/28/2019 Project Modul

    11/51

    10

    Explanation:40lbshasbeenusedbymanyjurisdictionsasareasonablelevelbelow

    whichpointloadingofroofjoistsandtrussescanbeignored.Moststandardmounting

    systemshavepointloadingsof2535lbsperattachment.

    e. MaximumSpacingBetweenAttachmentPointsonaRail______________inches

    (seeproductmanualformaximumspacingallowedbasedonwindloading)

    Explanation:

    Depending

    on

    the

    wind

    loading

    requirements

    of

    a

    particular

    jurisdiction,

    thespacingorattachmentsmaybedictatedbythemanufacturersdirections.Forinstance,a

    particularmanufacturermayallowa72attachmentspacingfora90MPHwindspeed

    design,butthespacingreducestoamaximumof48whenthedesignwindspeedexceeds

    100MPH.

    f. TotalSurfaceAreaofPVModules(squarefeet)_________________ft2Explanation:Takethesurfaceareaofasinglemodule,andmultiplyitbythetotal

    numberofmodulesintheroofmountedsystem.

    g. DistributedWeightofPVModuleonRoof(bf)_______________lbs/ft2

    IfdistributedweightofthePVsystemisgreaterthan5lbs/ft2,seeWKS1.

    Explanation:The5lbs/ft2limitisbasedontwothings:1)theroofistypicalofstandard

    codecompliantroofstructuressothatthestructureeitherhastheproperspansandspacing,

    orproperuseofengineeredtrusses(firstitemunderStep1:StructuralReview);and,2)

    thereisasinglelayerofroofingsothatthenormalweightallowanceforadditionalroof

    layersisunusedandavailablefortheweightofthePVsystem.Forapplicationson

    lightweightmasonryroofingmaterialsandotherlightweightroofingproducts(e.g.metal,

    shake,etc),thesematerialsdonotacceptmultiplelayersandthereforethe5lbs/ft2

    allowanceisusedtoidentifythemaximumallowableadditionalweightforroofsthatare

    exchangingtheallowableliveloadforadeadloadthatpreventsliveloadsuchaspeople

    walkingontheroof.

    Section3. Step2:ElectricalReviewofPVSystem(CalculationsforElectricalDiagram)

    InorderforaPVsystemtobeconsideredforanexpeditedpermitprocess,thefollowingmustapply:

    1. PVmodules,utilityinteractiveinverters,andcombinerboxesareidentifiedforuseinPV

    systems.

    Explanation:PVutilityinteractiveinvertersmustbespecificallylistedandlabeledforthis

    application(asrequiredbyNEC690.60and690.4)(Numbersinbracketsrefertosectionsinthe2008

    NECthroughoutthisdocument.).Withoutthisspecificidentificationprocessanunacceptable

    amountofreviewwouldbenecessarytoapproveaninverter.InvertersthatpassUL1741andare

    listedasutilityinteractivehavemettherequirement.Over500inverterscurrentlymeetthis

    requirement.Aninclusivelistoftheseinvertersisavailableonlineat

    http://gosolarcalifornia.com/equipment/inverter.php.

    PVmodulesmustalsobelistedandidentifiedforuseinPVsystems(asrequiredbyNEC690.4).PV

    modulesthatpassUL1703andhavea600Voltmaximumvoltagemeettherequirement.Alistof

    theseinvertersisavailableonlineathttp://gosolarcalifornia.com/equipment/pvmodule.php.Source

    combinersmustbelistedandlabeledtomeetthedcvoltagerequirementsofthePVsystemorbe

    specificallytestedforPVsystemsandclearlystatetheallowablemaximumcurrentandvoltage(as

    requiredbyNEC690.4).

  • 7/28/2019 Project Modul

    12/51

    11

    2. ThePVarrayiscomposedof4seriesstringsorless,and15kWSTCorless.Explanation:Thepurposeofthisrequirementistolimitthenumberofoptionsofwhatcan

    complyasasimplesystemsothatasingleelectricaldiagramcanbeusedtodescribealarge

    portionofthesystemsbeinginstalled.Theelectricaldiagramcanhandleupto4stringsinparallel.

    Themaximumof15kWreferstothearraysizebasedonthetotalinstallednameplatecapacity.The

    limitissettostaygenerallywithinelectricalinterconnectionsthatwouldbeconsideredsimpleand

    possiblyabletomeetthe120%ofbusbarratingallowanceinNEC690.64(B)inaresidence

    (Minimumbreakerfora13.44kWacPVsystemis70amps).

    3. TheInverterhasacontinuouspoweroutput13,440WattsorlessExplanation:A70ampbreakerisimportantsincea225ampbusbarina200amppanelwill

    allowa70ampPVbreaker.Sincethisdoeshappenfromtimetotime,andaninstallercanchooseto

    installsuchapanelboard,itisconsideredthelargestsimplePVsystemforpurposesofthis

    guideline.Atableofbreaker/panelboardcombinationsisinSection9ofthisGuideline.

    4. Theacinterconnectionpointisontheloadsideofservicedisconnectingmeans(NEC

    690.64(B)).

    Explanation:Loadsideinterconnectionsarebyfarthemostcommon,particularlyinresidential

    applications.AnylinesideconnectioniscoveredbyNEC690.64(A)and230.82.Althoughlineside

    connectionscanbequitestraightforward,theyshouldrequireanadditionalstepintheapproval

    processandrequireaslightlydifferentelectricaldrawing.

    5. Theelectricaldiagram(E1.1)canbeusedtoaccuratelyrepresentthePVsystem.Explanation:Thebasisforasimplifiedpermitistheuseofthestandardelectricaldiagram.

    Clearly,PVsystemscanvarysignificantlyinPVarraylayoutandinverterselection.However,the

    majorityofsmallscale,residentialsizedPVsystemscanbeaccuratelyrepresentedbythisdiagram.

    Thisdiagrammustbecompletelyfilledoutinorderforthepermitpackagetobeconsidered

    complete.Thisdiagramisnotintendedforusewithbatterybasedsystems.

    Section4. InverterInformation

    Acopyofthemanufacturersspecificationsheetisrequiredforapermitsubmittal.Inaddition,

    aprintedoutdigitalphotooftheinverterlistinglabelcanbeveryhelpfulforgatheringthe

    ratingsoftheequipment.Aprerequisiteforacodeapprovedinstallationistheuseofalisted

    inverter[NEC690.4;690.60].TodetermineifaninverterislistedbyaNationallyRecognized

    TestingLaboratory(NRTL)toULStd.1741,thelistinglabelcanbeexaminedtoseeifitislabeled

    UtilityInteractive.Iftheutilityinteractivelabelingisnotprovided,doestheunitcomplywith

    therequirementsofIEEEStd.1547asverifiedtheinstructionmanualsvalidatedbythelisting

    agency.For

    acurrent

    list

    of

    compliant

    inverters,

    visit

    the

    GoSolarCalifornia

    website

    at

    http://gosolarcalifornia.com/equipment/inverter.php.SomeNRTLshavecurrentlisting

    informationonlineaswell.

    a) INVERTERMAKE:Thisisthemanufacturersname:(e.g.PVPowered,SMA,etc)

    b) INVERTERMODEL#:Thisisthemodelnumberonthelistinglabel:(e.g.PVP5200,

    SB7000US,etc)

  • 7/28/2019 Project Modul

    13/51

    12

    c) MAXDCVOLTAGERATING:Providedeitheronlistinglabelorspecificationsheet.

    d) MAXPOWER@40C:Themaximumcontinuousoutputpowerat40

    Cisrequired

    informationforthelistinglabelandtheGoSolarCaliforniawebsite.Ifthespecification

    sheetdoesnotclearlystatethevalue,consulteitheroftheseothertwosources.

    e) NOMINALACVOLTAGE: Thisistheacoutputvoltageoftheinverterasconfiguredfor

    thisproject.

    Some

    inverters

    can

    operate

    at

    multiple

    ac

    voltages.

    f) MAXOCPDRATING:Thisisthemaximumovercurrentprotectivedevice(OCPD)rating

    allowedfortheinverter.Thisiseitherstatedonthelistinglabelorintheinstallation

    manual.Sometimesthisisalsolistedonthespecificationsheetbutnotalways.Itis

    importanttocheckthattheinverterOCPDratinginthepanelislessthanorequaltothis

    maximumratingtopreservethelistingoftheinverter.

    Section5. ModuleInformation

    Acopyofthemanufacturersspecificationsheetisrequiredforapermitsubmittal.Inaddition,

    aprintedoutdigitalphotoofthemodulelistinglabelcanbeveryhelpfulforgatheringthe

    ratingsoftheequipment.Aprerequisiteforacodeapprovedinstallationistheuseofalisted

    PVmodules[NEC690.4]toUL1703.ForacurrentlistofmodulesthatarelistedtoUL1703,

    visittheGoSolarCaliforniawebsite,http://gosolarcalifornia.com/equipment/pvmodule.php.Explanation:Thismoduleinformationisparticularlyimportantsinceitisusedtocalculate

    severalcurrentandvoltageparametersrequiredbytheNationalElectricalCode(NEC).Listing

    informationisnecessaryforNECtestingrequirements[90.7,100,110.3,690.4].(Numbersin

    bracketsrefertosectionsinthe2008NECthroughoutthisdocument.)

    a) MODULEMANUFACTURER: Thisisthemanufacturersname:(e.g.Evergreen,

    SunPower,etc)

    b) MODULEMODEL#:Thisisthemodelnumberonthelistinglabel:(e.g.EGS185,SP225,

    etc)c) MAXIMUMPOWERPOINTCURRENT(IMP)

    Explanation:TheratedIMPisneededtocalculatesystemoperatingcurrent.Thisisthecurrent

    ofthemodulewhenoperatingatSTCandmaximumpower.

    d) MAXIMUMPOWERPOINTVOLTAGE(VMP)Explanation:TheratedVMPisneededtocalculatesystemoperatingvoltage.Thisisthe

    voltageofthemodulewhenoperatingatSTCandmaximumpower.

    e) OPENCIRCUITVOLTAGE(VOC)Explanation:TheratedVOCisneededtocalculatedmaximumsystemvoltagespecifiedinNEC

    690.7.

    f) SHORTCIRCUITCURRENT(ISC)

    Explanation:TheratedISCisneededtocalculatemaximumcurrentspecifiedinNEC690.8(A).g) MAXIMUMSERIESFUSE(OCPD)

    Explanation:Maximumseriesfuse(OCPD)ratingisneededtoensurethattheproper

    overcurrentprotectionisprovidedforthemodulesandarraywiring.

    h) MAXIMUMPOWER(PMAX)atStandardTestConditions(STCis1000W/m2,25

    Ccelltemp,

    &AirMass1.5)

    Explanation:MaximumpoweratSTCspecifiestheratedpowerofthePVmoduleunder

    simulatedconditions.

