+ All Categories
Home > Documents > QATAR NATIONAL CEMENT · PDF filepreheater. We are informed that ... preliminary findings...

QATAR NATIONAL CEMENT · PDF filepreheater. We are informed that ... preliminary findings...

Date post: 17-Feb-2018
Category:
Upload: duongminh
View: 217 times
Download: 3 times
Share this document with a friend
27
1 Cunningham Lindsey QATAR LLC International Loss Adjusters P.O. Box 19462 Office 12, 3rd Floor Al Reem Tower West Bay, Doha State of Qatar Mob: (+974) 6686 7671 Tel: (+974) 4006 8949 Email: [email protected] Report No. 241203101395 Date: 14 December 2015 PRIVATE AND CONFIDENTIAL RISK SURVEY REPORT QATAR NATIONAL CEMENT COMPANY UM BAB QATAR ISSUED TO: Al Khaleej Takaful Insurance and Reinsurance Company QSC P.O. Box 455, Doha, Qatar
Transcript

1

Cunningham Lindsey QATAR LLC International Loss Adjusters P.O. Box 19462 Office 12, 3rd Floor Al Reem Tower West Bay, Doha State of Qatar Mob: (+974) 6686 7671 Tel: (+974) 4006 8949 Email: [email protected]

Report No. 241203101395

Date: 14 December 2015

PRIVATE AND CONFIDENTIAL

RISK SURVEY REPORT

QATAR NATIONAL CEMENT

COMPANY

UM BAB

QATAR

ISSUED TO:

Al Khaleej Takaful Insurance and Reinsurance

Company QSC

P.O. Box 455, Doha, Qatar

2

INTRODUCTION

The subject of this report is the Qatar National Cement Company (QNCC), a

publicly listed company on the Qatar Stock Exchange, who are a major

producer of Ordinary Portland Cement, Sulphate Resistant Cement, Hydrated

Lime, Calcined lime and Washed Sand in State of Qatar.

Over the past three years the Insured have expanded their facilities and this

report deals with both the existing facilities as well to outline the implications

of the future expansion plans.

1 – 2 – The proposer’s two main sites on the outskirts of Um Bab.

Further to your instructions we proceeded to the proposer’s offices in Um Bab

on the West Coast of Qatar where we initially met with their Finance

Manager, Mr Ashwin Kumar, in order to get an overview of this risk. We also

subsequently met with the organisation’s Production Manager, Mohammed

El-Shafeey Yousief and Head of Maintenance, Mohammed Fowzy, on three

separate occasions at their main plant to discuss the new expansion as well as

any issues that have been encountered in the recent past. Our enquiries are

now concluded and we trust will allow insurers to take a view with regards the

3

risk profile of the premises for insurance purposes in respect of the following

major perils :

- Fire / explosion

- Elemental Perils

- Impact

- Burglary

- Catastrophic Perils

- Machinery Breakdown

- Business Interruption

COMPANY PROFILE

The Insured are one of 43 public companies listed on the Qatar Stock

exchange with a 43% share of their stock held by the Qatar Government.

The company was established per the Emiri Decree No.07 in 1965 to produce

Ordinary Portland Cement in sufficient quantity to meet the growing demand

for cement in the State of Qatar.

The cement manufacturing units of company are situated on two large

separate sites at Umm Bab, approximately 82km from Doha, in close proximity

to a limestone which has been mined since 1969. They also operate their

admin offices out of Um Bab and own and manage a residential housing

estate for their staff nearby. A third plant in Al-Boaadiat is operated by them

and produces washed sand for the local construction industry.

In total six cement production lines have been commissioned on their sites

with a present total cement production capacity of 15,500 tons per day and

clinker production capacity of 11,900 tons per day.

4

The Insured are in the process of erecting a new production line on their site

outside Um Babb which will provide an additional capacity of 5,000 tons of

klinker and 5,500 tons of cement per day. This turnkey project started is

expected to come online with full klinker production by October 2016.

The Insured have also commissioned a Calcium Carbonate Production Unit

which essentially comprises two large scale crushers producing 180 tons of

1.4mm – 4mm sized calcium carbonate particles over a 10 hour daily

operating cycle.

The washed sand plant, purchased in January 2003 from the Ministry of

Municipality and Agriculture Affairs, has been upgraded to a present capacity

of 20,000 tons per day.

