Proposition MM Implementation
Update
Report to the Board of Education
by Lou Smith, Chief Operating Officer
Facilities ManagementSan Diego City Schools
November 12, 2002
2
($’s in millions)
328.00
265.00
$0
$200
$400
$600
$800
$1,000
$1,200
$1,400
$1,600
MAJOR REPAIR AND REPLACEMENT
NEW SCHOOL CONSTRUCTION
303.00
614.00
LAND
NEW CONSTRUCTION - EXISTING SCHOOLS
Prop. MM Funding Distribution
3
(cumulative actuals through 9/25/02)
Prop. MM Expenditures
New Construction - Existing Schools
Major Repair & Replacement
Land Acquisition
New School Construction
$0
$50,000,000
$100,000,000
$150,000,000
$200,000,000
$250,000,000
$300,000,000
$350,000,000
$400,000,000
New Construction - Existing Schools Major Repair & Replacement Land Acqusition New School Construction
4
Original and Current Prop. MM Plans
0
50
100
150
200
250
300
350
40019
98/1
999
1999
/200
0
2000
/200
1
2001
/200
2
2002
/200
3
2003
/200
4
2004
/200
5
2005
/200
6
2006
/200
7
2007
/200
8
SCHOOL YEAR
$ M
ILL
ION
S
Original Plan Actual Expenditures Current Plan
Original = 10/98 Current = 8/02
5
Cumulative Expenditure Plans
as of 9/25/02 ($’s in millions)
139.5
627.1
$0
$200
$400
$600
$800
$1,000
$1,200
$1,400
$1,600
98-99-00 00-01 01-02 02-03 03-04 04-05 05-06 06-07 07-08 08-09
Cu
mu
lati
ve
Ex
pen
dit
ure
s: P
lan
ned
an
d A
ctu
al
Cumulative Y/E Expenditures 98-99-00 Cumulative PlanCurrent Cumulative Plan Cumulative Expenditures to Date
311.8
365.3
6
What We Did in 2001
What We’re Doing Now
Where We’re Going in 2003
More than 58 sites had major repairs and upgrades
Working year-round on major repairs/upgrades at nearly 80 sites
Major repairs and upgrades begin at 60 more sites
More than $154M were awarded in construction contracts
Nearly $189M in construction contracts will be awarded by end of 2002
More than $212M will be awarded in construction contracts
More than $33M in trade-specific projects at 150 sites
932 trade-specific projects at 176 sites representing more than $37M
396 trade-specific projects at 132 sites representing nearly $18M
Prop. MM Progress
7
What We’re Doing Now
Program management costs at 6.8% (industry average is 8-10%)
Standardized costs and budgets for furniture and equipment nearly complete
New schools New facilities at existing schools
Acquiring land for new schools Brooklyn/Kimbrough area Cherokee Point Elementary School Herbert Ibarra Elementary School Scripps Ranch Middle School Lincoln High School (expansion & rebuilding)
Demolishing structures for new Cherokee Point Elementary School and new Brooklyn-Kimbrough area elementary school site
Planning physical consolidation of Facilities Management
8
Outreach
Approximately 97% of Proposition MM contracts went to San Diego firms
SBE and EBE outreach (as of June 2002) Approximately 41.6% of total
construction dollars went to EBE firms
Nearly 19.6% of total construction dollars went to DBE/WBE/DVBE firms
9
Process Improvements
Formalized monthly program management reporting cycle implemented September 2002
Facilities Assessment Contract Approved February 2002 Completed by February 2003
To date, the average change order rate is 4.35% for 2002 projects
Evaluating open contracts with service providers (fees and services)
10
Innovations
Teaming with the City and community groups San Diego Model School
Joint Powers Authority Memorandum of Understanding for Joint Use
Implementing design/build project delivery method Partnering with Division of State Architect
Dramatic increase in DSA approval time Peaked at 42 weeks in March/April 2002
