page 1 of 2 MEETING SUMMARY PURPOSE Project Status Review Meeting #48 DATE Wednesday, February 9, 2011 TIME 11:00AM – 12:30PM LOCATION 219 HB PARTICIPANTS Dave Tamm, Dale Bradley, Quentin Johnson, Maria Rose, Andy Raisovich, Steve Shala, Evie Brantmayer, Dan Gockley, Shane Jordan, Lynne Shala and Peter Wilkins. SUMMARY OF MAJOR PROJECTS Peter reviewed the items that were distributed to attendees with the meeting handout package. The Project Summary Report (Dashboard) shows seven projects, with one reporting completion, three progressing according to plan, two experiencing delay, and one placed onhold. The group also browsed the Major Project Summary Gantt Chart, and noted the progress of activities against the baseline schedules for all the projects. PROJECT STATUS REPORT UPDATES Automated Decision Rules – Evie reported progress continuing on rules programming and testing, while work still needs to be done on the residency check. She said report needs have been identified but programming reports have not started, and communication plan testing identified unforeseen issues in original rules forcing some rule redefinition. This is causing delay in timeline due to additional work that needs to be done. Adjustments have been made to the project timeline delaying estimated completion until May 2 nd . Housing Information System – Dan reported that weekly project meetings have been ongoing, and all documents for the completion of Stage 2 have been submitted with one exception. An addendum to the original contact must be issued in order to develop a custom link to the WVSTO for credit card payments in StarRez. Stage 3 has begun and remains on target for our March 18, 2011 deadline. The custom development of the online payment interface with the WVSTO may require a schedule modification. StarRez is committed to maintaining the original project schedule if possible. Content Management System – Upgrade to 6.x – Shane stated that the project was completed on December 19 th with a successful upgrade to Drupal 6.x. He said the web site has been separated into smaller sites,
Transcript
Page 1: Project Status Review Meeting - SUMMARY · 2018-03-14 · 16 Mail RFP to potential vendors Mon 3/22/10 Mon 3/22/10 ... 19 Issue purchase order for software Mon 5/31/10 Mon 7/26/10

page 1 of 2

MEETING SUMMARY  

PURPOSE  Project Status Review Meeting #48 

DATE  Wednesday, February 9, 2011 

TIME  11:00AM – 12:30PM 

LOCATION  219 HB 

PARTICIPANTS  Dave  Tamm, Dale Bradley, Quentin  Johnson, Maria Rose, Andy Raisovich, Steve Shala, Evie Brantmayer, Dan Gockley, Shane Jordan, Lynne Shala and Peter Wilkins. 

SUMMARY OF MAJOR PROJECTS 

Peter  reviewed  the  items  that  were  distributed  to  attendees  with  the meeting  handout  package.    The  Project  Summary  Report  (Dashboard) shows  seven  projects,  with  one  reporting  completion,  three  progressing according  to  plan,  two  experiencing  delay,  and  one  placed  on‐hold.    The group also browsed the Major Project Summary Gantt Chart, and noted the progress of activities against the baseline schedules for all the projects. 

PROJECT STATUS REPORT UPDATES 

Automated  Decision  Rules  –  Evie  reported  progress  continuing  on  rules programming  and  testing,  while  work  still  needs  to  be  done  on  the residency  check.    She  said  report  needs  have  been  identified  but programming  reports  have  not  started,  and  communication  plan  testing identified unforeseen issues in original rules forcing some rule redefinition.  This  is  causing delay  in  timeline due  to  additional work  that needs  to be done.    Adjustments  have  been  made  to  the  project  timeline  delaying estimated completion until May 2nd. 

Housing Information System – Dan reported that weekly project meetings have been ongoing, and all documents for the completion of Stage 2 have been submitted with one exception.   An addendum to the original contact must be  issued  in order  to develop a custom  link to the WVSTO  for credit card payments in StarRez.  Stage 3 has begun and remains on target for our March 18, 2011 deadline.  The custom development of the on‐line payment interface with the WVSTO may require a schedule modification.   StarRez  is committed to maintaining the original project schedule if possible. 

