Date post: | 13-Feb-2018 |
Category: |
Documents |
Upload: | imranrashid |
View: | 222 times |
Download: | 0 times |
of 22
7/23/2019 Quality Assurance Tests- Final
1/22
IQA for USAIDs Stabilization Program Activities in FATA and KPQuality Assurance Plan - Annexure G
30 April 2015 (1) Halcrow Pakistan
Annexure G Quality Assurance Tests
Protocols to be followed with Construction Contractor (FWO) Staff
At present the construction contractor has set up material testing laboratories at Hathala on DIK-Tank
road, at Wana on Wana Shakai Makin road and at Miranshah on Bannu Miranshah Ghulam Khan
road. The laboratories are fully equipped to perform tests to ascertain the quality of road construction
materials for all components of road/bridges. HPK is in the process of setting up its material testing
laboratory in D.I. Khan and Bannu with USAID provided equipment to carry out independent
testing. Certain tests have to be performed at approved outsourced laboratories where such testing
facilities are not available at Construction Contractor or HPK laboratories. The following is expected
to be the distribution of testing which will be practiced in the field and laboratories. HPK staff will
collect samples during their field visits/inspections and conduct the tests at established frequency at
Construction Contractor, HPK and approved outsourced laboratories for the systematic monitoring to
ensure that the product is meeting the requirements that have been established for quality checks.
Non-destructive tests will be carried out on site. This will include the Schmidt Hammer and Ultra
pulse velocity tests where required.
7/23/2019 Quality Assurance Tests- Final
2/22
IQA for USAIDs Stabilization Program Activities in FATA and KPQuality Assurance Plan - Annexure G
30 April 2015 (2) Halcrow Pakistan
Earthworks- Removal of excess soil and
debris and the preparation of sub gradefor sub base laying.
Co-ordination with construction contracto
on construction program
QA Monitors to check against design data
Checking 5 X-section/KmSoil Classification1 per 5 Km or as / when required.
Compaction/FDT 2/km
CBR 1 per 10 km & Site Photos
BASELINE MEASURE
Procedure for verifying the quality of material and works (Roads)
Granular Sub Base and Agg. Base course
Selected inert well graded material to
form a level.
QA Monitors to undertake & record
Specification Check (i-e) wt/Area 1 per 3 Km
Wearing Course- Mixture of Bitumen, Fine
& coarse aggregate/ Asphalt.
Prime Coat- Mixture of Bitumen &
Kerosene to keep base course intact.
IQA Staff to coordinate with construction
contractor with respect to defined milestones to
facilitate visits by QA Monitors/Supervisor.
QA Monitors to ensureGradation of Aggregate 1 per Km
Thickness 5 per Km
Extraction Test 1 per 5Km
Sam lin for stabilit 2 er Km
QA Monitors to undertake & record
Thickness Check 5/km
Sieve Analysis 1 per 3 km or as
required
Proctor Test 1 per km
FDT/Compaction Test 3/km or asrequired
CBR, Sand Equivalent 1 per 5Km
Key Outputs during Construction:
Field Inspection Form - Three copies
Bi weekly - Generated from South Office - (DI Khan)
Monthly Report - Generated by QA Manager - (Peshawar)
7/23/2019 Quality Assurance Tests- Final
3/22
IQA for USAIDs Stabilization Program Activities in FATA and KPQuality Assurance Plan - Annexure G
30 April 2015 (3) Halcrow Pakistan
Foundation upto Plinth
level
Co-ordination with construction
contractor on construction
program
QA Monitors to check against design data:
Width and depth of foundation 4 per building
Bearing capacity 1 for Foundations
Concrete Compressive Strength 1 Set for each grade of concrete
Reinforcement steel Complete Physical tests for each size
of bar from stock.
Bricks/Blocks Strength 5 Bricks/ 10,000 or change of source /as & when re uired.
Procedure for verifying the quality of material and works (Buildings)
Upto Walls bands
beams level
QA Monitors to check against design data:
Bricks/Blocks Strength 5 Bricks/ 10,000
4 Blocks per 10,000
Masonry Mortar Ratio verification Compressive strength as per requirement
Concrete Compressive Strength 1 Set for each grade of concrete for each part
of structure.
Reinforcement steel Complete Physical tests for each size of bar
from stock.
Upto roof slab level
IQA Staff to coordinate with construction contractors with respect to
defined milestones to facilitate visits by QA Monitors/Supervisor.
