+ All Categories
Home > Documents > PROPOSED (AD) BIOGAS PLANT, NAIVASHA - … IMPACT ASSESSMENT (EIA) REPORT FOR BIOJOULE KENYA LTD FOR...

PROPOSED (AD) BIOGAS PLANT, NAIVASHA - … IMPACT ASSESSMENT (EIA) REPORT FOR BIOJOULE KENYA LTD FOR...

Date post: 18-Mar-2019
Category:
Upload: hoangnhan
View: 218 times
Download: 0 times
Share this document with a friend
45
ENVIRONMENTAL IMPACT ASSESSMENT (EIA) REPORT FOR BIOJOULE KENYA LTD FOR PROPOSED (AD) BIOGAS PLANT, NAIVASHA BY Environmental Cost Management (ECM) Centre Limited (Reg: 196) JUNE 2013 EnvironmentalCostManagement(ECM)CentreLimited ThetaLaneoffLenanaRd,Kilimani,P.O.Box10135-00100,GPONairobi,Kenya Tel:254-3001661,020-2712999,0734947882,0720-828621Fax:020-27122999, E-mail:[email protected]
Transcript

ENVIRONMENTAL IMPACT ASSESSMENT

(EIA) REPORT

FOR

BIOJOULE KENYA LTD

FOR

PROPOSED (AD) BIOGAS

PLANT, NAIVASHA

BY

Environmental Cost Management (ECM) Centre Limited (Reg: 196)

JUNE 2013

Environ mental Cost Management (ECM) C entre Limited

Theta Lane off Lenana Rd, Kilimani, P.O. Box 101 35-001 00, GPO Nairobi, Kenya

Tel: 254-30 016 61, 0 20-27 1299 9, 07 349 4788 2, 07 20-82 8621 Fax :02 0 -271 2299 9,

E-ma il: ecm@ ecmcentre. com

I

Prepared by:

Environmental Cost Management (ECM) Centre Limited (Reg: 196)

Signed………………………………..date…………………………….

Proponent:

Biojoule ltd

Signed………………………………..date…………………………….

Operating Terms

AD Anaerobic digestion

DM Dry Matter

kWh Kilo watt per hour

MWh Mega Watt per Hour

KP&LC Kenya power and lighting Company

EXECUTIVE SUMMARY

Vegpro Limited deals in fresh produce, flowers and logistics from Kenya. After the fresh produce and

flowers for export are produced, wastes such as spent vegetable, rose plants (leaves, stems, etc.),

vegetable out grades, rose rejects and farm produced “green crops” that are left are first decomposed

and used as fertilizer for the farm. These wastes will henceforth collectively be referred to as

feedstock. Vegpro ltd also obtains waste from Vandenberg ltd Farm that is located nearby.

Approximately 23,024 tonnes per year of fresh feedstock is available at a dry matter (DM) content of

23.7%, giving 5,448 tonnes per year of dry matter (DM). In order to utilize the feedstock and

diversify revenue sources, the company proposes to set up a biogas plant within Gorge farm, at the

south-western end, a spot which is about 200 meters from an existing KP&L sub-station.

Photo 1: Aerial layout of the farm showing the earmarked site(in green)

The objective of the project is to satisfy the ever increasing demand for electricity in Kenya with a

clean alternative to the more fossil-fuel based electricity component of the Kenyan national grid. The

project aims to generate electricity. Some of the electricity will be used for the operation of the plant

itself, the farm with the balance being exported to the grid. Energy from Thermal sources like Coal,

Diesel is expensive and a source of pollution and contributes to the CO2 emissions. Electricity

generated from this plant will replace these sources sustainably.

It is recognised that a project of such magnitude as the proposed biogas plant could have certain

adverse environmental impacts if appropriate measures to protect the environment are not

undertaken.In order to ensure lasting co-existence of the site activities with other social and economic

activities in the area, and compliance with the Environmental Management and Coordination Act,

1999, Vegpro Limited commissioned this environmental assessment for the project.

The results of this study show that the proposed biogas plant does not have a potential for serious long

term negative environmental impacts and overall has a positive environmental and socioeconomic

benefit to the local community.

The project is sitting on a site where development had already been undertaken and the surrounding

areas are large scale agricultural activities, where agricultural equipment is already employed.

The major impacts that may be caused by the project will be short term and mainly during

construction. These include noise and air pollution due to heavy construction equipment, soil

excavation, excessive requirement of water and possible more energy requirements. For water and

energy usage, alternative sources should be sought without affecting the surrounding area.

The potential adverse environmental impacts during operations, such as wastewater, solid waste and

drainage systems, adequate mitigation measures will need to be put in place. Plans are also in place to

adequately mitigate the health and safety impacts of the project. The recommendations have been

provided in the Environmental management Plan (Section 7) as proposed actions. This report presents

the findings under the following headings:

• Environmental impact assessment objectives and scope;

• Nature of the project;

• Methodology;

• Policy and legal issues;

• Baseline conditions of the site;

• Anticipated environmental impacts;

• Environmental management plan;

• Annexes.

Contents ENVIRONMENTAL ASSESSMENT OBJECTIVES AND SCOPE OF WORK ............................... 8

Introduction ................................................................................................................................... 8

Assessment Objectives .................................................................................................................. 3

Scope ............................................................................................................................................ 3

Terms of Reference ....................................................................................................................... 3

Responsibilities ............................................................................................................................. 4

Methodology Outline ..................................................................................................................... 5

Environmental Screening ............................................................................................................... 5

Environmental Scoping.................................................................................................................. 5

Desk Study ................................................................................................................................ 5

Baseline Data/Information Gathering ......................................................................................... 6

Site Assessment ......................................................................................................................... 6

Reporting ................................................................................................................................... 6

POLICY AND LEGAL FRAMEWORK ........................................................................................... 7

General Overview .......................................................................................................................... 7

Policies .......................................................................................................................................... 7

National Environment Action Plan (NEAP) ............................................................................... 7

National Policy on Energy ......................................................................................................... 8

Kenyan Economic Strategy for Wealth and Employment Creation (2003-7) ............................... 8

Policy Guidelines on Environment and Development ................................................................. 8

Legal Aspects ................................................................................................................................ 9

The Environment Management and Co-ordination Act, 1999 ..................................................... 9

Electric Power Act, 2006 ......................................................................................................... 10

The Factories Other Places of Work Act (Cap 514) .................................................................. 10

The Water Act 2002 ................................................................................................................. 11

The Public Health Act (Cap. 242) ............................................................................................ 12

Local Government Act (cap 265) ............................................................................................. 13

EIA/ EA Regulations ............................................................................................................... 13

BASELINE INFORMATION & DATA .......................................................................................... 14

Project Site and Topography ........................................................................................................ 14

Drainage System and Hydrology.................................................................................................. 14

Vegetation ................................................................................................................................... 14

Rainfall and Climate .................................................................................................................... 15

Soils ............................................................................................................................................ 15

Water Resources .......................................................................................................................... 15

Bio-diversity................................................................................................................................ 15

Air Quality .................................................................................................................................. 15

Land Use Activities ................................................................................................................. 16

Areas of Cultural Importance ................................................................................................... 16

Environmentally Sensitive and/or Significant Areas ................................................................. 16

Economic Development ........................................................................................................... 16

Social Issues ............................................................................................................................ 16

PROJECT DESCRIPTION AND MAGNITUDE OF OPERATIONS .............................................. 17

General Description, Ownership and Project Location ................................................................. 17

Nature of the Project and Proposed Development ......................................................................... 18

Feedhopper Unit with Shredder and Feeder .............................................................................. 19

Hydrolyser 1 ............................................................................................................................ 19

Hydrolyser 2 ............................................................................................................................ 19

Digester ................................................................................................................................... 20

Recyclate Tank ........................................................................................................................ 20

