QUALITY CONTROL MANUAL EDITION 1 REV 0 Revision Date July 18, 2012 PAGE 1 of 2 TABLE OF CONTENTS SECTION 1: TABLE OF CONTENTS PAGE OF SECTION REVISION DATE SECTION 1: TITLE PAGE/TABLE OF CONTENTS 1 0 07/18/20 12 SECTION 2: SCOPE/STATEMENT OF AUTHORITY 1 OF 2 0 07/18/20 12 SECTION 3: ORGANIZATION CHART 1 0 07/18/20 12 SECTION 4: DEFINITIONS 1 OF 4 0 07/18/20 12 SECTION 5: TENDER & CONTRACT 1 0 07/18/20 12 SECTION 6: MANUAL CONTROL 1OF 2 0 07/18/20 12 EXHIBIT 6.1 DOCUMENT TRANSMITTAL 2 0 07/18/20 12 SECTION 7: DRAWINGS & DESIGN CALCULATIONS 1 OF 4 0 07/18/20 12 EXHIBIT 7.1 DRAWING INDEX 4 0 07/18/20 12 SECTION 8: MATERIAL CONTROL 1 OF 7 0 07/18/20 12 EXHIBIT 8.1 PURCHASE ORDER 4 0 07/18/20 12 EXHIBIT 8.2 PURCHASE REQUIREMENTS BY PRODUCT 5 0 07/18/20 12 EXHIBIT 8.3 COLOR CODE CHART 6 0 07/18/20 12 EXHIBIT 8.4 MATERIAL RECEIVING REPORT 7 0 07/18/20 12 SECTION 9: EXAMINATION & INSPECTION 1 OF 6 0 07/18/20 12 EXHIBIT 9.1 TRAVEL SHEET 4 0 07/18/20 12 EXHIBIT 9.3 NAME PLATE 6 0 07/18/20 12 SECTION 10: WELDING 1 OF 6 0 07/18/20 12
Transcript