Five Partnering sessions since February 2002 Marked decrease in approval time, 11 weeks in
August/September 2002 Lincoln-Gompers Redevelopment Committee
11
Accomplishments
Regional Golden Watchdog Award Efficient use of taxpayer dollars
American Planning Association Award First place for “Focused Issue Planning”
National press coverage American School & University Magazine
Fourth anniversary of Prop. MM Four new Prop. MM libraries opened
12
More than $365.3 million expended since the beginning of the program through September 2002
24.2% of Prop. MM funds Averaging $1 million a day in construction work-in-place
Completed FEIR for Edison/Hamilton/Parks Elementary School
Completed relocation plans Brooklyn/Kimbrough area elementary school Cherokee Point Elementary School Herbert Ibarra Elementary School
Total Program Cost Forecast Model Second quarterly forecast complete
What We’ve Done Since the Last Update
13
Program Costs
Third quarter 2002 Total Indicated Cost Model update nearly complete
Continued significant upward cost pressure on new school land and construction
14
T.I.C.–Forecast Summary (as of third
quarter 2002)
1.51
1.76
1.66 1.66
1.43
1.37 1.38
1.05
1.15
1.25
1.35
1.45
1.55
1.65
1.75
1.85
1.95
BIL
LIO
NS
($
)
Total Program Budget Reasonable High Forecast Reasonable Low Forecast
(Prelim)
(Prelim)
15
-80.0 -30.0 20.0 70.0 120.0 170.0 220.0
MILLIONS ($)
Site Discretionary FundsMajor Additions
Add'l Bldg SpaceWater to Elem Clrms
Replace PortablesLunch Court Shelters
New/Upgrade Sci ClrmsBuild/Expand Libraries
TechnologySingle Session Kinder
New SchoolsFuture MRR
Portable CertificationPlayground Equip
Climate ControlADA UpgradesBacklog MRR
Reasonable Low Forecast Reasonable High Forecast
UNDER BUDGET OVER BUDGET
Key: Arrow s reflect change from prior TIC. Up arrow = cost grow th
Preliminary
T.I.C.—Program Element Variances
16
T.I.C.—New-School Forecast Summary
0.51
0.712
0.6120.611
0.550
0.5000.500
0.25
0.35
0.45
0.55
0.65
0.75
0.85
BIL
LIO
NS
($
)
Total Program Budget Reasonable High Forecast Reasonable Low Forecast
(Prelim)
(Prelim)
17
New-School Costs--Original Program
Land acquisition $18 million(9 acres x $2M per acre)
Construction costs $10 million
Non-construction costs $2 million
Total $30 million
ORIGINAL COST ESTIMATES
18
Program Cost and Scope Pressures
Land acquisition Changes in ADA specifications Scope creep Construction costs
19
Escalating Land Costs
Year School $ Per Acre
1996 E.B. Scripps $.5 million
2001 Cherokee Point$2.5
million
2002(pending)
Adams/Franklin$3.7
million
20
New-School Cost Pressure
Options/alternatives Scope Cost Additional Resources
Cost management action plan District staff developing
options/alternatives Working with stakeholders and ICOC to
form possible scenarios Formulating a plan to present to ICOC and
Board of Education
21
Short-term Goals
Develop new school cost management action plan
Begin demolition for Herbert Ibarra Elementary School
Designate final new school Complete FEIRs and begin acquiring
land for seven new schools (eight w/Adams/Franklin which is going to the Board in December 2002)
22
Challenges New schools cost pressure Control “scope creep” to ensure completion of all program requirements Environmental requirements
Removal actions may be required at two sites Pre-acquisition Preliminary Endangerment Assessments needed at two sites Post-demolition PEA’s needed at a majority of sites
Occasional “unwilling sellers” requiring
eminent domain condemnation proceedings Continued funding of district’s
Major Repair & Replacement Program
23
Last Proposition MM School