The company presently employs approximately 1,350 staff, 1,200 of whom are

resident in the company housing in Um Bab and work at the Cement Plants

and 131 at the sand processing plant.

According to their 2014 financial statements the annual turnover of the

company was declared at QR 1,050,653,859 generating a bottom line profit of

QR420 million.

For more information please refer to their website at

http://www.qatarcement.com/ .

DESCRIPTION OF PREMISES

5

The Insured operate their cement production from two large independent

sites located 3km from each other at Um Bab on the West Coast of Qatar

approximately 80 km from Doha.

The sites are independent and surrounded by perimeter fencing separating

them from the neighbouring properties.

The site closest to Um Bab houses the oldest plant which was established in

1969 with a 100 tons per day production line using a semi dry production

process. A further two similar lines were added in 1974 and 1976 bringing the

capacity up to 300 tons per day.

The production lines can be used to produce either Portland or Sulphate

Resistant Cement and the process which is followed is regarded as old

technology.

The site also has a Calcined Lime production line which was originally

commissioned in 1982.

The buildings on site include their administrative building/head office, raw

material storage sheds, raw material hoppers, workshop/store, cement plant

facilities including raw material mills and 3 gas fired kilns, as well as a

laboratory to test the quality of their products.

The second site houses 3 production lines which were commissioned in 1998,

2007 and 2009. These lines are totally automated and follow a dry process

with capacities of 2,000, 4,000 and 5,000 tons per day respectively.

6

The new klinker production line is located on this site and is being erected in

parallel with the existing lines. In addition the Calcium Carbonate Production

crusher is also housed next to the existing production lines.

Facilities on this site include the administrative buildings, control centre, full

workshop facilities, raw material storage sheds, hoppers and cement plant

facilities including raw material mills, cyclone towers, gas fired kilns, clinker

grinders, cement and clinker silos.

Approximately halfway between the two cement production sites is the

limestone quarry where the Insured source raw limestone as part of their

production process. The limestone is blast mined although we are informed

that the entire process is controlled by the Ministry of Explosives under strict

police supervision with the Insured having no responsibility or control over the

process. The Insured use a fleet of diggers and dumper trucks to extract the

limestone to be fed into their production process.

3 – 4 – Views of the limestone quarry

As advised the Insured own and maintain a housing estate for their staff which

includes facilities on site including a mess hall, club house and medical centre.

In addition they also operate a desalination plant which provides water for

both the estate as well as their production processes.

7

We understand that the Insured also operate a Gypsum Quarry close to the

border of Saudi Arabia. During the course of our enquiry we did not get the

opportunity to visit this site although we were informed that this facility is

relatively minor using manual diggers only to extract the raw material.

The final site is the sand washing facility which is located approximately 30km

inland of Um Bab. There are two plants on the site which uses recycled water

that is pumped in from a lagoon approximately 6km away. Only one plant is

used at present although the second plant can be commissioned if the need

arises. Facilities on site include the administration offices, washing plant,

water recycling plant, store, heavy equipment generator and weighbridges.

5 – 6 – Views of the sand processing plant

PREVIOUS LOSSES

We were informed of an incident in 2009 where a gas explosion occurred in a

preheater. We are informed that the kiln was switched off at the time of the

explosion and a gas leak resulted in a build-up of gas which ignited. The

production line was out of action for 3 months and resulted in losses of QAR

25 million although the resulting claim was settled for approximately QAR 3

million.

8

Following this event a new gas monitoring system was introduce although the

technical details of this have not been made available.

We understand that since 2013 the following claims have been initiated under

the Insured's policies and remain outstanding:

1) Property All Risks

a) Claim No.: PAR/CL/100259/2014 Date of Loss: 01/05/2014 Damage to 2 Nos. Sand Conveyor Lines (Line No.1 & Line No. 3) at Old Sand Processing Plant at Al Rakia (Baid Al Gaa) due to high wind which caused collapse of both conveyor lines (Present Position : Further reports/supporting documents in this respect are awaited)

b) Claim No.: PAR/CL/100462/2015 Date of Loss: 22/03/2015 Leakage of water into Cement Silo 1 – Line 4 - Due to rain the water had accumulated on the roof of Silo 1 and 2, wetting the silo wall due to crack in drain pipe which caused the water falling on to silo and wet it (Present Position : Further reports/supporting documents in this respect are awaited)

c) Claim No.: PAR/CL/100566/2015 Date of Loss: 18/06/2015 Customer Truck caused accident to Sand Plant (Unit# 3 & 4) damaging water pipeline and electrical cable (Present Position : Supporting documents/reports are awaited)

