+ All Categories
Home > Documents > PROPOSED EXPANSION OF SILICA SAND PRODUCTION...

PROPOSED EXPANSION OF SILICA SAND PRODUCTION...

Date post: 11-Feb-2021
Category:
Upload: others
View: 9 times
Download: 0 times
Share this document with a friend
111
1 FORM-1 for PROPOSED EXPANSION OF SILICA SAND PRODUCTION PLANT (GLASS GRADE) & LPG STORAGE CAPACITY FOR GLASS MANUFACTURING UNIT of M/s. GUJARAT GUARDIAN LTD. VILLAGE: KONDH, VALIA ROAD, TAL: ANKLESHWAR - 393001, DIST: BHARUCH (GUJ.) NABL Accredited Testing Laboratory ISO 9001:2008 Certified Company Aqua-Air Environmental Engineers P. Ltd. 403, Centre Point, Nr. Kadiwala School, Ring Road, Surat - 395002 Prepared By: NABL Accredited Testing Laboratory ISO 9001:2008 Certified Company Aqua-Air Environmental Engineers P. Ltd. 403, Centre Point, Nr. Kadiwala School, Ring Road, Surat - 395002 NABL Accredited Testing Laboratory ISO 9001:2008 Certified Company Aqua-Air Environmental Engineers P. Ltd. 403, Centre Point, Nr. Kadiwala School, Ring Road, Surat - 395002 Prepared By:
Transcript
  • 1

    FORM-1

    for

    PROPOSED EXPANSION OF SILICA SAND

    PRODUCTION PLANT (GLASS GRADE) & LPG

    STORAGE CAPACITY FOR GLASS

    MANUFACTURING UNIT

    of

    M/s. GUJARAT GUARDIAN LTD.

    VILLAGE: KONDH, VALIA ROAD,

    TAL: ANKLESHWAR - 393001, DIST: BHARUCH (GUJ.)

    NABL Accredited Testing Laboratory

    ISO 9001:2008 Certified Company

    Aqua-Air Environmental Engineers P. Ltd.

    403, Centre Point, Nr. Kadiwala School, Ring

    Road, Surat - 395002

    Prepared By:

    NABL Accredited Testing Laboratory

    ISO 9001:2008 Certified Company

    Aqua-Air Environmental Engineers P. Ltd.

    403, Centre Point, Nr. Kadiwala School, Ring

    Road, Surat - 395002

    NABL Accredited Testing Laboratory

    ISO 9001:2008 Certified Company

    Aqua-Air Environmental Engineers P. Ltd.

    403, Centre Point, Nr. Kadiwala School, Ring

    Road, Surat - 395002

    Prepared By:

  • 2

    APPENDIX I

    (See paragraph - 6)

    FORM 1

    Sr.

    No.

    Item Details

    1. Name of the project/s M/s. Gujarat Guardian Limited

    2. S. No. in the schedule 2(b) & 6(b)

    3. Proposed capacity/ area/ length/

    tonnage to be handled/ command

    area/ lease area/ number of wells to

    be drilled

    Please refer Annexure – I

    4. New/Expansion/Modernization Expansion

    5. Existing Capacity/Area etc. Existing Capacity:

    Float Plant = 2,50,00,000 Sq. meter/Annum

    Silica Sand (Glass Grade) = 33,120 MT/Month

    LPG Tanks: 4 Nos. (Capacity = 56.25 MT each)

    i.e. Total Capacity = 225 MT

    Total Proposed Capacity:

    Float Plant = 2,50,00,000 Sq. meter/Annum

    Silica Sand (Glass Grade) = 86,500 MT/Month

    LPG Tanks: 6 Nos. (Capacity = 120 MT each) i.e.

    Total Capacity of 720 MT

    6. Category of Project i.e. ‘A’ or ‘B’ 'A'

    7. Does it attract the general condition?

    If yes, please specify.

    Yes. Located within 5 km of critically polluted

    area (Ankleshwar).

    8. Does it attract the specific condition?

    If yes, please specify.

    No

    Location

    Plot/Survey/Khasra No. As per the plot detail attached

    Village Kondh, Valia Road

    Tehsil Ankleshwar

    District Bharuch

    9.

    State Gujarat

    10. Nearest railway station/airport along

    with distance in kms.

    Railway Station: Ankleshwar (15.5 km)

    Airport: Surat (75 km)

    11. Nearest Town, city, District

    Headquarters along with distance in

    kms.

    Kondh Village (1.5 km),

    Bharuch (25 km)

    12. Village Panchayats, Zilla Parishad,

    Municipal Corporation, local body

    (complete postal address with

    telephone nos. to be given)

    Kondh Village, Taluka: Ankleshwar – 393 001,

    Dist: Bharuch (Gujarat)

    13. Name of the applicant M/s. Gujarat Guardian Limited

    14. Registered Address Village: Kondh, Valia Road,

  • 3

    Tal: Ankleshwar - 393001, Dist: Bharuch (Guj.)

    Address for correspondence:

    Name Mr. Shyam Raghuwanshi

    Designation (Owner/Partner/CEO) Executive (EHS)

    Address M/s. Gujarat Guardian Limited

    Village: Kondh, Valia Road,

    Tal: Ankleshwar - 393001, Dist: Bharuch (Guj.)

    Pin Code 393 001

    E-mail [email protected]

    Telephone No. Phone: (02643) 275106 to 275115

    Mob.: +91 7043058700

    15.

    Fax No. NA

    16. Details of Alternative Sites examined,

    if any.

    Location of these sites should be

    shown on a top of sheet.

    NA

    17. Interlinked Projects NA

    18. Whether separate application of

    interlinked project has been

    submitted?

    NA

    19. If yes, date of submission NA

    20. If no, reason NA

    21. Whether the proposal involves

    approval/clearance under: if yes,

    details of the same and their status to

    be given.

    (a) The Forest (Conservation) Act,

    1980?

    (b) The Wildlife (Protection) Act,

    1972?

    (c) The C.R.Z. Notification, 1991?

    No

    22. Whether there is any Government

    Order/Policy relevant/relating to the

    site?

    No

    23. Forest land involved (hectares) NA

    24. Whether there is any litigation

    pending against the project and/or

    land in which the project is propose

    to be set up?

    (a) Name of the Court

    (b) Case No.

    (c) Orders/directions of the Court, if

    any and its relevance with the

    proposed project.

    NA

    • Capacity corresponding to sectoral activity (such as production capacity for

    manufacturing, mining lease area and production capacity for mineral production,

  • 4

    area for mineral exploration, length for linear transport infrastructure, generation

    capacity for power generation etc.,)

    (II) Activity

    1. Construction, operation or decommissioning of the Project involving actions, which will cause physical changes in the locality (topography, land use, changes in water bodies, etc.)

    Sr.

    No.

    Information/Checklist

    confirmation

    Yes/No Details there of with approximate quantities

    frates, wherever possible) with source of

    information data

    1.1 Permanent or temporary change

    in land use, land cover or

    topography including increase

    intensity of land use (with

    respect to local land use plan)

    No Proposed Expansion will be carried out

    within the existing premises.

    Total Cost of the Project is Rs. 624 Crores

    (Existing = 584 Crores + Additional = 40

    Crores)

    Total Plot Area = 6,55,990.4 m2

    Green Belt = 80,936.51 m2

    1.2 Clearance of existing land,

    vegetation and Buildings?

    Yes Already available

    1.3 Creation of new land uses? No

    1.4 Pre-construction investigations

    e.g. bore Houses, soil testing?

    Yes Soil investigation will be done

    1.5 Construction works? Yes Plant Layout attached as Annexure - II

    1.6 Demolition works? Yes Demolition of existing sand plant

    1.7 Temporary sites used for

    construction works or housing of

    construction workers?

    No

    1.8 Above ground buildings,

    structures or earthworks

    including linear structures, cut

    and fill or excavations

    No Plant Layout attached as Annexure - II

    1.9 Underground works mining or

    tunneling?

    No

    1.10 Reclamation works? No

    1.11 Dredging? No

    1.12 Off shore structures? No

    1.13 Production and manufacturing

    processes?

    Yes For detail Please refer Annexure –III

    1.14 Facilities for storage of goods or

    materials?

    Yes Specified storage area shall be provided for

    storage of goods, Raw materials & Finished

    products.

    1.15 Facilities for treatment or

    disposal of solid waste or liquid

    effluents?

    Yes For detail please refer Annexure – IV & V

    1.16 Facilities for long term housing of

    operational workers?

    No

  • 5

    1.17 New road, rail or sea traffic

    during Construction or

    operation?

    No

    1.18 New road, rail, air waterborne or

    other transport infrastructure

    including new or altered routes

    and stations, ports, airports etc?

    No

    1.19 Closure or diversion of existing

    transport routes or infrastructure

    leading to changes in Traffic

    movements?

    No

    1.20 New or diverted transmission

    lines or Pipelines?

    No

    1.21 Impoundment, damming,

    culverting, realignment or other

    changes to the hydrology of

    watercourses or aquifers?

    No

    1.22 Stream crossings? No

    1.23 Abstraction or transfers of water

    form ground or surface waters?

    No No ground water shall be used. The raw

    water shall be supplied by Valia Water

    Supply System (Canal Water).

    1.24 Changes in water bodies or the

    land surface Affecting drainage or

    run-off?

    No

    1.25 Transport of personnel or

    materials for construction,

    operation or decommissioning?

    Yes Transportation of personnel, raw material

    and products will be primarily by road only

    1.26 Long-term dismantling or

    decommissioning or restoration

    works?

    Yes We will be dismantling the existing Sand

    beneficiation plant once the new sand

    beneficiation plant would be operational.

    1.27 Ongoing activity during

    decommissioning which could

    have an impact on the

    environment?

    No

    1.28 Influx of people to an area

    either temporarily or

    permanently?

    No M/s. Gujarat Guardian Limited will give direct

    employment to local people based on

    qualification and requirement. In addition to

    direct employment, indirect employment

    shall generate ancillary business to some

    extent for the local population.