Central Building ...................................................................................................................... 20

Biogas Store ............................................................................................................................ 21

Main Pump Assembly .............................................................................................................. 21

Main Plant Control System ...................................................................................................... 22

Solids Separator ....................................................................................................................... 22

Electricity Generating Sets (CHP Units)................................................................................... 23

Main Flare ............................................................................................................................... 23

Site Description ........................................................................................................................... 24

Process Description ..................................................................................................................... 24

Sources of Raw Materials ............................................................................................................ 26

Waste Generation ........................................................................................................................ 26

Project Construction .................................................................................................................... 26

Construction Inputs .................................................................................................................. 26

Construction Activities ............................................................................................................ 26

Current Status of the Project and Construction Period .............................................................. 27

Project Implementation and Operation ......................................................................................... 27

Project Budget ............................................................................................................................. 27

Project Lifetime and Decommissioning........................................................................................ 27

ANALYSIS OF ENVIRONMENTAL IMPACTS ........................................................................... 28

STAKEHOLDER COMMENTS ..................................................................................................... 31

TABLE 1: ENVIRONMENTAL ASPECTS, IMPACTS AND MITIGATION ................................ 33

ENVIRONMENTAL MANAGEMENT PLAN ............................................................................... 35

CONCLUSION ............................................................................................................................... 37

ANNEX: ............................................................................................ Error! Bookmark not defined.

ATTACHMENTS .............................................................................. Error! Bookmark not defined.

ENVIRONMENTAL ASSESSMENT OBJECTIVES AND SCOPE OF

WORK

Introduction

Vegpro Limited deals in fresh produce, flowers and logistics from Kenya. The company

operates two firms i.e. Gorge Farm and Longonot Farm in Naivasha located 15KM from Naivasha

town along Moi South Lake Road. Vegpro Ltd is a leading producer of vegetables and cut flowers.

After the fresh produce and flowers for export are produced, wastes such as spent vegetable, rose

plants (leaves, stems, etc.), vegetable out grades, rose rejects and farm produced “green crops” that

are left are first decomposed and used as fertilizer for the farm. These wastes will henceforth

collectively be referred to as feedstock.

Photo 2: Photo showing vegetables in the farm

Approximately 23,024 tonnes per year of fresh feedstock is available at a dry matter (DM) content of

23.7%, giving 5,448 tonnes per year of dry matter (DM). In order to utilize the feedstock and

diversify revenue sources, the company proposes to set up biogas plant within its Gorge farm, at the

south-western end, a spot which is about 200 meters from an existing KPLC sub-station. (see photo 1)

Photo 3: Photo Showing the process waste

used as feedstock

Photo 4: Photo showing sweet corn process

waste

Extensive testing of this material in laboratory scale digesters at Southampton University, UK, has

shown that this feedstock will yield 421M3/hr of biogas of which 232 M

3/hr will be methane. These

methane is used in electricity generation. Some of the electricity generated will be used for the

operation of the plant itself, on the farm with the balance being exported to the grid.

The project proposal is for an on-farm anaerobic digestion (AD) plant comprising a system of

hydrolysers and a digester to produce biogas, an engine driven electricity generating set (genset) and

other associated equipment to operate and manage the process. The whole project is designed to be

sited on a pre-leveled area on the farm. This project will establish an environmentally friendly and

sustainable form of electricity (and heat) production from the feedstock, also known as substrate once

loaded into the digestion system. The AD process uses naturally occurring bacteria and other

microbes to convert organic matter in the feedstock into:

• Biogas, which is an energy rich mixture of methane and carbon dioxide which is

suitable for use as a fuel to generate electricity and heat.

• Nutrient rich solid and liquid fertilisers to be used on the farm in place of purchased

chemical fertilisers.

The resulting biogas is burned in an engine driven generating set (genset) to produce electricity,

mostly for use on the farm with the balance available for export to the grid. The genset also produces

heat in the form of engine cooling water and some of this will be used to heat the hydrolysers to 50-

55C and to maintain the digester at a temperature of ~ 40-45C. The pre-hydrolysis of the feedstock

material in the two hydrolysers ensures

significantly higher biogas production and

shorter residence times than conventional

AD plants, maximizing biological

degradation and stabilization, minimizing

capital costs and plant footprint and

increasing electricity (and heat)

production.

Photo 5: AD plant photo (the

surface tanks and with top

storage domes)

Photo 6: Standard Biogas generator set

It is recognized that projects such as the proposed biogas plant by Vegpro Limited could have

certain adverse environmental impacts if appropriate measures to protect the environment are

not undertaken. In order to ensure lasting co-existence of the site activities with other social and

economic activities in the area, and compliance with the Environmental Management and

Coordination Act, 1999, the site operators commissioned this environmental assessment for the

project.

Assessment Objectives

The objective of this assessment is to determine and assess the impacts of the proposed project and to

develop appropriate mitigation measures. The assessment also aims to ensure compliance with the

provisions of the Environmental Management and Coordination Act, 1999 and to prepare

an Environmental Management Plan which can be used as the basis for future audits.

Scope

The Kenya Government has put forward measures aimed at protecting the environment by listing

projects which must undergo environmental impact assessment under schedule 2 of EMCA 1999. For

a proposed project to get a license form NEMA, they are required to either submit a project or EIA

report depending on the magnitude and nature of the project. This EIA report covers the following

aspects of the proposed cogeneration project:

• The baseline environmental conditions of the area

• Description of the nature and design of the project

• Description of the major activities at the site during construction, operation and

decommissioning phases of the project

• Provisions of the relevant environmental laws

• Identification of materials to be used and by-products and wastes

• Identification and discussion of the potential adverse impacts to the environment from

the site

• Establish appropriate mitigation measures for these impacts

• Provision of an environmental management plan.

Terms of Reference

The terms of reference for the EIA included the following:

• Hold appropriate meetings with the management to establish the procedures, define

requirements, responsibilities, and a timeframe

• Provide a description of the nature, design, activities of the proposed Biogas Plant

with a focus on potential impacts to the surrounding environment

• Inspect the site and its surroundings in collaboration with the management

• Carry out a systematic environmental assessment at the site following the gazetted

regulations

• Conduct a stakeholder meeting for the identification of social and community

concerns

• Produce an environmental assessment project report that should contain among

other issues identification of key environmental aspects, recommendations on

appropriate mitigation measure to minimize or prevent adverse impacts and ensure

health and safety of the workers and neighbouring communities

• Develop an environmental management plan.

Responsibilities

While the environmental impact assessment expert provided the technical understanding on

the baseline environmental status, potential impacts, management options and legal framework,

the client provided the following:

• Site map(s) showing roads, service lines, buildings’ layout and the actual size of the

site

• Full details of nature of the project, design, materials usage and by-products, site

operational outline and any wastes to be generated

• Anticipated measures for handling wastes on the site

• Anticipated management programme for the proposed development

• Arrangement with surrounding community/stakeholder meetings

The output from the environmental expert included the following:

• An environmental impact assessment project report comprising of an executive summary, study approach, operational nature of the project, baseline conditions, impacts

and appropriate mitigation measures

• An environmental management plan as part of the report recommendations

Methodology Outline

The general steps followed during the assessment were as follows:

• Preliminary assessment of the site

• Environment screening, in which the project was identified as among those requiring a project

report under schedule 2 of Environmental Management and Coordination Act (EMCA),

1999

• Environmental scoping that provided the significant environmental issues related to proposed

project and the site activities

• Desk studies and interviews with the site managers

• Detailed physical inspection of the site and the surrounding areas

• Community/stakeholder comments gathering

• Reporting

Environmental Screening

This step was applied to determine whether an environmental assessment project report was required

and what level of assessment was necessary. This was done in reference to requirements of the EMCA

(1999) and specifically the second schedule. Issues considered included the physical location,

sensitive issues, nature of the project, project design and nature impacts.

