PTF-PAC: CAC- Project Completion Report1
Name of the CSO: Transparency International India
Address: QUARTER NO-4, LAJPAT BHAVAN , LAJPATNAGAR 4, NEW DELHI-110024
Project name & PTF code: Supporting Activities of Integrity Pact Cell Under
Citizens Against Corruption Programme
Project Goal:
To improve the effectiveness, credibility and sustainability of the Integrity
Pact as a means for increased transparency and accountability on public
contracting processes and systems
2. Project Objectives:
As specified in the Approved
Project proposal
Status of achievement at completion
1 It is suggested that the Annexes be prepared first.
2
To increase the influence of
Integrity Pact through the
inclusion of more PSU’s as well
as governmental and private
sectors within the programme. .
� In this phase TII has signed MoU with
Tehri Hydro Development Corporation
Ltd (THDC)for adoption of IP.
� TII is also in touch with representative of
Odisha Hydro Power Corporation
Ltd(OHPC) and Andaman and Nicobar
Islands Integrated Development
Corporation Ltd (ANIIDCO Ltd) for
adoption of IP.
� TII has organized several meetings and
workshop(Delhi , Patna , Mumbai ,
Bengaluru ) for advocacy of IP among
Public and Private sector .
� TII has also written to various ministries,
Chambers of Commerce and gave
presentation on different forums for
adoption of IP.
To strengthen the
effectiveness of Integrity
Pact by monitoring Public
procurement of IP
signatories Public Sector
Undertakings (PSUs) and
other organizations and
also fine-tuning of IP
program .
• TII has taken various cases from
different PSUs including OIL ,
Power Grid Corporation , Coal
India , NALCO and effectively
resolve these cases .
• We have also engaged ourselves
with bodies like Comptroller and
Auditor General and Competition
commission of India for effective
monitoring of IP.
• TII has also done a study and
compiled cases related to
collusion in public sector.
• Cases related to Corruption in
various organizations like
NABARD , NALCO and TII’s effort
in highlighting cases of
whistleblowers have been widely
covered in various newspapers
like Hindu ,Economic Times,
Tribune, DNA and it has indirectly
3
helped in monitoring process.
• TII has organized various training
programs for capacity building of
procurement officers
Fine tuning of IP program ,
in order to achieve desired
results as being highlighted
in the in the assessment
report published after
phase I
• Various Bidders meet has been
organized to make IP effective
among private vendors.
• Reaching out to state PSUs and
governmental departments for
advocacy of IP.
• Special focus has been given for
addressing issues related to
cartels and transparency in
Defence Procurement .
3. Project Area location: The project area embraces whole India (Annexure 1)
4. Project period: a) Original: 12 months b) Actual: 13 months and 15 days
5. Project Budget 14, 70, 000.00 INR (33,409USD)
6. Budget utilized as on (date) 14, 70, 000.00 INR (33,409USD)
7. Project Completion Summary (maximum five pages).
((Summarize project implementation and results achieved. This should include
achievement of objectives. It should include a brief description of: (i) the activities that
were carried out and the outputs that were produced due to the activities; and (ii) the
results that were achieved (referring to the log frame / results framework for the
project) and how the outputs and activities from the project contributed to
4
accomplishment of each result. . In particular explain what impact the project had on
reducing corruption and provide quantitative and qualitative information in support of
the impact described. End this section with a self assessment of achievement of project
objectives, what main obstacles have been encountered, if any, and what actions have
been taken to overcome them and project efforts and experience with constructive
engagement.
Please note that PTF policy is to post the completion report on its website. So please
take extra care to ensure that your report is properly edited and is ready for
publication.)
7.1 Strategies used to achieve project goal and objectives
a. Engagement with Stakeholders
Integrity Pact has three important stakeholders
- Public Sector Undertakings
- Independent External Monitors
- Vendors/Bidders. Through various workshops, meetings, TII’s website and
communication material we have tried to get ourselves actively involved with all
stakeholders. This phase we have also reached out to agencies like Comptroller and
Auditor General of India , Competition Commission of India and State vigilance
Bureau and Lokayuktta office .
b. Assistance to stakeholders : TII as a facilitator
TII has taken cases of Bidders from various PSUs like OIL , Indian Oil etc and
effectively resolved them.
TII has also assisted PSUs for effective monitoring of IP.
With the active intervention from TII , whistleblowers like Shri Ram Padhy (NALCO)
and Shri A.K Jain (DVC) got relief
c. Engagement with TI’s National Chapters.