    1.29 Introduction of alien species? No

    1.30 Loss of native species or genetic

    diversity?

    No

    1.31 Any other actions? No

  • 6

    2. Use of Natural resources for construction or operation of the Project (such as land, water, materials or energy, especially any resources which are non-renewable or in short supply):

    Sr.

    No.

    Information/checklist confirmation Yes/No Details there of (with approximate quantities

    frates, wherever possible) with source of

    information data

    2.1 Land especially undeveloped or

    agricultural land (ha)

    No Land of 6,55,990.4 m2

    2.2 Water (expected source &

    competing users) unit: KLD

    Yes The entire water requirement will be met

    through Valia Water Supply System (Canal

    Water). Water available from GIDC. For detail

    please refer Annexure – VI

    2.3 Minerals (MT) No

    2.4 Construction material: stone,

    aggregates,

    and / soil (expected source – MT)

    Yes Construction materials like crushed stones,

    sand, rubble, cement, steel, etc. required for

    the project shall be procured from the local

    market of the region.

    2.5 Forests and timber (source – MT) No

    2.6 Energy including electricity and

    fuels (source, competing users)

    Unit: fuel (MT), energy (MW)

    Yes For detail please refer Annexure – VI

    2.7 Any other natural resources (use

    appropriate standard units)

    No

    3. Use, storage, transport, handling or production of substances or materials,

    which could be harmful to human health or the environment or raise concerns about actual or perceived risks to human health.

    Sr. No. Information/Checklist confirmation Yes/No Details there of (with approximate

    quantities/rates, wherever possible)

    with source of information data

    3.1 Use of substances or materials, which

    are hazardous (as per MSIHC rules) to

    human health or the environment

    (flora, fauna, and water supplies)

    Yes For detail please refer Annexure –VII.

    3.2 Changes in occurrence of disease or affect disease vectors (e.g. insect or water borne

    diseases)

    No

    3.3 Affect the welfare of people e.g. by

    changing living conditions?

    No

    3.4 Vulnerable groups of people who

    could be affected by the project e.g.

    hospital patients, children, the elderly

    etc.

    No

    3.5 Any other causes No

  • 7

    (II) Production of solid wastes during construction or operation or decommissioning (MT/month)

    Sr.

    No.

    Information/Checklist confirmation Yes/No Details there of (with approximate

    quantities/rates, wherever possible) with

    source of information data

    4.1 Spoil, overburden or mine wastes No

    4.2 Municipal waste (domestic and or

    commercial wastes)

    No

    4.3 Hazardous wastes (as per Hazardous

    Waste Management Rules)

    Yes Please refer Annexure – V

    4.4 Other industrial process wastes No

    4.5 Surplus product No

    4.6 Sewage sludge or other sludge from

    effluent treatment

    Yes

    Please refer Annexure – V

    4.7 Construction or demolition wastes

    Yes

    We will be dismantling the existing Sand

    beneficiation plant once the new sand

    beneficiation plant would be operational

    and that will result into generation of metal

    scrap and other waste.

    4.8 Redundant machinery or equipment No

    4.9 Contaminated soils or other materials No

    4.10 Agricultural wastes No

    4.11 Other solid wastes Yes

    Please refer Annexure – V

    5. Release of pollutants or any hazardous, toxic or noxious substances to air (Kg/hr.)

    Sr.

    No.

    Information/Checklist

    confirmation

    Yes/No Details there of (with approximate

    quantities/rates, wherever possible) with source

    of information data

    5.1 Emissions from combustion of

    fossil fuels from stationary or

    mobile sources

    Yes For details Please refer Annexure – VIII

    5.2 Emissions from production

    processes

    Yes For details Please refer Annexure – VIII

    5.3 Emissions from materials

    handling storage or transport

    Yes All liquid raw materials, chemicals are procured

    in tankers and are transferred through a closed

    pipe lines.

    Solid raw materials (Batch) are feed into furnace

    through close pipeline/chute/conveyors and the

    dust collection hoppers are connected to a bag

  • 8

    filter and ID fan.

    Also, all hazardous chemicals (flammable) storage

    tanks are provided with safety, Excess flow valve &

    remote operating valve for safety wherever

    applicable.

    5.4 Emissions from construction

    activities including plant and

    equipment

    Yes During construction work, only dust

    contamination will be there & water sprinklers

    shall be utilized whenever necessary.

    5.5 Dust or odours from handling

    of materials including

    construction materials,

    sewage and waste

    Yes All the waste shall be stored in designated place

    and shall be transported to TSDF site in approved

    closed vehicles owned by the TSDF authority.

    Dust from drying will be collected in to dust

    collector through cyclone separator & recovered

    powder will be recycled back to process. Air

    Handling Unit will be provided where ever

    applicable.

    5.6 Emissions from incineration of

    waste No

    5.7 Emissions from burning of

    waste in open air e.g. slash

    materials, construction debris)

    No

    5.8 Emissions from any other

    sources No

    (III) Generation of Noise and Vibration, and Emissions of Light and Heat:

    Sr. No. Information/Checklist confirmation Yes/No Details there of (with approximate

    quantities/rates, wherever possible) with

    source of information data with source of

    information data

    6.1 From operation of equipment e.g.

    engines, ventilation plant, crushers

    Yes All machinery / equipment shall be well

    maintained, shall have proper foundation with

    anti vibrating pads wherever applicable.

    Expected Noise level at different locations in

    the plant is enclosed as Annexure – IX

    6.2 From industrial or similar processes Yes Please refer Annexure – IX

    6.3 From construction or demolition Yes

    6.4 From blasting or piling No

    6.5 From construction or operational

    traffic

    Yes

    6.6 From lighting or cooling systems Yes Please refer Annexure – IX

    6.7 From any other sources No

  • 9

    7. Risks of contamination of land or water from releases of pollutants into the

    ground or into sewers, surface waters, groundwater, coastal waters or the sea:

    Sr. No. Information/Checklist confirmation Yes/No Details there of (with approximate

    quantities/rates, wherever possible) with

    source of information data

    7.1 From handling, storage, use or

    spillage of hazardous materials

    Yes Hazardous material shall be stored in

    designated storage area with bund walls for

    tanks. Other material will be stored in

    bags/drums on pallets with concrete flooring

    and no spillage is likely to occur. All liquid raw

    materials shall be transported through pumps

    and closed pipelines and no manual handling

    shall be involved. Spill Container will be kept at

    appropriate places to collect spillage. SOP for

    collection, decontamination & disposal of

    spilled material will be displaced at necessary

    locations. For details please refer Annexure –

    VII

    7.2 From discharge of sewage or

    other effluents to water or the

    land (expected mode and place of

    discharge)

    Yes The wastewater generated from Cooling,

    Chilling & Washing will be reused in Sand Plant

    for Sand Washing through recirculation. The

    Domestic wastewater will be treated in Sewage

    Treatment Plant and will be reused for Land

    Irrigation/Gardening. Hence it will be a Zero

    Liquid Discharge Plant.

    7.3 By deposition of pollutants

    emitted to air into the and or into

    water

    No

    7.4 From any other sources No

    7.5 Is there a risk of long term build

    up of pollutants in the

    environment from these sources?

    No

    8. Risk of accidents during construction or operation of the Project, which could affect human health or the environment

    Sr.

    No.

    Information/Checklist

    confirmation

    Yes/No Details there of (with approximate

    quantities/rates, wherever possible) with

    source of information data

    8.1 From explosions, spillages, fires

    etc from storage, handling, use

    or production of hazardous

    substances

    Yes For detail please refer Annexure – VII

  • 10

    8.2 From any other causes No

    8.3 Could the project be affected by

    natural disasters causing

    environmental damage (e.g.

    floods, earthquakes, landslides,

    cloudburst etc)?

    No

    9. Factors which should be considered (such as consequential development)

    which could lead to environmental effects or the potential for cumulative impacts with other existing or planned activities in the locality

    (IV) Environmental Sensitivity

    Sr. No. Areas Name/

    Identity

    Aerial distance (within 5 km.) Proposed

    project location boundary

    1 Areas protected under international

    conventions, national or local

    legislation for their ecological,

    landscape, cultural or other related

    value

    No Proposed expansion is within the existing

    premises.

    Sr.

    No.

    Information/Checklist confirmation

    Yes/

    No

    Details there of (with approximate

    quantities/rates, wherever possible)

    with source of information data

    9.1 Lead to development of supporting.

    utilities, ancillary development or

    development stimulated by the project

    which could have impact on the

    environment e.g.

    • Supporting infrastructure (roads, power

    supply, waste or waste water treatment,

    etc.)

    • housing development

    • extractive industry

    • supply industry

    • other

    Yes For detail please refer Annexure – X

    9.2 Lead to after-use of the site, which could

    have an impact on the environment

    No

    9.3 Set a precedent for later developments No

    9.4 Have cumulative effects due to proximity

    to other existing or planned projects with

    similar effects

    No

  • 11

    2 Areas which important for are or

    sensitive Ecol logical reasons –

    Wetlands, watercourses or other

    water bodies, coastal zone,

    biospheres, mountains, forests

    No

    3 Area used by protected, important

    or sensitive Species of flora or fauna

    for breeding, nesting, foraging,

    resting, over wintering, migration

    No

    4 Inland, coastal, marine or

    underground waters

    No No inland, costal or marine within 5 km

    from the proposed project

    5 State, National boundaries No 6 Routes or facilities used by the

    public for access to recreation or

    other tourist, pilgrim areas

    No

    7 Defense installations No

    8 Densely populated or built-up area Ankleshwar Ankleshwar is around 4 km from the

    proposed expansion project site.