  • 7/28/2019 Project Modul

    14/51

    13

    i) MAXIMUMSYSTEMVOLTAGEExplanation:Maximumsystemvoltage(often600Vdc)isneededtoshowthattheNEC690.7

    voltagedoesnotexceedthisvalue.

    Section6. Arrayinformation

    Thissection

    defines

    the

    configuration

    of

    the

    PV

    array.

    PV

    arrays

    are

    generally

    made

    up

    of

    severalmodulesinseries,calledsourcecircuits.Thesesourcecircuitsareoftenparalleledwith

    multipleothersourcecircuitstomakeuptheentiredcgeneratingunitcalledthearray.Thelast

    fouritemsrelatedtothePVarraymustbecalculatedandpostedonasignatthePVPower

    Sourcedisconnect.Thefirsttwoitemsa)andb)characterizethearraydesignandprovidesthe

    informationnecessarytocalculatethefouritemsneededtoproduceproperarrayidentification

    forPVPowerSourcesigndiscussedinSection7thatisrequiredatthesite.

    a) NUMBEROFMODULESINSERIESExplanation:Forsimplicity,thisdiagramonlyaddressesthemostcommonconfigurationofPV

    modulesmultiplemodulesinseries.AlthoughsinglemodulePVpowersourcesexist,itismorecommon

    toseePVarraysconfiguredwithasmanyas12or16modulesinseries.

    b) NUMBEROFPARALLELCIRCUITSExplanation:Sincesinglephaseinverterscanbeaslargeas12kWormore,andthelargestPV

    sourcecircuitsareonly2or3kW,itiscommonforPVarraystohavetwoormoresourcecircuitsin

    parallel.FromExampleinAppendixOne:

    Numberofmodulesinseries=12

    Numberofparallelsourcecircuits=4

    Totalnumberofmodules=12x4=48

    c) LOWESTEXPECTED

    AMBIENT

    TEMP

    Explanation:Upthroughthe2008edition,theNEChasnotclearlydefinedlowestexpectedambient

    temperature.ASHRAE(AmericanSocietyofHeating,Refrigeration,andAirConditioningEngineers)has

    performedstatisticalanalysisonweatherdatafromtheNationalWeatherService.Thesedatainclude

    valuesforthemeanextremetemperaturesforthelocationswithtemperaturedata.Themeanextreme

    lowtemperatureisthecoldestexpectedtemperatureforalocation.Halfoftheyearsonrecordhavenot

    exceededthisnumber,andtheresthaveexceededthisnumber.Thesedataaresuppliedintheappendix

    forreference.Aproposalislikelytoacceptedforthe2011NEC toincludeaFinePrintNoteto690.7that

    specifiestheuseoftheASHRAEmeanextremevalueforlowestexpectedambienttemperature.

    d) HIGHESTCONTINUOUSTEMP(ambient)

    Explanation:Upthroughthe2008edition,theNEChasnotclearlydefinedhighestcontinuousambienttemperature.ContinuousisdefinedintheNECasa3hourperiod(Article100).ASHRAE

    (AmericanSocietyofHeating,Refrigeration,andAirConditioningEngineers)hasperformedstatistical

    analysisonweatherdatafromtheNationalWeatherService.Thesedataincludedesignvaluesof0.4%,

    1%,and2%foreachmonthsignifyingthatthetemperatureonlyexceedstherecordedvalueupto2%of

    thetimeforagivenlocationwithtemperaturedata.The2%valuehasbeenchosenbytheCopper

    DevelopmentInstituteasthevaluethatbestrepresentsaconditionthatwouldcreatethe3hour

    continuousconditionreferredtoinArticle100.Twopercentofonemonthisabout14hours.Sincehigh

  • 7/28/2019 Project Modul

    15/51

    14

    temperaturesusuallylastforseveraldaysinmostlocations,theassumptionisthatatleastoneortwo3

    hourhightemperatureeventswillhappenduringagivenmonth.Thesedataaresuppliedintheappendix

    forreference.Aproposalforthe2011NEChasbeensubmittedtoincludeaFinePrintNotetoTable

    310.16thatspecifiestheuseoftheASHRAE2%dataforthehottestmonthtodeterminehighest

    continuousambienttemperature.

    Section7. SIGNS

    a) PVPOWERSOURCE

    i) RATEDMPP(MAXIMUMPOWERPOINT)CURRENT

    (sumofparallelsourcecircuitoperatingcurrents)

    Explanation:RatedMPPcurrentisfoundbymultiplyingthemoduleratedMPPcurrentfora

    moduleseriesstringbythenumberofsourcecircuitsinparallel.

    FromtheexampleinAppendixOne:

    IMP=4.89amps

    Numberofsourcecircuitsinparallel=44.89ampsx4=19.6amps

    ii) RATEDMPP(MAXIMUMPOWERPOINT)VOLTAGE

    (sumofseriesmodulesoperatingvoltageinsourcecircuit)

    Explanation:OperatingvoltageisfoundbymultiplyingthemoduleratedMPPvoltagebythe

    numberofmodulesinaseriessourcecircuit.

    FromtheexampleinAppendixOne:

    VMP=35.8Volts

    Numberofmodulesinseries=12

    35.8Voltsx12=430Volts

    iii) MAXIMUMSYSTEM

    VOLTAGE

    [NEC

    690.7]

    Explanation:MaximumsystemvoltageiscalculatedbymultiplyingthevalueofVoconthe

    listinglabelbytheappropriatevalueonTable690.7intheNEC,andthenmultiplyingthatvalue

    bythenumberofmodulesinaseriesstring.ThetableintheNECisbasedoncrystallinesilicon

    modulesanduseslowestexpectedambienttemperatureatasitetoderivethecorrectionfactor.

    Somemodulesdonothavethesametemperaturecharacteristicsascrystallinesiliconsothe

    manufacturersinstructionsmustbeconsultedtodeterminetheproperwaytocorrectvoltage

    basedonlowestexpectedambienttemperature.

    FromtheexampleinAppendixOne:

    ModuleVOC=44.4Volts

    NumberofModulesinSeries=12

    Lowestexpectedambienttemperature(ASHRAE)=0C(SanJose,California)

    Method1NECTable690.7:

    MaximumSystemVoltage=VMAX=VOCxNo.ofModulesinSeriesxTable690.7Value

    VMAX=44.4Vx12x1.10=586Volts

  • 7/28/2019 Project Modul

    16/51

    15

    PercentageMethod:

    VMODMAX=VOC+VOCx VOC(%)x(TempLOWTempRATED)

    VoltageMethod:

    VMODMAX=VOC+ VOC(V)x(TempLOWTempRATED)

    MaximumSystemVoltage=VMAX=VMODMAXxNumberofModulesinSeries

    MaximumSystemVoltage=VMAX

    =44.4V+44.4Vx0.0033/Cx(0C 25C)x12

    VMAX=[44.4V+44.4Vx0.0033/Cx(25C)]x12=577Volts

  • 7/28/2019 Project Modul

    17/51

    16

    Section8. WiringandOvercurrentProtection

    a) DCWiringSystems:

    Sourcecircuit

    conductors:

    InExposedLocations:

    PVmoduleinterconnectionsaregenerally90Cwetratedconductors(NEC690.31(A)

    FPN).Thesameconductortypeistypicallyusedforallhomerunconductorsneeded

    forsourcecircuitconductorsinexposedlocations.

    Allowablewiretypesareasfollows:

    USE2singleconductorcableforexposedlocations.[NEC690.31(B)]

    PVWireorPVCableasasingleconductorforexposedlocations(requiredforall

    ungroundedsystems).[NEC690.31(B)]ExplanationfortheneedforHighTemperatureConductors:Typicaltemperature

    forPVmodulesinfullsunat20Coutdoortemperatureis50C.Thisisa30Criseabove

    outdoortemperatures.Onthehottestdayoftheyear,outdoortemperaturescanreacha

    continuoustemperatureof41CinmanyhotlocationsthroughouttheUnitedStates.This

    meansthatthePVmodulecouldbeoperatingat71Conthehottestdayoftheyear

    (41C+30C=71C).75CwireisinsufficientforconnectiontoahotPVmoduleunderthis

    condition.

    TofurthersupporttheconcernoverthehightemperatureofPVmodules,afineprint

    notehasbeenaddedtothe2005NEC.

    NEC690.31(A)FPN: Photovoltaicmodulesoperateatelevatedtemperatureswhen

    exposedtohighambienttemperaturesandtobrightsunlight.Thesetemperaturesmay

    routinelyexceed70C(158F)inmanylocations.Moduleinterconnectionconductorsare

    availablewithinsulationratedforwetlocationsandatemperatureratingof90C

    (194F)orgreater.

    InConduitonRooftops:

    TWOOPTIONSFORSOURCECIRCUITCONDUCTORTYPE(INSIDECONDUITCIRCLE

    ONE)THWN2andXHHW2

    Explanation:Conductorsinconduit,whenexposedtodirectsunlight,mustaccountfor

    thehighertemperaturescausedbyintensesunlightandtheproximityoftheroof.The2005

    NECfirstrecognizedtheissueofsunlitconduitinafineprintnoteinNEC310.10.

    310.10FPNNo.2:Conductorsinstalledinconduitexposedtodirectsunlightinclose

    proximitytorooftopshavebeenshown,undercertainconditions,toexperiencea

    temperatureriseof17C(30F)aboveambienttemperatureonwhichtheampacityis

    based.