QUALITY CONTROL MANUAL

EDITION 1 REV 0 Revision Date July 18, 2012

PAGE 1 of 2

Table of Contents

SECTION 1: TABLE OF CONTENTSPAGE OF SECTIONREVISIONDATE

SECTION 1: TITLE PAGE/TABLE OF CONTENTS1007/18/2012

SECTION 2: SCOPE/STATEMENT OF AUTHORITY 1 OF 2007/18/2012

SECTION 3: ORGANIZATION CHART1007/18/2012

SECTION 4: DEFINITIONS1 OF 4007/18/2012

SECTION 5: TENDER & CONTRACT1007/18/2012

SECTION 6: MANUAL CONTROL1OF 2007/18/2012

EXHIBIT 6.1 DOCUMENT TRANSMITTAL2007/18/2012

SECTION 7: DRAWINGS & DESIGN CALCULATIONS1 OF 4007/18/2012

EXHIBIT 7.1 DRAWING INDEX4007/18/2012

SECTION 8: MATERIAL CONTROL 1 OF 7007/18/2012

EXHIBIT 8.1 PURCHASE ORDER4007/18/2012

EXHIBIT 8.2 PURCHASE REQUIREMENTS BY PRODUCT5007/18/2012

EXHIBIT 8.3 COLOR CODE CHART6007/18/2012

EXHIBIT 8.4 MATERIAL RECEIVING REPORT7007/18/2012

SECTION 9: EXAMINATION & INSPECTION 1 OF 6007/18/2012

EXHIBIT 9.1 TRAVEL SHEET4007/18/2012

EXHIBIT 9.3 NAME PLATE6007/18/2012

SECTION 10: WELDING1 OF 6007/18/2012

EXHIBIT 10.1 WPS INDEX & ESSENTIAL VARIABLE SUMMARY4007/18/2012

EXHIBIT 10.2 WELDERS LOG5007/18/2012

EXHIBIT 10.3 CONTINUITY LOG6007/18/2012

SECTION 11: NONCONFORMITIES1 OF 3007/18/2012

EXHIBIT 11.1 NONCONFORMITY REPORT2007/18/2012

EXHIBIT 11.2 HOLD TAG3007/18/2012

QUALITY CONTROL MANUAL

EDITION 1 REV 0 Revision Date July 18, 2012

PAGE 2 of 2

Table of Contents

SECTION 1: TABLE OF CONTENTS

PAGE OF SECTION REVISIONDATE

SECTION 12: NONDESTRUCTIVE EXAMINATION1 OF 3007/18/2012

EXHIBIT 12.1 CERTIFYING STATEMENT AND APPOINTMENT LETTER 3007/18/2012

SECTION 13: HEAT TREATMENT 1 OF 2007/18/2012

EXHIBIT 13.1 HEAT TREATMENT INSTRUCTIONS2007/18/2012

SECTION 14: MEASURING & TESTING EQUIPMENT 1 OF 2007/18/2012

EXHIBIT 14.1 EQUIPMENT CALIBRATION LOG2007/18/2012

SECTION 15: PRESSURE TESTS1 OF 3007/18/2012

EXHIBIT 15.1 GUIDELINES FOR THE PREPARATION OF A PENUMATIC TESTING PROCEDURE2007/18/2012

EXHIBIT 15.2 HYDROSTATIC TEST REPORT3007/18/2012

SECTION 16: REPAIRS & ALTERATIONS1 OF 4007/18/2012

EXHIBIT 16.1 REPAIR/ALTERATION INSPECTION CHECKLIST4007/18/2012

SECTION 17: RECORD RETENTION1 OF 2007/18/2012

SECTION 18: AUTHORIZED INSPECTORS1007/18/2012

SECTION 19: PRESSURE PIPING 1 OF 7007/18/2012

EXHIBIT 19.1 PRESSURE PIPING SPECIFICATION SHEET13007/18/2012

EXHIBIT 19.2 PRESSURE PIPING EXAMINATION CHECK LIST 14007/18/2012

EXHIBIT 19.3 PRESSURE PIPING EXAMINATION GUIDE 15007/18/2012

EXHIBIT 19.4 PRESSURE TEST EXAMINATION GUIDE 16007/18/2012

EXHIBIT 19.5 SAMPLE-PIPETHREAD ASSEMBLY DIMENSIONAL REQUIREMENTS17007/18/2012

SECTION 20: CONSTRUCTION OF FITTINGS:1 0F 2007/18/20

_____________________________________________________________

Authorized Inspector Acceptance QCM Approval

_____________________________________________________________

DateDate

QUALITY CONTROL MANUAL

EDITION 1 REV 0 Revision Date July 18, 2012

PAGE 1 of 1

SECTION 1. TITLE PAGEQUALITY CONTROL MANUAL

FOR THE FOLLOWING CONSTRUCTION ACTIVITIESIN ACCORDANCE WITH THE ALBERTA SAFETY CODES ACT AND REFERENCED STANDARDS: SECTION VIII DIVISION 1; PRESSURE VESSELS PRESSURE FITTINGS IN ACCORDANCE WITH CSA B51

BYALLIED VESSEL FABRICATION

AT

3808 46 AVE. STETTLER AB T0C 2L1AND CONSTRUCTION, REPAIR AND ALTERATIONSOF PRESSURE PIPING

IN ACCORDANCE WITH ASME B31.3 AND B31.1 INDIRECT FIRED HEATER COILS

REPAIR AND ALTERATION OF EXISTING PRESSURE VESSELSAT 3808 - 46 AVE.STETTLER AB. T0C 2L1AND FIELD SITES IN ALBERTA

CONTROLLED FROM THIS LOCATIONMANUAL NO________________

EDITION___________________

ASSIGNED TO_______________

QUALITY CONTROL MANUAL

EDITION 1 REV 0 Revision Date July18, 2012

PAGE 1 of 2

SECTION 2 - SCOPE1.This Quality Control Manual outlines the procedures that will be used by Allied Vessel Fabrication Ltd. in constructing ASME Code items in accordance with ASME Code Section VIII Division 1 and Alberta Safety Codes Act and Regulations at shop.

2.Repair and alterations to pressure vessels shall be performed in accordance with the procedures outlined in this Quality Control Manual, the requirements of Alberta Safety Codes Act and Regulations at shop and field locations.

3.Construction, repair, alteration and erection of pressure piping systems shall meet the requirements of Alberta Safety Codes Act and Regulations, ASME B31.3 and customer requirements at shop and field locations.

QUALITY CONTROL MANUAL

EDITION 1 REV 0 Revision Date July 18, 2012

PAGE 2 of 2

SECTION 2 STATEMENT OF AUTHORITY

This Quality Control Manual has been established to assure compliance with the ASME Code, CSA B51, B31.3 and the Alberta Safety Codes Act and Regulations.

This Quality Control Manual is intended to be used in the construction of pressure vessels in accordance with the ASME Boiler and Pressure Vessel Code Section VIII Division 1. Repairs and alternation of pressure vessels in accordance with Alberta Safety Codes Act and Regulation. Construction, repair, alteration and erection of pressure piping systems in accordance with B31.3 Code and Alberta Safety Codes Act and Regulations. The QCM is hereby assigned to administer the program described in this Quality Control Manual. The QCM has sufficient and well-defined responsibility, authority and the organizational freedom to identify quality control problems, to initiate, recommend or provide solutions to quality control problems and to ensure implementation of solutions. The QCM shall control the disposition of non-conforming items and issues until the non-conformance has been removed.

The quality control problems that cannot be resolved by the QCM shall be brought to my attention for the final resolution. Such resolution will not compromise any applicable codes, standards, Regulatory Authority, customer requirements or this Quality Control Manual.

The quality control system has my full support and shall be used in all stages, by all personnel engaged in fabrication, repairs and alternations, construction, testing and manufacturing of referenced above pressure equipment.

Any person assigned a responsibility within this Quality Control Manual may delegate the performance of the activity to another qualified person. However the responsibility remains with the individual assigned.

STATEMENT OF AUTHORITY

Signature_____________________________

Name _______________________________

Title ________________________________

Date_________________________________QUALITY CONTROL MANUAL

EDITION 1 REV 0 Revision Date July 18, 2012

PAGE 1 of 1

SECTION 3 ORGANIZATION CHART

Note: One person may hold more than one position

* Communication

QUALITY CONTROL MANUAL

EDITION 1 REV 0 Revision Date July 18, 2012

PAGE 1 of 4

SECTION 4 DEFINITIONS

4.DEFINITIONS

4.1Alberta Safety Code Act and Regulations:

a) Alberta Safety Codes Act

b) Pressure Equipment Safety Regulations

c) Pressure Welders Regulations

d) Pressure Equipment Exemption Order

e) Administrative Items Regulation.

