+ All Categories
Home > Documents > public spaces and associated development - Dublin … · f. canalside, Borneo Sporenburg, Amsterdam...

public spaces and associated development - Dublin … · f. canalside, Borneo Sporenburg, Amsterdam...

Date post: 18-Aug-2018
Category:
Upload: duongxuyen
View: 219 times
Download: 0 times
Share this document with a friend
13
public spaces and associated development urban projects 4.1 West Terrace (1) A new public space, the West Terrace, is proposed to the west of station, elevated over tracks. The West Terrace is part of a sequence of spaces running from IMMA to the Phoenix Park, linked by a legible and high quality pedestrian and cycle route. The space will allow vehicular access to lands at the rear of the station and provide a new forecourt to the station addressing land to the west. The West Terrace should be predominantly used by public transport, taxis and private cars East bound traffic is given the option to connect with the terrace from St. John’s Road. Traffic can continue across to Conyngham Road or access the station and station lands. The impact of traffic through the space should be minimised and access to the rear of the station efficient and controlled. Character: The West Terrace uses the topography of the valley to create the illusion that the terrace is at grade. By taking the level of Conyngham Road and continuing it across the river to the rear of the station and across the tracks, a new datum level is created. The space should be highly organised and have a civic character appropriate to the forecourt to the national station and gateway to the city. The West Terrace will lie in the centre of the valley between IMMA and the Wellington monument and will have a panoramic view of both structures and the Liffey Valley to the West. The West Terrace should be clearly divided into trafficked and pedestrian areas. The West Terrace will benefit from south-west to west aspect, with an almost unobstructed view to the setting sun. The southern edge of the space is partially enclosed by the development on the Eircom site on St. John’s Road West. The edge is defined by St. John’s Road (N4) at the lower level. CIE Lands substudy document Associated development: The west end of the station should be redeveloped with a new elevation onto the West Terrace. From this elevation the central concourse to the east can be accessed and therefore also Heuston Square and the Luas platforms. The site north of the station is considered suitable for a tall building. A Suggested use is hotel accommodation. A significant building of relatively low height should be developed to the northwest of the West Terrace. This building is within the protected view between IMMA and the Department of Defence (Gandon building). This building also has prominent frontage onto the space. a. views of Waverley Station and Princes Street Gardens, Edinburgh, Scotland b. Broadgate, Liverpool Street, London c. Santa Justa Station, Seville, Spain [Cruz + Ortiz] d. Attocha Station, Madrid, Spain [Rafael Moneo] a. b. c. d. CIE Lands site sections
Transcript

public spaces and associated developmenturban projects

4.1 West Terrace (1)

A new public space, the West Terrace, is proposed to the west of

station, elevated over tracks. The West Terrace is part of a sequence

of spaces running from IMMA to the Phoenix Park, linked by a legible

and high quality pedestrian and cycle route.

The space will allow vehicular access to lands at the rear of the

station and provide a new forecourt to the station addressing land to

the west. The West Terrace should be predominantly used by public

transport, taxis and private cars

East bound traffic is given the option to connect with the terrace from

St. John’s Road. Traffic can continue across to Conyngham Road or

access the station and station lands.

The impact of traffic through the space should be minimised and

access to the rear of the station efficient and controlled.

Character:

• The West Terrace uses the topography of the valley to create

the illusion that the terrace is at grade. By taking the level of

Conyngham Road and continuing it across the river to the rear

of the station and across the tracks, a new datum level is

created.

• The space should be highly organised and have a civic

character appropriate to the forecourt to the national station

and gateway to the city.

• The West Terrace will lie in the centre of the valley between

IMMA and the Wellington monument and will have a

panoramic view of both structures and the Liffey Valley to the

West.

• The West Terrace should be clearly divided into trafficked and

pedestrian areas.

• The West Terrace will benefit from south-west to west aspect,

with an almost unobstructed view to the setting sun.

• The southern edge of the space is partially enclosed by the

development on the Eircom site on St. John’s Road West. The

edge is defined by St. John’s Road (N4) at the lower level.

CIE Lands substudy document

Associated development:

• The west end of the station should be redeveloped with a

new elevation onto the West Terrace. From this elevation the

central concourse to the east can be accessed and therefore

also Heuston Square and the Luas platforms.

• The site north of the station is considered suitable for a tall

building. A Suggested use is hotel accommodation.