Environmental Scoping

The scoping process helped narrow down onto the most critical issues requiring attention during the

assessment. Environmental issues were categorized into physical, natural/ecological, social, and

economic aspects.

Desk Study

The desk study included documentary review on the nature of the site activities, project

design, operational requirements, policy and legislative framework as well as the environmental

setting of the area among others. It also included discussions with managers and staff.

Baseline Data/Information Gathering

Site information was gathered through observation and research. The site was visited for inspection of

the physical environment and status of the immediate surroundings. A pre-prepared data sheet was

used to record information gathered during the visit of the sites. The field data sheet addressed various

aspects of the project site and the general environment and had been adopted from the international

environmental protocol then adjusted to incorporate issues listed in the EIA regulations in the

Kenya Gazette Supplement No. 56 of 13th June 2003.

Project design documents, including main drawings, were reviewed. Physical investigation took into

consideration the environment where the plant will be located. The hydrology and surface geology of

the area, the drainage system, and the typical socio-economic activities around the site were

investigated. Also investigated were the public services provided in the area including the drainage

systems, water supply/abstractions, and access roads.

Site Assessment

Field visits were meant for physical inspections of the site characteristics and the environmental status

of the surrounding areas to determine the baseline data and potential impacts. The assessors

were conducted around the site by the General Manager of Gorge Farm. Community/stakeholder

consultation comments were also solicited during this stage through visits to individual

stakeholders/neighbours.

Reporting

In addition to briefing the management, this project report was prepared. The contents were

then presented to the client for submission to the National Environmental Management Authority

(NEMA) as required by law.

POLICY AND LEGAL FRAMEWORK

General Overview

Environmental impact assessment (EIA) is a tool for environmental conservation and is

used for the identification of significant environmental aspects and impacts of proposed projects

which when addressed ensure sustainable operations with respect to environmental resources and co-

existence with other socio-economic activities in the neighbourhood. At the national level,

Kenya has put in place necessary legislation that requires environmental impact assessments to be

carried out on specified types of operations and projects and reports to be submitted to the

National Environment Management Authority (NEMA) for approval and issuance of relevant

licenses.

To facilitate this process, regulations on EIA and environmental audits have been established

under the Kenya Gazette Supplement No. 56 of 13th June 2003. Besides, a number of other national

policies and legal statutes have been reviewed to enhance environmental sustainability in

national development projects across all sectors. Some of the policies and legal provisions that are

deemed relevant to the proposed project are briefly presented in the following sub-sections. For the

purposes of this report, emphasis has been put on those policies and legal provisions that relate to the

design, installation and operation of the proposed facilities.

Policies

National Environment Action Plan (NEAP)

According to the Kenya National Environment Action Plan (NEAP, 1994) the Government

recognized the negative impacts on ecosystems emanating from industrial, economic and

social development programmes that disregarded environmental sustainability. Following on

this, establishment of appropriate policies and legal guidelines as well as harmonization of the

existing ones have been accomplished and/or are in the process of development. Under the NEAP

process, EIA was introduced and among the key participants identified were the industrialists,

business community and local authorities.

National Policy on Energy

The National Policy on Energy, Sessional Paper 4 of 2004 recognizes that the success of

socio-economic and environmental transformation strategies pursued by the government at present

and in the future is to a large extent depended on the performance of the energy sector as an economic

infrastructure. The paper encourages the use of environmentally friendly and efficient

technology for the generation of electricity; and the generation of electricity from renewable energy

sources through a wider adoption and use of renewable technologies and thereby enhance their role in

the country’s energy supply matrix. This enhancement will reduce the country’s dependence on oil

based thermal generation. The proposed project is therefore in line with the policy.

Kenyan Economic Strategy for Wealth and Employment Creation (2003-7)

The strategy also identifies implementation of renewable sources of energy projects as part of

the key reforms necessary in the energy sector, which is in line with the proposed project. The

proposed project will improve the revenue base of Vegpro Limited with possible increase in job

creation for more people in the region. At the same time the project will lead to economic

improvement of the country through increased power availability.

Policy Guidelines on Environment and Development

Among the key objectives of the Policy Paper on Environment and Development (Sessional

Paper No. 6 of 1999) are:

• To ensure that from the onset, all development policies, programmes and projects take

environmental considerations into account,

• To ensure that an independent environmental impact assessment (EIA) report is prepared for

any industrial venture or other development before implementation,

• To come up with effluent treatment standards that will conform to acceptable health

guidelines.

Under this paper, broad categories of development issues have been covered that require

sustainable approach. These issues include the waste management and human settlement sectors. The

policy recommends the need for enhanced re-use/recycling of residues including wastewater, use of

low non- waste technologies, increased public awareness raising and appreciation of clean

environment. It also encourages participation of stakeholders in the management of wastes within

their localities. Regarding human settlement, the paper encourages better planning in both rural and

urban areas and provision of basic needs such as water, drainage and waste disposal facilities among

others.

The proposed project does not use any water for its operations except for personnel and washing

down, which is in very limited quantities, which support this policy guideline. No waste is generated

as both the liquid and solid fertilizers will be used in the farms.

Legal Aspects

Application of international conventions and national statutes and regulations on

environmental conservation and pollution prevention suggests that organizations have a legal duty and

responsibility to conserve resources and discharge only wastes of acceptable quality to the receiving

environment and without compromising public health and safety. The key international and national

laws of relevance that govern the management of environmental resources in the country have been

briefly discussed in the following paragraphs. Note that wherever any of the laws contradict each

other, the Environmental Management and Co-ordination Act, 1999 prevails.

The Environment Management and Co-ordination Act, 1999

This Act has sections which regulate the environmental aspects of the energy sector. Part II

of the Environment Management & Co-ordination Act, 1999 states that every person in Kenya is

entitled to a clean and healthy environment and has the duty to safeguard and enhance the

environment. To achieve this, the Act directs that any operator of any proposed significant

undertaking should carry out an environmental impact assessment and prepare an appropriate

report for submission to the National Environmental Management Authority (NEMA), who in turn

may issue a license as appropriate.

The second schedule of the same Act lists management of power projects among the projects

that must undergo an environmental impact assessment before implementation.

Part VIII section 72 of the Act prohibits discharging or applying poisonous, toxic, noxious or

obstructing matter, radioactive or any other pollutants into aquatic environment. Section 73 requires

those operators of projects, which discharge effluent or other pollutants to submit to NEMA accurate

information about the quantity and quality of the effluent. Section 80 demands that all owners of an

industrial establishment or trade emitting a substance or energy causing or likely to cause air pollution

to apply for an emission license from the Authority. However, NEMA has not yet established the

emission standards.

Biogas projects are renewable sources of energy which utilize feedstock. The waste

generated is mainly converted to both liquid and solid fertilizer, which are then re-used in the farms.

Electric Power Act, 2006

Section 121 (1) c of the Electric Power Act, 1997 empowers the Electricity Regulatory

Commission (ERC) to “formulate, enforce and review environmental, health, safety and quality

standards for the energy sector, in coordination with other statutory authorities”; ERC is therefore the

Lead Agency in respect of the electric power sub-sector, while section 9 (3) of the Act requires ERC

to take into account the need to protect the environment, conserve natural resources, and protect the

health and safety of service users and the public at large, among other things; when evaluating

applications for licenses.

The Act also empowers the board to ensure the licensees provide information to the

public on the environmental performance and sources of their electric power.

To ensure compliance, a copy of this EIA report will be issued to the ERC to verify

conformance before issuing of the license.