2) Machinery Breakdown

a) Claim No.: MB/CL/10011/2013 Date of Loss: 04/11/2013 Without any apparent external forces and without any warning, heavy vibration and sounds occurred from within cement mill at Plant 2. Extensive damage was noticed to Gear Box (Present Position : Further reports/supporting documents in this respect are awaited)

9

b) Claim No.: MB/CL/10018/2015 Date of Loss: 13/01/2015 Crack on base columns of Central Cone of the Silo which blocked the gate of the feed bin of Line 4 Raw Meal Silo as pieces of concrete got stuck in the gate opening (Present Position : Awaiting supporting documents/reports)

c) Claim No.: MB/CL/10019/2015 Date of Loss: 26/02/2015 Detachment of concrete in Clinker Silo of Line 4 (Present Position : Supporting documents/reports are awaited)

d) Claim No.: MB/CL/10020/2015 Date of Intimation: 08/03/2015 External Crack in Cement Silo 1 of Line 4 (Present Position : Supporting documents/reports are awaited)

e) Claim no : MB/1181/2014 Date of Loss : 15 November 2015 A further claim has arisen following the collapse of a SILO on 15 November 2015, being part of the calcined lime process with apparently no external operating mechanism. This claim is currently under investigations although preliminary findings would indicate that the corrosion due to the operating environment is not a key factor in the collapse.

BRIEF DESCRIPTION OF THE PRODUCTION PROCESSES

Site 1

The semi-dry process that is employed for all 3 production lines on the original

site is employed to produce either standard Portland or sulphate resistant

cement. The different variations depend on slightly different ratios in the pre-

mix. The basic ratios to manufacture clinker (the cement base) being

Limestone (75 – 80%), Clay (20 – 25%) and Iron Ore.

The process followed is an FLS process with plant supplied by Franco Tosi of

Italy and Bohlar in Germany.

The ingredients are ground together in the correct ratios until a fine powder is

created. The powder is then fed into a Nodulizer where it is mixed with water

to create granules of the constituent mix.

10

7 – The storage hoppers and mill for the raw materials

The granules in turn are fed into a gravity fed gas fired rotary kiln more than

100m in length where they are heated to 1,450 degrees centigrade, the

temperature required for clinker crystals to form.

8 – 9 – Views of the rotary kiln

The crystals are then fed into a cooler where they are quenched with cool air

to 800degrees centigrade before being fed into a clinker store.

The clinker is then ground in one of two mills together with Gypsum to form

the Portland cement which is the either bagged into 50kg bags or bulk loaded

for their customers.

11

There are numerous samples taken throughout the production process to

ensure consistency of product. These are taken at the limestone quarry, at the

raw materials mill, after the cooler, after the mill and as well as at the

dispatch.

10 – The laboratory on the old site where the sample quality is tested

The calcined lime production process is also a heat process where lime is

heated in a rotary kiln, crushed and fed into a bulk load silo for bulk loading

into trucks.

Site 2

The newer plant follows a dry process using the 3 kilns and cyclone towers.

Limestone, clay, and iron ore are loaded from the sheds into a grinder in the

correct ratios and then the ensuing mixture is fed into a raw mill store.

The milled product is then fed into a 5 stage pre-heater (cyclone) tower where

it is preheated to 850 degrees centigrade before being fed into a shorter gas

fired rotating kiln to be heated to 1,450 degrees centigrade .

12

11 – 12 – The Raw Material Hoppers and Mill Surface

13 – View of the cyclone towers

At the end of the kiln the same air cooling process is followed to reduce the

temperature of the clinker to 800 degrees centigrade before being stored in a

clinker silo. The clinker is then ground with Gypsum to create the finished

cement product.

14 – 15 – View of the shorter rotary kiln and cooler

13

We understand that the plant has a storage capacity of 80,000 tons of cement

in their silos while up to 1,000,000 tons of clinker can be stock piled.

The finished product is the bagged or bulkloaded for distribution.

16 – Bulk loading point at the base of the storage silos

The processes are entirely automated and controlled from a dedicated control

room on site.

