+ All Categories
Home > Documents > Project Schedule as of 03MAR2014 %28PDF Format%29 (2)

Project Schedule as of 03MAR2014 %28PDF Format%29 (2)

Date post: 13-May-2017
Category:
Upload: ismael-castro
View: 230 times
Download: 8 times
Share this document with a friend
15
Activity Name Start Finish OD RD InterGen Altamira Compression Station_MPR_February 03/01/13 A 08/05/14 523 159 Milestones 03/31/14 08/05/14 127 127 Project Management 03/31/14 08/05/14 127 127 Major Milestone 03/31/14 08/05/14 127 127 Major Milestone 03/31/14 08/05/14 127 127 Application for CRE Permit 03/31/14* 0 0 Initial Interconnection Completion (Contractual) 03/31/14* 0 0 Initial Interconnection Completion (Expected - Only 48" Pipeline(Red Line) Completion excl. F 05/19/14 0 0 > Initial Interconnection Completion (Expected - excl. East Side of Fence) 06/11/14 0 0 > Initial Interconnection Completion (Expected - incl. Fence Work) 07/15/14 0 0 Energizing 04/01/14 0 0 Mechanical Completion (for Compression Station) 05/31/14 0 0 Transfer Piping Work Finish 06/08/14 0 0 CRE Permit Approval 06/09/14 0 0 Gas Introduction to Compression Area - IIC(Only 48" Pipeline) + 45 days(Hot Tapping) 07/03/14 0 0 Substantial Completion (Contractual) 05/05/14* 0 0 Substantial Completion (Expected) 08/05/14 0 0 Construction 04/27/14 05/18/14 20 20 Mechanical 04/27/14 05/18/14 20 20 Compression Station (or Common) 05/11/14 05/18/14 6 6 Gas Compressor Installation Completion 05/11/14 0 0 Leak Test Start for Natural Gas Line (S-02~S-06) 05/18/14 0 0 Interconnection Zone 04/27/14 04/27/14 0 0 Pig Launcher & Receiver Installation Completion (Not yet decided) 04/27/14 0 0 Procurement 03/01/13 A 04/14/14 410 46 Compression Station (or Common) 03/01/13 A 04/14/14 410 46 Instrument 03/01/13 A 04/14/14 410 46 Equipment 03/01/13 A 04/14/14 410 46 Metering System with Alarm System 03/01/13 A 04/14/14 410 46 Metering System - Manufacturing & Inspection 03/01/13 A 03/10/14 229 11 Metering System - Transportation 03/11/14 04/14/14 35 35 ESD Valves (36") - New 03/01/14 A 03/26/14 14 26 ESD Valves - Transportation 03/01/14 A 03/26/14 14 26 Construction 08/23/13 A 08/05/14 323 159 Interconnection Zone 12/26/13 A 07/15/14 194 138 New Schedule with New Valves 12/26/13 A 07/15/14 194 138 Engineering 01/03/14 A 03/06/14 63 7 Civil DWG Issue (for Excavation) 01/03/14 A 03/06/14 7 7 Piping DWG Issue (Plot Plan, Piping Arrangement, ISO) 01/03/14 A 03/04/14 14 5 Design Approval (Expected) 03/06/14* 0 0 Procurement 02/09/14 A 03/25/14 44 26 New G/H Ball Valve (24") - Transportation 02/09/14 A 03/10/14 25 11 New G/H Ball Valve (48") - Transportation 02/28/14 A 03/25/14 26 26 48" By-pass Line 01/10/14 A 04/26/14 107 58 Existing Pipe Hot Cutting - 5 Points (2 for Elbows, 3 for Pipes) 03/01/14 A 03/05/14 5 3 Spool Transportation From Area 3 to LGCS Shop 03/06/14 03/06/14 1 1 Hot Cutting at the Shop - 4 Points 03/07/14 03/08/14 2 2 Shop Welding - 4 Points 03/09/14 03/14/14 6 6 Re-setting Existing Line (North) 01/10/14 A 03/13/14 6 14 Field Cold Cutting - 3 Points (2 for Elbows, 1 for 48x48 Tee) 03/14/14 03/18/14 5 5 Pipe Cold Cutting 1 Point (48" Header Line - Fitting) 03/14/14 03/15/14 2 2 48" Header Line Transportation to LGCS Shop 03/16/14 03/16/14 1 1 17 18 19 20 21 22 23 24 Mar Apr May Jun Jul Aug Sep Oct 2014 Application for CRE Permit Initial Interconnection Completion (Contractual) Initial Interconnection Completion (Expected - Only 48" Pipeline(Red Line) Completion excl. Fence Work > Initial Interconnection Completion (Expected - excl. East Side of Fence) > Initial Interconnection Completion (Expected - incl. Fence W Energizing Mechanical Completion (for Compression Station) Transfer Piping Work Finish CRE Permit Approval Gas Introduction to Compression Area - IIC(Only 48" Pipeline) + 45 days Substantial Completion (Contractual) Substantial Completion (Expected) Gas Compressor Installation Completion Leak Test Start for Natural Gas Line (S-02~S-06) Pig Launcher & Receiver Installation Completion (Not yet decided) Metering System - Manufacturing & Inspection, Metering System - Manufacturing & Inspection Metering System - Transportation ESD Valves - Transportation, ESD Valves - Transportation Civil DWG Issue (for Excavation), Civil DWG Issue (for Excavation) Piping DWG Issue (Plot Plan, Piping Arrangement, ISO), Piping DWG Issue (Plot Plan, Piping Arrangement, ISO) Design Approval (Expected) New G/H Ball Valve (24") - Transportation, New G/H Ball Valve (24") - Transportation New G/H Ball Valve (48") - Transportation, New G/H Ball Valve (48") - Transportation Existing Pipe Hot Cutting - 5 Points (2 for Elbows, 3 for Pipes), Existing Pipe Hot Cutting - 5 Points (2 for Elbows, 3 for Pipes) Spool Transportation From Area 3 to LGCS Shop Hot Cutting at the Shop - 4 Points Shop Welding - 4 Points Re-setting Existing Line (North), Re-setting Existing Line (North) Field Cold Cutting - 3 Points (2 for Elbows, 1 for 48x48 Tee) Pipe Cold Cutting 1 Point (48" Header Line - Fitting) 48" Header Line Transportation to LGCS Shop Actual Work Remaining Work Critical Remaining Work Milestone Project Overall Schedule Page 1 of 15 Date Revision Checked Approved 03/03/14 ISSUED FOR MONTHLY PROGRESS REPORT H.S. LEE J.L. NABORS
Transcript
Page 1: Project Schedule as of 03MAR2014 %28PDF Format%29 (2)

Activity Name Start Finish OD RD

InterGen Altamira Compression Station_MPR_February 03/01/13 A 08/05/14 523 159

Milestones 03/31/14 08/05/14 127 127

Project Management 03/31/14 08/05/14 127 127

Major Milestone 03/31/14 08/05/14 127 127Major Milestone 03/31/14 08/05/14 127 127Application for CRE Permit 03/31/14* 0 0Initial Interconnection Completion (Contractual) 03/31/14* 0 0Initial Interconnection Completion (Expected - Only 48" Pipeline(Red Line) Completion excl. F 05/19/14 0 0└> Initial Interconnection Completion (Expected - excl. East Side of Fence) 06/11/14 0 0└> Initial Interconnection Completion (Expected - incl. Fence Work) 07/15/14 0 0Energizing 04/01/14 0 0Mechanical Completion (for Compression Station) 05/31/14 0 0Transfer Piping Work Finish 06/08/14 0 0CRE Permit Approval 06/09/14 0 0Gas Introduction to Compression Area - IIC(Only 48" Pipeline) + 45 days(Hot Tapping) 07/03/14 0 0Substantial Completion (Contractual) 05/05/14* 0 0Substantial Completion (Expected) 08/05/14 0 0

Construction 04/27/14 05/18/14 20 20

Mechanical 04/27/14 05/18/14 20 20Compression Station (or Common) 05/11/14 05/18/14 6 6Gas Compressor Installation Completion 05/11/14 0 0Leak Test Start for Natural Gas Line (S-02~S-06) 05/18/14 0 0

Interconnection Zone 04/27/14 04/27/14 0 0Pig Launcher & Receiver Installation Completion (Not yet decided) 04/27/14 0 0

Procurement 03/01/13 A 04/14/14 410 46

Compression Station (or Common) 03/01/13 A 04/14/14 410 46

Instrument 03/01/13 A 04/14/14 410 46Equipment 03/01/13 A 04/14/14 410 46Metering System with Alarm System 03/01/13 A 04/14/14 410 46Metering System - Manufacturing & Inspection 03/01/13 A 03/10/14 229 11Metering System - Transportation 03/11/14 04/14/14 35 35

ESD Valves (36") - New 03/01/14 A 03/26/14 14 26ESD Valves - Transportation 03/01/14 A 03/26/14 14 26

Construction 08/23/13 A 08/05/14 323 159

Interconnection Zone 12/26/13 A 07/15/14 194 138

New Schedule with New Valves 12/26/13 A 07/15/14 194 138Engineering 01/03/14 A 03/06/14 63 7Civil DWG Issue (for Excavation) 01/03/14 A 03/06/14 7 7Piping DWG Issue (Plot Plan, Piping Arrangement, ISO) 01/03/14 A 03/04/14 14 5Design Approval (Expected) 03/06/14* 0 0

Procurement 02/09/14 A 03/25/14 44 26New G/H Ball Valve (24") - Transportation 02/09/14 A 03/10/14 25 11New G/H Ball Valve (48") - Transportation 02/28/14 A 03/25/14 26 26

48" By-pass Line 01/10/14 A 04/26/14 107 58Existing Pipe Hot Cutting - 5 Points (2 for Elbows, 3 for Pipes) 03/01/14 A 03/05/14 5 3Spool Transportation From Area 3 to LGCS Shop 03/06/14 03/06/14 1 1Hot Cutting at the Shop - 4 Points 03/07/14 03/08/14 2 2Shop Welding - 4 Points 03/09/14 03/14/14 6 6Re-setting Existing Line (North) 01/10/14 A 03/13/14 6 14Field Cold Cutt ing - 3 Points (2 for Elbows, 1 for 48x48 Tee) 03/14/14 03/18/14 5 5Pipe Cold Cutting 1 Point (48" Header Line - Fitting) 03/14/14 03/15/14 2 248" Header Line Transportation to LGCS Shop 03/16/14 03/16/14 1 1

17 18 19 20 21 22 23 24Mar Apr May Jun Jul Aug Sep Oct

2014

Application for CRE PermitInitial Interconnection Completion (Contractual)