The Factories Other Places of Work Act (Cap 514)

Section 13 states that every factory shall be kept in a clean state and free from effluvia arising

from any drain, sanitary convenience or nuisance including accommodation of dirt and refuse. Section

17 of the same Act requires that where any process is carried out which renders the floor liable to be

wet to such an extent that the wet is capable of being removed by drainage, effective means shall be

provided and maintained for safe draining off the wet. Section 51 requires suitable means of removing

dust or fumes from work places. Section 53 of this Act requires that workers employed in a process

involving exposure to wet or to any injurious or offensive substances, suitable protective clothing and

appliances (gloves, footwear, goggles, and head coverage) shall be provided.

Section 4 of Kenya subsidiary legislation of 2004, Legal Notice No. 31 of Kenya Gazette

Supplement No.25 of 24th May, 2004 of the Factories Act Cap 514, requires that, all factories or other

workplace owners to establish a safety and health committee, which shall consist of safety

representatives from the management and the workers. The number of the committee members will

range from 3 to 7 depending on the size (number) of employees. The Act also requires the

management to appoint a competent person who is a member of the management staff to be

responsible for safety, health, and welfare in the factory or workplace. Section 13 goes ahead to state

that a health and safety audit of the workplace be carried out in every twelve months by a

registered health and safety adviser. If the owner(s) or management contravenes any of the rules,

he/she shall be guilty of an offence.

Under environment health and safety performance in the electric power sub-sector, the

electricity generating stations are regarded as factories. The Factories Act has provisions dealing with

the safety and health of persons working in factory premises, which description encompasses

electricity generating plants. The provisions of the Factories and Other Places of Work Act (Cap

514) and the attendant subsidiary legislations are enforced by the Department of Occupational health

and Safety of the Ministry of Labour. The Electricity Regulatory Commission will therefore liaise

with the Department of Occupational Health and Safety to ensure that the safety and health of persons

working in utilities in the electric power sub-sector are safeguarded at all times.

Vegpro Ltd biogas project will be governed by this Act and since the project deals

with power generation, appropriate measures will be put in place to ensure safety of workers and

property as a whole.

The Water Act 2002

Part II section 18 of the Act provides for national monitoring and information systems on

water resources. Following on this, sub-section 3 allows the Water Resources Management Authority

to demand from any person or institution, specified information, documents, samples or materials on

water resources. Under these rules, specific records may need to be kept by a factory operator and

the information thereof furnished to the authority.

Section 73 of the Act allows a person with license (licensee) to supply water to make

regulations for purposes of protecting against degradation of water sources. Section 75 and sub-

section 1 allows the licensee to construct and maintain drains, sewers and other works for

intercepting, treating or disposing of any foul water arising or flowing upon land for preventing

pollution of water sources within his/her jurisdiction.

The proposed project will not create any further water demand from the current rates because

its operations do not require any water furthermore using the liquid digestate will reduce the amount

of water required to irrigate farm crops and chemical nutrients added to irrigation water

The Public Health Act (Cap. 242)

Part IX section 115 of the Act states that no person/institution shall cause nuisance or

condition liable to be injurious or dangerous to human health. Section 116 requires Local Authorities

to take all lawful, necessary and reasonably practicable measures to maintain their jurisdiction

clean and sanitary to prevent occurrence of nuisance or condition liable for injurious or dangerous to

human health.

Such nuisance or conditions are defined under section 118, and include waste pipes, sewers,

drains or refuse pits constructed or situated in such a state as in the opinion of the medical officer of

health to be offensive or injurious to health. Any noxious matter or waste water flowing or

discharged from any premises into a public street or into the gutter or side channel or watercourse,

irrigation channel or bed not approved for discharge is also deemed as a nuisance. Other nuisances are

accumulation of materials or refuse which in the opinion of the medical officer of health is likely to

harbour rats or other vermin.

Section 130 provides for making and imposing regulations by the county councils and others

the duty of enforcing rules in respect of prohibiting use of water supply or erection of structures

draining filth or noxious matter into water supply as mentioned in section 129. This provision is

supplemented by Section 126A that requires county councils to develop by-laws for controlling and

regulating among others private sewers, communication between drains and sewers and between

sewers as well as regulating sanitary conveniences in connection to buildings, drainage, cesspools,

etc. for reception or disposal of foul matter.

Part XII Section 136 states that all collections of water, sewage, rubbish, refuse and other

fluids which permits or facilitate the breeding or multiplication of pests shall be deemed nuisances

and are liable to be dealt with in the manner provided by this Act.

Vegpro Ltd will ensure that there is no holding for both fresh feedstock and the solid or liquid

waste (fertilizers) generated. All feedstock will be fed into the digesters and the remaining will be

decomposed at the existing composting operation. For the fertilizers, all will be used in the farms

immediately they are produced. This will ensure the plant areas are kept in such a way that they do

not constitute a health hazard.

Local Government Act (cap 265)

Section 163 allows the County Council to prohibit all businesses, which may be or become a

source of danger, discomfort or annoyance due to their noxious nature through smoke, fumes, dust,

noise, or vibrations

Section 165 allows the local authority to refuse to grant or renew any license which is

empowered in this act or any other written law on the grounds that the activity does not conform to

the requirements of any by-laws in force in the area of such local authority or the granting of the

license would be contrary to the public interest.

The chosen AD process operates in a closed and sealed system with limited potential for

odour escape; exclusion of air is a fundamental requirement of the process. The methods used to limit

the ingress of air also prevent the leakage of odour.

EIA/ EA Regulations

The environmental impact assessment guidelines require that the study be conducted in

accordance with the issues and general guidelines spelled out in the second and third schedules of the

regulations. These include coverage of the issues on schedule 2 (ecological, social, landscape, land

use and water considerations) and general guidelines on schedule 3 (impacts and their sources, project

details, national legislation, mitigation measures, a management plan and environmental schedules

and procedures.

BASELINE INFORMATION & DATA

Project information was gathered through site visit for comprehensive investigation of the

physical environmental status of the farm operation(s) and that of the immediate surroundings and

discussions with the company managers, staff, and other stakeholders.

Project Site and Topography

The Vegpro LTD Biogas Plant will be located within its Gorge farm, at the south-western

end, a spot which is about 200 meters from an existing KPLC sub-station (see phot 1). The area is flat,

well drained and is currently composed of soft loamy agricultural soils like the rest of the existing

farm site.

The area is surrounded by:

• Finlays farm to the south

• Karuturi Housing estate to the west

• The rest of the other sides are Vegpro farms i.e. Longonot farm and Gorge farm.

The current activities going on in the area are normal farm operation including water irrigation. To

access the KPLC sub-station for the power transmission, either Vegpro must use KPLC’s existing

way leaf of must ask either Finlays or Karuturi to provide a way leaf on their areas.

Drainage System and Hydrology

All the surface water drains to an existing drainage system within the farm. The farm has

established an elaborate drainage system for rainwater which is stored in a dam situated at the

eastern side of the location where the plant will be constructed. There will be no waste water

generation other than liquid fertilizer which will immediately be used in the farms.

Vegetation

The proposed site for the project is a farm site and therefore there are no existing vegetation

other than farm weeds.

Rainfall and Climate

The area has a relatively cool weather, with temperatures ranging between 10 0C and 22 0C

over the year. The Because of farming activities the area can be very dusty, especially during dry

season. The wind direct in the area has no distinct direction but changes depending on pressure

changes from time to time during the day.

The rain pattern appears to be spread through the year. Two seasons with the maximum

amounts of rain are between March and May and October and December. The lowest rainfall is

recorded in September at below 200 mm while the highest is recorded in April at slightly below 1200

mm.

(Source: http://www.world66.com/africa/kenya/theriftvalley/naivasha/lib/climate)

Soils

Naivasha is a small town located about 70 km. North West of Nairobi, and sits on the floor of

the Great Rift Valley. The farm being situated near Mt. Longonot, the majestic 11,000 ft. dormant

volcano, thrives in the fertile volcanic soils. (Source: http://www.kiangazifoundation.org/who-we-

are/about-naivasha.html)

The plant is not expected to have adverse impact on the soils in the site because the soil will

only be disturbed during the laying of the foundation and from construction activities.