Issues related to Non signing of IP by foreign bidders has been taken by TII with
respective TI Chapters.
TII with support from TIUK organized a conference on “ Transparency in Defence
Procurement “ it was attended by Executive Director TINepal and TI Srilanka.
d. Monitoring: Apart from advocacy of IP TII has been actively involved in monitoring
of IP in IP compliant PSUs and private bidders all complaints or issues related to IP
and other , were forwarded to concern officers and maximum cases were resolved .
e. Constructive Engagement with Central Vigilance Commission, Comptroller and
Auditor General and Competition Commission of India
5
CVC has been a great supporter of IP, it has issued various circulars, directing PSUs
for proper implementation of IP.TII has kept CVC informed about IP cell activities.
Representatives from CVC , CAG and CCI has been present in all IP related meetings
and workshops. The cases related to violation of IP or others, have been referred to
CVC for necessary action , the activities of IP cell has been widely covered by CVC
newsletters
f. Networking with Media.
Events and activities related to IP has been widely covered by major national dailies
including Economic Times, Times of India , Business standard etc. Few links
http://www.dnaindia.com/india/1704219/report-dna-investigation-how-pranabs-sullied-family-
run-iip-fixed-psu-recruitments.
http://www.dnaindia.com/india/1703768/report-dna-investigation-theres-a-blot-on-pranabs-
impeccable-cv
http://articles.economictimes.indiatimes.com/2013-02-18/news/37160612_1_integrity-pact-
defence-ministry-vendor-contract
http://www.dnaindia.com/india/1763467/report-govt-is-behind-cvcs-delay-in-acting-against-38-
officials.
g. Engagement with Chamber of Commerce and other private players In order to
promote IP among private sector , we have been actively involved with CII. Few
focus group meetings have been organized with representatives from CII and
private sector representatives , till date we haven’t got any breakthrough .
h. Peer learning (knowledge sharing)
The activity report, success stories and challenges faced have been shared with
stakeholders and these are also uploaded on our facebook page.
6
7.2. Project activities (Details in Annex 2).
• Conference /workshop at Delhi , Bengaluru ,Patna and Mumbai.
• Development and dissemination of IP related communication material like
quarterly newsletter, training manuals.
• Training programs have been organized for procurement officers.
• Address complaints received from IP stakeholders.
• Quarterly monitoring of progress of the project by Coordination Committee
for IP cell .
• Management of staff, finances and other logistics of the IP cell, at TII office.
• Field visits to the PSUs.
• Manual for Independent External Monitors.
7.3 Project outputs (Details in Annex 3)
Output as listed in logical framework :
a) Quarterly Newsletter
b) IEC material
c) Quarterly Progress report
d) Training Manuals (including write up on identifying red-flags in e - procurement)
e) Case Study on Cartel and Collusion in Indian Industries
7.4 Project Impact on Corruption (Outcomes /Results) (Details in Annex 4)
1. One more PSU have adopted IP , extending the regime of transparency in public
procurement to total 45 PSUs.
2. All complaints received were reviewed and marked to IEM , CVC for possible action.
3. TII has also actively helped whistleblowers.
4. The various workshops , discussions in different part of the country has helped in
advocacy of IP .Now stakeholders are more aware of various provisions of IP.
5. Trainings sessions especially on e procurement has helped a lot to the officers from
the PSU, it will surely benefit them in identifying red flags in procurement.
6. The Manual for IEMs will certainly help them to resolve issues related to IP speedily
7
Self-Assessment of Project Progress:
Include aspects of your team’s capacity and contributions, community involvement and
support; any significant impact seen and external factors affecting project success – positively
or negatively for the project period.
• Team Capacity and Contribution:
IP cell staff with active support from volunteers , having domain knowledge of the
subject has helped in making a positive impact on the project . Team has
streamlined the flow of IP related information from one PSU to the other . Given the
vast geographical extent of the PSUs , activities of IP cell is a small beginning which
has to be accelerated with time by engaging more and more people from different
domain.
The various training programs organized on transparency in procurement has
helped in capacity building of the organization
• Community Involvement and Support:
Various whistleblower groups like of PSUs of DVC , NALCO NABARD has helped in
dissemination of issues related to transparency in their organization and helped us
in exposing various cases of corruption
• Impact:
The activities of IP cell has exposed few mega corruption cases in the country eg in
Recruitment in PSUs, NABARD loan disbursement , victimization of whistleblower , it has
given a positive impact , now the cases reported to IP cell has been increased to many
fold . IP cell has started working as pressure group , which is very well appreciated by
many .