    The2008NECcodifiedthisissuebyclassifyingthetemperaturesbasedontheheightabove

    theroofsurface.Onresidentialroofs,whereconduittypicallyisspacedbetweenand3

    abovetheroofsurface,thetemperatureadderisstatedas22Cabovetheambient

    temperatureaccordingtoNECTable310.15(B)(2)(c).Usingthisadder,alongwiththe

  • 7/28/2019 Project Modul

    18/51

    17

    ASHRAE2%designdataforthehottestlocationintheU.S.(PalmSprings,CAis44C),

    producesadesigntemperatureof66C.andcorrectionfactorof0.58for90Cconductors

    basedonNECTable690.31andTable310.16.Ifnineconductorsorlessareintheexposed

    conduit(4pairsofconductorsorless),thentheconduitfillcorrectionfactoris0.7according

    toNECTable310.15(B)(2)(a).Puttingallthesecorrectionfactorstogethermeansthatthe

    30C.conductorampacitymustbeasfollows:

    Ifonlytwostringsinparallel(nofuses):

    I30C.=IMAX/0.58/0.7=2.46xIMAX

    IfISC=9.6ampsorless,thenIMAX=ISCx1.25=12ampsorless.

    IfIMAX=12Amps,thenI30C.=29.5Amps(12AWG,90Crequired(NECTable310.16))

    IfISC=6.4ampsorless,thenIMAX=ISCx1.25=8ampsorless.

    IfIMAX=8Amps,thenI30C.=19.7Amps(14AWG,90Crequired(NECTable310.16))

    IffusesareneededtoprotectPVmodules(mostcases):

    I30C.=IFUSE/0.58/0.7=2.46xIFUSE

    IfISC=9.6ampsorless,thenIMAX=ISCx1.25=12amps.Theminimumovercurrent

    protectivedevice(OCPD)asrequiredby690.8(B)is15amps(IFUSE=IMAXx1.25=15A).

    IfIFUSE=15Amps,thenI30C.=2.46x15A=36.9Amps(10AWG,90Crequired(NEC

    Table310.16)15Afusetoprotecttheconductor)

    IfISC=7.68ampsorless,thenIMAX=ISCx1.25=9.6amps.Theminimumovercurrent

    protectivedevice(OCPD)asrequiredbyNEC690.8(B)is12amps(IFUSE=IMAXx1.25=

    12A).

    IfIFUSE=12Amps,thenI30C.=2.46x12A=29.5Amps(12AWG,90Crequired(NEC

    Table310.16)12Afusetoprotecttheconductor)

    IfISC=6.4ampsorless,thenIMAX=ISCx1.25=8amps.Theminimumovercurrent

    protectivedevice(OCPD)asrequiredby690.8(B)is10amps(IFUSE=IMAXx1.25=10A).

    IfIFUSE=10Amps,thenI30C.=2.46x10A=24.6Amps(14AWG,90Crequired(NEC

    Table310.16)10Afusetoprotecttheconductor)

    Maximum

    ModuleISC

    RequiredFuse

    Size

    MinimumConductorSize

    inConduit(9conductors)

    MinimumConductorSizein

    FreeAir(atmodules)

    9.6Amps 15Amps 10AWG 10AWG

    7.68Amps 12Amps 12AWG 12AWG

    6.4Amps 10Amps 14AWG 14AWG

    SincethehighestISCmodulecommonlyavailableasofthewritingofthisguideislessthan9

    amps,10AWGconductorswillalwaysworkregardlessoflocationintheU.S.aslongasthere

  • 7/28/2019 Project Modul

    19/51

    18

    arenomorethan9currentcarryingconductorsintheconduitandtheconduitisatleast0.5

    abovetheroofsurface.SmallerwirecanbeusedaccordingtotheISCofthemodulesbeing

    usedandthenumberofconductorsintheconduit.Thesecalculationsareprovidedsothat

    contractorsandjurisdictionswillnotneedtorepeatthesestandardcalculationsoverand

    over.Asimpletablesummarizestheminimumconductorsizes.

    b) ACWiringSystems

    InverterOutputCircuitovercurrentprotectionshouldbesizedandprotectedaccordingthe

    manufacturersdirections.Thecircuitandcorrespondingovercurrentprotectionshouldbe

    sizedata125%ofthemaximumcontinuousoutputoftheinverter[NEC215.3Overcurrentfor

    FeederCircuits,andNEC690.8(A)(3)and690.8(B)].The125percentincreaseoverthe

    maximumInverterOutputCircuitcurrentistoaccountforthestandardlistingofovercurrent

    devicesto80%ofmaximumcircuitcurrentforcontinuousduty.Theinvertermayalsohavea

    maximumallowableovercurrentrequirement.

    Explanation:Forinstance,theSMASB7000UShasamaximumcontinuousoutputof29.2amps

    andamaximumallowableovercurrentprotectionof50amps.Thismeansthattheminimumallowableovercurrentis40amps(29.2ampsx1.25=36.5ampsrounduptothenextstandardsize,whichis40

    amps)andamaximumof50amps.Normallytheminimumallowablebreakersizeisusedsincethe

    panelboardsupplybreakersareconstrainedto120%ofthepanelboardbusbarrating.

    FromtheexampleinAppendixOne:

    Invertercontinuousoutputrating=7000Watts

    Nominalinvertervoltage=240Volts

    Maximumoperatingcurrent=7000Watts/240Volts=29.2Amps

    Min.InverterOutputCircuitampacity=29.2Ampsx1.25=36.5Amps

    Section9. ACPointofConnection

    NEC690.64(B)coverstherequirementsforPointofConnectionofthePVinvertertothe

    buildingelectricalsystem.Themostcommonmethodofconnectionisthroughadedicated

    circuitbreakertoapanelboardbusbar.Thesumofthesupplybreakersfeedingthebusbarofa

    panelcanbeupto120%ofthebusbarrating.AppendixBtreatsthissubjectindetail.

    Explanation:Aservicepanelcontaininga200ampbusbaranda200ampmainbreakerwill

    allowbreakerstotaling120%ofthebusbarrating(240amps).Sincethemainbreakeris200amps,the

    PVbreakercanbeupto40ampswithoutexceedingthe120%allowance.Foraservicepanelwitha125

    ampbusbaranda100ampmainbreaker,thisprovisionwillallowuptoa50ampbreaker(125ampsx

    1.2=150amps;150amps100ampmainbreaker=50ampPVbreaker).

    Aprovision

    in

    the

    2005NEC

    clarifies

    the

    fact

    that

    dedicated

    circuit

    breakers

    backfed

    from

    listed

    utilityinteractiveinvertersdonotneedtobeindividuallyclampedtothepanelboardbusbars.

    Thishasalwaysbeenthecase,butmanyinspectorshaveemployedtheprovisionsofNEC

    408.36(F)thatthebreakerbesecuredinplacebyanadditionalfastener.Utilityinteractive

    invertersdonotrequirethisfastenersincetheyaredesignedtoshutdownimmediatelyshould

    thededicatedbreakerbecomedisconnectedfromthebusbarunderanycondition.This

    provisionisrepeatedinthe2008NECinaclearandconcisestatement:

  • 7/28/2019 Project Modul

    20/51

    19

    NEC690.64(B)(6)Fastening.Listedplugintypecircuitbreakersbackfedfromutilityinteractiveinverterscomplyingwith690.60shallbepermittedtoomittheadditionalfastenernormally

    requiredby408.36(D)forsuchapplications.

    NEC690.64(B)coverstherequirementsforPointofConnectionofthePVinvertertothe

    buildingelectrical

    system,

    which

    is

    the

    most

    common

    method

    of

    connection.

    The

    table

    below

    showsthehowthemaximumcurrentoftheinverter(column1)requiresaminimumsizeOCPD

    (column2),whichrequiresaminimumsizeconductor(column3),whichrequiresacompatible

    busbar/mainbreakercombinationinthepanelboard(column4).Thewaytounderstand

    column4,minimumbusbar/mainbreakercombinationsistolookattherowthatcoincideswith

    theparticularbreakerbeingselected(fromcolumn2)anduseanycombinationfromcolumn4

    foundonthatroworhigherinthetable.Forinstance,a40Ampsinverterbreakerworkswitha

    200/200panelcombination,butitalsoworkswitha125/100combinationfoundontherow

    above.The40Ampbreakerdoesnotworkonthe150/150combination,sincethelargest

    breakerwouldbe30ampsforthe150/150combination.

    TableofNEC690.64(B)ACInterconnectionOptionsMaximum

    Inverter

    Current

    Required

    InverterOCPD

    Size

    Minimum

    ConductorSizein

    Conduit

    MinimumBusbar/MainBreaker

    Combinations

    (BusbarAmps/MainAmps)

    64Amps 80Amps 4AWG 400/400;200/150

    56Amps 70Amps 4AWG 225/200;250/225

    48Amps 60Amps 6AWG 300/300;200/175

    40Amps 50Amps 8AWG 125/100;150/125

    32Amps 40Amps 8AWG 225/225;200/200;150/125

    24Amps

    30

    Amps

    10

    AWG

    150/150

    16Amps 20Amps 12AWG 100/100;70/60

    12Amps 15Amps 14AWG 80/80

    Section10. Grounding

    a) SystemGrounding

    TheNECrequires[690.41]thatallsystemsoperatingabove50voltshaveoneconductor

    referencedtogroundunlessthesystemcomplieswiththerequirementsofNEC690.35for

    ungroundedPVarrays.

    b) EquipmentGrounding

    Thecodealsorequiresthatallexposednoncurrentcarryingmetalpartsofmoduleframes,

    equipment,andconductorenclosuresbegroundedregardlessofsystemvoltage[NEC690.43].

    Thegroundingofmoduleframeshasreceivedsignificantattentioninthelastseveralyears.

    Manyjurisdictions,withaheightenedconcernovertheissue,havedramaticallyrestricted

    effectivegroundingoptions. AdiscussiononmoduleframegroundingisfoundintheAppendix.