Water Resources

The main water source for the farm, other than rain water, is Lake Naivasha. The plant will

however not have any effects on the existing water abstraction situation as the plant does not need

water for feedstock digestion.

Bio-diversity

There is no major biodiversity within the farm site where the new equipment will be located.

Air Quality

The air quality will be affected during construction due to a lot of dust from excavation. It is

recommended that the ground be watered prior to excavation activities to preserve air quality.

Land Use Activities

The dominant land use in the area is predominantly commercial scale agriculture. The most

vibrant and fastest growing commercial activity is carried out by the large multinational owned flower

and horticulture farms nestled along the shores of Lake Naivasha. These large scale farms produce

almost exclusively for the European market earning Kenya US$ 150 million per year and employ up

to 60,000 farm workers. These farms draw water for irrigation from Lake Naivasha all year round,

resulting in receding water levels over the years.

(Source: http://www.kiangazifoundation.org/who-we-are/about-naivasha.html)

The proposed site, however, will be located on a very small section of the Gorget farm where

its effect on the farming activity will be completely insignificant.

Areas of Cultural Importance

The proposed project will be located within the existing Gorge farm compound where there

are no areas of cultural importance.

Environmentally Sensitive and/or Significant Areas

The proposed site will be located where there are no environmentally sensitive or significant areas.

Economic Development

The area is currently being used for large scale agricultural activities. The proposed site,

however, will be located on a very small section of the Gorge farm and will not have any effects on

the existing farming activities.

Social Issues

Currently there are no social issues associated with the site.

PROJECT DESCRIPTION AND MAGNITUDE OF OPERATIONS

General Description, Ownership and Project Location

Vegpro Limited deals in fresh produce, flowers and logistics from Kenya. After the fresh

produce and flowers for export are produced, waste/feedstock left are first decomposed at the

decomposing site and used as fertilizer for the farm.

Approximately 23,024 tonnes per year of fresh feedstock is available at a dry matter (DM)

content of 23.7%, giving 5,448 tonnes per year of dry matter (DM). In order to utilize the feedstock

and diversify revenue sources, the company proposes to set up a biogas plant within its Gorge farm,

at the south-western end, a spot which is about 200 meters from an existing KPLC sub-station.

Extensive testing of this material in laboratory scale digesters at Southampton University,

UK, has shown that this feedstock will yield 421m3/h of biogas of which 232m3/h will be methane.

Using the proposed gensets this methane will yield 11,800 Mwhrs per year of electricity. If this

energy was produced using diesel generators it would represent more than 3 Million litres of diesel.

The project proposal is for an on-farm anaerobic digestion (AD) plant comprising a system of

hydrolysers and a digester to produce biogas, an engine driven electricity generating set (genset) and

other associated equipment to operate and manage the process. The whole project is designed to be

sited on a pre-leveled area on the farm. This project will establish an environmentally friendly and

sustainable form of electricity (and heat) production from the feedstock, also known as substrate once

loaded into the digestion system. The AD process uses naturally occurring bacteria and other

microbes to convert organic matter in the feedstock into:

• Biogas, which is an energy rich mixture of methane and carbon dioxide which is suitable for

use as a fuel to generate electricity and heat.

• Nutrient rich solid state and liquid state fertilisers to be used on the farm in place of purchased

chemical fertilisers.

The resulting biogas is burned in an engine driven generating set (genset) to produce electricity,

mostly for use on the farm with the balance available for export to the grid. The genset also produces

heat in the form of engine cooling water and some of this will be used to heat the hydrolysers to 50-

55C and to maintain the digester at a temperature of ~ 40-45C.

The pre-hydrolysis of the feedstock material in the two hydrolysers ensures significantly

higher biogas production and shorter residence times than conventional AD plants, maximizing

biological degradation and stabilization, minimizing capital costs and plant footprint and increasing

electricity (and heat) production. The anaerobic digestion (AD) plant will be owned and run by

Vegpro Limited within its Gorge farm where it will also be located.

Nature of the Project and Proposed Development

The objective of the project is to satisfy the ever increasing demand for electricity in Kenya

with a clean alternative to the more fossil-fuel based electricity component of the Kenyan national

grid. The project aims to generate electricity from renewable sources. If this energy was produced

using diesel generators it would represent more than 3 Million litres of diesel Per year.

The plant will cover an approximate area of 80m by 55m. Construction work will include soil

excavation and concrete work, using heavy construction equipment. This will be followed by

installation of plant machinery before plant operation can commence.

The proposed project, the anaerobic digestion (AD) plant, is a power generation project

involving the generation of electricity using feedstock on site.

The principal components of the complete AD system are:

• A Feedhopper Unit with Shredder and Feeder

• 2 x Hydrolyser Tanks

• 1 x Digester Tank

• 1 x Recyclate Tank

• 1 x Biogas Store

• 1 x Central Building

• Main Pump System

• Main Plant Control System

• 1 x Solids Separator

• 3 x Outdoor packaged gensets

• 1 x Main Flare

Feedhopper Unit with Shredder and Feeder

This unit is a stationary system into which the feedstock is loaded by a conventional

tractor/loader with front bucket. The hopper has a volume comfortably in excess of that needed for a

single feed cycle of the AD plant. At its outlet an uptake auger “feeds” Hydrolyser 1 through a simple

water lock. In normal

operation at Longonot the

Feedhopper unit operates

twice per day for 1-2 hours

during the 2 feed cycles.

Feedstock is moved out of

the hopper and through the

shredder unit where it is

reduced in size to promote

digestion. This material is

mixed with liquid from the

recyclate store and is

pumped into Hydrolyser 1

through the Main Pump.

Hydrolyser 1

Hydrolyser 1 is a concrete tank. It is a sealed unit to prevent the escape of biogas or ingress

of air. It is fitted with 2 x stirrer units, an over/under pressure valve working on the water lock

principal, a heating coil for achieving and maintaining an internal temperature of 50-55C. There are

numerous small ports and tappings for fitting instrumentation such as level and temperature sensors

and transparent viewing ports. There are a number of openings to allow access for maintenance. The

tank has a corrosion resistant coating on the inside to cope with the acid conditions (pH 4 – 6) and a

minimum of 4cm of thermal insulation on the outside. There are also fixed inlet and outlet ports

connecting the tank to the Main Pump via a system of automatic and hand valves and a gas outlet pipe

connected to the Biogas Store.

Hydrolyser 2

Hydrolyser 2 is identical to Hydrolyser 1 except for the position of inlet and outlet ports,

instrumentation, etc.

Photo 7: Photo showing the feed hopper unit

Digester

The digester is a concrete

tank. It is a sealed unit to

prevent the escape of biogas

or ingress of air. It is the

heart of the digestion plant

and is controlled to produce a

high and constant volume of

biogas. To achieve this, the pH must be maintained at 6.5 – 8. It is fitted with 4 x stirrer units and an

over/under pressure valve working on the water lock principal. There are numerous small ports and

tappings for fitting instrumentation such as level and temperature sensors and transparent viewing

ports. There are a number of openings to allow access for maintenance. The tank has a corrosion

resistant coating on the inside and a minimum of 4cm of thermal insulation on the outside. There are

also fixed inlet and outlet ports connecting the tank to the Main Pump via a system of automatic and

hand valves and a gas outlet pipe connected to the Biogas Store. In normal operation the digester is

maintained at a temperature of 40-45C simply by mixing warmer material from Hydrolyser 2 with

existing material in the tank. The 3,000m3 of tank contents and the outer insulating layer ensure a

heat loss equivalent to < 1C per day so no heating of the tank is required and no heating system is

fitted. The four stirrer units operate intermittently and sequentially on an automated cycle to produce

a slow, steady, circular movement of substrate within the tank.

