+ All Categories
Home > Documents > Project Plan Management

Project Plan Management

Date post: 18-Jan-2016
Category:
Upload: don
View: 34 times
Download: 0 times
Share this document with a friend
Description:
Project Plan Management. What the Owner/Operator Needs to Know. FVOA Mini Conference August 2011. Presented by: Robyn Doescher & John D. Szwedo Baxter & Woodman, Inc. Consulting Engineers www.baxterwoodman.com. General Overview. Basic Introduction to a Construction Project. - PowerPoint PPT Presentation
Popular Tags:
36
Project Plan Management Project Plan Management What the Owner/Operator Needs to Know
Transcript
Page 1: Project Plan Management

Project Plan ManagementProject Plan Management

What the Owner/Operator Needs to Know

Page 2: Project Plan Management

FVOA Mini Conference FVOA Mini Conference August 2011August 2011

Presented by:

Robyn Doescher & John D. SzwedoBaxter & Woodman, Inc.

Consulting Engineers

www.baxterwoodman.com

Page 3: Project Plan Management

General OverviewGeneral OverviewBasic Introduction to a Construction Project

• Common terminology

• Owner and Engineer Relationship

• Project Completion

Page 4: Project Plan Management

Topics CoveredTopics Covered#1 – Common Terminology:• Project Manual

• Plans• Specs• Shop Drawings• RFI• Change Orders• Substantial/Final

Completion• As Built Plans• Bonds

Page 5: Project Plan Management

Topics Covered Topics Covered #2 - What the Owner should expect from the Engineer prior to and during the project:

• Involvement during the design phase

• Involvement during equipment selection

• Involvement during SCADA design

Page 6: Project Plan Management

Topics CoveredTopics Covered#3 - What happens if the Contractor doesn’t finish the job?

Page 7: Project Plan Management

Topic #1- Common Topic #1- Common TerminologyTerminology

Project Manual

• Description of the Project• Includes Legal Docs and General Req.• Broken up into Divisions• Includes Spec Sections

Page 8: Project Plan Management

PlansPlansPlans -

• Plans are the engineer’s vision, or blueprint, of what is to be.

• Plans provide a wealth of information.

• Piping plans, elevations, hydraulic profiles, flow diagram, etc.

Page 9: Project Plan Management

Plans Plans (continued)(continued)

• Flow Diagram – Details where process flows go

• Piping Plan – Shows piping runs

• Legend – Tells what symbols and abbreviations stand for

• Hydraulic Profile – Shows elevations starting at beginning of facility

• Details – Gives specifics to items such as manholes, outfall structures, wall sleeves, etc.

Page 10: Project Plan Management

SpecsSpecs

• Spec Sections in Project Manual provide detail of equipment specified

• May not specify manufacturer, but provides enough detail to eliminate non-worthy equipment

• Also details things such as door/hardware, masonry, pipe materials, contractor guidelines, etc.

Page 11: Project Plan Management

Shop DrawingsShop DrawingsProvide detailed information about particular piece of equipment

• Submitted to engineer by equipment supplier for approval prior to purchase of equipment

• Model #, features, drawings, ancillary equipment, controls and spare parts

• Example- Blower + associated valves, filters and motor

Page 12: Project Plan Management

RFIRFIRFI = Request for Interpretation

Sometimes called “Request for Information”

• Contractor is requesting clarification on a matter, such as piping conflicts, material use, etc.

Page 13: Project Plan Management

Change OrderChange Order• A change in work due to unforeseen

circumstances. It might include:

- A time extension- Piping modifications- Equipment changes

• Request for Interpretation (RFI) usually precedes the Change Order

• Change Orders must be approved by Engineer/Owner. Note: NOT BY OPERATOR!

Page 14: Project Plan Management

Substantial/Final Substantial/Final Completion Completion

• Substantial CompletionAllows for start up of facility, with major work being completed. Facility must run effectively and meet all permit limits.

