City of Marshfield, Engineering Division. Public Informational Meeting . for 2014 Mill-in-place. 2014 Construction. City of Marshfield, Engineering Division. Engineering Division Contacts. Tom Turchi, City Engineer Tim Cassidy, Assistant City Engineer Josh Mauritz, Civil Engineer II - PowerPoint PPT Presentation
Popular Tags:
37
Public Informational Meeting for 2014 Mill-in-place ty of Marshfield, Engineering Division 2014 Construction
Transcript
Page 1: Public Informational Meeting

Public Informational Meeting

for

2014 Mill-in-place

City of Marshfield, Engineering Division

2014 Construction

Page 2: Public Informational Meeting

Engineering Division Contacts

• Tom Turchi, City Engineer• Tim Cassidy, Assistant City Engineer• Josh Mauritz, Civil Engineer II• Kris Hawley, City Surveyor• Lance Oldham, Engineering Tech I• Shawn Miller, Engineering Tech I

• Phone: (715) 486-2034• Web Site: ci.marshshfield.wi.us• [email protected]

City of Marshfield, Engineering Division

Page 3: Public Informational Meeting

Street Division Contacts

• Brian Panzer, Street Superintendent• Kurt Bornbach, Assistant Street Superintendent• Mike Winch, Assistant Street Superintendent

• Phone: (715) 384-3606

• Web Site: • ci.marshshfield.wi.us

City of Marshfield, Engineering Division

Page 4: Public Informational Meeting

City of Marshfield, Engineering Division

312178 – Apple Avenue (15th Street to 17th Street)

Page 5: Public Informational Meeting

City of Marshfield, Engineering Division

312184 Broadway Avenue (Upham Street to McMillan Street)Shawano Drive (Broadway Avenue to Upham Street)Laird Street (Shawano Drive to St Joseph Avenue)

Page 6: Public Informational Meeting

City of Marshfield, Engineering Division

312183Carmen Drive (Waushara Drive to Upham Street)

Debra Lane (Carmen Drive to Hume Avenue)Renee Lane (Debra lane to Upham Street)

Page 7: Public Informational Meeting

City of Marshfield, Engineering Division

Page 8: Public Informational Meeting

City of Marshfield, Engineering Division

Page 9: Public Informational Meeting

Typical Progression of Events

• Ditching & Underdrain

City of Marshfield, Engineering Division

Page 10: Public Informational Meeting

• Pulverizing

City of Marshfield, Engineering Division

Typical Progression of Events

Page 11: Public Informational Meeting

• Grading & Compacting

City of Marshfield, Engineering Division

Typical Progression of Events

Page 12: Public Informational Meeting

• Raise / adjust manholes

City of Marshfield, Engineering Division

Typical Progression of Events

Page 13: Public Informational Meeting

• Asphaltic Paving

City of Marshfield, Engineering Division

Typical Progression of Events

Page 14: Public Informational Meeting

• Shouldering

City of Marshfield, Engineering Division

Typical Progression of Events

Page 15: Public Informational Meeting

Construction Schedule• Begin in June after school is out.• Ditching and under-drain construction • Pulverizing – this is based upon the schedule of

equipment.• Adjust manholes.• Prepare for paving – sometime in August before school

is in session.• Shouldering following the paving – August / September

• Both - Pulverizing and Paving are extremely fluid schedules. We typically know about one to two weeks ahead of time for their schedule. Even then the schedule can be disrupted very easily if it rains.

City of Marshfield, Engineering Division

Page 16: Public Informational Meeting

Sequence of Events• Adoption of budget (Nov 2013). • Survey (Fall 2013).• Initial PIM (January 2014).• Preliminary resolution (Jan 2014).• Design • Mail Special Assessment information (April 2014) –

– Notice of public hearing.– Installment assessment notice.– Report of the City Engineer.– Schedule ‘D’ including estimated special assessments.

