+ All Categories
Home > Documents > PROPOSED COMMERCIAL COMPLEX AT PLOT NO: C4A, SECTOR 16B, GREATER NOIDA … ·  ·...

PROPOSED COMMERCIAL COMPLEX AT PLOT NO: C4A, SECTOR 16B, GREATER NOIDA … ·  ·...

Date post: 16-Apr-2018
Category:
Upload: lyminh
View: 219 times
Download: 2 times
Share this document with a friend
79
ITHC/PRJ/16-17/EIA/58 IND TECH HOUSE CONSULT FORM 1, FORM 1A AND CONCEPTUAL PLAN FOR ENVIRONMENTAL CLEARANCE OF PROPOSED COMMERCIAL COMPLEX AT PLOT NO: C4A, SECTOR 16B, GREATER NOIDA (WEST), UTTAR PRADESH Project Proponent: M/S MAHESHWARI INFRATECH PVT LTD. EIA Consultant: Ind Tech House Consult (An ISO 9001:2008 Certified Organization) G-8/6, Ground Floor, Sector 11, Rohini Delhi – 110 085 Tel: +91 11 2757 1410, 6460 7252 Fax: +91 11 2757 2241 Email: [email protected] August, 2016
Transcript

ITHC/PRJ/16-17/EIA/58 IND TECH HOUSE CONSULT

FORM 1, FORM 1A AND CONCEPTUAL PLAN

FOR

ENVIRONMENTAL CLEARANCE

OF

PROPOSED COMMERCIAL COMPLEX

AT PLOT NO: C4A, SECTOR 16B, GREATER NOIDA (WEST),

UTTAR PRADESH

Project Proponent:

M/S MAHESHWARI INFRATECH PVT LTD.

EIA Consultant:

Ind Tech House Consult

(An ISO 9001:2008 Certified Organization)

G-8/6, Ground Floor, Sector 11, Rohini Delhi – 110 085

Tel: +91 11 2757 1410, 6460 7252 Fax: +91 11 2757 2241

Email: [email protected]

August, 2016

ITHC/PRJ/16-17/EIA/58 IND TECH HOUSE CONSULT

For and on behalf of: Ind Tech House Consult

Approved by: Mr. Arvind Narayan Devikar

Signed:

Position: EIA Coordinator

Date: August, 2016

PROPOSED COMMERCIAL COMPLEX AT PLOT NO: C4A, SECTOR 16B, GREATER

NOIDA (WEST) UTTAR PRADESH

Project Proponent:

M/S MAHESHWARI INFRATECH PVT LTD.

This report has been prepared by Ind Tech House Consult with all reasonable skill, care and diligence within the terms of the contract with the client, incorporating our general terms and conditions of business and taking account of the resources devoted to it by agreement with the client.

We disclaim any responsibility to the client and others in respect of any matters outside the scope of the above.

The document has been prepared for the titled project or named part thereof and should not be relied upon or used for any other project without an independent check being carried out as to its suitability and prior written authority of Ind Tech House Consult being obtained. Ind Tech House Consult accepts no responsibility or liability for the consequences of this document being used for a purpose other than the purpose for which it was commissioned. Any person using or relying on the document for such other purpose agrees, and will by such use or reliance be taken to confirm his agreement to indemnify Ind Tech House Consult for all loss or damage resulting there from. Ind Tech House Consult accepts no responsibility or liability for this document to any party other than the person by whom it was commissioned.

ITHC/PRJ/16-17/EIA/58 IND TECH HOUSE CONSULT

Declaration by Experts Contributing to the Report of Proposed Commercial Complex at Plot No: C4A, Sector 16B, Greater Noida (West) Uttar Pradesh I, hereby, certify that I was a part of the EIA team in the following capacity that developed the above Report.

EIA coordinator: Mr. Arvind Narayan Devikar Signature and Date Associate Coordinator: Mr. Soumya Dwivedi Functional Area Experts:

S. NO.

Functional areas

Name of the expert/s Signature and date

1 WP Mrs. Supriti Guha (FAE) Mr. Soumya Dwivedi (Team Member)

2 MSW Mrs. Supriti Guha (FAE)

Mr. Soumya Dwivedi (Team Member)

3 LU Mr. Rajveer Singh (FAE)

Mr. Manish Shukla (Team Member)

4 AP Mr. Suman Banerjee (FAE)

Mr. Soumya Dwivedi (Team Member)

5 NV Dr. Manoj Kr. Mishra (FAE)

Mr. Suman Banerjee (Team Member)

6 EB Dr. Sameer DeshPande(FAE)

Dr. Bideh Shukla (Team Member)

7 SE Dr. Debashish Bhttacharya (FAE)

8 SC Mr. Shrikant Mishra (FAE)

Dr. Bideh Shukla (Team Member)

DECLARATION BY EXPERTS

ITHC/PRJ/16-17/EIA/58 IND TECH HOUSE CONSULT

Signature For Ind Tech House Consult

Associate Staff 1. Mr. Anand Kumar Dubey

2. Mr. Indra Sharma

3. Ms Monika Singh

4. Saurabh Bharadwaj

Monitoring Laboratory Involved Ind Research and Development House ( NABL Approved Lab)

ITHC/PRJ/16-17/EIA/58 IND TECH HOUSE CONSULT

TABLE OF CONTENTS

S. No. Contents Page No.

GENERAL

I Form 1 1 to 18

II Form 1 A 19 to 38

III Conceptual Plan 39 to 54

Annexure

A DESCRIPTIVE

Site Location Map (on Google) Annexure-A1

500 Mt Radius Map Annexure-A2

10 Km Radius Map Annexure-A3

Environmental Budget Annexure-A4

Water balance Diagram Annexure-A5

Rain Water Harvesting Calculation Annexure-A6

B LAND DOCUMENTS

Land Ownership Documents Annexure-B1

CONSULTANT DISCLOUSURE

Consultant Disclosure Annexure-C1

NABET Accreditation letter Annexure-C2

C DRAWINGS

Site Plan with Area Calculation Annexure-D1

Ground Floor Plan Annexure-D2

First Basement Floor Plan Annexure-D3

Second Basement Floor Plan Annexure-D4

Third Basement Floor Plan Annexure-D5

ITHC/PRJ/16-17/EIA/58 IND TECH HOUSE CONSULT

TABLE OF CONTENTS

S. No. Contents Page No.

GENERAL

I Form 1 1 to 18

II Form 1 A 19 to 38

III Conceptual Plan 39 to 54

Annexure

A DESCRIPTIVE

Site Location Map (on Google) Annexure-A1

500 Mt Radius Map Annexure-A2

10 Km Radius Map Annexure-A3

Environmental Budget Annexure-A4

Water balance Diagram Annexure-A5

Rain Water Harvesting Calculation Annexure-A6

B LAND DOCUMENTS

Land Ownership Documents Annexure-B1

CONSULTANT DISCLOUSURE

Consultant Disclosure Annexure-C1

NABET Accreditation letter Annexure-C2

C DRAWINGS

Site Plan with Area Calculation Annexure-D1

Ground Floor Plan Annexure-D2

First Basement Floor Plan Annexure-D3

Second Basement Floor Plan Annexure-D4

Third Basement Floor Plan Annexure-D5

M/S MAHESHWARI INFRATECH PVT LTD

PROPOSED COMMERCIAL COMPLEX AT PLOT NO: C4A, SECTOR 16B, GREATER NOIDA (WEST) U.P.

FORM-1

ITHC/PRJ/16-17/EIA/58 1 IND TECH HOUSE CONSULT

Application for Prior Environmental Clearance (EC)

FORM 1 (See Paragraph – 6 Notification dt.14th September 2006)

As amended to EIA Notification, 2006 issued vide S.O. 3067(E) on

Dt.- 01.12.2009. Basic Information S. No. Item Details

1. Name of the project/s Construction of proposed commercial complex at plot no: C4A, Sector 16B, Greater Noida (west) Uttar Pradesh

2. S. No. in the schedule 8(a)

3. Proposed capacity/area/length/tonnage to be handled/command area/lease area/number of wells to be drilled

Plot Area: 10000 sq. m. Built Up area: 58037.13 sq. m. Green Area: 1522 sq. m. Max. Building height: 62.20 m.

4. New/Expansion/Modernization New

5. Existing capacity/area etc. Nil

6. Category of the project i.e. ‘A’ or ‘B’

B

7. Does it attract the general condition? If yes, please specify.

No

8. Does it attract the specific condition? If yes, please specify.

No

9. Location

Plot/Survey/Khasra No. Plot No: C4A, Sector-16B

Tehsil --

District Dadri

State Gautam Budh Nagar, Uttar Pradesh

10. Nearest railway station/airport along with distance in kms.

Hindon Air Base, 14.53 km, NW IGI Airport is at 32.69 km South west Ghaziabad Railway Station: 5.41 Km North

11. Nearest town, city, District Headquarters along with distance in Kms.

12. Village Panchayats, Zilla Parishad, Municipal Corporation, Local body (complete postal address with telephone nos. to be given)

Greater Noida Industrial Development Authority

M/S MAHESHWARI INFRATECH PVT LTD

PROPOSED COMMERCIAL COMPLEX AT PLOT NO: C4A, SECTOR 16B, GREATER NOIDA (WEST) U.P.

FORM-1

ITHC/PRJ/16-17/EIA/58 2 IND TECH HOUSE CONSULT

13. Name of the applicant M/S MAHESHWARI INFRATECH PVT LTD

14. Registered Address A-6, Ground Floor Yojna Vihar, Master Somnath Marg, Delhi-92

15. Address for correspondence: A-6, Ground Floor Yojna Vihar, Master Somnath Marg, Delhi-92

Name Mr. Brijesh Goyal

Designation (Owner / Partner / CEO)

Director

Address A-6, Ground Floor Yojna Vihar, Master Somnath Marg, Delhi-92

Pin Code 110092

E-mail [email protected]

Telephone No. 011-43434040

Fax No. 011-22116699

16. Details of Alternative Sites examined, if any. Location of these sites should be shown on a topo sheet.

As per master plan this site is allocated for commercial activities. Hence no other site is examined.

17. Interlinked Projects Not Applicable

18. Whether separate application of interlinked project has been submitted?

Not Applicable

19. If yes, date of submission Not Applicable

20. If no, reason. Not Applicable

21. Whether the proposal involves approval/ clearance under: if yes, details of the same and their status to be given. (a) The forest (Conservation)

Act, 1980? (b) The wildlife (Protection) Act,

1972? (c) The C.R.Z. Notification,

1991?

The project land is in commercial activities as per the Master Plan and does not belong to any forest land and protected area hence mentioned approval is not required.

22. Whether there is any Government Order/Policy relevant/ relating to the site?

No

23. Forest land involved (hectares).

No

24. Whether there is any litigation pending against the project and/or land in which the project is proposed to be set up? (a) Name of the Court (b) Case No. (c) Orders/directions of the

No

M/S MAHESHWARI INFRATECH PVT LTD

PROPOSED COMMERCIAL COMPLEX AT PLOT NO: C4A, SECTOR 16B, GREATER NOIDA (WEST) U.P.

FORM-1

ITHC/PRJ/16-17/EIA/58 3 IND TECH HOUSE CONSULT

Court, if any and its relevance with the proposed project.

(I) Activity 1. Construction, operation or decommissioning of the Project involving

actions, which will cause physical changes in the locality (topography, land use, changes in water bodies, etc.)

Sl. No.

Information/Checklist confirmation

Yes/ No

Details thereof (with approximate quantities /rates, wherever

possible) with source of information data

1.1 Permanent or temporary change in land use, land cover or topography including increase in intensity of land use (with respect to local land use plan)

No Proposed development is as per local development plan of GNIDA

1.2 Clearance of existing land, vegetation and buildings?

No Since the project site is vacant, no clearance of existing land and vegetation & buildings is required as the land is free from any vegetation & structure.

1.3 Creation of new land uses?

No There will be no creation of new land use. The landuse for proposed project is in conformity with Greater Noida Industrial Development Authority Master Plan.

1.4 Pre-construction investigations e.g. bore houses, soil testing?

Yes Geotechnical Soil investigation has been carried out.

1.5 Construction works? Yes The major construction works are given below:

Site Development Road Development

• Internal roads Utilities/Services

• Water Supply

• Sewerage

• Drainage

• Rain Water Harvesting Structures and Pits

• Power supply and back up facility,

Buildings

• Commercial • Multiplex

• Parking Provisions

1.6 Demolition works? No Demolition work is not involved in the

M/S MAHESHWARI INFRATECH PVT LTD

PROPOSED COMMERCIAL COMPLEX AT PLOT NO: C4A, SECTOR 16B, GREATER NOIDA (WEST) U.P.

FORM-1

ITHC/PRJ/16-17/EIA/58 4 IND TECH HOUSE CONSULT

Sl. No.

Information/Checklist confirmation

Yes/ No

Details thereof (with approximate quantities /rates, wherever

possible) with source of information data

project, as the site has no existing building or constructed area.

1.7 Temporary sites used for construction works or housing of construction workers?

Yes Mostly, local labors will be employed. However temporary labour camps will be established for labourers and a dormitory for the site supervisors during the construction stage at project site only. All the construction activities including storage of raw materials will be confined to the storage spaces earmarked on project site only.

1.8 Above ground buildings, structures or earthworks including linear structures, cut and fill or excavations

Yes Above ground building structures will include building of 01 block. The earthwork is involved for foundation and laying of underground services etc. Excavated soil will be used for site leveling, back filling/filling and road construction. Top 200 mm layer of soil will be separately stored and used for landscaping/horticulture development work.

1.9 Underground works including mining or tunneling?

Yes Underground works includes excavation of earth for construction of foundation, water storage tank and STP.

1.10 Reclamation works? No Not involved.

1.11 Dredging? No Not involved.

1.12 Offshore structures? No Not involved.

1.13 Production and manufacturing processes?

No This is a construction of Commercial/ Multiplex project. Hence no production or manufacturing activities will take place.

1.14 Facilities for storage of goods or materials?

Yes Temporary storage facilities will be created during construction phase for storage of construction materials.

1.15 Facilities for treatment or disposal of solid or liquid effluents?

Yes Solid Waste Construction Stage : Solid waste, generated during the construction phase, will comprise mainly of construction waste. The construction waste will be reused within the site for various constructions filling work.

In addition to that there will be

M/S MAHESHWARI INFRATECH PVT LTD

PROPOSED COMMERCIAL COMPLEX AT PLOT NO: C4A, SECTOR 16B, GREATER NOIDA (WEST) U.P.

FORM-1

ITHC/PRJ/16-17/EIA/58 5 IND TECH HOUSE CONSULT

Sl. No.

Information/Checklist confirmation

Yes/ No

Details thereof (with approximate quantities /rates, wherever

possible) with source of information data

generation of small quantity of municipal waste from 112 (Camp-70, Floating-42) construction labors. It will be ensured that the generated waste will be sent to nearest designated waste storage bins. Operation Stage: Solid waste generation from the facility will be approximately 1.29 TPD including 0.59 TPD bio-degradable. Solid waste generated from the block will be collected by the dedicated and trained housekeeping staff. Twin bin systems will also be provided for segregation at sources. Recyclable wastes will be sold to vendors and non-recyclable wastes will be disposed through authorized agency to municipal waste disposal site. Biodegradable waste will be treated in organic waste converter and used as manure for horticulture development. MSW including horticulture waste will be handled as per the Municipal Solid Waste Management & Handling Rules, 2000. Sewage sludge 96 kg/day of sewage sludge will be generated which will be used as manure for plants and surplus manure will be sold to the farmers. Waste water will also be generated from construction activities, cleaning, curing washing etc. which contain suspended materials. Hazardous waste: 10.5 liters/ day of waste oil will be generated and sold to authorized recyclers. E Waste : 2.4 Kg/day of E waste will be disposed-off as per E-waste Management & Handling Rules, 2011.

