Pump Monitoring & Rebuild Program Luz E. Penilla, Associate Engineer (Civil), Vibration Analyst: ISO Category III BAYWORK March 19, 2019
Transcript
Page 1: Pump Monitoring & Rebuild ProgramOverall Vibration (ANSI HI, ISO, EASA/NEMA) Shaft Vibration Displacement (ISO 20816-5) Shaft Deflection (API 610/ ANSI ASME B73.1) Setting Warning

Pump Monitoring & Rebuild Program

Luz E. Penilla, Associate Engineer (Civil), Vibration Analyst: ISO Category III

BAYWORK

March 19, 2019

Page 2: Pump Monitoring & Rebuild ProgramOverall Vibration (ANSI HI, ISO, EASA/NEMA) Shaft Vibration Displacement (ISO 20816-5) Shaft Deflection (API 610/ ANSI ASME B73.1) Setting Warning

|

Facts About SCVWD

10 Dams & Reservoirs

114 Miles Raw & Treated Pipelines

3 Portable Water Treatment Plants

1 Recycled Water Treatment Plant

3 District Pump Stations

Serves 2 million people

756 Employees

Engineering Maintenance Support

Mechanical (2)

Electrical (6)

Pump & Motor Rebuild Program - Condition Monitoring

2

Page 3: Pump Monitoring & Rebuild ProgramOverall Vibration (ANSI HI, ISO, EASA/NEMA) Shaft Vibration Displacement (ISO 20816-5) Shaft Deflection (API 610/ ANSI ASME B73.1) Setting Warning

|

Pumps Units Selected

Critical Pumps = 77

Sizes 50 hp ≥ 2000 Hp

Centrifugal

Vertical & Horizontal

Pump & Motor Rebuild Program - Condition Monitoring

3

Page 4: Pump Monitoring & Rebuild ProgramOverall Vibration (ANSI HI, ISO, EASA/NEMA) Shaft Vibration Displacement (ISO 20816-5) Shaft Deflection (API 610/ ANSI ASME B73.1) Setting Warning

|

Motivation for Change

Cost

Long rebuild process

Failures

Pump & Motor Rebuild Program

4

Page 5: Pump Monitoring & Rebuild ProgramOverall Vibration (ANSI HI, ISO, EASA/NEMA) Shaft Vibration Displacement (ISO 20816-5) Shaft Deflection (API 610/ ANSI ASME B73.1) Setting Warning

|

Pump & Motor Rebuild ProgramPump and Motor Rebuild Program Components

5

1. RISK INDICATORS

2. GENERAL SCOPE OF WORK (SOW)

3. REBUILD PROCESS & ROLES

4. TRAINING

5. RECORDS MANAGEMENT

Page 6: Pump Monitoring & Rebuild ProgramOverall Vibration (ANSI HI, ISO, EASA/NEMA) Shaft Vibration Displacement (ISO 20816-5) Shaft Deflection (API 610/ ANSI ASME B73.1) Setting Warning

|

When to Rebuild – Predictive Maintenance

Contact Wear

Vibration (Motor & Pump)

Bearing Impacts

Overall Vibration (ANSI HI, ISO, EASA/NEMA)

Shaft Vibration Displacement (ISO 20816-5)

Shaft Deflection (API 610/ ANSI ASME B73.1)

Setting Warning and Alarms levels

Progressive Wear

Hydraulic Performance

Motor Testing

Temperature

Pump & Motor Rebuild Program - Condition Monitoring

6

Page 7: Pump Monitoring & Rebuild ProgramOverall Vibration (ANSI HI, ISO, EASA/NEMA) Shaft Vibration Displacement (ISO 20816-5) Shaft Deflection (API 610/ ANSI ASME B73.1) Setting Warning

|

Vibration – Assigned Risk Indicators

Pilot Program

DFI: Vibration velocity limits

Roller Bearing Wear: Vibration acceleration

Pump & Motor Rebuild Program - Condition Monitoring

7

Dynamic Force Indicator (DFI) Level

ARI 1 2 3 4

Bea

rin

g W

ear

Stag

e (B

)

