PSI - Jun. 27th, 2006 1 Status of the electronics systems of the MEG experiment
Transcript
Page 1: PSI - Jun. 27th, 20061 Status of the electronics systems of the MEG experiment.

PSI - Jun. 27th, 2006 1

Status of the electronics systems of the MEG

experiment

Page 2: PSI - Jun. 27th, 20061 Status of the electronics systems of the MEG experiment.

PSI - Jun. 27th, 2006 2

Electronic chain

216

630

ActiveSplitter

1:11:14:1

ActiveSplitter

1:11:14:1

ActiveSplitter

1:11:14:1

Ramp60 120

Pre-Amp8:1

PMT

LXe

HV

PMT

lateral

front

TC

HV

HV

APD

PMTbars

fibers

DC

HV

Wires

Strips

Pre-Amp

Pre-Amp

576

1156

atten

DRSDRS

DRSDRS

DRSDRS

5 crates512

Hit registers

4 boards

TriggerTrigger

Trigger

32

3 crates

Aux. devices

Page 3: PSI - Jun. 27th, 20061 Status of the electronics systems of the MEG experiment.

PSI - Jun. 27th, 2006 3

DAQ and control

6 crates

DRSDRS

DRSDRS

DRSDRS

Hit registers

TriggerTrigger

Trigger

3 crates

20 MHz clock

clockstartstopsync

Trigger signalEvent numberTrigger type

Trigger

BusyError

Ancillarysystem

E5 area ‘counting room’

PC (Linux)

PC (Linux)PC (Linux)PC (Linux)PC (Linux)

PC (Linux)

PC (Linux)PC (Linux)PC (Linux)

Front-End PCs

Run startRun stopTrigger config

Main DAQ PC PC (Linux)

GigabitEthernet

On-line farm

PC (Linux)PC (Linux)PC (Linux)

storage

PC (Linux)

Event builder

Page 4: PSI - Jun. 27th, 20061 Status of the electronics systems of the MEG experiment.

PSI - Jun. 27th, 2006 4

HV

Page 5: PSI - Jun. 27th, 20061 Status of the electronics systems of the MEG experiment.

PSI - Jun. 27th, 2006 5

HV

Active down regulation of an external HV supply

PSI design• 10 chn per board• 180 chn per 3 HE crate• Back side connector• Total of 6 crates

Active down regulation of an external HV supply

PSI design• 10 chn per board• 180 chn per 3 HE crate• Back side connector• Total of 6 crates

4 different requirements:– Lxe: 1000V , 100 uA– TC bars: 2400V, 1 mA– TC curved: 500V, <1 uA– DC: 2400V, ~1 uA

Commercial HV supplies delivered

Mass production in progressInstallation in September

Page 6: PSI - Jun. 27th, 20061 Status of the electronics systems of the MEG experiment.

PSI - Jun. 27th, 2006 6

Splitters

Page 7: PSI - Jun. 27th, 20061 Status of the electronics systems of the MEG experiment.

PSI - Jun. 27th, 2006 7

Splitter layout

• ERNI high bandwidth output connector

• crosstalk with ERNI connector plus 2m cable is ~ 0.6%

DRS

Trigger

Trigger or DRS Input

Power

Page 8: PSI - Jun. 27th, 20061 Status of the electronics systems of the MEG experiment.

PSI - Jun. 27th, 2006 8

Backplane layout

• Test circuit was implemented on backplane• Debug completed • PCB production in progress, mounting in house

Page 9: PSI - Jun. 27th, 20061 Status of the electronics systems of the MEG experiment.

PSI - Jun. 27th, 2006 9

Crates

• Mechanic parts and fans delivered• Power supplies delivered and tested

Frontal panel

Back panel

Output (5V-36A)

Page 10: PSI - Jun. 27th, 20061 Status of the electronics systems of the MEG experiment.

PSI - Jun. 27th, 2006 10

Cables Inputs• Single coaxial cable (RG178 – 9m

long) bundled into a polyester braided sleeve

• Negligible crosstalk between cables.

DRS outputs• High bandwidth output (DRS)• high density twisted pairs cable (0.68

pitch) 2 m long with one flat zone in the middle (Amphenol SPECTRASTRIP 68p)

Trigger outputs– Low density twisted pairs cable (1.27

pitch) 2 m long with 2 flat zone (3M 34p/10p)

Page 11: PSI - Jun. 27th, 20061 Status of the electronics systems of the MEG experiment.