• PIM – 90% Design & Special Assessments.• Create final special assessments (Jan 2015).• Mail final special Assessments (Mar 2015).

City of Marshfield, Engineering Division

Page 17: Public Informational Meeting

Access Considerations• We would like to know if you or your neighbor may require special

access during construction due to a disability.

• Do you or your neighbor receive meals on wheels or other services that should be considered during the design process.

• Our goal is to try to be accommodating as possible during construction. (please note access can not be maintained at all times)

• Parking during construction will be allowed on the side streets when

access is restricted for the paving of the new surface.

City of Marshfield, Engineering Division

Page 18: Public Informational Meeting

How are services are affectedduring construction

• Mail - The post office will continue providing mail service as normal.

• Trash & recyclables - Veolia waste services will be able to provide service as normal.

• Water – This service will not be affected during construction.

• Sanitary - Sanitary sewer service will not be affected during construction. If you have had issues with your sanitary sewer lateral this would be an appropriate time to make any repairs necessary prior to final paving.

• Parking – Access to your driveway for the mill in place process is only disrupted when resetting or replacing your driveway culvert. During the actual asphaltic paving process we will need to restrict access to your property for a day or two until the asphalt has had the chance to cool.

• Emergency services – Our office continually updates the City’s emergency services to road closures, construction sites and locations of restricted access.

City of Marshfield, Engineering Division

Page 19: Public Informational Meeting

What can you do to prepare for the project?

• Begin financial planning for the assessment.

• Coordinate landscaping, driveway replacement and other construction plans you may have.

• Now would be the opportune time to lengthen a driveway culvert during the construction process. Please note the maximum length allowed by city policy is 40 feet.

• Ask questions; inform staff of your concerns.

City of Marshfield, Engineering Division

Page 20: Public Informational Meeting

Funding• Street

– Pulverizing and paving are assessable items– Assessments are based upon the ordinances 1/3, 1/3, 1/3.– 1/3 of the cost for pulverizing and asphalt paving assessed to

the homeowners on one side, 1/3 is assessed to the other side of the street and the remaining 1/3 is funded by general tax dollars.

• Driveway aprons– Are not assessable. – Driveways are paved as follows:

• Gravel Aprons are restored as gravel.• Asphalt aprons are restored in asphalt.• Concrete or brick paver aprons are restored in asphalt.• Please note special end wall treatments are not replaced. It

is the responsibility to remove and replace these end wall structures on their own.

City of Marshfield, Engineering Division

Page 21: Public Informational Meeting

Funding• Ditching

– Is not assessable. – This includes the installation of the under drain.

• Sump Pumps can be connected to the underdrain system.• Downspouts and other types of yard drains can not be connected.

• Culverts– The property owner is responsible for the cost associated with the

lengthen or replacement of their specific culvert pipe. Installation is included as part of the ditching process.

– If the culvert is removed and appears to be in good shape it will be reused.

– If the culvert has rust holes the city will require the replacement of the culvert.

• The culvert can be replaced with galvanized metal or dual wall black plastic (HDPE) pipe.

– Arrangements can be made with our Assistant Street Superintendent to coordinate the replacement of your culvert where he coordinates delivery and installation and pipe supplier mails the bill directly to the homeowner.

City of Marshfield, Engineering Division

Page 22: Public Informational Meeting

City of Marshfield, Engineering Division

Dual Wall HDPE

Page 23: Public Informational Meeting

City of Marshfield, Engineering Division

Page 24: Public Informational Meeting

City of Marshfield, Engineering Division

Galvanized Corrugated Metal Culvert Pipe or Aluminum Culvert Pipe

Page 25: Public Informational Meeting

Sanitary Sewer LateralReplacement Policy

• Now would also be a good time to review the condition of your sanitary sewer lateral.

• The City will televise your sanitary sewer lateral at no cost to the homeowner.– Access to the cleanout is necessary– If you have had root problems in the past they will need to be

removed before the televising can be effective.