M/S MAHESHWARI INFRATECH PVT LTD

PROPOSED COMMERCIAL COMPLEX AT PLOT NO: C4A, SECTOR 16B, GREATER NOIDA (WEST) U.P.

FORM-1

ITHC/PRJ/16-17/EIA/58 6 IND TECH HOUSE CONSULT

Sl. No.

Information/Checklist confirmation

Yes/ No

Details thereof (with approximate quantities /rates, wherever

possible) with source of information data

Liquid Effluent Construction Stage: During the construction stage domestic liquid effluent generation will be limited to small quantity from labor camp proposed at site. Wastewater generated from construction site contains suspended materials, and washings from various areas. Construction wastewater shall be collected in a separate basin and shall be reused after primary treatment for sprinkling on roads. Mobile toilets and potable water facilities will be provided at site during construction phase for labour and staff. Operation Stage: Approximately 263 KLD of waste water will be generated from the proposed facility. This effluent will be treated in Sewage Treatment Plant of 320 KLD. The total treated water from STP will be reused for flushing, horticulture and D. G. Cooling activities.

1.16 Facilities for long term housing of operational workers?

No Not applicable

1.17 New road, rail or sea traffic during construction or operation?

No Not applicable

1.18 New road, rail, air waterborne or other transport infrastructure including new or altered routes and stations, ports, airports etc?

No Not applicable

1.19 Closure or diversion of existing transport routes or infrastructure leading to changes in traffic movements?

No Not applicable

1.20 New or diverted transmission lines or pipelines?

No Not applicable

M/S MAHESHWARI INFRATECH PVT LTD

PROPOSED COMMERCIAL COMPLEX AT PLOT NO: C4A, SECTOR 16B, GREATER NOIDA (WEST) U.P.

FORM-1

ITHC/PRJ/16-17/EIA/58 7 IND TECH HOUSE CONSULT

Sl. No.

Information/Checklist confirmation

Yes/ No

Details thereof (with approximate quantities /rates, wherever

possible) with source of information data

1.21 Impoundment, damming, culverting, realignment or other changes to the hydrology of watercourses or aquifers?

No Not applicable

1.22 Stream crossings? No Not applicable

1.23 Abstraction or transfers of water form ground or surface waters?

No There will be no ground water extraction for the project during construction phase. During operation phase, water will be supplied by Greater Noida Industrial Development Authority.

1.24 Changes in water bodies or the land surface affecting drainage or run-off?

No Surface drainage may affect due to construction of the project. By considering run-off prior to development & run off after development there is some increment in storm water run-off. However, runoff generated from the project site during monsoon season will be used to recharge ground aquifer. Network of drainage system developed in the site will be used to collect roof as well as surface runoff. Potential Quantity of runoff will be 3747 CUM on annual basis which will be recharged to ground.

1.25 Transport of personnel or materials for construction, operation or decommissioning?

Yes During construction phase transport of personnel as well as construction materials would be required. The personnel would preferably be engaged from nearby areas. Precaution is being taken to reduce the impact of vehicular movement by trying to avoid the vehicular trips during peak hours. During operation phase, parking will be provided in Surface & basements.

1.26 Long-term dismantling or decommissioning or restoration works?

No Not applicable

1.27 Ongoing activity during No Not applicable

M/S MAHESHWARI INFRATECH PVT LTD

PROPOSED COMMERCIAL COMPLEX AT PLOT NO: C4A, SECTOR 16B, GREATER NOIDA (WEST) U.P.

FORM-1

ITHC/PRJ/16-17/EIA/58 8 IND TECH HOUSE CONSULT

Sl. No.

Information/Checklist confirmation

Yes/ No

Details thereof (with approximate quantities /rates, wherever

possible) with source of information data

decommissioning which could have an impact on the environment?

1.28 Influx of people to an area in either temporarily or permanently?

Yes Construction phase – Temporary influx of about 112 people is expected from the nearby areas.

Operation phase – 675 Peoples residential + 3046 Non Residential + 3874 Visitors

1.29 Introduction of alien species? No Not applicable

1.30 Loss of native species or genetic diversity?

No Not applicable

1.31 Any other actions? No None

2. Use of Natural resources for construction or operation of the Project

(such as land, water, materials or energy, especially any resources which are non-renewable or in short supply):

S.No. Information/checklist

confirmation Yes/ No

Details thereof (with approximate quantities /rates, wherever

possible) with source of information data

2.1 Land especially undeveloped or agricultural land (ha)

No The proposed project plot and its surrounding area have been designated for development of Integrated Sports Complex per master plan.

2.2 Water (expected source & competing users) unit: KLD

Yes Water requirement during construction phase will be met through tanker water supply.

During operation phase, fresh water demand will be met from Greater Noida Industrial Development Authority. Treated water demand for flushing, gardening and DG Set cooling shall be met from treated water from STP installed at Site.

206 KLD from treated water will be used within site premises from STP installed at site.

2.3 Minerals (MT) No Not applicable

2.4 Construction material – stone, aggregates, sand / soil (expected source – MT)

Construction materials such as Cement, Steel, Bricks, Stone aggregates, and Sand are required for construction of the project. These

M/S MAHESHWARI INFRATECH PVT LTD

PROPOSED COMMERCIAL COMPLEX AT PLOT NO: C4A, SECTOR 16B, GREATER NOIDA (WEST) U.P.

FORM-1

ITHC/PRJ/16-17/EIA/58 9 IND TECH HOUSE CONSULT

S.No. Information/checklist

confirmation Yes/ No

Details thereof (with approximate quantities /rates, wherever

possible) with source of information data

materials are being procured from local reputed licensed vendors.

2.5 Forests and timber (source – MT) No Limited use of timber will be done and it will be restricted to selected locations.

2.6 Energy including electricity and fuels (source, competing users) Unit: fuel (MT), energy (MW)

Yes Power for the proposed project will be supplied by Uttar Pradesh Power Corporation Ltd. Maximum power Demand for the proposed project is 6000 KW. DG sets of 7570 KVA will be used as power backup during power failure. HSD (low sulphur variety as per availability) fuel will be used for DG sets.

2.7 Any other natural resources (use appropriate standard units)

No --

3. Use, storage, transport, handling or production of substances or

materials, which could be harmful to human health or the environment or raise concerns about actual or perceived risks to human health.

S.No. Information/Checklist

confirmation Yes/ No

Details thereof (with approximate quantities/rates, wherever possible) with source of

information data

3.1 Use of substances or materials, which are hazardous (as per MSIHC rules) to human health or the environment (flora, fauna, and water supplies)

No Not applicable.

3.2 Changes in occurrence of disease or affect disease vectors (e.g. insect or water borne diseases)

No Not applicable.

3.3 Affect the welfare of people e.g. by changing living conditions?

No Not Applicable.

3.4 Vulnerable groups of people who could be affected by the project e.g. hospital patients, children, the elderly etc.,

No Not applicable.

3.5 Any other causes No Not applicable

4. Production of solid wastes during construction or operation or decommissioning (MT/month)

S. No. Information/Checklist

confirmation Yes/ No

Details thereof (with approximate quantities/rates, wherever possible) with source of

information data

M/S MAHESHWARI INFRATECH PVT LTD

PROPOSED COMMERCIAL COMPLEX AT PLOT NO: C4A, SECTOR 16B, GREATER NOIDA (WEST) U.P.

FORM-1

ITHC/PRJ/16-17/EIA/58 10 IND TECH HOUSE CONSULT

S. No. Information/Checklist

confirmation Yes/ No

Details thereof (with approximate quantities/rates, wherever possible) with source of

information data 4.1 Spoil, overburden or mine wastes No Top soil generated during earth

excavation will be stacked, covered, and preserved for reuse as top layer for horticulture development. Remaining soil will be used for site leveling, back filling/filling in raft and road construction.

4.2 Municipal wastes (domestic and or commercial wastes)

Yes Construction Phase: Municipal solid waste – 27.3 kg/day Operation Phase: Municipal solid wastes – 1.29 TPD. Wastes includes paper, Reapers, plastic cans etc. and wastes from street sweeping. Proper management will be done by the Greater Noida Industrial Development Authority.

4.3 Hazardous wastes (as per Hazardous Waste Management Rules)

Yes Waste oil 10.5 Lts on daily basis from DG sets will be the only hazardous waste generated from the project. This waste oil will be carefully stored in HDPE drums in isolated covered space and sold to recyclers authorized by CPCB / SPCB. Suitable care will be taken so as to prevent spills/ leaks of used oil from storage.

4.4 Other industrial process wastes No Not applicable

4.5 Surplus product No Not applicable

4.6 Sewage sludge or other sludge from effluent treatment

Yes Waste water will be treated in proposed on-site STP of 320 KLD.

4.7 Construction or demolition wastes Yes Demolition work is not involved. Construction Work: Excavated soil will be used for landscaping and back filling. Other construction waste like bricks, concrete etc will be used in sundary / road works / manholes etc. Gunny bags, cardboards will be sent to authorize recycler. The inert waste will be sent to land fill site.

4.8 Redundant machinery or equipment No Not applicable

M/S MAHESHWARI INFRATECH PVT LTD

PROPOSED COMMERCIAL COMPLEX AT PLOT NO: C4A, SECTOR 16B, GREATER NOIDA (WEST) U.P.

FORM-1

ITHC/PRJ/16-17/EIA/58 11 IND TECH HOUSE CONSULT

S. No. Information/Checklist

confirmation Yes/ No

Details thereof (with approximate quantities/rates, wherever possible) with source of

information data 4.9 Contaminated soils or other

materials

No Not applicable

4.10 Agricultural wastes No Not applicable

4.11 Other solid wastes No Not applicable

5. Release of pollutants or any hazardous, toxic or noxious substances to air

(Kg/hr)

S.No. Information/Checklist

confirmation Yes/ No

Details thereof (with approximate quantities/rates, wherever possible) with source of

information data

5.1 Emissions from combustion of fossil fuels from stationary or mobile sources

Yes Emission will be from: � Stationary Sources: DG sets 7570

KVA � Mobile Sources: Vehicular

emissions CPCB approved DG sets with acoustic canopy will be used only during power failure.

5.2 Emissions from production processes

No Not applicable

5.3 Emissions from materials handling including storage or transport

No Fugitive dust emission due to handling and loading - unloading activities is envisaged during construction. Frequent water sprinkling is being done to minimize the fugitive emissions.

5.4 Emissions from construction activities including plant and equipment

Yes Margi

nal

During the construction phase, major emission will be in the form of fugitive dust, use of DG sets and transportation of construction material.

5.5 Dust or odours from handling of materials including construction materials, sewage and waste

Yes The project may cause rise in dust levels during construction phase. Precautions are being taken to reduce dust generation during construction phase:-

• RMC use will reduce the handling of cement, sand and concrete thus dust emission will be minimized.

• Tarpaulins will be used to cover trucks carrying debris.

M/S MAHESHWARI INFRATECH PVT LTD

PROPOSED COMMERCIAL COMPLEX AT PLOT NO: C4A, SECTOR 16B, GREATER NOIDA (WEST) U.P.

FORM-1

ITHC/PRJ/16-17/EIA/58 12 IND TECH HOUSE CONSULT

S.No. Information/Checklist

confirmation Yes/ No

Details thereof (with approximate quantities/rates, wherever possible) with source of

information data Water sprinkling is being practiced at regular intervals to reduce dust emissions. Dust is likely to be generated during operation phase due to movement of vehicles and blowing of air. But the impact is negligible. Sewage generated from proposed project will be treated in onsite STP.

5.6 Emissions from incineration of waste

No Not applicable

5.7 Emissions from burning of waste in open air (e.g. slash materials, construction debris)

No Burning of any substances including biomass, slash materials and/ or construction debris will be prohibited

5.8 Emissions from any other sources No Nil

6. Generation of Noise and Vibration, and Emissions of Light and Heat:

S.No. Information/Checklist

confirmation Yes/ No

Details thereof (with approximate quantities/rates, wherever possible) with source of

information data

6.1 From operation of equipment e.g. engines, ventilation plant, crushers

Yes Noise is expected to be generated during construction phase mainly from operation of heavy machinery, DG sets, and traffic. The indicated noise levels from certain construction plants/equipment are indicated below: � Concrete Mixer - 85 dBA � Generator - 95 dBA � Pumps - 90 - 95 dBA � Trucks - 85 – 90 dBA For control of noise following measures shall be adopted:

• Properly maintained equipment with mufflers will be used.

• High noise generating construction activities would be carried out only during day time.

Workers working near high noise construction machinery would be supplied with ear muffs/ear plugs.

M/S MAHESHWARI INFRATECH PVT LTD

PROPOSED COMMERCIAL COMPLEX AT PLOT NO: C4A, SECTOR 16B, GREATER NOIDA (WEST) U.P.

FORM-1

ITHC/PRJ/16-17/EIA/58 13 IND TECH HOUSE CONSULT

S.No. Information/Checklist

confirmation Yes/ No

Details thereof (with approximate quantities/rates, wherever possible) with source of

information data During operation noise from operation of DG sets is envisaged. However, the generator sets installed will operate at noise level less than 75 dB (A) as the generators will be placed either in acoustic chambers or a canopy.

6.2 From industrial or similar processes No Not applicable

6.3 From construction or demolition Yes Noise Pollution Control: Noise pollution will be due to operation of machinery as well as transportation vehicles. As there is no habitation in nearby area hence there will be negligible impact. However following precautions shall be taken to control noise pollution:

• High noise generating construction activities would be carried out only during day time.

• Installation, use and maintenance of mufflers on equipment.

• Workers working near high noise construction machinery would be supplied with ear muffs/ear plugs.

6.4 From blasting or piling No Blasting & piling work is not involved

in the project.

6.5 From construction or operational traffic

Yes Construction Phase: Welding is light and heat generating activity during construction. Appropriate safety measures will be taken as per I.S. code and CPWD work manual.

Materials for construction work. Precautions will be taken to reduce the impact of the vehicular movement such as vehicular trips will not be at peak traffic hours.

Operation Phase: Car parking is provided on surface and in basement. Vehicular movement is restricted to roads and parking areas. Provision of soft green peripheral road side plantation will help in reduction of noise level.

M/S MAHESHWARI INFRATECH PVT LTD

PROPOSED COMMERCIAL COMPLEX AT PLOT NO: C4A, SECTOR 16B, GREATER NOIDA (WEST) U.P.

FORM-1

ITHC/PRJ/16-17/EIA/58 14 IND TECH HOUSE CONSULT

S.No. Information/Checklist

confirmation Yes/ No

Details thereof (with approximate quantities/rates, wherever possible) with source of

information data

6.6 From lighting or cooling systems No Nil

6.7 From any other sources No Nil

7. Risks of contamination of land or water from releases of pollutants

into the ground or into sewers, surface waters, groundwater, coastal waters or the sea:

S.No. Information/Checklist

confirmation Yes/ No

Details thereof (with approximate quantities/rates, wherever possible) with source of

information data

7.1 From handling, storage, use or spillage of hazardous materials

Yes The waste oil, generated during operation phase from the DG sets, will be collected and separately stored in HDPE drums, over concrete floor within the premises, before final disposal. All precautionary steps will be taken to avoid spillage. It will be directly transferred to authorized recyclers.

7.2 From discharge of sewage or other effluents to water or the land (expected mode and place of discharge)

No Sewage, generated from the complex, will be treated in proposed on-site STP of 320 KLD and recycled within the project facility for gardening, DG cooling etc.

7.3 By deposition of pollutants emitted to air into the land or into water

No Dust generation during construction phase from earthworks and movement of vehicles is a temporary phenomenon and will have short term impact during construction phase. Appropriate fugitive dust control measures, including water sprinkling of exposed areas and dust covers for trucks, will be provided to minimize any impacts. DG exhaust will be discharged at height stipulated by CPCB.