  • 7/28/2019 Project Modul

    21/51

    20

    c) SizingofGroundingConductors

    i) Equipmentgroundingconductor(EGC)sizing[NEC690.45]

    ThesizeoftheEGCisdependentonwhetherthesystemhasgroundfaultprotection

    (GFP)equipmentornot.TheprovisionsforGFPequipmentarestatedinNEC690.5.

    Almostall

    inverters

    have

    GFP

    equipment

    integral

    to

    the

    inverter

    and

    require

    that

    the

    PV

    arraybegroundedattheinverteronly.

    (1)Systemswithgroundfaultprotectionequipment

    SizeequipmentgroundingconductoraccordingtoNECTable250.122.

    (2)Systemswithoutgroundfaultprotectionequipment

    TheNECrequiresthatequipmentgroundingconductorsforsystemswithoutGFP

    equipmentbesizedfortwicethecircuitshortcircuitcurrent[NEC690.45].

    ii) Systemgroundingconductorsizing

    (1)ACSystem

    Sizegroundingelectrodeconductor(GEC)accordingtoNECTable250.66.

    Normallythesitealreadyhastheconductorandelectrodeinstalledfortheac

    buildingwiring.

    (2)DCSystem

    Sizegroundingelectrodeconductor(GEC)accordingtoNEC250.166.Thisresults

    inaminimumsizeof8AWG.ThemaximumsizeoftheGECisdependentupon

    thetypeofgroundingelectrodeorthemaximumsizeconductorinthesystem,

    whicheverissmaller.

  • 7/28/2019 Project Modul

    22/51

    21

    APPENDIX

  • 7/28/2019 Project Modul

    23/51

    22

    APPENDIXA:EXAMPLESUBMITTAL

    Step1:StructuralReviewofPVArrayMountingSystem

    Isthearraytobemountedonadefined,permittedroofstructure? Yes No

    (structuremeetsmoderncodes)

    IfNoduetononcompliantrooforgroundmount,submitcompletedworksheetforroofstructureWKS1.

    RoofInformation:

    1. Istheroofingtypelightweight(Yes=composition,lightweightmasonry,metal,etc)_Yescomposition

    If No,submitcompletedworksheetforroofstructureWKS1(No=heavymasonry,slate,etc).

    2. Doestheroofhaveasingleroofcovering? Yes No

    IfNo,submitcompletedworksheetforroofstructureWKS1.

    3. Providemethodandtypeofweatherproofingroofpenetrations(e.g.flashing,caulk).__flashing_____

    MountingSystemInformation:

    1. ThemountingstructureisanengineeredproductdesignedtomountPVmodules? Yes NoIfNo,providedetailsofstructuralattachmentcertifiedbyadesignprofessional.

    2. Formanufactured

    mounting

    systems,

    fill

    out

    information

    on

    the

    mounting

    system

    below:

    a. MountingSystemManufacturer_UniRac_ProductNameandModel#__SolarMount___

    b. TotalWeightofPVModulesandRails___1780________lbs

    c. TotalNumberofAttachmentPoints____48___

    d. WeightperAttachmentPoint(bc)____37___________lbs(ifgreaterthan40lbs,seeWKS1)

    e. MaximumSpacingBetweenAttachmentPointsonaRail______48______inches(seeproduct

    manualformaximumspacingallowedbasedonmaximumdesignwindspeed)

    f. TotalSurfaceAreaofPVModules(squarefeet)_____674____________ft2

    g. DistributedWeightofPVModuleonRoof(bf)______2.64______lbs/ft2

    IfdistributedweightofthePVsystemisgreaterthan5lbs/ft2,seeWKS1.

    Step2:ElectricalReviewofPVSystem(CalculationsforElectricalDiagram)InorderforaPVsystemtobeconsideredforanexpeditedpermitprocess,thefollowingmustapply:

    1. PVmodules,utilityinteractiveinverters,andcombinerboxesareidentifiedforuseinPVsystems.

    2. ThePVarrayiscomposedof4seriesstringsorless,and15kWSTCorless.

    3. TheInverterhasacontinuouspoweroutput13,440Wattsorless

    4. Theacinterconnectionpointisontheloadsideofservicedisconnectingmeans(690.64(B)).

    5. Theelectricaldiagram(E1.1)canbeusedtoaccuratelyrepresentthePVsystem.

    Filloutthestandardelectricaldiagramcompletely.Aguidetotheelectricaldiagramisprovidedtohelpthe

    applicantunderstandeachblanktofillin.Iftheelectricalsystemismorecomplexthanthestandardelectrical

    diagramcaneffectivelycommunicate,provideanalternativediagramwithappropriatedetail.

  • 7/28/2019 Project Modul

    24/51

    ContractorName,

    AddressandPhone:

    Billa

    ndTedsSolar

    456IndustrialDrive

    SanJose,CA

    40

    8-555-1212

    Bill

    Ted

    SitePlan

    forSmall-Scale,Single-PhasePVSystems

    SiteName:JoeandJaneHomeowner

    SiteAddress:123SunnysideSt.,SanJose,CA

    SystemACS

    ize:6.9kWSolarArray

    SIZE

    FSCMNO

    DWGNO

    REV

    S1.1

    0

    SCALE

    NTS

    Date:

    SHEET

    DrawnBy:

    CheckedBy:

    INVERTERWITH

    SUPPLIED

    COMBINERAND

    DCDISCONNECT

    3'-0"

    3'-0"

    3'-0"

    J

    EXISTINGALL-IN-ONE

    SERVICEEQUIPMENT

    W

    ITH40-AMPPV

    B

    REAKERASAC

    DISCONNECT

    24SOLARWORLDSW175

    MODULESIN2SERIESSTRINGS

    OF12MODULESEACHON

    EXISTINGROOFSTRUCTURE

    ROOFTOPJ-BOXTO

    TRANSITIONEXPOSED

    USE-2TOTHWN-2

    CONDUCTORSIN"EMT

    10'-8"

    11'-3"

    12'-7"

    EXISTINGFENCE

    24SOLARWORLDSW175

    MODULESIN2SERIESSTRINGS

    OF12MODULESEACHON

    EXISTINGSHADESTRUCTURE

    J

  • 7/28/2019 Project Modul

    25/51

    ContractorName,

    AddressandPhone:

    Billa

    ndTedsSolar

    456IndustrialDrive

    SanJose,CA

    40

    8-555-1212

    Bill

    Ted

    One-LineStandardElectricalDiagram

    forSmall-Scale,Single-PhasePVSystems

    SiteName:JoeandJaneHomeowner

    SiteAddress:123SunnysideSt.,SanJose,CA

    SystemACS

    ize:6.9kWSolarArray

    SIZE

    FSCMNO

    DWGNO

    REV

    E1.1

    0

    SCALE

    NTS

    Date:

    SHEET

    DrawnBy:

    CheckedBy:

    DESCRIPTIONORCO

    NDUCTORTYPE

    USE-2

    orPVWIRE

    BARECOPPEREQ.G

    RD.COND.(EGC)

    THWN-2

    orXHHW

    -2

    orRHW-2

    THWN-2

    orXHHW

    -2

    orRHW-2

    INSULATEDEGC

    DCGROUNDINGELE

    CTRODECOND.

    THWN-2

    orXHHW

    -2

    orRHW-2

    INSULATEDEGC

    TAG

    12345

    CONDUITANDCONDUCTORSCHEDULE

    COND.

    GAUGE

    10AWG

    10AWG

    10AWG

    N/A

    N/A

    6AWG

    8AWG

    10AWG

    NUMBEROF

    CONDUCTORS

    8BLACK

    1BARECU

    4-R,4-W,1-G

    N/A

    N/A

    1BARECU

    1-R,1-B,1-W

    1GREEN

    CONDUIT

    TYPE

    N/A

    N/A

    EMT

    N/A

    N/A

    EMT

    CONDUIT

    SIZE

    N/A

    N/A

    "

    N/A

    N/A

    "

    DESCRIPTION

    SOLARPVMODULE

    PVARRAY

    J-BOX(IFUSED)

    COMBINER(IFUSED

    )

    DCDISCONNECT

    DC/ACINVERTER

    GENMETER(IFUSE

    D)

    ACDISCONNECT(IF

    USED)

    SERVICEPANEL

    TAG

    123456789

    PARTNUMBER

    SW175mono

    N/A

    SMA-supplied

    SMA-supplied

    SB7000US

    FORM2S

    D222NRB

    SD200SL

    NOTES

    SOLARWOR

    LD,QUANTITY-36(SEENOTESSHEETFORDETAILS)

    ARRAYIS4

    STRINGSWITH12MODULESPERSERIES

    STRING

    NEMA4,PVCJUNCTIONBOX

    15-AMAXFUSEW/15-AFUSES,600VDC,4-STRINGMA

    X

    LISTEDWITHINVERTER,600VDC,60-AMP(SEEGUIDE

    APPENDIXB)

    SMA7000W

    ATT,SINGLEPHASE(SEENOTESSHEETFORDETAILS)

    GENERALE

    LECTRIC4-JAW

    SQUARED,

    240VAC,60-AMPFUSED(SEEGUIDEAPPE

    NDIXB)

    240VAC,200

    -AMAIN,200-ABUS,40-AINVERTEROCPD

    (SEENOTE5FORINVERTEROCPDs,ALSOSEEGUIDESECTION9)

    FORUNUSEDSERIESSTRINGS

    PUT"N/AinBLANKABO

    VE

    SEEGUIDEAPPENDIXB

    FOR

    INFORMATIONONMODUL

    EAND

    ARRAYGROUNDING

    ___12___MODULES

    IN

    SERIESSOURCE-CIRC

    UIT

    ___12___MODULES

    IN

    SERIESSOURCE-CIRC

    UIT

    ___12___MODULESIN

    SERIESSOURCE-CIRC

    UIT

    ___12___MODULESIN

    SERIESSOURCE-CIRC

    UIT

    DC

    DISCO

    INVERTER

    A

    C

    DIS

    CO

    AC

    DC

    M

    BUILDING

    GROUNDING

    ELECTRODE

    G

    Disrega

    rdif

    providedwith

    inverter

    COMBINER

    MUTILITY

    SERVICE

    MAINSERVICE

    PANEL

    MAIN

    OCPD

    INVERTER

    OCPD

    J-BOX

    1

    1

    3

    4

    5

    6

    7

    9

    2

    3

    4

    5

    8

    2

    EQUIPMENTSCH

    EDULE

  • 7/28/2019 Project Modul

    26/51

  • 7/28/2019 Project Modul

    27/51

    26

    APPENDIXB:STRUCTURAL

    STRUCTUREWORKSHEETWKS1

    Ifarrayisroofmounted:

    Thissectionisforevaluatingroofstructuralmembersthataresitebuilt.Thisincludesrafter

    systemsandsitebuilttrusses.Manufacturedtrussandroofjoistsystems,wheninstalledwith

    properspacing,meettheroofstructurerequirementscoveredinitem2below.