The new calcium carbonate line is a relatively simple process where limestone

is crushed in two crushers before storage and distribution.

Sand Processing Plant

The sand process is more simplified and starts with the delivery of sand which

is supplied by a third-party firm under a pre-negotiated contract.

14

The sand is the sifted to remove any oversized particles larger than 5mm. The

sand is then washed with water to remove silt and powder to finish the sand

which is then stockpiled to be loaded onto customer’s trucks and weighed on

a weighbridge for dispatch.

The process water is then recycled and fed back into the process.

ASSETS

We have received the attached financial statements which have summarised

the assets at cost as follows :

Description Total

Plant & Equipment QAR 2,437,149,147

Building QAR 546,429,339

Vehicles QAR 118,945,988

Furniture QAR 24,594,334

QAR 3,127,118,808

We have noted that the policy has a reinstatement value condition and

therefore care should be taken when fixing the Sum Insured to reflect price

increase from the original cost of the plant which lines were initially built a

considerable time ago.

MAINTENANCE

The plant operations are co-ordinated by Head of Production, Muhammed

Salim Choudery, who has more than 35 years experience with plants in

Pakistan and Saudi Arabia. He is assisted by Production Manager, Mohammed

El-Shafeey Yousief, who has been working at the plant for 8 months although

has 28 years experience with cement plants.

15

The maintenance of the Insured’s plant is undertaken by their own in-house

technical team in consultation with the guidelines of the suppliers of the

equipment and at recommended intervals.

Although the plant operates on a 24 hr basis the scheduled downtime for the

plant to undertake maintenance works was 505 days in 2015 including the

following major maintenance jobs :

- Plant 2 - Line 2 – Twin Cyclone Complete Erection and Refractory Lining

- Plant 2 – Line 2 - Pre-Calciner – All Refractory Work

- Plant 2 – Line 2- Tertiary Air Duct Refractory work

- Plant 2 – Line 3 – Pre-Calciner – All Refractory Work

- Plant 2 – Line 3 – Rising Duct Refractory Works

Further to the above the Insured have submitted the attached logs of

scheduled and unscheduled breakdowns for the various lines over the periods

2012 – 2014. The logs show the following total days shutdown against

planned maintenance :

2012 – Total 251 days – Planned 119 days

2013 – Total 262 days – Planned 121 days

2014 – Total 331 days – Planned 139 days

CRITICAL POINTS

As indicated the core business of the Insured is the production of klinker and

cement from basic raw materials with the key input components being

16

limestone, iron ore, gypsum and limestone fueled by gas and supported by

electrical systems.

The production process is fully integrated with raw material grinding, heating

of the klinker mix cooling and grinding of the end product in an automated

system. The system legs are interconnected through a network of conveyors

and bucket elevators which is centrally controlled and monitored by complex

IT systems. While the majority of the machinery, including the conveyors, fans

and other rotating machinery including the mills and kilns is driven by

electrically powered motors we consider that the most sensitive spares are

the computer system and large capacity motors.

The plants operate 24 hrs per day at approximately 85% capacity. There is

therefore some excess capacity that can be taken up in the event of the failure

of one of the lines.

Most of the key inputs for the klinker mix including gypsum, limestone and

clay are sourced locally so a shortage should not be an issue. The Iron ore

however is imported from sources in India and China although at any one time

a 6 month supply is stockpiled.

A 12 month supply of consumable spares is kept in the stores while a supply of

strategic key spares is also kept to minimize downtime in the event of failure.

The Insured acknowledges that some of the larger key components including

the reducer and main kiln drive can take up to 18 months to replace.

PHYSICAL HAZARDS

A) Site operations

17

A number of the Insured’s processes carry inherent loss exposures which we

highlight for your consideration.

The Integration of the Insured‘s cement production processes is facilitated by

large scale motors which are powered through independent substations.

These have an inherent risk of malfunction and electrical burnout. Each line

has 4 substations powering the major functions while there are 3 substations

for the cement mills.

The management and monitoring of the systems is co-ordinated by

sophisticated computer systems in a central command centre. The systems

are protected by UPS while 2 persons monitor each line at any one time.

17 – 18 – View inside the control room

The Kilns are heated by a piped gas supply that comes with Inherrent risks of

explosion, an occurrence that has previously taken place. As mentioned we

understand that state of the art monitoring systems have been installed to

prevent a recurrence of the previous explosion.