7.4 From any other sources No Not applicable 7.5 Is there a risk of long term build up

of pollutants in the environment from these sources?

No No.

M/S MAHESHWARI INFRATECH PVT LTD

PROPOSED COMMERCIAL COMPLEX AT PLOT NO: C4A, SECTOR 16B, GREATER NOIDA (WEST) U.P.

FORM-1

ITHC/PRJ/16-17/EIA/58 15 IND TECH HOUSE CONSULT

8. Risk of accidents during construction or operation of the Project, which could affect human health or the environment

S.No. Information/Checklist

confirmation Yes/ No

Details thereof (with approximate quantities/rates, wherever possible) with source of

information data 8.1 From explosions, spillages, fires etc

from storage, handling, use or production of hazardous substances

No This is a construction for commercial project and does not involve major hazardous construction activity. Hence chances of explosions, spillages, fires are minimal.

8.2 From any other causes No Nil

8.3 Could the project be affected by natural disasters causing environmental damage (e.g. floods, earthquakes, landslides, cloudburst etc)?

Yes The project area is located at seismic zone IV, according to Indian Standard Seismic Zoning Map. Suitable seismic coefficients in horizontal and vertical directions respectively, will be adopted while designing the structures. There are no chances of flood and landslide in the area.

9. Factors which should be considered (such as consequential

development) which could lead to environmental effects or the potential for cumulative impacts with other existing or planned activities in the locality

S. No. Information/Checklist

confirmation Yes/ No

Details thereof (with approximate quantities/rates, wherever possible) with source of

information data

9.1 Lead to development of supporting. facilities, ancillary development or development stimulated by the project, which could have impact on the environment e.g.:

Yes

The project will be equipped with dedicated internal road, parking, internal water distribution system, and fire fighting system, internal sewage collection network, lighting facilities, solar lighting and power backup facility.

• Supporting infrastructure (roads, power supply, waste or waste water treatment, etc.)

Yes Appropriate infrastructure like, roads, power supply and waste management will be developed within the site so that chances of occurrence of any adverse impacts are minimized.

• extractive industries No Not applicable

• supply industries No Not applicable

• other No Not applicable

M/S MAHESHWARI INFRATECH PVT LTD

PROPOSED COMMERCIAL COMPLEX AT PLOT NO: C4A, SECTOR 16B, GREATER NOIDA (WEST) U.P.

FORM-1

ITHC/PRJ/16-17/EIA/58 16 IND TECH HOUSE CONSULT

S. No. Information/Checklist

confirmation Yes/ No

Details thereof (with approximate quantities/rates, wherever possible) with source of

information data 9.2 Lead to after-use of the site, which

could have an impact on the environment

No - -

9.3 Set a precedent for later developments

Yes This is a construction project and there will be generation of employment during construction & operation phase.

9.4 Have cumulative effects due to proximity to other existing or planned projects with similar effects

No -

(III) Environmental Sensitivity

S.No. Areas Name/

Identity

Aerial distance (within 15 km.) Proposed project location

boundary

1 Areas protected under international conventions, national or local legislation for their ecological, landscape, cultural or other related value

No Not within 15 km from the project site.

2 Areas which are important or sensitive for ecological reasons - Wetlands, watercourses or other water bodies, coastal zone, biospheres, mountains, forests.

Yes Okhla Bird Sanctuary, 14.24 Km., SW

3 Areas used by protected, important or sensitive species of flora or fauna for breeding, nesting, foraging, resting, over wintering, migration

Yes Okhla Bird Sanctuary, 14.24 Km., SW

4 Inland, coastal, marine or underground waters

No Not located within 15 km of the proposed project location. Underground water is present.

5 State, National boundaries

Yes Delhi-U.P. Border, 11.15 Km., W

6 Routes or facilities used by the public for access to recreation or other tourist, pilgrim areas

No The site does no fall under any route to any pilgrim, tourist

7 Defence installations

Yes Hindon Air Force Station, 14.53 km, NW

8 Densely populated or built-up area No Density of surrounding development is as per master plan.

M/S MAHESHWARI INFRATECH PVT LTD

PROPOSED COMMERCIAL COMPLEX AT PLOT NO: C4A, SECTOR 16B, GREATER NOIDA (WEST) U.P.

FORM-1A

ITHC/PRJ/16-17/EIA/58 18 IND TECH HOUSE CONSULT

FORM-1 A (CHECKLIST OF ENVIRONMENTAL IMPACTS) 1.0 LAND ENVIRONMENT 1.1. Will the existing land use get significantly altered from the project that is not

consistent with the surroundings? (Proposed land use must conform to the approved Master Plan / Development Plan of the area. Change of land use, if any and the statutory approval from the competent authority be submitted). Attach Maps of (i) site location, (ii) surrounding features of the proposed site (within 500 meters) and (iii) the site (indicating levels & contours) to appropriate scales. If not available attach only conceptual plans.

The construction of commercial project is proposed at plot no: C4A, Sector 16B, Greater Noida (west) Uttar Pradesh. Project activity will not change the existing land use, since, the site is allocated for commercial activities as per GNIDA Master Plan. The following maps are attached. (i) Site location, (ii) Layout ( Conceptual ) plan, (iii) Surrounding features of the proposed site (within 500 meters and 10 Km, Ref.

Annexure 1.2 List out all the major project requirements in terms of the land area, built up area,

water consumption, power requirement, connectivity, community facilities, parking needs etc.

The proposed project is construction of the commercial project. Salient feature of the proposed project is given below in Table -1:

Table-1: Salient Feature of the Project

SN Description Details Unit

GENERAL 1 Plot Area 10000 SQM

2 Proposed Built Up Area 58037.13 SQM

3 Number of Building Blocks 1 NOS

4 Total no of Saleable DU's (Studio Apptts) 150 NOS

5 No of Seats in Multiplex 912 NOS

6 Max Height of Building 62.20 M

7 Max No of Floors 3B+G+15 NOS

8 Cost of Project 104 CR

9 Expected Population (675 Residential +6320 Floating) 7595 PERSONS

10 Permissible Ground Coverage Area (40%) 3982 SQM

11 Proposed Ground Coverage Area ( 39.95%) 3978 SQM

12 Permissible FAR Area (400) 39823 SQM

13 Proposed FAR Area (387.8) 38608.74 SQM

14 Basement Area (Non FAR) 15692.39 SQM

14 Other Non FAR & Services areas 3736.00 SQM

15 Proposed Built Up Area 58037.13 SQM

WATER 16 Total Water Requirement 575.58 KLD

17 Fresh water requirement (64.14% of total water req) 369.18 KLD

18 Waste water Generation 263.63 KLD

M/S MAHESHWARI INFRATECH PVT LTD

PROPOSED COMMERCIAL COMPLEX AT PLOT NO: C4A, SECTOR 16B, GREATER NOIDA (WEST) U.P.

FORM-1A

ITHC/PRJ/16-17/EIA/58 19 IND TECH HOUSE CONSULT

19 Proposed STP Capacity 320 KLD

20 Treated Water Available for Reuse 210.90 KLD

21 Recycled Water (35.86% of total water requirement) 206.40 KLD

22 Required Additional Surplus of Treated water 4.50 KLD

RAIN WATER HARVESTING 23 Rain Water Harvesting Potential 3747.36 CUM

24 No of RWH of Pits Proposed 2 NOS

PARKING

25 Total Parking Required as / Building Bye Laws 796.5 ECS

26 Proposed Total Parking 798 ECS

27 Proposed Parking on Surface 38 ECS

28 Basement Parking (2nd & 3rd Lev Mech Parking) 760 ECS

GREEN AREAS 29 Required Green Area (15% of Plot Area) 1495 SQM

30 Proposed Green Area (15.29% of Plot Area) 1522 SQM

WASTE GENERATION

31 Municipal Solid Waste Generation 1.29 TPD

32 Quantity of Hazardous waste Generation 550 LTS/DAY

33 Quantity of Sludge Generated from STP 125.0 KG/DAY

POWER 34 Total Power Requirement 6000 KW

35 DG set backup 7570 KVA

1.3 What are the likely impacts of the proposed activity on the existing facilities

adjacent to the proposed site? (Such as open spaces, community facilities, details of the existing land use, disturbance to the local ecology).

The project is being developed in accordance with GNIDA building bye laws, approved building plans and NBC - 2005 norms. The development will not cause any disturbance to local ecology and surrounding establishments. Peripheral green belt will be developed. Proposed project will provide all the basic utilities such as proper drainage, sewerage treatment & water supply system. The proposed development will have a positive impact as the project site is vacant and will be developed for commercial purposes. The project will provide organized open spaces and green areas adding to aesthetics and improvement of surrounding environment.

1.4 Will there be any significant land disturbance resulting in erosion, subsidence &

instability? (Details of soil type, slope analysis, vulnerability to subsidence, seismicity etc may be given).

The main reasons for erosion are over exploitation of groundwater, unstable slopes, landslides etc. The proposed site area is primarily a flat land and is not prone to erosion. The proposed construction will involve excavation for foundation. Excavated soil will be used for backfilling, play fields and parking area. The project would involve construction of paved areas which would reduce the chances of erosion subsidence. Subsidence was not anticipated, as ground water will not be used.

M/S MAHESHWARI INFRATECH PVT LTD

PROPOSED COMMERCIAL COMPLEX AT PLOT NO: C4A, SECTOR 16B, GREATER NOIDA (WEST) U.P.

FORM-1A

ITHC/PRJ/16-17/EIA/58 20 IND TECH HOUSE CONSULT

Structural design has already been vetted by the Govt agency nominated by local body & structural stability certificate will be submitted to local body as per rules. Soil investigation has been done. Seismo-Tectonic Appraisal of the Area: Bureau of Indian Standards (BIS) has prepared a seismic zoning map of India based on tectonic features and records of past earthquakes. The project site falls under Zone-IV as per the Seismic Zoning map of India (IS 1893, Part I, 2002.) Necessary seismic factors as per codes shall be incorporated suitably while designing the structures to safeguard against earthquake risks.

1.5 Will the proposal involve alteration of natural drainage systems? (Give details on a contour map showing the natural drainage near the proposed project site)

The proposed project activities will not cause any alteration of natural drainage system. No changes are expected outside from project premises. The project will implement planned drainage system within the site and there will be a positive change in the drainage pattern.

1.6 What are the quantities of earthwork involved in the construction activity-cutting, filling, reclamation etc. (Give details of the quantities of earthwork involved, transport of fill materials from outside the site etc.)

During construction phase, excavation is envisaged in order to provide foundations. This excavated soil will be properly stacked within the site under tarpaulin cover; and will be reused for backfilling purpose, road construction etc. The 8” top-soil will be preserved separately and will be used for landscaping purpose only. Hence, no immediate adverse impacts on the land environment are envisaged. The valuable top soil will not be dumped or wasted under any circumstance.

1.7 Give details regarding water supply, waste handling etc. during the construction

period.

� Water Supply: During construction stage, Treated waste water from the tanker water will be taken for construction works. This water is tested for fitness for construction purpose.

� Waste Generation and Handling: Excavated soil will be stored and covered at site and it will be reused for site leveling, back filling and road construction. The fertile top soil will be reused for landscaping purpose. Spillage of oil from the machinery is being properly collected in drums and disposed off. For construction laborers, proper sanitary facilities & wash areas is provided and good hygienic conditions is maintained. Handling of waste generated is being done by a good agency approved by SPCB/CPCB.

1.8 Will the low lying areas and wetlands get altered? (Provide details of how low lying

and wetlands are getting modified from the proposed activity).

There is no low lying area observed within and around the vicinity of the project site .

1.9 Whether construction debris and waste during construction cause health hazard? (Give quantities of various types of wastes generated during construction including the construction labor and the means of disposal)

M/S MAHESHWARI INFRATECH PVT LTD

PROPOSED COMMERCIAL COMPLEX AT PLOT NO: C4A, SECTOR 16B, GREATER NOIDA (WEST) U.P.

FORM-1A

ITHC/PRJ/16-17/EIA/58 21 IND TECH HOUSE CONSULT

The waste generated during construction phase can broadly be classified as construction waste and domestic waste. About 2321 MT of construction waste (Calculated using TIFAC (Technology Information, Forecasting, and Assessment Council standards, @ 40 Kg / sq m) and negligible quantity of domestic waste would be generated from labours employed at site.

Most of the construction waste generated will be used on the site as filler material for leveling and development of site and internal road. Construction waste if any remaining will be sent to an approved dumping site/landfill site through authorized agency.

Adequate labors per day will be employed during the construction stage of the project.

Required sanitary, drinking water and other requisite facilities will be provided at site. Wash areas will be constructed and good hygienic conditions would be maintained in labour camp.

2.0 WATER ENVIRONMENT

2.1 Give the total quantity of water requirement for the proposed project with the breakup of requirements for various uses. How will the water requirement met? State the sources & quantities and furnish a water balance statement. Total water requirement for this project is 575 KLD, out of which, 206 KLD of treated water from STP will be reused. The fresh water demand of 369 KLD will be met from GNIDA. Breakup of water requirements for various uses is given below. Efficient dual flushing fixtures will be provided to achieve conservation of fresh water. Detail of water requirement has been given in table – 3 below:

Table 3: Water Requirement Details of the Project

S. No. Particulars

Water requirement (KLD)

1. Total water requirement 575

2. Total treated water requirement 206

Treated waste water recycled for flushing 144

Air conditioning 220

Treated waste water recycled for landscaping within project area 8

D G Cooling 54

3. Net fresh water requirement 369

Water requirement for horticulture and dual flushing purpose will be fulfilled by treated waste water supply from on-site STP. Water Balance Diagram (attached as Annexure)

2.2 What is the capacity (dependable flow or yield) of the proposed source of water?

During operation stage fresh water will be supplied by GNIDA. Any shortfall in supply will be met from tanker supplies/extraction of potable water from tube well in the permission of CGWA.

M/S MAHESHWARI INFRATECH PVT LTD

PROPOSED COMMERCIAL COMPLEX AT PLOT NO: C4A, SECTOR 16B, GREATER NOIDA (WEST) U.P.

FORM-1A

ITHC/PRJ/16-17/EIA/58 22 IND TECH HOUSE CONSULT

2.3 What is the quality of water required, in case, the supply is not from a municipal source? (Provide physical, chemical, biological characteristics with class of water quality)

Treated water will be met through on-site STP. The quality of water would conform to the desirable drinking water standards as per IS: 10500.

2.4 How much of the water requirement can be met from the recycling of treated wastewater? (Give the details of quantities, sources and usage)

Approximately 206 KLD of treated water from proposed on-site STP will be used for flushing, D. G. Cooling and gardening.

2.5 Will there be diversion of water from other users? (Please assess the impacts of the project on other existing uses and quantities of consumption).

Fresh water conforming to the drinking water standard will be supplied by GNIDA. Therefore, no diversion of water from other user is expected and no impact on the existing users is anticipated.

2.6 What is the incremental pollution load from wastewater generated from the

proposed activity? (Give details of the quantities and composition of wastewater generated from the proposed activity).

Waste water expected to be generated from the project is 263 KLD which will be treated in on-site STP. Approx. 152 KLD treated water will be used in horticulture and dual flushing purpose.

2.7 Give details of the water requirements met from water harvesting? Furnish details

of the facilities created. As estimated, 263 KLD of waste water will be generated from the project which will be treated through proposed on-site STP. The characteristics of the wastewater and of the effluent after treatment are as follows:

Parameters Conc. Value Expected in

Wastewater Reclaimed Water Quality

mg/l mg/l

pH 6.5-8.5 7.0 to 8.5

Biochemical Oxygen Demand (BOD5) 300-500 < 5

Chemical Oxygen Demand (COD) 800-1000 < 30

Suspended Solids 250-300 <5

Oil & Grease <50 <5

2.8 What would be the impact of the land use changes occurring due to the proposed

project on the runoff characteristics (quantitative as well as qualitative) of the area in the post construction phase on a long term basis? Would it aggravate the problems of flooding or water logging in any way?