PSI - Jun. 27th, 2006 11

Splitter SummarySplitter

– first prototype finished in may successfully– PCB production started the first of June– PCB production time one month – Component procurement in progress – Board mounting 2 weeks end of July – Board test 1 week – Boards ready by the beginning of September

Backplane– Crates and power supply delivered– backplane production in Lecce

Cables– Trigger cables ready– LXe cables in production– DRS cables in production

Installation– Foreseen between September 5 and 20

Page 12: PSI - Jun. 27th, 20061 Status of the electronics systems of the MEG experiment.

PSI - Jun. 27th, 2006 12

TC

Page 13: PSI - Jun. 27th, 20061 Status of the electronics systems of the MEG experiment.

PSI - Jun. 27th, 2006 13

PMT ramp generator

RAMPGEN.

RAMPGEN.D/DD/D

S TC Analog Sign. Monitor

NIM Signal for any possible use

to Splitter

BB

BBAnalog signals to DRS and trigger

PassiveSplitter

PMT

Dual Threshold ORConstant Fraction ORLeading edge discriminator

to Splitters

Signals to DRS

6U Eurocards boards

8 boards

Page 14: PSI - Jun. 27th, 20061 Status of the electronics systems of the MEG experiment.

PSI - Jun. 27th, 2006 14

ProductionPMT ramp generator• Design of the final boards in progress• Mass production September (?)• system delivery 8 boards October (?)

APD pre amplifiers• First prototype with problems on IC and cross talk• Second prototype design and test completed • Mass production and test in progress• system delivery end of July

APD hit registers • board design completed• Production and test in progress• system delivery (6 boards – 6U VME) end of July

Page 15: PSI - Jun. 27th, 20061 Status of the electronics systems of the MEG experiment.

PSI - Jun. 27th, 2006 15

Trigger

Page 16: PSI - Jun. 27th, 20061 Status of the electronics systems of the MEG experiment.

PSI - Jun. 27th, 2006 16

TriggerBoards

Type1

Front end

Type2

Ancill

Page 17: PSI - Jun. 27th, 20061 Status of the electronics systems of the MEG experiment.

PSI - Jun. 27th, 2006 17

System test

4 Type12 Type22 Ancillary

•Synchronous operation

•No transmission errors

Page 18: PSI - Jun. 27th, 20061 Status of the electronics systems of the MEG experiment.

PSI - Jun. 27th, 2006 18

Splitter-Type1 connection

Alpha and cosmic muon events from the Pisa facility

Page 19: PSI - Jun. 27th, 20061 Status of the electronics systems of the MEG experiment.

PSI - Jun. 27th, 2006 19

Number of boards: summary table

row col tot faninn.

board Type1

Connections Type1-Type2

n. board Type2

Connections Type2-Type2

n. board Type2

inner 9 24 216 1 14 1

up 9 6 54 4 1 1

down 9 6 54 4 1 1

lateral 6 24 144 4

lateral 6 24 144 4

back 9 24 234 4 4 1

Total 846 25 3

TC u.s. 15 2 30 1 2 1

TC d.s. 15 2 30 1 2 1

TC curved 256 2 512 8 4 1

Total 572 8 1

DC wires 16 16 256 8 2 1

aux dev 16 1 16 1 1 1

36 4 10.35 0.55

49 8

1

PMT Number of trigger boards

5 11 2

2

TOTAL produced

TC1 1

1

LXe

TOTAL mounted

Spare fraction

Page 20: PSI - Jun. 27th, 20061 Status of the electronics systems of the MEG experiment.

PSI - Jun. 27th, 2006 20

Number of boards: status

Boards Type1• 48 funded• 36 needed• 40 delivered• 8 not completely

mounted• 40 tested

Boards Type2• 10 funded• 5 needed• 10 delivered• 10 tested

Boards Ancill• 8 funded• 4 needed• 4 delivered• 4 not completely

mounted• 2 tested

Front-End Boards • 800 funded• 576 needed• 800 delivered• 320 tested

Done !

Done !

Page 21: PSI - Jun. 27th, 20061 Status of the electronics systems of the MEG experiment.