QA Monitors to ensure:
Thickness of slab, concrete cover to Reinforcement
Concrete Compressive Strength 1 Set for each grade of concrete
Reinforcement steel Complete Physical tests for each size of
bar from stock
QA Monitors to ensure;
Surface Finishing, Painting, Joinery and Electrification works.
Finishing/Completion
Level
Key Outputs during Construction:
Field Inspection Form - Three copies
Bi weekly - Generated from North Office - (Swat)
Monthly Report - Generated by QA Manager - (Peshawar)
7/23/2019 Quality Assurance Tests- Final
4/22
IQA for USAIDs Stabilization Program Activities in FATA and KPQuality Assurance Plan - Annexure G
30 April 2015 (4) Halcrow Pakistan
Proposed IQA Process (Power Sector)
(2)Soil Investigations.(3)Design Basis & Standards.
(4)Detailed Construction Drawings.
(5)Final Bills of Quantities
(6)Final Cost Estimates & PC-1
(7)Final Technical Specifications
(8)Phase 1 Sco e of works
Procurement program.
Information release schedules
Pre-construction Process (Power)
Master Design program.
Master Construction Program IQA Team to review all documentation.
Review shall include checks on Design
standards adopted, Cost estimates,
Construction drawings and Specifications
meet the regulatory requirements. The
IQA process shall be based on the
detailed Construction program with
regard to a key performance indicator
been linked to the percentage completion
of the works. The construction scheduleshall form the baseline measure.
(BASELINE & OPERATIONAL
MEASURE)
KEY OUTPUTS:
A pre-construction as is report (attached) that
shall form a fundamental part of the Baseline
Measure.
QA Monitors/supervisor will be deployed to
ascertain the As is situation prior to
construction. Data collection shall include:
1. Existing distribution lines & conditions
2. Existing Grid stations & Conditions
Testing/Inspection of material in
manufacturing premises C.E design
NTDC/C.E M.I PEPCO and witnessed
by IQA Representatives.
7/23/2019 Quality Assurance Tests- Final
5/22
IQA for USAIDs Stabilization Program Activities in FATA and KPQuality Assurance Plan - Annexure G
30 April 2015 (5) Halcrow Pakistan
Earthworks- Removal of excess soil and
debris and the preparation for sub base
laying for foundation.
Co-ordination with Construction contractor
on construction program
QA Monitor/Supervisor to check the work against the
approved drawings and start on site.
( BASELINE MEASURE)
Procedure for verifying the quality of material and works Grid station & Transmission Lines
(Power)
Electrical Material procurement Schedule
QA Monitor/Supervisor to check and witness
Material Type against original order placement.
QA Monitor to check the Inspection Certificate.
Installation on site
Receipt of Material on site.
QA Monitor/Supervisor to check the date of order
placement.
IQA Staff to coordinate with construction contractor/
FATA Secretariat with respect to defined milestones to
facilitate visits by QA Monitors/Supervisor.
QA Monitors/Supervisor to check that the Electrical
Materials been Installed on site as per the approved
drawings & Certifications by (Chief Engineer
Design (NTDC) PEPCO Lahore).
QA Monitor/Supervisor & QA Manager to check
the Material Schedule, prior to order placement.
Material Placement of shipping order
(Approved by Design NTDC/Material
Inspection PEPCO
Key Outputs during Construction:
Field Inspection Form - Three copies
Bi weekly Progress Report - Generated from South & North Office (DIK and Swat)
Monthly Progress Report - Generated by QA Manager - (Peshawar)
Testing & Commissioning
7/23/2019 Quality Assurance Tests- Final
6/22
IQA for USAIDs Stabilization Program Activities in FATA and KPQuality Assurance Plan - Annexure G
30 April 2015 (6) Halcrow Pakistan
Possession of Site. Site survey check. Soil
Testing, Levelling
Co-ordination with Construction contractoron construction program
QA Monitors/Supervisor to check the work against the
approved drawings and undertake independent level and
geometrical checks.
BASELINE MEASURE
Procedure for verifying the quality of material and works (Grid Station)
Excavation of main unit Foundations.
Excavation of Power Transformer FoundationsExcavation of Cable laying foundations.
QA Monitor/Supervisor to check remaining
electrical components against certifications.
