Date post: | 13-Jan-2016 |
Category: |
Documents |
Upload: | angel-angelina-harrison |
View: | 216 times |
Download: | 0 times |
Public Enterprises PortfolioCommittee Briefing
Jacob Maroga31 May 2006
Objectives
Update from previous briefings
Provide a progress update on Cape Recovery activities
Outline winter plans and risks for 2006
Progress on Capex Programme
Western Cape Network – Load and Capacity
Eskom Peaking Generation400 MW Palmiet
Note: The above excludes The City of Cape Town’sgeneration
LoadWinter Max : 4250 MWSummer Max : 3900 MW
Transmission Capacity2400 -2800
Koeberg Generation1800 MW
Predicted Weekly Shortfall
Shortfall Risk: 300 to 400 MW during morning and evening peaks
Week Ending
Load Forecast
Tx Limit Koeberg Palmiet Customer
Interruptability
Predicted shortfall
before savings 1-May-06 4043 2694 606 400 200 -143 8-May-06 4094 2736 564 400 200 -194 15-May-06 4223 2778 522 400 200 -323 22-May-06 4202 2820 480 400 200 -302 29-May-06 4103 2400 900 400 200 -203 5-Jun-06 4276 2400 900 400 200 -376 12-Jun-06 4267 2400 900 400 200 -367 19-Jun-06 4207 2400 900 400 200 -307 26-Jun-06 4261 2400 900 400 200 -361 3-Jul-06 4191 2400 900 400 200 -291 10-Jul-06 4128 2400 900 400 200 -228 17-Jul-06 4261 2400 900 400 200 -361 24-Jul-06 4130 2400 1800 400 200 670 31-Jul-06 4151 2400 1800 400 200 649 07-Aug-06 4156 2400 1800 400 200 644 14-Aug-06 4201 2400 1800 400 200 599 21-Aug-06 4204 2400 1800 400 200 596 28-Aug-06 4146 2400 1800 400 200 654 4-Sep-06 4174 2400 1800 400 200 626 11-Sep-06 4067 2400 1800 400 200 733 18-Sep-06 4056 2400 1800 400 200 744 25-Sep-06 3948 2400 1800 400 200 852
Un
it 1
Un
it 1
an
d 2
Un
it 2
This week
Key Recovery Activities
Supply / Capacity Recovery Activities Koeberg Generation Transmission Grid Leased-in Generation
Demand / Load Reduction Activities Energy Saving programmes
Demand Side Management Demand Market Participation
Load Shedding When demand exceeds supply
Progress – Koeberg repairs on track
Area Activity or Milestone Target Completion Date
Status
Unit 1 Rebuilding of Stator 4th Week April 2006 Completed
Arrival of Rotor 4th Week April 2006 Completed
Ready for Commissioning 2nd Week May 2006 Completed
Synchronisation 3rd Week May 2006 Completed
Full Load 4th Week May 2006 On track (80%)
Unit 2 Commence Power reduction 4th Week May 2006 On track
Refuelling outage 4th Week May 2006 On track
Synchronisation 3rd Week July 2006
Full Load 4th Week July 2006
Progress – Transmission on track
Activity or Milestone Target Completion Date
Status
Substation Insulation 3rd Week March 2006 Completed
Compensation Equipment 4th Week May 2006 96%
Line Re-insulation Emergency re-insulation between
Muldersvlei and Elandskloof Mountains complete
Spraywashing on hold due to bad weather
4th Week July 2006 30%
Protection 4th Week May 2006 80%
Spares 5th Week May 2006 70%
Progress – Energy Savings to date
PROGRAMME AREA TARGET(1 June target)
ACHIEVED TO DATE
EXPECTED TO DATE
PROGRESS
Efficient lighting 155 MW (100 MW)
65MW 100MW Implementation in progress. 2.1m bulbs replaced to date
(471k replaced in last week).
Customer self generation 50 MW
(50 MW)
52MW 45MW Letter of Agreement/Contacts signed for 52 MW in evening
peak and 51 MW in morning peak
Industrial and commercial efficiency including HWLC
40 MW(20 MW)
(6.75)
3MW 3.25MW 40 MW of identified opportunities (inclusive of HWLC) First MW savings recorded Upgrades of HWLC systems for 6.5 MW expected by 1 June
Subsidy of energy efficient appliances and devices through retailers and suppliers
25 MW(2 MW)
0.36MW 2.83MW Appliances currently supported:
1.) 4,200 geyser blankets installations completed.
2.) 600 low flow shower heads to be installed
3.) Funding for solar water heaters under investigation
Voluntary Conservation campaign
80 MW to 160 MW
(180 MW)
5MW 0MW Interactive control centre in advance stages of development
(150MW) Voluntary load shedding commitments for 5MW to date
Gas Conversion 50 MW(5 MW)
0.52MW 3.86MW 1,000 double plate hotplates, 20 gas hobs, 40 gas
standalone ovens and 35 gas heaters distributed to date
Total DSM plan 400 MW 127 MW 155 MW
Demand Market Participation
- 102 MW - Confirmed DMP contracts placed for 102MW (operational
from 1 May) with further 24MW availability during morning peak.