Initial Interconnection Completion (Expected - Only 48" Pipeline(Red Line) Completion excl. Fence Work└> Initial Interconnection Completion (Expected - excl. East Side of Fence)

└> Initial Interconnection Completion (Expected - incl. Fence WEnergizing

Mechanical Completion (for Compression Station)Transfer Piping Work FinishCRE Permit Approval

Gas Introduction to Compression Area - IIC(Only 48" Pipeline) + 45 daysSubstantial Completion (Contractual)

Substantial Completion (Expected)

Gas Compressor Installation CompletionLeak Test Start for Natural Gas Line (S-02~S-06)

Pig Launcher & Receiver Installation Completion (Not yet decided)

Metering System - Manufacturing & Inspection, Metering System - Manufacturing & InspectionMetering System - Transportation

ESD Valves - Transportation, ESD Valves - Transportation

Civil DWG Issue (for Excavation), Civil DWG Issue (for Excavation)Piping DWG Issue (Plot Plan, Piping Arrangement, ISO), Piping DWG Issue (Plot Plan, Piping Arrangement, ISO)

Design Approval (Expected)

New G/H Ball Valve (24") - Transportation, New G/H Ball Valve (24") - TransportationNew G/H Ball Valve (48") - Transportation, New G/H Ball Valve (48") - Transportation

Existing Pipe Hot Cutting - 5 Points (2 for Elbows, 3 for Pipes), Existing Pipe Hot Cutting - 5 Points (2 for Elbows, 3 for Pipes)Spool Transportation From Area 3 to LGCS Shop

Hot Cutting at the Shop - 4 PointsShop Welding - 4 PointsRe-setting Existing Line (North), Re-setting Existing Line (North)

Field Cold Cutt ing - 3 Points (2 for Elbows, 1 for 48x48 Tee)Pipe Cold Cutting 1 Point (48" Header Line - Fitting)48" Header Line Transportation to LGCS Shop

Actual WorkRemaining WorkCritical Remaining Work

Milestone Project Overall Schedule

Page 1 of 15

Date Revision Checked Approved

03/03/14 ISSUED FOR MONTHLY PROGRESS REPORT H.S. LEE J.L. NABORS

Page 2: Project Schedule as of 03MAR2014 %28PDF Format%29 (2)

Activity Name Start Finish OD RD

48" Header Line Cold Cutting and Re-welding 03/17/14 03/26/14 10 10Short Pipe Cutting & Counter Flange Spool Re-welding at XV-1003 03/19/14 03/24/14 6 648" Header Line Re-installation (Field) 03/27/14 03/30/14 4 4Spool Transportation from LGCS Shop to Area 3 03/15/14 03/17/14 3 3Excavation and Sand Bedding (48" Bypass Line) 03/16/14 03/18/14 3 3

Field Welding - 9 Points (2 for Elbow-Pipe, 4 for Pipe-Pipe, Incl. 160mm Short Pipes) 03/19/14 04/07/14 20 20RAM-100 Coating & Holiday Test 04/08/14 04/11/14 4 448" By-pass Backfilling & Compaction 04/12/14* 04/26/14 15 15

Anchor Block Work for 48" Line (North & South) 04/29/14 05/19/14 21 21Concrete Pouring for Anchor Block Work for 48" Line 04/29/14 05/01/14 3 3Form Removal for Anchor Block Work for 48" Line 05/08/14 05/09/14 2 2Backfilling & Compaction for Anchor Block Work for 48" Line 05/10/14 05/19/14 10 10

Interconnection 36" & 24" Piping Work 02/26/14 A 06/18/14 113 111Pig & Valve Foundation Removal (48", 36" and 24") 02/26/14 A 03/06/14 5 7Pig & Valve Foundation Work (48", 36" and 24") 03/07/14 03/26/14 20 20[Additional Purchasing] 24" Elbow 4EA and 36" Elbow 1EA - On-site 03/31/14* 0 0Excavation for 36" & 24" Line 04/24/14 05/03/14 10 10Sand Bedding & Compaction for 36" & 24" Line 05/04/14 05/06/14 3 3Pipe Cold Cutting, Fit-up, Welding and Re-welding (36" Line) 04/24/14 05/28/14 35 35Pipe Cold Cutting, Fit-up, Welding and Re-welding (24" Line) 04/24/14 05/28/14 35 35NDE for 36" & 24" Line 05/05/14 05/29/14 25 25RAM-100 Coating & Holiday Test 05/30/14 06/05/14 7 736" & 24" Line Backfilling & Compaction 06/09/14 06/18/14 10 10Painting for A/G 36" & 24" Piping 06/09/14 06/13/14 5 5

Actuator Installation 03/07/14 03/29/14 23 23Valve Unloading (24" Valves) 03/11/14 03/11/14 1 1Valve Unloading (48" Valves) 03/26/14 03/26/14 1 1Actuator Installation (48", XV-1001) 03/27/14 03/27/14 1 1Actuator Installation (48", XV-1002) 03/28/14 03/28/14 1 1Actuator Installation (48", XV-1003) 03/29/14 03/29/14 1 1Actuator Installation (24", XV-1006) 03/12/14 03/12/14 1 1Actuator Installation (24", XV-1007) 03/13/14 03/13/14 1 1Actuator Installation (24", XV-1008) 03/14/14 03/14/14 1 1Actuator Installation (24", XV-1009) 03/15/14 03/15/14 1 1Actuator Installation (24", XV-1010) 03/16/14 03/16/14 1 1Actuator Installation (36", XV-1004) 03/07/14 03/07/14 1 1Actuator Installation (36", XV-1005) 03/08/14 03/08/14 1 1

Valve Installation 03/31/14 06/03/14 65 65Valve Installation (48", XV-1001) 04/02/14 04/05/14 4 4Valve Installation (48", XV-1002) 04/03/14 04/06/14 4 4Valve Installation (48", XV-1003) 04/04/14 04/07/14 4 4Valve Installation (24", XV-1006, 48" Line Header) 03/31/14 04/01/14 2 2Valve Installation (24", XV-1007, 48" Line Header) 04/02/14 04/03/14 2 2Valve Installation (24", XV-1008) 05/29/14 05/30/14 2 2Valve Installation (24", XV-1009) 05/31/14 06/01/14 2 2Valve Installation (24", XV-1010) 06/02/14 06/03/14 2 2Valve Installation (36", XV-1004, 48" Line Header) 03/31/14 04/02/14 3 3Valve Installation (36", XV-1005, 48" Line Header) 04/03/14 04/05/14 3 3

Hydrotest for 48" Line 04/08/14 04/20/14 13 13Water Filling 04/08/14 04/14/14 7 7Holding Time (8 Hrs) 04/15/14 04/15/14 1 1Water Draining 04/16/14 04/20/14 5 5

Pig Launcher & Receiver (Not Yet Decided) 12/26/13 A 04/27/14 95 59PO for Repair Work of Pig Launcher & Receiver 12/26/13 A 03/18/14 21 19

17 18 19 20 21 22 23 24Mar Apr May Jun Jul Aug Sep Oct

2014

48" Header Line Cold Cutting and Re-weldingShort Pipe Cutting & Counter Flange Spool Re-welding at XV-1003

48" Header Line Re-installation (Field)Spool Transportation from LGCS Shop to Area 3Excavation and Sand Bedding (48" Bypass Line)

Field Welding - 9 Points (2 for Elbow-Pipe, 4 for Pipe-Pipe, Incl. 160mm Short Pipes)RAM-100 Coating & Holiday Test

48" By-pass Backfilling & Compaction

Concrete Pouring for Anchor Block Work for 48" LineForm Removal for Anchor Block Work for 48" Line

Backfilling & Compaction for Anchor Block Work for 48" Line

Pig & Valve Foundation Removal (48", 36" and 24"), Pig & Valve Foundation Removal (48", 36" and 24")Pig & Valve Foundation Work (48", 36" and 24")

[Additional Purchasing] 24" Elbow 4EA and 36" Elbow 1EA - On-siteExcavation for 36" & 24" Line

Sand Bedding & Compaction for 36" & 24" LinePipe Cold Cutting, Fit-up, Welding and Re-welding (36" Line)Pipe Cold Cutting, Fit-up, Welding and Re-welding (24" Line)NDE for 36" & 24" Line

RAM-100 Coating & Holiday Test36" & 24" Line Backfilling & Compaction

Painting for A/G 36" & 24" Piping

Valve Unloading (24" Valves)Valve Unloading (48" Valves)Actuator Installation (48", XV-1001)Actuator Installation (48", XV-1002)Actuator Installation (48", XV-1003)

Actuator Installation (24", XV-1006)Actuator Installation (24", XV-1007)Actuator Installation (24", XV-1008)Actuator Installation (24", XV-1009)Actuator Installation (24", XV-1010)

Actuator Installation (36", XV-1004)Actuator Installation (36", XV-1005)

Valve Installation (48", XV-1001)Valve Installation (48", XV-1002)Valve Installation (48", XV-1003)

Valve Installation (24", XV-1006, 48" Line Header)Valve Installation (24", XV-1007, 48" Line Header)

Valve Installation (24", XV-1008)Valve Installation (24", XV-1009)

Valve Installation (24", XV-1010)Valve Installation (36", XV-1004, 48" Line Header)

Valve Installation (36", XV-1005, 48" Line Header)

Water FillingHolding Time (8 Hrs)

Water Draining

PO for Repair Work of Pig Launcher & Receiver, PO for Repair Work of Pig Launcher & Receiver

Actual WorkRemaining WorkCritical Remaining Work

Milestone Project Overall Schedule

Page 2 of 15

Date Revision Checked Approved

03/03/14 ISSUED FOR MONTHLY PROGRESS REPORT H.S. LEE J.L. NABORS

Page 3: Project Schedule as of 03MAR2014 %28PDF Format%29 (2)

Activity Name Start Finish OD RD

Transportation from Site to Repair Shop 03/19/14 03/20/14 2 2Repair Work of Pig Launcher & Receiver (Incl. Test & Inspection) 03/21/14 04/09/14 20 20Transportation from Repair Shop to Site 04/10/14 04/11/14 2 2Pig Launcher - Installation (Incl. Piping Work) 04/12/14 04/25/14 14 14Pig Receiver - Installation (Incl. Piping Work) 04/14/14 04/27/14 14 14

Pneumatic Test for 36" & 24" Lines (incl. Transfer Line) 06/04/14 06/08/14 5 5N2 Manifold Installation 06/04/14 06/05/14 1 1N2 Pressurization 87.5 bar 06/06/14 06/07/14 2 2Hold Time 24 hrs 06/07/14 06/08/14 2 2Venting 06/08/14 06/08/14 1 1