    9 Area occupied by sensitive man-

    made land uses Hospitals, schools,

    places of worship, community

    facilities)

    No

    10 Areas containing important, high

    quality or scarce resources (ground

    water resources, surface resources,

    forestry, agriculture, fisheries,

    No

    11 Areas already subjected to pollution

    environmental damage. (those

    where existing legal environmental

    standards are exceeded)or

    No

    12 Areas susceptible to natural hazard

    which could cause the project to

    present environmental problems

    (earthquakes, subsidence,

    landslides, flooding, erosion, or

    extreme or adverse climatic

    conditions)

    No

    IV). Proposed Terms of Reference for EIA studies: For detail please refer Annexure–

    XI

  • 12

  • 13

    LIST OF ANNEXURES

    SR. NO. NAME OF ANNEXURE

    I List of Products with their Production Capacity

    II Layout Map of the Plant

    III Brief Manufacturing Process Description

    IV Description of Effluent Treatment Plant with flow diagram

    V Details of Hazardous Waste

    VI Water, Fuel & Energy Requirements

    VII Details of Hazardous Chemicals Storage & Handling

    VIII Details of Stacks and Vents

    IX Expected Noise level at Different source within the premises

    X Socio-economic Impacts

    XI Proposed Terms of Reference for EIA studies

    XII Water Supply Letter

    XIII TSDF & CHWIF Membership Letter

    XIV Lease Deed Documents

    XV Toposheet

  • 14

    ANNEXURE-I

    LIST OF PRODUCTS ALONG WITH PRODUCTION CAPACITY

    Float Plant Details:

    Quantity in Square Meter/Annum S. No. Product

    Permitted Additional Total

    1 Float Glass

    2 Mirror

    3 Lacquered Glass

    4 Coater Glass

    2,50,00,000

    - 2,50,00,000

    Proposed Expansion Details:

    SR.

    NO.

    PRODUCT NAME EXISTING CAPACITY

    (MT/MONTH)

    PROPOSED CAPACITY

    (MT/MONTH)

    1 Silica Sand (Glass Grade) 13,500 56,225

    2 By-Products (Coarse, Fines and rejects) 19,620 30,275

    3 Total 33,120 86,500

    LPG Storage Tank Details

    Existing Capacity:

    LPG Tanks = 4 Nos. (Capacity = 56.25 MT each)

    SR.

    NO.

    Storage Material No. of Tanks Capacity Total Capacity Tank Dimensions

    1 LPG 4 56.25 MT (each) 225 MT Length = 16.2 m

    Diameter = 3200 mm

    Total Proposed Capacity:

    LPG Tanks = 6 Nos. (Capacity = 120 MT each)

    Proposed combine capacity: 720 MT

    SR.

    NO.

    Storage

    Material

    No. of Tanks Capacity Total Capacity Tank Dimensions

    1 LPG 6 120 MT

    (each)

    720 MT Design Pressure: 21 Kg/cm2

    Overall Length = 24000 mm,

    Tank ID 4010 mm,

    Tank Shell = 28 mm thick

    Dished End 18 mm Thick.

    Note: M/s. Gujarat Guardian Limited is exploring the option to merge the existing and

    proposed LPG storage yard for future so that the new LPG yard would be (existing + proposed)

    capacity which is 720 MT. By proposing this we are also proposing that existing yard be

    demolished and merged with new LPG storage yard in case above is the decision.

    Existing LPG storage yard: 225 MT

    Additional Proposed LPG storage: 495 MT

    Total Storage of LPG onsite: 720 MT

  • 15

    LIST OF RAW MATERIAL (EXISTING & PROPOSED)

    Consumption Quantity Per Month Sr.

    No. Raw Material

    UOM Permitted Proposed

    Additions Total

    Float Glass

    1 Sand MT 14,000 0 14,000

    2 Soda Ash MT 4,500 0 4,500

    3 Dolomite MT 3,800 0 3,800

    4 Limestone MT 1,400 0 1,400

    5 Feldspar MT 850 0 850

    6 Salt Cake MT 215 0 215

    7 Carbon MT 21 0 21

    8 Cullet MT 6,000 0 6,000

    Wet Coater

    1 Raw Glass Sq. Meter 5,83,000 0 5,83,000

    2 Washing & Polishing Chemicals Kg 2,062 0 2,062

    3 Tin Sensitizer Litre 119 0 119

    4 Palladium Sensitizer Litre 45 0 45

    5 Silver Solution

    Silver Nitrate

    Litre

    Kg

    2,600

    1,088 0

    2,600

    1,088

    6 Reducer/

    Silver less solution

    Litre

    Litre

    4,830

    2,920 0

    4,830

    2,920

    7 GMPA & GMPB Litre 1,190 0 1,190

    8 Paint MT 68 0 68

    9 Ortho-Xylene Litre 9,971 0 9,971

    10 HCL-32% Litre 11,393 0 11,393

    11 Caustic-32% Litre 13,508 0 13,508

    12 Ferric Sulfate kg 256 0 256

    Lacquered Glass

    1 Raw Glass Sq. Meter 1,50,000 0 1,50,000

    2 Washing and polishing chemical Kg 200 0 200

    3 Adhesion Promoter Litre 50 0 50

    4 Paint MT 10 0 10

    A GLASSOLUX NG 9003 PURE WHITE Kg 2,500 0 2,500

    B GLASSOLUX NG 2105 Sapphire Kg 2,500 0 2,500

    C GLASSOLUX NG 3004 Burgundy Kg 2,500 0 2,500

    D GLASSOLUX NG 6113 Fluo green Kg 2,500 0 2,500

    E GLASSOLUX NG 9005 Black Kg 2,500 0 2,500

    F Ivory Kg 2,500 0 2,500

    G Red Kg 2,500 0 2,500

    5 Ortho-Xylene Litre 1,000 0 1,000

    Sand Beneficiation Plant

    1 Raw Silica Sand MT 33,120 53,380 86,500

  • 16

    ANNEXURE-II

    LAYOUT MAP OF THE PLANT

  • 17

    LPG STORAGE LAYOUT (EXISTING)

  • 18

    LPG STORAGE LAYOUT (PROPOSED)

  • 19

    ANNEXURE-III

    BRIEF PROCESS DESCRIPTION

    EXISTING

    Below is the manufacturing process for following products;

    1. Float Glass

    2. Mirror Glass

    3. Deco crystal Glass

    1. Sand Beneficiation Process

    The basic beneficiation process comprises of chemical and mechanical treatment of

    raw sand to remove embedded heavy minerals, clay and over and under size grain.

    This involves washing sand with water and then applying mechanical media to scrub

    the impurities and there after treating with chemicals to froth out the heavy

    minerals and other impurities.

  • 20

    2. Glass Manufacturing

    a) Float Glass

    The basic float glass manufacturing process was invented in the mid- 1950’s due to

    inherent efficiency over the then existing sheet and plate production methods, the

    float glass industry worldwide has subsequently been essentially converted to the

    float process. The most significant advantages of the float process lie in its highly

    automated production process and the consistency of product quality. For example,

    the float process compared to the sheet glass process requires less manual handling,

    it is more cost efficient to produce and eliminates significant distortion in the glass.

    Over the last thirty years, there have been several technological advances towards

    design and manufacture of refractories and equipment applicable to the float glass

    manufacturing.

    The float glass manufacturing process would consist of receiving raw materials (Silica

    sand, Soda Ash, Limestone, Dolomite, Salt Cake, and minor ingredient materials

    including Rouge and Charcoal) in bulk quantities by rail and road from various

    locations. Raw materials would be unloaded and stored in batch house, then

    weighed into batches, mixed and then layered with broken glass (“Cullet”) returned

    from the end of the process line. The mixed batch would be conveyed to the furnace

    where the raw materials would be melted using either natural gas or fuel oil.

    Molten glass from the furnace would flow by gravity and displaced into a tin bath

    where a continuous ribbon would be formed by controlling glass temperature with

    time. The ribbon would be pulled, or drawn, through the bath on a layer of molten

    tin, the temperature of which would be controlled electrically. Upon existing the

    bath, the ribbon of glass would enter the electrically heated annealing lehr where in

    it would be cooled preparatory to cutting into sheets.

    A computer controlled automatic cutting system would cut the ribbon into

    predetermined sizes as dictated by customer orders. Pieces would than either be

    placed racks, boxes, or on dollies for storage or direct shipment. Any waste or

    damaged glass would be broken and recycled to the batch house as cullet. Additional

    information about each stage of the manufacturing process is contained in the

    following sections.

    Raw Materials:

    Raw materials needed for the manufacture of float glass include Silica sand, Soda

    Ash, Limestone, Dolomite, Salt Cake and minor amounts of Rouges and Charcoal.

    Silica sand would comprise about 60% of the total raw material input with Soda Ash,

    Dolomite together making up about 35% of the total by weight. The remainder

    would be distributed among Limestone, Salt cake, Charcoal and Rouge.

  • 21

    Batch House:

    Raw material would be received at the plant site in trucks and/or rail cars. Materials

    would be dumped into a hopper in a unloading area by a belt conveyer to a bucket

    elevator where they would be discharged into the proper bins with the help of a

    rotary spout. The concrete storage bins would be designed in such a way that

    material segregation would be reduced to a minimum, an important quality

    consideration in glass manufacturing. Each material would be weighed individually

    on high accuracy industrial scales, and then checked on a totalizer scale prior to the

    bin discharged into the mixer. The dry ingredients would be thoroughly mixed, and

    then measured amount of water would be added to the mixer for wet mixing. After

    mixing a precise amount of cullet would be layered on the mixed batch prior to

    conveying to a melting furnace. The batch would be stored in large hopper over the

    furnace feeder. In the event of mechanical or electrical failure of any batch, system

    component, this hopper would provide mixed batch for about six hours of continues

    feeding in to the furnace. Dust control equipment in the unloading area and batch

    house would operate continuously to maintain a safe, healthy and working

    environment for the employees, as well as to minimize dust and particulate

    emissions.

    Melting Furnace:

    The melting furnace would be capable of melting clear glass at a desired rate. The

    batch materials would be fed into the glass-melting furnace from the blanket. The

    operation of the feeder would control by a precise glass level controller.

    The melting furnace would be a large refractory structure enclosed in structure and

    binding steel. Many different types of refractory materials are used in furnace

    construction. Each one is carefully selected to use in certain areas where it will

    perform with a long life and not contribute to product defects. The furnace

    refractory, if misapplied, can very often be a major source of glass defects. The batch

    material would be pushed away from the furnace back wall by the blanket feeder.