• A significant building of relatively low height should be

developed to the northwest of the West Terrace. This building

is within the protected view between IMMA and the Department

of Defence (Gandon building). This building also has

prominent frontage onto the space.

a. views of Waverley Station and Princes Street Gardens, Edinburgh, Scotlandb. Broadgate, Liverpool Street, Londonc. Santa Justa Station, Seville, Spain [Cruz + Ortiz]d. Attocha Station, Madrid, Spain [Rafael Moneo]

a.

b. c. d.

CIE Lands site sections

public spaces and associated developmenturban projects

4.2 Heuston Square (2)

The space to the front of the Headquarters Building of the Great

Western Railway is considered to be in the centre of the Heuston

Gateway. All destinations in the area radiate from this space. Heuston

Square is the main arrival space from the city centre.

Heuston Square has river frontage along the north edge and links

Victoria Quay to the section of Quay north of the station building

(River Terrace). This is identified as a principal pedestrian desire line

and must therefore be appropriately detailed to allow safe and

controlled flow across traffic carriageways and Luas lines.

Heuston Square is the site of the three Luas platforms for Heuston

Station.

The Square provides access to the bridges at the end of the one-way

system on the quays. Traffic must therefore be carefully managed with

pedestrian and cycle paths protected.

Character:

• It is proposed that the space should be an active and central

urban square for the Heuston Gateway.

• The space must provide clear legibility for the entire area. The

views up to IMMA and across to Collins Barracks are important

in terms of orientation.

• The choice of hard landscaping surface should contrast with

the standard materials used throughout the city. The surface

should be of a high quality.

• The square will benefit from excellent views and light due to

the relatively low existing protected structures to the south and

west.

Associated development:

• The Guinness UDV site on Victoria Quay and Heuston Square

opposite the Headquarters Building should be developed with

a high profile building of the highest architectural standards.

General building height should generally be approximately

equivalent to six floors of commercial use.

• Part of the site should be developed as a landmark tall

building with appropriate slenderness and transparency.

• The development of the Caskworks on Steeven’s Lane

provides an opportunity for high-density commercial

development. The northern block will have frontage onto the

Heuston Square and Dr Steevens’ Hospital Park. Again six

floors of commercial or equivalent is proposed.

CIE Lands substudy document

a. b.

c. d. e.

a. existing Heuston Square from southb. existing Heuston Square from north-westc. Place des Terraux, Lyons, France [Christian Drevet]d. Schouwburgplein, Rotterdam, Holland [West 8]e. Place d’Armes, Namur, Belgium [Atelier 4D]

a. b. c. d.

public spaces and associated developmenturban projects

4.3 River Terrace (3)

The proposed access to the station lands from Conyngham Road

frees up the area between the existing station building and the river.

This creates a car-free terrace that marks the transition from the

man-made, urban quay condition to a natural, planted riverside

condition west of Heuston Station.

Character/quality

• The River Terrace should provide external amenity space for

the station services and circulation. Bars and cafes should be

developed along the edge of the station onto the terrace.

• The space will be characterised by the views across and along

the river.

• The movement of passengers from the West Terrace to the

station concourse and Heuston Square might be

accommodated along this space.

• A tall building is proposed to the west end of the River Terrace.

The Terrace will create a lower forecourt to the building.

Associated development

• The redevelopment of the northern edge of the station should

provide restaurant, bar and retail facil it ies.

• The tall building should be accessed from the River Terrace

and West Terrace. This will encourage movement in an east-

west direction through the River Terrace.

• Any development must allow for riverside walkways to

continue on the south bank as far as Clancy barracks.

CIE Lands substudy document

a. existing view of River Terrace looking eastb. view from Heuston Station lands to Sean Heuston Bridgec. view of Wellington Monument and Conyngham Road Bus Depot from existing River Terraced. north side of Heuston Station buildnge. Viaduct des Artes, Paris, Francef. canalside, Borneo Sporenburg, Amsterdamg. Brindley Place, Birmingham, England

e. f. g.

public spaces and associated developmenturban projects

4.4 Heuston Station – Redevelopment of the station and adjoining public spaces (4)

Heuston Station is the transport hub and focal space of the Heuston

Gateway. In order to meet future demands and create an appropriate

environment, the following proposals are put forward:

• redevelopment of station to allow greater capacity and

efficiency

• reorganisation of external urban spaces around the station:

West Terrace

East Square

River Terrace

South Facade

4.5 Conyngham Road Public Space (5)

A large public space is proposed on the Conyngham Road Bus Depot

site. The space is effectively an extension of the West Terrace, acting

as an intermediate space between the West Terrace and Phoenix

Park.

