Date post: | 04-Jan-2016 |
Category: |
Documents |
Upload: | colin-schwartz |
View: | 49 times |
Download: | 0 times |
QRL kick-off meetingQRL kick-off meeting
Presentation of Presentation of the cryogenic extensions the cryogenic extensions
for the QRL projectfor the QRL project
A. Bouillot - AT/ACR20.10.2005
A. Bouillot, AT/ACR-cd, 2005.10.202
Content
• Introduction» Type, location and numbers
• Activities supplied by Air Liquide » Components, external supports, interconnections, …
• Documentation and drawings• Engineering design
» Main issues and status (external supports and cryogenic extensions elements)
• Fabrication» Main issues and status (external supports, cryogenic
extensions elements, conditioning and tests)• Installation
» Main issues and status (external supports, transport, positioning and adjustment of the elements, leak tests, …)
• Schedule and planning
A. Bouillot, AT/ACR-cd, 2005.10.203
Introduction
• A cryogenic extension allows to link the QRL jumpers to different clients (DFBA, DFBL, Q6, ACS).
• The diameter of the cryogenic extensions is 355.6 mm QRLDF
DFBA
Y - distance from IP 1
Y Y
X
magnet cryostat axis
X0º
A. Bouillot, AT/ACR-cd, 2005.10.204
Introduction
• They are composed of several interconnection pipes (between 4 and 9 pipes) with different internal diameters (from 10 mm to 80 mm)
Interface of the cryogenic extension element QRLXD (sector 8-1)
Interface of the cryogenic extension element QRLXE (sector 8-1)
A. Bouillot, AT/ACR-cd, 2005.10.205
Introduction • Type, number and location
• Different designs :» Straight elements about 3m with diameter 355 mm» Elbow elements about 2.5x2.5 m2 each» Weight : ~ 80 kg/m
Sector Cavern Connected to Position Name Number of elements Pipes/interconnection
RH87 Q6 LSS 8R QRLXD 1 9
RR13 DFBL LSS 1L QRLXE 4 4
RUX45 et RB46 ACS LSS 4R QRLXF 1 6
RR53 DFBL LSS 5L QRLXG 4 4
3-4 RUX45 et RB44 ACS LSS 4L QRLXH 1 6
5-6 RR57 DFBL LSS 5R QRLXI 4 4
RA34 Q6 LSS 3L QRLXA 2 9
RA27 Q6 LSS 2R QRLXC 1 9
RR17 DFBL LSS 1R QRLXJ 4 4
RH23 DFBA LSS 2L QRLXK 2 6
RH23 Q6 LSS 2L QRLXL 1 9
2-3
1-2
8-1
4-5
A. Bouillot, AT/ACR-cd, 2005.10.206
Activities supplied by Air Liquide
• External supports» Design » Procurement» Transport to CERN
• Elements :» Design, fabrication, conditioning» Transport to CERN
• Interconnections» Design» Procurement of the different components:
vacuum jackets, MLI
A. Bouillot, AT/ACR-cd, 2005.10.207
Documentation
• Drawings associated with each cryogenic extension
• All Drawings are available on the AT/ACR-cd server :» \Srv2_div\CRYO\ACR-CD\Projects\QRL\Drawings\Plans TIF-PDF AL\cryo extensions\
Sector Name Pipe Element ElementsExternal envelop
ExternalSupports
SupportsCERN
drawings
QRLXD C1105J030-A5 — C1105Q515-A6 C1105S379-A2C1105S285-A3C1105S286-A2
LHCLJ8GQ0014-1st
QRLXE C1105J031-A7
C1105J085-A4C1105J086-A4C1105J087-A4C1105J088-A4
C1105Q510-A6 C1105S380-A1C1105S381-A1C1105S382-A1
LHCLJ1GQ0017-1st
QRLXF C1105J050-A2 C1105S555-A1C1105S541-A1C1105S542-A1 C1105S562-A1
LHCLJ4GQ0004-AB
QRLXG C1105J164-A3 C1105Q664-A2 C1105S565-A2C1105S563-A1C1105S564-A1
LHCLJ5GQ0012-AA
3-4 QRLXH C1105J052 Missing LHCLJ4GQ0006-1st
5-6 QRLXI C1105J053 Missing LHCLJ5GQ0010-1st
QRLXA C1105J011-A6 C1105J012-A3 Missing LHCLJ3GQ0004-1st
QRLXC C1105J029-A4 Missing LHCLJ_2U0008-1st
QRLXJ C1105J054 Missing LHCLJ1GQ0020-1st
QRLXK C1105J089 Missing LHCLJ2GQ0013-1st
QRLXL C1105J090 Missing LHCLJ2GQ0012-1st
1-2
8-1
4-5
2-3
A. Bouillot, AT/ACR-cd, 2005.10.208
Engineering design
• Straight and elbow pipes are in Invar material• The extremities of each interconnection pipes are
equipped with Stainless Steel sleeves• Most of cryogenic extensions have no active thermal
shield. Each interconnection pipe is equipped with MLI. Only cryogenic extensions QRLXF and QRLXH (linking ACS) have active thermal shield.