    Floating on top of the molten glass, the batch would pass under the fuel flames,

    pouring out of the ports above the furnace side wall. Temperature exceeding 2900

    degree F would melt the batch ingredients. Combustion products would be

    discharged through a stack.

    After the batch material melts into solution, the molten glass would be gradually

    cooled in the refiner section of the furnace. By the time the glass would reach the

    end of the melting furnace, it should be completely free of un-melted batch particles

    and uniform in composition. This homogeneous blend of molten glass would now be

    delivered to the float bath in a constant pouring action through the channel.

    Float Bath:

    The float bath would consist of an electrically heated forming oven. The glass would

    flow on to the surface of a pool of molten tin at approximately 2900 degree F. A

    continuous ribbon would be drawn from this pool and transported and cooled along

    the length of the float bath. The temperature of glass at the bath exist would be

    approximately 1100 degree F, still a plastic material but solid enough to the removed

  • 22

    from the surface of the tin with mechanical rolls. A flow of SO2 gas mixed with

    nitrogen is applied on these rolls to prevent any damage to the bottom of glass

    ribbon by these or the subsequent rolls. The bath chamber would be carefully sealed

    and maintained under positive pressure by a nitrogen atmosphere made slightly

    reducing by the addition of small amount of Hydrogen. This is necessary to maintain

    a clean pristine surface for the tin, which would rapidly oxidize in air.

    The molten glass, when flowing on the surface of the molten tin, forms a ribbon of

    perfectly flat parallel surface 6 mm thick. Additional process manipulation of the

    glass can produce thickness ranging from 2 mm to 12 mm and above. The ribbon

    emerges from the tin bath at different speeds to provide the desired thickness.

    Annealing Lehr:

    The Annealing lehr must cool the glass ribbon from 1100 degree F to approximately

    200 degree F, in a precise uniform manner to prevent residual stresses that make

    cutting difficult and also to prevent temporary stresses that causes ribbon fractures.

    The lehr would use small amounts of electric heat to keep the edge of the sheet

    from cooling faster than the center. There are special rollers and drive systems

    required for the lehr as well as a sophisticated temperature control system to

    accomplish the controlled cooling.

    Cutting Line:

    The glass would emerge from the annealing lehr in continuous ribbon at a

    temperature slightly above room temperature. The glass would pass under a

    darkened booth where, under special lighting conditions, inspector would scan every

    square foot for defects. An automated inspection system would detect defects in the

    glass ribbon and help command the defect marking system to spray ink on the

    defect. The glass sheets containing defect would be broken crushed and returned to

    the batch house to be recycled with the raw materials.

    The inspected ribbon would be cut to exact dimensions with precise, high-speed

    cutters. The edge trim would be eliminated, crushed and returned to the batch

    house. The glass sheets, free of defects, would now be boxed or put on metal racks

    and warehoused for shipment. Special vacuum units are required to unload large

    glass sheets. Due to the fragile nature of glass, most of the float glass leaving the

    plant would be shipped by truck.

  • 23

    Process Block Diagram:

    Product Sand

    (Used as Raw Material for

    Manufacturing of Float

    Glass)

    Chemical

    Dosing &

    Iron

    Removal

    Batching Melting Furnace

    Forming

    (Float Bath) Inspection Annealing Lehr

    Cutting Line and

    Storage

    Final Product Float Glass

    (Used as Raw Material for Mirror

    Glass Manufacturing)

    Sand Mining

    Screening Washing Sizing Sand Yard

  • 24

    Mirror from Float Glass

    Silvered mirror is manufactured by deposition of silver by reduction process. Layer of

    silver deposited on clear glass acts as reflective surface in which images can be seen

    clearly.

    Raw floated glass is loaded flat on the atmospheric side on the loading table with the

    help of robotic arm. This raw glass is rinsed with Ultra filtered water to get rid of

    separator powder, dirt, dust and any other water soluble contamination. After

    rinsing, Glass is cleaned and polished with the help of oscillating cylindrical brushes

    and applying a polishing agent. This process smoothens the surface of glass and

    exposes a fresh layer of glass.

    On the cleaned glass surface, first layer of sensitizer, which is basically a tin chloride

    solution, is applied. After first layer of sensitizer, second layer of super sensitizer i.e.

    Palladium chloride solution is sprayed. After sensitization, glass surface is rinsed off

    with D.M water and silver nitrate solution along with the reducer is sprayed. Silver

    nitrate is reduced to silver ion on the glass surface and deposited in multiple layers,

    forming a reflective surface. This reflective surface of silver is protected by spraying

    tin solution, and a reducer, which deposits a layer of tin over the layer of silver. This

    helps prolong the life of silver layer as it is not exposed directly to corroding

    atmosphere.

    After application of passivator, two coats of paint are applied with the help of curtain

    coater. First coat of paint provides chemical and corrosion resistance protection to

    the reflective surface. Second layer of paint provides mechanical resistance such as

    abrasion, dirt, dust etc. Both the paint are dried and cured in ovens which use MW IR

    heaters as source of heat. After application of paints, glass passes through ovens at a

    fixed speed for specified time duration and temperature. Mirror is then cooled,

    washed, branded and packed.

  • 25

    Flowchart for Mirror:

  • 26

    1. Lacquered Glass from Float Glass

    Lacquered glass is a back painted flat glass, used for decorative purposes.

    Raw floated glass is loaded flat on the atmospheric side on the loading table with the

    help of robotic arm. This raw glass is rinsed with Ultra filtered water to get rid of

    separator powder, dirt, dust and any other water soluble contamination. After

    rinsing, Glass is cleaned and polished with the help of oscillating cylindrical brushes

    and applying a polishing agent. This process smoothen the surface of glass and

    exposes a fresh layer of glass.

    On the cleaned glass surface, a layer of neutral silicone adhesive along with DI water

    is sprayed, allowed to settle and then excess is rinsed. After application of adhesive,

    a coat of paint is applied with the help of curtain coater. Paint is baked in electrically

    heated ovens for a fixed duration at certain temperature, which is dependent on

    thickness of glass and color of paint.

    Lacquered glass is cooled, washed, branded and packed.

    Flowchart for Lacquered Glass:

    Raw Glass

    UF WaterWashing with UF

    waterdrained

    Cerium

    Oxide

    slurry

    Cleaning with

    Cerium Powderdrained

    UF WaterFinal cleaning with

    cylindrical brushesDrained

    GMP A &

    GMP B SolnAdhesive spray drained Packing

    Dryer & Preheat Branding

    Base Coat paint

    CurtainFace wash

    Base Coat Oven Top Coat Oven

  • 25

    2. Coater Glass from Float Glass

    Float glass is used as the primary raw material for the coating operation. The glass is washed

    using ultra-pure water. A de-ionization and/or reverse osmosis (DI/RO) water treatment

    system is used to obtain the water purity necessary for washing the glass. A small amount of

    a detergent is added to the wash water. A scrubbing media, typically Aluminum Oxide, may

    be also be used to clean the glass. After the glass has been washed, it is air dried and then

    conveyed to the coater.

    The coater is a high-tech process in which a molecular-level deposit of metals and other

    compounds are bonded to the glass. This molecular-level thickness of coating compounds

    provides the glass with various reflective and refractive properties. The coater consists of a

    series of vacuum chambers in which the washed glass in conveyed into. Once the glass is in

    the vacuum chamber, short strong pulses of electricity are sent through both the glass and a

    ‘target’. The target is a pre-manufactured source of the coating. Examples of coating target

    materials include: Silver, Nickel, Chromium, Titanium, Aluminum, Tin, Zinc, and Silicone.

    None of the target materials used is emitted/released to atmosphere, because of a vacuum

    pressure within the coater.

    The target material is atomized by bombarding it with positively charged Argon ions from

    plasma. These are created by feeding gas into the plasma at the cathode (or target). A

    magnetic field determines the density of the plasma. The metal atoms emitted from the

    cathode target will adhere to the glass substrate. So that the gas discharge process can be

    initiated and maintained, the related electrostatic field intensity is necessary. These are

    created by a sputter power/current supply.

    After the glass receives the appropriate layers of coating, it is conveyed out of the coater,

    rinsed with water, cut into specific sizes, packed to reduce breakage, stored, and ultimately

    shipped to customers.

  • 26

    PROCESS FLOW DIAGRAM

  • 27

    SAND PLANT (PROPOSED – CAPACITY ENHANCEMENT)

    Process Description

    It is to be noted that the process description below is based upon preliminary information

    and design only at this stage. Further test work particularly in regards to the settling velocity

    of the slimes and efficiency of the dewatering/filter equipment will have ramifications on

    the design of the final process.

    FEED PREPARATION

    Feed will be received in a dump hopper with a 150mm grizzly screen. Feed will be metered

    into the circuit via belt feeder governed by a belt weigher on an inclined conveyor. The feed

    will be conveyed into a drum scrubber where it will have water added. The drum scrubber is

    intended to liberate the agglomerated material and free some of the clay material in the

    feed. The discharged product will pass through a coarse screen attached to the drum to

    remove any material >6mm.

    DESLIMING AND SIZING STAGE

    The scrubbed material will transfer via gravity to a desliming sump to be pumped to a

    cyclone for removal of clay particles. The overflow of the cyclone containing the fine clay

    particles will report to the thickener for processing. The underflow will report to a sizing

    screen. All particles less than 600 micron will be pumped to the attritioner feed cyclone.

    Oversize material will launder to the ball mill for comminution. Milled material will launder

    back to the desliming sump for re-processing in the desliming cyclone.

    ATTRITIONING STAGE

    Material that passes through the sizing screen will be pumped to a cyclone above the

    attritioner. The cyclone will dewater the feed to the attritioner to a high density prior to

    laundering to the attritioner. The attritioner scrubs the high density slurry using a series of

    rotating paddles to remove any contamination from the surface of the sand particles. The

    overflow from the cyclone will launder via gravity to the thickener.

