+ All Categories
Home > Documents > Quality Assurance Plan_Manoranjan

Quality Assurance Plan_Manoranjan

Date post: 03-Jun-2018
Category:
Upload: sourav-maji
View: 217 times
Download: 0 times
Share this document with a friend

of 28

Transcript
  • 8/12/2019 Quality Assurance Plan_Manoranjan

    1/28

    Quality Assur ance Process

  • 8/12/2019 Quality Assurance Plan_Manoranjan

    2/28

    ontent

    1. Project Rollout Overview2. Purpose of Quality Management & Setting Quality Obj3. Purpose of Quality Plan

    3.1 Project KPI & Measurement Criteria4. Quality Organization Structure5. Key Roles & Responsibility6. Quality Resource Plan7. Six Key Points8. Quality Assurance Vs Quality Control9. Quality Assurance Activities10. Quality Control Activities

    . me nes o comp e e au ac v es10.2 Schedule of Project Quality Review10.3 Reports

    11. Document & Record Control12. Performance Ranking Criteria13. Penalty Clauses & WCC Signoff Timelines14. Subcon Management

    15. H&S Management & Monitoring15.1 Health & Safety with tools requirement

    > Internal Only

    ectives

    ZTE Corporation. All rights reserved.

  • 8/12/2019 Quality Assurance Plan_Manoranjan

    3/28

    urpose of Quality Management and Sett

    Quality management ensures that an organization, productplanning, quality control, quality assurance and quality improvemequality, but also the means to achieve it. Quality management theproducts to achieve more consistent quality.

    Quality is seven attributes : Portability, Reliability, Efficiency, Usability,

    Quality is conformance to requirements : Discuss, Confirm & Record t

    Quality is fitness to use.

    Core of Pro ect Qualit Mana ement is revention : Do the ri ht in first

    problem reoccurrence.The performance standard of project quality management is ZERO def

    Quality is an attitude (State of Mind)

    The measurement of quality is the Price Of Non Conformance (PONC) :things (i.e. rework/rectification , frequent up-gradation of system & tro

    > Internal Only

    ing Quality Objectives

    or service is consistent. It has four main components: qualityt. Quality management is focused not only on product and serviceefore uses quality assurance and control of processes as well as

    estability, Understandability & Modifiability.

    e customer requirement before the activity start.

    time & Conduct root cause anal sis kee in backtrackin to avoid

    ZTE Corporation. All rights reserved.

    cts : Do the right in first time with out ignoring defects & minor faults.

    PONC includes the quality-related costs incurred in making certain bleshooting etc.

  • 8/12/2019 Quality Assurance Plan_Manoranjan

    4/28

    urpose of the Project Quality Plan

    To provide an instrument which can contribute to qubuilt-up process/guidelines/specifications in systematicGuideline & reference are given which can be used to s

    Quality can be defined to meet customers expectationsway of deliverables and/ or activities performed .

    Objective of the Project Quality plan :

    Control Project KPI within specified limit & Implementation LeaReduction of Material wastages.Implementation of proper Installation procedure , results cost rEnhance the relationship between Customer & ZTE.Enhance Management & Improvement.

    > Internal Only

    lity level & control of telecom implementation / Infradetailed description.

    et-up & control the process.

    or exceeding the customer expectations achieved by

    ZTE Corporation. All rights reserved.

    .

    d time as set by ZTE.

    ductions & time efficient.

  • 8/12/2019 Quality Assurance Plan_Manoranjan

    5/28

    roject KPI Target & Measurement Crit

    SLNo Description Target

    MeasurementCycle

    1 COQ (Penalty) Equal to 0 Monthly

    2 SITR/ITR Rate >=80% Monthly

    3 Self Check AcceptancePercentage >=70% Monthly

    4 Sample Check Rate >=15% Monthly

    5 Last Month Min >=100% Monthly

    O

    Calfor

    6 Site Engg. CoverageRate >=70% Monthly

    7 Sample CheckAcceptance Percentage >=90% Monthly

    8Training CoverageRate >=90% Monthly

    9 Model Site CoverageRate >=90% Monthly

    10 ATC Rate >=70% Monthly11 OTP Rate >=80% Monthly

    12 Circle Index >=.7 Monthly

    SccritOwStacolMeUni

    > Internal Only

    riaKPI Quality Management Coefficient

    jective To evaluate the performance of project on delivery quality point ofview

    culationula

    KPIQ= -(Q1*15%)+(Q2*15%)+(Q3*20%)+(Q4*10%)+(Q5*5%)+(Q6*5%)(Q7*10%)+(Q8*5%)+(Q9*15%)+(Q10*15%)