8. Lessons learnt and their replicability:
Difficulties faced and measures adopted to overcome the same:-
Successes met:-
Operational issues within the organisation that were favourable / not so favourable :-
Operational issues with other stakeholders like government, community,
panchayat/municipality etc. and how were they resolved:-
Explain where and how your experiences can be replicated:-
• Difficulties faced and measures adopted to overcome the same:-
8
� TII IP cell has a very small three member team and engaging with PSUs working
in different domain namely oil, mining , gas etc was challenging task . To achieve
desired results we took help of volunteers both in and out of TII , some of these
volunteers are Independent External Monitor of PSUs.They have helped us in
resolving various issues related to implementation of IP
� The stakeholders are located in different part of the country , so organizing
advocacy programs was a challenge , as we had limited grant from PTF . In order
to met expenses we explored possibility of getting funds from the companies and
we got sponsorship for the event.We have also raised money from other sources
like TAF
� Getting feedback from few PSUs was tough as officials were not willing to
cooperate, so we have to file RTIs in these companies.
� Many Bidders were skeptical to give there feedback in writing, they feared that
they can be penalized for their action, a confidentiality clause was added and
maximum feedback were orally taken.
• As in many PSUs bidders have formed cartels and no complain has been registered
to IEM , so it became very difficult to measure utility of IP in these companies .
Successes met:-
� Memorandum of Understanding with THDC,Public Sector Undertakings Exposing
corruption in recruitment in various PSUs
� Selected cases studies on collusion in Indian Industries .
� Registration of various complaints in CVC.
� Compilation of success stories, feedback from stakeholders.
� Protection and support to whistleblower Shri Rampadhy, Shri A.K. Jain and others.
� Operational issues within the organization that were favorable / not so
favorable :-
� Volunteer force of TII has been asset for us but we felt need for more paid staff ,
who has exposure of working in public sector undertakings.
� In case of non compliance of IP by any Multinational Bidders .We have engaged
our national chapters and TI-S , to peruse such cases at their level.
� Constraints like limited core funding have affected expansion and advocacy of IP
among private players.
� Discouraging response from state PSUs.
� Discouraging response from Private companies
• Operational issues with other stakeholders like government, community,
panchayat/municipality etc. and how were they resolved:-
9
� The PSUs have signed MoU with TII , so getting information from them was not
tough but in many cases we have filed RTI
� Many of the bidder companies , maximum of them are private companies , are
not aware of provisions of IP , so we don’t get desired support from them , so we
have proposed to all companies to organize vendors/bidders meet every year.
� We have got desired support from Central Vigilance Commission , and
Independent External Monitors.
• Explain where and how your experiences can be replicated:-
� Community Engagement and Empowerment
We have used social media like facebook , engaged with engineering and mba
students who will be future managers and employees of the organizations, they
have helped a lot in advocacy of IP and also assisted us in carrying out our
impact Assessment Survey. The help provided by TII on complaint received from
whistleblowers Mr A.K.Jain, Shri Padhy has encouraged others also to approach
us highlighting corruption in their respective organization.
� Constructive Engagement and Support
TII model of signing MoU with the Government agencies can be replicated by
other CSOs also . Because once you sign MoU , you are morally and legally bound
to share information related to project . Focus Group Discussion with
stakeholders are very effective in engaging all in achieving common goals and
objective
� Systematic Challenges and Change
The main challenge we faced during this phase was getting cooperation from
different stakeholders, for getting honest feedback about IP as being implement
in the PSU. Verifying the complaints forwarded to us was also a major challenge.
Workshops meetings and survey has helped in constructive engagement and this
has brought a positive change in some of the PSUs officials and bidders , now
they are more upfront and in case of any issue pertaining to IP they readily
approach us.
Policy level corruption and collusive corruption is hard to detect , a strong
relation between stakeholders is required .
9. Constructive engagement:
Please include instances of useful interactions and constructive engagements with other
stakeholders (government officials, media, CSOs, NGOs including other CAC partners etc.) and
how they have helped further project success. Please name specific officials, offices that you
10
have interacted with.
• Government officials
We have got desired support from officials from PSUs CVC, CAG and Others .