    UP CURRENT CLASSIFICATION STAGE

    After processing in the attritioner the slurry will be pumped to an up current classifier (UCC)

    for classification by size using a current of rising water in a vessel. Larger, higher density

    particles pass down through the current while smaller, lighter particles are lifted over a

    weir. The flow rate of the up current water can be varied to adjust the cut size of the

    particles reporting to the overflow. The UCC overflow consisting of particles

  • 28

    launder to a process sump feeding the product dewatering cyclone and screen. The product

    will be dewatered and transferred to a conveyor system for stockpiling. The overflow

    fraction of the cyclone will be laundered directly to the drum scrubber for re-use. The

    middlings fraction will either be sent to the rejects process sump or returned to the spiral

    feed sump in response to operational conditions and feed characteristics.

    PROCESS WATER AND THICKENER

    A process water tank will be the source of all water distribution through the circuit. Through

    the use of dewatering equipment on all output streams MT has endeavored to minimize the

    net water loss therefore reducing water make-up demand into the circuit. Clean water is

    recirculated within the system, where possible, to reduce both thickener size and flocculent

    consumption. Water removed from the circuit in high slimes stages will be treated in the

    thickener using a flocculent such that clean water will flow over the weir. This water will

    then report via a coarse static screen to the process water tank. Thickened slimes will flow

    via the underflow to a process pump for transfer to the belt filter press. The filter press will

    dewater the slimes as much as possible prior to stockpiling. A requirement for further

    flocculent dosage prior to filtering will be determined in detailed test work.

    Chemical Usage

    The only chemical addition to the plant process will be a flocculant. Detailed test work will

    determine the best type of flocculant for these slimes, what type of dosing system would be

    most appropriate and at what rate flocculant will need to be added to the system to remove

    the slimes and clarify the water. Assuming a dry granular type flocculant is to be used then

    consumption has been assumed to be between approx. 0.5 to 1.5 metric tonne/month.

    Product Mass Balance

    Given the variability and range of feed sources the mass balance can vary markedly. Below is

    an estimate based upon information provided by Gujarat Guardian.

    Estimated Output Quantities as % per Month

    Note: Values are based upon feed characteristics provided by GG.

    Product Name

    Minimum

    Throughput

    MT/month)

    Maximum

    Throughput

    (MT/month)

    Remarks

    X Feed 100% Based upon nominal feed rate of 120 t/h at 80%

    plant availability

    A Finished Sand for Float

    Glass 70% 90% Based upon range of values provided by GG

    B Fines Rejection of (-) 150

    micron 5% 25% 5% to 25% of head feed

    C

    Pebbles and Coarser

    Particle (+) 6 mm to (-) 50

    mm

    0% 5% Allowance only

    D Boulders (+) 50 mm 0% 0% Allowance only

    E Rejected Clay 5% 25% This assumes 5-25% slimes however actual rejected

    clay depends upon sale of clay product

    F Any other (HMC) 2% 10%

    This assumes 2-10% HMC within the head feed.

    Actual reject depends upon saleability of HMC

    product.

  • 29

    Proposed Sand Beneficiation Process Diagram

  • 30

    LPG SYSTEM START-UP TO FURNACE

    This procedure will describe the entire startup process of the LPG system from the tanks to

    the peak shaving station.

    Under normal operating conditions the LPG system should have 80-90 Degree C water

    running through the vaporizers.

    1. Recirculation System:

    a. Start circulating water:

    i. Verify all valves are open to circulate water through the boiler and

    vaporizer

    ii. Ensure the water system has a pressure of 1-1.5 bar

    iii. Start the recirculation pump for the desired vaporizer and hot water

    generator (Note: valves have been provided to allow either hot water

    generator to feed either vaporizer)

    iv. Pump inlet pressure should be 1 – 1.5 bar and outlet should be 3.0 – 4.0 bar

    depending on water temperature

  • 31

    i. Verify the vapor pressure before the second stage regulator is 2.5 bar.

    ii. Open safety shut-off valve on second stage regulator by opening the

    bypass valve while at the same time, pull down on the bottom handle.

    iii. Verify the pressure after the second stage regulator is 300 mbar

    iv. Check that the final regulated pressure is 50-60 mbar when burner is

    working.

    c. Hot Water Generator Startup

    i. Verify control voltage to the boiler control panel from the 220V panel next to the

    AES control panel is on.

    ii. On the boiler control panel, Turn “Burner Control” switch to “on” and turn

    “Circulation” switch to “on”.

    iii. Check the Burner start-up sequence (ref. figure 3)

  • 32

    Note: If there is a burner fault (light F) reset by pressing button 2, if the fault reappears,

    contact Engineering.

    2. LPG Supply (ref. figure 4):

    a. Verify that the tank valves are open. (They are normally all open)

    b. Verify that the System pressure is above 4.8 bar at the liquid transfer pumps.

    c. Verify that inlet and outlet valves of the pump(s) are open.

    d. If system pressure is below 4.8 bar you will need to start one of the pumps.

    e. The Liquid Return line going from the transfer pump to the tank(s) where LPG is

    being consumed from should be open while the transfer pump is running

  • 33

    3. Vaporizers (ref. Figure 5.):

    a. Confirm that the vaporizer that will be used is hot. The water inlet temperature

    should be above 65oC. (Note: if water inlet temp is cold, the LPG liquid level will rise

    in the vaporizer. If the LPG liquid level reaches the liquid carry over sensor or if the

    vapor out temp is below 10oC, the solenoid valve allowing liquid LPG into the

    vaporizer will close)

    b. Power on the vaporizer from the vaporizer control panel.

    c. The LPG liquid inlet valve should be closed

    d. Open the vaporizer vapor discharge valve.

    e. Open the LPG inlet pneumatic valve by pressing “inlet valve open/close” on the

    Vaporizer control panel.

    f. Open LPG liquid inlet ball valve slowly allowing LPG to the vaporizer.

  • 34

    4. Mixer/Blender (ref. figure 6.):

    a. Ensure that the manual valves at the discharge of the mixer are closed

    b. Open the inlet ball valves on the LP vapor and compressed air lines

    c. Turn on the power at the control panel.

    d. Open the inlet ball valves by pressing “Inlet valve open/close”.

    e. Check the inlet pressure gauges. They should read around 6.2 bar on the

    compressed air and 5.0 bar or greater on the LPG vapor.

    f. If the pressure difference in less than 1.4 bar, then open the regulators by pressing

    “POM start/stop”. [If not, check plant compressed air and/or start the liquid transfer

    pumps (tank to vaporizer) if needed.]

    g. Start the flare unit (this will allow the system to stabilize). The flare can be shut

    down once LPG is flowing to the furnace.

    h. Verify that the outlet pressure at the mixer is as follows:

    i. When flowing LPG: 3.5 bar

    ii. When outlet valves are closed: 4.0 bar

    iii. Alarm pressure: 4.3 bar

    Note: At this point, the PLC will energize the loading solenoid valve for a period of time,

    overriding any alarm conditions. If all alarm conditions clear during this time, the mixer will

    continue to operate. If any alarm conditions remain, the mixer will shut down. These alarm

    conditions must be cleared before the mixer will start and remain in operation.

  • 35

    PROPANE GAS TO THE FURNACE (ref. figure 8):

    1. After completing steps 1 – 5, communicate with the furnace to ensure the supply

    pressure at the furnace is 3.5 bar and the incoming LPG valve is closed.

    2. SLOWLY open the outlet valve to the furnace at the mixer.

    3. Verify the peak shaving valve is closed and then open the isolation valve after the peak

    shaving valve.

    4. Using the peak shaving valve, slowly open the flow to the furnace and confirm that the

    blended LPG vapor is flowing.

    5. Once flow is confirmed, slowly close the natural gas valve feeding the furnace

  • 36

    NATURAL GAS TO THE FURNACE:

    1. SLOWLY close the peak shaving valve on the LPG supply line as you slowly open the

    natural gas supply valve.

    2. You should now be able to hear the natural gas flowing to the furnace.

    3. Leave the outlet valve at the mixer to the furnace open, and start the flare to bleed the

    excess pressure from the supply line to the furnace.

    LPG SYSTEM SHUTDOWN:

    1. Vaporizers:

    a. Shut off the liquid transfer pump (if running), this can either be done locally or from the

    AES panel.

    b. Close the vaporizer inlet valve, allowing the propane gas in the system to evacuate and

    burn off using the flare

    2. Mixer/Blender

    a. Close mixer air and propane valves.

    b. Close the solenoid supply to the regulators.

    c. Close the flare valve at the outlet of the mixers.

    3. LPG Storage Tanks:

    a. Verify transfer pumps are off.

    b. Close pump outlet valve only, leave the inlet valve open.

    4. Flare stack:

    a. Close the flare stack pilot valve and main line valve.

    b. Swing the rain cap over the top of the flaring stack for weather protection.

  • 37

    EMERGENCY SHUT-DOWN SWITCHES (ESD) AND REMOTE OPERATED VALVES (ROV’s)

    There are six (6) emergency shut-down pushbuttons located within the LPG area as follows:

    a. Unloading shed #1

    b. Unloading shed #2

    c. Transfer pump shed

    d. Hot Water Generator and Vaporizer shed (near overhead door)

    e. Hot Water Generator and Vaporizer shed (west end)

    f. Blender room

    These buttons maintain a constant air supply to the ROV’s at the LPG supply tanks to keep

    them open. During an emergency, any of these buttons can be pressed to stop ALL flow out

    of the LPG tanks.

    When any of these six buttons are pressed, it will trigger a relay in the main control panel.

    The relay will release the compressed air out of the remote operated valves on the tanks.

    There is also a manual 3 way valve on the compressed air supply in the hot water generator

    and vaporizer shed that will stop the incoming supply of compressed air and dump the air

    out of the line supplying the ROV’s. This will also cause the valves on the bottom of the

    tanks to close.

    Pull out the ESD pushbutton to reset the alarm and apply pressure back to the excess flow

    valves.

  • 38

    ROV CONTROL PANEL (Figure 11)

    Outside the South gate of the LPG yard there is a panel that allows you to control each ROV

    Independently. This can be used if you want to utilize LPG from a specific tank. It also

    receives signals from the high level sensors on the tanks (set at 85%). If one of the sensors is

    tripped an alarm will be triggered at this station.