4.2 ABSA: ABSA is a regulatory organization delegated by the Province of Alberta to provide pressure equipment safety services under the Alberta Safety Codes Act, and act as the Sole Jurisdiction /Regulatory Authority as defined in the CSA B51 Code and as accredited by ASME.4.3 Alteration: Any change in the item described on the original Manufacturers Data Report. Any change which affects the pressure containing capacity of a boiler, pressure vessel, piping or fitting. Non-physical changes such as increase in the maximum allowable working pressure (internal or external) or design temperature of a pressure item shall be considered an alteration. A reduction in the minimum design metal temperature of a pressure item shall be considered an alteration. 4.4 AQP: Means Alberta Quality Program number issued by ABSA. A company holding a valid AQP number from ABSA is qualified to undertake activities that are authorized by the Certificate of Authorization Permit.4.5Code: American Society of Mechanical Engineers, latest Edition and Addenda of:

a) Section II Material Specifications Part A, B, C & D

b) Section V Non-Destructive Testing

c) Section VIII Division 1 Rules for Construction of Pressure Vessels

d) Section IX Welding and Brazing Qualifications

e) Section B31.3 Process Piping

4.6Authorized Inspector (AI):

An inspector, regularly employed by the ASME Accredited Authorized Inspection Agency, who is qualified by written examination in accordance with the ASME QAI-1 Standard. The AI Inspector shall hold a valid National Board Commission and Endorsement and is also a Safety Codes Officer appointed to administer the Alberta Safety Codes Act.

4.7 CGSB: Canadian General Standards BoardQUALITY CONTROL MANUAL

EDITION 1 REV 0 Revision Date July 18, 2012

PAGE 2 of 4

SECTION 4 DEFINITIONS

4.8CRN: Canadian Registration Number; registration number allotted by the regulatory authority to

design and specifications when accepted and registered.

4.9 CSA-B 51 Canadian Standard Association; Boiler, Pressure Vessel and Pressure Piping Code.

4.10 Examination means quality control functions performed by the manufacturer, fabricator, or erector.4.11Expansible Fluid:

Expansible Fluid meansa) a vapor or gaseous fluid orb) a liquid under pressure and at a temperature at which the liquid changes to a gas or vapor when the pressure is reduced to atmospheric pressure or when the temperature is increased to ambient temperature.

4.12 Fitting or Pressure Fitting: Fitting means a valve, gauge, regulating or controlling device, flange,

pipe fitting or any other appurtenance that is attached to, or forms part of, a boiler. pressure vessel, indirect fired heater pressure coil, thermal liquid heating system or pressure piping system.4.13Inspection: means functions performed for the Owner by the Owners Inspector or inspectors

delegate.4.14Job File: A file which contains all records documenting quality control for the item constructed.

This file shall be assigned a unique number to identify the job.4.15NDE: means Nondestructive Examination conducted in accordance with the requirements

of the ASME Section V Code.4.16Non-conformance: Any condition which renders an item unacceptable or indeterminate for use because it does not comply with Code, owners specifications, design specifications or the requirements of this Quality Control Manual. Examples of non-conformance include physical defects, test failures, improper documentation, and loss of material identification.

4.17 Owners Inspector - An Inspector designated by the owner to certify that all required examinations and testing have been completed. For the inspections of piping systems, OI shall satisfy them self that the piping system conforms to all Code and customer requirements.

QUALITY CONTROL MANUAL

EDITION 1 REV 0 Revision Date July 18, 2012

PAGE 3 of 4

SECTION 4 DEFINITIONS

4.18 PQ Performance Qualification: The demonstration of a welder or welding operator skill and ability to produce welds in accordance with WPS.(see 4.31)4.19 PQR: Procedure Qualification Record: The document that records the test results that establish the properties of a weldment.4.20Pressure Equipment: means a thermal liquid heating system and any containment for an expansible

fluid under pressure, including but not limited to, fittings, boilers, pressure vessels and pressure

piping systems, as defined in the regulations.4.21PESR: means Pressure Equipment Safety Regulation, Alberta Regulation 49/2006.4.22Pressure Piping System: (Under the Jurisdiction of the Safety Codes Act) Pressure piping systems means pipes, tubes, conduits, fittings, gaskets, bolting and other components that make up a system for the conveyance of an expansible fluid under pressure and may also control the flow of that fluid. The Pressure Equipment Safety Regulation does not apply to a pressure piping system that is fully vented or operating with one or more pressure relief devices with a set pressure not exceeding 15 psi (103 kPa) and sized so that the operating pressure cannot exceed 15 psi (103 kPa). The Safety Codes Act and Pressure Equipment Safety Regulation (PESR) do not apply to pressure piping under the jurisdiction of the Alberta Oil & Gas Conservation Act and Regulations or the Alberta Pipeline Act and Regulation (see ERCB Directive 077). There is also a partial exemption from some requirements of the PESR for pressure piping meeting the requirements of PESR paragraph 4(2). 4.23 Pressure Vessel: Means a vessel used for containing, storing, distributing, processing or otherwise

handling an expansible fluid under pressure. 4.24QC: Quality Control (part of QMS focused on fulfilling quality requirements).

4.25 QMS: Quality Management System for the purpose of directing and controlling an organization

in regards to quality4.26QCM (Quality Control Manager)

An employee of Allied Vessel Fabrication Ltd. designated by the President or General Manager to have the responsibility and authority to maintain this Quality Control System, and the organizational freedom to recognize quality control problems and provide solutions to those problems.4.27 Quality Control Inspector; QCI: An employee of Allied Vessel Fabrication Ltd. designated by the QCM to perform the quality control duties as defined in this Quality Control Manual. The QC Inspector reports directly to the QCM on any quality related function. QUALITY CONTROL MANUAL

EDITION 1 REV 0 Revision Date July 18, 2012

PAGE 4 of 4

SECTION 4 DEFINITIONS

4.28 Registered Design: Drawings, specifications and information required by Section 15, of the Pressure Equipment Safety Regulation that have been reviewed and registered by ABSA.

4.29 Repair - The work necessary to restore a pressure item (e.g. boiler, pressure vessel, and piping) to a safe and satisfactory operating condition, providing there is no deviation from the original design.

4.30 SNT-TC-1A Latest construction code accepted edition addenda of the American Society for Qualification in Non-Destructive Testing; Recommended Practice No. SNT-TC-1A: Personnel Qualification and Certification in Nondestructive Testing.