Content Management  System  – Upgrade  to  6.x  –  Shane  stated  that  the project  was  completed  on  December  19th  with  a  successful  upgrade  to Drupal  6.x.    He  said  the web  site  has  been  separated  into  smaller  sites, 

Page 2: Project Status Review Meeting - SUMMARY · 2018-03-14 · 16 Mail RFP to potential vendors Mon 3/22/10 Mon 3/22/10 ... 19 Issue purchase order for software Mon 5/31/10 Mon 7/26/10

page 2 of 2

making them much more manageable and easier for users to maintain. 

Admissions Workflow  Implementation  – Andy  reported  that  this  project remains ON‐HOLD, with reactivation anticipated in mid‐April under Quentin Johnson’s sponsorship. 

Modular Course  Integration Study – Peter reported the study team’s final deliverable,  summarizing  implementation  actions  and  options,  was completed  and  reported  to  the  Project  Sponsor  on  November  18th.    He added  that  overall  project  completion  is  pending,  and  has  been  delayed from the original estimate. 

Online  Application  for  Graduate  Programs  –  Lynne  reported  several meetings with  Enrollment  Services  to  review  and  test  information  being pushed  from application  into Banner  system  to accelerate  the Enrollment graduate  application process.   Development of  application  fee processing was  completed, and we plan  to move  it  into production after  testing and approval.  A demo has been scheduled with Van Dempsey and the Graduate Programs  Committee  to  review  the  online  application  process.   We  will continue to meet with stakeholders to attempt to fast‐track completion of the application  status  report  to coincide with  the February 28th estimated completion date for the project. 

CampusEAI myCampus Implementation – Andy reported that the discovery document was received and confirmed by CampusEAI.   The VM  instance  is up and available, VPN/networking setup  is complete, and  internal systems are reachable via the tunnel.  Basic color scheme and portal layout has been submitted  to  CampusEAI.    Basic  portal  roles  have  been  defined,  and scripting for establishing those in the Active Directory is underway.  Pending testing  this  week,  we  are  on  track  and  ready  to  continue  into  pre‐production/launch tasks. 

PENDING PROJECT PORTFOLIO REVIEW 

 

Peter  reviewed  the  portfolio  of  pending  projects,  and  mentioned  the addition of WIMBA Classroom Implementation to the list.  Dave stated that a charter is expected within 2‐3 weeks. 

Dave  explained  that  Blackboard  hosting  services  were  to  transfer  to WVNET,  and  stated  that  a  project  describing  the  transition,  and incorporating XIV for Disaster Recovery, would be chartered within the next 1‐2 weeks. 

NEW BUSINESS  None. 

NEXT MEETING  Date:         Wednesday, March 30, 2011 Time:         11:00AM – 12:30PM Location:   219 HB 

 

Page 3: Project Status Review Meeting - SUMMARY · 2018-03-14 · 16 Mail RFP to potential vendors Mon 3/22/10 Mon 3/22/10 ... 19 Issue purchase order for software Mon 5/31/10 Mon 7/26/10

MEETING AGENDA Subject: Project Status Review #48 Date: Wednesday, February 9, 2011 Time: 11:00AM – 12:30PM Location: 219 HB Project Summary Report:

• Project Dashboard • Summary Gantt Chart

Project Status Reports: • Automated Decision Rules • Housing Information System • Content Management System - Upgrade to 6.x • Admissions Workflow Implementation • Modular Course Integration Study • Online Application for Graduate Programs • CampusEAI myCampus Implementation

Pending Project Portfolio Review: • Virtualization of Phone System • Recruiter Goals and Tracking • VMS Platform Retirement-Phase 2 • Blackboard - Vista to Learn 9.1 Upgrade • Enterprise Data Warehouse and Operational Data Store Implementation • IT Procurement Process Automation • Web-based Classroom Scheduling • Online Application for Competitive Programs • XIV for Disaster Recovery • Acceluraid Refunds • WIMBA Classroom Implementation

New Business Schedule Next Meeting Adjourn

Page 1

Page 4: Project Status Review Meeting - SUMMARY · 2018-03-14 · 16 Mail RFP to potential vendors Mon 3/22/10 Mon 3/22/10 ... 19 Issue purchase order for software Mon 5/31/10 Mon 7/26/10

Estimate Actual

Automated Decision Rules 091103‐01 Quentin Johnson Evie Brantmayer ACTIVE Nov‐09 Nov‐09 May‐11