Due to construction of the project on vacant land there would be change in the runoff characteristics quantitative and qualitative as well The quantitative change: Runoff coefficient from the project site prior to development of project = 0.2 Runoff coefficient from the project site after development of project = 0.67 (Considering different coefficients for paved area, soft area, terrace etc)

M/S MAHESHWARI INFRATECH PVT LTD

PROPOSED COMMERCIAL COMPLEX AT PLOT NO: C4A, SECTOR 16B, GREATER NOIDA (WEST) U.P.

FORM-1A

ITHC/PRJ/16-17/EIA/58 23 IND TECH HOUSE CONSULT

Hence incremental runoff = 0.67 – 0.2 = 0.47 Qualitative change: Runoff from parking areas Storm water drainage & Rain water harvesting system as described in item no: 2.7 above meet quantitative, qualitative & prevention of over flooding/water logging requirements.

2.9 What are the impacts of the proposal on the ground water? (Will there be tapping

of ground water; give the details of ground water table, recharging capacity, and approvals obtained from competent authority, if any). There will be no tapping of ground water and will be strictly prohibited during construction and operation phase of the project.

2.10 What precautions/measures are taken to prevent the run-off from construction

activities polluting land and aquifers? (Give details of quantities and the measures taken to avoid the adverse impacts).

During the construction operation, Runoff from the construction site shall not be allowed to stand or enter into the roadside or nearby drain. Adequate measures shall be taken to collect such run off and either shall be reused (if possible) or disposed at the designated construction waste disposal location. Suitable garlanding drain as per the existing contours of the plot will be developed.

2.11 How is the storm water from within the site managed? (State the provisions made to avoid flooding of the area, details of the drainage facilities provided along with a site layout indication contour levels).

There will be a provision of storm water drain along the site. Storm water from run offs will be collected and channelized to common storm water collection system. Storm water from roof top of the commercial/multiplex will be collected and channelized to rain water harvesting pits. Water so collected will pass through de-silting-cum-filter chamber, oil and grease separators.

2.12 Will the deployment of construction laborers particularly in the peak period lead to

unsanitary conditions around the project site (Justify with proper explanation)

Labour camp for 70 labour will be constructed at project site. Temporary rest rooms, office and first aid/ safety office will also be provided on site. Proper sanitation facility shall also be made available on site.

2.13 What on-site facilities are provided for the collection, treatment & safe disposal of sewage? (Give details of the quantities of wastewater generation, treatment capacities with technology and facilities for recycling and disposal)

During operational phase estimated quantity of sewage to be generated on project site is 263 KLD, which will be treated in proposed on-site STP. Approx 206 KLD treated water will be used in horticulture, Air Conditioning, D. G. Cooling and flushing.

M/S MAHESHWARI INFRATECH PVT LTD

PROPOSED COMMERCIAL COMPLEX AT PLOT NO: C4A, SECTOR 16B, GREATER NOIDA (WEST) U.P.

FORM-1A

ITHC/PRJ/16-17/EIA/58 24 IND TECH HOUSE CONSULT

2.14 Give details of dual plumbing system if treated waste water is used for flushing of toilets or any other use.

Treated waste water will be used for flushing of toilets. Treated waste water will be collected and stored in underground tank. This tank will provide water for horticulture and flushing. Water for flushing will be pumped from this tank to terrace tank of each tower and will be connected to each toilets through separate pipes.

3.0 VEGETATION

3.1 Is there any threat of the project to the biodiversity? (Give a description of the local ecosystem with its unique features, if any)

There is no endangered plant or animal species in the region. Moreover, the area does not fall under the path of any migratory species. There is no reserve forest, wild life sanctuary or protected forest around the project site. Hence no threat to biodiversity is envisaged.

3.2 Will the construction involve extensive clearing or modification of vegetation?

(Provide a detailed account of the trees & vegetation affected by the project)

The proposed project site is vacant and clear from vegetation. The construction of proposed project does not involve extensive clearing or modification of vegetation.

3.3 What are the measures proposed to be taken to minimize the likely impacts on important site features (Give details of proposal for tree plantation, landscaping, creation of water bodies etc along with a layout plan to an appropriate scale) Landscape development plan prepared for the project includes peripheral & avenue plantation with local species, ornamental as well as thick foliage plants especially on the periphery. Trees and plant species for plantation in the project will be selected from the list given below.

Table-3: List of Evergreen, Shady, Ornamental and Flowering Trees

for Green Belt Development

SN Botanical Name Common Name

1 Ficus Infectoria Pakur

2 Delonix regia Gulmohur

3 Cassia fistula Amaltas

4 Azadirachtha Indica Neem

5 Peltophorum ferrugineum Copper pod

6 Ficus retusa Usha

7 Alstonia Scholaris Scholar tree

8 Thespesia populnea Paras Pipal

9 Churasia tabularis Chukrasia

10 Anthocephalus cadamba Kadamba

11 Jacaranda mimosifolia Jacaranda

12 Mimusops Elengi Maulsari

13 Plumeria alba Temple tree

14 Terminalia arjuna Arjuna

15 Bauhinea Variegata Kachnar

16 Sarca indica Ashoka

17 Silver oak Grevillea Robusta

18 Semal Bombax Ceiba

19 Pilkhan Ficus

M/S MAHESHWARI INFRATECH PVT LTD

PROPOSED COMMERCIAL COMPLEX AT PLOT NO: C4A, SECTOR 16B, GREATER NOIDA (WEST) U.P.

FORM-1A

ITHC/PRJ/16-17/EIA/58 25 IND TECH HOUSE CONSULT

4.0 FAUNA 4.1 Is there likely to be any displacement of fauna-both terrestrial and aquatic or

creation of barriers for their movement? Provide the details.

No fauna has been recorded from the project influenced area. This site is not a natural host to any sensitive creature. Therefore, no animal habitat is likely to be effected due to construction of the proposed building.

4.2 Any direct or indirect impacts on the avifauna of the area? Provide details.

No direct or indirect impact on the avifauna of the area is envisaged.

4.3 Prescribe measures such as corridors, fish ladders etc. to mitigate adverse impacts on fauna. Measures such as corridors, fish ladders are not applicable for this project.

5.0 AIR ENVIRONMENT 5.1 Will the project increase atmospheric concentration of gases and result in heat

islands? (Give details of background air quality levels with predicted values based on dispersion models taking into account the increased traffic generation as a result of the proposed constructions)

Heat island effect will effect will be negligible due to reduction in hard area more plantation of hard area along roads and parking lots. Construction Phase The important activities during the construction phase that produce particulate matter and affect the air quality are excavation of earth for foundation structure, material storage, transportation and handling of excavated earth and construction materials like cement, sand and aggregates. Gaseous pollutants like SO2, NOx, CO emitted from the various machineries and vehicles used in construction activities. Appropriate mitigation measure will be employed during this stage of the project to reduce the pollution level to the acceptable limit. Operational Phase During this stage, there will be no major impact on air environment. Low sulpher diesel for DG Set will be used as a fuel which will causes air pollution. But APMC will minimize the pollution load into environment.

5.2 What are the impacts on generation of dust, smoke, odorous fumes or other hazardous gases? Give details in relation to all the meteorological parameters.

During construction phase, generation of dust, Particulate Matter is the main pollutant. Other emission sources are intermittent and include emissions of SO2 NOx and CO from materials transport of heavy vehicles on site & periodic operation of DG sets etc. Proper upkeep and maintenance of vehicles, DG sets, sprinkling of water on roads and construction site are some of the measures that would reduce the impact during construction phase.

M/S MAHESHWARI INFRATECH PVT LTD

PROPOSED COMMERCIAL COMPLEX AT PLOT NO: C4A, SECTOR 16B, GREATER NOIDA (WEST) U.P.

FORM-1A

ITHC/PRJ/16-17/EIA/58 26 IND TECH HOUSE CONSULT

Sources of Air pollution during operational phase

• The gaseous emission from vehicles.

• Emissions from DG set while in operation only during power failure.

Mitigation measures:

• The traffic congestion will be avoided by proper parking arrangement and maintaining smooth traffic flow.

• Regular PUC check up for vehicles.

• CPCB approved DG sets only will be used.

• Regular maintenance of DG sets shall be done & low sulphur diesel shall be used.

5.3 Will the proposal create shortage of parking space for vehicles? Furnish details of the present level of transport infrastructure and measures proposed for improvement including the traffic management at the entry & exit to the project site.

No, proposal does not create shortage of parking space; for vehicles parking provisions exceed bye law requirements, well organized parking arrangement has been designed for the project.

5.4 Provide details of the movement patterns with internal roads, bicycle tracks, pedestrian pathways, footpaths etc., with areas under each category.

Movement pattern is given in parking and circulation plan. 5.5 Will there be significant increase in traffic noise & vibrations? Give details of the

sources and the measures proposed for mitigation of the above.

The source of noise is mainly vehicular noise. Well organized parking arrangement is designed to maintain smooth traffic flow which would help in reducing traffic congestion and noise levels. Trees planned along road & periphery and soft areas would act as noise barrier and will reduce the noise level.

5.6 What will be the impact of DG sets & other equipment on noise levels & vibration in & ambient air quality around the project site? Provide details.

D.G. Sets will be operated only in case of power failures during construct ion and operational phase in case of group housing. The Pollutants like SPM, SO2 that may arise from emissions from D.G. sets will be discharged through vent of proper height. D.G. sets will be installed with inbuilt acoustic enclosures to reduce the noise of D.G. sets while in construction or operation. Plantation of trees would act as noise barrier and will reduce noise level.

DG sets of 7570 KVA capacity have been proposed for operation phase as power backup during failure of power supply.

6.0 AESTHETICS

6.1 Will the proposed constructions in any way result in the obstruction of a view, scenic amenity or landscapes? Are these considerations taken into account by the proponents?

As the proposed site is in conformity with the local land use and represent Integrated Sports Complex Land use. There is no scenic amenity or landscaping in its surroundings so there is no possibility of obstruction of abovementioned conditions.

M/S MAHESHWARI INFRATECH PVT LTD

PROPOSED COMMERCIAL COMPLEX AT PLOT NO: C4A, SECTOR 16B, GREATER NOIDA (WEST) U.P.

FORM-1A

ITHC/PRJ/16-17/EIA/58 27 IND TECH HOUSE CONSULT

6.2 Will there be any adverse impacts from new constructions on the existing structures? What are the considerations taken into account? Since the developmental plan is as per the approved master plan by Greater Noida Industrial Development Authority, hence, the construction of the proposed project will not have any adverse impact on the existing structures.

6.3 Whether there are any local considerations of urban form & urban design influencing the design criteria? They may be explicitly spelt out. There are no local consideration of urban forms and urban design influencing the project area. The project will be constructed within the site and as per the building by laws, defined by the Greater Noida Industrial Development Authority.

6.4 Are there any anthropological or archaeological sites or artifacts nearby? State if any other significant features in the vicinity of the proposed site have been considered. No, anthropological or archeological sites of significance do not exist in the vicinity of the project site. However all possible measures will be taken to reduce the impact on air and noise pollution during construction and operation phase.

7.0 SOCIO-ECONOMIC ASPECTS 7.1 Will the proposal result in any changes to the demographic structure of local

population? Provide the details.

No change in demographic structure is expected.

7.2 Give details of the existing social infrastructure around the proposed project. The area is of commercial activities status as per master plan. The proposed project site is located at plot no: C4a, Sector 16B, Greater Noida (west) Uttar Pradesh. Bus stand for public transport, hospitals/ clinics, market, educational institutions are located in a convenient distance.

7.3 Will the project cause adverse effects on local communities, disturbance to sacred sites or other cultural values? What are the safeguards proposed? The proposed construction will not have any adverse effects on local communities.

8.0 BUILDING MATERIALS

8.1 May involve the use of building materials with high-embodied energy. Are the construction materials produced with energy efficient processes? (Give details of energy conservation measures in the selection of building materials and their energy efficiency) ISI marked building materials of reputed brands to be procured from 400 km range as far as possible. Preference will be given to locally available building materials for construction. Use of alternative technologies for each component of the buildings of envelope, superstructure, finishes and the road and surrounding areas will be as per guidelines provided in NBC 2005. Some of them are given below:

• Ready mix concrete with 15-20% fly ash.

• Fly ash bricks will be used for walls.

M/S MAHESHWARI INFRATECH PVT LTD

PROPOSED COMMERCIAL COMPLEX AT PLOT NO: C4A, SECTOR 16B, GREATER NOIDA (WEST) U.P.

FORM-1A

ITHC/PRJ/16-17/EIA/58 28 IND TECH HOUSE CONSULT

Some of the alternate materials proposed for construction will be used to the extent possible

• Use of steel of smaller diameter from recycled content,

• Saw dust/Particles board for door panels,

• Alternatives for floor finishes include Ceramic tiles The use of the above alternatives for building materials will help reduce the use of non-renewable resources and impact on natural resources.

8.2 Transport and handling of materials during construction may result in pollution, noise & public nuisance. What measures are taken to minimize the impacts?

Mitigation Measures for Air Pollution during Construction Stage The impact on ambient air quality during construction stage around the project site will be assessed. Various construction activities especially related to handling of loose material likely to cause generation of fugitive dust will affect the air quality of the surrounding area of the project site. To minimize such impact following measures shall be taken: � The construction material will be carried in properly covered vehicles.

� Construction material will be stored at identified site/temporary go downs at site. � All the loose material either stacked earth or transported shall be provided with

suitable covering such as tarpaulin, etc. � Internal roads will be maintained in good conditions with regular sprinkling of

water (WBM) to curb the dust nuisance to the surrounding. � Water sprinkling shall be done at the location where dust generation is anticipated. � Tin sheets will barricade the periphery of the plot.

Mitigation Measures for Noise Pollution during Construction Stage During the construction stage, expected noise levels shall be in the range of 80-85 dB (A) which will decrease with increase in distance as per the Inverse Square Law. Administrative as well as engineering control of noise will be implemented. Isolation of noise generation sources and temporal differentiation of noise generating activities will ensure minimum noise at receiver’s end. To prevent any occupational hazard, ear muff / ear plug shall be given to the workers working around or operating plant and machinery emitting high noise levels. Use of such plant or machinery shall not be allowed during night hour. Careful planning of machinery operation and scheduling of operations shall be done to minimize such impact.

8.3 Are recycled materials used in roads and structures? State the extent of savings achieved? Locally available recyclable & recycle content materials would be given preference However, bricks made from the fly-ash will be used for construction of pavements, side walls, boundaries for parks etc. Readymade concrete (RMC) will be used in construction. This will result in significant saving in the total cost of project.

M/S MAHESHWARI INFRATECH PVT LTD

PROPOSED COMMERCIAL COMPLEX AT PLOT NO: C4A, SECTOR 16B, GREATER NOIDA (WEST) U.P.

FORM-1A

ITHC/PRJ/16-17/EIA/58 29 IND TECH HOUSE CONSULT

8.4 Give details of the methods of collection, segregation & disposal of the garbage generated during the operation phases of the project. As estimated, generation of solid waste is 1.29 TDP from block will be generated. Waste Management during operation phase: Municipal Solid Waste Sweepers will be engaged for collection and handling municipal waste. Location for bin/container at common places would be identified for collection of waste. Adequate number of collection bins separately for biodegradable and non-biodegradable waste shall be provided as per the Municipal Solid Waste (Management and Handling) Rule, 2000. Wastes from such bins shall be collected on daily basis handed over to authorized agency for disposal

Appropriate site for storage and segregation will be identified in the project.

� All waste collection bins shall be properly maintained on regular basis.