PSI - Jun. 27th, 2006 21

Type1 : VIRTEX II- PRO (XC2VP20-7-FF1152) • Type1-0 LXe front face • Type1-1 LXe lateral faces • Type1-2 LXe top,bottom and back face • Type1-3 TC bars • Type1-4 TC fibers

• Type1-5 DC • Type1-6 Auxiliary devices • Type1-7 LXe back face x

Type2 : VIRTEX II- PRO (XC2VP40-7-FF1152) • Type2-0 Final Level completed • Type2-1 LXe front+up/down faces

• Type2-2 LXe lateral faces • Type2-3 TC

Firmware V1.0 Present Status

Page 22: PSI - Jun. 27th, 20061 Status of the electronics systems of the MEG experiment.

PSI - Jun. 27th, 2006 22

Board Type3

Page 23: PSI - Jun. 27th, 20061 Status of the electronics systems of the MEG experiment.

PSI - Jun. 27th, 2006 23

Board Type3

• Type3 board 32 channels• Number of boards for the LXe lateral sides(612 chn): 20• Boards design : ~ ready• PCB prototype : end of July • Component delivery: (12 weeks) ~ beginning of September• Test: September• Production: October• Installation: end of October

Modified Type1 boards to produce an auxiliary digitization of the LXe signals

Page 24: PSI - Jun. 27th, 20061 Status of the electronics systems of the MEG experiment.

PSI - Jun. 27th, 2006 24

Comments on triggerInstallation

- Ready: any time from beginning of Jul. to end of Aug.- Should follow the NaI moving system- Should precede the electronic integration Sep. - DAQ computers

Configuration- Baseline version V1.0 written- Needs tuning, at least 1 month during purification- Needs analysis tools, under development

Documentation - Hardware register list available- Almost available for Type1- In progress for Type2

Page 25: PSI - Jun. 27th, 20061 Status of the electronics systems of the MEG experiment.

PSI - Jun. 27th, 2006 25

DRS

Page 26: PSI - Jun. 27th, 20061 Status of the electronics systems of the MEG experiment.

PSI - Jun. 27th, 2006 26

DRS• DRS2 available for all channels• New PMC card finished

– Reduced noise 1.2 mV → 0.5 mV RMS– Self-calibration on card– Mass production started– cards expected in August

• PSI GPVME boards in production– Delivery end of August

Page 27: PSI - Jun. 27th, 20061 Status of the electronics systems of the MEG experiment.

PSI - Jun. 27th, 2006 27

DRS2 issues

Issue Solution DRS2 DRS3Voltage nonlinearity

Calibration with cubic splines in Front-end

Clock nonlinearity Time calibration & frequency regulation

Cross talk 1% @ 7ns risetime

Redesign of CMC card with ERNI 68-pin connector and interleaved ground lines

Temperature dependence

- Calibration maybe possible to some extend- Keep electronics temperature constant- On-chip temperature compensation

?()

Self-heating of cells - Only use small signals (<0.5 V)- On-chip temperature compensation

()

Ghost pulses - Veto trigger ~5us after cosmic or LED event- Veto trigger after other calorimeter hits?- Record 2us calorimeter history in each event?- Redesign sampling cell

??

All issues could be resolved as planned

Page 28: PSI - Jun. 27th, 20061 Status of the electronics systems of the MEG experiment.

PSI - Jun. 27th, 2006 28

DRS3

• DRS3 design finished • Prototypes expected in August• Tests foreseen at the end of the year

Page 29: PSI - Jun. 27th, 20061 Status of the electronics systems of the MEG experiment.

PSI - Jun. 27th, 2006 29

DRS3 layout

• Smaller “standard cells”

• Totally > 600,000 transistors

• Smaller package (QFP64)

• 12 channels/chip• ROI readout and

parallel readout to reduced dead time:230 s → 50 s → 5 s

• Smaller “standard cells”

• Totally > 600,000 transistors

• Smaller package (QFP64)

• 12 channels/chip• ROI readout and

parallel readout to reduced dead time:230 s → 50 s → 5 s

Page 30: PSI - Jun. 27th, 20061 Status of the electronics systems of the MEG experiment.

PSI - Jun. 27th, 2006 30

DRS and Trigger Crates

Power distribution boxPower distribution box Issue: “Splitter” rack cannot be accessed easily from back side!

Issue: “Splitter” rack cannot be accessed easily from back side!