Housing Information System 100115‐01 Quentin Johnson Dan Gockley ACTIVE Feb‐10 Feb‐10 Apr‐11

Content Management System ‐ Upgrade to 6.x 100603‐01Dave Tamm              Devanna Corley

Shane Jordan COMPLETE Jun‐10 Jun‐10 Dec‐10

PROJECT SUMMARY REPORTApproval Date

Project Name StatusProject Identifier

Project StatusProject Sponsor Project ManagerCompletion Date

Start Date

y

Admissions Workflow Implementation 100623‐01 Dave Tamm Andy Raisovich ON‐HOLD May‐10 Jun‐10 TBD

Modular Course Integration Study 100722‐01 Doreen Larson Peter Wilkins ACTIVE Jul‐10 Jul‐10 Feb‐11

Online Application for Graduate Programs 100728‐01 Quentin Johnson Lynne Shala ACTIVE Jul‐10 Jul‐10 Feb‐11

Campus EAI myCampus Implementation 101130‐01 Dave Tamm Andy Raisovich ACTIVE Nov‐10 Nov‐10 Sep‐11

Page 2

Page 5: Project Status Review Meeting - SUMMARY · 2018-03-14 · 16 Mail RFP to potential vendors Mon 3/22/10 Mon 3/22/10 ... 19 Issue purchase order for software Mon 5/31/10 Mon 7/26/10

ID Task Name Start Finish

1 Automated Decision Rules Tue 11/3/09 Mon 5/2/112 Project Start Tue 11/3/09 Tue 11/3/093 Create design specs for the process that will load decision codes Tue 11/3/09 Fri 11/20/094 Determine reporting needs for the process that will load decision Tue 11/3/09 Fri 11/20/095 Communicate design specs and reporting needs to IT Fri 11/20/09 Fri 11/20/096 Refine reporting needs for the process that will load decision code Mon 11/1/10 Fri 11/19/107 IT Development (Initial Scope) Mon 11/23/09 Tue 12/22/098 IT Development (Expanded Scope) Mon 2/15/10 Mon 2/28/119 Testing Mon 8/30/10 Thu 3/31/11

10 Redo procedures Mon 4/4/11 Fri 4/15/1111 Conduct Training Mon 4/18/11 Fri 4/29/1112 Implement Mon 5/2/11 Mon 5/2/111314 Housing Information System Mon 2/1/10 Thu 4/14/1115 Develop RFP for Housing software Mon 2/1/10 Mon 3/8/1016 Mail RFP to potential vendors Mon 3/22/10 Mon 3/22/1017 Review RFP documents Wed 4/28/10 Wed 5/19/1018 Oral Presentations by Candidate Vendors Tue 5/18/10 Wed 5/19/1019 Issue purchase order for software Mon 5/31/10 Mon 7/26/1020 StarRez Implementation Project Tue 7/27/10 Thu 4/14/1121 Project initiation activities Tue 7/27/10 Thu 9/23/1022 Project Kick-off Fri 9/24/10 Fri 9/24/1023 Stage 1-Pre-Installation Planning & Standard Solution Setup Mon 9/27/10 Fri 11/5/1024 Stage 2-On-Site Introduction Training & RFI Review through Mon 11/8/10 Fri 1/21/1125 Stage 3- Development, Data Conversion & Configuration Mon 2/7/11 Fri 3/18/1126 Stage 4-Testing & Fine Tuning of Configuration, StarRez-Po Mon 3/21/11 Mon 4/11/1127 Stage 5-On-Site Training Refresher & Go-Live Tue 4/12/11 Thu 4/14/112829 Content Management System - Upgrade to 6.x Tue 6/1/10 Sun 12/19/1030 Project Start Tue 6/1/10 Tue 6/1/1031 Solicit Web Tester suggestions for upgrade Tue 6/1/10 Tue 6/1/1032 Identify Business Units and responsible parties Tue 6/1/10 Wed 6/16/1033 Separate the web site into micro sites Mon 6/7/10 Wed 12/15/1034 Upgrade micro-sites from Drupal 5.x to Drupal 6.x Mon 6/7/10 Wed 12/15/1035 Train users on Drupal 6.x Fri 8/6/10 Wed 12/15/1036 Enhance micro-sites with new features Mon 11/1/10 Tue 11/30/1037 Pierpont rebranding redesign Mon 8/2/10 Fri 12/3/1038 Rebranding of the Pierpont website Mon 8/2/10 Sun 12/19/1039 Program Completion Sun 12/19/10 Sun 12/19/104041 Admissions Workflow Implementation Fri 5/7/10 Mon 10/18/1042 User and role definitions Fri 5/7/10 Fri 5/7/1043 Workflow definitions, paper Fri 5/7/10 Fri 5/14/1044 Document management research, technical Thu 7/1/10 Tue 8/17/1045 Event definition, technical Mon 10/18/10 Mon 10/18/10