11.41 2.24 3.16 4.12

22.24 2.83 3.61 4.47

33.16 3.61 4.24 5

44.12 4.47 5 5.65

DFI L1<ANSI/HI

LIMIT

DFI L2≥ HI Limit,

< 1.5x ANSI/HI

Limit

DFI L3 = ≥ 1.5x

ANSI/HI Limit, <2x ANSI/HI Limit

DFI L4 = ≥ 2x

ANSI/HI Limit

Page 8: Pump Monitoring & Rebuild ProgramOverall Vibration (ANSI HI, ISO, EASA/NEMA) Shaft Vibration Displacement (ISO 20816-5) Shaft Deflection (API 610/ ANSI ASME B73.1) Setting Warning

|

Assigned Risk Indicator (ARI)

Assigning Risk Indicator (ARI)

≤2 = Low Risk of Failure (Normal)

2>3 = Moderate Risk of Failure (Next Planned Maintenance)

3>4 = High Risk of Failure (Repair in 30 Days)

4> = Very High Risk of Failure (Repair Immediately)

Pump & Motor Rebuild Program - Condition Monitoring

8

P. Graney and Ken Starry,“Rolling Element Bearing Analysis”, 2011

22 BDFI ARI +=

Page 9: Pump Monitoring & Rebuild ProgramOverall Vibration (ANSI HI, ISO, EASA/NEMA) Shaft Vibration Displacement (ISO 20816-5) Shaft Deflection (API 610/ ANSI ASME B73.1) Setting Warning

|

FY17 ResultsPump & Motor Rebuild Program – Condition Monitoring

9

36

3 46

73%

6% 8%12%

0

5

10

15

20

25

30

35

40

GOOD (Low Risk) Fair (Moderate Risk) Alarm 1 (High Risk) Alarm 2 (Very High Risk)

Ma

ch

ine

s Eva

lua

ted

Condition Ratings

Predictive Maintenance

Vibration Condition Ratings as of June 2017 (49 Units Surveyed)

Pump Monitoring Report (PG. 1)

Page 10: Pump Monitoring & Rebuild ProgramOverall Vibration (ANSI HI, ISO, EASA/NEMA) Shaft Vibration Displacement (ISO 20816-5) Shaft Deflection (API 610/ ANSI ASME B73.1) Setting Warning

|

2000 Hp Pump – Sleeve Bearings

Overall Vibration Velocity

Pump & Motor Rebuild Program – Condition Monitoring

10

Page 11: Pump Monitoring & Rebuild ProgramOverall Vibration (ANSI HI, ISO, EASA/NEMA) Shaft Vibration Displacement (ISO 20816-5) Shaft Deflection (API 610/ ANSI ASME B73.1) Setting Warning

|

Hydraulic Performance

Baselines

Pump & Motor Rebuild Program - Condition Monitoring

11

Page 12: Pump Monitoring & Rebuild ProgramOverall Vibration (ANSI HI, ISO, EASA/NEMA) Shaft Vibration Displacement (ISO 20816-5) Shaft Deflection (API 610/ ANSI ASME B73.1) Setting Warning

|

Pump & Motor Rebuild ProgramPump and Motor Rebuild Stages

12

1. RISK INDICATORS

2. GENERAL SCOPE OF WORK (SOW)

3. REBUILD PROCESS & ROLES

4. TRAINING

5. RECORDS MANAGEMENT

Page 13: Pump Monitoring & Rebuild ProgramOverall Vibration (ANSI HI, ISO, EASA/NEMA) Shaft Vibration Displacement (ISO 20816-5) Shaft Deflection (API 610/ ANSI ASME B73.1) Setting Warning

|

Team: Roles & Responsibilities

13

Maintenance & Operations (MAINT)

Field Operations Administrator (FOA)

Purchasing Dept (PURCH)

Contractor (CONTR)

Engineering (MECH & ELEC)

Asset Management (AM)

