+ All Categories
Home > Documents > QRL kick-off meeting Presentation of the cryogenic extensions for the QRL project

QRL kick-off meeting Presentation of the cryogenic extensions for the QRL project

Date post: 04-Jan-2016
Category:
Upload: colin-schwartz
View: 49 times
Download: 0 times
Share this document with a friend
Description:
QRL kick-off meeting Presentation of the cryogenic extensions for the QRL project. A. Bouillot - AT/ACR 20.10.2005. Content. Introduction Type, location and numbers Activities supplied by Air Liquide Components, external supports, interconnections, … Documentation and drawings - PowerPoint PPT Presentation
Popular Tags:
27
QRL kick-off meeting QRL kick-off meeting Presentation of Presentation of the cryogenic extensions the cryogenic extensions for the QRL project for the QRL project A. Bouillot - AT/ACR 20.10.2005
Transcript
Page 1: QRL kick-off meeting Presentation of  the cryogenic extensions  for the QRL project

QRL kick-off meetingQRL kick-off meeting

Presentation of Presentation of the cryogenic extensions the cryogenic extensions

for the QRL projectfor the QRL project

A. Bouillot - AT/ACR20.10.2005

Page 2: QRL kick-off meeting Presentation of  the cryogenic extensions  for the QRL project

A. Bouillot, AT/ACR-cd, 2005.10.202

Content

• Introduction» Type, location and numbers

• Activities supplied by Air Liquide » Components, external supports, interconnections, …

• Documentation and drawings• Engineering design

» Main issues and status (external supports and cryogenic extensions elements)

• Fabrication» Main issues and status (external supports, cryogenic

extensions elements, conditioning and tests)• Installation

» Main issues and status (external supports, transport, positioning and adjustment of the elements, leak tests, …)

• Schedule and planning

Page 3: QRL kick-off meeting Presentation of  the cryogenic extensions  for the QRL project

A. Bouillot, AT/ACR-cd, 2005.10.203

Introduction

• A cryogenic extension allows to link the QRL jumpers to different clients (DFBA, DFBL, Q6, ACS).

• The diameter of the cryogenic extensions is 355.6 mm QRLDF

DFBA

Y - distance from IP 1

Y Y

X

magnet cryostat axis

X0º

Page 4: QRL kick-off meeting Presentation of  the cryogenic extensions  for the QRL project

A. Bouillot, AT/ACR-cd, 2005.10.204

Introduction

• They are composed of several interconnection pipes (between 4 and 9 pipes) with different internal diameters (from 10 mm to 80 mm)

Interface of the cryogenic extension element QRLXD (sector 8-1)

Interface of the cryogenic extension element QRLXE (sector 8-1)

Page 5: QRL kick-off meeting Presentation of  the cryogenic extensions  for the QRL project

A. Bouillot, AT/ACR-cd, 2005.10.205

Introduction • Type, number and location

• Different designs :» Straight elements about 3m with diameter 355 mm» Elbow elements about 2.5x2.5 m2 each» Weight : ~ 80 kg/m

Sector Cavern Connected to Position Name Number of elements Pipes/interconnection

RH87 Q6 LSS 8R QRLXD 1 9

RR13 DFBL LSS 1L QRLXE 4 4

RUX45 et RB46 ACS LSS 4R QRLXF 1 6

RR53 DFBL LSS 5L QRLXG 4 4

3-4 RUX45 et RB44 ACS LSS 4L QRLXH 1 6

5-6 RR57 DFBL LSS 5R QRLXI 4 4

RA34 Q6 LSS 3L QRLXA 2 9

RA27 Q6 LSS 2R QRLXC 1 9

RR17 DFBL LSS 1R QRLXJ 4 4

RH23 DFBA LSS 2L QRLXK 2 6

RH23 Q6 LSS 2L QRLXL 1 9

2-3

1-2

8-1

4-5

Page 6: QRL kick-off meeting Presentation of  the cryogenic extensions  for the QRL project