Laying of control & Power Cables
La in of 132kV Bus Bar
Installation of remaining proprietary
elements
QA Monitors/Supervisor to check Transformer
types against specifications and drawings.
IQA Staff to coordinate with construction contractor /FATA Secretariat with respect to defined milestones to
facilitate visits by QA Monitors/Supervisor.
QA Monitors/Supervisor to check that the
Electrical Materials been Installed on site as per the
approved drawings & Certifications and carry out
independent verifications & testing.
QA Monitors/Supervisor to check depth of
excavations arrange soil sample for testing at DIKPeshawar University
Installation of Power Transformer
Installation of Current Transformer
Installation of potential Transformer
Key Outputs during Construction:
Field Inspection Form - Three copies
Bi weekly Progress Report - Generated from South & North Office (DIK and Swat)
Monthly Progress Report - Generated by QA Manager (Peshawar)
Connecting all equipments in the switchyard
Testing and earthing of all equipment
7/23/2019 Quality Assurance Tests- Final
7/22
IQA for USAIDs Stabilization Program Activities in FATA and KPQuality Assurance Plan - Annexure G
30 April 2015 (7) Halcrow Pakistan
Procedure for verifying the quality of material and works (Transmission Line)
Coordination with Construction
contractor on construction program.
Possession of site. Site survey check
Soil testing leveling
Excavation of tower foundation and
concreting of stubs
Erection of towers
Laying/sagging of conductor on
towers
Jump ring and installation of
dampers
Testing/commission of transmission
line
IQA Staff to coordinate with construction
contractor/ FATA Secretariat with respect to
defined milestones to facilitate visits by QA
Monitors/Su ervisor.
QA Monitors/Supervisor to check the work
against the approved drawings and
undertake independent level and geometrical
QA Monitors/Supervisor to check the depth
of excavations arrange soil sample for
testing at DIK/Peshawar University
QA Monitors/Supervisor to check electrical
components of transmission line against
s ecifications.
QA Monitors/Supervisor to check that the
Electrical Material been installed on site as
per the approved drawings & Certifications
and carry out independent verification &
Testing.
Key Outputs during Construction:
Field Inspection Form - Three copies
Bi weekly Progress Report - Generated from South & North Office - (DIK and Swat)
Monthly Progress Report - Generated by QA Manager - (Peshawar)
7/23/2019 Quality Assurance Tests- Final
8/22
IQA for USAIDs Stabilization Program Activities in FATA and KPQuality Assurance Plan - Annexure G
30 April 2015 (8) Halcrow Pakistan
Procedure for verifying the quality of material and works (Rehabilitation 11kV/33kV)
Co-ordination with constructioncontractor on Construction Program
Site survey and dismantle/Removal of
damaged items.
Possession of site and
excavation/Concreting of HT/LT pole
foundations.
Installation of transformers and
remaining proprietary elements.
Connecting/Jumpering of transformers
and conductors.
Earthing/Testing and energization of all
equipments.
IQA Staff to coordinate with constructioncontractor (FWO) with respect to defined
milestones to facilitate visits by QA
QA Monitors/Supervisor to check the work
against the approved drawings and
undertake independent level and
QA Monitors/Supervisor to check depth of
excavations arrange soil sample for testing
at DIK/Peshawar University
QA Monitors/Supervisor to check
transformer types against specifications and
drawin s.
QA Monitors/Supervisor to checkremaining electrical components against
certifications.
QA Monitors/Supervisor to check that the
Electrical Materials been installed on site
as per the approved drawings &
Certifications and carry out independent
verifications & testing
Key Outputs during Construction:
Field Inspection Form - Three copies
Bi weekly Progress Report - Generated from South & North Office - (DIK and Swat)
Monthly Progress Report - Generated by QA Manager - (Peshawar)
7/23/2019 Quality Assurance Tests- Final
9/22
IQA for USAIDs Stabilization Program Activities in FATA and KPQuality Assurance Plan - Annexure G
30 April 2015 (9) Halcrow Pakistan
Ongoing construction
Filed Offices
QA Monitors verbally informs and hands over a
copy of Field Inspection form to QA Engineer. QAEngineer reports to QA Manager.
Non Compliance Monitoring Process
Instruction given to site and remedial works
carried out
USAID COR
USAID initiates instruction to FATASecretariat / PaRRSA and informs clients
rectification of defects.