48" Main Line Work (South) 04/21/14 05/08/14 18 18Cap Cutting & Fit-up for South Golden Joint 04/21/14 04/21/14 1 1Welding for South Golden Joint 04/22/14 04/25/14 4 4NDE for South Golden Joint 04/24/14 04/25/14 2 2RAM-100 Painting & Holiday Test for South Golden Joint 04/26/14 04/28/14 3 3Backfilling & Compaction for TP-South 04/29/14 05/08/14 10 10Painting for South A/G Piping 04/21/14 04/27/14 7 7

48" Main Line Work (North) 04/21/14 05/08/14 18 18Cap Cutting & Fit-up for North Golden Joint 04/21/14 04/21/14 1 1Welding for North Golden Joint 04/22/14 04/25/14 4 4NDE for North Golden Joint 04/24/14 04/25/14 2 2RAM-100 Painting & Holiday Test for North Golden Joint 04/26/14 04/28/14 3 3Backfilling & Compaction for TP-North 04/29/14 05/08/14 10 10Painting for North A/G Piping 04/21/14 04/27/14 7 7

Fence Work 04/22/14 07/15/14 85 85Fence Work (West) 04/22/14 05/21/14 30 30Fence Work (North & South) 05/18/14 06/11/14 25 25Fence Work (East) 06/16/14 07/15/14 30 30

Transfer Piping 01/25/14 A 06/03/14 130 96

New Schedule with New Valves (Incl. Tunneling) 01/25/14 A 06/03/14 130 96Permit 01/25/14 A 05/11/14 106 72Preparation for CRE Permit 01/25/14 A 05/10/14 75 72Application for CRE Permit 05/11/14* 0 0

Tunneling Work for 36" Line 02/25/14 A 03/16/14 25 1736" NG Pipe Weling & Installation (Incl. NDE, Vent & RAM-100 Coating) 02/25/14 A 03/16/14 25 17End Point Sealing & Insert Machine Takeout 03/16/14 03/16/14 1 1

Anchor Block Work for Transfer Line 03/18/14 05/19/14 63 6336" Anchor Block Excavation & Lean Con'c Pouring 03/18/14 03/25/14 8 8Re-bar & Form Work 05/01/14 05/10/14 10 10Concrete Pouring 05/11/14 05/12/14 2 2Form Removal 05/19/14 05/19/14 1 1

Transfer Piping Work 03/11/14 06/03/14 85 85Hydro Test for Anchor Flange (6m 2EA, 12m 1EA, Anchor Flange 2EA) 03/11/14 03/18/14 7 7Installation of Anchor Flange Spool after Hydro Test 03/26/14 03/26/14 1 136" NG Pipe Fit-up & Welding (Incl. Anchor Flange) 03/27/14 04/30/14 35 3536" Boring Point Tie-in & Welding 03/27/14 03/31/14 5 5NDE for Transfer Line 03/24/14 05/02/14 40 40Backfilling & Compaction 05/15/14 06/03/14 20 20

Compression Station (or Common) 08/23/13 A 08/05/14 323 159

Civil Works 02/10/14 A 04/28/14 87 60Fence & Gate 03/01/14 03/10/14 10 10Gate 03/01/14 03/10/14 10 10Gate Installation 03/01/14 03/10/14 10 10

Road 02/20/14 A 04/28/14 68 60

17 18 19 20 21 22 23 24Mar Apr May Jun Jul Aug Sep Oct

2014

Transportation from Site to Repair ShopRepair Work of Pig Launcher & Receiver (Incl. Test & Inspection)

Transportation from Repair Shop to SitePig Launcher - Installation (Incl. Piping Work)

Pig Receiver - Installation (Incl. Piping Work)

N2 Manifold InstallationN2 Pressurization 87.5 barHold Time 24 hrsVenting

Cap Cutting & Fit-up for South Golden JointWelding for South Golden JointNDE for South Golden Joint

RAM-100 Painting & Holiday Test for South Golden JointBackfilling & Compaction for TP-South

Painting for South A/G Piping

Cap Cutting & Fit-up for North Golden JointWelding for North Golden JointNDE for North Golden Joint

RAM-100 Painting & Holiday Test for North Golden JointBackfilling & Compaction for TP-North

Painting for North A/G Piping

Fence Work (West)Fence Work (North & South)

Fence Work (East)

Preparation for CRE Permit, Preparation for CRE PermitApplication for CRE Permit

36" NG Pipe Weling & Installation (Incl. NDE, Vent & RAM-100 Coating), 36" NG Pipe Weling & Installation (Incl. NDE, Vent & RAM-100 Coating)End Point Sealing & Insert Machine Takeout

36" Anchor Block Excavation & Lean Con'c PouringRe-bar & Form Work

Concrete PouringForm Removal

Hydro Test for Anchor Flange (6m 2EA, 12m 1EA, Anchor Flange 2EA)Installation of Anchor Flange Spool after Hydro Test

36" NG Pipe Fit-up & Welding (Incl. Anchor Flange)36" Boring Point Tie-in & Welding

NDE for Transfer LineBackfilling & Compaction

Gate Installation

Actual WorkRemaining WorkCritical Remaining Work

Milestone Project Overall Schedule

Page 3 of 15

Date Revision Checked Approved

03/03/14 ISSUED FOR MONTHLY PROGRESS REPORT H.S. LEE J.L. NABORS

Page 4: Project Schedule as of 03MAR2014 %28PDF Format%29 (2)

Activity Name Start Finish OD RD

Asphalt Road 03/01/14 04/08/14 39 39Grading & Cleaning 03/01/14 03/07/14 7 7Sub-Base Course Rolling 03/18/14 03/24/14 7 7Final Base Course 03/25/14 03/31/14 7 7Final Wearing 04/01/14 04/08/14 8 8

Concrete 02/20/14 A 04/28/14 50 60CLEANING & DRAIN 02/20/14 A 04/18/14 50 50Concrete Puring 02/22/14 A 04/23/14 30 55Finishing 03/30/14 04/28/14 30 30

Equipment Foundation 03/07/14 03/13/14 7 7Septic Tank_(T-201) 03/07/14 03/13/14 7 7Backfilling 03/07/14 03/13/14 7 7

Lighting Pole Foundation 02/10/14 A 03/29/14 20 30Common 02/10/14 A 03/29/14 20 30Excavation 02/10/14 A 03/19/14 20 20Foundation Installation 02/15/14 A 03/24/14 5 25Backfilling 02/15/14 A 03/29/14 5 30

Building Works 12/10/13 A 03/31/14 119 32MCC Building 12/10/13 A 03/20/14 107 21Floor Finish 02/10/14 A 03/07/14 20 8Tile Work 02/10/14 A 03/07/14 20 8

Ceiling Finish 12/10/13 A 03/20/14 30 21Ceiling 12/10/13 A 03/20/14 30 21

Water Proofing 02/20/14 A 03/14/14 20 15Roof Work 02/20/14 A 03/14/14 20 15

EGG Building 02/10/14 A 03/31/14 50 32Opening 02/10/14 A 03/07/14 10 8Door & Window 02/10/14 A 03/07/14 10 8

Wall Finish 02/10/14 A 03/07/14 7 8Painting 02/10/14 A 03/07/14 7 8

Floor Finish 02/28/14 03/09/14 10 10Painting 02/28/14 03/09/14 10 10

Ceiling Finish 03/27/14 03/31/14 5 5Painting 03/27/14 03/31/14 5 5

Water Proofing 02/28/14 03/14/14 15 15Roof Work 02/28/14 03/14/14 15 15

Maintenance Building 02/20/14 A 03/14/14 14 15Floor Finish 02/28/14 03/13/14 14 14Painting 02/28/14 03/13/14 14 14

Water Proofing 02/20/14 A 03/14/14 14 15Roof Work 02/20/14 A 03/14/14 14 15

Guard House 02/28/14 03/13/14 14 14Floor Finish 02/28/14 03/09/14 10 10Tile Work 02/28/14 03/09/14 10 10

Water Proofing 02/28/14 03/13/14 14 14Roof Work 02/28/14 03/13/14 14 14

Fire Water Pump Shelter 02/28/14 03/14/14 15 15Structure 02/28/14 03/14/14 15 15Clading 02/28/14 03/14/14 15 15

Mechanical-Rotating 05/06/14 05/11/14 6 6Compressor 05/06/14 05/11/14 6 6Natural Gas Compressor_(C-201A) 05/06/14 05/11/14 6 6Final Alignment 05/06/14 05/09/14 4 4Inspection 05/10/14 05/11/14 2 2

Natural Gas Compressor_(C-201B) 05/06/14 05/11/14 6 6Final Alignment 05/06/14 05/09/14 4 4

17 18 19 20 21 22 23 24Mar Apr May Jun Jul Aug Sep Oct

2014

Grading & CleaningSub-Base Course Rolling

Final Base CourseFinal Wearing

CLEANING & DRAIN, CLEANING & DRAINConcrete Puring, Concrete Puring

Finishing

Backfilling

Excavation, ExcavationFoundation Installation, Foundation Installation

Backfilling, Backfilling

Tile Work, Tile Work

Ceiling, Ceiling

Roof Work, Roof Work

Door & Window, Door & Window

Painting, Painting

Painting

Painting

Roof Work

Painting

Roof Work, Roof Work

Tile Work

Roof Work

Clading

Final AlignmentInspection

Final Alignment

Actual WorkRemaining WorkCritical Remaining Work

Milestone Project Overall Schedule

Page 4 of 15

Date Revision Checked Approved

03/03/14 ISSUED FOR MONTHLY PROGRESS REPORT H.S. LEE J.L. NABORS

Page 5: Project Schedule as of 03MAR2014 %28PDF Format%29 (2)

Activity Name Start Finish OD RD

Inspection 05/10/14 05/11/14 2 2Natural Gas Compressor_(C-201C) 05/06/14 05/11/14 6 6Final Alignment 05/06/14 05/09/14 4 4Inspection 05/10/14 05/11/14 2 2

Natural Gas Compressor_(C-201D) 05/06/14 05/11/14 6 6Final Alignment 05/06/14 05/09/14 4 4Inspection 05/10/14 05/11/14 2 2

Mechanical-Stationary 02/28/14 04/27/14 59 59Nitrogen (N2) 02/28/14 03/09/14 10 10N2 Bottle Rack_(N-201) 02/28/14 03/09/14 10 10Foundation Check & Padding Work 02/28/14 03/02/14 3 3Installation 03/03/14 03/05/14 3 3Centering & Alignment 03/06/14 03/08/14 3 3Inspection 03/09/14 03/09/14 1 1