20 cm

Page 31: PSI - Jun. 27th, 20061 Status of the electronics systems of the MEG experiment.

PSI - Jun. 27th, 2006 31

DAQ cluster

Page 32: PSI - Jun. 27th, 20061 Status of the electronics systems of the MEG experiment.

PSI - Jun. 27th, 2006 32

DAQ Cluster Layout

80 GB System DiskRAID 1 (Mirror)

/home/meg

1.2 TG Data DiskRAID 5

80 GB System DiskRAID 1 (Mirror)

80 GB System DiskRAID 1 (Mirror)

Back-End

Front-End #1

Front-End #2

. . .NFS

/home/meg |-- root <- ROOTSYS |-- midas <- MIDASSYS |-- mxml |-- rome <- ROMESYS `-- meg <- MEGSYS |-- meganalyzer |-- megbartender |-- megmc `-- online |-- drivers |-- eventbuilder |-- frontend |-- slowcontrol | |-- bts | |-- calorimeter | `-- scfe |-- trigger `-- VPC

/home/meg |-- root <- ROOTSYS |-- midas <- MIDASSYS |-- mxml |-- rome <- ROMESYS `-- meg <- MEGSYS |-- meganalyzer |-- megbartender |-- megmc `-- online |-- drivers |-- eventbuilder |-- frontend |-- slowcontrol | |-- bts | |-- calorimeter | `-- scfe |-- trigger `-- VPC

VME-Interface

VME-Interface

SC-FE

Data rate100 MB/s

Page 33: PSI - Jun. 27th, 20061 Status of the electronics systems of the MEG experiment.

PSI - Jun. 27th, 2006 33

Front-end computers

Back-end1.2 TB disk

Back-end1.2 TB disk

Front-end #1Front-end #1

GBit SwitchGBit Switch

• Two DAQ computer installed with DAQ software

• Remaining computers delivered

• Installation end of July

Page 34: PSI - Jun. 27th, 20061 Status of the electronics systems of the MEG experiment.

PSI - Jun. 27th, 2006 34

Offline Cluster

Sun Fire x4100 quad core 4 GB

Sun Fire x4100 quad core 4 GB

Sun Fire x4100 quad core 4 GB

Sun Fire x4100 quad core 4 GB

Sun Fire x4100 quad core 4 GB

Fib

er

Ch

an

nel Sw

itch

15 x 500 GB SATA

• Ordered on June 14th: 20 cores + 30 TB disk• Easily extensible• Redundancy through GFS/GPFS file systems• GBit link to online cluster requested

GB

it E

thern

et

Page 35: PSI - Jun. 27th, 20061 Status of the electronics systems of the MEG experiment.

PSI - Jun. 27th, 2006 35

Slow control

Page 36: PSI - Jun. 27th, 20061 Status of the electronics systems of the MEG experiment.

PSI - Jun. 27th, 2006 36

SCS-2000 • Replaces SCS-1001 unit

• 64 I/O lines (analog, digital, opto-coupler, PT100, etc.)

• Outputs stable during CPU firmware upgrade (→ BTS control)

• “Soft” fuse

• LED pulser (40 lines, computer controllable)

• Replaces SCS-1001 unit

• 64 I/O lines (analog, digital, opto-coupler, PT100, etc.)

• Outputs stable during CPU firmware upgrade (→ BTS control)

• “Soft” fuse

• LED pulser (40 lines, computer controllable)

Page 37: PSI - Jun. 27th, 20061 Status of the electronics systems of the MEG experiment.

PSI - Jun. 27th, 2006 37

BTS slowcontrol

• Slowcontrol back-end to MSCB slow control units

• Integrated in MIDAS history system

• Monitoring and control though MIDAS web pages

• More pages added as SC equipment gets operational

Page 38: PSI - Jun. 27th, 20061 Status of the electronics systems of the MEG experiment.

PSI - Jun. 27th, 2006 38

MIDAS history

Page 39: PSI - Jun. 27th, 20061 Status of the electronics systems of the MEG experiment.

PSI - Jun. 27th, 2006 39

Conclusions

• All the key elements of the electronic system are available for integration in September

• Some parts will arrive with ~1 month delay

Page 40: PSI - Jun. 27th, 20061 Status of the electronics systems of the MEG experiment.

PSI - Jun. 27th, 2006 40

Rack space


Recommended