CONSTRUCTION CONTRACTORS
Construction Contractor receives written
instruction from USAID/Clients for
rectification.
PESHAWAR PROJECT OFFICE
COP checks non-compliance report for onwardsubmission to USAID COR.
QA Field Monitor identifies non-compliance either in
Design or Construction. Non-compliance is noted in
Field Inspection form.
(BASELINE MEASURE)
PESHAWAR PROJECT OFFICE
QA Manager reviews report & analyses the non-
compliance and forwards to construction
contractor and COP.
QA Monitors re-checks the rectified work.
7/23/2019 Quality Assurance Tests- Final
10/22
IQA for USAIDs Stabilization Program Activities in FATA and KPQuality Assurance Plan - Annexure G
30 April 2015 (10) Halcrow Pakistan
G-1 QA Tests for Roads
Specified Tests Frequency
Earth works
Proctor test to be done in site lab ( I per 5 Km)
Sieve analysis to be done in site lab ( I per 5 Km or as required)
FDT 2 per KM
Soil
Classificationto be done in site lab (1 per 5 Km or as required)
CBR to be done in site lab (1 per 10 Km)
Granular Subbase & Agg. Basecourse
Proctor test to be done in site lab ( I per Km)
Sieve analysis to be done in site lab ( I per 3 Km)
FDT to be done in site lab ( 3 per Km)
CBR, Sand
equivalentto be done in site lab (1 per 10Km or as required)
Los Angeles
abrasion value
to be done in site lab if equipment is available (1
test for 10 Km or as required)
Bitumen / Asphalt
Grade of
bitumenMin 1 test for one road project
Sampling for
stabilityone sample per 5 Km.
Gradation ofaggregates as above
Spray rate For each work day
Temperature During each work day
Soundness test of
aggregates
to be done in site lab if equipment is available (1 ~
2 tests for each road project)
Los Angeles
abrasion value
to be done in site lab if equipment is available (1 ~
2 tests for each source of material)
Coring from
pavement forthickness and
compaction
Four samples per km
7/23/2019 Quality Assurance Tests- Final
11/22
IQA for USAIDs Stabilization Program Activities in FATA and KPQuality Assurance Plan - Annexure G
30 April 2015 (11) Halcrow Pakistan
Specified Tests Frequency
Concrete
Bricks
Blocks
Masonry Mortar
Compressive
Strength
(Cylinder)
Slump Test
Strength,
Absorption, Size
Strength,
Absorption, Size
CompressiveStrength
After 10 , 30 & 50 Cu.m for column, wall and large
pours or minimum one set for each grade ofconcrete as and when required.
Hourly
5 bricks / 10,000
4 blocks / 10,000
From plaster/brick laying, Monthly
Steel Complete
physical test
(Bend,
elongation%,
yield & Ultimate
strength)
For each size of bar from source / shipment.
Structures
X-drainage (Culvert/Cause way)B/walls
R/walls
Side drain
Gabions / Protection works
Foundation
checking(Ht & Width)
Masonry work
measurement
3 per Km2 per Km.
2 per Km
3 per Km
2 per each location
Pavement Marking / studs
Sign boards
Guard Rail
Design
conformity /
specification
02 Location per km
Every 10thsign board
Every 5thGuard Rail
Location of Laboratories for Testing
Component Tests Conducted by Laboratory Field
Earth Work
Proctor test
Halcrow/Constr
uction
Contractor joint
Construction
Contractor
Sieve Analysis
Halcrow/
Construction
Contractor joint
Construction
Contractor
/Halcrow
7/23/2019 Quality Assurance Tests- Final
12/22
IQA for USAIDs Stabilization Program Activities in FATA and KPQuality Assurance Plan - Annexure G
30 April 2015 (12) Halcrow Pakistan
FDT
Halcrow/
Construction
Contractor joint
Field
Classification
Halcrow/
Construction
Contractor joint
Field
CBR
Halcrow/
Construction
Contractor joint
Construction
Contractor
/Halcrow
Granular Sub-base &
Aggregate. Base course
Proctor test
Halcrow/
Construction
Contractor joint
Construction
Contractor
Sieve Analysis
Halcrow/
Construction
Contractor joint
Construction
Contractor
/Halcrow
FDT
Halcrow/
Construction
Contractor jointField
CBR, Sand
equivalent
Halcrow/
Construction
Contractor jointFWO/Halcrow
Los Angeles
Abrasion value
Halcrow/
Construction