  • 39

  • 40

    LPG UNLOADING PROCEDURE

    This procedure will describe the unloading procedure using the new Alternate Energy

    Systems (AES) equipment.

    1. Pre-Unloading Checklist:

    a. Prior to unloading the technician responsible should check the level of the tanks

    by using the Roto-Gauge on the front (see figure 1)

    b. Verify that there is enough room in the LPG tanks to unload the LPG (an LPG truck

    in India will have around 18 tons of LPG). Note: Each tank has a 60 ton LPG capacity,

    but they should not be filled up beyond the 85% mark (51 tons), if a tank is filled

    beyond this point the high level alarms will trip.

    c. For maximum unloading efficiency the LPG should be unloaded into two or more

    tanks simultaneously (this is because the LPG liquid in lines at the top of the tanks is

    2” and the liquid line feeding them from the unloading stations is 3”)

    d. Once the tanks have been determined the liquid inlet and vapor inlet valves at the

    top of these tanks should be opened (see figure 2).

    e. Prior to connecting the liquid and vapor hoses to the tanker all valves in the

    unloading shed should be closed.

  • 41

    2. Unloading LPG

    a. It takes approximately 4 hours to fully unload an LPG tanker, ensure that the

    proper personnel will be available to witness the entire unloading.

    b. The first tanker should always pull up to the South unloading station, this will

    allow the second tanker to pull in behind the first and unload at the North unloading

    station (if required)

    c. When the truck is in position the grounding lead on the unloading shed should be

    connected to the frame of the truck

    d. Connect the liquid and vapor unloading hoses to the truck.

    e. Verify all the valves in the unloading shed are closed and SLOWLY open the valves

    on the tanker. Check for leaks.

    f. Once no leaks have been observed, slowly open the vent line on the liquid line to

    purge the air from the line. Liquid will begin to flow through the check valve on the

    unloading skid. When the liquid fills 50% of the check valve (this can be witnessed

    through the sight glass) close the vent line.

    g. Open the inlet and outlet valves on the liquid transfer pump (figure 3)

    h. SLOWLY open the globe valve on the unloading skid. As it is opened LPG will begin

    flowing from the truck to the tanks based on the pressure differential.

    Typically the tanks will be around 6 bar and the truck will be around 7 bar when

    unloading begins.

  • 42

    i. When the pressure in the truck lowers and gets closer to the pressure in the tanks

    the flow will slow down. At this point the liquid transfer pump can be turned on.

    j. Eventually the pump will begin to vibrate because the pressure in the truck is not

    high enough. At this time the transfer pump should be shut off, and the compressor

    should be turned utilized.

    k. BEFORE TURNING ON THE COMPRESSOR slowly open the ALL the valves on the

    vapor line in the unloading shed and the skid (including the compressor bypass

    valve). The pressure between the tanker and the tanks having LPG unloaded to them

    will equalize. The 4-way valve should be pointing to the LEFT in order to pressurize

    the tanker by pulling vapor from the LPG tanks.

    l. Verify all the valves are open, if a valve is closed on the discharge side of the

    compressor the pressure will quickly rise, causing a very unsafe condition.

    m. Turn on the compressor, the pressure gauges for the suction and return lines on

    the compressor should be equal because the bypass valve is open. Very SLOWLY

    close the bypass valve while monitoring the discharge pressure. The pressure should

    rise slightly and LPG liquid will once again begin flowing to the tanks. Note: the

    discharge pipe going from the compressor to the tanker will heat up due to the

    compressed gases; this is normal and can be used as a verification the flow is in the

    correct direction.

    n. Monitor the pressure on the tanker, it should not go above 8 bar, if it does shut off

    the compressor until it drops below 7.5 bar and start again. If time is a concern the

    transfer pump can also be turned on again to maximize the flow to the tanks (if the

    transfer pump begins to vibrate again turn off the pump and continue unloading

    with the compressor)

  • 43

    o. If there is too much flow coming from the truck tanker, the excess flow valve on

    the truck will trip and flow will be reduced or cut off completely. If this happens, shut

    the valve on the truck (you will hear the excess flow valve reset when flow is

    stopped) and slowly open it again.

    p. Throughout the process the LPG level on the truck and the tanks being unloaded

    to should be checked and recorded.

    q. When the Roto-Gauge on the truck shows less than 3% only the unloading

    compressor should be used (while making sure the truck tanker does not exceed 8

    bar pressure.

    r. As the last amounts of liquid leave the truck the check valve will begin to shut and

    LPG will cease to flow. When this happens the compressor should be turned off and

    all the valves on the liquid line should be shut and the remaining LPG in the

    unloading hose should be SLOWLY vented until all pressure is gone. At this point the

    hose can be removed from the truck.

    3. Depressurizing the truck

    a. SLOWLY open the vapor bypass line around the compressor. This will cause the

    pressure in the truck to equalize with the LPG tanks in the yard.

    b. When the pressure difference drops to the point where vapor is no longer flowing

    on its own the 4-way valve on the compressor should be rotated so that the handle

    is pointed UP. In this configuration the compressor will pull vapor from the truck and

    load it back into the tanks.

  • 44

    c. BEFORE TURNING ON THE COMPRESSOR verify ALL the valves on the vapor line in

    the unloading shed and the skid are open (including the compressor bypass valve).

    d. Turn on the compressor and verify the pressure on the suction and discharge are

    correct.

    e. Continue to run the compressor until the pressure on the tanker is around 2.5 bar.

    f. Turn the compressor OFF

    g. Close all the valves on the vapor line and the outlet of the truck.

    h. Depressurize the hose using the vent on the skid by SLOWLY opening the valves.

    i. The vapor hose can now be removed from the truck.

    j. Close the valves on top of the LPG tanks

    k. Close the gates to the LPG yard

    l. Unloading Complete

  • 45

    ANNEXURE-IV

    TREATMENT PROCESS

    DETAILS OF STP

    Process Description of Sewage Treatment Plant

    The Domestic waste water (Sewage) from the service/amenity blocks of plant flows through

    gravity towards a dedicated Sewage Treatment Plant provided within the GGL Ankleshwar

    Premise.

    As per the original design, sewage/domestic waste water through gravity flows into the 1st

    Unit of STP provided viz. the equalization tank through hand racked bar screens. The sewage

    in the Equalization tanks is kept well mixed with the help of air supply through 2 blowers (1

    working 1 standby) The Equalized sewage is pumped to the Aeration Tank by means of 1

    Nos. submersible pump.

    The Aeration Tank is designed for Extended Aeration for considerable reduction of organic

    matter. To maintain the MLSS in Aeration Tank and for continuous oxygen supply to

    maintain the DO levels, surface Aerator provided in the Aeration Tank is kept in continuous

    operation also we have provided back up air supply line from blowers which are used for

    supply air in equalisation tank. The overflow from the Aeration tank is taken to the Clarifier.

    In the Clarifier, the particulate as well as colloids and suspended solids are allowed to settle

    down by gravity. For better settlement, we have provided flocculent dosing in secondary

    clarification process. The supernatant thus formed is taken to filter feed tank by gravity,

    where we have provided filtration process by passing the water through Pressure sand filter

    and Activated charcoal filter an finally collected into treated water tank cum chlorine

    contact tank.

    To kill the pathogenic bacteria we are using sodium Hypochloride chemical, doing is through

    the automated dosing pump which dose the quantity based on the PPM level of water in

    treated water tank to maintain the minimum 0.5 PPM all the time before pump it to reuse

    for gardening by means of a piping network. The partial sludge from the Clarifier is recycled

    back to Aeration Tank, which accelerates the aerobic digestion of sewage. As and when

    required, part of sludge is wasted to sludge drying beds. The filtrate from the Sludge Drying

    Beds is returned back to the bar screen chamber by gravity and the solar dried sludge is

    used as manure for gardening purpose.

    Adequacy Statement of Existing STP Units is suitable to 90 KLD Hydraulic Load and

    Characterization

    Sr. No. Parameters GPCB Limit for Sewage Outlet water

    1 BOD < 20

    2 SS < 30

    3 Residual Chlorine � 0.5

  • 46

    DISPOSAL MODE OF SEWAGE

    The domestic waste water after treatment in STP is used for irrigating the green belt area

    within the plant Premise. Consolidated Consent and Authorization Order No. AWH-62530 of

    GPCB valid up to 27-01-2019, stating the parameters for disposal of treated domestic waste

    water for gardening.

    Details of Existing Sewage Treatment Plant

    Description of Units and sizing of Existing Sewage Treatment Plant are enlisted in Table

    Sr. No. Name of the Unit Size Capacity/Volume No. of Units

    1 Screen Chamber 3.3 x 2.5 x 3.5 m SWD 28.9 m3 1

    2 Equalization Tank 4.0 x 3.5 x 3.5 m SWD 49 m3 1

    3 Aeration Tank 6.0 x 5.0 x 3.0 m SWD 90 m3 1

    4 Secondary Clarifier 4.0 m Diameter x 1.5

    m SWD 19 m3 1

    4 Chlorine Contact

    Tank 4.0 x 2.0 x 5.0 m SWD 40 m3 1

    5 Sludge Drying Beds

    3.0 x 2.0 m with 1.5 m

    Sludge Application

    Depth

    Area = 6 m2 x 6

    Nos. = 36 m2 6 Nos.

    6 MCC Panel/Return

    Sludge Pump House ---- ---- 1

    7 Flocculation dosing

    tank Capacity 500 litres Capacity 500 litres 1

    8 PSF 5 m3/Hr capacity 5 m3/Hr capacity 1

    9 ACF 5 m3/Hr capacity 5 m3/Hr capacity 1

    Description of Existing Sewage Treatment Plant Units with Suggestive Modifications

    1. Inlet Collection Sump and Screen Chamber: (1 No.)

    The prime purpose of providing the Inlet Collection sump cum Screen Chamber is that the

    sewage through gravity from the entire plant Premise is conveyed to this unit. MSEP Fine

    Screens of 50 mm spacing are provided to arrest any large floating matter, settle-able solids,

    rags, plastics etc. Fine bar screens shall be manually cleaned periodically.