Network Optimisation - 7 MW - 7MW gained by reallocating open point on Hydra line Potential of MW voltage reductions being investigated
Total Energy Savings 236 MW
Update – Energy Savings Highlights
Power Alerts being flighted on SABC 1, 2 and 3 From 18h00 to 21h00 until 31st August Communicate status of energy demand and call people to
reduce energy usage Broadcast educational infomercials on savings tips every 15
minutes Expect to achieve 150 MW demand reduction impact if only a
conservative 20% of the residential consumers react
Update – Load Shedding to date
Load Shedding is required during periods where energy demand exceeds supply capacity Load shedding has taken place on 11 April and 22 May Weekly schedules are published in the newspapers a week in
advance
What could go wrong?
Risk
Koeberg Unit tripping
Late commissioning of Koeberg Unit 2
Transmission lines tripping
Mitigation
Additional capacity assigned to manage risk
Focused project team in place
Monitoring of Fires Replacement of insulators Protection settings have been
reviewed
What could go wrong?
Risk
Cold Weather
Unavailability of Palmiet Pumped Storage
Equipment failure at key substations on the whole network
Mitigation
Demand Side Management
Focus on dam levels Standby transformer on site
Special precautions taken to prevent faults
Strategic spares have been relocated closer to point of use
Overview of the ESKOM Winter 2006 Plan &
Outlook for 2007
Winter 2006 Supply – Demand Balance
Resources Available
MAXMUM CAPABILITY RATING (MW)
Commissioned Plant 1 May to 30 September
Coal Fired Thermal Stations
32 066
Nuclear Power Stations 1 800 Pump Storage Schemes 1 400 Hydro Schemes 600 Gas Turbines 342 Total Eskom 36 208
Cahora Bassa 1 050
TOTAL 37 258
(RTS excluded)
Emergency Resources
Additional assistance
Approximate MW available Approximate period available
DMP (Supplemental
reserve)
435 MW 2 hours per day
Emergency Level 1 ~360 MW Recommended not to exceed 2 hours per day
Interruptible load shedding
2105 MW Approximately 2 hours per week
Classification of Capacity Adequacy for winter 2006
Date Week Forecast Actual Supply Operating Reserve
Deficit(exc emergency))
8-May 19 33569 33202 1900 -2267
15-May 20 34055 33728 1900 -2227
22-May 21 34509 34610 1900 -1799
29-May 22 34443 34663 1900 -1680
5-Jun 23 34951 35422 1900 -1429
12-Jun 24 35450 35532 1900 -1818
19-Jun 25 35277 35532 1900 -1645
26-Jun 26 35151 36090 1900 -961
3-Jul 27 35268 36147 1900 -1021
10-Jul 28 35347 36090 1900 -1157
17-Jul 29 35473 36147 1900 -1226
24-Jul 30 34361 36954 1900 693
31-Jul 31 34122 36249 1900 227
7-Aug 32 33440 36470 1900 1130
14-Aug 33 33699 36130 1900 531
21-Aug 34 33015 34934 1900 19
28-Aug 35 32722 34464 1900 -158
4-Sep 36 33183 34230 1900 -853
11-Sep 37 32330 34090 1900 -140
18-Sep 38 32239 34278 1900 139
25-Sep 39 32249 33170 1900 -979
Risks & Mitigation - Generation
Risk Probability Impact Mitigation Strategy
Production Risks :
Risk 1 – Increase in plant unavailability factor by 1%
Risk 2 – Delay in return to service of Koeberg Unit 1 and 2
Risk 3 – Long term outage of 600 MW unit (catastrophic failure)
Risk 4 – Import reduction from Cahorra Bassa
High
Medium
Medium
High
~300MW
~900MW
~600MW
~240MW
If these risks materialise the response is as follows:
- There will be increased burn at Majuba and Tutuka Power Stations putting pressure on the coal stockpile at these stations. The mitigation of the coal stockpile risk is described below.
- The supply-demand imbalance has to be met through the use of contracted interruptible customers and customers on the DMP product (demand market participants).
Coal Availability, Procurement and Supply
Medium Reduction of stockpiles and
possible reduction of capacity to
manage stockpiles
- Additional emergency coal purchases.
- Continuous stockpile balancing between stations.
- Continuous interactions with mines to understand and manage geological and environmental issues.
- Contracting additional transport companies
Key Conclusion: Generation Capacity
We have enough available capacity but it very tight We have about 500MW additional emergency DMP and more is being
sourced Key risks
Impact of Koeberg on the national situation Technical problems on the running plants(loading and age) Higher demand than expected( weather and commodity prices)
Shortage of Supply does not mean blackouts! One can predict shortfalls and schedule emergency resources and if that runs
out have controlled load shedding managed by regional control centres. Sudden loss of generation due to faults are managed through the utilisation of
operational reserves and automatic under-frequency load shedding schemes which prevents cascading outages.