Recyclate Tank

Excess substrate from the digester is piped to the recyclate tank. A simple, screw press type

separator is fitted to the plant so that the mixture of solid and liquid leaving the digester can be

separated into liquid and solid fertiliser fractions. It is necessary to store a small amount of the liquid

fertiliser as some is needed to mix with fresh feedstock in the Feedhopper system during each feed

cycle; this is stored in the recyclate tank which has sufficient liquid for 3 - 4 day’s use.

Central Building

The 2 hydrolyser tanks, the Digester and the Recyclate Tank are positioned on site such that a

building can be erected between them using the outside of the tank walls for part of the building

structure. This building is used to house the Main Pump assembly, the Main Plant Control System

and many of the minor services required by the plant, such as the compressed air system. This design

ensures that the maximum amount of equipment is sited indoors free from the adverse effects of

weather.

Photo 8: Photo showing the digester tanks

Biogas Store

Biogas produced by the digestion plant is stored in a membrane type gas holder which is

situated on the roof of the digester. The store has is fitted with a system of gas content monitors

which detect the rate of gas production relative to use. This signal is used to control the injection of

material from Hydrolyser 2 into the digester to achieve the desired rate of gas production. The

volume of biogas stored is sufficient for ~ 8 hours

operation when meeting the farm’s maximum

electricity demand and longer at reduced demand.

This allows for fluctuations in biogas supply and

demand to be compensated for and for routine

maintenance operations on gensets and hydrolyser

and digester accessories. It also minimises the

flaring of excess biogas, which is wasteful, and

minimises the need to vent gas under emergency

conditions.

Main Pump Assembly

The AD plant is provided with a Main Pump

Assembly situated in the Central building. This

comprises a powerful Rotocut type centrifugal pump

with inlet and outlet manifolds, stone trap, etc. This

pump is capable of chopping any oversize clumps of

material that may have agglomerated in any of the

tanks. The inlet and outlet manifolds have multiple

ports individually connected to all of the tanks and

system inlets and outlets and individually controlled by pneumatically operated valves so that the

pump can be programmed to move tank contents to and from anywhere on the plant. The Main Pump

operates intermittently throughout each 24 hour day to meet the needs of normal operation of the plant

and also allows for individual tanks to be emptied for inspection and repair whilst maintaining plant

operation under a wide variety of circumstances.

Photo 9: Photo showing the storage dome

Photo 10: Photo showing the main pump

passembly

Main Plant Control System

The AD plant is automatically

managed and controlled by a computer

system situated in the Central building.

Sensors in the biogas store, the 2 Hydrolysers

and the Digester monitor the pH, temperature,

movement of feedstock and substrate, tank

levels and biogas production and

consumption. This control system provides

for continuous and fully automatic operation

of the plant to achieve a high and continuous

production of biogas. It also monitors correct

operation of the plant and individual items of plant equipment and ensuring safe plan operation at all

times and alerting operators to any potential problem. The control system also provides an automatic

feed cycle for fresh material, which simply requires the operator to fill the Feedhopper with fresh

feedstock using a bucket loader, and for continuously controlling the operation of the tank stirrers.

The Control System also records and analyses data collected from all of the sensors mounted on the

AD plant so that a complete history of plant operation is available and operating trends can be plotted.

Information is provided to operators via local and remote screen interface(s) allowing the operator to

view all of the current and historical operating parameters in the plant.

Solids Separator

The AD plant is fitted with a simple

screw press type solids separator for

separating the solid and liquid

fertiliser fractions of the material

leaving the digester. The solids

fraction is dropped into a small

bunker adjacent to the Separator and

is ready for immediate use as a

fertiliser or for adding to the farm’s

existing composting operation. The liquid fertiliser fraction and is also available for immediate use

as a fertiliser. However, a proportion of this liquid is required for mixing with fresh feedstock so a

Recyclate Tank is provided to store sufficient liquid for this purpose.

Photo 11: Photo showing the main control system

Photo 12: Photo of the separator

Electricity Generating Sets (CHP Units)

The AD plant will eventually be fitted with 2 site rated outdoor packaged generating sets,

providing an electrical capacity comfortably in excess of biogas production to cover maintenance

periods, etc. The gensets will be fitted with full

heat recovery, distribution and cooling systems so

that they can operate in Combined Heat and Power

(CHP) mode. The gensets will be fully outdoor

packaged to provide full weather protection for the

units and their accessories and full soundproofing

for the protection of the environment. These

gensets have been selected to provide an operating

efficiency (to electricity) of more than 40% over a

wide operating range to maximise electricity

production from the available biogas. Each genset

is equipped with its own microprocessor based control system controlling the gensets themselves and

their ancillary systems (pumps, water coolers, intercoolers, oil coolers, gas carburettors, ignition

systems, etc.). All information from the control system is available on a screen interface and this

information can be provided to remote screens and to the plant’s data logging system.

Main Flare

The AD plant is fitted with a Main Flare. This unit can take

biogas from the plant and burn it under controlled conditions to

achieve complete combustion with low emissions. The flare unit can

be used to burn excess biogas in circumstances where the gensets are

not running but it is desired to keep the biogas plant running at full

output. The flare will also be activated if the Control System detects

excessive gas pressure in the plant.

Photo 13: Photo showing the cogeneration sets

Photo 14: Photo of the flaring

unit

Photo 15: Aerial layout of the farm showing the proposed location of the AD plant

Site Description

The AD plant will be sited in one corner of the Longonot/Gorge site in reasonable proximity

to the adjacent KPLC switchyard. The design footprint of the AD plant and associated access and

maintenance roadways is the minimum required for efficient management of the plant and its

associated processes. In designing the plant care has been taken to keep structures compact and the

overall footprint as small as practical. The overall scale of the plant ensures that there will be no

significant increase in visual impact beyond that created by existing developments on the

Longonot/Gorge and existing sites. The current activities going on in the area are normal farm

operation including water irrigation.

Process Description

The type of AD plant chosen for this project features 2 x Hydrolysers which are separate from

the main Digester tank so that digestion takes place as a staged process with each stage occurring

under optimum but different conditions. The two Hydrolysers are allowed to become acidic through

natural biological action which promotes the breakdown of the substrate and maximises the

production of methane in the digester. The volume of the 2 hydrolysers, 2 x 471m3, gives a nominal

residence time of the substrate in the two tanks as 3 days. The use of 2 hydrolysers instead of a single

larger unit prevents fresh feedstock being passed straight to the digester without being pre-treated.

The residence time of the substrate in the Digester is 15 days.

During plant operation the stirrer units operate intermittently and sequentially on an

automated cycle for approximately 5 minutes every ½ an hour to maintain homogenisation and

temperature of the substrate. Stirrers may also be activated in exceptional circumstances, e.g. if

falling gas production is detected.

The AD plant is designed so that it can operate continuously and automatically at its

maximum capacity or to meet any electrical demand lower than this whilst only intermittently loading

feedstock into the Feedhopper. Continuous operation with intermittent loading is achieved as follows:

• Immediately following a feed cycle the status of the 2 Hydrolysers and the Digester is that

they are all 100% full. During normal operation material is fed from Hydrolyser 2 to the

Digester to maintain the desired biogas production rate as determined by the plants

instrumentation and Control System. This is a semi continuous process and material will

be moved to the digester at roughly 30 minute intervals to achieve steady gas biogas

production. Excess material in the digester leaves through the overflow pipe and water

lock to maintain a constant digester level. During this operating phase the level in

Hydrolyser 2 falls as material is removed; on a plant with 12 hours between feed cycles ~

130m3 of material will have been forwarded to the digester so Hydrolyser 2 will be ~

80% full at the end of this period.

• During (1) Hydrolyser 1 remains full and so all feedstock is subjected to 12 hours of

hydrolysis fermentation.