• Officials closely associate with this project
(It’s difficult to list name of all officials , few name are)
List of officials
a) Shri M.B. Sagar I.P.S , CVO Shipping Corporation of India Ltd
b) Shri Paul Thomas Nodal Officer (IP) SAIL
c) Shri A.K. Jain Senior Engineer , DVC
d) Smt Vismita Tej I.R.S. CVO CCL
e) Shri M.N. Buch IEM NCL
f) Shri Reetesh Ramal Assistant Manager Vigialnce SCI
g) Shri V Murali Dy CS HPCL
h) Smt Neena Singh Pandey CVO KVIC.
i) Shri V.K Gupta IEM GAIL
j) Shri R.C Agarwal IEM OIL
k) Shri R Srikumar VC , CVC
l) Shri Ram Padhy DGM NALCO
• Civil society organizations (Coalition Against Corruption)
TII has kept informed other NGOs like CUTS , Chetna , SOFAR etc about activities of
IP cell.
• Media
Coverage of important reports , events, like workshops , signing of MoU , release of
IP report has been widely covered by all major dailies they are :
• The Times of India .
• The Economic Times
• Business Standard
• MINT
• DNA
• Hindustan Times
• Prabhat Khabar
10. Community Empowerment:
11
Explain the specific interventions that led to community empowerment. Also explain
Community Organizations Developed or Supported through this Project. Please list and
comment on quality of CBO contribution to the objectives of CAC.
• Community Engagement
We have engaged our self in meaningful dialogues with employees’ association,
students organizations. This has helped us into two ways on one hand it has
helped us in advocating IP to them, on other hand we have also got feedback on
implementation of IP in many PSUs . The employees of PSUs have helped us in
monitoring of IP.
• Community Empowerment Specific sessions were devoted in our workshop
and meetings , on identification of red flags in procurement , these sessions have
been attended by representatives from CSOs.
Quality and contribution of CBO’s
� Advocacy of IP
� Active participation in all workshops meetings conducted
� Regular meeting and interaction
� Knowledge sharing
11. Peer learning:
Please comment on the peer learning experiences in terms of:
1. your organisation under review and
2. you reviewing other organisations and
3. comment on the quality of such exercise and contribution to success of CAC project
• Your organization under review and (N/A)
• You reviewing other organizations and
� Better interaction between CSOs
� Exposure to new methods of tackling corruption.
� Help in improving documentation process.
� Gives an opportunity to collaborate with likeminded organization on
common agenda.
12
• Comment on the quality of such exercise and contribution to success of
CAC project
� Helps in sharing and learning from others
� CSOs are linked in a network , it is beneficial in longer run
� In longer run CAC partner can act as potential nodal points for advocacy
of IP at grass root level.
12. Project sustainability:
Technical: • What measures have been taken to ensure sustainability of project
processes like knowledge generation, constructive engagement and
community empowerment adopted in the project?
> Formed a IP committee consisting of people having domain
knowledge , it has helped us a lot in case of resovling compaints
from a stakeholders.
> MoU that has been signed between TII and the PSU, helps us in
engaging us with officials from PSUs.
> Representatives of various CSOs have been invited to all workshops
and meetings ,it will surely help them to identify redflags in
procurement process..
> Facebook and IEC material has helped us ensuring flow of knowledge
between stakeholders.
> Manual has been prepared to identify redflags in Public Procurement
• What plans for upcoming initiatives to ensure sustainability of
project outcomes?
> Training sessions for representatives from PSUs , CSOs
> Advocacy of IP at state and grass root level.
> Ensuring regular interaction between stakeholders though meetings
, social media etc.
> Dedicated website for IP
Social: • How much ownership does the community have of the process?
> A common man’s life is indirectly affected by corruption in
procurement , though it is not directly hit by it in many cases but in
longer run corruption in PSUs like of oil, gas &coal sector ,
contribute to the inflation, we are trying to educate masses about
repercussions of corruption in industries .
13
• How far the community is independent in dealing with the
corruption issues on their own?
• Identifying red flags and dealing with corruption in public procurement
and e procurement in PSUs is a technical matter .Representatives from
Whistleblower Groups has to be trained before they deal with
corruption issues on their own. They have the potential to deal
independently, we need to train them.
• How far the community can independently organize the road shows
or protests for their rights and curbing corruption?
> The community has potential to independently organize the road
shows or protest.
Institutional: • What are the organizational plans to continue the project on your
own?