    1. Roofconstruction: Rafters Trusses Other:

    ___________________________________

    2. Describesitebuiltrafterororsitebuilttrusssystem.

    a. RafterSize:___x___inches

    b. RafterSpacing:________inches

    c. Maximumunsupportedspan:_____feet,_____inches

    d. Aretheraftersoverspanned?(seetheIRCspantablesinB.2.) Yes No

    e. IfYes,completetherestofthissection.

    3. Iftheroofsystemhas:

    a. overspannedraftersortrusses,

    b. thearrayover5lbs/ft2onanyroofconstruction,or

    c. theattachmentswithadeadloadexceeding40lbsperattachment;

    itis

    recommended

    that

    you

    provide

    one

    of

    the

    following:

    i. Aframingplanthatshowsdetailsforhowyouwillstrengthentherafters

    usingthesuppliedspantablesinB.2.

    ii. Confirmation certifiedbyadesignprofessionalthattheroofstructurewill

    supportthearray.

    Ifarrayisgroundmounted:

    1. Showarraysupports,framingmembers,andfoundationpostsandfootings.

    2. Provideinformationonmountingstructure(s)construction.Ifthemountingstructureis

    unfamiliarto

    the

    local

    jurisdiction

    and

    is

    more

    than

    six

    (6)

    feet

    above

    grade,

    it

    may

    requireengineeringcalculationscertifiedbyadesignprofessional.

    3. Showdetailonmoduleattachmentmethodtomountingstructure.

  • 7/28/2019 Project Modul

    28/51

    27

    B.2 SPANTABLESAframingplanisrequiredonlyifthecombinedweightofthePVarrayexceeds5poundsper

    squarefoot(PSForlbs/ft2)ortheexistingraftersareoverspanned.Thefollowingspantables

    fromthe2003InternationalResidentialCode(IRC)canbeusedtodetermineiftheraftersare

    overspanned.Forinstallationsinjurisdictionsusingdifferentspantables,followthelocal

    tables.

    SpanTableR802.5.1(1),

    Usethistableforrafterspansthathaveconventionallightweightdeadloadsanddonothaveaceilingattached.

    10 PSF Dead LoadRoof live load = 20 psf, ceiling not attached to rafters, L/=180

    Rafter Size 2 x 4 2 x 6 2 x 8 2 x 10 2 x 12

    Spacing(inches)

    Species GradeThemeasurementsbelowareinfeetinches

    (e.g.910=9feet,10inches).

    16Douglas

    Firlarch

    #2or

    better910 144 182 223 259

    16 Hemfir#2or

    better92 142 1711 2111 255

    24Douglas

    Firlarch

    #2or

    better710 119 1410 182 210

    24 Hemfir#2or

    better73 115 148 1710 209

    Usethistableforrafterspansthathaveheavydeadloadsanddonothaveaceilingattached.

    20 PSF Dead LoadRoof live load = 20 psf, ceiling not attached to rafters, L/=180

    Rafter Size 2 x 4 2 x 6 2 x 8 2 x 10 2 x 12

    Spacing(inches)

    Species GradeThemeasurementsbelowareinfeetinches

    (e.g.910=9feet,10inches).

    16Douglas

    Firlarch

    #2or

    better86 125 159 193 224

    16 Hemfir#2or

    better85 123 156 1811 220

    24Douglas

    Firlarch

    #2or

    better611 102 1210 158 183

    24 Hemfir#2or

    better610 100 128 156 1711

  • 7/28/2019 Project Modul

    29/51

    28

    SpanTableR802.5.1(2),

    Usethistableforrafterspanswithaceilingattachedandconventionallightweightdeadloads.

    10 PSF Dead LoadRoof live load = 20 psf, ceiling attached to rafters, L/=240

    Rafter Size 2 x 4 2 x 6 2 x 8 2 x 10 2 x 12

    Spacing(inches)

    Species GradeThemeasurementsbelowareinfeetinches

    (e.g.910=9feet,10inches).

    16Douglas

    Firlarch

    #2or

    better811 141 182 223 259

    16 Hemfir#2or

    better84 131 173 2111 255

    24Douglas

    Firlarch

    #2or

    better710 119 1410 182 210

    24 Hemfir#2or

    better73 115 148 1710 209

    Usethistableforrafterspanswithaceilingattachedandwhereheavydeadloadsexist.

    20 PSF Dead LoadRoof live load = 20 psf, ceiling attached to rafters, L/=240

    Rafter Size 2 x 4 2 x 6 2 x 8 2 x 10 2 x 12

    Spacing(inches)

    Species GradeThemeasurementsbelowareinfeetinches

    (e.g.910=9feet,10inches).

    16Douglas

    Firlarch

    #2or

    better86 125 159 193 224

    16 Hemfir#2or

    better84 123 156 1811 220

    24

    DouglasFirlarch

    #2or

    better611

    10

    2

    1210

    15

    8

    183

    24 Hemfir#2or

    better610 100 128 156 1711

    Usetheconventionallightweightdeadloadtablewhentheexistingroofingmaterialsarewood

    shake,woodshingle,compositionroofingorlightweighttileroofs.(Therationaleforallowing

    thesetablestobeusedisthattheinstallationofaPVsystemshouldbeconsideredaspartof

    theliveload,sinceadditionalloadingwillnotbeaddedtothesectionoftheroofwhereaPV

    arrayisinstalled.)

    Whereheavy

    roofing

    systems

    exist

    (e.g.

    clay

    tile

    or

    heavy

    concrete

    tile

    roofs),

    use

    the

    20

    lbs/ft

    2

    deadloadtables.

  • 7/28/2019 Project Modul

    30/51

    29

    APPENDIXC:SPECIALELECTRICALTOPICS

    ModuleFrameGrounding:

    Theprimary

    concern

    raised

    by

    industry

    experts,

    including

    the

    Solar

    ABCs,

    has

    been

    the

    fact

    that

    theanodizedaluminumframesincontactwithanodizedaluminumrailsmaynotcreatean

    adequateandreliableelectricalconnection.Untilthisissuewasraised,mostinspectorsand

    contractorsweresatisfiedwithgroundingthemetalsupportstructureratherthangrounding

    individualmodules.Severalstandardandnewgroundingmethodscanaddresstheelectrical

    bondofthemoduleframetoitssupportbypenetratingeachnonconductivesurfacewitha

    sharp,metallurgicallycompatibledevice.Thisdevicemaybeasimpleasastainlesssteelstar

    washer,orasuniqueasaspeciallydesignedgroundingclipwithsharppointstopiercethe

    anodizing.

    PVmodule

    grounding

    options

    include

    avariety

    of

    methods

    including

    grounding

    screws

    or

    lugs

    oneachmoduleconnectedtoagroundwire,ormethodsthatcreateanelectricalbond

    betweenthemoduleframeanditssupportstructure.InstallationmanualsforPVmoduleshave

    becomemoreexplicitaboutgroundingmethods,butitisnotnecessaryforthemanualtostate

    everypossiblemethodofcompliance.TheUL1703teststandardforthesafetyofPVmodulesis

    beingrevisedtoallowanymethodthatmeetstherequirementsofUL467,Groundingand

    BondingEquipmentaslongasthemetalsarecompatibleandthematerialsareableto

    withstandanoutdoorenvironmentandexpandstheoptionsforgroundingmodules.

  • 7/28/2019 Project Modul

    31/51

    30

    ACConnectiontoBuildingElectricalSystems

    ACConnectiontoLoadSideofMainServicePanel

    The

    connection

    of

    PV

    systems

    inverter

    output

    circuit

    to

    the

    load

    side

    of

    the

    Main

    Service

    panel

    isthemostcommoninstallationmethod.Thistypeofconnectionisgovernedbythe

    requirementsofNEC690.64(B). TheserequirementsdictatethatthemaximumsumofOCPDs

    thatcanbefedintoaconductororbusbaris120%ofthebusbarorconductorrating(NEC

    690.64(B)(1)).Forexample,ifabusbarhasacurrentratingof225amps,andamainbreaker

    ratedat200amps,thenthemaximumbreakerratingforaPVinverteris70ampsasshown

    below:

    MaximumallowableOCPD:Busbar=225A;120%ofBusbar=225Ax1.2=270A

    ExistingMainOCPD=200A

    MaximumPVOCPD=MaximumallowableOCPDExistingMainOCPD

    =270A200A=70A

    Todeterminethemaximumsizeinverterthatcanbefedintoa70AOCPD,rememberthatmost

    circuitbreakersandotherOCPDsarelimitedto80%oftheircurrentratingforcontinuous

    operation. Thismeansthat70Acircuitbreakermustbesizedsothat56Acanpassthroughthe

    breakeronacontinuousbasis(3hoursormore).SincePVinvertersareratedbasedontheir

    maximumpowerat40Cforacontinuous3hourperiod,aninvertercapableofacontinuous

    56Aiscapableof11,648Wattsat208Vac;13,440Wacat240Vac;and15,512Wacat277Vac.