4.31 WPS: Welding Procedure Specification: This document describes in detail all of the variables, which are essential, supplementary essential, and non-essential to the welding process employed by the ASME Code, Section IX.QUALITY CONTROL MANUAL

EDITION 1 REV 0 Revision Date July 18, 2012

PAGE 1 of 1

SECTION 5 TENDER & CONTRACT

5.TENDER AND CONTRACT

5.1This section describes the method of carrying out a tender and contract review, in order to ensure that contractual requirements can be met before contract is accepted.

5.2Upon the receipt of a tender, the General Manager shall define the scope of the project, the time and tender submissions and the requirements for preparation and review in consultation with:

1) President

2) QCM5.3Before accepting the contract, the General Manager shall review the contract to ensure its conformance with the tender. All discrepancies and deficiencies between the tender and the contract shall be resolved and accepted by the customer and Allied Vessel Fabrication Ltd.

5.4The contract shall be then presented to the General Manager of Allied Vessel Fabrication Ltd. for final approval.

QUALITY CONTROL MANUAL

EDITION 1 REV 0 Revision Date July 18, 2012

PAGE 1 of 2

SECTION 6 MANUAL CONTROL6.MANUAL CONTROL

6.1This section describes the system for preparing, revising and controlling the distribution of this Quality Control Manual.

6.2The QCM is responsible for the control and implementation of this system. These duties include:

a) The review the Quality Control Manual every 12 months coincident with the issue of any ASME Code Edition and to revise the Quality Control Manual and or system as necessary to incorporate any required changes within six months of the issue of the new Edition or Addenda. The review of Code Editions or Addenda shall be documented by initials and date of the person performing the review on the summary of changes page for each Code section.

b) The QCMs approval and AI acceptance shall be by signature and date on the Table of Contents.c) Approving all proposed changes and ensure that all revisions have been presented to and accepted by the AI prior to implementation.d) Maintaining a list of controlled Quality Control Manual holders showing assigned Quality Control Manual number and revision status and to distribute revisions to each Quality Control Manual holder using the Document Transmittal Form (Exhibit 6.1).e) The Quality Control Manual shall be revised by section including the Exhibits and the Table of Contents.f) The Quality Control Manual Edition shall be updated coincident with each Audit/Review6.3 The edition number, revision number and date will be shown on each page of the Quality Control Manual along with number of pages within each section, and revisions will also be indicated by a triangle, with the revision number in each margin along the changed paragraph.

6.4 Uncontrolled Quality Control Manuals may be used for information only and shall not be used by Allied Vessel Fabrication Ltd. Personnel. Uncontrolled Copy shall be permanently indicated on the front page of these Quality Control Manuals.

6.5ABSA AB forms used shall be identified through the Quality Control Manual but will not be shown as Exhibits. Only the latest ABSA forms will be used.

APPLICABLE DOCUMENTS/FORMS Document Transmittal, Exhibit 6.1

QUALITY CONTROL MANUAL

EDITION 1 REV 0 Revision Date July 18, 2012 PAGE 2 of 2

EXHIBIT 6.1 DOCUMENT TRANSMITTAL

Allied Vessel Fabrication Ltd.

DOCUMENT TRANSMITTAL

To: Please Print Your Company Name Below: DATE:

The following copies of controlled documents are forwarded to you for your use. Please sign and

return this transmittal sheet within 7 days to [email protected] or fax it to 403-228-4009.

I acknowledge receipt of the documents noted below (destroying superseded documents)

Print Receivers Name: _______________________________________

Receivers Signature :_________________________________________ Date ___________________

Document NumberDocument TitleRevision #

QUALITY CONTROL MANUAL

EDITION 1 REV 0 Revision Date July 18, 2012

PAGE 1 of 4

SECTION 7 DRAWINGS & DESIGNCALCULATION7. DRAWINGS & DESIGN CALCULATION

7.1This section provides the system for review, approval, distribution and retrieval of drawings, design

calculations, specifications and instructions.

7.2The QCM is responsible for ensuring the following functions are performed by the subcontract Engineering (Designer) acting on behalf of Allied Vessel Fabrication Ltd. or when the design is supplied by the customer, that the functions are completed by the customer:

a) Review the customer specifications to ensure that the vessel can be designed and constructed in

accordance with the ASME Code, additionally the Designer shall determine the system of units to be used consistently throughout construction of the Code items. (IE: metric or US Customary)b) Verifying drawings to ensure that the following are included:

a title block identifying the vessel

drawing number and revisions

date and job number and/or serial number detailed drawings showing dimensions and orientations with tolerances where applicable material list (Bill of Material) with material specifications acceptable by Code in consistent units of measurement material thickness, nozzle details and corrosion allowance

Maximum Allowable Working Pressure (MAWP) at coincident Max. Design Temp. Max. Allowable External Working Pressure (if a design condition) and Minimum Design Metal Temp. (MDMT) at MAWP.