� Arrangement will be made with local civic authority, for providing garbage station or transfer point (preferably near the entry/ exit point of the site), for collection and disposal of inert waste. It will be assured that there is no spillage of waste along the internal roads during collection of wastes.

� The garbage storage/transfer point will be covered and cleaned every day to as to avoid any nuisance, vectors and unhygienic conditions.

Landscape waste comprises of fallen leaves and other vegetative material which shall be collected and treated along with other biodegradable waste.

9.0 ENERGY CONSERVATION

9.1 Give details of the power requirements, source of supply, backup source etc. What is the energy consumption assumed per square foot of built-up area? How have you tried to minimize energy consumption?

� Power will be sourced from Uttar Pradesh Power Corporation Ltd.

The maximum power demand for the project is estimated to be as around 6000 KW. The power shall be supplied by Uttar Pradesh Power Corporation Ltd. DG set of 7570 KVA Capacity: is proposed to meet requirement of power back up during grid failure. � Energy Conservation Measures & Management Plan:

During operation phase, appropriate energy conservation measures & management plan will be adopted in order to minimize the consumptions of conventional energy. The following energy saving measures are suggested to be adopted.

o Incorporate solar passive techniques in a building design to minimize load on conventional systems.

o Programmable switching arrangement for common areas/ street lighting. o Energy efficient lighting fixture & LED lamps to reduce energy consumption. o Use of local building material (400 Km range) to reduce pollution & transportation

energy. o The DG sets shall be automatically controlled to optimize the usage based on the

actual load requirement at any given time. These measures will effectively cut down fuel & energy consumption.

o Variable frequency drive with Motors, Pumps and Lifts. o Power factor shall be maintained 0.96 or higher

M/S MAHESHWARI INFRATECH PVT LTD

PROPOSED COMMERCIAL COMPLEX AT PLOT NO: C4A, SECTOR 16B, GREATER NOIDA (WEST) U.P.

FORM-1A

ITHC/PRJ/16-17/EIA/58 30 IND TECH HOUSE CONSULT

o Transformer shall have minimum no load losses as compared to conventional transformers.

o Cables shall be derated to avoid heating and reduce losses o Variable frequency drive with Motors, Pumps and Lifts.

9.2. What type of, and capacity of, power back-up to you plan to provide?

I) Type: D.G. Set II) 7570 KVA

9.3 What are the characteristics of the glass you plan to use? Provide specifications

of its characteristics related to both short wave and long wave radiation?

Glass panes will have high light transmission, but low solar heat inflow. This will reduce the quantity of heat flowing into the buildings, lessens cooling load on air-conditioners and induces energy saving.

9.4 What passive solar architectural features are being used in the building? Illustrate the applications made in the proposed project.

Passive solar technique:- Building design and envelope has been optimized through selection of appropriate wall and roof construction and through adoption of solar passive measures after analysis of sun path movement.

Predominantly N/S orientation Day light integrated to reduce artificial lighting demand.

9.5 Does the layout of streets & buildings maximize the potential for solar energy devices? Have you considered the use of street lighting, emergency lighting and solar hot water systems for use in the building complex? Substantiate with details.

Yes, the layout of streets & buildings has been designed to maximize the potential for solar energy devices. Further, solar energy will also be used for street lighting, common area lighting and water heating.

9.6 Is shading effectively used to reduce cooling/heating loads? What principles have been used to maximize the shading of Walls on the East and the West and the Roof? How much energy saving has been effected?

Provision of peripheral plantation for shading & reduction of cooling load. Roof shall have insulation to reduce solar gains. Minimum opening in East/ West walls.

9.7 Do the structures use energy-efficient space conditioning, lighting and mechanical systems? Provide technical details. Provide details of the transformers and motor efficiencies, lighting intensity and air-conditioning load assumptions? Are you using CFC and HCFC free chillers? Provide specifications.

Yes, energy efficient air conditioning system shall be free of CFC and HCFC.

M/S MAHESHWARI INFRATECH PVT LTD

PROPOSED COMMERCIAL COMPLEX AT PLOT NO: C4A, SECTOR 16B, GREATER NOIDA (WEST) U.P.

FORM-1A

ITHC/PRJ/16-17/EIA/58 31 IND TECH HOUSE CONSULT

9.8 What are the likely effects of the building activity in altering the micro-climates? Provide a self assessment on the likely impacts of the proposed construction on creation of heat island & inversion effects?

Proposed green area and treatment of hard area will reduce heat island effect.

9.9 What are the thermal characteristics of the building envelope? (a) roof; (b) external walls; and (c) fenestration? Give details of the material used and the U-values or the R values of the individual components.

• Glass: Energy efficient low U Value glass shall be selected for external glazing.

• Roof: shall have insulation.

• Walls: Energy efficient material with low U values shall be selected for paneling screen for external wall.

• Building envelope shall comply ECBC norms.

9.10 What precautions & safety measures are proposed against fire hazards? Furnish details of emergency plans.

In design component of the project, adequate measure has being taken as per the provisions of the National Building Code (SP 7: 1983 Part IV Amendment No 3 of January 1997 to provide for fire protection services. Sufficient quantity of water will be stored within the premise to subdue fire if at all required. Water will be supplied from the underground water storage reservoir. Apart from providing sufficient water for firefighting, other measures that have been considered include:

� The 6 m internal road will have sufficient load bearing capacity to withstand fire engines

� The building materials shall be of appropriate fire resistance standard. Further, design shall include provision for the following:

o The electrical systems shall be provided with automatic circuit breakers activated by the rise of current as well as activated by over current.

o Fire Alarm systems at appropriate places

o Means of escape,

o Access for fireman

o Adequate fire fighting requirement shall be taken into account while designing the electrical distribution system

Details of firefighting system have been given in Annexure.

9.11 If you are using glass as wall material provides details and specifications including emissive and thermal characteristics.

Glass on external walls shall be as per ECBC recommendation of WWR to reduce solar gain.

9.12 What is the rate of air infiltration into the building? Provide details of how you are mitigating the effects of infiltration.

Air conditioned areas are made air tight with the provision of weather strips, sealants. Infiltration rate will be controlled within the limits specified in ECBC.

M/S MAHESHWARI INFRATECH PVT LTD

PROPOSED COMMERCIAL COMPLEX AT PLOT NO: C4A, SECTOR 16B, GREATER NOIDA (WEST) U.P.

FORM-1A

ITHC/PRJ/16-17/EIA/58 32 IND TECH HOUSE CONSULT

9.13 To what extent the non-conventional energy technologies are utilized in the overall

energy consumption? Provide details of the renewable energy technologies used.

Solar energy will be used for street lighting and solar water heater for hot water supply in canteen.

10.0 Environment Management Plan

The Environment Management Plan would consist of all mitigation measures for each item wise activity to be undertaken during the construction, operation and the entire life cycle to minimize adverse environmental impacts as a result of the activities of the project. It would also delineate the environmental monitoring plan for compliance of various environmental regulations. It will state the steps to be taken in case of emergency such as accidents at the site including fire.

Table 5: Environment Management Plan

Sl. No.

Potential Impact

Action Parameters for Monitoring Timing

I. Construction Phase

1. Air Emission

All equipments are Operated within specified design parameters.

Random checks of Equipment logs/ manuals

Construction activities

Vehicle trips to be minimized to the extent Possible

Vehicle logs

Site Clearance and Construction activities

Any dry, dusty materials stored in sealed containers or prevented from blowing.

Absence of stockpiles or open containers of dusty materials.

Construction activities

Compaction of soil during various construction activities

Construction logs

Construction activities

Ambient air quality within the premises of the proposed unit to be monitored.

The ambient air quality will conform to the standards for PM10, PM2.5, SO2, NOx, CO

As per PCB requirement.

2. Noise

List of all noise generating machinery onsite along with age to be prepared. Equipment to be maintained in good working order.

Equipment logs, noise reading

During construction phase.

Night working to be minimized. Working hour records Construction activities

Generation of vehicular noise Maintenance records of vehicles

During construction phase.

Implement good working practices (equipment selection and siting) to minimize noise and also reduce its impacts on human health (ear muffs, safe distances, enclosures).

Site working practices records, noise reading

During construction phase.

Acoustic mufflers / enclosures to be provided in large engines

Mufflers / enclosures in place.

Prior to use of equipment.

Noise to be monitored in ambient within the plant premises.

Noise reading

As per PCB requirement or quarterly whichever is lesser.

The Noise level will not exceed the permissible limit both during day and night times.

All equipment operated within specified design parameters.

Random checks of Equipment logs/ manuals

During construction phase.

Vehicle trips to be minimized to the extent Possible

Vehicle logs

During construction phase.

3. Wastewater No untreated discharge to be No discharge hoses in During construction

M/S MAHESHWARI INFRATECH PVT LTD

PROPOSED COMMERCIAL COMPLEX AT PLOT NO: C4A, SECTOR 16B, GREATER NOIDA (WEST) U.P.

FORM-1A

ITHC/PRJ/16-17/EIA/58 33 IND TECH HOUSE CONSULT

Sl. No.

Potential Impact

Action Parameters for Monitoring Timing

Discharge made to surface water, groundwater or soil.

vicinity of watercourses. phase.

The discharge point should be selected properly and sampling and analysis should be undertaken prior to discharge

Discharge norms for effluents as given in consent to operate by PCB.

During construction phase. Take care in disposal of

wastewater generated such that soil and groundwater resources are protected.

Discharge norms for effluents as given in consent to operate by PCB.

4. Soil Erosion

Minimize area extent of site clearance, by staying within the defined boundaries

Site boundaries not extended / breached as per plan document.

During construction phase.

Protect topsoil stockpile where possible at edge of site.

Effective cover in place.

During construction phase.

5. Drainage and effluent Management

Ensure drainage system and specific design measures are working effectively. The design to incorporate existing drainage pattern and avoid disturbing the same.

Visual inspection of drainage and records thereof

During construction phase

6. Waste Management

Implement waste management plan that identifies and characterizes every waste arising associated with proposed activities and which identifies the procedures for collection, handling & disposal of each waste arising.

Comprehensive Waste Management Plan in place and available for inspection on-site. Compliance with MSW Rules, 1998 and Hazardous Wastes (Management and Handling Rules), 2003

Prior to site Clearance.

7.

Non-routine events and accidental releases

Plan to be drawn up, considering likely emergencies and steps required to prevent/limit consequences.

Mock drills and records of the same

During construction phase

8. Environmental Management Cell/Unit

The Environmental Management Cell/Unit is to be set up to ensure implementation and monitoring of environmental safeguards.

A formal letter from the management indicating formation of Environment Management Cell

During construction phase

II. Operational Phase

9. Air Emission

Stack emissions from DG set to be optimized monitored

The ambient air quality will conform to the standards for SPM, SO2 and NOx as given by PCB.

During operation phase

Ambient air quality within the premises of the proposed unit to be monitored. Exhaust from vehicles to be minimized by use of fuel efficient vehicles and well maintained vehicles having PUC certificate.

The ambient air quality will conform to the standards for PM10, PM2.5, SO2 and NOx, CO and Pb as given by PCB Vehicle logs to be maintained

During operation phase

Vehicle trips to be minimized to the extent possible

Vehicle logs

During operation phase

10. Noise

Noise generated from operation of DG set to be optimized and monitored DG sets to generate less than 75 dB(A) Leq at 0.5 m from the source DG sets are to be provided with acoustic enclosures with height of chimney as specified by PCB

Maintain records of vehicles

Generation of vehicular noise Maintain records of vehicles During operation phase

11. Wastewater Discharge

No untreated discharge to be made to surface water, groundwater or soil.

No discharge hoses in vicinity of watercourses.

During operation phase.

M/S MAHESHWARI INFRATECH PVT LTD

PROPOSED COMMERCIAL COMPLEX AT PLOT NO: C4A, SECTOR 16B, GREATER NOIDA (WEST) U.P.

FORM-1A

ITHC/PRJ/16-17/EIA/58 34 IND TECH HOUSE CONSULT

Sl. No.

Potential Impact

Action Parameters for Monitoring Timing

Take care in disposal of wastewater generated such that soil and groundwater resources are protected

Discharge norms for effluents

12. Drainage and Effluent Management

Ensure drainage system and specific design measures are working effectively. Design to incorporate existing drainage pattern and avoid disturbing the same.

Visual inspection of drainage and records thereof

During operation phase

13. Energy Usage Replacement of conventional luminaries to energy efficient luminary fittings

Luminary parameters During operation phase

14.

Emergency preparedness, such as fire fighting

Fire protection and safety measures to take care of fire and explosion hazards, to be assessed and steps taken for their prevention.

Mock drill records, on site emergency plan, evacuation plan

During operation phase

15. Environment Management Cell/Unit

The Environment Management Cell/Unit to be set up to ensure implementation and monitoring of environmental safeguards.

A formal letter from the management indicating formation of Environment Management Cell

During operation phase

M/S MAHESHWARI INFRATECH PVT LTD

PROPOSED COMMERCIAL COMPLEX AT PLOT NO: C4A, SECTOR 16B, GREATER NOIDA (WEST) U.P.

CONCEPTUAL PLAN

ITHC/PRJ/16-17/EIA/58 35 IND TECH HOUSE CONSULT

1.0 Introduction

M/S Maheshwari Infratech Pvt Ltd. is one of the well-known real estate developers executing various projects under various stages of development and execution. They have rich experience in the field of real estate and other construction / infrastructure projects. With their creative, innovative ideas and world class technologies; they have completed many commercial / infrastructural projects. In continuation of the same and considering the requirement of commercial/multiplex in Delhi NCR. M/S Maheshwari Infratech Pvt Ltd. has proposed a commercial/multiplex at plot no: C4a, Sector 16B, Greater Noida (west) Uttar Pradesh.

Figure-1: GNIDA Master Plan Land use- Residential

2.0 Project Details

The proposed project is planned on a plot area of 10000 sq. m. The total built up area will be 58.37.13 sq m. Project will provide, following facilities to make it comfortable and convenient for its users.

• Commercial/multiplex

• 24 X 7 hrs. Security.

• Adequate parking facility,

• DG set Power back up.

The Design approach shall be sensitive to environmental issues. The main thrust shall be laid on energy conservation, safety and ease of maintenance and current technological development. The Design Philosophy is to ensure fulfillment of all functional requirements in accordance with Design Guidelines, Relevant Standards and Codes as well as local Bye Laws.

M/S MAHESHWARI INFRATECH PVT LTD

PROPOSED COMMERCIAL COMPLEX AT PLOT NO: C4A, SECTOR 16B, GREATER NOIDA (WEST) U.P.

CONCEPTUAL PLAN

ITHC/PRJ/16-17/EIA/58 36 IND TECH HOUSE CONSULT

The following design standards/guidelines with latest amendments shall be followed during detailed design of services. In case of any discrepancy, the stringent shall be followed:

� National Building Code of India – 2005. � Relevant Codes of National Fire Codes 2008. � Relevant Codes of Bureau of Indian Standards � Energy Conservation Building Codes 2009 � Indian Electricity Rules 1956 � Environmental Guidelines. � State Byelaws. � IEC 60726/ IS: 2026 (Part 1, II and IV)/ IS 11171(Part III): Transformers (Cast

Resin) � IEC 60831/ IS 13340 & IS 13341: Capacitors � IEC 60947/ IS 13947: Specification for low voltage switch gear & control gear � BS 6651/ IS 2309: Lightning protection system � BS 7430, IS 3043: Earthing & bonding � BS 7671 requirements for electrical installation � NEC – NFPA 70, National Electric Code.

The project area statement and its components are as per the table 1 details given below:

Table1- Area Statement for Proposed Commercial/Multiplex Project

Particulars Area, sq. m.

Plot Area 10000 sq. m.

Proposed Built Up Area 58037.13 sq. m.

