+ All Categories
Home > Documents > Project PV-GRID Barriers Recomendations

Project PV-GRID Barriers Recomendations

Date post: 15-Oct-2021
Category:
Upload: others
View: 3 times
Download: 0 times
Share this document with a friend
12
19/03/2014 1 Project PV-GRID B i d d ti 18/03/2014 Barriers and recommendations 1 Index 1. List of barriers 2. List of recommendations 2
Transcript

19/03/2014

1

Project PV-GRIDB i d d ti

18/03/2014

Barriers and recommendations

11

Index1. List of barriers

2. List of recommendations

2

19/03/2014

2

1

List of barriers

1

3

List of barriers

Rules forbidding RES energy curtailment except for security issues

Currently only an exception.

Curtailing small quantities of energy could increase significantly the hosting capacity of PV.

Analyze whether slightly increasing the conditions could be beneficial.

Compensate the PV agent for the curtailment.

419/03/2014 4

Source: http://www.louyeh.com

19/03/2014

3

Insufficient Self-consumption Framework

Necessity to be legislated.

Net meetering.

Legal uncertainties.

Direct or indirect incentives.

Review the tariffs.

519/03/2014 5

Source: www.iit.upcomillas.es

Insufficient DSO access to advanced PV Inverter Capabilities

Technically available.

DSO has no access.

Access to inverters and control over their capabilities should be granted to DSOs.

Boundary conditions.

619/03/2014 6

Source: http://www.freepatentsonline.com

19/03/2014

4

Insufficient Framework for Prosumer Storage Solutions

Fluctuations.

Natural technical solution.

Allowed and regulated.

Economic compensation.

719/03/2014 7

http://blog.carritus.com/2012/01/pilas-cuales-elegir/

Insufficient Framework for DSO Storage Solutions

DSOs compensation of the fluctuations.

Undbundling policies.

Impacts in the market.

How the DSOs can make use of this technology.

819/03/2014 8

Source: http://www.saftbatteries.com

19/03/2014

5

Insufficient Framework for Demand Response

Local network conditions.

Voluntary basis.

Possibility of contracting load reduction and load activation with the consumers.

Presently DSOs are not expected to exchange information with final customers.

Communication system.

S t t

919/03/2014 9

Smart meters

A detailed regulation.

Source: http://www.millennialliving.com

Incoherent Metering Framework

Foster a quicker implementation of some of the technical solutions.

Directive 2009/72/EC Target 80% for 2020 Directive 2009/72/EC. Target 80% for 2020 depending on a cost benefit analysis.

Required not only for consumers, but also for the photovoltaic installations

1019/03/2014 10

Source: http://www.cypresscreekestates.com

19/03/2014

6

Regulatory Frameworks that do not Incentivise “Smart Grid” Development

Communication infrastructures.

Favor technologies with high potential impact and good readiness which find regulatoryand good readiness, which find regulatory barriers.

DSO should be incentivized for using smart solutions instead of just conventional solutions.

A regulatory framework.

1119/03/2014 11

Source: http://www.myseek.org

2

List of recommendations

2

12

List of recommendations

19/03/2014

7

DSO investments recovery

1) Avoid that the DSO have an excessive delayPrevent at least a financial risk of DSO.

2) Ens re DSOs are rem nerated b the efficient in estments2) Ensure DSOs are remunerated by the efficient investments.

stria

gium

garia

Rep

ublic

ance

many

eece

taly

land

tugal

vackia

pain

eden

U.K.

1319/03/2014 13

Au

Belg

Bulg

Czech

R

Fra

Ger

Gre It

Po Por

Slov Sp Swe U

1 X X X X X X

2 X X X X ?

Grid Connection Charges

1) Clear methodology based on simple and transparent rules

2) Provide an indication of the connection cost in advance

Austria

Belgium

Bulgaria

chRepublic

France

Germ

any

Greece

Italy

Poland

Portugal

lovackia

Spain

Sweden

U.K.

1419/03/2014 14

A B B

Czec G G P S S

1 X X X X X X

2 X X X X X

19/03/2014

8

Rules Forbidding RES Energy Curtailment Except For Security Issues

1) Debates on whether the conditions should be slightly increased.

Conditions transparent and non-discriminatory.

Ensure an adequate compensationEnsure an adequate compensation.

lic

1519/03/2014 15

Austria

Belgium

Bulgaria

Czech Repub

France

Germany

Greece

Italy

Poland

Portugal

Slovackia

Spain

Sweden

U.K.

1 X X X \ X X X X X

Insufficient Self-consumption Framework

1) A legislation should rapidly be approved

2) Proper economic incentives should be introduced

3) The use-of-system tariffs should be reviewed.