    KPIQ: Indicates key performance indicator coefficientQ1 - Indicates the score of Critical of Quality

    Q2 - Indicate the score of Site Issue Till Resolution/ Issue TillResolutionQ3 - Indicate the score of Self Check Acceptance RateQ4 - Indicate the score of Self Check Rate

    ZTE Corporation. All rights reserved.

    n on -Q6 - Indicate the score of Sample Check Acceptance RateQ7 - Indicate the score of Training Coverage Rate

    Q8 - Indicate the score of Model Site Coverage Rate

    Q9 - Indicate the score of Acceptance Test Coverage Rate

    Q10 - Indicate the score of One Time Pass Rate

    ringeria Project Quality Score (PQS)=KPIQ

    ner fortisticsection

    Quality Department

    suringt

    100 points

  • 8/12/2019 Quality Assurance Plan_Manoranjan

    6/28

  • 8/12/2019 Quality Assurance Plan_Manoranjan

    7/28

  • 8/12/2019 Quality Assurance Plan_Manoranjan

    8/28

    uality Assurance Vs Quality Control

    uality Assurance: QA is fault prevention throughprocess design & auditing

    Creating process , procedure , tools etc to prevent faults

    Examples: Templates, Checklists, Procedure and Guideline

    uality Assurance Activities:

    ey quality assurance activities are very important for assuringuality through out the project .

    Confirm project acceptance procedure, Quality expectation &agreed with customer.Validation of project quality standard which meets customer

    quality expectation.Review & Publish of site design documents.Built model site.Training & Competence development and certification / worklicense to team lead of subcon.(skill card & certificates)Adheres of Installation Procedure in Project as per guideline.

    > Internal Only

    uality Control- QC is fault/failure detection throughstatic & /dynamic testing artifacts

    Examining the artifacts against pre-determined criteria tomeasure conformance.

    Examples: Audit & Problem analysis through quality tools.

    uality Control Activities:

    ZTE Corporation. All rights reserved.

    ey quality control activities are very important for controlling quality.

    100% Self Check after site completion by the Subcon.Spot Check / Sample Audit must be performed by ZTE SE, CL,IM, Infra Lead , Quality Lead & CH/CPD.

    Summarize , analyze & Review the project quality .Evaluate Subcon/Vendor Analysis quality performance.Site DocumentsOrganize routine meetings with Project ,Sub cons & Key teammembers

  • 8/12/2019 Quality Assurance Plan_Manoranjan

    9/28

    Quality AssuranceSix Key Activities Fl

    Key point 1

    Key point 2

    Key point 3

    Confirm project q

    Training to subcon atea

    Model Sit

    Key point 4

    Key point 5

    Key point 6

    Subcontractor perfor

    ZTE site engineer/cluste

    performs qualit

    Summarize, analyzedefe

    > Internal Only ctivities: ow Chart

    uality standard

    nd ZTE Site Impl

    Building

    ZTE Corporation. All rights reserved.

    . . .

    s 100% self-check

    leads/ infra leads/QL

    spot-check

    nd correct qualityts

  • 8/12/2019 Quality Assurance Plan_Manoranjan

    10/28

    onfirm project acceptance procedure a

    onfirm project acceptance procedure , Quality expecta

    Project clarification meeting to be done with account/sales team b

    Build team & define the deliverable/ownership of quality activities.

    CH/CPD & PD should ensure that the site acceptance scheme, Q

    Acceptance scheme must be signed by both ZTE & Customer.

    s ou ensure t at customer s u y aware o agre

    alidation of Project Quality Standard

    CH/CPD/PD should communicate with customer and collect custoQuality Assurance Plan need to be concurred by PD and time to tim

    Customer concurrence need to be taken on all standards /specific

    The final project quality standards/spec, must be shared with all pr

    > Internal Only

    d Validation of Quality standard

    tion as agreed with customer.

    CH/CPD/PD prior to discussion with customer.

    ality expectation, documentation are agreed with customer.

    ZTE Corporation. All rights reserved.

    t e n ra requ rements pr or to pro ect start.

    ers installation specification and project quality requirement. information shared with PQM.

    tion through built up Model Sites as part of record .

    ject staffs & subcon.

  • 8/12/2019 Quality Assurance Plan_Manoranjan

    11/28

    odel Site Process

    Build model site in three levels (Project level, Circle Level & Vendo

    Customer concurrence is mandatory for Model Site .