Column 02/28/14 03/08/14 9 9Vent Column_(VC-201) 02/28/14 03/08/14 9 9Foundation Check & Padding Work 02/28/14 03/02/14 3 3Installation 03/03/14 03/05/14 3 3Centering & Alignment 03/06/14 03/07/14 2 2Inspection 03/08/14 03/08/14 1 1

Tank Installation 02/28/14 03/14/14 15 15Condensate Drain Tank_(V-201) 02/28/14 03/01/14 2 2Installation 02/28/14 02/28/14 1 1Inspection 03/01/14 03/01/14 1 1

Raw Water Storage Tank_(T-202) 02/28/14 03/14/14 15 15Painting 02/28/14 03/14/14 15 15

Metering Skid 04/15/14 04/27/14 13 13Metering Skid_(M-203) 04/15/14 04/27/14 13 13Installation 04/15/14 04/24/14 10 10Centering & Alignment 04/25/14 04/27/14 3 3

Piping Works 10/29/13 A 05/11/14 195 73Natural Gas Piping Installation 11/05/13 A 05/11/14 188 73Battery Limit to Separator 11/05/13 A 05/05/14 182 67Field Installation 11/05/13 A 04/20/14 60 52PWHT/NDE 11/25/13 A 04/25/14 57 7Hydro & Pneumatic Test 04/26/14 05/05/14 10 10

Gas Separator to Coalscing Filter 04/26/14 05/05/14 10 10Hydro & Pneumatic Test 04/26/14 05/05/14 10 10

Coalscing Filter to Compressor 04/26/14 05/05/14 10 10Hydro & Pneumatic Test 04/26/14 05/05/14 10 10

Compressor to NG Compressor Discharge Cooler 04/26/14 05/05/14 10 10Hydro & Pneumatic Test 04/26/14 05/05/14 10 10

NG Compressor Discharge Cooler to Metering Skid 04/26/14 05/05/14 10 10Hydro & Pneumatic Test 04/26/14 05/05/14 10 10

Metering Skid to Battery Limit 11/25/13 A 05/11/14 168 59Field Installation 04/09/14 04/24/14 16 16PWHT/NDE 11/25/13 A 05/01/14 88 49Hydro & Pneumatic Test 05/02/14 05/11/14 10 10

ESD Valves (36") - New 03/27/14 04/11/14 16 16ESD Valves - Unloading & Actuator Installation 03/27/14 03/29/14 3 3ESD Valves - Valve Installation 03/30/14 04/01/14 3 3ESD Valves - Other Installation (Air Tank, Instrument, etc.) 04/02/14 04/08/14 7 7ESD Valves - Loop Test & Function Test 04/09/14 04/11/14 3 3

Utility Piping Installation 10/29/13 A 04/15/14 169 47Plant Air Distribution System 02/06/14 A 04/06/14 60 38

17 18 19 20 21 22 23 24Mar Apr May Jun Jul Aug Sep Oct

2014

Inspection

Final AlignmentInspection

Final AlignmentInspection

Foundation Check & Padding WorkInstallation

Centering & AlignmentInspection

Foundation Check & Padding WorkInstallation

Centering & AlignmentInspection

InstallationInspection

Painting

InstallationCentering & Alignment

Field Installation, Field InstallationPWHT/NDE, PWHT/NDE

Hydro & Pneumatic Test

Hydro & Pneumatic Test

Hydro & Pneumatic Test

Hydro & Pneumatic Test

Hydro & Pneumatic Test

Field InstallationPWHT/NDE, PWHT/NDE

Hydro & Pneumatic Test

ESD Valves - Unloading & Actuator InstallationESD Valves - Valve Installation

ESD Valves - Other Installation (Air Tank, Instrument, etc.)ESD Valves - Loop Test & Function Test

Actual WorkRemaining WorkCritical Remaining Work

Milestone Project Overall Schedule

Page 5 of 15

Date Revision Checked Approved

03/03/14 ISSUED FOR MONTHLY PROGRESS REPORT H.S. LEE J.L. NABORS

Page 6: Project Schedule as of 03MAR2014 %28PDF Format%29 (2)

Activity Name Start Finish OD RD

A/G Pipe Fabrication & Installation 02/06/14 A 04/01/14 55 33A/G Pipe Hydro-test 04/02/14 04/06/14 5 5

Plant Air System 02/10/14 A 03/12/14 30 13A/G Pipe Fabrication & Installation 02/10/14 A 03/09/14 30 10A/G Pipe Hydro-test 03/10/14 03/12/14 3 3

Instrument Air System 12/23/13 A 03/07/14 95 8A/G Pipe Fabrication & Installation 12/23/13 A 03/02/14 30 3A/G Pipe Hydro-test 03/03/14 03/07/14 5 5

Potable Water System 12/16/13 A 03/15/14 103 16A/G Pipe Fabrication & Installation 12/16/13 A 03/10/14 30 11A/G Pipe Hydro-test 03/11/14 03/15/14 5 5

Raw Water System 11/25/13 A 03/09/14 105 10A/G Pipe Fabrication & Installation 11/25/13 A 03/04/14 30 5A/G Pipe Hydro-test 03/05/14 03/09/14 5 5

Service Water System 10/29/13 A 03/31/14 154 32U/G Pipe Fabrication & Installation 10/29/13 A 03/07/14 61 8U/G Pipe Hydro-test 03/08/14 03/13/14 6 6A/G Pipe Fabrication & Installation 12/16/13 A 03/26/14 61 27A/G Pipe Hydro-test 03/27/14 03/31/14 5 5

Deminaeralized Water System 11/25/13 A 03/31/14 127 32A/G Pipe Fabrication & Installation 11/25/13 A 03/25/14 44 26A/G Pipe Hydro-test 03/26/14 03/31/14 6 6

Oily water System 12/16/13 A 03/31/14 119 32U/G Pipe Hydro-test 02/28/14 A 03/04/14 5 5A/G Pipe Fabrication & Installation 12/16/13 A 03/26/14 61 27A/G Pipe Hydro-test 03/27/14 03/31/14 5 5

Nitrogen System 12/23/13 A 04/15/14 134 47A/G Pipe Fabrication & Installation 12/23/13 A 04/10/14 61 42A/G Pipe Hydro-test 04/11/14 04/15/14 5 5

Condensate Drain System 12/23/13 A 04/15/14 134 47A/G Pipe Fabrication & Installation 12/23/13 A 04/10/14 61 42A/G Pipe Hydro-test 04/11/14 04/15/14 5 5

Gas Venting System 12/23/13 A 04/15/14 134 47A/G Pipe Fabrication & Installation 12/23/13 A 04/10/14 61 42A/G Pipe Hydro-test 04/11/14 04/15/14 5 5

Fuel Gas System 12/23/13 A 03/31/14 99 32A/G Pipe Fabrication & Installation 12/23/13 A 03/26/14 61 27A/G Pipe Hydro-test 03/27/14 03/31/14 5 5

Seal gas System 11/25/13 A 03/31/14 127 32A/G Pipe Fabrication & Installation 11/25/13 A 03/26/14 61 27A/G Pipe Hydro-test 03/27/14 03/31/14 5 5

HVAC Works 01/06/14 A 03/13/14 79 14HVAC (by Building) 01/06/14 A 03/13/14 79 14MCC Building 01/06/14 A 03/13/14 51 14MCC 1st FL System Air Conditon 01/06/14 A 03/13/14 32 14MCC 1st FL HVAC & Exhaust Fan 01/17/14 A 03/13/14 32 14

EGG Building 02/28/14 A 03/13/14 10 6Air Conditon 02/28/14 A 03/13/14 10 6

Guard House 02/28/14 03/04/14 5 5Air Conditon 02/28/14 03/04/14 5 5

Fire Fighting Works 02/17/14 A 03/29/14 30 30Fire Fighting (by Area) 02/17/14 A 03/29/14 30 30Yard 03/03/14 03/29/14 27 27AG Pipe Installation 03/15/14 03/29/14 15 15Out door Hydrant 03/03/14 03/19/14 17 17

17 18 19 20 21 22 23 24Mar Apr May Jun Jul Aug Sep Oct

2014

A/G Pipe Fabrication & Installation, A/G Pipe Fabrication & InstallationA/G Pipe Hydro-test

A/G Pipe Fabrication & Installation, A/G Pipe Fabrication & InstallationA/G Pipe Hydro-test

A/G Pipe Fabrication & Installation, A/G Pipe Fabrication & InstallationA/G Pipe Hydro-test

A/G Pipe Fabrication & Installation, A/G Pipe Fabrication & InstallationA/G Pipe Hydro-test

A/G Pipe Fabrication & Installation, A/G Pipe Fabrication & InstallationA/G Pipe Hydro-test

U/G Pipe Fabrication & Installation, U/G Pipe Fabrication & InstallationU/G Pipe Hydro-test

A/G Pipe Fabrication & Installation, A/G Pipe Fabrication & InstallationA/G Pipe Hydro-test

A/G Pipe Fabrication & Installation, A/G Pipe Fabrication & InstallationA/G Pipe Hydro-test

U/G Pipe Hydro-test, U/G Pipe Hydro-testA/G Pipe Fabrication & Installation, A/G Pipe Fabrication & Installation

A/G Pipe Hydro-test

A/G Pipe Fabrication & Installation, A/G Pipe Fabrication & InstallationA/G Pipe Hydro-test

A/G Pipe Fabrication & Installation, A/G Pipe Fabrication & InstallationA/G Pipe Hydro-test

A/G Pipe Fabrication & Installation, A/G Pipe Fabrication & InstallationA/G Pipe Hydro-test

A/G Pipe Fabrication & Installation, A/G Pipe Fabrication & InstallationA/G Pipe Hydro-test

A/G Pipe Fabrication & Installation, A/G Pipe Fabrication & InstallationA/G Pipe Hydro-test

MCC 1st FL System Air Conditon, MCC 1st FL System Air ConditonMCC 1st FL HVAC & Exhaust Fan, MCC 1st FL HVAC & Exhaust Fan

Air Conditon, Air Conditon

Air Conditon

AG Pipe InstallationOut door Hydrant

Actual WorkRemaining WorkCritical Remaining Work

Milestone Project Overall Schedule

Page 6 of 15

Date Revision Checked Approved

03/03/14 ISSUED FOR MONTHLY PROGRESS REPORT H.S. LEE J.L. NABORS

Page 7: Project Schedule as of 03MAR2014 %28PDF Format%29 (2)