> Continue engagement with the PSUs , CVC
> Knowledge and experience sharing with stakeholders
> Capacity building of staff .
> Raising funds from other sources.
• How far the CBOs formed/strengthened can work on their own?
> CBO can advocate IP on their own.
> Monitoring of implementation of IP needs training and at this stage
CBO are not in position to do so.
Financial: Does the community financially contribute to the project? NO
• How much financial support can your organisation mobilize on its
own from other donors?
> We have raised funds in form of sponsorship for our events.
• Have any other donors expressed interest in supporting such
initiatives?
> Till date No
14
Annexes to be attached to the Completion Report
1. Geographical Spread of Project Area
2. Activities (Inputs) table (see the suggested format below).
3. Outputs Table (Plan vs actual –see the suggested format below).
4. Outcomes/Results (update log frame)
5. Financial Progress Report (see the suggested format below)
6. Success stories (include photos if possible) and case studies (a soft copy has been attached)
7. Materials/reports/toolkits published/disseminated and/r posted on the website.
15
Detailed Map of the Project Area (Geographical Spread)
The project area embraces whole India. The card below shows the geographical location of the
headquarters of the PSUs, which have already signed MoU. The plant location of these PSUs are
located in different part of India, e.g. National Mineral Development Corporation Limited
headquarter is at Hyderabad but have its plant in Chhattisgarh and Madhya Pradesh.
16
List of PSU’S who have adopted Integrity Pact
Sl. No. Company Head Quarter
1 Oil & Natural Gas Corporation (ONGC) New Delhi
2 Rashtriya Ispat Nigam Limited (RINL/VIZAG) Vishakhapatnam
3 Hindustan Petroleum Corporation Ltd (HPCL) Mumbai
4 Coal India Ltd. (CIL) Kolkata
5 Gas Authority of India Ltd. (GAIL) New Delhi
6 Hindustan Steelworks Construction Ltd. (HSCL) Kolkata
7 MECON Ranchi
8 Metal Scrap Trading Corporation Ltd (MSTC Ltd). Kolkata
9 National Mineral Development Corporation (NMDC) Hyderabad
10 Ferro Scrap Nigam Ltd (FSNL) Bhilai
11 Steel Authority of India Ltd (SAIL) New Delhi
12 Kudremukh Iron Ore Company Ltd. (KIOCL) Banglore
13 Bharat Refractories Ltd. (BRL) Bokaro
14 Manganese Ore (India) Ltd. (MOIL) Nagpur
15 Oil India Limited (OIL) Noida
16 Container Corp. of India (CONCOR) New Delhi
17 Neyveli Lignite Corporation Ltd –Tamil Nadu Neyveli
18 Bharat Petroleum Corporation Ltd. (BPCL) Mumbai
19 Indian Oil Corporation Ltd. (IOCL) New Delhi
20 Airports Authority of India
New Delhi
21 Mahanagar Telephone Nigam Limited New Delhi
22 Northern Coalfields Limited (NCL) Singrauli
17
23 South Eastern Coalfields Limited (SECL) Bilaspur
24 Mahanadi Coalfields Limited (MCL) Sambalpur
25 Western Coalfields Limited (WCL) Nagpur
26 Central Coalfields Limited (CCL) Ranchi
27 Central Mine Planning Design & Institute Ltd. (CMPDI) Ranchi
28 Telecommunication Consultants India Ltd (TCIL) New Delhi
29 Hindustan Copper Limited Kolkata
30 BHEL (Bharat Heavy Electrical Ltd.) New Delhi
31 National Thermal Power Corporation (NTPC) New Delhi
32 Eastern Coalfield limited ( ECL) Burdwan
33 Bharat Sanchar Nigam Limited (BSNL) New Delhi
34 Bharat Coking Coal Limited (BCCL) Dhanbad
35 RITES Gurgaon
36 Chennai Petroleum Corporation Limited (CPCL) Chennai
37 Shipping Corporation of India Ltd (SCI) Mumbai
38 National Hydro-Electric Power Corpn Ltd. ( NHPC Ltd) Faridabad
39 Power Grid Corporation of India Limited Gurgaon
40 S J V N Limited Shimla
41 Numaligarh Oil Refinery Numaligharh
42 Engineers India Ltd New Delhi
43 Pawan Hans Helicopters New Delhi
44 Orissa Power Generation Corporation Bhubaneswar
45 THDC India Ltd. Rishikesh
18
Annex 2: Accomplishment of Activities:
Project Activities Planned
(Please reproduce what was in the
Approved Proposal).