    Deviations to agreed specs/guidelines, if any, must be recorded an

    After the model site is accepted by customer , On site Training to oQuality teams ,it helps to understand the project quality expectatio

    Photo Album need to be made neatly in capturing all specification .

    Circle QL need to communicate the Model site photo album to resEach team of each subcon builds its first installed site as Model Sit

    1

    1. 2. 3. .

    2

    1. 2. 3. .

    > Internal Only

    r Level)

    d signed by both ZTE & Customer.

    ther subcons need to be arranged by respective circle projectand installation quality requirements.

    ZTE Corporation. All rights reserved.

    ective subcon teams and project implementation teams . e.

    ,

    3

    1. 2. , 3. .

  • 8/12/2019 Quality Assurance Plan_Manoranjan

    12/28

    raining and Competence Development

    Training to all project staff / sub-cons team lead/ Engineers/CPD m

    Subcon trainings need to continue in every Quarter.

    Issue of skill card, certificates /work licenses to subcon team whileModel site installation .Details may be referred to Training Regulati

    Trainers could be QL/ IM/ PQM/ H&S Manager.

    Module -1 (Prior to work start) Expectation of customer, Knowledgimplementation safety.

    Module -2 (During project phase) Special training on installation dviolation implementation safety.

    If any Subcon introduced during implementation period then separ

    Only trained & certified team leader/engineers will be allowed to w

    Assessment along with Training report must be in place after every

    > Internal Only

    ust be conducted prior to project start & should continue in quarter.

    fulfilling preconditions of Test evaluation and becoming part ofns .

    on equipment installation process/project quality standard and

    ZTE Corporation. All rights reserved.

    eviation, new products if any, improvement plan, Health & Safety /

    te training Module 1 shall be arranged before work allocation.

    rk at site.

    training and uploaded in requisite servers.

  • 8/12/2019 Quality Assurance Plan_Manoranjan

    13/28

    , .

    . .

    Adobe Acrobat

    Document

    Adobe AcrobaDocument

    > Internal Only

    & ,

    /

    ZTE Corporation. All rights reserved.

    . . .

    t

  • 8/12/2019 Quality Assurance Plan_Manoranjan

    14/28

    ubcontractor performs 100% self-check

    Subcon have to carry out self check after completion of each site..

    The assessment has to as per agreed specs/drawing/ guidelines &Use correct checklist for the assessment..

    Self check list need to be filled with punch points and due deligen

    Documentation of Self check list need to be submitted to QL /PQM

    The site assessment should be done by a qualified engineer/teamName ,Contact no ,Designation etc to be put .

    IM, Infra Lead, Cluster Lead & SE has to ensure that this assessm

    Penalty need to be imposed for non compliances .

    Review of Self Check to be made as main agenda in Weekly /Fort

    Appreciation /Reward /Recognition to be made for deserved Subc

    > Internal Only

    as per their deliverable in project.

    e need to be taken for rectification

    with in 4 days of time after completion of site .

    lead from Subcon QC team.and duly Signature with details e.g

    ZTE Corporation. All rights reserved.

    ent process is being followed by each subcon.

    ightly/Monthly meetings .

    n teams , need to be recorded as part of process .

  • 8/12/2019 Quality Assurance Plan_Manoranjan

    15/28

  • 8/12/2019 Quality Assurance Plan_Manoranjan

    16/28

    Control Process of Project Quality .

    Process need to be in sequential manner as Summarize , Analyz

    To Avoid occurrence of quality defects through preventive actions

    Provide stack holder visibility w,r.t overall quality management pro

    Circle QL collect quality defects , analyze the cause of common pro

    share the project quality analysis report with concern stake holder

    Suggest the process/guidelines/procedures/tools required to be u

    Review the project quality as per schedule enclosed with all conce

    Scheduled meeting to be held in presence of all stake holders an

    Recognition of good workmanship need to be done and shared a

    > Internal Only

    & Review.