    Theonlywaytoputmorecurrentintotheloadsideoftheservicepanelinthisisexample,isto

    reducethesizeofthemainOCPD.TotheextentthatthemainOCPDisreduced,thePVinverter

    OCPDmaybeincreased.However,anytimeamainOCPDisreduced,aloadcalculation

    followingtherequirementsofNECArticle220mustbecalculatedtoshowthattheloadonthe

    mainOCPDwillnotseemorethanan80%continuousloadatthechosenOCPDrating.

    Ifnootherpanelboardsexistonthisservice,theonlyotheropportunitytoinstallalargerPV

    systemistomakeasupplysideserviceconnection(NEC690.64(A)).Thismethodisdiscussedin

    theACSupplySideConnectionsectioninthisAppendix.

  • 7/28/2019 Project Modul

    32/51

    31

    ACConnectiontoSubpanel:

    Whenasiteservicecontainsmorethanonepanelboard,thepanelsfedfromthemainservice

    panelarereferredtoassubpanels.TheNEC,in690.64(B)(1),allowstheinverterOCPDtobe

    connectedatanylocationinthepremiseswiringsystem,providedthatthe120%ofbusbarand

    conductorampacity

    limitation

    is

    observed.

    Forexample,alargeresidencehasamainpanelwitha400ampratingwitha400ampmain

    OCPD.Froma200ampbreakerinthis400amppanelisa200amppanelattheoppositeend

    oftheresidence.Inthisexample,thePVarrayislocatedmuchclosertothe200amppanel,so

    thepreferredinterconnectionpointisthe200amppanel.AslongastheinverterOCPD

    complieswithlimitationsofthe200amppanel,theinvertercaninterconnectatthatpanel.

    Witha200ampbusbaranda200ampmainbreaker,thelargestPVOCPDallowedinthatpanel

    is40amps(seediscussiononACConnectiontoLoadSideofMainServicePanelinthis

    Appendix).Assuming

    a40

    amp

    PV

    OCPC

    is

    sufficient

    for

    the

    PV

    inverter

    (e.g.

    7000

    Watt

    inverter),theissuesofconcerninthesubpanelareaddress.

    Nowconsiderthecurrentflowatthemainservicepanel.The2008NECinstructstheinstallerto

    calculatethesumofthesupplyOCPDsatthemainservicepanelbasedontheratingofinverter

    OCPD,whichis40amps,notthe200ampfeederbreakerthatfeedsthesubpanel[NEC

    690.64(B)(1)].Clearly,the40ampPVOCPDdoesnotexceedthe120%ofbusbarratinginthe

    400amppanel,whereas,hadthe200ampfeederbreakervaluebeenusedinthecalculation,

    theinstallationwouldhavebeeninviolation.

    Takingthisexampleoneadditionalstep,shouldanotherPVinverterbedesired,duetothelarge

    electricalconsumptionoftheresidence,thereisstillampacityallowanceinthe400ampmainpanelbusbar.TheallowableinverterOCPDsizewouldbecalculatedasfollows:

    MaximumallowableOCPD:Busbar=400A;120%ofBusbar=400Ax1.2=480A

    ExistingMainOCPD=400A;InverterOCPDin200Asubpanel=40A

    MaximumPVOCPDin400Apanel=MaximumallowableOCPDExistingMainOCPD

    InverterOCPDin200Asubpanel=480A400A=40A

    Thereforean

    additional

    40A

    inverter

    OCPD

    could

    be

    placed

    in

    the

    main

    panel

    without

    any

    changestothepanel.

    ShouldalargerPVsystembedesiredthancouldbehandledbythetwo40Abreakersinthis

    example,refertothediscussionsinACConnectiontoLoadSideofMainServicePanelinthis

    Appendix.

  • 7/28/2019 Project Modul

    33/51

    32

    ACSupplySideConnection:

    WhenthesizeofPVsystemisrelativelylargerelativetothesizeofthesiteservice,itisfairly

    commontoconsiderasupplysideconnectionfortheinverterOCPD.Wheneverthe120%

    allowanceforOCPDsconnectedtobusbarsorconductorscannotbeobserved,duetosizeof

    therequired

    PV

    OCPD

    and

    the

    limited

    size

    of

    the

    service

    panel,

    the

    supply

    side

    connection

    may

    betheonlyalternativeavailable.Asupplysideconnectionbydefinitionismadebetweenthe

    servicemeterandtheservicedisconnect.

    Notallservicescanbelegallyconnectedatthispoint.Forinstance,manyallinonemeter

    panels,usedroutinelyinnewresidentialconstruction,havenomeansofmakingsucha

    connectionwithoutviolatingthelistingoftheproduct.Ontheotherendofthesizespectrum,

    manylarge3,000ampservicepanelshavenospaceforsuchaconnection.Tofurther

    complicatethissituation,someutilitieshavebegunrequiringmeteringcurrenttransformersto

    beinstalledontheloadsideofserviceOCPD,makingasupplysideconnectionimpossible.

    Withthosecomplicationsaside,wewilldiscussthesituationswhereasupplysideconnectionis

    possibleanddoesnotviolatetheequipmentlistingsoftheserviceequipment.TheNECcovers

    supplysideconnectionsin230.82.ThesupplysideconnectionforthePVsystemmusthavea

    disconnectandOCPDlocatedimmediatelyadjacenttothemainservicedisconnectasspecified

    in230.91.Eventhoughthetaprule,discussedinArticle240.99doesnotapplytosupplyside

    connections,thesizeoftheconductorsconnectingthesupplysideconnectiontothePVOCPD

    aresizedaccordingtoratingoftheOCPD.Therefore,ifa60ampfuseddisconnectisusedas

    thePVOCPD,theconductorsizebetweenthesupplysideconnectionandthePVOCPDneed

    onlybe6AWG,regardlessofthesizeofserviceconductors.

    ThemethodofterminationofPVconductorstothesupplyconductorsorbusbar,dependsontheserviceequipmentandconductors.Inanycase,theservicevoltagewillneedtobe

    interruptedtotieintotheserviceconductorsorbusbarunlesstheveryrareexceptions

    outlinedinNFPA70Eareinvolvedatfacilitieslikehospitalswherethecutinprocessmustbe

    donewhileenergized.Typicalterminationmethodsincludeseveraloptions:

    1. luggingtoanaccessibleperforatedbuswithinserviceequipment;

    2. usingemptysetofdoublebarrellugswithinserviceequipment;

    3. usingpiercinglugsonconductorsbetweenmeterandservicedisconnect;

    4. anylugidentifiedformakingconnectionstoconductorsofthesizerangeinstalled.

    Ofteninstallinglugsonserviceconductorswillrequireremovalofserviceconductorsand

    conduitandreinstallingconductorswithajunctionboxtoaccommodatetheconnection.

  • 7/28/2019 Project Modul

    34/51

    33

    SourceCircuitOvercurrentProtection:

    SourcecircuitovercurrentprotectionmustbesizedsothatboththePVmoduleandthe

    conductorfromthemoduletotheovercurrentdeviceareproperlyprotected[690.9(A),240.20

    (A)].PVmodulesmustbeprotectedsothatthemaximumseriesfuserating,printedonthe

    listinglabel,

    is

    not

    exceeded.

    It

    is

    important

    to

    note

    that

    even

    though

    the

    listing

    label

    states

    fuserating,amoreaccuratetermwouldbethemaximumseriesovercurrentprotection

    ratingsinceeitherafuseoracircuitbreakermaybeusedtosatisfythislistingrequirement.The

    modulemaybeprotectedeitherbyinstallingfusesorcircuitbreakersinaseriesstringof

    modulesorbythedesignofthePVsystem.

    InverterslistedwithaMaximumutilitybackfeedcurrentthatiswellabove2amps(typically

    equaltothemaximumallowableoutputovercurrentprotection)mustbeassumedtoprovide

    backfeedcurrenttothePVarray.Eachsourcecircuitmusthaveovercurrentprotectionthatis

    greaterthanorequaltotheminimumPVSourceCircuitcurrentratingandlessthanorequalto

    the

    maximum

    series

    fuse

    rating.

    Explanation:Foranarraywithamaximumsourcecircuitcurrentof6.8ampsandamaximum

    seriesfuseratingof15amps,Theminimumfuseratingwouldbe9amps(nextlargerfuseratingabove

    8.5amps;6.8Ax1.25=8.5A)andthemaximumwouldbe15amps.

    Inverterslistedwithamaximumutilitybackfeedcurrentthatis2ampsorless(e.g.FroniusIG

    5100),twosourcecircuitscanbeconnectedtotheinverterwithoutrequiringovercurrent

    protectiononeithercircuit.

    Explanation:Ifanarraycontainingtwostringsinparallelisconnectedtoaninverterthatisa

    limitedbackfeedingsource(2ampsorless),themaximumcurrentinastringisequaltothecurrentfrom

    theotherstringinparallelplusthemaximumbackfedcurrentfromtheinverter.Ifthemaximumcurrent

    ofeachstringis6.8Amps,andtheinverterprovides2amps,thenthemaximumcurrentinafaultatanyPVmoduleis8.8Ampsandthemaximumseriesfuseratingofthemodulewillneverbeexceeded(i.e.a

    modulewithanISCof5.4ampwillhaveamaximumseriesovercurrentdeviceratingofatleast10amps).

    Forsmallerinverterslistedwithamaximumutilitybackfeedcurrentthatisnolargerthanthe

    modulemaximumovercurrentdevicerating(e.g.EnphaseM200witha1.6amputility

    backfeed),asinglesourcecircuitcanbeconnectedtotheinverterwithoutrequiring

    overcurrentprotectiononthearraycircuit.

    Explanation:Ifasinglestringarray(couldbeasinglemodulearray)isconnectedtoaninverter

    thatprovideslessthantheratedmodulemaximumovercurrentdeviceratinginbackfeedcurrent,itis

    equivalenttohavingthatsizeovercurrentdevicepreventcurrentflowfromtheutilityandthearrayis

    protected.ThemaximumreversefaultcurrentatanyPVmoduleistheamountoftheinverterutilitybackfeedcurrentandthemaximumseriesfuseratingofthemodulewillneverbeexceeded.