    Dimensions of Existing Inlet Collection Sump cum Screen Chamber are 3.3 x 2.5 x 3.5 m SWD

    (Side Water Depth) with a retention time of 12.8 hours at an existing flow of 54 KLD.

    2. Equalization Tank: (1 No.)

    The main objective of providing an Equalization Tank is to store and homogenize the sewage

    waste water in this unit so as to have constant load onto the further treatment units.

    Dimensions of Equalization tank are 4.0 x 3.5 x 3.5 m SWD (Side Water Depth) with a

    retention time of 21.7 hours at an existing flow of 54 KLD.

  • 47

    After equalization, sewage will be pumped into the Aeration Tank through pumps manually.

    This is important to prevent back flow of sewage into the Screen Chamber cum Inlet

    Collection sump.

    3. Aeration tank: (1 No.)

    Extended Aeration is adopted as the biological treatment wherein micro organisms are

    introduced in waste water which has the capacity to stabilize the organic matter present in

    sewage and in turn results in reduction of BOD load. Aeration is provided so that the waste

    water is brought in contact with oxygen which serves as energy for the micro organisms for

    aerobic decomposition. Aeration tank is provided with surface aerator for providing

    required amount of dissolved oxygen for microbial activity. MLSS (Mixed Liquor Suspended

    Solids) shall be maintained in the Existing Aeration tank at retention time of 24 hours has

    been provided. Treated sewage from aeration tank will be discharged under gravity into the

    Secondary Clarifier. Dimensions of Existing Aeration tank are 6.0 x 5.0 x 3.0 m SWD (Side

    Water Depth) with a retention time of 40 hours at an existing flow of 54 KLD.

    4. Secondary Clarifier: (1 No.)

    The biological sludge generated in Aeration tank will be allowed to settle in Secondary

    Clarifier. Secondary Settling for circulation of clarified biomass is essential to maintain

    required MLSS concentrations in Aeration Tank. The return sludge from the bottom of the

    Secondary Clarifier will be withdrawn and re-circulated back to Aeration tank for

    maintaining required MLSS concentration by means of sludge recirculation pumps and

    partly wasted to Sludge Drying Beds. Effluent from Aeration tank is received into central

    well of secondary clarifier from where it is allowed to move down and subsequently moved

    up with very slow velocity. In the process of downward and upward movement MLSS is

    settled down and clear supernatant effluent is obtained at the outlet of the clarifier; the

    basic purpose of the secondary clarifier is to separate solids from liquids by the process of

    gravity sedimentation. The clarifier is of conventional type having central shaft for

    scrapping, from where the clarified effluent is transferred to Chlorine Contact Tank.

    Dimensions of Existing Secondary Clarifier are 4.0 m Diameter x 1.5 m SWD (Side Water

    Depth) with a retention time of 8.37 hours at an existing flow of 54 KLD.

    5. Flocculent Chemical dosing tank: (1No)

    The Flocculent Chemical dosing attached to secondary clarifier is used to help better

    settlement of solids and to prevent any solids into the pressure sand filter and activated

    charcoal filter system for better operation, less maintenance and better efficiency with

    better treated waste water quality parameters complying with CCA conditions.

    6. Sodium Hypochlorite mixing and treated water tank: (1 No.)

    The clarified sewage from Secondary Clarifier shall be pumped to the Chlorine Contact Tank

    cum final treated water storage tank. The clarified sewage will be dossed with sodium

    Hypochloride solution for disinfection and killing of pathogenic bacteria and viruses.

    Chlorine dosing is controlled such that the resulting treated waste water has residual

    chlorine of 0.5 mg / lit. The treated waste water is being further pumped and re-used for

    irrigating the green-belt area with GGL Ankleshwar Plant Premise.

  • 48

    Dimensions of Existing Chlorine Contact Tank are 4.0 x 2.0 x 5.0 m SWD (Side Water Depth)

    with a retention time of 17.7 hours at an existing flow of 54 KLD.

    The treated waste water from the outlet of Chlorine contact tank is stored in a Final

    Collection sump within the plant Premise.

    7. Sludge Drying Beds: (6 Nos.)

    The biological sludge formed in the Secondary Settling tank shall be discharged directly to

    sludge drying beds. The resulting sludge shall be solar dried in the sludge drying beds. Six

    Nos. of sludge drying beds are provided of dimensions 3.0 x 2.0 m and sludge application

    depth of 0.3 m. The sludge drying bed will be divided into compartments to facilitate in easy

    sludge drying handling and disposal. The dried sludge is being currently used as a fertilizer or

    manure within the existing green belt area at GGL Plant Premise.

    Contingency plan for incidents possibly encountered in sewage treatment plant

    � CONTENTS

    1) Introduction

    2) Objective

    3) Activation of contingency plan

    4) Emergency action

    5) Deactivation of contingency plan.

    � Introduction

    The contingency plan is to provide guidelines for all employee of plant in dealing with

    different incidents, which have potential of environmental nuisance

    � Objectives

    The contingency plan has following objectives.

    1) To avoid and, if not possible, to minimize environmental impact to the surroundings.

    2) To seek assistance from relevant work agents for emergency handling.

    3) To minimize damages to affected plant.

    4) To ensure emergency procedure required is organized & implemented in an orderly

    manner.

    � Activation Of contingency plan

    Types of incidents, which is considered to vulnerable to giving rise to possible

    environmental nuisance, are given below.

    a) Power failure

    Mains failure leading to total blackout in a part or whole of STP plant area; interruption

    of power supply due to failure of switchgear & operator malpractice.

    b) Fire breakout

    Setting furniture & equipment on fire through negligence, overheating of equipment &

    improper handling of inflammable materials.

    c) Abnormal effluent

    Abnormal swage to plant, which directly affect normal operation of process.

    d) Swage overflow

  • 49

    Excessive flow particularly in rainy season burst of pipes, treatment failure due to

    inadequate standby equipment

    e) Non-compliance with discharge standard.

    Plant overloaded in terms of quantity or quality. Illegal discharge of toxic waste.

    � Emergency action

    Action to be taken, where appropriate, are shown below

    o To detect sign of abnormality

    o To investigate & assess environmental impact

    o Wherever required arrange emergency equipment

    o To consider various actions to implement measures to mitigate

    environmental impact & restore plant to normal operation.

    o To plan corrective action & preventive action to improve plant reliability

    � Deactivation of contingency plan

    Contingency plan will be deactivated when the concerned plant is brought back to

    normal working condition & potential of generating environmental nuisance is

    eliminated.

  • 50

    FLOW DIAGRAM

  • 51

    EXPECTED CHARACTERISTIC OF EFFLUENT

  • 52

    ANNEXURE-V

    HAZARDOUS WASTE GENERATION AND DISPOSAL

    S. No. Items Category Existing Additional Total Treatment and Disposal

    Method

    1 Used Oil 5.1 25

    KL/Year

    - 25

    KL/Year

    Collection, Storage,

    Transportation & Sending to

    Registered Refiners for recycle

    / reuse

    2 Chemical Sludge

    from Wastewater

    Treatment

    35.3 5

    MT/Year

    - 5

    MT/Year

    Collection, Storage,

    Transportation & Disposal by

    landfill at authorized TSDF

    3 Waste residue

    containing oil

    5.2 20

    MT/Year

    - 20

    MT/Year

    Collection, Storage,

    Transportation & Sent to GPCB

    registered TSDF for land Filling

    or Incineration

    4 Process wastes,

    residues & debris

    from production

    and/or industrial use

    of paints, pigments,

    lacquers, varnishes,

    plastics and inks

    21.1 20

    MT/Year

    - 20

    MT/Year

    Collection, Storage,

    Transportation & Sent to

    licensed disposal company

    Recycle as a fuel or

    Incineration

    5 Spent solvents from

    the production

    and/or industrial use

    of solvents

    20.2 5

    MT/Year

    - 5

    MT/Year

    Collection, Storage,

    Transportation & Sent to

    licensed disposal company

    Recycle as a fuel or

    Incineration

    7 Discarded Containers

    & barrels

    contaminated with

    hazardous

    wastes/chemicals

    33.3

    240

    MT/Year

    - 240

    MT/Year

    Collection, Storage,

    Transportation & Disposal by

    selling to Registered Vendors

    8 Furnace/reactor

    residue and debris

    from pyrolytic

    operations

    D1 60

    MT/Year

    - 60

    MT/Year

    Collection, Storage,

    Transportation & Disposal by

    landfill at authorized TSDF

    9 Inorganic Tin

    compounds

    B 7 1

    MT/Year

    - 1

    MT/Year

    Collection, Storage,

    Transportation & Sent to

    licensed disposal company for

    Recycling

    10 Spent catalyst and

    molecular sieves

    1.7 4

    MT/Year

    - 4

    MT/Year

    Collection, Storage,

    Transportation & Sent to

    licensed disposal company for

    Recycling

    11 Spent ion exchange

    resin containing toxic

    metal

    34.2 15

    MT/Year

    - 15

    MT/Year

    Collection, Storage,

    Transportation & Disposal by

    landfill at authorized TSDF

  • 53

    Solid (Non-Hazardous) Wastes:

    S.No Waste Type Permitted Additional Total Disposal Method

    1. Mirror Cullet 100

    MT/Month

    0 100

    MT/Month

    Collection, Storage,

    Transportation & Sold as non-

    hazardous waste for recycling

    / reuse

    2. Bad Batch, Gcore, other NH

    organic chemicals

    100

    MT/Month

    0 100

    MT/Month

    Collection, Storage,

    Transportation &

    Recycling/Reuse/Landfill

    3. G-Core 100

    Kg/Month

    0 100

    Kg/Month

    Collection, Storage,

    Transportation & Reuse in-

    house for water

    neutralization

    4. Waste sand 9200

    MT/Month

    5800

    MT/Month 15000

    MT/Month

    Collection, Storage,

    Transportation & Recycling in

    house / Landfill & Recycled in

    house

    5. Cullet 2500

    MT/Month

    0 2500

    MT/Month

    Collection, Storage,

    Transportation & Recycling

    in house / Landfill

    6. Sludge Generation from STP 1

    MT/Month

    0 1

    MT/Month

    Collection, Storage, Transportation &

    Using as manure in-house

    7. Furnace refractory waste,

    Kwool, Mud, Cement etc.