Develop Punch list

• Final CompletionAll items have been completed, including punch list (laundry list) items. BE PICKY!

Page 15: Project Plan Management

As Built PlansAs Built PlansAlso known as “As Builts”

• Revised plans/drawings due to changes in the field

• Example: Change in piping due to unforeseen circumstances

• Are the latest and most accurate drawings

Page 16: Project Plan Management

As Built PlansAs Built Plans((continuecontinuedd) )

What happens next?

• Marked up in field, dated and signed• Original plan/drawing marked up

OR• Marked up in field• Redrawn, with original plan/drawing left

in, but noted

Page 17: Project Plan Management

BondsBonds

• Bid Bond

• Performance Bond

• Payment Bond

Page 18: Project Plan Management

Bid BondBid Bond

• Required of a contractor submitting lowest bid

• Ensures contractor is serious about his bid

• If contractor negates, penalties can be assessed

Page 19: Project Plan Management

Performance BondPerformance Bond

• Replaces Bid Bond

• Ensures work is completed as specified

• Guarantees client will be compensated for any monetary loss up to the amount of the bond

Page 20: Project Plan Management

Payment BondPayment Bond

• Guarantees payment to laborers, suppliers and subcontractors in the event of the contractor defaulting

• Usually issued with the Performance Bond

Page 21: Project Plan Management

Topic #2 – Expectations During Topic #2 – Expectations During ProjectProject

Involvement during design phase

• Owner involvement when developing vision

• Owner takes part in design meetings

• Engineer keeps owner

involved throughout

Page 22: Project Plan Management

Owner InvolvementOwner Involvement• Owner/Operator need to contribute• Should present/discuss

Past operational issuesProblems meeting permit limitsEquipment performance issuesDevelop a “Wish List” for considerationDiscuss issues with staff

Page 23: Project Plan Management

Equipment SelectionEquipment SelectionOwner should have input, based on:

• Past experiences

• Current needs/problems

• Preference

Page 24: Project Plan Management

Flow SheetsFlow SheetsPlan sheets outlining each step of process

• Work with Engineer on Flow Sheets• Discuss each process, and what you

expect it to do• Discuss how it can be automated

Page 25: Project Plan Management

SCADA DesignSCADA Design• What are you trying to accomplish?

Monitoring vs. complete control

• Be creative when controlling equipment

• Reporting

• Alarms- Who?

- What?- When?

Page 26: Project Plan Management

Advantages of SCADAAdvantages of SCADA

Better control of equipmentBetter control of process

Reduced labor costs (Manpower)Reduced operational costs (Electrical)Provides historical data (Trending)

Page 27: Project Plan Management

SCADA DesignSCADA DesignExamples of screens:

• General OverviewProvides a “quick glance” status report

• MaintenanceNotification when maintenance is due

• TrendingProvides history of events

Helps with troubleshooting

Note: Work with designer to design your screens

Page 28: Project Plan Management

General OverviewGeneral Overview

Page 29: Project Plan Management

General OverviewGeneral Overview

Page 30: Project Plan Management

General OverviewGeneral Overview

Page 31: Project Plan Management

MaintenanceMaintenance

Page 32: Project Plan Management

TrendingTrending

Page 33: Project Plan Management

ReportingReporting

Page 34: Project Plan Management

Topic #3 - What Happens if the Topic #3 - What Happens if the Contractor Doesn’t Finish?Contractor Doesn’t Finish?

• Performance Bond

• Engineer/Owner informs contractor that Bond Company will be notified

• 30-day period to respond

• If no action, Bond Company responds

• Contractor’s rating is affected

Page 35: Project Plan Management

SummarySummary

• Owner involvement critical

• Engineer and Owner need to work together

• Engineer and Owner need to have same long range goals

Page 36: Project Plan Management

Questions?Questions?

John D. [email protected] • 847.223.5088 •

www.baxterwoodman.com


Recommended