4) It may further evaluated to introduce net-metering

Austria

Belgium

Bulgaria

zech Rep

ublic

France

Germany

Greece

Italy

Poland

Portugal

Slovackia

Spain

Swed

en

U.K.

1619/03/2014 16

C

1 X

2 X X X X X X X X X

3X X X X X X X X X X X X X X

4X X X X X X X X X X X

19/03/2014

9

Insufficient DSO access to advanced PV Inverter Capabilities

1) Provide DSOs the right to use or impose functions to PV inverters

Define boundary conditions.

An economic compensation for DG operators.

Avoid conflict of interests with the TSOs and energy providers.

2) Define the framework for advanced reactive power controls.

a m ia public

e ny e d al kia

n en

1719/03/2014 17

Austri

Belgium

Bulgar

Czech Rep

France

German

Greece

Italy

Poland

Portug

Slovac k

Spain

Swed

e

U.K.

1 X X X X X X X X

2X X X X X X X X

Insufficient Framework for Prosumer Storage Solutions

1) Prosumer storage solutions should be regulated and allowed.

Ensure not posing the system into a security problem or interfering with the metering.

2) Establish mechanisms for incentivising the storage solutions, when applied to reduce the peaks of PV installations.

ustria

lgium

lgaria

Republic

ance

rmany

eece

taly

oland

rtugal

vackia

pain

eden

U.K.

1819/03/2014 18

Au

Bel

Bul

Czech 

Fra

Ger Gr It

Po Por

Slov Sp Sw

U

1 X X X X X X X X

2X X X X X X X X X X X X X

19/03/2014

10

Insufficient Framework for DSO Storage Solutions

1) There should be a reflection on how to activate this potential;

Roles, rights and limitations must be clearly defined;stria

gium

garia

Republic

ance

many

eece

aly

and

tugal

ackia

ain

eden

.K.

1919/03/2014 19

Aus

Belg

Bulg

Czech R

Fra

Germ

Gre Ita

Pol

Port

Slov Sp Swe U

1 X X X X X X X X X X X X

Insufficient Framework for Demand Response

1) Technical features for Demand Response should be assessed. However, the main focus must be on the customers’ side

Establish a compensation scheme for users participating voluntarily.

2) DSOs should be allowed to manage load activation services2) DSOs should be allowed to manage load activation services

3) The communication between DSO and final customers, should be defined.

Austria

Belgium

Bulgaria

ech Rep

ublic

France

Germany

Greece

Italy

Poland

Portugal

Slovackia

Spain

Swed

en

U.K.

2019/03/2014 20

Cze

1 X X X X X X X X

2 X X X X X X X X X X X

3X X X X X X X X X X X

19/03/2014

11

Incoherent Metering Framework

1) It should be analysed whether also DG installations should also be equipped with these devices.

2) It should also be ensured that their potential is used.Austria

Belgium

Bulgaria

zech Rep

ublic

France

Germany

Greece

Italy

Poland

Portugal

Slovackia

Spain

Swed

en

U.K.

2119/03/2014 21

Cz

1 X X X X X X

2X X X X X X X X X X X X X X

Regulatory Frameworks that do not Incentivise “Smart Grid” Development

1) Adaptation of national regulatory frameworks to promote “Smart Grid” investments

A stable and transparent regulatory framework

Where necessary, explicit incentives should also be established:

To innovative projects in smart grids or generalized.

tria um

aria

epublic

nce

many

ece

ly nd

ugal

ckia

in den

K.

2219/03/2014 22

Aust

Belgi

Bulga

Czech Re

Fran

Germ

Gree

Ital

Pola

Portu

Slovac

Spa

Swed U.K

1 X X X X X X X X X X

19/03/2014

12

Regulatory Frameworks that do not Incentivise “Smart Grid” Development

2) DSOs and NRAs should evaluate the regular collection of measurement data in MV and LV networks, to decide on whether start increasing the monitoring in the medium voltage, and then change to low voltage grids, by making use of smart meter technologyby making use of smart meter technology.

3) DSOs and NRAs should evaluate the regular collection of measurement data in LV networks, to decide on whether start increasing the monitoring of the low voltage grids, by making use of smart meter technology.

blic

y a2319/03/2014 23

Austria

Belgium

Bulgaria

Czech Rep

u

France

Germany

Greece

Italy

Poland

Portugal

Slovackia

Spain

Swed

en

U.K.

2 X X X ? X X

3 X ? X X X ? X X

Thank you for your attention

Stelios Psomas

Disclaimer: The sole responsibility for the content of this presentation lies with the authors. It does not necessarily reflect the opinion of the European Union. Neither the EACI nor the European Commission are responsible for any use that may be made of the information 

i d h icontained therein.


Recommended