Code Edition year and Addenda

NDE and heat treatment requirements

Weld details and welding procedure specifications

Notes detailing any supplementary requirements

Hydrostatic test pressure

CRN

Impact test requirements or exemptions from Impact Testing

Notes identifying additional requirements.

c)Submission of the drawings and specifications in duplicate to ABSA or applicable jurisdiction for acceptance and registration. The design Registration application AB-31 will accompany the drawings and calculations.QUALITY CONTROL MANUAL

EDITION 1 REV 0 Revision Date July 18, 2012

PAGE 2 of 4

SECTION 7 DRAWINGS & DESIGNS

CALCULATION7.3 The design specifications and drawings are subcontracted to a Designer:

a) Prepares design calculations and drawings in accordance with the ASME Code.b)Coincident with the issue of a New Code Edition or Addenda, the Designer reviews the master document to ensure compliance with any changes to the Code. The program is ran using standard test data from Appendix L Example L-7-2 and visually compare the results in the formulas to the numbers in the Code example to verify the program is operating correctly. At this point the program is password protected again.c) Review of computer programs annually to coincide with Code revisions and to alter the program to meet Code requirements or if the computer program has any updates or changes.

d) Installation of a safeguard system to prevent tampering with the programs.e) Prior to reissuing drawings for previously designed vessels or issuing new drawings based upon the existing design drawing, the Designer will review and revise as necessary, the design drawings and design calculations to ensure compliance with the latest mandatory Code Edition and Addenda. The Designer sends verification that all designs comply with the latest Code Edition and Addenda.7.4 A description of all revisions to drawings will be recorded in the revision block and all revision

items will be identified with a triangle, containing the revision number, adjacent to the revised item.

Revised items will be distributed and issued in the same manner as the original issue. 7.5If the design specifications and drawings are provided by the owner, or are subcontracted to a engineering design organization, the QCM is responsible for:

a) Reviewing and approving by signature and date the drawings and calculations.

b) Ensuring that the drawings representing the design have been accepted and registered by the jurisdiction where the vessel is to be located.

7.6The QCM will maintain a Drawing Index (Exhibit 7.1) detailing the drawing title, drawing number, revision number, issue, number of copies and person they are assigned to. All essentialdocuments to outside organizations will be controlled by use of Document Transmittal (Exhibit 6.1). The QCM is responsible for control of documents at shop and field sites. He will issue the latest Revisions and recall and destroy all superseded documents. One copy of each superseded document Marked VOID shall be kept in the job file for reference. Issued for Construction will be stamped on all drawings followed by the signature and date of person releasing the drawings.QUALITY CONTROL MANUAL

EDITION 1 REV 0 Revision Date July 18, 2012

PAGE 3 of 4

SECTION 7 DRAWINGS & DESIGNCALCULATION7.7The QCM is responsible for assigning the job and serial numbers for all vessels. He/she will maintain a file for each vessel containing design calculations, drawings and specifications.

7.8The QCM will ensure that the latest Editions and Addenda of the ASME Codes are available in the shop and field.

APPLICABLE DOCUMENTS/FORMS

Document Transmittal, Exhibit 6.1

Drawing Index Exhibit 7.1

ABSA FORMS

Design Registration Application, AB-31QUALITY CONTROL MANUAL

EDITION 1 REV 0 Revision Date July 18, 2012Section 7

PAGE 4 of 4

EXHIBIT 7.1 DRAWING INDEX

DRAWING INDEX

Job Number: Copies To Field

Copies ToABSA

Copies ToEng. File

Copies ToPurch. Mgr.

Copies ToShop Mgr.

Copies ToQCM

DateIssued

DrawingTitle

Rev. No.

Drawing Number

QUALITY CONTROL MANUAL

EDITION 1 REV 0 Revision Date July 18, 2012

PAGE 1 of 7

SECTION 8 MATERIAL CONTROL8.MATERIAL CONTROL8.1This section describes the system of controlling, ordering, receiving, identification and use of all Code material in compliance with ASME Code and design specification requirements.

8.2The Purchasing Manager is responsible for the ordering of all material. The Purchasing Manager will prepare a Purchase Order (Exhibit 8.1) from the approved drawing Bill of Material.. The Purchase Order will include (as applicable):

a) the Purchase Order number and job number (unless ordered for stock).b) the material ASME specification number (SA/SB), grade, schedule, dimensions,

c) a request for Material Test Report (MTR) when required,

d) a request for Partial Manufacturers Data Report or Certificate of Compliance for all code stamped and standard welded parts supplied by a subcontractor,e) a request for certification to UG-79 and referenced paragraphs for formed items.

f) a request that tack welds be performed to a Welding Procedure Specification qualified to ASME Section IX.

g) a request for certification for any supplementary test (I.e. impacts),

h) heat treatment requirements,

i) NDE requirements,

j) Statement that all fitting designs must be registered with ABSA.

k) The SFA Specification and AWS Classification on all Purchase Orders for welding consumables.l) A requirement that all Code required material markings must be accurately transferred to formed material or if a Coded Marking System is used to maintain traceability to the original Code required markings and the MTR, the Coded Marking System used must have prior acceptance by Allied Vessel Fabrication Ltd. and the AI

8.3The Purchase Order will be issued by Purchasing Manager and the QCM will review prior to issue. When Code materials are ordered an attachment to the Purchase Order titled Purchase Requirements by Product Form (Exhibit 8.2) shall be used to convey mandatory requirements. One copy of the Purchase Order will be issued to the Vendor, one copy will be kept in the Purchasing File, one copy to the Shipper/Receiver and one copy will be sent to the QCM.

8.4Material substitutions must be approved by the QCM, the customer, Designer and accepted by the AI. Approved material changes will be noted on the drawing. Revised calculations and drawings will be prepared and issued in accordance with this Quality Control Manual.

QUALITY CONTROL MANUAL

EDITION 1 REV 0 Revision Date July 18, 2012

PAGE 2 of 7

SECTION 8 MATERIAL CONTROL8.5 The Shipper/Receiver is responsible for receiving of all materials.