Contractor joint
Construction
Contractor Lab
Bitumen Asphalt
Grade of
Bitumen
UET
Peshawar/Taxila Out Source Lab
Sampling for
Stability
Halcrow/
Construction
Contractor joint
Construction
Contractor
/Halcrow
Gradation of
Aggregates
Halcrow/
Construction
Contractor joint
Construction
Contractor
/Halcrow
Spray rates
Halcrow/
ConstructionContractor joint
Field
Temperature Halcrow Field
Soundness test
of aggregate
Halcrow/
Construction
Contractor joint
Construction
Contractor Lab
Los Angeles
abrasion value
Halcrow/
Construction
Contractor joint
Construction
Contractor Lab
Coring frompavement for
Halcrow/
ConstructionContractor Joint
Field
7/23/2019 Quality Assurance Tests- Final
13/22
IQA for USAIDs Stabilization Program Activities in FATA and KPQuality Assurance Plan - Annexure G
30 April 2015 (13) Halcrow Pakistan
thickness &
compaction
Concrete
Compressive
Strength
(Cylinder
/Cube)
Halcrow/Construction
Contractor joint
ConstructionContractor /Out
Source
Slump test Halcrow Field
Strength,
Absorption
(Bricks)
Halcrow/
Construction
Contractor joint
Construction
Contractor /Out
Source
Size (Bricks)
Halcrow/
Construction
Contractor joint
Field
Strength,
Absorption
(Blocks)
Halcrow/
Construction
Contractor joint
Construction
Contractor /Out
Source
Size (Blocks)
Halcrow/
Construction
Contractor jointField
Compressive
Strength of
masonry mortar
Halcrow/
Construction
Contractor joint
Construction
Contractor /Out
Source
Steel
Complete
Physical test (%
elongation,
bend, yield and
ultimate
strength)
Out Source Lab
In addition the job mix formula for asphalt concrete will be carried out jointly at the Construction
Contractor laboratory. The tests related to the mix design will be supervised jointly and approved by
the material engineer/technician of Construction Contractor and Halcrow.
The concrete mix design if required by the specification will be conducted jointly by the Halcrow andConstruction Contractor staff and approved by the material engineer/technicians.
If in case the material tested at the different laboratories yield results which differ in respect of
meeting the specification then, it is recommended to jointly test the material to arrive at a conclusion
of either accepting or rejecting the material.
It is highly recommended to conduct the field test by Halcrow jointly with Construction Contractor
staff.
It will be difficult at this stage to ascertain the exact percentage of testing to be carried out at
Halcrow or Construction Contractor and outsource laboratories as Halcrow will mostly be spot
checking the test in the field and at the laboratory. It is envisaged that about 25% of the testingshould be carried out independently at the Halcrow laboratories.
7/23/2019 Quality Assurance Tests- Final
14/22
IQA for USAIDs Stabilization Program Activities in FATA and KPQuality Assurance Plan - Annexure G
30 April 2015 (14) Halcrow Pakistan
G-2 QA Tests for Buildings and Other Works
The works being executed in the North region (Malakand) shall be controlled from Swat office
and a central laboratory established at Swat.
Material Test Test Method Frequency
Soil
Soil and graded materials
Classification
MDD
Field Density
Moisture content
Gradation
Plasticity Index
Bearing Capacity
AASHTO M-145
AASHTO T-180
AASHTO T-191
ASTM C-566
ASTM C-136
AASHTO T-90
ASTM D1194
As per
requirement
As per
requirement
As per
requirement
As per
requirement
As perrequirement
As per
requirement
Once for
foundations
Coarse Aggregate Gradation
Water Absorption & Sp.Gr.
L. A. Abrasion
Soundness (Na2So4)
Flat & Elongated particlesClay lumps & Friable part.
Unit Weight
Material finer # 200 sieve
ASTM C-136
ASTM C-127
ASTM C-131
ASTM C-88
ASTM D-4791ASTM C-142
ASTM C-29
ASTM C-117
From built
stock as per
requirement
Monthly
As perrequirement
After 3-
months
Monthly
As per
requirement
As per
requirement
As perrequirement
Fine Aggregate Gradation with F.M.
Water Absorption & Sp.Gr.