Actual Project Activities.
(Please Describe what was actually
done
Status of completion2
and (Description of
any major change in
the activity with
explanation as
needed.)
Objective – 1: To increase the influence of Integrity Pact through the inclusion of more PSU’s as well as
governmental and private sector within the programme.
• Regional workshop at Lucknow Bengaluru and Mumbai.
• Inclusion of more PSU’s/
government departments/ municipal corporations and
expansion of the program to
include private sectors within the
ambit of public contracting
• Capacity building of nodal officers, monitors and Chief Vigilance
Officers (CVOs )through organization of training and
workshops and collaboration with
civil society organizations and other like-minded individuals
� Regional Workshops were held in Bengaluru on Ethics
in Governance, Forensic
Audit and Transparency in
Public Procurement on 23rd September, and in
Mumbai on Making
Integrity Work for Business on 19th Dec. Workshop in
Lucknow was not
conducted instead of
Lucknow it was done at Patna 29 September
� THDC has signed MoU with
TII for implementation of
IP. Talks are going with
Other PSUs and CII for
adoption of IP
• Various workshops,
meetings , focus Group
Discussions have been
organized in different part
of the country, namely
Muzaffarpur
• C=fully
completed
• C=fully
completed
2 C= fully completed, NC = very limited or no completion, D= Deferred to Phase 2, IP=In progress.
19
/organizations.
• Creation and distribution of a
newsletter, reports , brochure.
(27th June’12), Delhi(22-
23rd Aug’12, 17th Oct’12,
23rd Jan’13), Bangaluru
(23rd Sep’12), Patna (29th
Sep’12), Mumbai (19th
Dec’12), in these
Conferences a session was
devoted on identifying red
flags in procurement ,
experts gave their views on
the subject. Experts
included CVOs, CMDs, IEMs,
Nodal officer, Govt officials,
CSO representatives etc.
• A very comprehensive
manual for Examination of
Public Procurement Process
has been produced. The
manual is meant for the
IEMs, CVOs, Procurement
officials and all other
individuals who concern
about transparency in
public procurement.
• IP Quarterly Newsletters
have been prepared.
• Minutes of the meetings,
issues related to IP and
progress report were
compiled and soft copy was
circulated through mail.
• C=fully
completed
• C=fully
completed
20
Objective – 2: To strengthen the effectiveness of Integrity Pact by monitoring public procurement of IP
signatories Public Sector Undertakings (PSUs) and other organizations.
• Address complaints received from IP stakeholders
• Review meeting with stakeholders
• Conduct an evaluation study to
assess presence of cartels and collusive corruption in Coal Oil
and Gas sector.
• During phase II we have received petition
/complaints relating to
NALCO, OPGC, NABARD,
DVC, THDCIL, etc from bidders/vigilance
officers/whistleblowers/ot
hers, after due diligence
complaints were forwarded to CVC and matter was
pursued by TII, the
complaints have been registered with CVC and
enquiry is going on in these
cases, progress can be
monitored on CVC website.
• IP cell held Review Meetings along with
representatives from PAC
Shri Srikanth and CUTS Shri
Madhusudan with Mr. Sunil Kaul, General Manager
(C&P), Engineers India
Limited; Mr. Parvez Hayat, CVO, Power Grid
Corporation of India; Shri
Selva Kumar, CVO, TCIL;
Mrs. Upma Srivastav, CVO, AAI; and Mr. D. Satija, Nodal
officer, ONGC.
IP Cell has framed the
questionnaire. It has conducted a
Round Table discussion on “The
presence of cartels and collusive corruption in Indian Industries”
and has received inputs from
various Stakeholders. The 9 case studies have been
complied
• C=fully completed
• C=fully completed
• C=fully completed
21
Objective – 3: Fine tuning of IP program, in order to achieve desired results as being highlighted
in the in the assessment report published after phase I .
The activities have been guided by the
observations and findings of Assessment
survey done in Phase I.
GENERAL OBSERVATIONS AND
SUGGESTIONS
General:
1) Sub-contractor must be a part of IP
process and program
2) In case of any default in various
provisions of IP including bribery by
sub-contractor, the contractor has to
be held responsible and accountable.
3) Every IP compliant PSU should also
sign IP document of Principal while
participating in bidding process.