  • 7/28/2019 Project Modul

    35/51

    34

    DisconnectingMeans:

    TheNECdefinesdisconnectingmeansinthefollowway:

    NECArticle100DisconnectingMeans.Adevice,orgroupofdevices,orothermeansbywhich

    theconductors

    of

    acircuit

    can

    be

    disconnected

    from

    their

    source

    of

    supply.

    Aprimarypurposeofadisconnectingmeansistoopenacircuitprovidingasourceofsupplyso

    thattheequipmentfedbythatsourcecanbemaintainedwithoutexposingtheoperatorto

    hazardousvoltages(NFPA70E).

    DisconnectingMeansinInverters:

    Variousinvertershaveprovidedavarietyofintegraldcandacdisconnects.Thesedisconnects

    mayormaynotprovidethenecessaryisolationformaintenance.Thekeyindifferentiating

    whetherthesupplieddisconnectsprovidetheappropriateisolationistoreviewtheprimary

    method

    of

    maintenance

    and

    repair

    of

    the

    device.

    If

    the

    device

    has

    a

    standard

    means

    of

    removingthepartsneedingservice,withoutexposingthetechniciantohazardousvoltages

    (anythingover50Volts),thesupplieddisconnectsmeettheintentofmaintenance

    disconnectingmeans.Ifthetechnicianisexposedtovoltagesabove50Voltsduringservice,

    evenwiththesupplieddisconnectingmeans,externaldisconnectingmeansmaybenecessary.

    ItisimportanttopointoutthateverycurrentlyavailablePVinverter,thatdoesnotoperateon

    abatterysystem,hasinputcapacitors.Thesecapacitorsmayremainenergizedforfiveormore

    minutesafterallexternalsourcesareremovedfromaninverter.Internalbleedresistors

    removethisvoltageoveraprescribedtimeperiod,andwarninglabelsareprovidedonthe

    invertertoidentifythishazard.Thishazardistypicalofelectricalequipmentusingsignificant

    capacitance.This

    capacitive

    source

    is

    controlled

    by

    warning

    signage

    and

    bleed

    resistors

    and

    not

    generallybyinternalorexternaldisconnects.Disconnectsshouldnotberequiredtocontrolthe

    capacitivesourceduringmaintenanceorserviceoftheinverter.

    UtilityRequiredDisconnectingMeans:

    UtilitiesmayrequiresomemethodtoisolatePVsystemsfromtheirgridduringmaintenance

    procedures.Theisolationdeviceisusuallyrequiredtoprovideavisiblebreakinorderto

    comply,andmoldedcasecircuitbreakersdonotmeetthatrequirement.Severalutilities,

    includingtheutilitywiththemostPVinstallationsintheU.S.,PacificGas&Electric,have

    adoptedapolicy

    of

    allowing

    residential

    PV

    systems

    with

    self

    contained

    meters

    (the

    most

    commonresidentialtypemeter)toprovidethenecessaryvisiblebreakviaremovalofthe

    meter.Forinstallationswithcurrenttransformermeters,aseparatevisiblebreakswitchis

    almostalwaysrequired.Whentheutilityrequiresavisiblebreakswitch,thisswitchmaybe

    usedtoprovidetheNECrequiredacswitchformaintainingtheinverteriftheinverterislocated

    intheimmediatevicinityoftheswitch.

  • 7/28/2019 Project Modul

    36/51

    35

    Provisionsforthephotovoltaicpowersourcedisconnectingmeans:

    The2005NECstatesin690.14(C)(1),Location.Thephotovoltaicdisconnectingmeansshallbe

    installedatareadilyaccessiblelocationeitheroutsideofabuildingorstructureorinside

    nearestthepointofentranceofthesystemconductors.Thephotovoltaicsystemdisconnecting

    meansshall

    not

    be

    installed

    in

    bathrooms.

    a) ReadilyaccessibleNECArticle100states,Accessible,Readily(ReadilyAccessible).

    Capableofbeingreachedquicklyforoperation,renewal,orinspectionswithoutrequiring

    thosetowhomreadyaccessisrequisitetoclimboverorremoveobstaclesortoresortto

    portableladders,andsoforth.

    b) Readilyaccessibleprovisionisprimarilyforemergencyoperation.Ifthedisconnectis

    notmountedincloseproximityoftheserviceentrancedisconnect(usuallywithin10

    feetofthemeterlocationorservicedisconnectswitch),thenadiagramordirectory

    mustbeprovidedtoclearlyidentifywherethedisconnectingmeansislocated.

    c) A

    rooftop

    disconnect

    on

    a

    residential

    roof

    will

    normally

    not

    qualify

    as

    a

    readily

    accessibledisconnect.

    Anexceptiontothisrequirementwasaddedtothe2005NECtoprovideadditionalclarification

    forresidentialandbuildingintegratedPVsystems.Thisexceptionreads:

    Exception:Installationsthatcomplywith690.31(E)shallbepermittedtohavethe

    disconnectingmeanslocatedremotefromthepointofentryofthesystemconductors.

    NEC690.31(E)states:

    (E)Direct

    Current

    Photovoltaic

    Source

    and

    Output

    Circuits

    Inside

    aBuilding.

    Where

    direct

    currentphotovoltaicsourceoroutputcircuitsofautilityinteractiveinverterfromabuilding

    integratedorotherphotovoltaicsystemareruninsideabuildingorstructure,theyshallbe

    containedinmetallicracewaysorenclosuresfromthepointofpenetrationofthesurfaceofthe

    buildingorstructuretothefirstreadilyaccessibledisconnectingmeans.Thedisconnecting

    meansshallcomplywith690.14(A)through690.14(D).

    Althoughmetalcladcableisnotspecificallycalledoutin690.31(E),manyjurisdictionsconsider

    installationswithmetalcladcableasmeetingtheintentofthisnewprovision.Notethatthis

    newsectionspecificallymentionsbuildingintegratedsystems.Thewaythe2002NECwas

    written,aroof

    integrated

    PV

    system

    cannot

    reasonably

    comply

    the

    690.14(C)(1)

    as

    written.

  • 7/28/2019 Project Modul

    37/51

    36

    APPENDIXD:COSTSOFPERMITS

    Eachjurisdictionmayhavedifferentinternalcostsstructuresandapproachestoworking

    withsolarPVsystems.Thefollowingsectionisprovidedasasuggestionindevelopingthe

    coststructureforalocaljurisdiction.

    Explanation:Costsforpermitsareoftenbasedontheoverallprojectcost.Thisworkswellfor

    manyconventionalprojectsbecausethisaccuratelyrepresentsthescaleoftheproject.However,

    withaPVinstallation,theequipmentcostsaremuchhigherthanwithotherprojectsofsimilar

    scope.ItisthereforerecommendedthatanalternativepermitfeescalebeusedforPVsystem

    installations.ThescopeofaPVinstallationissimilartothatofinstallingaretrofittedresidential

    HVACsystem.ThepermittingcostsforaPVsystemshouldbesimilartothoseforanHVAC

    system.

    Althoughinitialplanreviewandfieldinspectioncostsmaybeslightlyhigherforthefirstfew

    systems,thosecostsshouldreduceasthelocaljurisdictionbecomesfamiliarwiththe

    installations.Asubdivisionofmorethan10unitsshouldbeconsideredforanadditionalfee

    reductionbasedontherepetitivenatureofthereviews.Asuggestedfeescheduleisasfollows:

    SmallPVsystem(upto4kW):$75 $200

    LargePVsystem(upto10kW):$150 $400

    Forsystemsof1050kW,considerapermitcostof$15 $40perkW.

    Forsystemsof50100kW,considerapermitcostof$1,500.

    Forsystemsof100500kW,considerapermitcostof$3,000.

    Forsystemsupto1000kW,considerapermitcostof$3,000$5,000.

  • 7/28/2019 Project Modul

    38/51

    37

    APPENDIXE:TEMPERATURETABLES

  • 7/28/2019 Project Modul

    39/51

    High2%

    DB 0"0.5" 0.5"3.5" 3.5"12" 12"36" Max Min

    AK BARROW 4 14 47 36 31 28 19 43

    AK DEADHORSE 23 19 52 41 36 33 24 45

    AK BARTERISWSOAP 11 15 48 37 32 29 N/A N/A

    AK KOTZEBUE 5 20 53 42 37 34 24 39

    AK BETTLES 205 26 59 48 43 40 29 47

    AK FORTYUKON 135 27 60 49 44 41 29 48

    AK NOME 7 21 54 43 38 35 24 37

    AK SAINTMARY`S(AWOS) 95 22 55 44 39 36 24 34

    AK UNALAKLEETFIELD 4 21 54 43 38 35 N/A N/A

    AK BETHEL 46 22 55 44 39 36 25 35

    AK MCGRATH 103 25 58 47 42 39 2846

    AK TALKEETNA 105 24 57 46 41 38 27 36

    AK KENAIMUNICIPALAP 26 20 53 42 37 34 24 33

    AK SOLDOTNA 33 21 54 43 38 35 24 34

    AK NENANAMUNICIPALAP 109 27 60 49 44 41 30 46

    AK FAIRBANKS 138 27 60 49 44 41 31 43

    AK EIELSONAFB 167 27 60 49 44 41 31 44

    AK BIGDELTA 388 25 58 47 42 39 28 47

    AK FTRICHARDSON/BRYANTAPT 115 23 56 45 40 37 27 31

    AK GULKANA 481 24 57 46 41 38 27 45

    AK ELMENDORFAFB 65 23 56 45 40 37 25 29

    AK ANCHORAGE 35 22 55 44 39 36 25 26

    AK ANCHORAGEMERRILLFIELD 42 23 56 45 40 37 26 26

    AK VALDEZWSO 7 21 54 43 38 35 25 17

    AK WHITTIER 9 21 54 43 38 35 23 17

    AK SEWARD 18 21 54 43 38 35 26 17

    AK NORTHWAYAIRPORT 522 26 59 48 43 40 28 48

    AK CORDOVA 12 21 54 43 38 35 26 23

    AK STPAULIS. 7 12 45 34 29 26 15 19

    AK COLDBAY 29 15 48 37 32 29 19 17

    AK DILLINGHAM(AMOS) 29 21 54 43 38 35 24 34

    AK KINGSALMON 15 22 55 44 39 36 25 35

    AK PORTHEIDEN(AMOS) 29 18 51 40 35 32 N/A N/A

    AK ILIAMNAARPT 56 21 54 43 38 35 N/A N/A

    AK HOMERARPT 27 18 51 40 35 32 21 21

    AK MIDDLETONISLANDAUT 36 17 50 39 34 31 19 10

    AK KODIAK 34 20 53 42 37 34 24 17

    AK YAKUTAT 9 20 53 42 37 34 2421

    AK SITKAJAPONSKIAP 4 19 52 41 36 33 24 11

    AK JUNEAUINT`LARPT 3 23 56 45 40 37 27 18

    AK WRANGELL 13 21 54 43 38 35 25 13

    AK KETCHIKANINTLAP 23 22 55 44 39 36 25 14

    AK ANNETTE 34 23 56 45 40 37 27 12

    AK SHEMYA 30 13 46 35 30 27 14 8

    AK ADAKNAS 5 15 48 37 32 29 20 11

    AK FIVEFINGERISLAND 7 18 51 40 35 32 22 9

    AL MOBILE 67 34 67 56 51 48 36 7

    AL MONTGOMERY 62 36 69 58 53 50 37 9

    DesignTemperaturesForVariousU.S.CitiesThefollowingtableindicatesthe2%designtemperature(averagedforJuneAugust)forvariouscities;andthe