Load is then restored in a controlled fashion.
We are focused at avoiding mandatory load shedding at a national level at all costs.
However multiple technical problems can result in load shedding.
Transmission Corridors and Bulk Supply Points
Transmission Network Adequacy
Transmission Corridors supplying a significant geographical area from the Mpumalanga Generation Pool were identified .
The demand in these areas has been forecast and the capacity of these corridors assessed through power system studies.
Classification is as follows: Green : The corridor can supply the peak demand even if a single
credible contingency occurs (N-1). Orange : The corridor can supply the peak demand if no contingency
occurs (N-0) and a contingency plan exists to re-configure the distribution network to supply the load. Interruption of supply could occur based on the nature of the contingency and the load will then be restored.
Red : The corridor cannot supply the peak demand with the existing network and load shedding is required over the peak periods.
Brown : The corridor cannot supply the demand at peak periods as well as at other times of the day and rotational load shedding is required throughout the day.
Corridors
LimpopoPOLOKWANE
Firmness of Supply – Major Cities
LimpopoPOLOKWANE 1
3
4
2
6
7
8
910
5
1. Polokwane2. Rustenberg3. Pretoria4. Johannesburg5. Bloemfontein6. Richards Bay7. Durban8. East London9. Port Elizabeth10. Cape Town
Risks & Mitigation - Transmission
Risk Probability Impact Mitigation Strategy
41 single line contingencies that violate operating criteria and could lead to load shedding
Medium Possible interruptions of supply during contingency
- Purchase of emergency towers (eventually 3 per grid)
- Purchase of 2 permanent towers per grid
- Fire management and prevention programme
- Emergency Preparedness Plans in place to swing load on the distribution networks
35 unfirm transformation sites
Medium Possible interruptions of supply during contingency
- There are contingency plans for all but 3 of the sites. At these sites there is a possibility of load shedding over peak periods if a transformer fails.
- Pre-winter oil checks and on-line condition monitoring
Transmission Corridor firmness
Medium Load shedding over peak periods
- As per single line contingencies.
Credible contingencies at substations
Medium Possible interruptions of supply for short
periods
- Infrared scanning of all substations by end of May 2006.
- Substations EPPs in place.
- Risk analysis of critical outages.
- Manage outages in the nights and weekends.
- Purchase and re-location of key spares to site to reduce restoration times.
Key Conclusion: Transmission Grid
The Cape corridor remains a risk until Koeberg units are back
Risk at the other corridors are considered low Risks of double contingencies are always present
Distribution Network
Risks & Mitigation - Distribution
Risk Probability Impact Mitigation Strategy
Loss of Transmission infeeds
Medium Possible interruptions of supply during contingency
- Emergency Preparedness Plans in place to swing load on the distribution networks.
- Joint planning with Transmission grids on contingency plans and holding exercises to assess readiness
Poor performance of under-frequency load shedding scheme relays and/or the deliberate switching off relays on customer sites
Low Excessive load shed in certain
areas and increased risk of
brown-outs
-Schemes are regularly tested and calibrated (at least once a year).-Plan to monitor relays on SCADA system
- Have been utilised in recent incidents on the grid with satisfactory performance. Audits done after every incident
Slow restoration times due to poor communication with municipalities and metros
Medium Prolonged outages to end customers
-Distribution regions communicate with municipalities and metros to inform on capacity situation and contingency plans.- Implement lessons from Cape incidents
Illegal Connections Medium to High
Overloading of local transformers and reticulation lines causing localised
interruptions
- Awareness campaign on illegal connections- Removal of identified illegal connections
Aging Infrastructure Medium Failure of lines or transformers
causing localised interruptions
-Strategic spares and key spares procured and kept at key sites
- Mobile transformers to be used in remote sites
2007 Outlook and beyond
Capacity outlook for 2007
27500
29500
31500
33500
35500
37500
39500
41500
08-M
ay
05-J
un
03-J
ul
31-J
ul
28-A
ug
25-S
ep
23-O
ct
20-N
ov
18-D
ec
15-J
an
12-F
eb
12-M
ar
09-A
pr
07-M
ay
04-J
un
02-J
ul
30-J
ul
27-A
ug
24-S
ep
22-O
ct
19-N
ov
17-D
ec
MW
PEAK DEMAND FORECAST TOTAL MAINTENANCE GENERATION CONSTRAINTSUCLF Projection +Allowance OPERATING RESERVE MAX CAPACITYNEW OCGT'S DMP (435 MW) INTERRUPTABLES (2105 MW)PEAK DEMAND FORECAST (High) PEAK DEMAND FORECAST (Low)