Oct NovDec Jan e Mar Apr MayJun Jul AugSep Oct NovDec Jan e Mar Apr MayJun Jul AugSep OctQtr 4, 2009 Qtr 1, 2010 Qtr 2, 2010 Qtr 3, 2010 Qtr 4, 2010 Qtr 1, 2011 Qtr 2, 2011 Qtr 3, 2011 Qtr

Task

Progress

Baseline

Milestone

Baseline Milestone

Summary

Rolled Up Task

Rolled Up Milestone

Baseline Summary

Rolled Up Baseline

Rolled Up Baseline Milestone

Rolled Up ProgTask

Progress

Baseline

Milestone

Baseline Milestone

Summary

Rolled Up Task

Project: Major Project OverviewDate: Tue 2/8/11Page 1

Page 3

Page 6: Project Status Review Meeting - SUMMARY · 2018-03-14 · 16 Mail RFP to potential vendors Mon 3/22/10 Mon 3/22/10 ... 19 Issue purchase order for software Mon 5/31/10 Mon 7/26/10

ID Task Name Start Finish

46 Event programming Mon 10/18/10 Mon 10/18/1047 Testing Mon 10/18/10 Mon 10/18/1048 Security profile definitions (Application Xtender in Banner) Mon 10/18/10 Mon 10/18/1049 Updated process flow documentation, including scanning and han Mon 10/18/10 Mon 10/18/1050 Post-testing code revisions and cleanup Mon 10/18/10 Mon 10/18/1051 Meet with Deans and train faculty and non-Enrollment Services s Mon 10/18/10 Mon 10/18/1052 Enrollment Services staff training Mon 10/18/10 Mon 10/18/1053 Production deployment Mon 10/18/10 Mon 10/18/105455 Modular Course Integration Study Thu 7/15/10 Mon 2/28/1156 Develop project scope and approach Thu 7/15/10 Fri 7/23/1057 Approved Project Charter Fri 7/23/10 Fri 7/23/1058 Assess Open Learning Capabilities Thu 7/15/10 Fri 10/8/1059 Assess Issues and Opportunities Thu 7/15/10 Fri 10/1/1060 Perform Gap Analysis Fri 10/1/10 Mon 11/1/1061 Create Solution Study Report Wed 10/13/10 Thu 11/18/1062 Modular Course Integration Scope and Approach Fri 11/19/10 Mon 2/28/116364 Online Application for Graduate Programs Wed 7/28/10 Mon 2/28/1165 Create list of needed application types Wed 7/28/10 Fri 7/30/1066 Research Communication Plan Wed 7/28/10 Fri 8/13/1067 Create Communication Plan Mon 8/16/10 Tue 11/30/1068 Research Checklist items Wed 7/28/10 Fri 8/13/1069 Create Checklist Items Mon 8/16/10 Mon 10/18/1070 Identify blocks and questions for each application type Wed 8/11/10 Mon 11/8/1071 Develop Decision Tree design Wed 8/11/10 Tue 9/14/1072 Develop Decision tree program Mon 11/8/10 Mon 12/6/1073 Check point to review progress of Decision tree design, blocks an Tue 9/14/10 Tue 9/14/1074 Check point to review progress and update project baseline sche Mon 10/18/10 Mon 10/18/1075 Check point to review progress and project baseline schedule Tue 11/30/10 Tue 11/30/1076 Check point to review progress of Decision tree design, applicatio Tue 12/14/10 Tue 12/14/1077 Check point to review progress of application program, workflow, Thu 1/6/11 Thu 1/6/1178 Check point to review progress before for testing Fri 1/28/11 Fri 1/28/1179 Create Workflow for automated emails Mon 11/15/10 Wed 12/15/1080 Develop Graduate Online Application Prototype Mon 11/8/10 Mon 12/6/1081 Develop Application programs Mon 12/6/10 Mon 1/17/1182 Develop Application Fee Processing Mon 12/6/10 Fri 2/11/1183 Prepare environment for testing decision tree, applications, suppo Mon 1/17/11 Fri 1/28/1184 Test decision tree, applications, supporting code, reports and fee Mon 1/31/11 Fri 2/18/1185 Finalize updates to decision tree, application, supporting code, re Fri 2/4/11 Fri 2/18/1186 Roll application to Production Mon 2/21/11 Mon 2/28/1187 Develop application status report Tue 2/8/11 Mon 2/28/118889 Campus EAI myCampus Implementation Wed 11/3/10 Fri 9/30/1190 General release Wed 11/3/10 Sun 6/5/1191 Transition to maintenance Mon 6/6/11 Fri 9/30/11