The space should be functional and active. Pedestrian access should

be provided from the space down to the riverside walk on the North

Bank.

Character:

• The space should be active and carefully designed to allow

safe and efficient flow of all modes of transport including

pedestrians.

• The space will be at the same level as Conyngham Road and

allow panoramic views over the river and Heuston Station

lands to The Royal Hospital Kilmainham.

• The detailing, materials and planting should be consistent with

the West Terrace.

Associated development:

• A mix of uses should be developed onto the space

with building lines dictated by the new vehicular bridge and

pedestrian route.

• Building to the west of the space onto the vehicular carriage

ways to be 5 storeys residential and must not interrupt the

‘significant view’ from The Royal Hospital Kilmainham to the

Department of Defence Headquarters.

CIE Lands substudy document

• Building to the east of the space to be 6 storeys commercial

with facade following the line of the pedestrian and cycle track.

A section of this site onto Conyngham Road should have

restricted height to avoid interrupting the ‘significant view’ as

indicated on plan.

a. view to Conyngham Road Bus Depot from Heuston Station car parkb. view of Conyngham Road Bus Depot from quays by Heustoin Stationc. view of Guinness UDV Brewery from apartments on Conyngham Roadd. view of IMMA at Royal Hospital Kilmainham from apartments on Conyngham Road

a. b. c. d.

building heights and viewsurban projects

5.0 Building Heights and Views

The western half of the CIE lands are within the ‘significant view’

identified by the Heuston Station and Environs Regeneration Strategy

and Development Framework Plan, from the Royal Hospital to the

Phoenix Park. The lines of the significant view are taken from the west

corner of the north range of the Royal Hospital Kilmainham and east

corner of the Deputy Master’s House to the western side of the

Magazine Fort and east edge of the main elevation of the Department

of Defence Headquarters respectively. Therefore the east side of the

West Terrace is not within the view.

It is proposed that a tall and elegant building is constructed on the

east side of the West Terrace.

The West Terrace will provide a new platform for viewing the Phoenix

Park, west city and Royal Hospital Kilmainham. The tall building

addressing the space will locate the station from a distance.

CIE Lands substudy document

visual connections

high buildings

building heights and viewsurban projects

5.0 Building Heights and Views

CIE Lands substudy document

b. c. d.

f. g. h.

a.

e.

B section through west terrace looking east

B1 section through Liffey Valley looking west

heuston gateway: sections

A

A

B1

B1

B

B

C

C

a. view of Royal Hospital from Phoenix Parkb. view of Royal Hospital rail bridge from Conyngham Roadc. view of full north range of Royal Hospital from Conyngham Road d. Royal Hospital north facadee. view of Phoenix Park from Royal Hospital to westf. view of Phoenix Park from Royal Hospital to north-westg. view of Phoenix Park from Royal Hospital to northh. view of Phoenix Park from Royal Hospital to north-east

connectionsurban projects

6.0 Connections

In order to increase permeability through the site and connect with the

wider city, the Development Framework Plan proposes a series of

connections throughout the study area.

6.1 Pedestrian / Cycle route connecting PhoenixPark and IMMA

The Phoenix Park and Royal Hospital Kilmainham Park have been

separated since the construction of the Heuston Station in the mid

1800s. Consequently both parks have lost any direct connection to

each other and with the river. Both parks also suffer from poor linkage

to the city or public transport nodes.

The construction of a pedestrian and a cycle link between the Phoenix

Park and the Royal Hospital Kilmainham area will directly address the

above issues.

The overall configuration is proposed as an arch in plan as shown.

The route is described from north to south.

• A new pedestrian and cycle entrance to the Phoenix Park

should link the main axis (Chesterfield Avenue) to a new

pedestrian and cycle crossing on Conyngham Road.

• The new crossing should link onto the south side of

Conyngham Road and Parkgate St., and into the present

Dublin Bus depot. New buildings should provide elevations

onto the pedestrian/cycle link at this point.

• A new pedestrian/cycle bridge is proposed over the River

Liffey linking onto the new West Terrace above the tracks.

