STUDENT PASSPORT PROJECT
Project Team:
1 -Ali Mohammed Al-Feteisi2 -Zaid Saleh Said Al Obaidani
OUTLINES1. Project Overview
1.1 Purpose, Scope, and Objectives
1.2 Assumptions, Constraints and Risks
1.3 Project Deliverables
1.4 Schedule and Budget Summary
2. Project Organization
2.1 External Interfaces
2.2 Internal Structure
2.3 Roles and Responsibilities
3. Managerial Process Plans
3.1 Start‑up Plan
3.2 Work Plan
3.3 Project Tracking Plan
3.4 Project Closeout Plan
1 .PROJECT OVERVIEW
Nowadays, the travel and tourism move is going so fast towards
better knowledge techniques and better education .Learning
process begun to be the main concern that most of stakeholder
insist to have among the new upcoming generations .
Therefore, most of families and parents especially used to take
their children to a foreign countries in order to get a better
language skills and a better learning interaction in a adequate
atmosphere .
1 .PROJECT OVERVIEW
1.1 Purpose, Scope, and Objectives
We as a developers came with a technical solution to make the booking and
traveling process become easier to the student and to the parent as well .
We gathered more than 4 specific main places that most of traveler went to
before traveling, which are travel agencies, airports, embassies, and main
institutes in one easy and interactive platform.
The period time of project plan is 83 days starting from 21-Oct-2015 till 17-03-
2015 ,and we are targeting three main criteria’s at first :
• High School Student.
• Academic Students (University and college students).
• Amateurs.
1 .PROJECT OVERVIEW
1.1 Purpose, Scope, and Objectives
We could enhance it furthermore in the near future to include more than those
specific categories of people, and provide other related services to it .
However, we have a several needs as a developers that we will select to be
achieved through the design of the application which are :
1. Student details information.
2. Contact and Scheduling (travel agencies + airport + institutes).
And other deliverables that the customer will find it easier for him rather than
the usual booking process such as :
3. Travel abroad with cheap price.
4. Simplify the process of getting visa and insurance.
5. Contact with institutes regarding study nature.
1 .PROJECT OVERVIEW
1.2 Assumptions, Constraints and Risks
Assumptions for the Project :
Assumptions are circumstances and events that need to occur for the
project to be successful, but are outside the total control of the project
team. Assumptions are accepted as true and are often without proof or
demonstration. So through the analysis of project we found the following :
• All resources required by the developers will be exist and easy to
require.
• During the rainy season, cheap labor will be available.
• The important stakeholders will come to the next meeting.
1 .PROJECT OVERVIEW1.2 Assumptions, Constraints and Risks
After we showed the assumptions, we moved now to show the main resources
of a project which are :
Technical Resources : Which are the software to be used during design
process:
1. Oracle Development Package.
2. Android Studio
3. Adobe Photoshop.
Other Resources :
1. Reviews with other corporations as mentioned before
(Airports, Travel Agencies).
2. Updated database of Travel tickets.
3. Updated Visa forms, and direct contact to embassies.
1 .PROJECT OVERVIEW
1.3 Project Deliverables
Project Deliverables Description
Written report of Technical RequirementsWritten description of minimum technical
requirements for the needs by the developers , and meets needs of Consumer Protection initiative
Written acknowledgement of top 3 travel agencies responses
Evaluate travel agencies responses and determine top 3 scores based on evaluation process; respond
to the agencies challenges
Written Assessment of current reproduction processes
A written assessment of each member of the team document reproduction needs and requirements
Establishment of an on-going Maintenance & Operation Plan for
Program
Security of the Program will be subject to audit every three years either by the developers
themselves or selected 3rd party, or the state Auditor's office
1 .PROJECT OVERVIEW1.4 Schedule and Budget Summary
The Schedule of the Project plan is attached with MS Project Chart, the
following picture is a snapshot of the main schedule plan.
1 .PROJECT OVERVIEW1.4 Schedule and Budget Summary
The budget of the project is as following :
Purpose Amount
Staff 900 RO
services 600 RO
Backup 200 RO
Total 1700 RO
2 .PROJECT ORGANIZATION
2.1 External Interfaces
Figure (1): External interface of the main interface for the application
2 .PROJECT ORGANIZATION
2.1 External Interfaces
Figure (2 + 3): External interface list of institutions and registration pages .
2 .PROJECT ORGANIZATION
2.2 Internal Structure
The project sections will consist of:
- List of countries in Europe.
- List of institutes and universities.
- List of known travel agencies with names of people to
contact with.
- Updated list of known travel agencies to contact with
regarding the payment and residence issues.
- Schedule of travel plans from the airports database.
2 .PROJECT ORGANIZATION
2.2 Internal Structure
Development Team Tasks :
•Application Develop
Developer1
•Database design
Developer2
•Test application
success
Tester
2 .PROJECT ORGANIZATION
2.3 Roles and Responsibilities
Project Manager : The ones who is in charge of the plan, the project, the
decisions, and the team. He is the main supervisor of the project and the
development process .
Project Team : Consist of developers, designers, and marketers. They play
an important role as each one of them present his ideas and do his part
towards the achieving the goals of the project.
Project Sponsor : The main contributor to the project, who could fund and
support the project financially and non-financially .
3 .MANAGERIAL PROCESS PLANS
3.1 Start up Plan
3.1.1 EstimatesAccording to the following estimate, the project take 4 months to be done, and the cost will come in about 900.0 OR.