Activity Name Start Finish OD RD

Portable Fire Extinguishers 03/20/14 03/22/14 3 3Gas Compressor 02/28/14 03/22/14 23 23Out door Hydrant 02/28/14 03/16/14 17 17Portable Fire Extinguishers 03/20/14 03/22/14 3 3

Combustion TBN 02/17/14 A 03/07/14 26 8Water Spray System 02/17/14 A 03/07/14 26 8

MCC Building 02/17/14 A 03/22/14 23 23Sprinkler System 02/17/14 A 03/03/14 22 4Out door Hydrant 02/24/14 A 03/12/14 17 13Portable Fire Extinguishers 03/20/14 03/22/14 3 3

Maintenance Building 02/17/14 A 03/22/14 23 23Sprinkler System 02/17/14 A 03/16/14 17 17Out door Hydrant 02/24/14 A 03/16/14 17 17Portable Fire Extinguishers 03/20/14 03/22/14 3 3

EGG Building 02/28/14 03/22/14 23 23Out door Hydrant 02/28/14 03/16/14 17 17Portable Fire Extinguishers 03/20/14 03/22/14 3 3

Guard House 03/20/14 03/22/14 3 3Portable Fire Extinguishers 03/20/14 03/22/14 3 3

Fire Water Pump Shelter 02/28/14 03/22/14 23 23Sprinkler System 03/15/14 03/21/14 7 7Out door Hydrant 02/28/14 03/16/14 17 17Portable Fire Extinguishers 03/20/14 03/22/14 3 3

Electrical Works 08/23/13 A 05/29/14 255 91Equipment Installation 02/28/14 03/21/14 22 22Emergency Gas Generator 02/28/14 03/21/14 22 22Panel Installation & Cable Connection 02/28/14 03/21/14 22 22

Cable Tray Installation 02/01/14 A 05/29/14 118 76Process 05/22/14 05/29/14 8 8Tray Cover Installation 05/22/14 05/26/14 5 5Final Inspection 05/27/14 05/29/14 3 3

Building 02/01/14 A 04/27/14 86 44Tray & Support Installation (EGG) 02/01/14 A 03/26/14 15 12Tray Cover Installation 04/20/14 04/24/14 5 5Inspection 04/25/14 04/27/14 3 3

Conduit Installation 01/25/14 A 04/07/14 73 24Building 01/25/14 A 04/07/14 73 24Conduit Installation (Fire Water Pump Shelter) 01/25/14 A 04/02/14 5 19Inspection 04/03/14 04/07/14 5 5

Cable Pulling 01/25/14 A 04/17/14 84 492nd for Compression Area 02/28/14 A 03/09/14 18 10Gas Compressor Unit 3&4 02/28/14 A 03/04/14 4 5Other Euipment in Compression Area 02/28/14 03/09/14 10 10

2nd for Utility 01/25/14 A 03/12/14 3 13Oily Water Sump Pump 01/25/14 A 03/12/14 3 13

Power & Control Cable Termination 02/26/14 A 03/18/14 50 19Fire Water Pump 02/26/14 A 03/03/14 4 4Oily Water Sump Pump 03/13/14 03/15/14 3 3Gas Compressor Unit 1&2 02/28/14 03/04/14 5 5Gas Compressor Unit 3&4 03/05/14 03/09/14 5 5Other Euipment in Compression Area 03/10/14 03/12/14 3 3Inspection 03/13/14 03/18/14 6 6

Fiber Optic Cable Termination 03/10/14 04/17/14 39 39Patch Cord Connection 03/10/14 03/29/14 20 20Communication Test 03/30/14 04/17/14 19 19

17 18 19 20 21 22 23 24Mar Apr May Jun Jul Aug Sep Oct

2014

Portable Fire Extinguishers

Out door HydrantPortable Fire Extinguishers

Water Spray System, Water Spray System

Sprinkler System, Sprinkler SystemOut door Hydrant, Out door Hydrant

Portable Fire Extinguishers

Sprinkler System, Sprinkler SystemOut door Hydrant, Out door Hydrant

Portable Fire Extinguishers

Out door HydrantPortable Fire Extinguishers

Portable Fire Extinguishers

Sprinkler SystemOut door Hydrant

Portable Fire Extinguishers

Panel Installation & Cable Connection

Tray Cover InstallationFinal Inspection

Tray & Support Installation (EGG), Tray & Support Installation (EGG)Tray Cover Installation

Inspection

Conduit Installation (Fire Water Pump Shelter), Conduit Installation (Fire Water Pump Shelter)Inspection

Gas Compressor Unit 3&4, Gas Compressor Unit 3&4Other Euipment in Compression Area

Oily Water Sump Pump, Oily Water Sump Pump

Fire Water Pump, Fire Water PumpOily Water Sump Pump

Gas Compressor Unit 1&2Gas Compressor Unit 3&4

Other Euipment in Compression AreaInspection

Patch Cord ConnectionCommunication Test

Actual WorkRemaining WorkCritical Remaining Work

Milestone Project Overall Schedule

Page 7 of 15

Date Revision Checked Approved

03/03/14 ISSUED FOR MONTHLY PROGRESS REPORT H.S. LEE J.L. NABORS

Page 8: Project Schedule as of 03MAR2014 %28PDF Format%29 (2)

Activity Name Start Finish OD RD

Grounding & Lightning System 08/23/13 A 04/04/14 189 36Lightning System 02/15/14 A 03/24/14 25 13MCC & EGG Building 02/15/14 A 03/24/14 25 13

Grounding System 08/23/13 A 04/04/14 149 36MCC & EGG Building 09/17/13 A 03/29/14 90 30Compression Area 08/23/13 A 04/04/14 149 36

Fire Alarm System Installation 02/28/14 04/02/14 34 34Plant Area 02/28/14 04/02/14 34 34Installation for Plant Area 02/28/14 04/02/14 34 34

Lighting System Installation 12/17/13 A 03/31/14 123 32Building Lighting 03/08/14 03/28/14 21 21Fire Pump Water Shelter 03/08/14 03/28/14 21 21

Other Lighting 12/17/13 A 03/31/14 123 32Plant Lighting 12/17/13 A 03/31/14 28 32Road Lighting 02/17/14 A 03/31/14 50 32

Communication System 12/09/13 A 04/05/14 119 37TEL/LAN System Installation 12/09/13 A 04/05/14 119 37MCC Building 12/09/13 A 03/04/14 37 5Maintenance Building 03/05/14 03/14/14 10 10EGG Building 03/15/14 03/24/14 10 10Guard House 03/25/14 04/05/14 12 12

Paging System Installation 03/15/14 03/24/14 10 10Fire Water Pump Shelter 03/15/14 03/24/14 10 10

CCTV System Installation 02/28/14 03/21/14 22 22MCC Building 02/28/14 03/19/14 20 20Plant Area 02/28/14 03/21/14 22 22

Pre-commissioning 02/25/14 A 05/20/14 82 82Equipment Test 02/25/14 A 04/02/14 34 34UPS Panel 02/25/14 A 03/05/14 3 6Battery with Charger 02/25/14 A 03/10/14 9 11Power Transformer 03/14/14 03/19/14 6 6Capacity & NGR Panel 03/20/14 03/23/14 4 4MV SWGR 03/14/14 03/17/14 4 4LV SWGR 03/18/14 03/21/14 4 4LV MCC 03/22/14 03/28/14 7 7Compressor VFD Panel 03/05/14 03/09/14 5 5Emergency Gas Generator 03/25/14 04/02/14 9 9

Fire Alarm Test 03/13/14 04/12/14 31 31Main Control Panel Assembly 03/13/14 03/16/14 4 4MCC Building 03/17/14 03/30/14 14 14EGG Building 04/08/14 04/10/14 3 3Maintenance Building 03/31/14 04/02/14 3 3Local Control Panel Assembly 04/03/14 04/05/14 3 3Plant Area 04/06/14 04/07/14 2 2Fire Water Pump Shelter 04/11/14 04/12/14 2 2

Lighting Illumination Test 04/25/14 05/20/14 26 26Illumination Test for Building 04/25/14 05/14/14 20 20Illumination Test for Plant Lighting 05/15/14 05/17/14 3 3Illumination Test for Road Lighting 05/18/14 05/20/14 3 3

Communication System 04/30/14 05/14/14 15 15TEL/LAN System Test 04/30/14 05/04/14 5 5Paging System Test 05/05/14 05/09/14 5 5CCTV System Test 05/10/14 05/14/14 5 5

Motor Rotating Test (Uncoupling) 04/10/14 04/29/14 20 20Utility 04/10/14 04/16/14 7 7

17 18 19 20 21 22 23 24Mar Apr May Jun Jul Aug Sep Oct

2014

MCC & EGG Building, MCC & EGG Building

MCC & EGG Building, MCC & EGG BuildingCompression Area, Compression Area

Installation for Plant Area

Fire Pump Water Shelter

Plant Lighting, Plant LightingRoad Lighting, Road Lighting

MCC Building, MCC BuildingMaintenance Building

EGG BuildingGuard House

Fire Water Pump Shelter

MCC BuildingPlant Area

UPS Panel, UPS PanelBattery with Charger, Battery with Charger

Power TransformerCapacity & NGR Panel

MV SWGRLV SWGR

LV MCCCompressor VFD Panel

Emergency Gas Generator

Main Control Panel AssemblyMCC Building

EGG BuildingMaintenance Building

Local Control Panel AssemblyPlant Area

Fire Water Pump Shelter

Illumination Test for BuildingIllumination Test for Plant Lighting

Illumination Test for Road Lighting

TEL/LAN System TestPaging System Test

CCTV System Test

Utility

Actual WorkRemaining WorkCritical Remaining Work

Milestone Project Overall Schedule

Page 8 of 15

Date Revision Checked Approved

03/03/14 ISSUED FOR MONTHLY PROGRESS REPORT H.S. LEE J.L. NABORS

Page 9: Project Schedule as of 03MAR2014 %28PDF Format%29 (2)

Activity Name Start Finish OD RD

Process (Air Fin Fan Cooler) 04/17/14 04/19/14 3 3Process (Gas Compressor) 04/20/14 04/29/14 10 10

Power Energizing 04/01/14 04/04/14 4 4Interlock Test 04/01/14 04/01/14 1 1MV Power Energizing (Incomming) 04/02/14 04/02/14 1 1LV Power Energizing (SWGR) 04/03/14 04/03/14 1 1LV Power Energizing (MCC) 04/04/14 04/04/14 1 1