The Insured operate a laboratory on site with stored chemical products which

has been duly licensed by the Qatar Civil Defence as aprt of the nature of their

business.

18

The administrative offices house the non-critical administration functions and

are subject to the normal risks associated with offices while the housing

estate properties would be subject to the standard domestic risks.

Turning to the sandprocessing plant the motorized feeder buckets would be

subject to possible damage to the motors. Only one of the two plant lines is

active at present so in the event of a failure the second production line could

be promptly commissioned.

B) Services

1. Electrical load – The electrical supply to the building sections is

supplied by Karahmaa. There are two feeds to the main plant so

that in the event of a failure of one feed the power supply will be

uninterrupted. The power to the control centre also has two feeds

through two 15kva UPS connected in parallel. The main power

source is 415V 3 phase with generator backup as well as a further 6

hours by battery.

2. Steam – There is no steam requirement in this process.

3. Gas – The gas is piped in directly from Qatar Petroleum thorugh a

1m diameter pipe. The gas is fed through a special gas station which

regulates the feed to the kilns.

4. Air Conditioning – There are number of wall units and chiller banks

providing cooling for the office and control centre of the facility.

5. Personnel – The Insured’s personnel on the plant are well drilled in

the event of emergency.

6. Security – The site security is contracted to an independent security

firm sand at the time of meeting with the Insured they were inviting

19

tenders. The perimeter protections of the sites comprise 8 ft wire

mesh fences with gated access regulated by two security guards.

7. Maintenance - The maintenance of the premises is under the span

of control of the Insured’s engineering team although external

parties are contracted in as required

FIRE PROTECTION MEASURES

The fire protection system in the offices and control centre comprises smoke

alarms, hose reels and portable fire extinguishers which were apparent at the

time of our initial attendance.

19 – Fire Fighting Equipment inside the administration offices

There is a strict non-smoking policy across the facility with a designated

smoking zone outside the premises away from the buildings

The Insured have a maintenance contract with M/s Chubb to maintain the fire

protection systems.

The Insured are in discussions with the Civil Defence authority with a view to

upgrading their current systems and we have not been advised of any timeline

in this regard.

20

The nearest Civil Defence fire station is located approximately 1km from their

main offices and their reaction time in the event of an incident at the cement

plant would not be expected to exceed 5 to 10 minutes.

We understand that the water pressure to the site is boosted by fire

suppression pumps with a capacity of 100 cubic meters per hour with 90m of

head operating at 8 bar.

HOUSEKEEPING

The housekeeping arrangements are managed internally by the Insured and

we did not notice any obvious cause for concern at the time of our inspection.

The plants are located in the open desert however and is therefore a

naturally dusty environment.

SECURITY MEASURES

The sites are encircled with 8 ft wire mesh fencing with the entry points

having guard stations which are manned by two security guards on a 24hr

basis.

20 – 21 – Guard station and wire mesh perimeter fencing

21

The Insured also have a cashier’s desk in their offices who looks after wages

and makes substantial cash payments to the workers weekly. No extra

protection measures are adopted although the plant is remote and the

likelihood of a robbery is considered remote.

RISK EXPOSURES

Fire

Fire and/or explosion is the most likely threat of damage to the premises due

to the nature of the processes, plant as well as the control systems.

The design and implementation of the fire protection and extinguishment

systems should be of a high calibre although as we have not seen the full fire

plan we cannot provide comment on the knock on effect of a conflagration in,

say, the command centre. It is however possible that a localized fire within

the centre could have a knock on effect and result in smoke damage affecting

the equipment within.

The electrical distribution system is protected by a UPS and circuit breakers

and this should result in the detection and isolation of any electronic

equipment that is faulty before a malfunction occurs.

Explosion

The gas fired kilns pose significant risk of explosion due to possible build-up of

explosive gases in the event of a leak or malfunction.

22

In addition the presence of Carbon Monoxide which can build up and combine

with oxygen to form a potentially spontaneous explosion by the exothermic

reaction produced by hot gases from the kiln mixing with air. Such an

explosion can cause serious damage to the plant lines.

Although we are not aware of the specific controls in place these should

include monitors which measure the levels of Carbon Monoxide, Oxygen and

Oxides of Nitrogen to shut down the fire kiln in the event of a build-up of

Carbon Monoxide.