Pump and Motor Rebuild Team

Page 14: Pump Monitoring & Rebuild ProgramOverall Vibration (ANSI HI, ISO, EASA/NEMA) Shaft Vibration Displacement (ISO 20816-5) Shaft Deflection (API 610/ ANSI ASME B73.1) Setting Warning

|

Rebuild Phase 1:

Procurement, Removal, Shop Inspection, As-Found Report

14

Page 15: Pump Monitoring & Rebuild ProgramOverall Vibration (ANSI HI, ISO, EASA/NEMA) Shaft Vibration Displacement (ISO 20816-5) Shaft Deflection (API 610/ ANSI ASME B73.1) Setting Warning

|

Rebuild Phase 1: Steps 1-3Pump and Motor Rebuild Process

15

ENGR

MAINT1. Problem

Detected

2. Perform

Pre-Tests

3. Does

Equipment

require a

Rebuild?

Yes,

Step 4

No, Initiate

minor repairs

Page 16: Pump Monitoring & Rebuild ProgramOverall Vibration (ANSI HI, ISO, EASA/NEMA) Shaft Vibration Displacement (ISO 20816-5) Shaft Deflection (API 610/ ANSI ASME B73.1) Setting Warning

|

Rebuild Phase 1: Steps 4-7Pump and Motor Rebuild Process

16

FOA

4. Request SOW

from AM. Work

with Engr to

finalize SOW.

AM

5. Provide

General SOW

and O&M Data

6. Initiate RFP

Purchasing 7. Process RFP

Continued from Step 3

Page 17: Pump Monitoring & Rebuild ProgramOverall Vibration (ANSI HI, ISO, EASA/NEMA) Shaft Vibration Displacement (ISO 20816-5) Shaft Deflection (API 610/ ANSI ASME B73.1) Setting Warning

|

Rebuild Phase 1: Steps 8-10Pump and Motor Rebuild Process

17

FOA

10b. Support

Contr

9. Coordinate

Removal with

Maint, Contr &

Engr

Contr8. Schedule

Removal &

Transport

Continued from Step 7

ENGR

MAINT

10c. Witness

Removal (Take

Photos)

10a. Remove,

Transport & Sch.

Disassembly

Date

Page 18: Pump Monitoring & Rebuild ProgramOverall Vibration (ANSI HI, ISO, EASA/NEMA) Shaft Vibration Displacement (ISO 20816-5) Shaft Deflection (API 610/ ANSI ASME B73.1) Setting Warning

|

Rebuild Phase 1: Steps 11-15Pump and Motor Rebuild Process

18

FOA

11. Notify Engr

of Shop

Disassembly

Contr

Continued from Step 10

ENGR 12. Witness

Disassembly

13. Disassemble

& Inspect

14. Submit As-

Found to Engr

15. Review

Report and

Authorize to

Proceed

Page 19: Pump Monitoring & Rebuild ProgramOverall Vibration (ANSI HI, ISO, EASA/NEMA) Shaft Vibration Displacement (ISO 20816-5) Shaft Deflection (API 610/ ANSI ASME B73.1) Setting Warning

|

Rebuild Phase 1 - Summary

Pre-Tests

Procurement

Removal (FOA, Maint, Contr)

Shop Inspection (Engr/Maint, Contr)

As-Found Report

Pump and Motor Rebuild Process

19

Page 20: Pump Monitoring & Rebuild ProgramOverall Vibration (ANSI HI, ISO, EASA/NEMA) Shaft Vibration Displacement (ISO 20816-5) Shaft Deflection (API 610/ ANSI ASME B73.1) Setting Warning

|20

Rebuild Phase 2: Rebuild

Page 21: Pump Monitoring & Rebuild ProgramOverall Vibration (ANSI HI, ISO, EASA/NEMA) Shaft Vibration Displacement (ISO 20816-5) Shaft Deflection (API 610/ ANSI ASME B73.1) Setting Warning

|

Rebuild Phase 2: Steps 16-20Pump and Motor Rebuild Process

21

FOA

16. Notify

Contractor to

Proceed with

Rebuild

Contr

Continued from Step 15

ENGR

17. Rebuild, Test &

As-Found Report –

HOLD POINTS for

Engr to Witness

18. Submit As-

Build Report to

Engr

19. Review

Report; Do

results meet

specifications?