Organic Impurities
Unit Weight
Material finer # 200 sieve
ASTM C-131
ASTM C-128
ASTM C-40
ASTM C-29
ASTM C-117
From built
stock as per
requirement
Monthly
As per
requirement
As per
requirement
As per
requirement
7/23/2019 Quality Assurance Tests- Final
15/22
IQA for USAIDs Stabilization Program Activities in FATA and KPQuality Assurance Plan - Annexure G
30 April 2015 (15) Halcrow Pakistan
Material Test Test Method Frequency
Concrete
Clay Bricks
Blocks
Masonry Mortar
Compressive Strength
(Cylinder)
Slump Test
Strength, Absorption, Size
Strength, Absorption, Size
Compressive Strength
ASTM C-39
ASTM C-143
ASTM C-67
ASTM C-140
ASTM C-109
After 5, 10 ,
30 & 50 Cu.m
for column,wall and
large pours or
minimum one
set for each
grade of
concrete or as
required.
During
concreting (as
required)
5 bricks /10,000
4 blocks /
10,000
From plaster
or brick
laying,
Monthly
Water Chlorides, Sulphates,
pH.,TDS
AASHTO T-26 once for
source
Cement Physical tests ASTM C-150 (Mill Test
certificate)
Reinforcement steel Complete physical tests
(bend, % elongation, yield
and ultimate strengths)
ASTM A-615 For each size
of bar from
source.
Piping works Pressure test
Leakage test
ASTM C-828
ASTM C-828
As per
requirement
As per
requirement
Electric cables
Specify testing and
commissioning
For each
source / as
per
requirement
7/23/2019 Quality Assurance Tests- Final
16/22
IQA for USAIDs Stabilization Program Activities in FATA and KPQuality Assurance Plan - Annexure G
30 April 2015 (16) Halcrow Pakistan
G-3 QA Tests for Power
11kV / 33kV Distribution Systems
Material Specified Routine Lab Tests Frequency
HT and LT Structure
a) Complete structuresOnce before pre
shipment from
Manufacture Premises
Verification of dimensions, weights and
Transverse load test.
-do-
b) On members-do-
Tensile strength Test , Elongation Test , Bend Test
, Embrittlement Test , Hardness Test and Yield
Strength Test.
-do-
c) Galvanizing-do-
Weight , uniformity and Adherence of zinc
coating
-do-
Rabbit ConductorACSR , Al-Aluminum
Conductor ACC and
GSL Wire
a) Aluminum
Verification of Diameter, Weight, Breaking load of
single strand, Tensile strength, Resistivity test,
Wrapping and DCR of single wire and complete
strand.
-do-
b) Steel (For ACSR Only)-do-
Verification of Diameter, Tensile strength,
Elongation, Wrapping, Lay Ratio Test Adherence,
Uniformity and Adherence of Zn coating.
-do-
c) Complete conductor-do-
Breaking load and unit weight -do-
Transformers 11 and 33
/ 0.415kV
25, 50 , 100 and 200
KVA
d) Transformer oil tests
Checking Specific gravity, Viscosity, Flash Point,
Acidity value, Dielectric Strength and Pour Point.
-do-
e) Routine tests
Polarity and Phase relationship, Load and No
Load test, Losses test, Induced voltage test and
over voltage withstand test, Tank pressure test,
Bird test and Paint thickness test, Turn Ratio and
Transformer resistance test.
-do-
Steel cross arm ,Pin
steel , Tension Clamp , Verification of dimension and weight, Tensile Testand Yield Strength, Elongation and Embrittlement-do-
7/23/2019 Quality Assurance Tests- Final
17/22
IQA for USAIDs Stabilization Program Activities in FATA and KPQuality Assurance Plan - Annexure G
30 April 2015 (17) Halcrow Pakistan
G-4 132kV Transmission Line
Eye Nut , D-Shackle ,
Earthling Unit , Stay
Rod , PG Connector ,
Misc Material.
test. Mechanical Test: (Lead should not loose or
separate at 1000Kg load.)
a) Galvanizing -do-
Weight of Zn, uniformity, Adherence and bend
test.
-do-
Concrete
Compressive Strength (Cylinder) 1 test per 5 HT and LT
foundations.
Gradation of Course and Fine Aggregate As per requirement
Material Specified Routine Lab Tests Frequency
Verification of weights ,UTS ,Elongation ,Bend
test , chemical analysis test ,Embrittlement ,
Yield Strength and Thermal Shock Test.