His duties include:

a) Checking all Code materials received against Purchase Order, packing slip, and MTR, Examining the material for visible damage, correct identification, Code required markings, ASME specification & grade and quantity.

b) Identifying all acceptable material ordered with the Purchase Order number.

c) Recording the Code required markings, material specification number, grade, thickness etc. on a Material Receiving Report (Exhibit 8.4). Heat and slab number shall also be recorded for all head, shell and plate material.d) Ensuring that all pipe material is color coded by a stripe over the full length. The Color Code Chart (Exhibit 8.3) shall be posted in the storage area and the shop area. Pipe material used for a vessel shells will be identified with a heat number and supported by a MTR.e) Ensuring that flanges and fittings are identified by Purchase Order number and stored by the job.

8.6The QCI responsible for identification and traceability of all materials.

His duties include:

a) Recording the material specification number, grade, and the code required material identification

markings verified thickness as listed on the Travel Sheet (Exhibit 9.1). When the materials are examined prior to fabrication. the QCI shall confirm that the material identification markings match the MTRs or Manufacturers Partial Data Reports and shall also ensure that all plate material used as a pressure retaining component and any other material for vessel, shells, heads or nozzle reinforcing pads, remain traceable to the material properties as described in MTR b) Examining all material for the purpose of detecting imperfections that would affect the safety of

the Code item and verifying that the material is as specified on the drawings and conforms to

Code requirements. If material defects are detected, if the material is not in full conformance

with Code requirements or if further material testing is required then the material shall be

identified as nonconforming and handled as described in Section 11.

c) Ensuring that in addition to the material tabulation on the Travel Sheet, Code required material identification markings are transferred before dividing any material so that each piece will be identified visibly on the completed vessel.QUALITY CONTROL MANUAL

EDITION 1 REV 0 Revision Date July 18, 2012

PAGE 3 of 7

SECTION 8 MATERIAL CONTROL

d) Ensuring that all identification markings are transferred prior to dividing any plate or pipe material, so that each piece will be identified on the completed vessel. The identification will be stamped on carbon steel plate over 1/4 thick and written by water proof marker on other material and the information will also be recorded on a drawing of the vessel.

e) Verifying that the MTRS conform to ASME Code Section II same Edition and Addenda as on the drawing. If the MTRS conform to Section II, the QCI will sign and date the MTR and indicate the Code Edition and Addenda used.f) Ensuring that when pipe material, which will have a Heat # and Purchase Order # at each end and is color coded by a paint strip over the full length, is fabricated as a nozzle: that the marking is stamped on each nozzle as per color code chart (Exhibit 8.3).g) Maintain traceability to Code required identification markings for all pressure fittings used on a Code item. For product form such as couplings or threadolets, if the original fitting manufacturers markings will be obscured by construction then after the fitting is attached to the code item all of the original Code required identification markings will be recorded on the Material Sheet in the applicable row for the item.h) Ensuring that the color code and coded markings detailed in Exhibit 8.3 are posted in the storage area and the shop.

i) Alternate marking system shall be acceptable to the AI.8.7Material purchased for stock, customer supplied material, or excess material remaining from previous jobs may be used for construction of Code items providing the material is re- inspected and MTRS are verified to the Code Edition/Addenda specified on the construction drawing.

APPLICABLE DOCUMENTS/FORMS

Purchase Order, Exhibit 8.1

Purchase Requirements by Product, Exhibit 8.2 Color Code and Code Markings, Exhibit 8.3 Material Receiving Report, Exhibit 8.4 Travel Sheet Front,

Exhibit 9.1

Material Sheet (Back)

Exhibit 9.1 QUALITY CONTROL MANUALEDITION 1 REV 0 Revision Date July 18, 2012

PAGE 4 of 7

SECTION 8 MATERIAL CONTROL

Exhibit 8.1Allied Vessel Fabrication Ltd.PURCHASE ORDER

Page 3 of 7

p.o. #

Job#

DatE:

Billing Address: #107 535- 10Ave SW

Calgary AB T2R 0A8

vENDORSHIP TOAttn: Jeff Hagel

Allied Vessel Fabrication

3808-46 Ave.

Stettler, AB TOC 2L2Ph:1-403-740-9788

Fax:1-403-742-6400

Page:

SHIPPING METHODSHIPPING TERMSDELIVERY DATE

jobunit priceline total

subtotal

sales tax

total

PO is issued as per quote number as referenced above.

Enter this order in accordance with the prices, terms, delivery method, and specifications listed above.

Please notify us immediately if you are unable to ship as specified.

Authorized by:

Date: QUALITY CONTROL MANUALEDITION 1 REV 0 Revision Date July 18, 2012

PAGE 5 of 7

SECTION 8 MATERIAL CONTROL

EXHIBIT 8.2 PURCHASE REQUIREMENTS BY PRODUCT FORMA- Rolled Plate (Shells and rolled Plate Nozzle Reinforcing Pads)1) Materials: SA-516-70 or SA-516-70 Normalized (SA-516-70N) as specified on Purchase Order. 2) 30 degree outside bevel-no land A/A [Excluding Reinforcing Pads]3) Longitudinal seam tack-welded using a Welding Procedure Specification that meets all the requirements of ASME Section IX: one-eighth inch weld gap-no land. If the purchase order specifies welding of the longitudinal seam that manufactures Partial Data Report must be supplied for this item.4) Must conform to ASME Section VIII, Div.1 paragraphs UG-79 and reference paragraph or UHA-44 when applicable.5) All ASME Code required material markings must be accurately transferred to this item or, if a coded marking system is used to maintain traceability to the original Code required markings and material test report for formed items, the coded marking system must be accepted prior to confirming this order.

6) Material test reports must be supplied for this item(s).

7) This item(s) must meet the ASME Section II,_____Edition-____ Addenda material specification, and general specifications applicable to the product form.B- Formed Plate (Heads and Formed Plate Nozzle Reinforcing Pads)

1) Materials: SA-516-70 or SA-516-70 Normalized (SA-516-70N) as specified on Purchase Order.