    Keeping track of recurrence of past quality defects

    ess .

    blems & Quality KPI involved in project

    eriodically.

    ed to avoid the occurrence & communicate to PQM/HQ

    ZTE Corporation. All rights reserved.

    n..

    action plan /timeline to be agreed upon in forum,

    ong all subcons and project implementation teams

  • 8/12/2019 Quality Assurance Plan_Manoranjan

    17/28

    uality Control Activities:imelines to complete the QC activities

    Activity

    Subcon performs 100% self check andsubmission of reports as per timeline Withi

    Site Engineers performs the sample audit andvalidate self inspection report

    Withicomp

    QL performs quality audit on sample basis Sam

    Lead time of closing punch points observed duringaudit

    CritiMajoMino

    > Internal Only

    Timeline

    4 days after the completion of hardware installation work

    the time duration starting from 48hrs to 72hrs afterletion of hardware installation work

    ZTE Corporation. All rights reserved.

    le check of previous month installation work completed

    al problem must be closed with 48hrs problem must be closed within 72hrsproblem must be closed within a week

  • 8/12/2019 Quality Assurance Plan_Manoranjan

    18/28

  • 8/12/2019 Quality Assurance Plan_Manoranjan

    19/28

    eneration of Report

    Project

    Report Prepared by

    Project Circle Weekly Report QL

    Pro ect Circle Qualit Monthl Re ort QL

    Project Weekly Report PQM

    Project Quality Monthly Report PQM

    > Internal Only

    Report

    Frequency Submit to

    Weekly PQM

    Monthl PQM

    ZTE Corporation. All rights reserved.

    Weekly CPD/PD/IM/Infra Lead/CL/QH

    Monthly CPD/PD/IM/Infra Lead/CL/QH/HQ

  • 8/12/2019 Quality Assurance Plan_Manoranjan

    20/28

    ocument and Record control

    uality documents need to be handled only by authorized Quality DThese documents includes Site Checklists, ATP checklist & Qualityo be made thru Notice with copy of documents /manuals/copies with

    QM & PM are responsible person to publish required quality docum

    ll documents to be uploaded in the server as per the below docume

    ocuments Control

    . . .

    ecord Control

    lassification of records need to be made and kept back up documeong records need to be kept in server till further order of deletion /nssessment / HQ requirement

    xpired record should be destroyed according to specific requiremen

    # .

    11 001

    > Internal Only

    partment officials and confidentiality of data to be maintainedtandards. Amendment on records to be done and proper publishingduly approved by Approver .

    ents & procedure among the implementation team.

    nt identification table.

    ZTE Corporation. All rights reserved.

    ts in requisite server ,PQM need to preserve same in safe /custodyeed to be produced while any requirement of submission of maturit

    t. Record Control table is as shown below

  • 8/12/2019 Quality Assurance Plan_Manoranjan

    21/28

    erformance Ranking Criteria

    PQM will evaluate subcon engineering service quality and index b

    Feedback Report w.r.t supplier performance on quality to be shar

    Evaluate the site engineer performance through sample visit ..

    Feedback of site engineers performance (Competency & process

    Evaluate of subcons to be done on competency , capability & proc

    > Internal Only

    sed as per the measurement criteria.

    d with CPD, PD and OSD.

    ZTE Corporation. All rights reserved.

    .

    dherence). to be shared with IM, CL, Infra Lead , CPD

    ss adherence.

  • 8/12/2019 Quality Assurance Plan_Manoranjan

    22/28

    enalty Clauses & WCC Signoff Timelin

    Regulation on punishment for ZTE Site engineer

    f QA Engineer finds quality problems e.g weak supervision and timelssues to be intimated with out delay to CPD/CH keeping in loop to Phe PQM and CPD/CH must consult with PD to make a decision on

    o be made )Regulation on punishment for Vendor

    roject team/PQM can take action against concern subcon after conFor submission of fake reports.

    egulation on punishment/ penalty clauses are as per below:

    .

    For not meeting Red line requirementFor not taking corrective action after getting the site quality problFor not giving proper response to project team.For damaging of material and for wasting of materials.For violation of implementation safety etc

    CC Signoff Timelines:

    . Submission of signed off documents in after the SLA e.g Hardwahe document to QL and the QC can give the sign off the same, so thhile sign off by Project Impl team /CH /CPD.

    . if the site is having punch point, the QL cant give the sign off on th

    > Internal Only

    s

    y rectification problems /issues having inadequate reasons All theseQM.unishment (Warning letter or Criticism letter or Penalty notice need

    ulting with Outsourcing Manager in the following cases.

    ZTE Corporation. All rights reserved.

    m .

    e Installation /Self Inspection documents. The subcon can submitat on the online system PQM can approve the document accordingl

    document until the sites get rectified.