A. Bouillot, AT/ACR-cd, 2005.10.206

Activities supplied by Air Liquide

• External supports» Design » Procurement» Transport to CERN

• Elements :» Design, fabrication, conditioning» Transport to CERN

• Interconnections» Design» Procurement of the different components:

vacuum jackets, MLI

Page 7: QRL kick-off meeting Presentation of  the cryogenic extensions  for the QRL project

A. Bouillot, AT/ACR-cd, 2005.10.207

Documentation

• Drawings associated with each cryogenic extension

• All Drawings are available on the AT/ACR-cd server :» \Srv2_div\CRYO\ACR-CD\Projects\QRL\Drawings\Plans TIF-PDF AL\cryo extensions\

Sector Name Pipe Element ElementsExternal envelop

ExternalSupports

SupportsCERN

drawings

QRLXD C1105J030-A5 — C1105Q515-A6 C1105S379-A2C1105S285-A3C1105S286-A2

LHCLJ8GQ0014-1st

QRLXE C1105J031-A7

C1105J085-A4C1105J086-A4C1105J087-A4C1105J088-A4

C1105Q510-A6 C1105S380-A1C1105S381-A1C1105S382-A1

LHCLJ1GQ0017-1st

QRLXF C1105J050-A2 C1105S555-A1C1105S541-A1C1105S542-A1 C1105S562-A1

LHCLJ4GQ0004-AB

QRLXG C1105J164-A3 C1105Q664-A2 C1105S565-A2C1105S563-A1C1105S564-A1

LHCLJ5GQ0012-AA

3-4 QRLXH C1105J052 Missing LHCLJ4GQ0006-1st

5-6 QRLXI C1105J053 Missing LHCLJ5GQ0010-1st

QRLXA C1105J011-A6 C1105J012-A3 Missing LHCLJ3GQ0004-1st

QRLXC C1105J029-A4 Missing LHCLJ_2U0008-1st

QRLXJ C1105J054 Missing LHCLJ1GQ0020-1st

QRLXK C1105J089 Missing LHCLJ2GQ0013-1st

QRLXL C1105J090 Missing LHCLJ2GQ0012-1st

1-2

8-1

4-5

2-3

Page 8: QRL kick-off meeting Presentation of  the cryogenic extensions  for the QRL project

A. Bouillot, AT/ACR-cd, 2005.10.208

Engineering design

• Straight and elbow pipes are in Invar material• The extremities of each interconnection pipes are

equipped with Stainless Steel sleeves• Most of cryogenic extensions have no active thermal

shield. Each interconnection pipe is equipped with MLI. Only cryogenic extensions QRLXF and QRLXH (linking ACS) have active thermal shield.

• The vacuum jacket is in Stainless Steel.• The number of elements composing one cryogenic

extension can vary from 1 to 4 elements.• Interconnection pipes are supported inside the vacuum

jacket with spacers• The thermal losses per meter is around equal to ~ 1.5

W/m.• External interconnections are made with rigid sleeves.• Horizontal cardan compensator on QQS jumper side.• Flexible hoses are added on Q6 and DFBA side for the

cryogenic extensions QRLXD, QRLXA, QRLXC, QRLXK and QRLXL.

Page 9: QRL kick-off meeting Presentation of  the cryogenic extensions  for the QRL project

A. Bouillot, AT/ACR-cd, 2005.10.209

Engineering design

• Status

Sector Element TypeDiameter

[mm]Length[mm]

ConceptionMechanicalValidation

[%]

ThermalValidation

[%]

Drawings[%]

QRLXDCryogenic extension

355.6 10035Drawings folder finished

Calculation note : C1105NT166100%

QRLXECryogenic extension

355.6 4838Drawings folder finished

Calculation note : C1105NT161100%

QRLXFCryogenic extension

355,6 13155Drawings folder finished

Mechanical Calculation note : C1105NT190Thermal Calculation note : C1105NT169

100%[AL]