Costs Total
Direct cost
Team
Developer1 200.0 OR
Developer2 200.0 OR
Designer 50.0 OR
Marketer 50.0 OR
Contributors (Travel Agencies, Airports …
etc.)300.0 OR
Total direct cost 800.0 OR
PM cost 100 RO
Overall project cost 900 RO
3 .MANAGERIAL PROCESS PLANS
3.1 Start up Plan
3.1.2 Staffing
Staff Type staff personnel Duration required
Programme developer Contractor Phase 3 – development
Database developer Contractor Phase 3 – development
Application designer Contractor Phase 3 – development
Marketer Contractor Phase 4 – after testing
3 .MANAGERIAL PROCESS PLANS
3.1 Start up Plan
3.1.3 Resource Acquisition
• Development resources:- 2 computers with (windows 8.1) OS.- Database Server.- Network establishment with Access to internet.- Backup device.
• Test resources: - 1 android built in device - 1 pc - Server connection
• Product resources: - Evaluator person - 1 mobile device
3 .MANAGERIAL PROCESS PLANS
3.1 Start up Plan
3.1.4 Project Staff Training
Since all the staff are in contract and they have will based skills,
they need a training in meeting the schedule plan for each phase.
The Training will take 2 weeks, and it will be supervised by the PM,
and it will be located in another company before starting the real
project.
3 .MANAGERIAL PROCESS PLANS
3.2 Work Plan
3.2.1 Work Breakdown Structure
Developing Student Passport Application
1.0 Planning
1.1 Plan Requirements
1.2 Plan Design
2.0 Implementation
2.1 Implement
2.2 Test
3.0 Present and Recheck
3.1 Taking Feedback
3 .MANAGERIAL PROCESS PLANS
3.2 Work Plan
3.2.2 Schedule Allocation
Task NameResource
NameMilestone Duration Start Finish
Dependent task
Analysis -Scope phase
27 days 3/1/2016 30/1/2016 -
Get Feedback PM, Psponser - 2 days 1/2/2016 3/02/2016Developing prototypes
Review Functional
SpecificationsDevelopers - 4 days 5/02/2016 9/02/2016
Complete Design
3 .MANAGERIAL PROCESS PLANS
3.2 Work Plan
3.2.3 Resource Allocation
The Resource that will be used is listed in section 3.1.3 (Resource Acquisition).
3.2.4 Budget Allocation
Type of service needed/Resource Cost
Travel 50.0 RO
meetings None
Computing resource 300.0 RO
software tools 50.0 RO
Special testing and simulation facilities 150.0 RO
Administrative support 50.0 RO
Total 600.0 RO
3 .MANAGERIAL PROCESS PLANS
3.3 Project Tracking Plan
3.3.1 Requirements Management
Change Request
INITIATIONPreliminary Scope
High –level Impact Analysis
PLANNING
Impact Analysis Planning Document
DEVELOPMENT
Requirements Collection
Documentation
Review
VERIFICATION & VALIDATION
BASELINE TRACEABILITY
3 .MANAGERIAL PROCESS PLANS
3.3 Project Tracking Plan
3.3.2 Schedule Control
Table following lists each schedule control technique used in the project plan:
Technique Relatedness to the actual scheduling
Performance Reviews
As we have done this approach we compared through dates, and the percentage of work done within the same duration. It
found that it’s really affective.
Critical Path Method
We Predicted the project duration by analyzing the sequence of activities that has the least amount of scheduling flexibility. It really enhance the duration and time needed through the real
scheduling.
3 .MANAGERIAL PROCESS PLANS
3.3 Project Tracking Plan :
3.3.3 Budget Control :
After analysis of budget needed in part (3.2.4) and Estimates in part
(3.1.1) It found that the needed budget match the estimates, and that is
against the risk of losing the price needed or lowering its cost .
3.3.4 Quality Control :
As used in the last stage of requirement management (Verification and
validation) is the main concern of how good the quality presented if the
application and the real product, and is it really match the world standards
and invokes all aspects need without any errors made.
3 .MANAGERIAL PROCESS PLANS
3.3 Project Tracking Plan :
3.3.5 Reporting
Type of
Communication
Communication
Schedule
Typical
Communication
Mechanism
Who Initiates Recipient
Status Report every Friday team meeting Project Manager Project Team
Schedule and
Effort Tracking
Report
weekly email Project Manager Developers
Project Review monthly face to face Project Manager Project Team
Risk Mitigation
Status
as mitigation
actions are
completed
emailresponsible team
memberProject Manager
Supplier
Management
at project life
cycle gatesvideoconference Program Manager
Project Manager,
Program Sponsor
3 .MANAGERIAL PROCESS PLANS
3.3 Project Tracking Plan :
3.3.6 Project Metrics
This job has been assigned to the marketing team, so that he keep
evaluate the project process along with the PM, and validate it.
3 .MANAGERIAL PROCESS PLANS
3.4 Project Closeout Plan :
To achieve the project plan to be work as planned we need to
enclosed it with reports of lessons learned and analysis of project
objectives , and also addressing the staff assignments in the same
report , which will be presented to the PM eventually .
NO. Risk Type Possible Risks
1 Technology Software components that should be reused contain defects that limit their functionality.
2 People Required training for staff is not available.
3 Tools Required tools are not available.
4 Requirements Requirements do not match what customer wants.
5 Estimation The time required to develop the software is underestimated