+ All Categories
Home > Documents > Quadrupoles and orbit correctors bus bars routing along ...

Quadrupoles and orbit correctors bus bars routing along ...

Date post: 26-Jan-2022
Category:
Upload: others
View: 6 times
Download: 0 times
Share this document with a friend
22
Quadrupoles and orbit correctors bus bars routing along the inner triplet string MQXF Workshop at CERN– February the 3 rd 2016 H. Prin With acknowledgements to A. Ballarino, C. Scheuerlein, D. Ramos Duarte, J.-P. Tock and P. Fessia for their comments and contributions
Transcript

Quadrupoles and orbit correctors bus bars routing along the inner triplet string

MQXF Workshop at CERN– February the 3rd 2016H. Prin

With acknowledgements to A. Ballarino, C. Scheuerlein, D. Ramos Duarte, J.-P. Tock and P. Fessia for their comments and contributions

•Base line scheme

• Internal vs External routing - Pros and Cons

•Busbar vs cable - Pros and Cons

•Bus technology towards Routing

•Preliminary layout proposal

•Comparison with existing situation in the LHC DS

• Summary

2

Outline

Base line scheme

Orbit Correctors

Trim Q1

Trim Q2b

Q1 – Q3

CLIQ

Q2a-Q2b

Base line schemeOrbit Correctors

Trim Q1

Trim Q2b

Q1 – Q3

CLIQ

Q2a-Q2b

1

1

2

1

2

3

8

1

4

1

1

1

2

2

2

8

2

8

6

6

16

4

2

16

2 5 16 2 3 22

50

1

1

2

1

2

2

3

8

2

6

2

2

8

2

1

6

2

2

8

2

8

2

2

8

2

8

2 5 21 21 22 22

11 +5

9 +3

32 +16

9 +5

2

30 +14

+43

93

Spliced in the tunnelSpliced on surface

External bus bars Internal bus bars

Splice quantity > 80%

Short to ground on a circuit or electrical fault

Cable exchange between the DFX and concerned interconnect

Cryoassembly exchange

Possibility to alternate the impedances on themain circuit: Q2a and b on the return bus bar

Not really needed according

to Mr Circuit

Magnet exchange 3 to 5 ICs to open

Less splices to be redone

Or only affected buses

2 ICs to open

All splices to be

de-soldered/re-soldered

InterchangeabilityQ1Q3 and Q2AQ2B

Q1 and Q2a have to house all

circuit present in respectively Q3 and Q2b to allow

Cryogenic Scheme Plugs or restrictions

between the external line and the cold mass volume

Flexibility for cold test (Q1, Q3) on surface Possibility to test each MQXA

individually

Additional bus bar needed to

power each MQXA individually

Int./Ext. routing - Pros and Cons

(48 to 50) (87 to 93)

Busbar(stabilized Rutherford cable)

Round cable

Development & experience Strand and cable availability with low external

field Cable development and validation

Protection (current distribution)

Proven technology

Soldered stabilizer To be studied and proven

Fabrication place Cable availability if LHC cable retained

CERN in the busbar factory To be developed with industry

Integration stability

3D flexibility

Containment of electromagnetic forces to be

studied

InstallationPreferably during cold mass assembly

Cartridges could be envisaged Opportunity to be installed in the tunnel from

one connection point to the other

Expansion loops Well known (lyre profiles) but

integration volume (radial and longi)

Insulation To be settled according existing developments

Splices

To be developed

(existing experience on the 6kA circuits)

Preparation in case of reconnection (ALARA)

QA Process(Splices validation @warm) To be developed

6

Busbar vs Cable - Pros and Cons

++ Splices types and validation

+ Well known technology

- Longitudinal space for expansion loops

- Entire cold mass disassembly in case of bus bar problem (may be solved with cartridges?)

- More splices

- Surrounding field

-- Cryoassembly exchange in case of short

-- Ergonomic for splices and ALARA principle

++ Longitudinal space gain for the expansion loops playing with cable flexibility

+ Easier bus exchange in case of problem

- More splices

- Splices types and validation

++ Splices types and validation

+ self magnetic field

? Expansion loop integration

-- Installation

-- Rigidity

++ Less splices

++ Installation in the tunnel

++ Cable exchange in case of a short

? Magnet exchange

? Plugs or restrictions

- Splices types and validation

- Cable development

7

CableBusbarBus technology

Inte

rna

lEx

tern

al

Ro

uti

ng

Bus technology towards Routing

8

Orbit Correctors

Trim Q1

Trim Q2b

Q1 – Q3

CLIQ

Q2a-Q2b

Worst condition:(without considering cables for D1 and CP)