Permissible Ground Coverage Area (40%) 3982 sq. m.

Proposed Ground Coverage Area (39.95%) 3978 sq. m.

Permissible FAR Area (400) 39823 sq. m.

Proposed FAR Area (387.8 of total plot area) 38608.74 sq. m.

Green Area Proposed (15.29% of plot area) 1522 sq. m.

3.0 Connectivity

The project site is well connected to the major roads through network of road and is situated at 3.52/ NE km from NH-24, 3.46 KM from NH-91, 8.09 KM from NH-58 & 8.39 KM from SH-57.

M/S MAHESHWARI INFRATECH PVT LTD

PROPOSED COMMERCIAL COMPLEX AT PLOT NO: C4A, SECTOR 16B, GREATER NOIDA (WEST) U.P.

CONCEPTUAL PLAN

ITHC/PRJ/16-17/EIA/58 37 IND TECH HOUSE CONSULT

Figure-2: Project site Location

Figure-3: 500 m Radius Map

M/S MAHESHWARI INFRATECH PVT LTD

PROPOSED COMMERCIAL COMPLEX AT PLOT NO: C4A, SECTOR 16B, GREATER NOIDA (WEST) U.P.

CONCEPTUAL PLAN

ITHC/PRJ/16-17/EIA/58 38 IND TECH HOUSE CONSULT

Figure-4: 10 km radius map

4.0 Project Surroundings

The proposed commercial project site is located at plot no: C4a, Sector 16B, Greater Noida (west) in the state of Uttar Pradesh. Project site is at 28°36’13.95”N to 77°27’01.74”E. The details of site surroundings are given below in Table- 2.

Table-2: Site and Surrounding of the project Site

S. No. Particulars Details

1. Nearest National Highway NH-91, 3.46 Km., NE NH-24, 3.52 Km., NE NH-58, 8.09 Km., NW

2. Nearest Railway Station Ghaziabad Rly. Station, 5.41 Km., North

3. Nearest Airport IGI Airport, 32.69 KM, SW

4. Nearest Town/ City NOIDA

5. River Body Hindon-2.47 km, W

6. Hills/ Valleys Not within 10 km from the project site

7. Site Topography Plain

8. Archaeologically Important Site Nil

9. National Parks/ Wildlife Sanctuaries Okhla Bird Sanctuary- 14.24 km, SW

10 State Boundary Delhi-U. P. Border 11.15 km, W

11. Reserved/ Protected Forests Nil within 10 km radius of the project site

12. Seismicity The study area falls under Seismic Zone-IV

500 m and 10 km radius surroundings of the project site are given above in Fig 3 and Fig 4 respectively:

M/S MAHESHWARI INFRATECH PVT LTD

PROPOSED COMMERCIAL COMPLEX AT PLOT NO: C4A, SECTOR 16B, GREATER NOIDA (WEST) U.P.

CONCEPTUAL PLAN

ITHC/PRJ/16-17/EIA/58 39 IND TECH HOUSE CONSULT

5.0 Occupancy Details

The floating population of the project during construction and operation phases will be 112 and 7595 respectively. The total floating population will be 7595 persons.

6.0 Water Demand

6.1 Water supply & source

The water supply for the project during operation phase will be sourced from Greater Noida Industrial Development Authority. The total water requirement based on the population will be 575 KLD. The daily water requirement calculation for the project and waste water generation and reuse details are provided in Table 4 and the water balance Diagram is given below in Figure-5.

Table 4: Calculations for Daily Water Demand for Proposed Project

WATER REQUIREMENT

POPULATION/

AREA/UNIT RATE IN

LTS

TOTAL QTY IN

KL

RESIDENTIAL

DOMESTIC 675 65 43.88

FLUSHING 675 21 14.18

NON RESIDENTIAL COMMERCIAL (Working)

DOMESTIC 3046 15 45.68

FLUSHING 3046 30 91.37

VISITORS

DOMESTIC 3874 5 19.37

FLUSHING 3874 10 38.74

TOTAL POPULATION 7595

FOODCOURT/RESTAURANT (SEATS) 575 70 40.25

GARDENING 1522.1 5 7.61

AIR CONDITIONING (HVAC) 2000 10 220.00

D G COOLING 7570 0.9 54.504

TOTAL WATER REQUIREMENT 575.58

TOTAL TREATED WATER REQUIREMENT

206.40

TOTAL FRESH WATER 369.18

CAPACITY OF STP

WATER FLOW TO STP (DOMESTIC) 80%

119.34

M/S MAHESHWARI INFRATECH PVT LTD

PROPOSED COMMERCIAL COMPLEX AT PLOT NO: C4A, SECTOR 16B, GREATER NOIDA (WEST) U.P.

CONCEPTUAL PLAN

ITHC/PRJ/16-17/EIA/58 40 IND TECH HOUSE CONSULT

WATER FLOW TO STP (FLUSHING) 100%

144.28

TOTAL WASTE WATER GENERATION

263.63

REQUIRED CAPACITY OF STP - 120% 316

SAY 320

AVAILABLE TREATED WATER (80%) 210.90

REUSE OF TREATED WATER 210.90

SURPLUS TREATED WATER TO BE USED FOR HORTICULTURE DEVELOPMENT ALONG ROADS (IN FRONT OF PROJECT SITE )

4.50

Fig 5: Water Balance Diagram for Proposed Commercial/Multiplex

7.0 Solid Waste Generation, Collection, Transport and Disposal

Solid waste would be generated both during the construction as well as during the operation phase. The solid waste expected to be generated during the construction phase will comprise of excavated materials, used bags, bricks, concrete, MS rods,

M/S MAHESHWARI INFRATECH PVT LTD

PROPOSEDC4

ITHC/PRJ/16-17/EIA/58

tiles, wood etc. The following steps are to be followed for the management solid waste:

• Construction yards are used for storage of construction materials.

• The excavated material such as topsoil and stones will be stacked for reuse during later stages of construction

• Excavated top soil will be stored in temporary constructed soil reused for landscaping of the Commercial Project

• Remaining soil shall be utilized for refilling / road work / rising of site level at locations/ selling to outside agency fo

Figure 6: Solid Waste Management Scheme (Construction Phase)Following the guidelines of Central Public Health and Environmental Engineering Organization (CPHEEO) Tones per day (@ 500g. wastes generated has been considered

Table 5: Quantity of

Total Waste Generation

Organic Waste Generation

Hazardous Waste Generation (DG Waste Oil)

N B: The solid waste generation has been calculated @ 0.5 basis. Following arrangements will be made at the site in accordance to Municipal Solid Wastes (Management and Handling) Rules, 2000 and amended Rules, 2008. � Collection and Segregation of waste

1. For adequate number of colored bins (Green and Blue & dark grey bins

separate for Bio-degradable and Non Biothe strategic locations of the commercial area.

8.0 Power Requirement Details

The power supply shall be supplied by connected load for the project

PROPOSED COMMERCIAL COMPLEX AT PLOT NO: C4A, SECTOR 16B, GREATER NOIDA (WEST) U.P.

41 IND TECH HOUSE CONSULT

The following steps are to be followed for the management solid

Construction yards are used for storage of construction materials.

The excavated material such as topsoil and stones will be stacked for reuse during later stages of construction.

Excavated top soil will be stored in temporary constructed soil bank and will be for landscaping of the Commercial Project.

Remaining soil shall be utilized for refilling / road work / rising of site level at locations/ selling to outside agency for construction of roads etc.

Solid Waste Management Scheme (Construction Phase)Following the guidelines of Central Public Health and Environmental Engineering Organization (CPHEEO) manual, quantity of solid waste generated will be

500g. per capita per day for residents. Green area andgenerated has been considered @ 15 kg/acre/day).

of Waste Generation from Commercial / Multiplex

1.29 TPD

Generation 0.59 TPD

Hazardous Waste Generation (DG Waste Oil) 10.5 Lts/

The solid waste generation has been calculated @ 0.5 kg. per capita per day Following arrangements will be made at the site in accordance to Municipal

(Management and Handling) Rules, 2000 and amended Rules, 2008.

Collection and Segregation of waste

dequate number of colored bins (Green and Blue & dark grey binsdegradable and Non Bio-degradable) are to be provided at

strategic locations of the commercial area.

Power Requirement Details

The power supply shall be supplied by Uttar Pradesh Power Corporation Ltdproject will be approx.6000 KW.

Table: 6 Power Demand

CONCEPTUAL PLAN

IND TECH HOUSE CONSULT

The following steps are to be followed for the management solid

The excavated material such as topsoil and stones will be stacked for reuse

bank and will be

Remaining soil shall be utilized for refilling / road work / rising of site level at

Solid Waste Management Scheme (Construction Phase)

Following the guidelines of Central Public Health and Environmental Engineering quantity of solid waste generated will be 1.29

area and landscape

from Commercial / Multiplex

TPD

TPD

Lts/ DAY

per capita per day Following arrangements will be made at the site in accordance to Municipal

(Management and Handling) Rules, 2000 and amended Rules, 2008.

dequate number of colored bins (Green and Blue & dark grey bins– degradable) are to be provided at

Uttar Pradesh Power Corporation Ltd. The

M/S MAHESHWARI INFRATECH PVT LTD

PROPOSED COMMERCIAL COMPLEX AT PLOT NO: C4A, SECTOR 16B, GREATER NOIDA (WEST) U.P.

CONCEPTUAL PLAN

ITHC/PRJ/16-17/EIA/58 42 IND TECH HOUSE CONSULT

Electrical - Demand Load 6000 KW Power Back Up - DG Sets 7570 KVA

DG Stack Height (6M Above Tallest Tower) 68.20 M 8.1 Backup Power Details

There is provision of DG set of 7570 KVA for power back up in proposed commercial/multiplex project. The DG sets will be equipped with acoustic enclosure to minimize noise generation and adequate stack height for proper dispersion.

Energy Conservation Measures: The energy conservation measures shall be adopted to minimize the demand on non- renewable resources and maximize the utilization efficiency of these resources. The benefits of Energy Conservation measures are as follows:

• Reduced Energy Consumption without sacrificing comfort levels.

• Reduced destruction of natural resources.

• Reduced air pollution.

• Reduced Pollution Loads.

• Increased user productivity.

Following Energy Conservation Measures will be adopted:

a) Energy efficient LED Lamps

b) All cables shall be derated to avoid heating during use. This also indirectly reduces losses and improves reliability.

c) Power factor shall be maintained 0.9 or higher. This will reduce electrical

power distribution losses in the installation. 9.0 Construction of Storm Water Drains

A network of storm water drainage shall be planned to collect rain water for recharge& excess rain water shall be discharged in municipal drain.

10.0 Rain Water Harvesting System The storm water disposal system for the premises shall be self-sufficient to avoid any collection/stagnation and flooding of water. The amount of storm water run-off depends upon many factors such as intensity and duration of precipitation, characteristics of the tributary area. Rain water will be harvested and the potential for rain water harvesting projected is given as per the Table 7. Two rain water harvesting pits at selected locations, which will harvest the maximum run-off from the area. Design specifications of the rain water harvesting plan are as follows:

• Catchments/roofs would be accessible for regular cleaning.

• The roof will have smooth, hard and dense surface which is less likely to be damaged allowing release of material into the water. Roof painting has been avoided since most paints contain toxic substances and may peel off.

M/S MAHESHWARI INFRATECH PVT LTD

PROPOSED COMMERCIAL COMPLEX AT PLOT NO: C4A, SECTOR 16B, GREATER NOIDA (WEST) U.P.

CONCEPTUAL PLAN

ITHC/PRJ/16-17/EIA/58 43 IND TECH HOUSE CONSULT

• No sewage or wastewater would be admitted into the system.

Table 7: Calculations for storm water Harvesting Potential

Particulars Road/Paved

Area/Open Area Green Area

Roof Top Area

Area (Sq.m.) 1333.3 2725.00 1522.08

Runoff coefficient 0.3 0.75 0.2

Rainfall (m) 0.7006 0.7006 0.7006

Harvesting potential (cu.m.) 280.2266 1431.8513 213.2733

Net water availability and potential for recharge (cu.m.) per year (considering 20% losses)

3747.4

Rain Water Harvesting Pit Design Particulars Values Unit

Peak hourly rate taken @ 45 mm/hr for one hour duration 300.87 CUM

Peak hourly rate taken @ 45 mm/hr for 15 min duration 75.22 CUM

Volume of recharge pit 37 CUM

No. of recharge pit required 2.0 NO

Proposed 2 NO

Total of 02 Rain Water Harvesting pits are to be proposed for artificial rain water recharge within the project premises.

Figure-8: A typical recharge pit

M/S MAHESHWARI INFRATECH PVT LTD

PROPOSED COMMERCIAL COMPLEX AT PLOT NO: C4A, SECTOR 16B, GREATER NOIDA (WEST) U.P.

CONCEPTUAL PLAN

ITHC/PRJ/16-17/EIA/58 44 IND TECH HOUSE CONSULT

11.0 Landscape & Shelterbelt development Total green area measures 1522 m2 i.e. 15.29% of the plot area will be under tree plantation within the plots, commercial area and along the roads. There are several trees which will be planted along the sides of the Project boundary. Trees that are to be planted in the project premises are given below in below:

List of Evergreen Trees, Dense Foliage, Shady, Ornamental and

Flowering Trees for Green Belt Development

SN Botanical Name Common Name

1 Ficus Infectoria Pakur

2 Delonix regia Gulmohur

3 Cassia fistula Amaltas

4 Azadirachtha Indica Neem

5 Peltophorum ferrugineum Copper pod

6 Ficus retusa Usha

7 Alstonia Scholaris Scholar tree

8 Thespesia populnea Paras Pipal

9 Churasia tabularis Chukrasia

10 Anthocephalus cadamba Kadamba

11 Jacaranda mimosifolia Jacaranda

12 Mimusops Elengi Maulsari

13 Plumeria alba Temple tree

14 Terminalia arjuna Arjuna

15 Bauhinea Variegata Kachnar

16 Sarca indica Ashoka

17 Silver oak Grevillea Robusta

18 Semal Bombax Ceiba

19 Pilkhan Ficus

12.0 Parking Facilities

Adequate provision will be made for parking at proposed commercial/multiplex. There shall also be adequate parking provisions for visitors so as not to disturb the traffic and allow smooth movement at the site.

12.1 Parking Details Table 8: Parking Facilities

1. Proposed Total Parking 798 ECS

2. Proposed Parking on Surface 38 ECS

3. Basement Parking (2nd & 3rd Lev Mech Parking) 760 ECS

13.0 Seismicity

Based on the tectonic features and records of earthquake, a Seismic Zoning map has been developed for the country by Bureau of Indian Standard (BIS). The area under study falls in Seismic Zone-IV. Suitable seismic coefficients in horizontal and vertical directions respectively, will be adopted while designing the structures. Earthquake resistant construction material will be used.

M/S MAHESHWARI INFRATECH PVT LTD

PROPOSED COMMERCIAL COMPLEX AT PLOT NO: C4A, SECTOR 16B, GREATER NOIDA (WEST) U.P.

CONCEPTUAL PLAN

ITHC/PRJ/16-17/EIA/58 45 IND TECH HOUSE CONSULT

14.0 Emergency Lighting

The emergency lights operated on battery power should be provided at appropriate locations – such as corridors, common area, staircase, exit and entrance doors, parking, etc. The transformers will be kept energized and should feed independently alternate rows of lights so that in case of failure of one transformer, there will not be complete darkness.

15.0 Fire Safety

� Fire Fighting Designed: As per National Building Code 2005/guideline of Dist fire department.

� Fire Tender route with access to each block

� Fire escape staircases as per NBC requirements.

� Fire Alarm system

� Sand buckets will be placed on each floor of convenient shopping.