    10 MT/

    Year

    0 10 MT/

    Year

    Collection, Storage, Transportation &

    Sent for Construction earth-

    filling

    8. Cullet Dust 40

    MT/Month

    0 40

    MT/Month

    Collection, Storage, Transportation &

    Sold To GPCB approved

    recycler

    9. E-waste 250

    Kg / Month

    0 250

    Kg /

    Month

    Collection, Storage, Transportation &

    Sold to scrap vendor

    10. Trash and Packaging

    material waste

    20

    MT/Month

    0 20

    MT/Month

    Collection, Storage, Transportation &

    Sold to scrap vendor

    11. Metal Scrap 10

    MT/Month

    15

    MT/Month 25

    MT/Month

    Collection, Storage, Transportation &

    Sold as non-hazardous waste

    for recycling / reuse (increase

    in scrape would be because

    of demolish of existing sand

    beneficiation plant)

  • 54

    ANNEXURE-VI

    _______________________________________________________________________

    WATER, FUEL & ENERGY REQUIREMENT

    WATER CONSUMPTION AND WASTEWATER GENERATION: NO CHANGE

    Water Consumption Waste Water Generation Sr.

    No.

    Section

    (KL/day)

    Existing Proposed Existing Proposed

    1. Domestic 350 350 205* 205*

    2. Process 25 25 0 0

    3. Boiler NA NA NA NA

    4. Cooling & Chilling 400 400 150** 150**

    5. Washing 775 775 566** 566**

    6. Gardening 100 100 0 0

    Total 1650 1650 921 921

    * 205 m3/day of domestic wastewater is treated in STP and then reused for land

    irrigation/gardening.

    ** 716 (i.e. 150 + 566) m3/day is recycled back to Sand Plant for Sand Washing.

  • 55

    WATER BALANCE DIAGRAM (TOTAL PROPOSED)

    Domestic

    350

    Washing

    775

    Water Consumption

    1650

    Domestic

    205

    Cooling &

    Chilling

    400

    Wastewater

    716

    Washing

    566

    Cooling

    150

    716

    Reused back in Sand Plant for

    Sand Washing and irrigation –

    Process

    25

    Gardening

    100

    All Figures in KL/Day

    STP and Septic Tank

    205

    Reused for Land

    Irrigation/Gardening

  • 56

    TOTAL POWER REQUIREMENT & SOURCE OF POWER

    Power requirement is 6.5 MW which is taken from GEB in addition 4 Nos. of (155 KVA each)

    & 3 Nos. of (2.5 MW, 2.5 MW & 500 KVA) DG Sets will be kept for emergency power back

    up. We also have 34 wind mills installed at Dwarka (Gujarat).

    FUEL REQUIREMENT

    Quantity S.No Fuel

    Existing Additional Total Proposed

    1 Natural Gas 6600 m3/hr - 6600 m

    3/hr

    2 LPG 4 MT/hr* - 4 MT/hr*

    3 Diesel 1515 Ltrs /Hr 60 Ltrs/Hr 1575 Ltrs /Hr

  • 57

    ANNEXURE-VII

    STORAGE DETAILS OF HAZARDOUS CHEMICALS

    Existing:

    Sr.

    No.

    Name of the

    Material

    Type of

    Hazard

    Kind of

    Storage

    Max.

    quantity to

    be stored

    (MT)

    Storage

    condition

    i.e. temp.

    pressure

    Tank Dimensions Dyke

    Dimensions

    1 Ammonia Corrosive,

    Toxic

    Bullets 20 4 to 7.5 Kg/cm2 Length: 6.546 m

    Dia: 2 m

    32' x 32' x 1'

    2 LPG Storage Flammable Bullets 56.25 x 4 =

    225

    5 to 8.5 Kg/Cm2 Dia: 3200 mm

    Length: 16.126 m

    MOC: SA-515/SA

    35 x 11.2 m

    3 H2SO4

    Storage

    Corrosive Tank 4 KL Atmospheric

    Pressure

    Dia: 1.15 m

    Length: 2.85 m

    7 x 4.5 x 0.2 m

    4 Diesel

    Storage

    Flammable Tanks 145 KL 0.344 Kg/cm2 @

    200C

    Ht: 4.2 m

    Dia: 5.6 m

    16.7 x 10.1 x 1 m

    5 MTO &

    Xylene

    Flammable Barrels 30 KL Atmospheric

    Pressure

    Room Size:

    7.7 x 9 x 7 m

    7.7 x 9 x 0.5 m

    Proposed:

    Sr.

    No.

    Name of the

    Material

    Type of

    Hazard

    Kind of

    Storage

    Max.

    quantity to

    be stored

    (MT)

    Storage

    condition

    i.e. temp.

    pressure

    Tank Dimensions Dyke

    Dimensions

    1 Ammonia Corrosive,

    Toxic

    Bullets 20 4 to 7.5 Kg/cm2 Length: 6.546 m

    Dia: 2 m

    32' x 32' x 1'

    2 LPG Storage Flammable Bullets 120 x 6 =

    720

    21 Kg/Cm2 Dia: 4010 mm

    Length: 24 m

    35 x 11.2 m

    3 H2SO4

    Storage

    Corrosive Tank 4 KL Atmospheric

    Pressure

    Dia: 1.15 m

    Length: 2.85 m

    7 x 4.5 x 0.2 m

    4 Diesel

    Storage

    Flammable Tanks 145 KL 0.344 Kg/cm2 @

    200C

    Ht: 4.2 m

    Dia: 5.6 m

    16.7 x 10.1 x 1 m

    5 MTO &

    Xylene

    Flammable Barrels 30 KL Atmospheric

    Pressure

    Room Size:

    7.7 x 9 x 7 m

    7.7 x 9 x 0.5 m

  • 58

    ANNEXURE-VIII

    _______________________________________________________________________

    DETAILS OF STACKS & VENTS

    There is no addition or changes in the Flue Gas Stacks & Process Vents

    Flue Gas Stacks

    Sr.

    No.

    Stack Attached

    To

    No. of

    Stacks

    Height From

    Ground (m)

    Fuel Used Air Pollution

    Control System

    Expected

    Pollutants

    1. Melting Furnace 1 91 Natural Gas,

    LPG

    Low NOx Burner,

    Stack height

    PM,TF

    2. DG Set

    (2.5 MW)

    1 30 Diesel - PM, NOx,

    NMHC, CO

    3. DG Set

    (2.5 MW)

    1 30 Diesel - PM, NOx,

    NMHC, CO

    4. DG Set

    (500 KVA)

    1 14 Diesel - PM, NOx,

    NMHC, CO

    5. LPG Hot water

    generator

    exhaust

    1 12 LPG - PM, SO2, NOx

    6. Diesel Engine 1

    (155 KVA)

    1 12 Diesel - PM, NOx, CO

    7. Diesel engine 2

    (155 KVA)

    1 12 Diesel - PM, NOx, CO

    8. Diesel engine 3

    (155 KVA)

    1 11 Diesel - PM, NOx, CO

    9. Diesel engine 4

    (155 KVA)

    1 11 Diesel - PM, NOx, CO

    10. Glass Edge

    Burner

    1 16 Natural Gas,

    LPG

    - PM, SO2, NOx

  • 59

    Process Vents

    S.

    No.

    Stack attached to No. of

    Stacks

    Stack

    height (m)

    Pollutant

    Emitted

    Air Pollution Control

    Measures Attached

    1. Main Melting Furnace 1 91 PM, TF Stack

    2. Ammonia Cracking Plant 1 21 PM,

    Ammonia

    Stack, Nitrogen

    Purging

    3. Mirror Line Plant 7 12 VOC,

    Ammonia

    Stack

    4. SO2 Vent 2 17 SO2 Stack

    5. Batch House Raw

    Materials DCF Vents

    9 36.5 PM Dust Collector

    6. Batch House Raw

    Materials DCF Vents at

    Basement

    2 5.5 PM Dust Collector

    7. Batch House Unloading

    DCF Vent

    1 6 PM Dust Collector

    8. Cullet Return System DCF

    Vent

    1 3 PM Dust Collector

    9. Hot Air Exhaust 5 16 PM Not Required

  • 60

    ANNEXURE-IX

    _______________________________________________________________________

    EXPECTED NOISE LEVEL AT DIFFERENT SOURCE WITHIN PREMISES

    Various sources of noise in industry have been identified as under,

    • Pumps

    • Blowers

    • Rod Mill

    The typical noise levels of equipments, as indicated by the equipments manufacturers are

    given below:

    Sr. No. Name of Machinery / Units Noise level, dB(A)

    1 Pumps 60 – 65

    2 Blowers 80 – 85

    3 Rod Mill 85 – 95

    EXPECTED NOISE LEVELS:

    SR.

    NO.

    SOURCE OF NOISE PERMISSIBLE LIMIT

    (DAY/NIGHT)

    dB (A)

    EXPECTED NOISE

    LEVEL dB (A)

    1. Near Security Gate 75/70 60

    2. Near Administration Building 75/70 60

    3. Near Cooling tower & Utility Block 75/70 65

    4. Near DM Plant 75/70 65

    5. Near Process Plant 75/70 65

    6. Near Canteen 75/70 50

    • Ear muffs & ear plugs are provided to operators where ever noise level is higher than

    85 dB(A) inside the plant.

    • Regular preventive maintenance of equipments is carried out.

  • 61

    ANNEXURE-X

    _______________________________________________________________________

    SOCIO - ECONOMIC IMPACTS

    1) EMPLOYMENT OPPORTUNITIES

    During construction phase, skilled and unskilled manpower will be needed. This will

    tempo


Recommended