NT169100%

QRLXGCryogenic extension

355,6 8512Drawings folder finished

Calculation note : C1105NT191100%NT074

100%

3-4 QRLXHCryogenic extension

355,6Drawings folder under approvalCalculation note : C1105NT207

100%100%[AL]

NT16990%

5-6 QRLXICryogenic extension

355,6 10837Under approval

Calculation note under approval0% 0% 90%

QRLXACryogenic extension

355,6 22252 To be defined 0% 0% 0%

QRLXCCryogenic extension

355,6 4267 To be defined 0% 0% 0%

QRLXJCryogenic extension

355,6 12000 To be defined 0% 0% 0%

QRLXKCryogenic extension

355,6 10000 To be defined 0% 0% 0%

QRLXLCryogenic extension

355,6 12000 To be defined 0% 0% 0%

1-2

2-3

Status

4-5

8-1100%NT161NT166

100%[AL]

NT074

100%NT190NT191

Page 10: QRL kick-off meeting Presentation of  the cryogenic extensions  for the QRL project

A. Bouillot, AT/ACR-cd, 2005.10.2010

Fabrication

• Main issues» The fabrication takes place at DTA (Air Liquide-

Sassenage).» Each interconnection pipe (Invar) is He tested after the

prefabrication.» The possible weld interfaces can be :

• Stainless Steel / Invar• Invar / Invar

» Each weld is X-rayed (norm EN 25817-Class B) and have associated qualifications

» Each cryogenic extension undergoes the following tests :

• Pressure test• He test• Cold test

Page 11: QRL kick-off meeting Presentation of  the cryogenic extensions  for the QRL project

A. Bouillot, AT/ACR-cd, 2005.10.2011

Fabrication

• QRLXE Cryogenic extension

HCQRLXE100-AL000001

Element HCQRLXE101-AL000001

Element HCQRLXE102-AL000001

Element HCQRLXE103-AL000001

Element HCQRLXE104-AL000001

Page 12: QRL kick-off meeting Presentation of  the cryogenic extensions  for the QRL project

A. Bouillot, AT/ACR-cd, 2005.10.2012

Fabrication

• QRLXD

Cryogenic extension

HCQRLXD100-AL000001

Page 13: QRL kick-off meeting Presentation of  the cryogenic extensions  for the QRL project

A. Bouillot, AT/ACR-cd, 2005.10.2013

Fabrication

• Status» HCQRLXE100-AL000001 85%

• 3 elements (HCQRLXE101-AL000001, HCQRLXE102-AL000001, HCQRLXE103-AL000001) are already fabricated (succeed in the cold test)

• HCQRLXE104-AL000001 is prepared for the tests

» HCQRLXD100-AL000001 70%• HCQRLXD100-AL000001 is under fabrication

(installation of the vacuum jacket)

» Others 0%

Page 14: QRL kick-off meeting Presentation of  the cryogenic extensions  for the QRL project

A. Bouillot, AT/ACR-cd, 2005.10.2014

Fabrication

• Cryogenic extension QRLXE

Element

HCQRLXE103-AL000001

Element

HCQRLXE101-AL000001

Page 15: QRL kick-off meeting Presentation of  the cryogenic extensions  for the QRL project

A. Bouillot, AT/ACR-cd, 2005.10.2015

Fabrication

• Cryogenic extension QRLXE

Element HCQRLXE103-AL000001

Element HCQRLXE102-AL000001

Element HCQRLXE101-AL000001

Page 16: QRL kick-off meeting Presentation of  the cryogenic extensions  for the QRL project

A. Bouillot, AT/ACR-cd, 2005.10.2016

Fabrication

• Cryogenic extension QRLXD

Element HCQRLXD100-AL000001

Page 17: QRL kick-off meeting Presentation of  the cryogenic extensions  for the QRL project

A. Bouillot, AT/ACR-cd, 2005.10.2017

Fabrication

• Conditionnement» Double housse thermo soudable» Mise en place de l'élément dans la première

housse» Soudage de la housse» Avant fermeture de celle ci balayage azote

(mesure hygrométrie)» Mise sous vide de l'enveloppe (à l'aspirateur)» Fermeture de l'enveloppe» Scellement de la 2eme housse avec déshydratant» La 2eme housse sera réalisée avec un complexe

épais et résistant» L'ensemble conditionné sous housse est posé sur

un plateau de type habituel.