16.0 Environmental Pollution Mitigation Measures

16.1 Air Pollution

Increased traffic generation due to project (no. of parking space proposed for the project is not going to cause significant increase in atmospheric concentration of gases and will not result in heat island formation as adequate landscaping has been provided.

Mitigation Measures for Air Pollution during Construction Stage Air quality around the project site will be impacted during construction stage. Various construction activities especially related to handling of loose material are likely to generate fugitive dust that will affect the air quality of the surrounding area of the project site. To minimize such impacts following measures has been proposed:

� All the loose material either stacked or transported will be provided with suitable

covering such as tarpaulin, etc.

� Water sprinkling shall be done at the locations where dust generation is anticipated.

� To minimize the occupational health hazard, proper personal protective gears i.e. mask shall be provided to the workers who are engaged in dust generation activity.

Mitigation Measures for Air Pollution during Operational Stage Operation of DG Sets is the only source of air pollution during operational phase. Sufficient stack height will be provided for proper dispersion of pollutants. Also, it is proposed to minimize air pollution by providing plantation as buffer on the periphery of the project site and on the open spaces. An area of 1522 m2 i.e. 15.29% of plot area has been kept for plantation purposes.

M/S MAHESHWARI INFRATECH PVT LTD

PROPOSED COMMERCIAL COMPLEX AT PLOT NO: C4A, SECTOR 16B, GREATER NOIDA (WEST) U.P.

CONCEPTUAL PLAN

ITHC/PRJ/16-17/EIA/58 46 IND TECH HOUSE CONSULT

16.2 Water Pollution

The source of water pollution during construction and operation phase is due to waste water generated from toilets and washing. Mitigation Measures for Water Pollution during Operational Stage: Waste water generation and treatment and reuse are dealt in 6.1.

16.3 Noise Environment

It is envisaged that there shall be maximum movement of light motor vehicles within the project site, which will lead to some increase in noise levels. It is proposed to minimize the noise levels by providing plantation as buffer on the sides of internal roads, on the open spaces inside and around the periphery of whole complex. Proper maintenance of the internal roads will also be carried out and Informatory signboards shall be provided to encourage vehicle owners to maintain their vehicle, not to blow horns and follow the emission standards fixed by Government Authorities. DG sets will be kept in the acoustic chamber and ambient noise will be within the CPCB standard limits.

Mitigation Measures for Noise Pollution during Construction Stage During the construction stage, expected noise levels shall be in the range of 80-85 dB (A) which will decrease with increase in distance as per the Inverse Square Law. Administrative as well as engineering control of noise will be implemented. Isolation of noise generation sources and temporal differentiation of noise generating activities will ensure minimum noise at receiver’s end. To prevent any occupational hazard, ear muff / ear plug shall be given to the workers working around or operating plant and machinery emitting high noise levels. Use of such plant or machinery shall not be allowed during night hour. Careful planning of machinery operation and scheduling of operations shall be done to minimize such impact. Mitigation Measures for Noise Pollution during Operation Stage It is envisaged that there shall be maximum movement of light motor vehicles, which will lead to some increase in noise levels. It is proposed to minimize the noise levels by providing plantation as buffer on the open spaces and around the periphery of whole complex. Informatory signboards shall be provided to encourage vehicle owners to maintain their vehicle, not to blow horns and follow the emission standards fixed by Government Authorities DG sets will be kept in the acoustic chamber and ambient noise will be within the CPCB standard limits.

17.0 Construction Materials

The following construction materials are required for residential construction;

1. Coarse sand

2. Fine sand

3. Stone aggregate

4. Cement

5. Fly Ash

11. P.V.C. conduit

12. MCBs/DBs

13. PVC overhead water tanks

14. Pavors

15. GI pipe

M/S MAHESHWARI INFRATECH PVT LTD

PROPOSED COMMERCIAL COMPLEX AT PLOT NO: C4A, SECTOR 16B, GREATER NOIDA (WEST) U.P.

CONCEPTUAL PLAN

ITHC/PRJ/16-17/EIA/58 47 IND TECH HOUSE CONSULT

6. Reinforcement steel

7. Plywood & steel shuttering

8. Pipe scaffolding (cup lock system)

9. Bricks

10. Marble/ ceramic

16. waste water lines

17. S.W. sewer line upto main sewer

18. PVC pipes

19. Glass

20. Joinery hardware

Apart from this, in order reduce the overall energy requirement of the building; materials with low U value will be used.

18.0 List of Machinery Used During Construction

(i) Dumper (ii) Concrete mixer with hopper (iii) Excavator (iv) DG Sets (v) Cranes (vi) Road roller (vii) Tower Cranes (viii) Hoist (ix) Concrete pressure pumps (x) Mobile transit mixer

SITE LOCATION MAP ON GOOGLE

500 M RADIUS MAP ON GOOGLE

10 KM RADIUS MAP ON GOOGLE EARTH

ENVIRONMENT BUDGET (Opertaion Stage)

COMPONENT CAPITAL

COST (Rs in Lacs)

RECURRING COST (Rs in Lacs)

SEWAGE TREATMENT PLANT (310 KLD) 45 5.71

RAIN WATER HARVESTING SYSTEM (18 Nos) 8 1

HORTICULTURE DEVELOPMENT (Tree plantation)

7.6 1.51

HEAT REFLECTIVE PAINT (HIGH ALBEDO SRI PAINT) TO TERRACES

9.5 1

ENVIRONMENT MONITORING - Amb Air, DG Flue, DG Noise, Amb Noise, STP outlet Water, Ground Water - 6 Monthly monitoring

7

TOTAL 70 16.6

RAIN WATER HARVESTING

PARTICULARS OTHER OPEN AREAS

ROAD/PAVEMENT/PARKING AREAS

GREEN AREA

ROOF TOP

AREA

Area (Sq.m.) 1333.3 2725.00 1522.08 4375.4

Runoff coefficient 0.3 0.75 0.2 0.9

Rainfall (m) 0.7006 0.7006 0.7006 0.7006 Harvesting potential (cu.m.) 280.2266 1431.8513 213.2733 2758.8485 Net water availability and potential for recharge (cu.m.) per year (considering 20% losses)

3747.4

Rain Water Harvesting Pit Design Particulars Values Unit

Peak hourly rate taken @ 45 mm/hr for one hour duration 300.87 CUM

Peak hourly rate taken @ 45 mm/hr for 15 min duration 75.22 CUM

Volume of recharge pit 37 CUM

No. of recharge pit required 2.0 NO

Proposed 2 NO

Ind Tech House Consult

EIA Consultancy Organization: Ind Tech House Consult, G-8/6, Ground Floor, Rohini, Delhi –

110 085, has been appointed as EIA Consultant to carry out Environmental Impact Assessment

Study and Obtaining Environmental Clearance for the Construction of proposed commercial

complex at plot no: C4A, Sector 16B, Greater Noida (west) Uttar Pradesh

Accreditation to NABET Status: Ind Tech House Consult was assessed by the NABET on 30th

and 31st January 2012 and has provisionally accredited the Consultancy organization in Building

and Construction Projects.

Similar Assignment: Following are some of projects of similar kind successfully carried out/

ongoing by the Consultancy organization.

a. Environmental Impact Assessment for Extension of Parliament House Annexe Project,

Parliament House Complex, New Delhi;

b. Environmental Impact Assessment for Construction of Group Housing for LokSabha

Secretariat, New Delhi;

c. Environmental Impact Assessment for Park at Sector 92, Noida (under direction of

Hon’ble Supreme Court);

d. Environmental Impact Assessment for Expansion of LNJP Hospital, New Delhi;

e. Environmental Impact Assessment for Construction of Institutional Campus at Rohtak;

f. Environmental Impact Assessment for Construction of Police Line by Delhi Armed

Police, Dwarka, New Delhi.

Disclosure of the EIA Consultant

Intellectual Strength of Ind Tech House Consult

I Name : Mr. Arvind Narayan Devikar

1 Status in the Organization : Vice President & EIA Coordinator

2 Educational Qualification : Bachelor of Architecture (Visvesvaraya Regional College of

Engineering – Nagpur (1973)

3 Work Experience : 44 Years

4 Work Experience related

to EIA

: 12 years

More than 100 successful EIA projects in Building Construction

Sector

5 Previous Organizations

Served

: Senior Architect, CPWD, Directorate General, CPWD Nirman

Bhawan (1976 – 2007)

6 Specialization : Planning and Designing, Energy Efficient Buildings, Climate

Responsive Architectural Design, Passive Energy in Buildings,

Energy Conservation, Landscape and Environmental Impact

Assessment

7 Additional Qualification : Evaluator and Trainer for GRIHA - Green Rating for Integrated

Habitat Assessment;

Panel member for National Building Code 2005 in Landscaping,

CED 46:p18;

Architecture, Energy and Environment – Lund University Sweden

Planning and Design of Energy Efficient Building – CPWD

Ghaziabad;

Post Graduate Diploma in Public Administration (IIPA)

II Name : Mrs. Supriti Guha

1 Status in the Organization : General Manager & EIA Coordinator

2 Educational Qualification : B. Tech Chemical Engineering

3 Work Experience : 19 Years

4 Work Experience related

to EIA

: 7 years

More than 80 EIA Studies

5 Previous Organizations

Served

: West Bengal Pollution Control Board for 12 years as Regional

Officer

6 Specialization : Air Quality, Water Pollution, Solid and Hazardous Waste,

Environmental Assessment for Industries and Thermal power

Plant and Environmental Impact Assessment

III Name : Mr. Suman Banerjee

1 Status in the Organization : Managing Partner & EIA Coordinator

2 Educational Qualification : B.E. Environmental Engineering

3 Work Experience : 15 Years

4 Work Experience related

to EIA

: 12 Years

More than 50 successful EIA projects

5 Previous Organizations

Served

: Common - Hazardous Waste Management Facility at Taloja,

Mumbai;

Common - Biomedical Waste Management Facility at Taloja,

Mumbai;

Consultant for JBIC for Environment and Social Guideline Frame

Work for Steel and Thermal Power Projects in India;

Consultant for JICA for Dedicated Freight Corridor for DFCCL -

Ministry of Railways, projects;

EIA Consultant and Environmental Trainer for JBIC funded Kerala

water supply project for Thiruvananthapuram, Meenad,

Cherthala, Kozhikode & Pattuvam.

6 Specialization : Air Pollution, Water Pollution, Noise and Vibration, Green

Building, Municipal Solid Waste, Hazardous Waste and

Biomedical Waste;

Environmental Impact Assessment for Building and Construction

Projects, Highway Projects, Area Development Projects, Industrial

Estate/ Park/ Leather Park Projects, SEZ, Oil and Natural Gas

Exploration Projects, Mineral Beneficiation Projects, Highway and

Solid and Hazardous Waste Management Projects;

Noise and Vibration assessment and analysis expert

7 Additional Qualification : GRIHA – Green Rating for Integrated Habitat Assessment

ECBC – Energy Conservation Building Code

EIA Trainer for CPWD Officials at CPWD Training Institute,

Ghaziabad

IV Name : Mr. Anand Kumar Dubey

1 Status in the Organization : Partner

2 Educational Qualification : M. Sc. Environment and Ecology

3 Work Experience : 11 years

4 Work Experience related

to EIA

: 11 years

More than 50 successful EIA projects

5 Previous Organizations

Served

: - -

6 Specialization : Environmental Impact Assessment for Building Construction,

Industrial Estates/ Parks, Solid Waste Management, Area

Development Projects, Oil and Natural Gas Exploration, Highway

Projects, Air Quality, Water Quality, Solid Waste and Ecology and

Biodiversity Expert

V Name : Dr. Debasish Bhattacharya

1 Status in the Organization : Social Expert

2 Educational Qualification : Ph.D. – IIT Kharagpur (Tribal Development/ Social Science)

MRP Regional Planning – IIT Kharagpur

3 Work Experience : 28 years

4 Work Experience related

to EIA

: 23 years

More than 70 successful EIA projects

5 Previous Organizations

Served

: IIT Kharagpur – Senior Project Manager;

LEA Associates;

SMEC India Pvt. Ltd.;

Feedback Ventures Pvt. Ltd.;

Nippon Koei;

External Funding Agency Projects for World Bank, ADB, JICA.

6 Specialization : Tribal Development, Socio economic Development, Social Study

in Forest Management, Preparation of RAP, SIA, SE Framework

Development, Rehabilitation and Resettlement (R&R)

VI Name : Dr. Chandrashekhar Anantrao Moghe

1 Status in the Organization : EIA Coordinator;

Water Pollution, Soil Conservation Expert

2 Educational Qualification : M.Sc. Environmental Science (Nagpur University)

Ph.D.

3 Work Experience : 36 years

4 Work Experience related

to EIA

: 28 years

5 Previous Organizations

Served

: NEERI - Nagpur

6 Specialization : EIA

7 Specialized Study : Senior Executive Program on Environmental Management for

Selected Asian Countries by APO Japan at Singapore;

Initial Environmental Legislation and Internal Audit for EMS (ISO

14001);

SIDA Financed Advanced International Training Program on

EIA/SEA at Stockholm and Malmo (Sweden);

Training on "Certified Measurement Uncertainty Analyst"

Chemical Parameters - Centre for Electronics Test Engineering,

Bangalore

VII Name : Dr. Srikant Mishra

1 Status in the Organization : Soil Expert

2 Educational Qualification : Bachelor's Degree in Agricultural Science;

LLB;

M.Sc. Agriculture;

Ph.D.

3 Work Experience : 51 years

4 Work Experience related

to EIA

: 6 Years

5 Previous Organizations

Served

: Government Agricultural College Kanpur / Chandra Shekhar Azad

University of Agriculture and Technology, Kanpur

6 Specialization : Soil Science and Agricultural Chemistry

VIII Name : Mr. Alok Pathak

1 Status in the Organization : EIA Coordinator

Ecology and Biodiversity Expert;

Air Pollution Expert;

Solid & Hazardous Waste Management Expert.

2 Educational Qualification : Bachelor of Engineering - Civil;

Master of Engineering - Management & IE;

Diploma in Forestry - (FRI-Dehradun);

LLB - CCSU Meerut

3 Work Experience : 28 Years

4 Work Experience related

to EIA

: 10 Years

5 Previous Organizations

Served

: Deputy Conservator of Forest (Govt. of Madhya Pradesh);

General Manager (Corporate Affairs) - Adani Group;

Addl. Vice President (Corporate Affairs) - Reliance ADA Group.

6 Specialization : Ecology & Biodiversity, Forestry

7 Specialized Study : MDP on Criteria & Indicators for Sustainable Development of

Forests - Indian Institute of Forest Management, Bhopal;

Certificate Program on "Self Help Groups" by National Institute of

Rural Development, Hyderabad

IX Name : Mr. B. Kulaala Anandan

1 Status in the Organization : General Manager - Corporate Relations

2 Educational Qualification : Bachelor of Engineering - Mechanical Engineering

3 Work Experience : 15 Years

4 Work Experience related

to EIA

: - -

5 Previous Organizations

Served

: Ramky Enviro Engineers Ltd.

Garware Wall Ropes Ltd.