Once before pre shipment
from Manufacture
Premises.
Galvanizing
Thickness , weight and uniformity of zinc
coating and Impact Test.
ACSR Lynx Conductor
and 9mm Earthwire
Dimension , weight , TST , Lay ratio , DCR of
single and complete ,breaking load test,wrapping test, Elongation ,Weight , adherence
and uniformity of Zn coating.
-do-
Disc InsulatorsDimensional test, Temperature cycle,
Mechanical breaking, Porosity, Galvanizing, Oil
puncture voltage and operation test.
-do-
Hardware
(ST-L , SF-9, MS-9 , SB
vibration Dampers , PG
Clamp and Misc)
Breaking Load, Elongation, unit weight,
verification of dimensions, TST, Galvanizing test
and Zn coating thickness.
-do-
Tower FootingResistance Measuring tower footing Resistance TFR
Checking earth resistance
of each Tower.
Concrete
Compressive Strength (Cylinder /cube) 1 test per 5 Tower
Gradation of Coarse and Fine Aggregate As per requirement
Slump test As per requirement
7/23/2019 Quality Assurance Tests- Final
18/22
IQA for USAIDs Stabilization Program Activities in FATA and KPQuality Assurance Plan - Annexure G
30 April 2015 (18) Halcrow Pakistan
G-5 132kV Grid Station
Material Specified Routine Lab Tests Frequency
Power Transformer with
Auxiliary control panel
a) On Power Transformer
Once before pre
shipment from
Manufacture
Premises.
Measurement of insulation resistance of
windings , Voltage ratio and phase
displacement , winding resistance (HV &
LV) , Capacitance and Dissipation factor of
insulation of T/F and bushings ,No load loss
& current , short circuit impedance & load
loss (ONAN&ONAF) , separate source
voltage withstand test, induced over-voltage
withstand test & measurement of partial
discharge , OLTC functional tests AND
lightning impulse voltage withstand test.
a) Oil Tests
Viscosity, Pour point, acidity value, Moisture
content, Dielectric Dissipation factor,
Interfacial tension and dielectric strength.
b) Auxiliary Control Panel Functional Tests
11KV Switchgear Panels
(Incoming, Outgoing, Bus
Coupler & Capacitor Bank Panel)
Visual Inspection & Dimensions,
Electrical operation tests, (Ampere,
voltage, Pf, Energy meter), Indication
Lights, Push buttons, continuity of earth.
Trip Circuit Supervision, O/C, S/C, E/F,
Back up E/F, Capacitor Un-balanced
protection, under & over voltage Relays.
Load break switches Mechanical
performance, Mechanical Interlocking.
Power frequency withstand Voltage test
(Auxiliary circuit) 2KV for one minute to
Auxiliary circuit.
Power frequency withstand Voltage test
(Main circuit) 36KV for one minute to
Main Circuit
Insulation test of VCB Vacuum Tube and
resistance of Main circuit and
Verification of Interchangeability of
Components & Mechanical operation
test.
-do-
AC/DC Auxiliary Panel
Line Control Panel CP-30
Transformer Control Panel CP-50
Applied 2KV across Auxiliary Circuit for 1
minute, General and functional Tests on AC
and DC portion
-do-
Line Relay Panel RP-3Transformer Relay Panel RP-4
Applied 2KV across Auxiliary Circuit for 1
minute, General Tests, Functional Tests on
Panel, Functional Tests on Tripping &
-do-
7/23/2019 Quality Assurance Tests- Final
19/22
IQA for USAIDs Stabilization Program Activities in FATA and KPQuality Assurance Plan - Annexure G
30 April 2015 (19) Halcrow Pakistan
Supervision, Distance Relay, O/C & E/F
Relays.
95 mm Copper Conductor,
Al-Aluminum Conductor 600
mmEarth wire 7/3 (9mm Dia)
Measuring Diameter , Breaking Load ,
Elongation , Lay ratio , Resistance and Unitweight , TST , Zinc coating ,Uniformity , and
adherence.
-do-
I. 2.5mm 4 core control cables
II. 2.5mm 8 core control cables
III. 2.5mm 16 core control
cables
IV. 6mm2 4 core control cables
Thickness of insulation, sheath, Diameter of
single wire, elongation of conductor, TST and
elongation of PVC sheath and insulation
before and after ageing.