Instrumentation Works 12/29/13 A 05/29/14 152 91Cable Tray Installation 05/22/14 05/29/14 8 8Process Area 05/22/14 05/29/14 8 8Tray Cover Installation 05/22/14 05/26/14 5 5Final Inspection 05/27/14 05/29/14 3 3

Conduit Installation 01/11/14 A 03/24/14 73 25Process Area 01/11/14 A 03/24/14 73 25Conduit Installation (Utility) 01/18/14 A 03/16/14 20 17Conduit Installation (Compession Area) 01/11/14 A 03/19/14 30 20Inspection 03/20/14 03/24/14 5 5

SCADA 02/21/14 A 03/06/14 4 7SCADA Cabinet Installation 02/21/14 A 03/06/14 4 7Communication Cable Laying & Connection 02/21/14 A 03/03/14 4 4Inspection 03/04/14 03/06/14 3 3

Fire & Gas Detection System 01/31/14 A 03/14/14 35 15Plant Gas Detection 01/31/14 A 03/14/14 35 15Gas Detector Installation 01/31/14 A 03/12/14 35 13Cable Pulling & Connection 02/03/14 A 03/14/14 15 15

Instrument Cable Pulling & Termination 01/30/14 A 03/27/14 57 28Cable Pulling 01/30/14 A 03/27/14 30 282nd Cable Pulling (Utility) 01/30/14 A 03/12/14 15 132nd Cable Pulling (Compression Area) 01/30/14 A 03/27/14 30 28

Cable Termination 02/15/14 A 03/27/14 20 28Control Signal Cable Termination 02/15/14 A 03/27/14 20 28

Field Instrument 12/29/13 A 04/13/14 96 45In-line Instrument 12/29/13 A 04/13/14 63 45Calibration, Installation and Connection 12/29/13 A 04/13/14 63 45

Field Instrument 01/14/14 A 04/03/14 96 35Calibration 01/14/14 A 03/16/14 40 17Stantion & Support Installation 02/28/14 03/17/14 18 18Field Instrument Installation (Utility) 03/18/14 04/01/14 15 15Field Instrument Installation (Gas Comp'r Unit 1&2) 02/28/14 03/14/14 15 15Field Instrument Installation (Gas Comp'r Unit 3&4) 03/15/14 03/29/14 15 15Inspection (Gas Comp'r) 03/30/14 04/03/14 5 5

Air/Impulse Piping & Tubing 02/28/14 04/04/14 36 36Compressor Unit 1&2 Area 02/28/14 03/16/14 17 17Installation & Connection for Comp'r Unit 1&2 02/28/14 03/16/14 17 17

Compressor Unit 3&4 Area 03/07/14 03/23/14 17 17Installation & Connection for Comp'r Unit 3&4 03/07/14 03/23/14 17 17

Utility Area 03/19/14 04/04/14 17 17Installation & Connection for Utility Area 03/19/14 04/04/14 17 17

Pre-commissioning 03/24/14 05/27/14 65 65DCS Control System 03/24/14 04/15/14 23 23DCS/ESD/F&G System SAT 03/24/14 04/06/14 14 14SCADA System SAT 04/02/14 04/15/14 14 14

Metering System 04/28/14 05/27/14 30 30Metering System SAT 04/28/14 05/27/14 30 30

Painting Works 04/13/14 05/29/14 47 47A/G Piping Work-Field Painting 04/13/14 05/29/14 47 47

17 18 19 20 21 22 23 24Mar Apr May Jun Jul Aug Sep Oct

2014

Process (Air Fin Fan Cooler)Process (Gas Compressor)

Interlock TestMV Power Energizing (Incomming)LV Power Energizing (SWGR)LV Power Energizing (MCC)

Tray Cover InstallationFinal Inspection

Conduit Installation (Utility), Conduit Installation (Utility)Conduit Installation (Compession Area), Conduit Installation (Compession Area)

Inspection

Communication Cable Laying & Connection, Communication Cable Laying & ConnectionInspection

Gas Detector Installation, Gas Detector InstallationCable Pulling & Connection, Cable Pulling & Connection

2nd Cable Pulling (Utility), 2nd Cable Pulling (Utility)2nd Cable Pulling (Compression Area), 2nd Cable Pulling (Compression Area)

Control Signal Cable Termination, Control Signal Cable Termination

Calibration, Installation and Connection, Calibration, Installation and Connection

Calibration, CalibrationStantion & Support Installation

Field Instrument Installation (Utility)Field Instrument Installation (Gas Comp'r Unit 1&2)

Field Instrument Installat ion (Gas Comp'r Unit 3&4)Inspection (Gas Comp'r)

Installation & Connection for Comp'r Unit 1&2

Installation & Connection for Comp'r Unit 3&4

Installation & Connection for Utility Area

DCS/ESD/F&G System SATSCADA System SAT

Metering System SAT

Actual WorkRemaining WorkCritical Remaining Work

Milestone Project Overall Schedule

Page 9 of 15

Date Revision Checked Approved

03/03/14 ISSUED FOR MONTHLY PROGRESS REPORT H.S. LEE J.L. NABORS

Page 10: Project Schedule as of 03MAR2014 %28PDF Format%29 (2)

Activity Name Start Finish OD RD

Common(Compression Area) 04/13/14 05/29/14 47 47Intermediate Coat 04/13/14 05/12/14 30 30Finish Coat 04/18/14 05/17/14 30 30Touch-Up 04/23/14 05/22/14 30 30Inspection 05/23/14 05/29/14 7 7

Steel Structure Work-Field Painting 04/23/14 05/19/14 27 27Common(Compression Area) 04/23/14 05/19/14 27 27Touch-Up 04/23/14 05/12/14 20 20Inspection 05/13/14 05/19/14 7 7

Insulation Works 02/28/14 05/13/14 75 75Shop Insulation 02/28/14 03/29/14 30 30Common(Compression Area) 02/28/14 03/29/14 30 30Cover Sheet Forming 02/28/14 03/19/14 20 20Fitting Insulator Cutting 02/28/14 03/29/14 30 30

Duct & V/V Insulation 02/28/14 05/13/14 75 75Common(Compression Area) 02/28/14 05/13/14 75 75Scaffolding 02/28/14 04/08/14 40 40Surface Cleaning 03/05/14 04/13/14 40 40Insulation Installation 03/10/14 04/18/14 40 40Cover Sheet Installation 03/15/14 04/23/14 40 40Finish Work 04/24/14 05/08/14 15 15Inspection 05/09/14 05/13/14 5 5

Commissioning Works 03/08/14 08/05/14 151 151Plant Air Compressor and Receiver (S-09-01) 03/13/14 04/16/14 35 35Precommissioning 03/13/14 04/12/14 31 31Flushing/Blowing & Reinstallation 03/13/14 03/17/14 5 5Final Box-up (V-208) 03/18/14 03/18/14 1 1Leak Test 03/19/14 03/19/14 1 1Loop Test 04/07/14 04/09/14 3 3Function Test (Inst.) 04/10/14 04/10/14 1 1Motor Uncoupled Run Test 04/08/14 04/09/14 2 2Mechaniacl Running Test (C-202A/B, A-202A/B) 04/11/14 04/12/14 2 2Mechanical Completion (S-09-01) 04/12/14 0 0

Commissioning 04/16/14 04/16/14 1 1Start PA Compressor and into Normal Operation 04/16/14 04/16/14 1 1Ready for Service 04/16/14 0 0

Plant Air Distribution (S-09-02) 04/07/14 04/18/14 12 12Precommissioning 04/07/14 04/12/14 6 6Flushing/Blowing & Reinstallation 04/07/14 04/11/14 5 5Leak Test 04/12/14 04/12/14 1 1Mechanical Completion (S-09-02) 04/12/14 0 0

Commissioning 04/18/14 04/18/14 1 1Into Normal Operation 04/18/14 04/18/14 1 1Ready for Service 04/18/14 0 0

Instrument Air (S-10-01) 03/08/14 04/17/14 41 41Precommissioning 03/08/14 04/10/14 34 34Flushing/Blowing & Reinstallation 03/08/14 03/12/14 5 5Final Box-up (V-207, U-210A/B) 03/13/14 03/13/14 1 1Leak Test 03/14/14 03/14/14 1 1Loop Test 04/07/14 04/09/14 3 3Function Test (Inst.) 04/10/14 04/10/14 1 1Mechanical Completion (S-10-01) 04/10/14 0 0

Commissioning 04/17/14 04/17/14 1 1Plant Air Service To Dryer 04/17/14 04/17/14 1 1Ready for Service 04/17/14 0 0

17 18 19 20 21 22 23 24Mar Apr May Jun Jul Aug Sep Oct

2014

Intermediate CoatFinish Coat

Touch-UpInspection

Touch-UpInspection

Cover Sheet FormingFitting Insulator Cutting

ScaffoldingSurface Cleaning

Insulation InstallationCover Sheet Installation

Finish WorkInspection

Flushing/Blowing & ReinstallationFinal Box-up (V-208)Leak Test

Loop TestFunction Test (Inst.)

Motor Uncoupled Run TestMechaniacl Running Test (C-202A/B, A-202A/B)Mechanical Completion (S-09-01)

Start PA Compressor and into Normal OperationReady for Service

Flushing/Blowing & ReinstallationLeak TestMechanical Completion (S-09-02)

Into Normal OperationReady for Service

Flushing/Blowing & ReinstallationFinal Box-up (V-207, U-210A/B)Leak Test

Loop TestFunction Test (Inst.)Mechanical Completion (S-10-01)

Plant Air Service To DryerReady for Service

Actual WorkRemaining WorkCritical Remaining Work

Milestone Project Overall Schedule

Page 10 of 15

Date Revision Checked Approved

03/03/14 ISSUED FOR MONTHLY PROGRESS REPORT H.S. LEE J.L. NABORS

Page 11: Project Schedule as of 03MAR2014 %28PDF Format%29 (2)

Activity Name Start Finish OD RD

Potable Water (S-15-01) 03/16/14 04/19/14 35 35Precommissioning 03/16/14 04/15/14 31 31Flushing/Blowing & Reinstallation 03/16/14 03/20/14 5 5Final Box-up (V-204) 03/21/14 03/21/14 1 1Leak Test 03/22/14 03/22/14 1 1Loop Test 04/12/14 04/13/14 2 2Function Test (Inst.) 04/14/14 04/14/14 1 1Motor Uncoupled Run Test 04/10/14 04/10/14 1 1Mechaniacl Running Test (P-203A/B) 04/15/14 04/15/14 1 1Mechanical Completion (S-15-01) 04/15/14 0 0

Commissioning 04/19/14 04/19/14 1 1Normal Start Potable Water Pump 04/19/14 04/19/14 1 1Ready for Service 04/19/14 0 0