6 Specialization : Customer Relations

7 Specialized Courses : NEBOSH - International General Certification in Occupational

Health & Safety;

IOSH - Institution of Occupational Safety & Health

X Name : Mr. Sameer Vilasrao Deshpande

1 Status in the Organization : Ecology and Biodiversity Expert

2 Educational Qualification : M.Sc. Botany

3 Work Experience : 11 years

4 Work Experience related

to EIA

: 11 years

5 Previous Organizations

Served

: National Environmental Engineering Research Institute - NEERI

Nagpur

6 Specialization : Biological Monitoring, preparation of Biodiversity report,

conservation plan for scheduled plant and animals, green belt

development plan

XI Name : Dr. Rahul Ramarao Deshmukh

1 Status in the Organization : Social Expert

2 Educational Qualification : Ph.D. Social Work (R&R), Nagpur University; Master of Social

Work

3 Work Experience : 11 years

4 Work Experience related

to EIA

: 11 years

5 Previous Organizations

Served

: National Environmental Engineering Research Institute - NEERI

Nagpur

6 Specialization : Socio Economic Monitoring, Rehabilitation and Resettlement,

Corporate Social Responsibility

XII Name : Mr. Umesh Pratap Singh Chauhan

1 Status in the Organization : General Manager -Projects

2 Educational Qualification : M.Sc. Geology

3 Work Experience : 32 years

4 Work Experience related

to EIA

: 10 years

5 Previous Organizations

Served

: Uttar Pradesh State Mineral Development Corporation Ltd.;

Directorate of Geology and Mining

6 Specialization : Senior Geologist;

Mining Plan;

R&D project for Mining and Quality Control;

Exploration, Surveying and Mapping.

XIII Name : Dr. Manoj Kumar Mishra

1 Status in the Organization : Air Pollution, Meterology, Modeling and Noise and Vibration

Expert

2 Educational Qualification : M.Tech. Atmospheric Sciences – University of Pune

Ph.D. Atmospheric Sciences (Air Quality Modelling and

Micrometeorology – IIT Delhi)

3 Work Experience : 19 years

4 Work Experience related

to EIA

: 19 years

5 Previous Organizations

Served

: IIT Delhi – Research Associate

SENES Consultants India Pvt. Ltd.

6 Specialization : Air and Noise Impact Assessment Studies;

Air Quality and Noise Modeling by ISCST3, AERMOD, CALPUFF,

OCD, CALINE, INM, DHAWANI, TNM, etc.;

Air and Noise Modeling for Coal and Gas fired industries, landfill,

helipads, airports, wind farms, highways & SEZ Projects;

7. Specialized Study : Coastal Atmospheric Boundary Layer (CABL) field experiment at

Kalpakkam in collaboration with Indira Gandhi Centre for Atomic

Research (IGCAR) Kalpakkam, Bhabha Atomic Research Centre

(BARC) Mumbai and Institute of Meteorology and Physics,

University of Agriculture, Forestry and Renewable Resources –

Vienna, Austria

XIV Name : Dr. Suraj Kumar Sharma

1 Status in the Organization : Hydrology, Ground Water, Water Conservation, Geology and

Land Use Expert

2 Educational Qualification : M.Sc. Geology – Jammu University

Diploma in Remote Sensing – Indian Institute of Remote Sensing

(IIRS Dehradun)

Diploma in Advance Course in Remote Sensing – ITC, The

Netherlands

3 Work Experience : 48 years

4 Work Experience related

to EIA

: 9 years

5 Previous Organizations

Served

: Assistant Geologist – Geological Survey of India

Director Hydrogeology – Central Ground Water Authority

Member Hydrogeology – Central Ground Water Authority

6 Specialization : Water Harvesting;

Water Shed Management;

Ground Water Study under NNRMS Program along with ISRO;

Appraisal and Examination of Environmental Projects of MoEF;

Interpretation and Analysis of Aerial photographs and satellite

imageries and providing S&T inputs to ground water projects in

the states, investigation and exploration of ground water

resources;

Geological and hydro-geological data processing.

XV Name : Dr. Bideh Shukla

1 Status in the Organization : Project Incharge

2 Educational Qualification : Ph.D. Botany

3 Work Experience : 15 years

4 Work Experience related

to EIA

: 5 years

5 Previous Organizations

Served

: B.H.U., I-Service India (Pvt. Ltd.), Dimension India Network (Pvt.)

Ltd.

6 Specialization : GIS, Water Pollution, Ecology

XVI Name : Mr. Satish Verma

1 Status in the Organization : Project Coordinator

2 Educational Qualification : M.Tech. – Energy & Environment Management

3 Work Experience : 04 Years

4 Work Experience related

to EIA

: 03 Years

5 Previous Organizations

Served

: United Spirits Limited, Shahjahanpur

6 Specialization : EIA

XVII Name : Mr. Jai Singh

1 Status in the Organization : Project Coordinator

2 Educational Qualification : M.Tech. – Energy & Environment Management

3 Work Experience : 04 Years

4 Work Experience related

to EIA

: 03 Years

5 Previous Organizations

Served

: UEM India Pvt. Ltd.

6 Specialization : EIA

XVIII Name : Mr. Soumya Dwivedi

1 Status in the Organization : Risk and Hazard Expert

2 Educational Qualification : B.E. Chemical

3 Work Experience : 07 years

4 Work Experience related

to EIA

: 07 years

5 Previous Organizations

Served

: Mantec Consultants Pvt. Ltd.

6 Specialization : Risk and Hazard Study for Oil & Gas Pipeline and Depots, Ports,

Harbors& Jetties and Thermal Power Plant

XIX Name : Mr. Manish Kumar

1 Status in the Organization : Project Executive

2 Educational Qualification : M.Sc Geology

3 Work Experience : 01 Years

4 Work Experience related

to EIA

: 01 Years

5 Previous Organizations

Served

: None

6 Specialization : EIA

XX Name : Indra Kumar

1 Status in the Organization : Project Executive

2 Educational Qualification : B.Tech. – Electronics and Commutations

3 Work Experience : 01 year

4 Work Experience related

to EIA

: 01 Year

5 Previous Organizations

Served

: None

6 Specialization : Mapping

XXI Name : Saurabh Bhardwaj

1 Status in the Organization : Project Executive

2 Educational Qualification : Bachelor in Computer Application

3 Work Experience : 5 Years

4 Work Experience related

to EIA

: 1 Year

5 Previous Organizations

Served

: Haryana State Pollution Control Board

6 Specialization : Consent Management

XXII Name : Monika Singh

1 Status in the Organization : Project Executive

2 Educational Qualification : M. Tech. - Environmental Science & Engineering

3 Work Experience : 1 Year

4 Work Experience related

to EIA

: 1 Year

5 Previous Organizations

Served

: - -

6 Specialization : EIA

S. NO. DIM(m) X DIM(m) FEC. NOS. AREA(SQM.)

G01 7.970 X 2.650 1 1 21.121

G02 1.320 X 6.370 0.67 1 5.634

G03 1 15.589

G04 1 191.991

G05 1 141.550

G06 4.980 X 4.440 0.5 1 11.056

G07 6.330 X 1.300 0.67 1 5.513

G08 1 84.927

G09 1 34.676

G10 1 32.233

G11 3.000 X 2.650 1 3 23.850

G12 1 109.789

G13 1 71.994

G14 1 50.557

G15 0.530 X 2.500 0.5 1 0.663

G16 1 22.277

G17 2.650 X 2.965 1 3 23.572

G18 1 8.456

G19 9.525 X 11.065 0.5 1 52.697

G20 1 222.313

G21 1 11.919

G22 40.620 X 2.315 0.67 1 63.004

G23 2.650 X 2.280 1 4 24.168

G24 3.350 X 2.650 1 2 17.755

G25 13.970 X 8.670 1 1 121.120

G26 10.030 X 11.905 1 1 119.407

G27 15.120 X 2.850 1 1 43.092

G28 1 30.686

1561.607

D01 18.765 X 0.715 0.67 1 8.989

D02 14.705 X 3.100 0.67 1 30.542

39.532

1522.076

TOTAL DEDUCTION AREA (B)

GREEN AREA AT OPEN SURFACE

(29.555 + 17.125 )/2 X 9.525

(15.145 + 13.750 )/2 X 0.825

DEDUCTION AREA

(10.250 + 10.140 )/2 X 3.010

GREEN AREA CALCULATION CALCULATION

GREEN AREA AT OPEN SURFACE = ADDITION -DEDUCTION

ADDITION AREA

TOTAL ADDITION AREA (A)

(5.680 + 1.180 )/2 X 4.545

(2.870 + 3.055 )/2 X 11.705

(42.375 + 42.490 )/2 X 0.525

(2.920 + 3.025 )/2 X 36.935

(3.025 + 2.760 )/2 X 24.890

(2.700 + 2.500 )/2 X 19.445

(5.335 + 5.680 )/2 X 34.860

(13.230 + 2.870 )/2 X 10.550

(3.045 + 2.650 )/2 X 11.320

(16.280 + 15.935 )/2 X 0.525

(5.255 + 4.980 )/2 X 27.660

9955.72 Sq.mt.

3982.29 Sq.mt.

39822.88 Sq.mt.

3977.613 Sq.mt.

38608.744 Sq.mt.

S.NO. FLOORS IN SQ.M.

1 1st. BASEMENT FLOOR 5229.467 Sq.mt.

2 GROUND FLOOR 3563.787 Sq.mt.

3 FIRST FLOOR 3645.819 Sq.mt.

4 SECOND FLOOR 3648.632 Sq.mt.

5 THIRD FLOOR 3737.369 Sq.mt.

6 FOURTH FLOOR 2690.612 Sq.mt.

7 FIFTH FLOOR 1896.851 Sq.mt.

8 SIXTH FLOOR 1976.099 Sq.mt.

9 7TH FLOOR 1680.819 Sq.mt.

10 8th FLOOR 1420.524 Sq.mt.

11 9th FLOOR 1420.524 Sq.mt.

12 10th FLOOR 1420.524 Sq.mt.

13 11th FLOOR 1420.524 Sq.mt.

14 12th FLOOR 1420.524 Sq.mt.

16 13th FLOOR 1420.524 Sq.mt.

17 14th FLOOR 1420.524 Sq.mt.

18 15th FLOOR 595.621 Sq.mt.

38,608.744 Sq.mt.

18 1st. BASEMENT FLOOR 2133.668 Sq.mt.

19 2nd. BASEMENT FLOOR 7748.580 Sq.mt.

20 3rd. BASEMENT FLOOR 7943.810 Sq.mt.

21 SERVICES FLOOR (23.800 LVL.) 1602.328 Sq.mt.

19,428.386 Sq.mt.

58,037.130 Sq.mt.TOTAL BUILT - UP AREA (A+B)

PROPOSED F.A.R. @ 3.878%

F.A.R. AREA CALCULATION

TOTAL PLOT AREA

PERMISSIBLE GROUND COVERAGE @ 40%

PERMISSIBLE F.A.R @ 4.0

PROPOSED GROUND COVERAGE @ 39.95%

TOTAL NON F.A.R. AREA (B)

TOTAL F.A.R. AREA (A)

F.A.R. AREA

NON F.A.R. AREA

4625.000 Sq.mt.

5973.432 Sq.mt.

3619.299 Sq.mt.

S.NO. FLOORS

1 3rd. BASEMENT FLOOR 562.303 Sq.mt.

2 1st. BASEMENT FLOOR 214.518 Sq.mt.

3 GROUND FLOOR 142.631 Sq.mt.

4 FIRST FLOOR 202.640 Sq.mt.

5 SECOND FLOOR 199.827 Sq.mt.

6 THIRD FLOOR 198.394 Sq.mt.

7 FOURTH FLOOR 235.698 Sq.mt.

8 FIFTH FLOOR 95.361 Sq.mt.

9 SIXTH FLOOR 236.565 Sq.mt.

10 7TH FLOOR 270.213 Sq.mt.

11 8th FLOOR 219.246 Sq.mt.

12 9th FLOOR 122.971 Sq.mt.

13 10th FLOOR 122.971 Sq.mt.

14 11th FLOOR 122.971 Sq.mt.

15 12th FLOOR 122.971 Sq.mt.

16 13th FLOOR 122.971 Sq.mt.

17 14th FLOOR 122.971 Sq.mt.

18 15th FLOOR 174.236 Sq.mt.

19 MACHINE ROOM , MUMTY & O.H. WATER TANK 129.841 Sq.mt.

3,619.299 Sq.mt.TOTAL SERVICE AREA

SERVICE AREA

PROPOSED SERVICE AREA 9.088% OF ( 39822.88 )

SERVICE AREA CALCULATION

TOTAL PLOT AREA

PERMISSIBLE SERVICE AREA 15% OF ( 39822.88 )PER.FAR

IN SQ.M.

S. NO. DIM(m) X DIM(m) FEC. NOS. AREA(SQM.)

F01 1 1270.734

F02 1 2785.503

F03 1 808.872

F04 3.105 X 12.010 0.5 1 18.646

F05 0.440 X 1.685 0.5 1 0.371

F06 1 22.522

F07 0.840 X 1.125 0.5 1 0.473

F08 2.605 X 9.990 0.5 1 13.012

F09 1 159.914

5080.046

D01 12.815 X 6.200 1 2 158.906

D02 5.945 X 13.400 1 1 79.663

D03 1 96.680

D04 1.025 X 1.355 0.5 1 0.694

D05 1 33.474

D06 1 8.200

D07 1 22.892

D08 1 51.030

D09 1 414.745

D10 1 148.245

D11 9.065 X 7.905 0.5 1 35.829

D12 2.060 X 7.905 0.5 1 8.142

D13 37.045 X 1.770 0.67 1 43.932

C01 0.580 X 4.430 1 1 2.569

C02 3.000 X 4.660 1 1 13.980

C03 1 41.661

C04 1 8.009

C05 4.935 X 3.425 1 1 16.902

C06 2.300 X 3.195 1 1 7.349

C07 3.710 X 0.950 1 1 3.525

C08 4.030 X 3.570 1 1 14.387

C09 2.430 X 4.375 1 1 10.631

C10 0.900 X 3.000 1 1 2.700

C11 2.955 X 5.460 1 1 16.134

C12 0.645 X 2.200 1 1 1.419

C13 19.220 X 7.565 1 1 145.399

C14 12.845 X 3.275 1 2 84.135

C15 0.980 X 6.415 1 1 6.287

C16 5.360 X 6.455 1 1 34.599

C17 2.300 X 1.800 1 1 4.140

1516.259

3563.787

3977.613

(11.335 + 21.645)/2 X 8.990

( 1.355 + 7.760 )/2 X 7.345

GROUND FLOOR AREA CALCULATION

FAR AREA AT GROUND FLOOR = ADDITION AREA - DEDUCTION AREA

ADDITION AREA

TOTAL ADDITION AREA (A)

(14.165 + 12.010 )/2 X 61.805

(76.600 + 85.560)/2 X 34.355

(45.910 + 76.600)/2 X 20.745

(1.685 + 1.125 )/2 X 16.030

(14.705 + 17.310 )/2 X 9.990

(13.400 + 3.305)/2 X 11.575

( 21.645 + 15.880 )/2 X 22.105

DEDUCTION AREA

( 15.880 + 6.700 )/2 X 4.520

( 7.760 + 6.440 )/2 X 1.155

( 3.025 + 1.595 )/2 X 9.910

TOTAL GROUND COVERAGE ( C)+ (C01 TO C17)

(4.395 + 4.385)/2 X 9.490

(4.935 + 2.330)/2 X 2.205

TOTAL DEDUCTION AREA (B)

TOTAL FAR AREA AT GROUND FLOOR (C)= (A-B)

C01 0.580 X 4.430 1 1 2.569

C02 3.000 X 4.660 1 1 13.980

C04 1 8.009

C05 4.935 X 3.425 1 1 16.902

C06 2.300 X 3.195 1 1 7.349

C07 3.710 X 0.950 1 1 3.525

C08 4.030 X 3.570 1 1 14.387

C09 2.430 X 4.375 1 1 10.631

C10 0.900 X 3.000 1 1 2.700

C11 2.955 X 5.460 1 1 16.134

C12 0.645 X 2.200 1 1 1.419

C15 0.980 X 6.415 1 1 6.287

C16 5.360 X 6.455 1 1 34.599

C17 2.300 X 1.800 1 1 4.140

142.631

SERVICES AREA AT GROUND FLOOR

SERVICES AREA

(4.935 + 2.330)/2 X 2.205

TOTAL SERVICES AREA AT GROUND FLOOR (S)


Recommended