• The pedestrian/cycle areas on the West Terrace are to be

clearly defined and separated from vehicular areas. The route

should be adjacent to, and dictate the line of the elevation of

the tall building by the station and the new west elevation of

the station.

• The route should cross St John’s Road and follow the existing

curve of Military Road. The height difference should be

accommodated within the Eircom/OPW development.

• The route should link up to the junction with the entrance to

IMMA and Irwin Street/ Bowbridge. The route should

notionally continue west through IMMA to the Inchicore Road,

Kilmainham Gaol and Memorial Gardens, or south to

Kilmainham Village and James Street (linking with the existing

steps at Cromwell’s Quarters).

CIE Lands substudy document

east bound

west bound

access to lands

pedestrian / cycle amenity

connectionsurban projects

6.2 Pedestrian/cycle route from Victoria Quay to Memorial Gardens

The pedestrian and cycle route from Victoria Quay to Memorial

Gardens / Islandbridge is part of a wider vision for a route on the

South Bank of the river connecting Chapelizod to the Docklands.

The CIE lands make up the largest section of this route. The route

should have 2 distinct characters through the CIE lands; the River

Terrace at the station and a Riverside Walk along the south bank of

the river. The River Terrace is described in section 4.3.

The new Riverside Walk should run below the new bridges through

the area to the existing rail bridge. The route should respond to the

more ‘natural’ condition of the river in this area, and provide a

relatively secluded amenity from the station to Clancy Barracks.

6.3 Eastbound traffic: St Johns Road (N4) to Conyngham Road

Traffic from the N4 eastbound currently travels along St. John’s Road,

past the south façade and across the east façade of the station and

the Frank Sherwin Bridge to the North Quays.

It is proposed to disperse the traffic at a number of points to reduce

loading around the station, across Heuston Square and on the North

Quays.

This is to be achieved by highlighting three locations for reaching the

northside at:

South Circular Road

West Terrace

Heuston Square

A new eastbound traffic ramp from St John’s Road to the West Terrace

is proposed. The road should continue into a new bridge across the

river and onto Conyngham Road.

6.4 Clancy Barracks to Heuston Station Lands

At present Clancy Barracks and the Heuston Station Lands are cut off

from each other and the general network of the city.When Heuston

Station Lands are developed, it is proposed that a tunnel vehicular

link is created using the height difference of the sites at the railway

line. It is proposed that the Heuston Station Lands should be

accessed from the new West Terrace. These links will help integrate

both sites into the city fabric and increase accessibility.

Adequate provision should be made for pedestrians and cyclists.

CIE Lands substudy document

6.5 Clancy Barracks / Heuston Station Lands to Phoenix Park

Despite their proximity, Clancy Barricks and the Heuston Station

Lands are relatively unconnected to the Phoenix Park. Where Sarah

Bridge in the west and the proposed new bridge onto the West Terrace

both provide north-south linkage. There is still an area that is not

easily accessible from the park. However an existing iron railway

bridge on the Phoenix Park line provides the opportunity for a

pedestrian and cycle link, 'hanging' off the existing structure.

This considerably improves the amenity provision to the Clancy

Barricks and Heuston Station Lands, and provides direct linkage to

major public transport services on Conyngham Road

6.6 Public Transport Connections: Bus

The existing bus routes through the area should be maintained and

increased. Buses should stop at various points in close proximity to

the station and associated public spaces.

Buses on Conyngham Road / Parkgate Street should have the option

of a station drop-off on the West Terrace / Conyngham Road bus

depot site or by the Hickeys site.

The no. 90 bus running between Connolly station, the Quays and

Heuston should have a dedicated lane allowing a right turn into

Heuston Square, so relating the stop to the Luas.

a. tram, Montpelier, Franceb. Luas, photomontage, Connolly Station, Dublinc. train station forecourt, Nordhausen, Germanyd. bus on public space, Place des Terraux, Lyons, France

a. c. d.b.

connectionsurban projects

6.7 Public Transport Connections: LUAS

The Luas stop on Heuston Square is on the Luas Line A, due for

completion in 2003. The line runs between Tallaght and Abbey Street,

with proposals to extend to

6.8 Public Transport Connections: Taxis

The present taxi provision is a pick up area on the south façade of the

station building directly on St. Johns Road, and a drop off in the area

between the station and the river. Queuing is not sheltered and the

environment is of a poor quality.