• The vacuum jacket is in Stainless Steel.• The number of elements composing one cryogenic
extension can vary from 1 to 4 elements.• Interconnection pipes are supported inside the vacuum
jacket with spacers• The thermal losses per meter is around equal to ~ 1.5
W/m.• External interconnections are made with rigid sleeves.• Horizontal cardan compensator on QQS jumper side.• Flexible hoses are added on Q6 and DFBA side for the
cryogenic extensions QRLXD, QRLXA, QRLXC, QRLXK and QRLXL.
A. Bouillot, AT/ACR-cd, 2005.10.209
Engineering design
• Status
Sector Element TypeDiameter
[mm]Length[mm]
ConceptionMechanicalValidation
[%]
ThermalValidation
[%]
Drawings[%]
QRLXDCryogenic extension
355.6 10035Drawings folder finished
Calculation note : C1105NT166100%
QRLXECryogenic extension
355.6 4838Drawings folder finished
Calculation note : C1105NT161100%
QRLXFCryogenic extension
355,6 13155Drawings folder finished
Mechanical Calculation note : C1105NT190Thermal Calculation note : C1105NT169
100%[AL]
NT169100%
QRLXGCryogenic extension
355,6 8512Drawings folder finished
Calculation note : C1105NT191100%NT074
100%
3-4 QRLXHCryogenic extension
355,6Drawings folder under approvalCalculation note : C1105NT207
100%100%[AL]
NT16990%
5-6 QRLXICryogenic extension
355,6 10837Under approval
Calculation note under approval0% 0% 90%
QRLXACryogenic extension
355,6 22252 To be defined 0% 0% 0%
QRLXCCryogenic extension
355,6 4267 To be defined 0% 0% 0%
QRLXJCryogenic extension
355,6 12000 To be defined 0% 0% 0%
QRLXKCryogenic extension
355,6 10000 To be defined 0% 0% 0%
QRLXLCryogenic extension
355,6 12000 To be defined 0% 0% 0%
1-2
2-3
Status
4-5
8-1100%NT161NT166
100%[AL]
NT074
100%NT190NT191
A. Bouillot, AT/ACR-cd, 2005.10.2010
Fabrication
• Main issues» The fabrication takes place at DTA (Air Liquide-
Sassenage).» Each interconnection pipe (Invar) is He tested after the
prefabrication.» The possible weld interfaces can be :
• Stainless Steel / Invar• Invar / Invar
» Each weld is X-rayed (norm EN 25817-Class B) and have associated qualifications
» Each cryogenic extension undergoes the following tests :
• Pressure test• He test• Cold test
A. Bouillot, AT/ACR-cd, 2005.10.2011
Fabrication
• QRLXE Cryogenic extension
HCQRLXE100-AL000001
Element HCQRLXE101-AL000001
Element HCQRLXE102-AL000001
Element HCQRLXE103-AL000001
Element HCQRLXE104-AL000001
A. Bouillot, AT/ACR-cd, 2005.10.2012
Fabrication
• QRLXD
Cryogenic extension
HCQRLXD100-AL000001
A. Bouillot, AT/ACR-cd, 2005.10.2013
Fabrication
• Status» HCQRLXE100-AL000001 85%
• 3 elements (HCQRLXE101-AL000001, HCQRLXE102-AL000001, HCQRLXE103-AL000001) are already fabricated (succeed in the cold test)
• HCQRLXE104-AL000001 is prepared for the tests
» HCQRLXD100-AL000001 70%• HCQRLXD100-AL000001 is under fabrication
(installation of the vacuum jacket)
» Others 0%
A. Bouillot, AT/ACR-cd, 2005.10.2014
Fabrication
• Cryogenic extension QRLXE
Element
