Overall view of tower,

Need to be change every

month

Tower 1

TOWER

STATUS

• Door & Window work in

progress.

• Stilt floor column & shaft

plastering in progress.

• MEP work in progress.

• External painting work in

progress.

• Lift gladding work in

progress.

MILESTONES

ACHIEVED

• Door work started.

• External plaster 100%

completed.

UPCOMING

MILESTONES

• 1st coat painting will complete

116 flats.

• External paint 1st coat complete.

• Lift gladding 100%.

• Bison board & false ceiling 100%.

• Stilt 100% columns plaster.

• Terrace OTS covering 100%.

PROGRESS TIMELINE

Actual site photograph

Construction Updates

April 21 May 21 June 21

Tower 2

TOWER

STATUS

• External plastering in

progress.

• Tile work in progress.

• Water proofing in

progress.

MILESTONES

ACHIEVED

• External plaster completed 45%.

• Toilet waterproof 220 flats completed.

• Lift wall & Duct wall plaster

completed.

• Tile dado 80 flats completed.

• Floor tile 11 flats completed.

UPCOMING

MILESTONES

• External plaster 100% complete.

• Waterproofing 100% complete.

• Toilet dada up to 100 flats

complete.

• Floor tile work up to 40 flats

complete.

• 2nd coat putty 100% complete.PROGRESS TIMELINE

Actual site photograph

Construction Updates

April 21 May 21 June 21

Tower 3

TOWER

STATUS

• External plastering work

in progress.

• Putty work in progress.

• Tile work in progress.

• Stilt floor material

removing work in

progress.

MILESTONES

ACHIEVED

• External plaster 80% completed.

• Putty work 12 flats completed.

• Tile work 57 flats completed.

• External primer 60% completed.

UPCOMING

MILESTONES

• External plaster 100% complete.

• Putty work complete up to 5th floor.

• Tile work complete 60 flats.

• External primer 100% complete.

PROGRESS TIMELINE

Actual site photograph

Construction Updates

April 21 May 21 June 21

Tower 4

TOWER

STATUS

• Door fixing work in progress.

• Lift gladding work in

progress.

• Stilt floor columns &

basement columns

plastering in progress.

• Stilt floor material removing

work in progress.

MILESTONES

ACHIEVED

• Putty work completed.

UPCOMING

MILESTONES

• Service lift gladding complete.

• Stilt floor Screed complete.

PROGRESS TIMELINE

Actual site photograph

Construction Updates

April 21 May 21 June 21

Tower 5

TOWER

STATUS

• Tile work in progress.

• Putty work in progress.

• Internal plaster in progress.

• Stilt floor Block work in

progress.

MILESTONES

ACHIEVED

• Tile work completed 17 flats.

• Internal plaster 118 flats completed.

• 1st coat putty 118 flats completed.

• Lift waterproofing completed.

• External plastering 100% completed.

• External primer 70% completed.

UPCOMING

MILESTONES

• Tile work complete up to 3rd floor.

• Stilt floor columns plaster & wall

plaster complete 100%.

• Putty work complete 100%.

• Lift Plaster complete 100%.

• External primer 100% complete.

PROGRESS TIMELINE

Actual site photograph

Construction Updates

April 21 May 21 June 21

Tower 6

TOWER

STATUS

• Internal plastering in

progress.

• Tile work in progress.

• Putty work in progress.

• Lift block work in progress.

• Stilt floor columns plastering

in progress.

MILESTONES

ACHIEVED

• Tile work completed 40 flats.

• Putty completed 110 flats.

• Internal plastering 95% completed.

• Lift block work 90% completed.

UPCOMING

MILESTONES

• Tile work complete up to 6th floor.

• Stilt floor columns plaster complete 100%.

• Putty work complete 100%.

• Lift Plaster complete 100%.

PROGRESS TIMELINE

Actual site photograph

Construction Updates

April 21 May 21 June 21

Tower 12

TOWER

STATUS

• External plastering in

progress 7th series OTS.

• 1st & 2nd floor flat inside

1st coat putty work in

progress.

• Common area internal

plastering in progress.

• Toilet waterproofing &

screed work in progress.

• Toilet tile marking & rough

plastering in progress.

MILESTONES

ACHIEVED

• Toilet wall Rough plastering up to

6th floor.

• Internal putty work completed 5 flats.

• External plastering 8 series

completed.

UPCOMING

MILESTONES

• 1st coat putty complete 2nd to 6th floor.

• Tile work complete 36 flats.

• Toilet rough plaster 100% complete.

• External wall plaster 100% complete.

PROGRESS TIMELINE

Actual site photograph

Construction Updates

April 21 May 21 June 21

Tower 13

TOWER

STATUS

• Above terrace OHT wall, &

slab work in progress.

• Terrace floor screed

concrete in progress.

• External plastering in

progress.

• Block work in progress in

10th floor.

• Internal Wall & ceiling

plaster in progress.

• Toilet waterproofing &

screed work in progress.

MILESTONES

ACHIEVED

• Toilet waterproofing completed up to

3rd floor.

• Internal wall plaster completed 90 flats.

• Flats ceiling work completed 140 flats.

• External plastering 13 & 14 series

completed.

UPCOMING

MILESTONES

• Flats ceiling plaster complete 100%.

• Toilet waterproofing complete up to 6th floor.

• Toilet screed complete up to 6th floor.

• External plastering complete 30%.

• Internal wall plaster complete up to 8th floor.

• ALL OHT complete.

PROGRESS TIMELINE

Actual site photograph

Construction Updates

April 21 May 21 June 21

Site Office :Provident Kenworth

6-1-33, Inner Ring Rd, Shivrampalli Village, Shivarampally Jagir,

Hyderabad, Telangana 500052

Regional Office :Provident Housing Limited

No.8, Ulsoor Road, Bengaluru- 560 042

Tel: 080-44555544

Email : [email protected] (Subject line – Project name/ unit number)

Call Us : +91 - 80-67724001 / 1 860 208 0000

Web : www.providenthousing.com


Recommended