Oct NovDec Jan e Mar Apr MayJun Jul AugSep Oct NovDec Jan e Mar Apr MayJun Jul AugSep OctQtr 4, 2009 Qtr 1, 2010 Qtr 2, 2010 Qtr 3, 2010 Qtr 4, 2010 Qtr 1, 2011 Qtr 2, 2011 Qtr 3, 2011 Qtr

Task

Progress

Baseline

Milestone

Baseline Milestone

Summary

Rolled Up Task

Rolled Up Milestone

Baseline Summary

Rolled Up Baseline

Rolled Up Baseline Milestone

Rolled Up ProgTask

Progress

Baseline

Milestone

Baseline Milestone

Summary

Rolled Up Task

Project: Major Project OverviewDate: Tue 2/8/11Page 2

Page 4

Page 7: Project Status Review Meeting - SUMMARY · 2018-03-14 · 16 Mail RFP to potential vendors Mon 3/22/10 Mon 3/22/10 ... 19 Issue purchase order for software Mon 5/31/10 Mon 7/26/10

PROJECT STATUS REPORT    

Project ID  091103‐01  Date  2/8/11 

Project Name  Automated Decision Rules 

Project Description 

To design a process that will assign the appropriate decision code to applicants in Banner and produce specified reports. 

Project Sponsor  Quentin Johnson 

Project Manager  Evie Brantmayer 

Progress and Accomplishments 

 Progress  continues  on  rules  programming  and  testing.  Work  has  begun  on  communication  plan  development.  Work still needs to be done on the residency check. Report needs have been  identified but programming  reports have not started. 

Schedule Variances 

 Communication plan testing  identified unforeseen  issues  in original rules forcing some rule redefinition.   

Issues or Risks 

 Rule  redefinition  is  causing  delay  in  timeline  due  to additional work that needs to be done. 

Project Outlook (Estimate To Complete) 

Project is not on schedule and adjustments in time line have been made. 

 

Page 5

Page 8: Project Status Review Meeting - SUMMARY · 2018-03-14 · 16 Mail RFP to potential vendors Mon 3/22/10 Mon 3/22/10 ... 19 Issue purchase order for software Mon 5/31/10 Mon 7/26/10

PROJECT STATUS REPORT   

Project ID  100115‐01  Date  2/8/11 

Project Name  Housing Information System 

Project Description 

Implement StarRez, a housing information system. 

Project Sponsor  Quentin  Johnson 

Project Manager  Dan Gockley 

Progress and Accomplishments 

 Weekly project meetings have been ongoing.   All documents for the  completion  of  Stage  2  have  been  submitted  with  one exception.   An addendum to the original contact must be  issued in order  to develop a custom  link  to  the WVSTO  for credit card payments  in StarRez.   Stage 3 has begun and  remains on  target for our March 18, 2011 deadline.  Within  the  test  environment,  room  configurations  have  been built  and  sample  student  data  has  been  uploaded.    StarRez  is uploading  account  information  which  will  allow  us  to  begin testing the system. 

Schedule Variances 

None. 

Issues or Risks 

 The custom development of  the on‐line payment  interface with the WVSTO may require a schedule modification.  The paperwork for  the  addendum was  recently  submitted  to  the  Procurement Office.    The  contracts  must  be  completed  in  order  for  the schedule to be developed.   StarRez  is committed to maintaining the original project schedule if possible. 