2) 2:1 Semi Ellipsoidal, 2-Inch Straight Flange.

3) 30 degree outside bevel-no land A/A [Excluding Reinforcing Pads]

4) Must conform to ASME Section VIII, Div.1 paragraphs UG-79 and reference paragraph or UHA-44 when applicable.

5) All ASME Code required material markings must be accurately transferred to this item or, if a coded marking system is used to maintain traceability to the original Code required markings and material test report for formed items, the coded marking system must be accepted prior to confirming this order.

6) Material test reports must be supplied for this item(s).

7) This item(s) must meet the ASME Section II,_____Edition-____ Addenda material specification, and general specifications applicable to the product form.C- Rolled Plate (Skid Material and Rolled Plate Saddle Pads or Wear Plates)1) Materials: SA-516-70 or SA-516-70 Normalized (SA-516-70N) as specified on Purchase Order.2) 30 degree outside bevel-no land A/A [Excluding Saddle Pads or Wear Plates]

3) Longitudinal seam tack-welded using a Welding Procedure Specification that meets all the requirements of ASME Section IX: one-eighth inch weld gap-no land. [Excluding Saddle Pads or Wear Plates]

4) All ASME Code required material markings must be accurately transferred to this item or, if a coded marking system is used to maintain traceability to the original Code required markings and material test report for formed items, the coded marking system must be accepted prior to confirming this order.

5) Material test reports must be supplied for this item(s).

6) This item(s) must meet the ASME Section II,_____Edition-____ Addenda material specification, and general specifications applicable to the product form.D- Pipe

1) Materials SA-106B seamless pipe or SA-333 Gr.6 seamless pipe as specified on Purchase order.

2) Material test reports must be supplied for this item(s).

3) For cut lengths all markings required by the material specifications must be accurately transferred to this item.4) This item(s) must meet the ASME Section II,_____Edition-____ Addenda material specification, and general specifications applicable to the product form.E- Flanges and Fittings

1) Materials: SA-105 or SA-105 Normalized to Supplementary Requirements S-2 (SA-105N), SA-234-WPB, SA-350-LF2, or SA-420- WPL as specified on Purchase order.

2) Fitting design must be registered with ABSA for this item(s). Canada Registration Number(s) must be available upon request.

3) Material test reports must be supplied for this item(s).

4) This item(s) must meet the ASME Section II,_____Edition-____ Addenda material specification, and general specifications applicable to the product form.5) Unless otherwise specified all Pipe Flanges and Flange fittings shall be in accordance nwith ASME B16.5(_____).

6) Unless otherwise specified all Factory- Made Wrought Steel Buttwelding Fittings shall be in accordance with ASME B16.9(_____).

7) Unless otherwise specified all Forged Fittings, Socket-Welding and Threaded shall be in accordance with ASME B.16.11(_____).

F- Welding Consumables

1) All welding consumables mus conform to the SFA specification and AWS classification listed on purchase order.

QUALITY CONTROL MANUAL

EDITION 1 REV 0 Section: 8

Revision Date July 18, 2012

PAGE 6 of 7EXHIBIT 8.3 COLOR CODE CHARTCOLOR CODE FOR PLATE PIPE & FITTINGS

PLATE MATERIAL COLOR CODE PAINT CODEDISC

SA-36REDE164Plate

CSA G40-21 44WWHITEPlate

CSA G40.21 50WGREENPlate

SA516-70NORANGE Plate

QT-100YELLOWPlate

QT-400BLUEPlate

PIPE MATERIAL SPECIFICATIONSCOLOR CODE DIE STAMPDISC

SA/A 420 WPL 60Fitting

SA/A 350 LF21Fitting

SA/A 333 GRADE 6BLUE2Pipe

SA/A 234 WPB3Fitting

SA/A 1054Fitting

SA/A 105N4NFitting

SA/A 106 GRADE B WHITE 5Pipe

SA 53B (ERW)YELLOW 6Pipe

SS MATERIAL SPECIFICATIONS COLOR CODE DIE STAMPDISC

SA 312-304LGREEN7

SA 240-304L8

SA 479-304 NON PRESSURE 9

SA 182-30410

Other materials will have a color stripe as determined by the QCM. Each length of pipe will have a continuous stripe of the designated color.Each piece will be die stamped with indicated letter or digit code.

QUALITY CONTROL MANUAL

EDITION 1 REV 0 Revision Date July 18, 2012Section 8

PAGE 7 of 7

EXHIBIT - 8.4 MATERIAL RECEIVING REPORT

MATERIAL RECEIVING REPORT Date Initials JOBNUMBER

P.O. NUMBER

SUPPLIER

RECORD OF ACTUAL CODE REQUIRED MARKINGS[Note: The markings required by the material specification are described in the material specification and the general specification for the product form]

QUANTITY

DIAMETER

VERIFIED THICKNESS/ PRODUCT

SERIAL NUM.

QUALITY CONTROL MANUAL

EDITION 1 REV 0 Revision Date July 18, 2012

PAGE 1 of 6

SECTION 9 EXAMINATION AND INSPECTION

9.EXAMINATION AND INSPECTION

9.1This section describes the system of inspection and examination required to verify that fabrication has been completed in accordance with ASME Code and this Quality Control Manual.