Page 18: QRL kick-off meeting Presentation of  the cryogenic extensions  for the QRL project

A. Bouillot, AT/ACR-cd, 2005.10.2018

Installation

• External supports for HCQRLXD100-AL000001:

Supports C1105S285

Supports C1105S286

Page 19: QRL kick-off meeting Presentation of  the cryogenic extensions  for the QRL project

A. Bouillot, AT/ACR-cd, 2005.10.2019

Installation

• External supports C1105S286:

Page 20: QRL kick-off meeting Presentation of  the cryogenic extensions  for the QRL project

A. Bouillot, AT/ACR-cd, 2005.10.2020

Installation

• External supports C1105S285:

Page 21: QRL kick-off meeting Presentation of  the cryogenic extensions  for the QRL project

A. Bouillot, AT/ACR-cd, 2005.10.2021

Installation

• External supports for HCQRLXE100-AL000001:

Support C1105S381

Support C1105S382

Page 22: QRL kick-off meeting Presentation of  the cryogenic extensions  for the QRL project

A. Bouillot, AT/ACR-cd, 2005.10.2022

Installation

• External supports C1105S381:

Page 23: QRL kick-off meeting Presentation of  the cryogenic extensions  for the QRL project

A. Bouillot, AT/ACR-cd, 2005.10.2023

Installation

• External supports C1105S382:

Page 24: QRL kick-off meeting Presentation of  the cryogenic extensions  for the QRL project

A. Bouillot, AT/ACR-cd, 2005.10.2024

Installation

• Activities supplied by CERN» Handling» Transport CERN/tunnel with dedicated tooling» Positioning and adjustment» Interconnections :

• welding : same interface type as standard jumper connection (+ leak tests associated)

• Installation of rings and sleeves :– D < 30 mm rings– D ≥ 30 mm sleeves

• MLI : 30 layers on each interconnection pipe• Welding of external rigid sleeve

Page 25: QRL kick-off meeting Presentation of  the cryogenic extensions  for the QRL project

A. Bouillot, AT/ACR-cd, 2005.10.2025

Installation

• Activities supplied by CERN» Interconnections :

Rings for diameter pipes 10/12 mm

Sleeves

Page 26: QRL kick-off meeting Presentation of  the cryogenic extensions  for the QRL project

A. Bouillot, AT/ACR-cd, 2005.10.2026

Schedule and planning

• Planning (supplied by R. Girardot on 19.10.2005)Semaines 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26

LSS 8R XDLSS 1L XELSS 4R XFLSS 5L XG

3-4 LSS 4L XH5-6 LSS 5R XI

LSS 3L XALSS 2R XCLSS 1R XJLSS 2L XKLSS 2L XL

mai-06 juin-06

2-3

1-2

janv.-06

8-1

févr.-06 mars-06 avr.-06

4-5

Semaines 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 48 49 50 51 48 49 50 51

LSS 8R XDLSS 1L XELSS 4R XFLSS 5L XG

3-4 LSS 4L XH5-6 LSS 5R XI

LSS 3L XALSS 2R XCLSS 1R XJLSS 2L XKLSS 2L XL

déc.-06 janv.-07 févr.-07juil.-06 août-06 sept.-06 oct.-06 nov.-06

2-3

1-2

8-1

4-5

installation cryogenic extensionsmagnets end installation

Page 27: QRL kick-off meeting Presentation of  the cryogenic extensions  for the QRL project

A. Bouillot, AT/ACR-cd, 2005.10.2027

Cryogenic extensions project

• Link person for AT/ACR : A. Bouillot• Link person for other activities : to be defined• Periodic meetings : every two weeks ???• Proposed subject for next meeting: finalization

of organization


Recommended