4) There are various instances, where
bribes are routed through sub-
contractors, big bidder companies,
including MNCs.
5) No cases of Bribery have been
reported.
6) Almost all respondents feel that there
is a need of IP like tool in India, and
this tool is to be further fine tuned by
taking feedback from them.
7) Almost all respondents feel satisfied
with role played by CVC and TII. Major
chunk of the bidders feel that TII has
to be more proactive in terms of
advocacy of IP and complaint
redressal.
8) Almost all PSUs feel that they are not
All the TII activities in
phase II has been guided in
keeping findings of phase 1
• C=fully
completed
22
overburdened with expenses on IEMs.
9) No PSU and CVO feels that IEM(s) is/
are duplicating the work of vigilance
department.
10) Some PSUs are changing
nomenclature of External
independent Monitor for Independent
External Monitor (IEM), TII suggest a
common nomenclature of
Independent External Monitor should
be used by all.
11) Interactive meetings with IEMs
should be conducted more frequently
and at regular intervals for speedier
review of cases
PSUs:
Minutes of IEM-Management meeting,
annual report submitted by IEMs,
action taken report on complaints be
uploaded on the PSUs website.
CVCs:
Since maximum IEMs are retired
bureaucrats, there is a need to
diversify them among persons of
impeccable integrity and having
domain knowledge. They may be from
private sector, academics, NGOs,
Media, PSUs etc.
IEM(s):
IEM must submit annual report
pertaining to implementation of IP to
the concerned CMD, with a copy to
CVC and TII.
Private Sector:
• Private sector is no more
23
victim of corruption. Instead
they are instrumental and
hand-in-gloves with public
officers.
• Bribery among officials of
private firms is rampant.
They pay bribes to others to
get deals successfully done.
• Government must bring a
strong deterrent tool to curb
corruption in private sector.
Multinational and World Bank:
• A few PSUs have reported
that World Bank doesn’t
allow its funded project to be
a part of IP program. TII and
TI-S can take up this matter
with WB Officials.
TI India:
• List of all bidding companies
which are not signing IP,
must be displayed on
concerned PSUs’ and TII’s
website. In case of a foreign
multinational, TII may raise
and pursue this matter with
their counterparts located in
the countries concerned.
24
Annex 3: Planned and Actual Outputs
Outputs Planned
(Please reproduce what was in the
Approved Proposal).
Actual Project Outputs
Status of completion3
(Description of any
major change in
the outputs with
explanation as needed.)
• Quarterly newsletter.
• Manual on Examination of
Public Procurement
Process.
• Quarterly report on
progress of the project.
• Quarterly newsletters containing
highlights of all events, meetings,
complains handled, queries asked,
and major activity have been
prepared for each of four quarters of
the session.
• With technical inputs from Shri S. Z.
S. Tabish engineer from CPWD and
Shri Jitendra Kohli, Managing
Director, Electronic Tender we have
prepared a manual as a guide to help
Independent External monitors and
other stakeholders in public
procurement process, and also to
identify red flags in procurement. We
have received sponsorship for the
manual from ONGC, THDC, and SCI.
• Progress report has been shared with
all stakeholders .
• C=fully completed
• C=fully completed
• C=fully completed
3 C= fully completed, NC = very limited or no completion, D= Deferred to Phase 2, IP=In progress.
25
• Survey on "Presence of Cartels in Indian business
environment".
• Survey has been done selected case
studies have been compiled and
submitted to TII Board for
publication
• C=fully completed
26
Annex 4: Project Outcomes/Impact
Project Impact
Indicators
Baseline Value
End of Phase I
End of project Value Sources and evidence to
verify the results
• Level of satisfaction of
different
stakeholders.
• Findings from
Survey on
"Presence of
Cartels and
collusion in
Indian business
environment".
• 87% of the
respondent
from PSUs are
satisfied with
role played by
the TII.
• 84% of the
CVOs from IP
complaint
PSUs are
satisfied with
the role played
by TII.
• Can’t be assigned as no
such evaluation/stu
dy has been
carried out before the
present study.
As we have not done any
survey so we don’t have
any quantifiable data as
was there in phase I ,
but qualitative feedback
shows that level of
satisfaction is the same
• IP Cell has
conducted a Round
Table discussion on
“The presence of
cartels and
collusive corruption
in Indian
Industries”
• We have received
inputs from
various Stakeholder
s.