• When the operator selects the next feed cycle the operating sequence changes temporarily as

follows. Initially the only activity is that Hydrolyser 1 feeds material to Hydrolyser 2

until it is full. This leaves Hydrolyser 1 80% full and Hydrolyser 2 100% full. When this

action is complete Hydrolyser 2 and the Digester return to normal operation exactly as per

(1) above. In addition to this the Feedhopper system is then activated and a mixture of

fresh feedstock and liquid from the Recyclate Store is pumped into Hydrolyser 1. When

Hydrolyser 1 is full the plant returns to normal operation exactly as per (1) above.

• During (3) ~ 20% fresh material and recyclate is introduced to Hydrolyser 1 reducing its

temperature. This is automatically compensated for by the Control System which

introduces genset cooling water to Hydrolyser 1’s heating coils until the desired

temperature has been re-established.

• During this whole process the only action required by plant personnel is to top up the

Feedhopper with fresh feedstock using a bucket loader and to select the feed cycle at

roughly 12 hour intervals. All other plant operation is completely automated.

• The electricity generated will be metered at various locations to determine the quantity used

internally or exported to the grid.

It is expected that apart from the electricity used by the plant itself, the rest will be fed into the

national grid and Vegpro’s electricity consumption will be netted off from what it fed into the grid

Sources of Raw Materials

Every day, the Longonot farm generates approximately 63 tonnes (23,024/365) of feedstock.

Besides this, more than 20 tonnes of feedstock is received daily from Van Den Berg, a neighbouring

flower farm who uses the Longonot farm to dispose their feedstock since they have no space. This

makes more than 80 tonnes per day.

The input to the Biogas plant will be the over 80 tonnes per day of feedstock generated from

the two farms.

Waste Generation

The main wastes to be generated by the biogas plant will be wash water used to clean the

plant. The solid and liquid fertilizers are also by-products of the plant, but will be used in the farm.

The wash water from the plant will be directed to an existing drainage system.

Project Construction

Construction Inputs

Construction will require the following inputs:

• Some raw construction materials such as ballast, cement, stones, sand, and steel since

the foundation is already in place

• Construction labour force (both semi-skilled and skilled)

• Some water for construction purposes, especially for plinths and other equipment mounting

points

• Heavy machinery (hoisting equipment and delivery trucks)

Construction Activities

Construction activities will involve the following:

• Site preparation, including construction of plinths and equipment mounting points

• Procurement and delivery of construction materials

• Storage of materials, including fuels

• Construction, with significant welding activities

• Disposal of construction wastes

• Completion of the development and commissioning

Current Status of the Project and Construction Period

The project has evolved from preliminary through to final detailed design stages. It is not

known how long the construction period is expected to last but construction is expected to begin from

the time a NEMA license is issued. Most of the work will be carried out during standard working

hours (from 0800hrs to 1700hrs).

Project Implementation and Operation

The project implementation and operation phase is covered under 4.4 to 4.6 above.

Project Budget

The total project budget is estimated at USD 1.4million.

Project Lifetime and Decommissioning

This has not been established as at now but a full environmental impact assessment will be

conducted before decommissioning in order to ensure that it is carried out in environmentally

responsible manner.

ANALYSIS OF ENVIRONMENTAL IMPACTS

The Vegpro Biogas Plant will be located within its Longonot farm, at the south-western end, a

spot which is about 200 meters from an existing KPLC sub-station. The area is flat, well drained and

is currently composed of soft volcanic soils like the rest of the existing farm site.

The potential environmental impacts mainly relate to construction, operation and

management of the cogeneration plant as opposed to the project siting and site preparation. These

are:

• The construction activities, waste generation and their management.

• The operations of the biogas plant, waste and their management.

During the construction phase, the most important aspect is occupational health and safety of all

involved in the activity. A lot of soil is expected from excavation, some waste from construction

materials and off cuts are expected. High standards of health and safety and full compliance with the

Factories and Other Places of Work Act will be required as a mitigation measure.

During operation, no significant waste will be generated. However, the following were taken into

consideration when analyzing and assessing the significance of the impacts that may be created:

• Loading and Transportation of Feedstock to the AD Plant

This project will use biomass feedstock materials produced on-farm and that from Van Den Berg.

This material is currently used on-farm in a composting operation. No additional environmental

impacts will arise from transporting the material to the AD plant instead of the composting operation;

all operations will remain on site using normal farming equipment and practices.

• Transportation and End Use of Liquid and Solid Fertilisers

The proposed AD plant produces ~ 15,500m3 per year of mixed solid and liquid fertiliser. This

material is automatically separated into solid and liquid fractions for use as solid and liquid fertilisers.

It is proposed that all of this material will be used on-farm as part of normal farming operations,

displacing the need to transport in some of the chemical fertilisers already used on site. The solid

fertiliser will be transported to cultivated areas or the composting operation using farm vehicles. The

liquid fertiliser will be transported and used by the farm’s existing irrigation system. Any marginal

increases in the use of farm vehicles and irrigation systems will be more than offset by reductions in

the use of delivery vehicles for chemical fertilisers. There will be NO additional environmental

impacts from the on-site transportation of solid and liquid fertilisers produced by the AD plant.

• Odour Production and Control

Odour control is a key feature of the proposed plant’s design. The process chosen is biologically

aggressive in degrading the substrate and this, together with adequate retention time, ensures the

maximum possible yield of gas and the minimum possible odour potential in the final substrate.

Odour control and operating efficiency are closely linked and the chosen technology typically yields

20% more methane than more conventional systems, reducing the potential for odour even further. In

addition to the applicant’s desire to achieve the highest possible plant operating efficiency some odour

abatement measures have been included in the plant design. They are listed in the environmental

aspects and impacts (EA&I) in table 1 below.

• Dust Production and Control

The AD process for the Gorge site is essentially a wet process. Feedstock from the farm needs to

be used in as fresh (wet) a condition as possible to prevent rotting. The feedstock material is 75-80%

water so there is no possibility of dust generation during feedstock storage (short term) and handling.

Similarly, the fertiliser products are both wet, even the solid fraction is 70% water, so no dust can

arise from the storage or use of this material. The proposed AD plant site is rural and contained

within land occupied by the applicant. For these reasons there is NO risk of dust nuisance from this

project and NO special dust control measures are needed on site.

• Noise Production and Control

There are four main items of equipment in the AD plant that could give rise to the generation of

noise; Main Pump, stirrers, Feedhopper and Gensets. The Main Pump is situated in the Central

Building which is formed from the walls of the 4 AD system tank walls. These tanks are full of sound

deadening liquid. The Main Pump operates intermittently and is considered to produce NO noise and

NO abatement measures are necessary.

The stirrers and feedhoppers themselves are propeller like units which operate at very low speed,

~ 40 rpm, and are submerged in liquid. The stirrers themselves produce NO noise. However, the

stirrers are electrically driven via gearboxes and these drive systems are mounted on the outside of the

tanks. The drive systems will produce noise typical of electric motors and gears, which, due to its

frequency content is easily attenuated by ~ 30dB by a typical acoustic enclosure. The proposed AD

plant site is contained within land occupied by the applicant so the risk of unattenuated noise nuisance

at the site boundary is LOW. If noise levels at the site boundary are measured as being unacceptable

typical acoustic enclosures could be fitted to the offending stirrer(s) to achieve acceptable noise

levels.

The Gensets proposed for this project are outdoor packaged in accoustic enclosures and fitted

with roof mounted cooling systems and exhaust systems which discharge > 3m above ground level.

The noise output from the complete genset system is 60dB(A) at 1m from the enclosure wall at 1.2m

above ground level. The proposed AD plant site is contained within land occupied by the applicant so

the risk of genset noise nuisance at the site boundary is LOW. If noise levels at the site boundary or

any receptor are measured as being unacceptable additional noise mitigation measures would have to

be introduced. These could be fences, earth banks, tree plantations, etc. Any of these could also be

used to adjust the visual impact of the development. The most likely impacts are described in Table 1

below. Some are short term and a few are long term.