Free section 47.9 cm2

Ext. routing preliminary layout proposal

2

2/1/0

8

2/3

8

To be developed:

34 Nb-Ti strands Ø1.065 mmCu/Sc ratio = 1.6

34 Cu OFE strands Ø1.065 mm

Present LHC 6kA cable:13 Nb-Ti wires Ø0.87 mm

Cu/Sc ratio = 1.36 7 Cu wires Ø0.96 mm

Present LHC 1kA cable:1 Nb-Ti/Cu wires Ø1.6 mm

or34 Nb-Ti strands Ø1.065 mm

Cu Stabiliser equivalent cross section

9

Ext. routing preliminary layout proposal

Extracted from Delio’s talk on December the 3rd 2015

Preferred locations from the cold masspoint of view taking into accountinterconnections, standardization, sparepolicy and ergonomics :

1. bus bar line in the cryostat in the verticalsymmetry plane

2. bus bar entrance in the cold mass in thevertical symmetry plane on top

3. Heat exchangers on the bottomapertures of the magnets

Worst case btw Q2A-Q2BSection 2.53cm2

without insulation norEM forces restraints

or guiding pieces

Worst case btw Q3-DFXSection 5.37cm2

without insulation norEM forces restraints

or guiding pieces

10

Present situation in the LHC DS N-Line

See Procedures: LHC-QBBI-IP-0030, 31 and 32 used during LS1 for MB exchanges

Bus Bar line for the HL-LHC triplet(scaled)

Metallic hose to be avoided

11

Today

2016 2017

Decision

Validation

Procurement

Feasibility study 6 Months

10 MonthsPrice inquiry and Prototype cable production

3 MonthsTests

Procurement process 4 Months

Series production

Splices developments

Technical specification 1 Month

Steps for 18kA Nb-Ti cable development up to production

2018

QA Splices

According to discussions with A. Ballarino

• Up to 22 buses to be housed (only for the quads and the orbit correctors,CP and D1 to be added and integrated in between Q3 and DFX).

• Using an external routing saves up to 40% splices, simplify consolidationin case of short and simplify the standardization in between Q1-Q3 andQ2A-Q2B.

• Cable eases the expansion lyres design, integration and installation. It ismore appropriate to external routing. But it has to be developed as wellas the splices procedures and tooling (~2 years required).

• Copper stabiliser soldered to Rutherford cable bus bars is a verydeveloped and mastered technology both for production and splicesconnections. LHC cable could be used and is available. This design is notsuitable for long dimensions and require volume for the expansion loops.It does not seem to be very suitable for external routing.

12

Summary

13

Conclusions• Global integration work is going on taking into account environment

constraints and requirements (cryogenics, vacuum, beaminstrumentation…). Despite the last longitudinal increase of theinterconnection length it is not straightforward to design.

• An important part of the integration work is dedicated to the electrical busintegration taking into account the technology and the related constraints(splices quantity and types, ergonomics, ALARA principal…) as well as thebus installation.

• Orbit correctors, trims and CLIQ circuits can be routed externally usingexisting sc cables currently used in the LHC.

• For 18 kA circuits, the “busbars” solution shall be kept as base line until a“cable” type solution has been developed and validated. Internal routing isconsidered inside the cooling holes but an external solution is not excludedtoday, extensive integration work is ongoing. Situation has to be studied atthe level of the Corrector Package and the D1.

• The different intervention scenarios will considered to determine theintervention time and the shielding possibilities in order to support thedifferent choices.

14

Alternate scheme is a bit less consuming in terms of bus, current leads and splicesThe routing seems more adequate for internal routing.

Comments on alternative scheme

The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme 7 Capacities Specific Programme, Grant Agreement 284404.

Back-up slides

Alternative schemeOrbit Correctors

Trim Q1

Trim Q2b

Main Quads

CLIQ

1

1

2

1

2

1

8

1

4

1

1

1

1

2

2

8

3

8

1

7

16

6

2

16

1

10 +3

32 +16

12 +6

4 +2

28 +12

+39

Orbit Correctors

Trim Q1

Trim Q2b

Main Quads

CLIQ

2 5 14 3 3 21

18 20 21

48

87

1

1

2

1

2

2 5

2

8

2

2

4

2

8

3

1

6

2

8

3

8

2

8

3

8

21

Additional trim on Q3 or Q2A could be installed on the warm par without further bus bar

18

Magnetic Field in the MQXF cooling holes

Courtesy of Susana Izquierdo Bermudez

19

Courtesy of Francois Eymin

Piping integration – latest version

Present LHC SC cables specifications

21

Triplet flow diagram

22

Courtesy of Carlos Ortiz Ferrer

Entire scheme taking into account CP and D1


Recommended