It is proposed that the taxi rank is relocated to the West Terrace to

create:

• a controlled, managed taxi rank away from a main

thoroughfare with increased accommodation for taxis and

customers.

• a sheltered waiting area directly accessible to the station.

Taxis should be able to access to the West terrace from St. Johns

Road eastbound and Conyngham Road in both directions. Egress will

be possible onto Conyngham Road in both directions.

6.9 Private cars

The present provision for private cars to drop off and pick up is

inadequate and unsustainable. It is proposed that the West Terrace

should provide safe and ample provision for private cars away from a

main road. Access and egress are as for taxis.

The present access to the car park for the station is between the

station and the river. With increased development on the site and the

increased traffic congestion caused by Luas, the bridge from

Conyngham Road to the West Terrace is essential to provide

adequate access. Access to the ground level car park should be from

the West Terrace.

Pedestrian access to the station and river should be provided from the

car park.

CIE Lands substudy document

traffic on the quays by Heuston Station, summer 2002

sustainability strategyurban projects

7.0 Sustainability Strategy

The Development Framework Plan for the Heuston Gateway shouldincorporate a sustainability strategy for appropriate development. Alldevelopments should follow the basic guidelines andrecommendations for sustainable urban design as described in thiss e c t i o n .The sustainability strategy is in line with the National SustainableDevelopment Strategy of the Government of Ireland, The StrategicPlanning Guidelines for the Greater Dublin Area (2000), DTO: APlatform for Change and the Dublin City Development Plan 1999.

The aims of the sustainability strategy for the Heuston Gatewayshould be:• create an appropriate balance between dense urban

development and preservation or creation of green amenity areas

• to encourage development of high density mixed use areas forliving and working

• to integrate large underused stakeholders’ sites into the urbangrain of Dublin

• to reduce car dependency and provide efficient public transport

• to protect water quality and air quality • to control noise pollution• to manage waste and recycling• to preserve natural landscapes and ecosystems• to protect architecturally or historically significant structures

The sustainability strategy is described in the areas of1. Density and Mixed Use2. Transport3. Environmental Quality4. Conservation

7.1 density and mixed use

The Development Framework Plan aims to reduce urban sprawl andexpansion by:• remodelling of public spaces and amenity• development of vacant infill sites• regeneration of industrial sites• increased densityThis is in line with section 14.1.1 of the Dublin City Development Plan1999, Managing Intensification and Change: A Strategy for DublinBuilding Height, and the DOE Guidelines for Planning Authorities onResidential Density, 1999.

The Development Framework Plan promotes mixed use development

CIE Lands substudy document

with close proximity of housing, jobs, services and amenities.Development should create an attractive and vibrant environmentthat appeals to a wide range of people including the elderly andfamilies. Mixed use areas should allow synergies to be developedbetween non residential uses.

High density housing should be encouraged.Housing design shouldaddress issues of:• accessibility• adaptability• lifetime use• energy use• natural ventilation• water conservation• communal facilities • waste management

Building designs should be assessed using BREEAM assessmentmethod of EcoHomes and materials specified using the BRE’sGreen Guide to Housing Specification.Social and affordable housing should be integrated into the development to encourage social heterogeneity. Private developers,local authorities, informed design teams and approved housing bodies should be encouraged to work together to provide appropriate standards in design, construction and provision. Thecomplete environment of the housing should be fully designed andimplemented.The developers should be encouraged to use new systems and techniques to allow greater output, higher standards and reduce sitetime.

social and affordable housing, Dublin [Urban Projects]; housing for elderly, Amsterdam [KCAP]; terraced housing,Rotterdam; housing, Helsinki [Arrak Architects]

housing, Dornbirn, Austria [Herman Kaufmann]; terraced housing and apartments, Rotterdam [KCAP]

sustainability strategyurban projectsCIE Lands substudy document

7.2 transport

The Development Framework Plan aims to reduce dependency on the

car and promote use of public transport, cycling and walking. The high

density, mixed use developments proposed around the

station will reduce distances travelled between home, workplace and

services.

Cars currently dominate the area creating a compromised

environment due to:

• and noise pollution

• tiredness and stress

• danger of accidents

• visual disamenity

• occupied space

Transport and parking policies should be designed to promote public

transport use. Park and ride schemes at out of town locations should

reduce the numbers of cars being brought into the city.

Initiatives such as car-sharing should be investigated.