• Addressing your sanitary sewer lateral now can save a road cut in the future which in turn helps with the longevity of the new roadway.

• To schedule the televising please contact the Marshfield Wastewater Treatment Plant at (715) 591-2022.

City of Marshfield, Engineering Division

Page 26: Public Informational Meeting

City of Marshfield, Engineering Division

Page 27: Public Informational Meeting

City of Marshfield, Engineering Division

Page 28: Public Informational Meeting

City of Marshfield, Engineering Division

Page 29: Public Informational Meeting

Special Assessment Payment Options• Estimated

– The estimated special assessments will be calculated and mailed prior to the start of construction.

• Final– Final assessments calculated in early 2014 and mailed out in March of

2014.

• Payment Options– Pay the entire amount 30 – days from date delivered (note this will not

occur until 2014).– Place assessments on tax roll and pay for it over a 10 - year time frame

at an interest rate set by the common council. Typically 1.5% over the interest rate for that years borrowing which has been set at 3.28%.

City of Marshfield, Engineering Division

Page 30: Public Informational Meeting

Example of how SpecialAssessments are calculated

• Frontage– The this is the actual front measurement of the

parcel.

• Sideage– If the parcel is a corner lot the side

measurement is prorated to 50% the front foot rate for residential properties and 75% the front foot rate for all other uses..

• Example shown– Frontage is 110 linear feet

• 110 * 15 = $ 1,650

– Sideage is 130 linear feet• 130 * 15 * .5 = $ 975

– Assume both the front and side are being milled.

• Total Special Assessment = $ 2,625

– Assume a front foot rate of $15.00 / Linear Foot

– 2013 rates are as follows:• Mill / Pave WO C&G – estimate $12.16 per LF

City of Marshfield, Engineering Division

Page 31: Public Informational Meeting

City of Marshfield, Engineering Division

Page 32: Public Informational Meeting

Information we need from you the Resident• Items not located by Diggers Hotline such as the items Listed below:

• Sump pump discharge service line – Is your discharge already buried and where is it located.

• Private underground utilities - Buried irrigation systems and pet containment. Buried underground power (owned by homeowner).

• Issues that you believe should be reviewed in the design process.

• Miscellaneous items or issues that should be addressed in design which could effect construction.

City of Marshfield, Engineering Division

Page 33: Public Informational Meeting

Property Owner Contact Information

• During the design and construction process questions do arise for our designers and construction inspectors.

• Having your contact information will help our staff address issues in a timely and efficient manner.

• Please verify your information on our mailing labels. Make any corrections necessary and please provide the following information. (if you know your neighbors information and they could not make it to this meeting please provide what you can)

– Name – Phone Number

• Work (only used in extreme situations unless otherwise noted)• Home

– Other

City of Marshfield, Engineering Division

Page 34: Public Informational Meeting

How can you give inputand stay informed?

[email protected]– Drop us an email

• (715) 486-2034– Call us; office hours are 8:00 a.m. to 5:00 p.m.– Schedule an appointment.

• City of Marshfield, Engineering Division, 630 S. Central Ave.– Stop by the office; office hours are 8:00 a.m. to 5:00 p.m.

• www.ci.marshfield.wi.us– Visit the city’s website.

City of Marshfield, Engineering Division

Page 35: Public Informational Meeting

Thank You for Attending • Your input on this project is very important to us.

• Questions and answers

City of Marshfield, Engineering Division

Page 36: Public Informational Meeting
Page 37: Public Informational Meeting

Engineering Division ContactsThank You for Attending

• Tom Turchi, City Engineer• Tim Cassidy, Assistant City Engineer• Josh Mauritz, Civil Engineer II• Kris Hawley, City Surveyor• Lance Oldham, Engineering Tech I• Shawn Miller, Engineering Tech I

• Phone: (715) 486-2034• Web Site: ci.marshshfield.wi.us