STAKEHOLDER COMMENTS

Stakeholders / neighbours were visited individually to inform them about the project and its

potential impacts. The method for collecting their concerns was through a face to face interview.

Generally, they were positive and no to the project’s development were raised. A few issues were

however raised by some of them. The following are the details of what the stakeholders felt:

Mr. Gilbert Bii – Van Den Berg LTD

• He felt the positive impact would be the assurance that his feedstock would be going for the

right use.

• He also felt that this would ensure proper usage of waste. This would ensure reduction of lake

pollution since floods would not sweep the feedstock wastes to the lake.

Ms Everlyne Silali – Research Officer, Kenya Wildlife Services (Hell’s Gate)

Responded that there would ease off some power demand burden from KPLC’s main grid.

She however had some concerns as follows:

• Fear of holding raw materials overnight attract their wild animals, especially baboons,

resulting in a conflict between KWS and the Longonot Farm.

• The facility should be properly fenced to make it baboon proof.

• Generation of punget smell in the event of holding of waste.

• Liquid discharge in to the lake through normal drainage system.

• Increased water usage resulting in more water abstraction from lake.

Mr. Johnson Maina – Service Manager, Finlays

He felt this was a good idea which was long overdue. He mentioned they had thought about

the same but never went far as they were still contemplating approaching the other neighbours so they

could pull resources together. To him, this project would increase power availability for all.

He was however, concerned that the transportation of feedstock from Van Den Berg would

litter the main road. This would increase the green leaf litter from that which Karuturi trucks are

already putting.

Mr. Amos Otieno – Farm Manager, Kedong Ranch

He had all the support for the project. No concerns at all.

Robert van Paul, Director Business operations, Sher Karuturi

He said this was a very positive move that should be supported by all. He even felt that

Vegpro should consider incorporation Karuturi so that they can expand the capacity of the plant.

TABLE 1: ENVIRONMENTAL ASPECTS, IMPACTS AND MITIGATION

# Environmental

Issues

Aspect Impact Mitigation

1 Surface

water

quantity &

quality

• Increased

water usage

• Discharge

of effluent

• No quality impact due to water usage as no water is required

for feedstock digestion. Only during construction. • No quality impact due to waste treatment.

• Maintain / improve the current drainage system

2 Air quality • Exhaust

gasses

• dust • Odour

• Pollution of air with exhaust gases from construction machinery during construction

• Pollution of the air with dust from construction machinery during construction

• Pollution of the air with from substrate, during operations.

• Use of properly serviced machinery during construction.

There is no added effect on environment during

operation • Pour water on the ground to avoid dust.

• Continuous regulation of gas production in the Digester to

ensure constant and effective operating conditions

• Regulation of biogas production to ensure minimum

flaring and venting of biogas

3 Soil Soil

excavation • Soil disturbance due to excavation during construction • No mitigation.

4 Noise Noise

generation

• Noise pollution from main pump, stirrers, feedhopper and

gensets

• Noise to be controlled by use of acoustic enclosures for

respective equipment or other noise mitigation measures

would have to be introduced

5 Health

and safety Occupationa

l hazard • Accidents and injuries to worker during

construction and operation of the project

• Fire outbreak

• Increased noise levels from construction equipment

• Identification and elimination of potential hazards

• Provision and use of appropriate and adequate

personal protective equipment. Ensuring contractor

compliance

• Provision of adequate fire fighting equipment

and

emergency procedures as is currently the

case

6 Socio-

economic

impacts

Increased

incomes from

project activities

• Increasing employment opportunities for the local community

• Increased revenue generation for the company which

eventually trickles down to local residents

The company should continue with diversification

programme so as to increase the revenue generation and

economic development.

7 Resource

conservatio

n

Use of

clean

technology

• Use of ash for soil pH stabilisation eliminates the

need for artificial fertilisers

• Water conservation due to reduced water consumption

• Use of renewable resources for electricity generation

reduces the pressure of fossil fuels and vegetation

Putting measures in place to ensure that operational

procedures are followed always and identification of

non- conformity identified and addressed

ENVIRONMENTAL MANAGEMENT PLAN

Item

No. Environmenta

l

Issue

Impacts Proposed Actions

Implementation

Timeframe

s

Cost Responsibility

General Remarks

1 Surface

water

quantity &

quality

• Increased water usage

• Discharge of

effluent

• Maintain / improve the current

drainage system

During

construction Contractor costs

involved are

part of contractor

costs

Contractor Water conservation will

ensure that downstream

flow is increased and

water pollution from

construction activities

does not occur

2 Air quality • Exhaust gasses

• dust • Odour

• Use of properly serviced machinery during

construction. There is no added effect on

environment during operation • Pour water on the ground to avoid dust.

• Continuous regulation of gas production in the

Digester to ensure constant and effective

operating conditions

• Regulation of biogas production to ensure

minimum flaring and venting of biogas

During

construction and

durin

g operation

Vegpro Limited

Contractor

Use of properly serviced

equipment and effective

control of dust and odour

will ensure that that

health of the workers and

individuals living in the

area will not be affected

3 Soil Soil excavation • No mitigation. During

construction All costs

involved are

part of

preliminary

contractor costs

Vegpro Limited

Contractor

Ensure effective

disposal of excavated

soils

4 Noise Noise generation • Noise to be controlled by use of acoustic

enclosures for respective equipment or other

noise mitigation measures would have to be

introduced

During operation Project developer

costs are part

of the wider

Vegpro

operations

management

costs

Vegpro Limited Ensure application of

PPEs

5

Health

and

safety

Occupational hazard • Identification and elimination of potential hazards

• Provision and use of appropriate and

adequate personal protective equipment.

Ensuring contractor compliance

• Provision of adequate fire fighting

equipment and

emergency procedures as is currently the case

Continuous - Vegpro Limited

6 Socio-

economic

impacts

Increased incomes from project activities

The company should continue with

diversification programme so as to increase the

revenue generation and economic development.

Continuous -

7 Resource

conservati

on

Use of clean

technology Putting measures in place to ensure that

operational procedures are followed

always and identification of non-

conformity identified and addressed

Continuous - Vegpro Limited • A legal register will

ensure compliance

with laid down

guidelines at all

times,

• Obtain necessary

permits where

required, e.g. Water

abstraction permit. 8 Compliance

Aspects Compliance with the legal

requirements, market

demands and ethical

obligations.

• Establish a legal register with a focus on the

critical relevant environmental laws,

• Carry out annual environmental audits as

required by law,

• Review all contractual agreements to reflect

the environmental legal requirements,

• Review a corporate environmental policy guideline,

Continuous - Vegpro Limited • A legal register will

ensure compliance

with laid down

guidelines at all

times,

CONCLUSION

The results of this study show that the proposed Vegpro Limited’s Biogas Plant will not have

a potential for serious negative environmental impacts. The project is siting within a large

commercial farm belonging to the company and the neighbours are also commercial entities where

similar activities are taking place.

The project will use renewable waste to produce energy in Kenya where at least 50% of the

energy is hydro based and very susceptible to weather patterns. The other potion is significantly fossil

fuel based thermal energy which is prone to exchange fluctuations and other political instability in

certain regions of the world. Energy source diversification is therefore very beneficial to the whole

country.

The potential adverse environmental impacts such as odour, noise, wastewater or any gas

emissions will be adequately mitigated. Plans are also in place to adequately mitigate the health and

safety impacts of the project.

From a socio-economic point of view, the project has significant economic benefits not only

to the community but also to the whole country.

The recommendations have been provided in the Environmental management Plan as

proposed actions.


Recommended