Raw Water Tank and Pump (S-12-01) 03/10/14 04/22/14 44 44Precommissioning 03/10/14 04/19/14 41 41Flushing/Blowing & Reinstallation 03/10/14 03/14/14 5 5Final Box-up (T-202) 03/15/14 03/15/14 1 1Leak Test 03/16/14 03/16/14 1 1Loop Test 04/10/14 04/11/14 2 2Motor Uncoupled Run Test 04/11/14 04/11/14 1 1Function Test (Inst.) 04/18/14 04/18/14 1 1Mechaniacl Running Test (P-204A/B) 04/19/14 04/19/14 1 1Mechanical Completion (S-12-01) 04/19/14 0 0

Commissioning 04/21/14 04/22/14 2 2Fill up Raw Water Tank & Pump Start 04/21/14 04/22/14 2 2Ready for Service 04/22/14 0 0

Fire Water Pump & Distribution (S-13-01) 03/30/14 04/27/14 29 29Precommissioning 03/30/14 04/25/14 27 27Flushing/Blowing & Reinstallation 03/30/14 04/03/14 5 5Leak Test 04/04/14 04/04/14 1 1Loop Test 04/12/14 04/14/14 3 3Function Test (Inst.) 04/15/14 04/15/14 1 1Motor Uncoupled Run Test 04/12/14 04/12/14 1 1Mechaniacl Running Test (FP-201/202/203) 04/23/14 04/24/14 2 2Flushing (Fire Water Distribution Line) 04/25/14 04/25/14 1 1Mechanical Completion (S-13-01) 04/25/14 0 0

Commissioning 04/27/14 04/27/14 1 1Fill Distribution Header 04/27/14 04/27/14 1 1Ready for Service 04/27/14 0 0

Service Water Distribution (S-12-02) 04/01/14 04/23/14 23 23Precommissioning 04/01/14 04/15/14 15 15Flushing/Blowing 04/01/14 04/05/14 5 5Leak Test 04/06/14 04/06/14 1 1Loop Test 04/15/14 04/15/14 1 1Mechanical Completion (S-12-02) 04/15/14 0 0

Commissioning 04/23/14 04/23/14 1 1Fill Distribution Header 04/23/14 04/23/14 1 1Ready for Service 04/23/14 0 0

Demineralized Water (S-14-01) 04/01/14 04/24/14 24 24Precommissioning 04/01/14 04/06/14 6 6Flushing/Blowing & Reinstallation 04/01/14 04/05/14 5 5Final Box-up (V-209) 04/06/14 04/06/14 1 1Mechanical Completion (S-14-01) 04/06/14 0 0

Commissioning 04/24/14 04/24/14 1 1Fill up Tank with Demineralized Water 04/24/14 04/24/14 1 1

17 18 19 20 21 22 23 24Mar Apr May Jun Jul Aug Sep Oct

2014

Flushing/Blowing & ReinstallationFinal Box-up (V-204)Leak Test

Loop TestFunction Test (Inst.)

Motor Uncoupled Run TestMechaniacl Running Test (P-203A/B)Mechanical Completion (S-15-01)

Normal Start Potable Water PumpReady for Service

Flushing/Blowing & ReinstallationFinal Box-up (T-202)Leak Test

Loop TestMotor Uncoupled Run Test

Function Test (Inst.)Mechaniacl Running Test (P-204A/B)Mechanical Completion (S-12-01)

Fill up Raw Water Tank & Pump StartReady for Service

Flushing/Blowing & ReinstallationLeak Test

Loop TestFunction Test (Inst.)

Motor Uncoupled Run TestMechaniacl Running Test (FP-201/202/203)Flushing (Fire Water Distribution Line)Mechanical Completion (S-13-01)

Fill Distribution HeaderReady for Service

Flushing/BlowingLeak Test

Loop TestMechanical Completion (S-12-02)

Fill Distribution HeaderReady for Service

Flushing/Blowing & ReinstallationFinal Box-up (V-209)Mechanical Completion (S-14-01)

Fill up Tank with Demineralized Water

Actual WorkRemaining WorkCritical Remaining Work

Milestone Project Overall Schedule

Page 11 of 15

Date Revision Checked Approved

03/03/14 ISSUED FOR MONTHLY PROGRESS REPORT H.S. LEE J.L. NABORS

Page 12: Project Schedule as of 03MAR2014 %28PDF Format%29 (2)

Activity Name Start Finish OD RD

Ready for Service 04/24/14 0 0Oily Water (S-16-01) 04/01/14 04/25/14 25 25Precommissioning 04/01/14 04/21/14 21 21Flushing/Blowing & Reinstallation 04/01/14 04/05/14 5 5Final Box-up (S-202) 04/06/14 04/06/14 1 1Loop Test 04/07/14 04/07/14 1 1Function Test (Inst.) 04/08/14 04/08/14 1 1Motor Uncoupled Run Test 04/13/14 04/13/14 1 1Fill up Sump with Service Water for Pump MRT 04/17/14 04/18/14 1 1Mechaniacl Running Test (P-205A/B) 04/19/14 04/19/14 1 1Mechaniacl Running Test (P-206) 04/20/14 04/20/14 1 1Leak Test (Service Test with Service Water) 04/19/14 04/21/14 3 3Mechanical Completion (S-16-01) 04/21/14 0 0

Commissioning 04/25/14 04/25/14 1 1Into Operation 04/25/14 04/25/14 1 1Ready for Service 04/25/14 0 0

Nitrogen Distribution (S-11-01) 04/16/14 06/03/14 49 49Precommissioning 04/16/14 04/22/14 7 7Flushing/Blowing & Reinstallation 04/16/14 04/20/14 5 5Leak Test 04/21/14 04/21/14 1 1Loop Test 04/22/14 04/22/14 1 1Mechanical Completion (S-11-01) 04/22/14 0 0

Commissioning 06/01/14 06/03/14 3 3Inerting 06/01/14 06/01/14 1 1Ready for Service 06/01/14 0 0N2 Service for System Inerting 06/03/14 0 0

Gas Compressor Inlet (S-02-01) 05/06/14 07/06/14 62 62Precommissioning 05/06/14 05/24/14 19 19Flushing/Blowing & Reinstallation 05/06/14 05/13/14 8 8Final Box-up (S-201A/B/C, F-201A/B/C) 05/14/14 05/15/14 2 2Leak Test 05/18/14 05/22/14 5 5Loop Test 05/23/14 05/23/14 1 1Function Test (Inst.) 05/24/14 05/24/14 1 1Mechanical Completion (S-02-01) 05/24/14 0 0

Commissioning 06/01/14 07/06/14 36 36Inerting 06/01/14 06/05/14 5 5Introduction of Naural Gas 07/04/14 07/06/14 3 3Ready for Start-up 07/06/14 0 0

Fuel Gas System (S-03-01) 04/01/14 07/06/14 97 97Precommissioning 04/01/14 05/20/14 50 50Flushing/Blowing & Reinstallation 04/01/14 04/07/14 7 7Final Box-up (V-203, H-201) 04/08/14 04/08/14 1 1Leak Test 05/18/14 05/18/14 1 1Loop Test 05/19/14 05/19/14 1 1Function Test (Inst.) 05/20/14 05/20/14 1 1Mechanical Completion (S-03-01) 05/20/14 0 0

Commissioning 06/01/14 07/06/14 36 36Inerting 06/01/14 06/05/14 5 5Introduction of Naural Gas 07/04/14 07/06/14 3 3Ready for Service 07/06/14 0 0

Gas Compressor 0utlet (S-05-01) 04/12/14 07/06/14 86 86Precommissioning 04/12/14 05/24/14 43 43Flushing/Blowing & Reinstallation 05/06/14 05/13/14 8 8Leak Test 05/18/14 05/22/14 5 5Loop Test 05/23/14 05/23/14 1 1

17 18 19 20 21 22 23 24Mar Apr May Jun Jul Aug Sep Oct

2014

Ready for Service

Flushing/Blowing & ReinstallationFinal Box-up (S-202)Loop TestFunction Test (Inst.)

Motor Uncoupled Run TestFill up Sump with Service Water for Pump MRTMechaniacl Running Test (P-205A/B)Mechaniacl Running Test (P-206)Leak Test (Service Test with Service Water)Mechanical Completion (S-16-01)

Into OperationReady for Service

Flushing/Blowing & ReinstallationLeak TestLoop TestMechanical Completion (S-11-01)

InertingReady for Service

N2 Service for System Inerting

Flushing/Blowing & ReinstallationFinal Box-up (S-201A/B/C, F-201A/B/C)

Leak TestLoop TestFunction Test (Inst.)Mechanical Completion (S-02-01)

InertingIntroduction of Naural GasReady for Start-up

Flushing/Blowing & ReinstallationFinal Box-up (V-203, H-201)

Leak TestLoop TestFunction Test (Inst.)Mechanical Completion (S-03-01)

InertingIntroduction of Naural GasReady for Service

Flushing/Blowing & ReinstallationLeak TestLoop Test

Actual WorkRemaining WorkCritical Remaining Work

Milestone Project Overall Schedule

Page 12 of 15

Date Revision Checked Approved

03/03/14 ISSUED FOR MONTHLY PROGRESS REPORT H.S. LEE J.L. NABORS

Page 13: Project Schedule as of 03MAR2014 %28PDF Format%29 (2)

Activity Name Start Finish OD RD

Function Test (Inst.) 05/24/14 05/24/14 1 1Complete Motor Uncoupled Run Test 04/12/14 04/13/14 2 2Mechaniacl Running Test (A-201) 04/14/14 04/15/14 2 2Mechanical Completion (S-05-01) 05/24/14 0 0

Commissioning 06/01/14 07/06/14 36 36Inerting 06/01/14 06/05/14 5 5Introduction of Naural Gas 07/04/14 07/06/14 3 3Ready for Start-up 07/06/14 0 0

Seal Gas (S-06-01) 04/01/14 07/06/14 97 97Precommissioning 04/01/14 05/20/14 50 50Flushing/Blowing & Reinstallation 04/01/14 04/07/14 7 7Final Box-up (F-202A/B) 04/08/14 04/08/14 1 1Leak Test 05/18/14 05/18/14 1 1Loop Test 05/19/14 05/19/14 1 1Function Test (Inst.) 05/20/14 05/20/14 1 1Mechanical Completion (S-06-01) 05/20/14 0 0

Commissioning 06/01/14 07/06/14 36 36Inerting 06/01/14 06/05/14 5 5Introduction of Naural Gas 07/04/14 07/06/14 3 3Ready for Service 07/06/14 0 0