HCQRLXE103-AL000001
Element
HCQRLXE101-AL000001
A. Bouillot, AT/ACR-cd, 2005.10.2015
Fabrication
• Cryogenic extension QRLXE
Element HCQRLXE103-AL000001
Element HCQRLXE102-AL000001
Element HCQRLXE101-AL000001
A. Bouillot, AT/ACR-cd, 2005.10.2016
Fabrication
• Cryogenic extension QRLXD
Element HCQRLXD100-AL000001
A. Bouillot, AT/ACR-cd, 2005.10.2017
Fabrication
• Conditionnement» Double housse thermo soudable» Mise en place de l'élément dans la première
housse» Soudage de la housse» Avant fermeture de celle ci balayage azote
(mesure hygrométrie)» Mise sous vide de l'enveloppe (à l'aspirateur)» Fermeture de l'enveloppe» Scellement de la 2eme housse avec déshydratant» La 2eme housse sera réalisée avec un complexe
épais et résistant» L'ensemble conditionné sous housse est posé sur
un plateau de type habituel.
A. Bouillot, AT/ACR-cd, 2005.10.2018
Installation
• External supports for HCQRLXD100-AL000001:
Supports C1105S285
Supports C1105S286
A. Bouillot, AT/ACR-cd, 2005.10.2019
Installation
• External supports C1105S286:
A. Bouillot, AT/ACR-cd, 2005.10.2020
Installation
• External supports C1105S285:
A. Bouillot, AT/ACR-cd, 2005.10.2021
Installation
• External supports for HCQRLXE100-AL000001:
Support C1105S381
Support C1105S382
A. Bouillot, AT/ACR-cd, 2005.10.2022
Installation
• External supports C1105S381:
A. Bouillot, AT/ACR-cd, 2005.10.2023
Installation
• External supports C1105S382:
A. Bouillot, AT/ACR-cd, 2005.10.2024
Installation
• Activities supplied by CERN» Handling» Transport CERN/tunnel with dedicated tooling» Positioning and adjustment» Interconnections :
• welding : same interface type as standard jumper connection (+ leak tests associated)
• Installation of rings and sleeves :– D < 30 mm rings– D ≥ 30 mm sleeves
• MLI : 30 layers on each interconnection pipe• Welding of external rigid sleeve
A. Bouillot, AT/ACR-cd, 2005.10.2025
Installation
• Activities supplied by CERN» Interconnections :
Rings for diameter pipes 10/12 mm
Sleeves
A. Bouillot, AT/ACR-cd, 2005.10.2026
Schedule and planning
• Planning (supplied by R. Girardot on 19.10.2005)Semaines 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
LSS 8R XDLSS 1L XELSS 4R XFLSS 5L XG
3-4 LSS 4L XH5-6 LSS 5R XI
LSS 3L XALSS 2R XCLSS 1R XJLSS 2L XKLSS 2L XL
mai-06 juin-06
2-3
1-2
janv.-06
8-1
févr.-06 mars-06 avr.-06
4-5
Semaines 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 48 49 50 51 48 49 50 51
LSS 8R XDLSS 1L XELSS 4R XFLSS 5L XG
3-4 LSS 4L XH5-6 LSS 5R XI
LSS 3L XALSS 2R XCLSS 1R XJLSS 2L XKLSS 2L XL
déc.-06 janv.-07 févr.-07juil.-06 août-06 sept.-06 oct.-06 nov.-06
2-3
1-2
8-1
4-5
installation cryogenic extensionsmagnets end installation
A. Bouillot, AT/ACR-cd, 2005.10.2027
Cryogenic extensions project
• Link person for AT/ACR : A. Bouillot• Link person for other activities : to be defined• Periodic meetings : every two weeks ???• Proposed subject for next meeting: finalization
of organization