NO

YES

20.

Coordinate

installation

Page 22: Pump Monitoring & Rebuild ProgramOverall Vibration (ANSI HI, ISO, EASA/NEMA) Shaft Vibration Displacement (ISO 20816-5) Shaft Deflection (API 610/ ANSI ASME B73.1) Setting Warning

|

Stage 17: Rebuild, Shop Test & Report (CONTR)

Hold Points for District staff

Shaft Runout

Impeller Balancing

Electrical Testing

Vibration Testing

Rebuild Process and Roles

22

Page 23: Pump Monitoring & Rebuild ProgramOverall Vibration (ANSI HI, ISO, EASA/NEMA) Shaft Vibration Displacement (ISO 20816-5) Shaft Deflection (API 610/ ANSI ASME B73.1) Setting Warning

|

Phase 2 – Shop Test References & Tools

Pump Clearances/Balance

Mfg. or API 610

Motor

IEEE 112, ANSI/EASA AR100

O&M manual

E.g. end play

Vibration Analyzer

Pump and Motor Rebuild Process

23

Page 24: Pump Monitoring & Rebuild ProgramOverall Vibration (ANSI HI, ISO, EASA/NEMA) Shaft Vibration Displacement (ISO 20816-5) Shaft Deflection (API 610/ ANSI ASME B73.1) Setting Warning

|24

Rebuild Phase 3: Install, Baseline &Close-Out

Page 25: Pump Monitoring & Rebuild ProgramOverall Vibration (ANSI HI, ISO, EASA/NEMA) Shaft Vibration Displacement (ISO 20816-5) Shaft Deflection (API 610/ ANSI ASME B73.1) Setting Warning

|

Rebuild Phase 3: Steps 21-23Pump and Motor Rebuild Process

25

FOA

21b. Support Contr

& Engr’s testing

Contr

Continued from Step 20

ENGR

MAINT

21c. Witness Install &

Perform or Witness

Baseline Testing

21a. Install, Test &

Field Report

22. Submit As-Build

Report to Engr

23. Do results

meet

specifications

?

NO

YES

Page 26: Pump Monitoring & Rebuild ProgramOverall Vibration (ANSI HI, ISO, EASA/NEMA) Shaft Vibration Displacement (ISO 20816-5) Shaft Deflection (API 610/ ANSI ASME B73.1) Setting Warning

|

Rebuild Phase 3: Steps 24-25Pump and Motor Rebuild Process

26

FOA

Continued from Step 23

24. Close-out

Project

AM25. Update Records,

& Record baselines

for Trending

Page 27: Pump Monitoring & Rebuild ProgramOverall Vibration (ANSI HI, ISO, EASA/NEMA) Shaft Vibration Displacement (ISO 20816-5) Shaft Deflection (API 610/ ANSI ASME B73.1) Setting Warning

|

Pump & Motor Rebuild ProgramPump and Motor Rebuild Stages

27

1. RISK INDICATORS

2. GENERAL SCOPE OF WORK (SOW)

3. REBUILD PROCESS & ROLES

4. TRAINING

5. RECORDS MANAGEMENT

Page 28: Pump Monitoring & Rebuild ProgramOverall Vibration (ANSI HI, ISO, EASA/NEMA) Shaft Vibration Displacement (ISO 20816-5) Shaft Deflection (API 610/ ANSI ASME B73.1) Setting Warning

|

Pump & Motor Rebuild ProgramPump and Motor Rebuild Stages

28

Page 29: Pump Monitoring & Rebuild ProgramOverall Vibration (ANSI HI, ISO, EASA/NEMA) Shaft Vibration Displacement (ISO 20816-5) Shaft Deflection (API 610/ ANSI ASME B73.1) Setting Warning

|

THANK YOU

What is your organization‘s process?

Pump and Motor Rebuild Stages

29

What changes do you recommend?

Biggest Challenge?


Recommended