• Selected cases have
been compiled
• Feedback form filled by the officials of the PSUs ,
CVO and Bidders .
Survey documents on the study
on Cartelization and collusion
27
Improvement in India’s ranking
according
Corruption Perception
Index(CPI)
CPI rank of India in
2011 95th .
• CPI score of
India in 2012 is
36 (out of 100)
and rank is - 94th
Corruption Perception Report
Released by Transparency
International .
Number of MoU
signed between
PSU
(organization) and
TII.
• Increase
the domain
knowledge
of the
Independe
nt External
Monitors
(IEM) and
their
capacity to
identify red
flags within
the
tendering
process.
• 44 PSUs have
signed MoU
with TII.
• Can’t be
assigned as
no such
evaluation/st
udy has been
carried out
before the
present
study.
• One more PSU
THDC India Ltd
have signed MoU
, so total number
has increased to
45.
• It was difficult to
measure how their
presence in our
meeting has added
or enriched their
knowledge base , but
still there are
instance like in OIL,
GAIL. India , where
monitors have
acknowledged the
assistance of TII in
resolving issues
related to
procurement
• Copy of the MoU
• Participants list of
the meetings,
workshop.
• E mail from the
monitor.
28
• Satisfaction
of
aggrieved
party.
• Measure
the
effectivene
ss of the IP
program
implement
ed within
individual
IP principal
stakeholde
rs
• Can’t be
assigned as
no such
record has
been
maintained
before phase
I.
• Can’t be
assigned as
no such
evaluation/st
udy has been
carried out
before the
present
study.
process.
A majority of the
parties who had
approached TII
in relation to
implementation
of IP in the PSUs
were satisfied
with role of TII.
• There are PSUs
where IP has
been properly
implemented at
same time there
are PSUs where
implementation
of IP is below
our expectation.
Communication from the
Parties.
Feedback from stakeholders
Name of the CSO: Transparency International India
USD INR
Total Budget of the Project $ 33,409.00 14,70,000.00
Total Expenses incurred $ 35,492.00 15,61,631.00
PTF Contribution to the Project $ 25,000.00 11,00,000
PTF Grant received so far $ 22,500.00 9,90,000
PT Grant Spent so far $ 25,000.00 11,00,000
Last tranche amount receivable from
PTF
$ 2,500 1,10,000
29
Budget Category* Budget (INR)**
Actual
Expenses
(INR)
Sources of Funding Used
PTF Organisation
(currency) (USD) (INR)
A Humar Resource Cost
1 Project Director 4,80,000 5,34,120 376675 $ 8,561.00 1,57,445
2 Regional Coordinator 1,80,000 2,02,800 80,400 $ 1,827.00 1,22,400
3 Stipend to members
of Coordination
Committee & Interns. 50,000
93,633 18,633 $ 423.00 75,000
Total A 7,10,000 8,30,553 4,75,708 $ 10811.54 3,54,845
B Office Expenses
1 Internet &
Communication, and
other miscellaneous
expenses including
administrative
expenses by
collaborating civil
society organisations
at State Level 1,60,000
2,25,668
1,30,268
$ 2,961
95,400
Total B 1,60,000 2,25,668 1.30,268 $ 2961 95,400
C Project Activities
1 Expenses for three
regional workshops
for capacity building
of stakeholders,
including expenses
on documentations
1,10,000.00
50,128
19,628
$ 446
30,500
2 Expenses on
orientation session
for Monitors,
Vigilance Officers
including civil society
organisations
90,000.00
90,000
67,500
$ 1,534
22,500
3 Field Visits to Public
Sector Undertakings
(PSUs)
1,00,000.00
1,31,560
76,160
$ 1,731
55,400
4 Survey for Impact
Assessment including
collection of data
2,00,000.00
1,76,377
1,26,377
$ 2,872
50,000
5 Printing of
Newsletters, reports
1,00,000.00
57,345
57,345
30
and distribution,
stipend to the editor
Total C 6,00,000 5,05,410 2,89,665 $ 6583 2,15,745
D Workshop on
Transparency in
Defiance
Procurement held on
15 May 2013
2,06,000 $4682
Total D 2,06,000 $4682
Total (A+B+C+D) 14,70,000 15,61,631 11,01,641 $ 25037 6,65,990
* These categories are reproduced from the original project budget.
** Use data from the original budget.
# 1 USD = INR 44 ( as per the conversion rates used at the time of Project Approval and as per the agreement
signed)