    lowestexpectambienttemperature[690.7]foreachlocation(MinMeanExtremeAnnualDB).Thefirstcolumnis

    elevationofthestationforcomparingclimateswithlocationsnotlisted.ColumntworepresentstheASHRAE2%

    designtemperature(1).Thethirdthroughsixthcolumnistheresultantambienttemperatureinsidetheconduit

    unloaded(2).Itisthetemperaturethewireissubjectedto.Thelastcolumnisthelowestexpectambient

    temperatureforthatcity,basedon30yearsofweatherdata.Thisisthetemperaturetobeusedformaximum

    voltagecalculationsinNEC690.7.AlltemperaturesinCelcius.

    Distanceaboveroof.Temp.

    in

    Conduit

    in

    Sunlight

    (C)Elev

    (M)

    ExtremeAnnual

    DB

    MeanState Station

  • 7/28/2019 Project Modul

    40/51

    State Station Elev (M) 2% 0"-0.5" 0.5"-3.5" .3.5"-12" 12"-36" Max Min .

    AL MAXWELLAFB 53 36 69 58 53 50 38 6

    AL DOTHANMUNICIPALAP 97 35 68 57 52 49 37 8

    AL CAIRNSFIELDFORTRUCKER 91 35 68 57 52 49 37 8

    AL BIRMINGHAM 192 35 68 57 52 49 37 12

    AL GADSENMUNI(AWOS) 173 34 67 56 51 48 N/A N/A

    AL TUSCALOOSAMUNICIPALAP 51 36 69 58 53 50 37 12

    AL ANNISTONMETROPOLITANAP 186 35 68 57 52 49 37 12

    AL CENTREVILLEWSMO 140 34 67 56 51 48 36 11

    AL HUNTSVILLE 190 35 68 57 52 49 36 13

    AL MUSCLESHOALSREGIONALAP 164 35 68 57 52 49 37 13

    AL DAUPHINISLAND 8 31 64 53 48 45 33

    2

    AR NORTHLITTLEROCK 170 35 68 57 52 49 37 12

    AR LITTLEROCKADAMSFIELD 78 37 70 59 54 51 39 12

    AR LITTLEROCKAFB 103 37 70 59 54 51 39 13

    AR WALNUTRIDGE(AWOS) 83 35 68 57 52 49 38 13

    AR JONESBOROMUNICIPAL 80 36 69 58 53 50 38 16

    AR BLYTHEVILLEAFB 79 36 69 58 53 50 38 15

    AR STUTTGART(AWOS) 68 36 69 58 53 50 38 9

    AR PINEBLUFFFAAAP 63 36 69 58 53 50 38 9

    AR TEXARKANAWEBBFIELD 110 37 70 59 54 51 39 10

    AR ELDORADOGOODWINFIELD 76 37 70 59 54 51 39 9

    AR FORTSMITH 141 37 70 59 54 51 39 14

    AR BENTONVILLE(AWOS) 395 34 67 56 51 48 36 17

    AR FAYETTEVILLE

    DRAKE

    FIELD 381 35 68 57 52 49 37

    18AR HARRISONFAAAP 418 35 68 57 52 49 37 16

    AR FLIPPIN(AWOS) 350 36 69 58 53 50 N/A N/A

    AR BATESVILLE(AWOS) 141 37 70 59 54 51 38 13

    AR ROGERS(AWOS) 415 34 67 56 51 48 37 16

    AZ DOUGLASBISBEEDOUGLASIN 1249 37 70 59 54 51 40 9

    AZ TUCSON 779 41 74 63 58 55 43 3

    AZ DAVISMONTHANAFB 808 40 73 62 57 54 43 2

    AZ SAFFORD(AMOS) 950 40 73 62 57 54 42 10

    AZ PHOENIX 339 43 76 65 60 57 46 0

    AZ LUKEAFB 331 44 77 66 61 58 47 1

    AZ YUMAINTLARPT 62 44 77 66 61 58 47 2

    AZ KINGMAN(AMOS) 1033 38 71 60 55 52 40 8

    AZ PAGEMUNI(AMOS) 1304 37 70 59 54 51 40 9

    AZ PRESCOTTLOVE

    FIELD 1536 35 68 57 52 49 37

    13

    AZ WINSLOWMUNICIPALAP 1490 36 69 58 53 50 39 15

    AZ FLAGSTAFF 2135 30 63 52 47 44 32 22

    CA ELTOROMCAS 116 33 66 55 50 47 38 3

    CA TUSTINMCAF 18 34 67 56 51 48 39 2

    CA MARCHAFB 462 38 71 60 55 52 42 2

    CA ONTARIO 303 38 71 60 55 52 42 1

    CA NORTONAFB/SANBERN 353 39 72 61 56 53 43 2

    CA BURBANKGLENDALEPASADENA 225 37 70 59 54 51 41 1

    CA SANLUISOBISPO 64 31 64 53 48 45 37 2

    CA SANDIEGO 9 29 62 51 46 43 34 5

    CA SANDIEGONORTHISLANDNA 14 28 61 50 45 42 34 5

    CA CAMPPENDLETONMCAS 22 34 67 56 51 48 39 3

    CA SANDIEGOMIRAMARNAS 139 33 66 55 50 47 38 1

    CA LOSANGELES 32 29 62 51 46 43 35 4

    CA LONGBEACH 17 33 66 55 50 47 39 2

    CA EDWARDSAFB 705 41 74 63 58 55 44 10

    CA DAGGETT 588 42 75 64 59 56 45 5

    CA LANCASTERGENWMFOXFIEL 712 39 72 61 56 53 42 9

    CA GEORGEAFB 869 38 71 60 55 52 41 6

    CA SANDBERG 1376 33 66 55 50 47 35 6

    CA BAKERSFIELD 150 40 73 62 57 54 43 2

    CA FRESNO 100 40 73 62 57 54 42 3

    CA VISALIAMUNI(AWOS) 89 38 71 60 55 52 40 3

    2

  • 7/28/2019 Project Modul

    41/51

    State Station Elev (M) 2% 0"-0.5" 0.5"-3.5" .3.5"-12" 12"-36" Max Min .

    CA PT.PIEDRASBLANCA 21 26 59 48 43 40 N/A N/A

    CA POINTMUGUNF 3 28 61 50 45 42 34 2

    CA SANTABARBARAMUNICIPALA 2 29 62 51 46 43 35 1

    CA SANTAMARIA 72 29 62 51 46 43 35 3

    CA PASOROBLESMUNICIPALARP 243 39 72 61 56 53 43 6

    CA BISHOPAIRPORT 1250 38 71 60 55 52 41 14

    CA CASTLEAFB 60 38 71 60 55 52 40 3

    CA SACRAMENTO 8 38 71 60 55 52 41 3

    CA MATHERFIELD 29 38 71 60 55 52 41 3

    CA MCCLELLANAFB 25 39 72 61 56 53 42 3

    CA BEALEAFB 38 38 71 60 55 52 41

    3

    CA SACRAMENTOMETROPOLITANA 7 38 71 60 55 52 41 3

    CA SALINASMUNICIPALAP 21 28 61 50 45 42 35 1

    CA STOCKTONMETROPOLITANARP 6 38 71 60 55 52 41 3

    CA OAKLANDMETROPOLITANARPT 1 28 61 50 45 42 33 1

    CA SANFRANCISCO 5 28 61 50 45 42 35 1

    CA SANJOSEINTLAP 15 34 67 56 51 48 38 0

    CA BLUECANYONAP 1609 29 62 51 46 43 31 9

    CA UKIAHMUNICIPALAP 188 38 71 60 55 52 42 3

    CA REDBLUFFMUNICIPALARPT 106 41 74 63 58 55 44 4

    CA REDDINGMUNICIPALARPT 153 41 74 63 58 55 44 5

    CA EUREKA 18 20 53 42 37 34 N/A N/A

    CA ARCATA 69 21 54 43 38 35 28 3

    CA MOUNT

    SHASTA 1077 33 66 55 50 47 35

    12CA ALAMEDANAS 4 29 62 51 46 43 34 3

    CA MOUNTAINVIEWMOFFETTFLD 11 31 64 53 48 45 36 0

    CA TRAVISFIELDAFB 18 37 70 59 54 51 41 3

    CA LEMOOREREEVESNAS 73 40 73 62 57 54 42 3

    CA IMPERIAL 17 44 77 66 61 58 47 1

    CA PALMSPRINGSTHERMALAP 34 44 77 66 61 58 48 5

    CA BLYTHERIVERSIDECOARPT 118 45 78 67 62 59 48 1

    CA POINTARENA 12 17 50 39 34 31 21


Recommended