  • 8/12/2019 Quality Assurance Plan_Manoranjan

    23/28

    ubcon Management

    ollowing needs to be understand prior to work starts/w

    Understand the deliverables which are incorporate in Subcon SO

    Kick-off meeting with Subcon , prior to work starts.----Owner CPD/

    Understand the deliverable capability /Skill set of each resource n

    Make them aware the Quality Plan of the project & requirements.--

    Documentation required to be produced at different stages of proje

    Understand the Project & Quality organization of subcon. ----Owne

    Communication & problem resolution methods. ----Owner-PQM/ C

    Invoice & Financial status. ----Owner-CPD/CH

    Technical performance of subcon team. ----Owner-IM/CL/Infra Lea

    Define Reward & penalization scheme in contract ----Owner-OSD /

    > Internal Only

    ork allotment to Subcon

    as per Contract /Agreement --Owner CPD/CH

    H/PQM .

    ed to be identified .----Owner-CPD/CH/PQM

    --Owner-PQM

    ct. ----Owner-CPD/CH/PQM

    ZTE Corporation. All rights reserved.

    r- PQM /CPD/CH

    D/CH

    /PQM

    Project Technical Team /PD

  • 8/12/2019 Quality Assurance Plan_Manoranjan

    24/28

    &S Management and Monitoring

    D ev el o

    pH

    & S a s s

    K e y c on

    t r ol

    A n

    al y z e

    pr o

    j e c

    m an a g em

    en

    t r e

    q

    D ev el o

    p s u b c on

    t r

    m an

    a g em

    en

    t a g

    Or g

    ani z e

    t r ai ni n

    g an

    a c t i v i t i e s

    E v al u

    a t e pr o

    j e c t

    EstablishprojectPlan projectAnalyze project

    r a

    n c e pl an

    c t i vi t i e

    s

    t H

    & S

    i r em en

    t s

    c t or H

    & S

    r e em en

    t

    d p u b l i c i t y

    Smooth channel for comsu

    Customer

    H & S r i s k

    > Internal Only

    P er f or m

    an

    c em

    an

    C u s t om

    er

    s a t i sf

    s u c c e s sf ul d

    H

    & S S p o t - c h e c k

    a

    I m pr ov e

    aw

    ar d

    s a

    s c h em

    e

    Hand overproject Close project

    S umm

    ar i z e

    pr o

    j e

    H & S m

    an

    a g em

    en

    Implementproject

    ZTE Corporation. All rights reserved.

    g em

    en

    t

    c t i on

    an

    d

    el i v er y

    d

    s el f - c h

    e c k

    n d

    p en

    al t y

    unication with the customer andcontractor

    SubcontractorTE

    t

    t

  • 8/12/2019 Quality Assurance Plan_Manoranjan

    25/28

    ealth & Safety with tools requirement.It is ZTE prime objective that all operations are to be carried out in

    e taken to prevent personal injuries to our staff, contracts, customerave legitimate interaction with our work operations.

    Few Key Points in Project H&S Management

    Make H&S assurance plan

    Record the H&S management regulations in the subcontractsAssess general risksTraining ( Preventive and Responsive )Self-check and spot-checkRewarding, punishment, and improvement

    Hazard Prevention and ControlStart by determining that a hazard or potential hazard exists,If the hazard cannot be eliminated, use hazard controlsEliminate or control hazards in a timely mannerControlling the Hazards

    Engineering controlsAdministrative controlsPersonal protective equipmentSafe work practices communicated via training, positive reinforcement , correAdditional Worksite AnalysisCollect near miss / Major and Minor ,Promotion of adherence of Safety Measure s on Sites .Building Safety as a Culture

    Personal Safety and Site Safety

    > Internal Only

    a safe manner, and that every measure is toand members of the general public who

    ZTE Corporation. All rights reserved.

    tion of unsafe performance, and enforcement

    PPE for Work at Height& Electrical Works

  • 8/12/2019 Quality Assurance Plan_Manoranjan

    26/28

    . a e y wareincluding Vendors

    2. Road Safety

    3. Electrical Sa

    ess o a ec n c ans& Customers

    Defensive Driving Trainings

    fety & Work at Height Demos

  • 8/12/2019 Quality Assurance Plan_Manoranjan

    27/28

    PREVENTIVE

    Defensive Driving Training Electrical Safety

    Training Safe Height Work Training

    RE

    Tr

    Fir

    Re

    PONSIVE

    ining on Fire Fighting

    t-Aid Training

    scue Operations

  • 8/12/2019 Quality Assurance Plan_Manoranjan

    28/28

    Internal Only


Recommended