Project Outlook (Estimate To Complete) 

Good. 

 

Page 6

Page 9: Project Status Review Meeting - SUMMARY · 2018-03-14 · 16 Mail RFP to potential vendors Mon 3/22/10 Mon 3/22/10 ... 19 Issue purchase order for software Mon 5/31/10 Mon 7/26/10

PROJECT STATUS REPORT   

Project ID  100603‐01  Date  2/8/11 

Project Name  Content Management System – Upgrade to 6.x 

Project Description 

This  project  represents  the  first major  upgrade  to  the  content management system.  This upgrade is needed to ensure that the content management  system  stays up‐to‐date with any  security issues and the newest technology available.   

Project Sponsor  Dave Tamm & Devanna Corley 

Project Manager  Shane Jordan 

Progress and Accomplishments 

This project has been completed on 12/19/2010 with a successful upgrade to Drupal 6.x.  The web site has been separated into smaller sites, making them much more manageable and easier for users to maintain. 

Schedule Variances 

The redesign of Pierpont’s web site has been removed from this project, and will be have a project charter created with Sarah Hensley as the project manager. 

Issues or Risks  None 

Project Outlook (Estimate To Complete) 

Completed Project on 12/19/2010 

 

Page 7

Page 10: Project Status Review Meeting - SUMMARY · 2018-03-14 · 16 Mail RFP to potential vendors Mon 3/22/10 Mon 3/22/10 ... 19 Issue purchase order for software Mon 5/31/10 Mon 7/26/10

PROJECT STATUS REPORT    

Project ID  100623‐01  Date  2/8/11 

Project Name  Admissions Workflow Implementation 

Project Description 

 To  implement  Banner  Workflow  for  Admissions,  integrate  the capture  and  handling  of  scanned  documents,  and  leverage  the software to help streamline the admissions‐to‐student process.  

Project Sponsor  Quentin Johnson 

Project Manager  Andy Raisovich 

Progress and Accomplishments 

Project placed ON‐HOLD as of 10/18/10. 

Schedule Variances 

 

Issues or Risks   

Project Outlook (Estimate To Complete) 

Reactivation estimated by mid‐April, 2011. 

 

Page 8

Page 11: Project Status Review Meeting - SUMMARY · 2018-03-14 · 16 Mail RFP to potential vendors Mon 3/22/10 Mon 3/22/10 ... 19 Issue purchase order for software Mon 5/31/10 Mon 7/26/10

PROJECT STATUS REPORT    Project ID  100722‐01  Date  2/8/11 

 Project Name  Modular Course Integration Study 

 Project Description 

 The purpose of this project  is to research and evaluate the capabilities of existing and  available  software,  such  as  the SunGard Open  Learning: Registration  solution  to  integrate and  or  supplement  Banner  and  other  automated functionality  for  administering  courses  in  flexible modules that are not tied to the semester system. 

 Project Sponsor 

 Doreen Larson 

 Project Manager 

 Peter Wilkins 

 Progress and Accomplishments 

 An  Opportunities  Assessment  was  completed  on  October 1st,  and  the  Open  Learning  Capability  Assessment completed on October 8th.  A gap analysis was compiled into a merged  Requirements  Analysis  document  on November 1st.  The project team subsequently identified potential areas for Banner configuration and Open Learning  set‐up; candidate areas  for minor  or major  system modification;  and  areas where  business  processes  would  need  to  be  created  or changed.    These  were  documented  in  an  Action  Matrix, which was completed on November 11th.    The  study  team’s  final  deliverable,  summarizing implementation  actions  and  options,  was  completed  and reported to the Project Sponsor on November 18th. 

 Schedule Variances 

 Overall project completion has been delayed. 

Page 9

Page 12: Project Status Review Meeting - SUMMARY · 2018-03-14 · 16 Mail RFP to potential vendors Mon 3/22/10 Mon 3/22/10 ... 19 Issue purchase order for software Mon 5/31/10 Mon 7/26/10

 Issues or Risks 

 The  final project deliverable documented alternative paths forward.    Due  to  the  strategic  nature  of  the  reported options,  Dr.  Larson  stated  that  she  would  convene  a meeting  of  senior  institutional  representatives  to  discuss them,  and  make  an  informed  decision.    Thereafter,  she would  communicate  approval  to  complete  or  additional requirements. 

