Project Planning. Project. Group of Activities Beginning, Middle, End Well-Defined End Result. Projects Example. Examples of Projects. Construction Research and Development Design of New Product or Process Space Shuttle Wedding Can You Think of Projects? Can You Think of Non-Projects?. - PowerPoint PPT Presentation
Popular Tags:
19
1 Project Planning
Transcript

1

Project Planning

2

Project

Group of Activities

Beginning, Middle, End

Well-Defined End Result

3

Projects Example

4

Examples of Projects

Construction Research and Development Design of New Product or Process Space Shuttle Wedding Can You Think of Projects? Can You Think of Non-Projects?

5

Project Life Cycle

6

Project Layout

Layout is Oriented Around Project

7

Growth in Project Management

Decline of Repetitive Manufacturing in U.S. Growth of U.S. Service & Project Oriented Industries Lack of Foreign Competition in Defense, Construction Need to Rebuild U.S. Infrastructure Greater Demand for New Product Introduction Proliferation of Project Management Software

(Over 100 Kinds - $20 to $8000) Project Management Institute (PMI)

8

Growth in Project Management

Growing Demand for Complex Goods, Services

And Exponential Explosion of Human Knowledge

Results in Larger and Larger Projects.

This Creates Need for Sophisticated Management System

9

Project Planning Consists of:

Purpose Objectives Overview and General Approach Schedules (PERT/CPM) Resources Personnel Risk Management Plans Evaluation and Control (Feedback)

10

Planning and Managing Risk

Risk Management Planning – Form Team Risk Identification – Delphi Method Qualitative Risk Analysis – Subjective Likelihood Quantitative Risk Analysis – Use Probabilities Risk Response Planning – Avoid, Mitigate,

Accept, Control Risk Monitoring and Control Risk Management Register

11

Initial Project Planning:Draw System Boundaries

A System Consists of the Following: Mission and Goals

- Objectives

- Performance

- Effectiveness

- Cost Environment Resources Subsystems

12

In Project Planning Activities Must be Identified

Activities are Groups of Work Elements or Tasks with:

Similar Technology & Groups of Personnel

Single Duration of Time (Activity Completion is Event)

Definite Beginning & End

13

List of Activities Can Be Developed with:

“Gozinto” Chart

Bill of Materials

Work Breakdown Structure (WBS) Basically a “Bill of Work Units”

14

Work Breakdown Structure (WBS)

15

WBS Information

For Each Work Element (Activity) We Can Record:

Work Statement (Input/Output) Vendors, Contacts, Subcontractors End Item Specifications Cost Accounting Numbers & Costs (ABC) Resource Needs Probability Personnel (Linear Responsibility Chart, Trend) Times (Scheduling, PERT/CPM, Gantt Charts) Sequence Requirements

16

Activity Analysis:Example One

Activity Description Follows Days

A Define Problem --- 3

B Lease Computer --- 5

C Obtain Data A, B 4

D Determine Alternatives A, B 1

E Feasible Alternatives D 1

F Evaluation & Modeling C, E 5

G Find Best Alternative F 1

H Implementation G 3

17

Activity Analysis:Example Two

Activity Description Follows Days

X --------------- --- 1

Y --------------- --- 2

Z --------------- --- 3

A --------------- X, Y 1

B --------------- X, Y, Z 2

Draw Activity-On-Node (AON or CPM) Diagram.

Draw Activity-On-Arrow (AOA or PERT) Diagram.

18

Activity Analysis:Example Three

Activity Description Follows

a Plan Survey ---b Hire Personnel ac Design Questionnaire a d Train Personnel b,ce Select Households cf Print Questionnaire cg Conduct Survey d,e,fh Analyze Results g

Draw Activity-On-Node (AON or CPM) Diagram.Draw Activity-On-Arrow (AOA or PERT) Diagram.