Condensate Drain (S-08-01) 04/16/14 06/05/14 51 51Precommissioning 04/16/14 04/23/14 8 8Flushing/Blowing & Reinstallation 04/16/14 04/20/14 5 5Final Box-up (V-201) 04/21/14 04/21/14 1 1Leak Test 04/22/14 04/22/14 1 1Loop Test 04/23/14 04/23/14 1 1Mechanical Completion (S-08-01) 04/23/14 0 0

Commissioning 06/01/14 06/05/14 5 5Inerting 06/01/14 06/05/14 5 5Ready for Operation 06/05/14 0 0

Gas Venting (S-07-01) 04/16/14 06/06/14 52 52Precommissioning 04/16/14 04/22/14 7 7Flushing/Blowing & Reinstallation 04/16/14 04/20/14 5 5Leak Test 04/21/14 04/21/14 1 1Loop Test 04/22/14 04/22/14 1 1Mechanical Completion (S-07-01) 04/22/14 0 0

Commissioning 06/01/14 06/06/14 6 6Inerting 06/01/14 06/05/14 5 5N2 Service to Vent Header 06/06/14 06/06/14 1 1Ready for Operation 06/06/14 0 0

Natural Gas Compression C-201A (S-04-01) 04/05/14 07/14/14 101 101Precommissioning 04/05/14 05/31/14 57 57Flushing/Blowing & Reinstallation 05/14/14 05/17/14 4 4Leak Test 05/18/14 05/24/14 7 7Loop Test 05/25/14 05/29/14 5 5Function Test (Inst.) 05/30/14 05/31/14 2 2Compressor Package - I&C Precommissioning & Calbration 04/05/14 04/29/14 25 25Compressor Package - Loop Check Remote Control Console 04/30/14 05/01/14 2 2Compressor Package - Soft Ware Loading (HMI TT4000) 05/01/14 05/01/14 1 1Compressor Package - Final Alignment 04/30/14 05/02/14 3 3Mechanical Completion (S-04-01) 05/31/14 0 0

Commissioning 06/01/14 07/14/14 44 44Inerting 06/01/14 06/05/14 5 5Introduction of Naural Gas 07/04/14 07/06/14 3 3

17 18 19 20 21 22 23 24Mar Apr May Jun Jul Aug Sep Oct

2014

Function Test (Inst.)Complete Motor Uncoupled Run Test

Mechaniacl Running Test (A-201)Mechanical Completion (S-05-01)

InertingIntroduction of Naural GasReady for Start-up

Flushing/Blowing & ReinstallationFinal Box-up (F-202A/B)

Leak TestLoop TestFunction Test (Inst.)Mechanical Completion (S-06-01)

InertingIntroduction of Naural GasReady for Service

Flushing/Blowing & ReinstallationFinal Box-up (V-201)Leak TestLoop TestMechanical Completion (S-08-01)

InertingReady for Operation

Flushing/Blowing & ReinstallationLeak TestLoop TestMechanical Completion (S-07-01)

InertingN2 Service to Vent HeaderReady for Operation

Flushing/Blowing & ReinstallationLeak Test

Loop TestFunction Test (Inst.)

Compressor Package - I&C Precommissioning & CalbrationCompressor Package - Loop Check Remote Control ConsoleCompressor Package - Soft Ware Loading (HMI TT4000)Compressor Package - Final Alignment

Mechanical Completion (S-04-01)

InertingIntroduction of Naural Gas

Actual WorkRemaining WorkCritical Remaining Work

Milestone Project Overall Schedule

Page 13 of 15

Date Revision Checked Approved

03/03/14 ISSUED FOR MONTHLY PROGRESS REPORT H.S. LEE J.L. NABORS

Page 14: Project Schedule as of 03MAR2014 %28PDF Format%29 (2)

Activity Name Start Finish OD RD

First Crank 07/04/14 07/05/14 2 2Engine wash & Ignition Test 07/07/14 07/08/14 2 2Back-up Overspeed System Test 07/09/14 07/09/14 1 1On-line Operation Check 07/10/14 07/12/14 3 3Engine Performance 07/12/14 07/14/14 3 3

Natural Gas Compression C-201B (S-04-02) 04/05/14 07/19/14 106 106Precommissioning 04/05/14 05/31/14 57 57Flushing/Blowing & Reinstallation 05/14/14 05/17/14 4 4Leak Test 05/18/14 05/24/14 7 7Loop Test 05/25/14 05/29/14 5 5Function Test (Inst.) 05/30/14 05/31/14 2 2Compressor Package - I&C Precommissioning & Calbration 04/05/14 04/29/14 25 25Compressor Package - Loop Check Remote Control Console 04/30/14 05/01/14 2 2Compressor Package - Soft Ware Loading (HMI TT4000) 05/01/14 05/01/14 1 1Compressor Package - Final Alignment 04/30/14 05/02/14 3 3Mechanical Completion (S-04-02) 05/31/14 0 0

Commissioning 06/01/14 07/19/14 49 49Inerting 06/01/14 06/05/14 5 5Introduction of Naural Gas 07/04/14 07/06/14 3 3First Crank 07/04/14 07/05/14 2 2Engine wash & Ignition Test 07/09/14 07/10/14 2 2Back-up Overspeed System Test 07/11/14 07/11/14 1 1On-line Operation Check 07/15/14 07/17/14 3 3Engine Performance 07/17/14 07/19/14 3 3

Natural Gas Compression C-201C (S-04-03) 04/05/14 07/24/14 111 111Precommissioning 04/05/14 05/31/14 57 57Flushing/Blowing & Reinstallation 05/14/14 05/17/14 4 4Leak Test 05/18/14 05/24/14 7 7Loop Test 05/25/14 05/29/14 5 5Function Test (Inst.) 05/30/14 05/31/14 2 2Compressor Package - I&C Precommissioning & Calbration 04/05/14 04/29/14 25 25Compressor Package - Loop Check Remote Control Console 04/30/14 05/01/14 2 2Compressor Package - Soft Ware Loading (HMI TT4000) 05/01/14 05/01/14 1 1Compressor Package - Final Alignment 04/30/14 05/02/14 3 3Mechanical Completion (S-04-03) 05/31/14 0 0

Commissioning 06/01/14 07/24/14 54 54Inerting 06/01/14 06/05/14 5 5Introduction of Naural Gas 07/04/14 07/06/14 3 3First Crank 07/04/14 07/05/14 2 2Engine wash & Ignition Test 07/11/14 07/12/14 2 2Back-up Overspeed System Test 07/13/14 07/13/14 1 1On-line Operation Check 07/20/14 07/22/14 3 3Engine Performance 07/22/14 07/24/14 3 3

Natural Gas Compression C-201D (S-04-04) 04/05/14 07/29/14 116 116Precommissioning 04/05/14 05/31/14 57 57Flushing/Blowing & Reinstallation 05/14/14 05/17/14 4 4Leak Test 05/18/14 05/24/14 7 7Loop Test 05/25/14 05/29/14 5 5Function Test (Inst.) 05/30/14 05/31/14 2 2Compressor Package - I&C Precommissioning & Calbration 04/05/14 04/29/14 25 25Compressor Package - Loop Check Remote Control Console 04/30/14 05/01/14 2 2Compressor Package - Soft Ware Loading (HMI TT4000) 05/01/14 05/01/14 1 1Compressor Package - Final Alignment 04/30/14 05/02/14 3 3Mechanical Completion (S-04-04) 05/31/14 0 0

17 18 19 20 21 22 23 24Mar Apr May Jun Jul Aug Sep Oct

2014

First CrankEngine wash & Ignition TestBack-up Overspeed System Test

On-line Operation CheckEngine Performance

Flushing/Blowing & ReinstallationLeak Test

Loop TestFunction Test (Inst.)

Compressor Package - I&C Precommissioning & CalbrationCompressor Package - Loop Check Remote Control ConsoleCompressor Package - Soft Ware Loading (HMI TT4000)Compressor Package - Final Alignment

Mechanical Completion (S-04-02)

InertingIntroduction of Naural GasFirst Crank

Engine wash & Ignition TestBack-up Overspeed System Test

On-line Operation CheckEngine Performance

Flushing/Blowing & ReinstallationLeak Test

Loop TestFunction Test (Inst.)

Compressor Package - I&C Precommissioning & CalbrationCompressor Package - Loop Check Remote Control ConsoleCompressor Package - Soft Ware Loading (HMI TT4000)Compressor Package - Final Alignment

Mechanical Completion (S-04-03)

InertingIntroduction of Naural GasFirst Crank

Engine wash & Ignition TestBack-up Overspeed System Test

On-line Operation CheckEngine Performance

Flushing/Blowing & ReinstallationLeak Test

Loop TestFunction Test (Inst.)

Compressor Package - I&C Precommissioning & CalbrationCompressor Package - Loop Check Remote Control ConsoleCompressor Package - Soft Ware Loading (HMI TT4000)Compressor Package - Final Alignment

Mechanical Completion (S-04-04)

Actual WorkRemaining WorkCritical Remaining Work

Milestone Project Overall Schedule

Page 14 of 15

Date Revision Checked Approved

03/03/14 ISSUED FOR MONTHLY PROGRESS REPORT H.S. LEE J.L. NABORS

Page 15: Project Schedule as of 03MAR2014 %28PDF Format%29 (2)

Activity Name Start Finish OD RD

Commissioning 06/01/14 07/29/14 59 59Inerting 06/01/14 06/05/14 5 5Introduction of Naural Gas 07/04/14 07/06/14 3 3First Crank 07/04/14 07/05/14 2 2Engine wash & Ignition Test 07/13/14 07/14/14 2 2Back-up Overspeed System Test 07/15/14 07/15/14 1 1On-line Operation Check 07/25/14 07/27/14 3 3Engine Performance 07/27/14 07/29/14 3 3

Plant Performance Test 07/30/14 08/05/14 7 7Plant Performance Test 07/30/14 08/05/14 7 7Plant Performance and Reliability Test 07/30/14 08/05/14 7 7

17 18 19 20 21 22 23 24Mar Apr May Jun Jul Aug Sep Oct

2014

InertingIntroduction of Naural GasFirst Crank

Engine wash & Ignition TestBack-up Overspeed System Test

On-line Operation CheckEngine Performance

Plant Performance and Reliability Test

Actual WorkRemaining WorkCritical Remaining Work

Milestone Project Overall Schedule

Page 15 of 15

Date Revision Checked Approved

03/03/14 ISSUED FOR MONTHLY PROGRESS REPORT H.S. LEE J.L. NABORS


Recommended