 Project Outlook (Estimate To Complete) 

 Pending  the  Sponsor’s  approval,  the  project  team  has completed the deliverables identified in the charter.  Estimated completion has been revised to 2/28/11. 

 

Page 10

Page 13: Project Status Review Meeting - SUMMARY · 2018-03-14 · 16 Mail RFP to potential vendors Mon 3/22/10 Mon 3/22/10 ... 19 Issue purchase order for software Mon 5/31/10 Mon 7/26/10

PROJECT STATUS REPORT    Project ID 

100728‐01 Date 

2/8/11 

Project Name  Online Application for Graduate Programs 

Project Description 

Create the new graduate online application based on the current paper application. This will entail establishing: 

• Graduate students and admit‐types.  • Intended Degree Program and Concentrations as filter for 

graduate requirements for each program • Filter  process  to  provide  the  applicants  information  to 

the appropriate departments. • A communication plan for graduate students.  • Checklist items of required information for each graduate 

program • Workflow for automated emails • Application fee processing 

Project Sponsor  Quentin Johnson 

Project Manager  Lynne Shala 

Progress and Accomplishments 

 e met with  some members  of  Enrollment  Services  several  times  to 

review  and  test  application  to  ensure  information  is  pushed  from W

application  into Banner  system  to accelerate  the Enrollment graduate application process. Shane finished the development of application fee processing,  and we  plan  to move  it  into  production  after  testing  and approval.  We  scheduled  a  demo  with  Van  Dempsey  and  Graduate Programs  Committee  on  2/9/2011  to  review  the  online  application process.  We  are  continuing  to  test  the  application  with  Enrollment Services, finding minor issues and correcting them.  We plan to continue to test with Enrollment Services  in working sessions until all agree  it  is ready  for  production.  We  will  continue  to  meet  with  Enrollment Services  and Dr. Van Dempsey  to  attempt  to  fast‐track  completion of the  application  status  report  to  coincide  with  a  2/28/11  estimated completion date for the project. 

Schedule Variances 

Baseline  schedule  has  been  updated  from  original  Project  Charter. There was a  slight delay on  the application  fee processing due  to  the complexity and security of that process and resources being pulled onto other projects.  Development on this is complete, but we are waiting on final detail codes to be established, which can be plugged in quickly. 

Page 11

Page 14: Project Status Review Meeting - SUMMARY · 2018-03-14 · 16 Mail RFP to potential vendors Mon 3/22/10 Mon 3/22/10 ... 19 Issue purchase order for software Mon 5/31/10 Mon 7/26/10

Issues or Risks 

Because other projects are also scheduled  in the same timeframe with upcoming  scheduled  training,  vacations,  and  holidays,  the  time  of Enrollment Services as the subject matter experts and testers will be at a premium and  could affect project participants’ abilities  to meet  the deliverable  schedule.  If  this  is  necessary,  delays  may  occur  in  the timeline. 

We are discussing application status reporting options.  Once a delivery method  is  agreed  upon,  development  can  start;  however,  conflicting schedules may delay this discussion. 

Project Outlook (Estimate To Complete) 

The  latest version of the baseline schedule shows an estimated project completion in February 2011. Project Outlook is cautiously optimistic. 

 

Page 12

Page 15: Project Status Review Meeting - SUMMARY · 2018-03-14 · 16 Mail RFP to potential vendors Mon 3/22/10 Mon 3/22/10 ... 19 Issue purchase order for software Mon 5/31/10 Mon 7/26/10

PROJECT STATUS REPORT   

Project ID  101130‐01  Date  2/8/11 

Project Name  CampusEAI myCampus Implementation 

Project Description Implementation of a campus portal for Fairmont State University and Pierpont Community and Technical College. 