Hot deformation of PVC insulation and
sheath.
Heat Shock, cold bend test, Color fastness
test, Resistance to burning test, Waterabsorption and loss of mass for a PVC
insulation/sheath.
Insulation resistance, copper tape resistance
and DC resistance of copper conductor.
-do-
120mm 3 core power cables
500mm Single core Power cables
Verification of dimensions, power frequency
voltage test Conductor resistance test , Heat
Shock test , Behavior of low temperature test,
Flame test, Heat deformation of PVC sheath ,
DC resistance of copper conductor ,
Resistivity of semi conducting screens
-do-
Battery charger Visual inspection , Dielectric strength test ,
Properties of smoothing circuit , Checking of
protective devices , Properties of current
limiter , Noise level test and Checking of
alarms
-do-
12 m Beam
13.1 m Column
13.1 m Earth Mast
11kV Structure 4m Long and
substation connectors.
Yield load, Breaking load , Yield stress
Ultimate stress , Elongation, Bend test
-do-
I. 132kV Circuit Breaker
II. 132kV Line / Bus
Disconnector
Average speed of opening and closing,
Opening and closing synchronism between
plates, closing & Opening time.
-do-
Mechanical Operation Test
Switching Operation opening and closing
voltage. Motor charging time and normalworking voltage.
7/23/2019 Quality Assurance Tests- Final
20/22
IQA for USAIDs Stabilization Program Activities in FATA and KPQuality Assurance Plan - Annexure G
30 April 2015 (20) Halcrow Pakistan
Dielectric test of main circuit, Aux & control
circuit.
Alarm and Lock pressure of SF6 gas.
132kV Surge Arrestor Residual voltage test at nominal discharge
current , Power frequency reference voltage
test ,Partial discharge test and Verification of
Terminal Markings
-do-
132kV Transformer
Current Transformer and 132kV
Line Current Transformer.
Measurement of Capacitance and dielectric
dissipation factor ,Test of short-time power
frequency withstand voltage,
Partial discharge measurement(B)
-do-
Error Test
a) Error of Metering /Protection
Winding
Ratio Error
Phase Displacement Error
132kV Voltage Transformer Verification of Terminal Markings ,
Measurement of DC resistance ,
Measurement of capacitance and dielectric
dissipation factor , Induced withstand
voltage test , Measurement of Excitation and
Partial discharge measurement
To be performed in
the Manufacture
Lab
Concrete Compressive Strength (Cylinder) After 5, 10, 30 & 50Cu.m for column,
wall and large
pours or minimum
one set for each
grade or as
required.
Gradation of Course and Fine Aggregate As per requirement
Slump Test During concreting
(As per
requirement)
Masonry Mortar Compressive Strength Plaster or Brick
laying (As per
requirement)
Cement Physical Test Mill Test certificate
Bricks / Blocks Water Absorption , size , Compressive
strength
5 bricks / 10,000
4 blocks / 10,000
Reinforcement steel Complete physical tests (bend, % elongation,
yield and ultimate strengths)
For each size of bar
from source.
7/23/2019 Quality Assurance Tests- Final
21/22
IQA for USAIDs Stabilization Program Activities in FATA and KPQuality Assurance Plan - Annexure G
30 April 2015 (21) Halcrow Pakistan
G6 Water (Irrigation/Dams)
Specified Tests Frequency
Earth works
(Excavation of foundations and abutments)
X-Sect 3 No.
Soil
Classification3 Nos.
Concrete
Tests3 Nos.
Foundation
treatment & grouting
Concrete
Test3 Nos.
Embankment completion in layers from
bottom to crest
Compaction 3Nos per Meter of compacted fill
Thickness 3Nos per Meter of compacted fill
Gradation 3Nos per Meter of compacted fill
Spillway & intake Structure
Soil
Classification
3 Nos per structure
Concrete After 5, 10, 30 & 50 Cu.m for column, wall
and large pours or minimum one set for
each grade or as required.
Masonry 03 Nos. per 5m
Irrigation Channels X Section 03 Nos. per km
Concrete After 5, 10, 30 & 50 Cu.m for column, walland large pours or minimum one set for
each grade or as required.
7/23/2019 Quality Assurance Tests- Final
22/22
IQA for USAIDs Stabilization Program Activities in FATA and KPQuality Assurance Plan - Annexure G
30 April 2015 (22) Halcrow Pakistan