Storm

Qatar is located on a peninsula projecting into the Arabian Gulf and serviced

by sub-tropical weather systems. Rainfall is low with an annual average of

approximately 75mm mostly falling in the Winter when sudden electrical

storms are known to develop.

We would expect the plant design to be able to respond to any challenges

posed by the normal and seasonal peak weather conditions.

Earthquake / Volcanism

Doha is located within a seismically stable zone with no major events recorded

over the last century and the risk of damage caused by this peril is regarded as

low.

23

Theft / Robbery

The 24 hour security measures should ensure that security is maintained at a

high level while the current climate in Qatar in secure and the crime statistics

are very low in comparison to other countries.

Impact with motor vehicles

The plant is set back far away from the main Um Bab Road and poses no

discernable risk.

There are however trucks and other vehicles moving on the site although any

related damage caused by an impact would be minimal.

Impact with falling debris

The building has been erected off the direct flight path of the existing Doha

International Airport and the likelihood of related damage should be remote.

Machinery Breakdown

The plant equipment has been sourced through reputable Cement plant

suppliers and requires minimal workers to operate the systems. We are

informed that critical component spares are readily available and trained

technicians are employed to minimize downtime.

In case of a breakdown of a component where spares are not to hand these

should be able to be sourced from the suppliers.

24

The proposer has a well trained maintenance team which carries out

comprehensive preventative maintenance as well as a breakdown system

which properly logs breakdowns.

It is a known factor that an element of corrosion risk is present due to the

nature of the plant being exposed to the elements for a considerable time.

Business Interruption / Loss of Profit

There are several factors which should ensure that even after a major event,

the consequential profit losses suffered by the organization should be

manageable.

The plant has been supplied by reputable suppliers and spares components

should be available.

The plant has multiple lines which are not run at 100% capacity and if a line is

lost the other lines would be able to increase their output in the short term.

Materials have been stockpiled and the primary output component, clinker,

can be imported separately and ground with gypsum to make cement and

maintain the Insured’s customers in the short term.

We have requested that the proposer forward a copy of their Business

Continuity Plan so that we can gauge their preparedness in the event of an

incident. This has however not been presented.

25

VALUE AT RISK

The proposer presently have two policies in force for the year ending 31

December 2015.

Under their Property All Risks Policy the plant is insured for a total of QAR

3,370,600,000 against a 12 month Gross Profit Sum Insured of QR

693,000,000.

The second Machinery Breakdown policy on the other hand QAR

2,043,400,000 against a 12 month Gross Profit Sum Insured of QAR

685,000,000.

We have not received a breakdown as to what asset falls under which policy

to date.

When comparing the above combined totals to the asset register summary

total of QAR 3,127,118,808 there would appear to be an allowance for

increased cost of the plant from cost although, considering the age of the

plant without a detailed line by line costs analysis we care not in a position to

provide further comment.

The Gross Profit Sum Insured would appear to be in line with the financial

performance based on the 2014 financial statements.

26

MAXIMUM PROBABLE LOSS (MPL)

We suggest that the following Maximum Probable Loss amounts against the

related sums insured should be allocated:

Fire : 10%

Water Damage : 5%

Explosion : 10%

Flood / Weather : 5%

Earthquake : 50% (very low risk)

Impact with vehicle : 1%

Theft : 1%

Impact with aircraft : 50% (very low risk)

Business Interruption

Machinery Breakdown

Business Interruption

: 20% over a 12 month

period

: 10%

: 40%

CONCLUSION

The above mentioned is submitted for your consideration and should allow

your considered opinion as to the degree and acceptance of the proposed

risk.

If any further detail is required please let us know and we will gladly

accommodate.

27

DISCLAIMER:

This report is issued without prejudice and is based on the physical

inspection carried out in the subject premises and the material information

provided by the Proposer. Our company or attending surveyors are not

responsible for any error or discrepancy in the report due to

misrepresentation by the Proposer at the time of our inspection.

Carl Roberts Senior Adjuster

BCOM, FILA(SA), FIFAA, MIRMSA, M.Inst.D

Regional Head of Business Interruption

Claims

Major & Complex Loss - Middle East

Office 12, Third Floor, Al Reem Tower, P.O.Box 19462

West Bay – State of Qatar

T +974 4006 8949| M +974 6686 7671 E [email protected] W cl-mcl.com

Cunningham Lindsey International | cunninghamlindsey.com


Recommended