Project Sponsor  David Tamm 

Project Manager  Andy Raisovich 

Progress and Accomplishments 

 Discovery  document  was  received  and  confirmed  by CampusEAI.  VM instance is up and available.  VPN/networking  setup  is  complete,  and  internal  systems (Active Directory and Banner) are reachable via the tunnel.  DNS  CNAME  for  the  site  has  been  defined.    Thanks  to Systems and Networking for coordinating calls with Cisco to make this happen.  Live@EDU  (student  email)  certificates,  required  for  single sign‐on  (SSO)  to  this  service,  have  been  provided  to CampusEAI.  SSL certificates, necessary  for  the secure exchange of data between clients and the service, have been purchased and delivered to CampusEAI.  Basic color scheme and portal layout has been submitted to CampusEAI.   More  work  is  necessary  to  determine  what widgets and  features  should be displayed by default upon login.   Mock‐ups were presented at the 2/3/2011 meeting, and CampusEAI has  stated  that  their goal  is  to  implement the designs by 2/8/2011.  The first round of portal administration training occurred on 2/2/2011, with a showcase to occur this week, and further administration training (phase 2) to be determined.  Basic  portal  roles  have  been  defined,  and  scripting  for 

Page 13

Page 16: Project Status Review Meeting - SUMMARY · 2018-03-14 · 16 Mail RFP to potential vendors Mon 3/22/10 Mon 3/22/10 ... 19 Issue purchase order for software Mon 5/31/10 Mon 7/26/10

establishing those in the Active Directory is underway.  We are well underway and, pending  testing  this week, are ready to continue into pre‐production/launch tasks.  

Schedule Variances  None. 

Issues or Risks  None so far. 

Project Outlook (Estimate To Complete) 

Good. 

 

Page 14

Page 17: Project Status Review Meeting - SUMMARY · 2018-03-14 · 16 Mail RFP to potential vendors Mon 3/22/10 Mon 3/22/10 ... 19 Issue purchase order for software Mon 5/31/10 Mon 7/26/10

PROJECT OR INITIATIVE Sponsor Project Manager Target Timeframe

Expected Cost (Large, Medium, Small)

Scope of Work (Large, Medium, Small)

Probable Impact (High, Medium, Low)

Comments

Virtualization of Phone System Dave Tamm Steve ShalaThis project awaits Cisco's support decision and timeline.

Recruiter Goals and Tracking Quentin Johnson TBDExpected to be activated and completed in the near‐term.

VMS Platform Retirement‐Phase 2 Dave Tamm Andy Raisovich FY2011 InitiativeAndy informed the group that he is working on ways to emulate the platform and bring about a migration to mitigate the risk, and cost, of continuing to operate this outdated technology.

Blackboard ‐ Vista to Learn 9.1 Upgrade Dave Tamm Andy Raisovich

Enterprise Data Warehouse and Operational Data Store I l i

Dave Tamm Andy RaisovichDave described this project as a t t i i iti ti f 2010 11

PENDING PROJECT PORTFOLIO

ImplementationDave Tamm Andy Raisovich

strategic initiative for 2010‐11.

IT Procurement Process Automation Dave Tamm Joanie RaisovichDave mentioned an effort to streamline the process under the wing of the newly formed TLC (Teaching and Learning Commons).

Web‐based Classroom Scheduling Quentin Johnson Andy Raisovich Key link to year‐long registration and scheduling requirements.

Online Application for Competitive Programs Quentin Johnson Andy RaisovichShould be treated as a supplement to the online application, within FELiX, after we have gained some experience with the application and the Banner Workflow product.

XIV for Disaster Recovery Dave Tamm Steve Shala

Acceluraid Refunds Rick Porto Neil Tennant March‐April, 2011 Debit card refunding of financial aid.

WIMBA Classroom Implementation Dave Tamm Joanie RaisovichProject Charter and Kick‐off expected by March, 2011

Page 15

Page 18: Project Status Review Meeting - SUMMARY · 2018-03-14 · 16 Mail RFP to potential vendors Mon 3/22/10 Mon 3/22/10 ... 19 Issue purchase order for software Mon 5/31/10 Mon 7/26/10

EXPECTED COST PROBABLE IMPACT

LARGE

MEDIUM

SMALL LOW

MEDIUM

HIGH

Under $25K

Critical to the attainment of institutional strategies and/or required by law or regulation

Supports multifunctional goals or provides “best practice” improvements to key institutional processes

Supports functional area goals or objectives, or improves one or more current processes

PENDING PROJECT PORTFOLIO ‐ LEGEND

SCOPE OF WORK

LARGE

MEDIUM

SMALLLess than 3 months duration, and relatively few stakeholders

3‐9 months duration, and multiple stakeholders

10 or more months duration and broad, institution‐wide, scope

$25‐50K

Over $50K

Page 16


Recommended