New and improved public transport services should be introduced as

necessary with well designed timetables and tariff structures, and

increased safety and security. New services should be provided to

help integrate and revitalise areas as necessary.

The new streets should be designed to give less space to the car and

increased space for pedestrians, cyclists and public transport. Areas

for different modes of transport should be clearly defined using

materials and sectional changes.

Cycling is a sustainable form of urban transport due to:

• quality of life and health issues

• independence, speed and versatility

• physical size of transport mode - low occupied space

• ability to integrate into all environments without dominating or

causing an adverse impact

Adequate provision of cycle tracks and parking should be provided.

Initiatives such as bicycle loan schemes should be investigated.

An appropriate balance between pedestrian and vehicular traffic

should be created. Communal space in residential and commercial

areas should be detailed to create pedestrian dominant areas with

car park, Heilbronn, Germany [Mahler Gunster Fuchs]cycle lane, Copenhagenpedestrian, Dublin

sustainability strategyurban projectsCIE Lands substudy document

controlled access for cars.

7.3 environmental quality

The strategy for maintaining a high quality and sustainable environment in the Heuston Gateway is described in terms of energymanagement, water management and green spaces.

7.3.1 energy managementThe developments in the Heuston Gateway should aim to reduceenergy consumption by:• high density development• site design orientation to ensure optimum passive solar gain• use of a rational energy supply and efficient use• high levels of insulation and thermal capacity in building

fabric

Proposals for the Heuston Station lands should apply for grants andaward schemes such as the House of Tomorrow Research,Development and Demonstration Programme (RD&D). This programme is administered by the Irish Energy Centre under theEconomic and Social Infrastructure Operational Programme of theNational Development Plan. Proposals of a significant scale areencouraged. Model projects for new build, refurbishment or retrofit ofhousing, demonstrating superior energy design and technologyimplementation in homes or groups of homes under real operatingconditions with the potential for market influence and replication aresuitable for consideration in this scheme.

7.3.2 water managementGroundwater and surface water should be protected and waste waterminimized.Diverting surface water to reservoirs within green spaces can havethe following positive effects:• improvement in air quality by helping evaporation and

therefore increasing air humidity• improvement in microclimate• aiding slow soaking and restoration of natural water table• improvement in social and visual amenity

Flooding risk should be minimized by retaining permeable groundareas and improving surface drainage.It is essential to avoid loss of soil permeability by:• maximising areas of green roofs• use of permeable surfaces in car parks• promotion of grassed areas in courtyards

Rainwater collection can be an economical solution to applicationssuch as toilet flushing, washing machines, cleaning and production

processes. Rainwater recovery systems should be used in all developments. The natural river banks along the Liffey and Cammock through theHeuston Gateway should be preserved or restructured as necessary.The Regeneration Strategy for the Heuston Gateway states that ‘thecontrasting conditions within the Heuston Gateway should beappropriately preserved and strengthened.’ The preservation of thecontrast between natural riverbank conditions to the west of HeustonStation and the urban quay condition at Heuston Station and to theeast is an essential aspect of this recommendation.

7.3.3 green spacesThe Development Framework Plan for the Heuston Gatewaypromotes:• preservation of open spaces• protection of plant life• biodiversity• regeneration of river banks

The provision of green spaces is considered essential for the following reasons:• to increase air water content• absorption of CO2 and release of O2• absorption of dust• regulation and regeneration of natural water balance• natural filtration of water• absorption of sound • positive physical and psychological effects• provision of social and leisure space• economic opportunities• preservation of natural environment, wildlife and plant

conservation

Meadow areas in gardens and parks should be promoted to encourage a wide variety of wild flowers, grasses and wildlife.Courtyards and open spaces should be green and used for energyand water conservation, waste management and amenity.

smart facades:offices, Athens

[Meletitiki/A.N. Tombazis and Associates Architects Ltd]

rainwater recovery system: Potsdamer Platz, Berlin [masterplan, Renzo Piano]

sustainability strategyurban projects

7.4 conservation

The station building is a protected structure. The proposal retains the

sandstone and brick buildings but suggests the removal of all internal

cast iron structures as these are not architecturally significant, restrict

sustainable and efficient development (number of platforms) and

create a low quality environment in terms of light and space.

The listed terrace on Conyngham Road should be restored and found

an appropriate new use.

CIE Lands substudy document

Sean Heuston Bridge and Heuston Station


Recommended