9.2The QCM is responsible for the examination and inspection program. His duties include:

a. Initiating a job file, which includes the Travel Sheet, drawings, calculations, MTRs, certificates of compliance, NDE reports, Heat Treatment instructions, welder records, Manufacturers Data Reports, CRN acceptance letter and a photocopy of the name plate.b. Initiating a Travel Sheet (Exhibit 9.1) for each job and presenting it to the AI prior to the start of the job so that AI may indicate his / her hold and inspection points. Work shall not proceed beyond an established hold point until the AI has released the hold by signing the Travel Sheet.

c. Notifying the AI reasonably in advance of any hold points.

d. Performing any examination functions specified on the Travel Sheet. Signing/dating each function when is completed.. Welders symbols for specific joints shall be recorded, and visual examinations of fit-up and for type-one-joint verification shall be documented by initial to indicate completion or verification, and acceptance. 9.3In addition to the examination and inspection functions on the Travel Sheet, the QCM will ensure that:

a. All applicable material is identified on the Travel Sheet with specifications and heat numbers and that these heat numbers are transferred and remain traceable throughout construction.

b. The material contains no visible scars or defects.c. MTRs are available for all plate material, pipe and fittings used for vessel shells and additional components as required by the customer.

d. Alignment tolerances are maintained during construction.

e. Weld details are correct.

f. Non-destructive examination is performed in accordance with Section 12 of this Quality Control Manual and the Code.

g. Heat treatment charts comply with instructions.h. The correct hydrostatic test pressure is applied.

QUALITY CONTROL MANUAL

EDITION 1 REV 0 Revision Date July 18, 2012

PAGE 2 of 6

SECTION 9 EXAMINATION AND INSPECTION

9.4 The QCM shall prepare the Manufacturers Data Report, the AB-25. 9.5 The QCM will verify that the nameplate stamping information is complete and correct in the

Nameplate format (Exhibit 9.3). After the hydrostatic test has been witnessed by AI, and accepted, the QCM will certify the Manufacturers Data Report and present it along with the nameplate to the AI for acceptance and signature on the Manufacturers Data Report. 9.6The QCM is responsible for ensuring that the completed nameplate is installed on the correct vessel. Prior to installing the nameplate, the vessel serial number on the nameplate will be verified as matching the serial number which is die stamped on the vessel shell, or nameplate bracket.

Note: Manufacturers Data Reports shall not be changed or altered after they have been signed by

the QCM and the AI. If errors are found, a corrected Manufacturers Data Report must be completed and certified. 9.7The QCM will distribute the Manufacturers Data Report to:

a) The AI

b) The customer or designated agent c) The job file

d) The jurisdiction where the vessel will be located (if other than Alberta).

9.10 The AI or the AI Supervisor, reserves the right to audit this program at any time where Code work is in progress.APPLICABLE DOCUMENTS/FORMS

Travel Sheet,

Exhibit 9.1

Sample Nameplate, Exhibit 9.3

ABSA FORMS Manufacturers Data Report, for pressure vessel AB-25QUALITY CONTROL MANUALEDITION 1 REV 0 Revision Date July 18, 2012

PAGE 4 of 6

EXHIBIT 9.1 TRAVEL SHEET (FRONT)

DO NOT START CONSTRUCTION WITHOUT AI REVIEW

TRAVEL SHEET REVISION NO.:

AI REVIEW:

REVIEW DATE:

SERIAL NO.:

JOB NO.:

VESSEL TYPE:

DRAWING NO.:

DWG. REVISION NO.:

TRAVEL SHEET INITIATION BY:

Seq.ItemCommentsQCIDateAI Hold PointsAIDateOwnerDate

1.Calculations in File

2.Release of Appd Dwg.

3.Materials Examined

4.Heat Numbers Recorded

5.MTRs Checked

6.WPS(s) Checked

7.Welder(s) Qualified

8.Thicknesses Verified & Recorded

9.Shell(s) & Head(s) Fit-up Inspection

10.Nozzles & Fittings Fit-up Inspection

11.Nozzle Orientation

12.Nozzle & Flange Rating Checked

13.Impact Tests

14.Internals Checked

15.Final Internal InspectionShell Side

Tube Side

16.Weld Sizes Checked

17.Welder I.D. Checked

18.Final External Inspection

19.Radiography

20.Other N.D.E.

21.Final Ext. Prior to P.W.H.T.

22.PWHT Chart Checked

23.Hydrostatic TestShell Gauge #

Side

Tube Gauge #

Side

24.CRN DrawingCRN#

25.N.C.R. #

26.Nameplate Stamping

27.Manuf. Data Report Completed & Verified

28.Nameplate Installation

29.Hold Points Established

The AI shall be presented with the Travel Sheet prior to construction so that he can designate additional inspection points and/or Hold Points. Any revisions shall be marked with a delta symbol with revision number and described at the bottom of this page.

* Denotes an A.I. Inspection Point ** Denotes an A.I. Hold Point

QUALITY CONTROL MANUAL

EDITION 1 REV 0 Revision Date July 18, 2012

PAGE 5 of 6

EXHIBIT 9.1 MATERIAL SHEET (BACK)MATERIAL THICKNESS VERIFICATION AND IDENTIFICATIONWELD I.D. / WELDER SYMBOLS / FIT-UP

DescriptionThicknessMaterial Spec. & GradeHeat & Plate Identifieror I.D. NumberWeld I.D.Welder SymbolFit-Up Exam.Weld I.D.Welder SymbolFit-Up Exam.Verify Type 1 Joint

Shell #1L

C

Shell #2L

C

Shell #3L

C

Shell #4L

C

Shell #5L

C

Shell #6L

C

Head #1C

Head #2C

Head #3C

Head #4C

Boot #1 ShellL

C

Boot #1HeadC

Boot #2 ShellL

C

Boot #2HeadC

Cone

ConeL

L -C

ATTACHMENT AND / OR NOZZLE MATERIAL THICKNESS VERIFICATION AND IDENTIFICATIONWELDER SYMBOLS / FIT-UP

MarkMat. I.D.NeckFittingFlangeRepad or AttachmentCat. BCat. CCat. DPad OD

Spec.-Grd.

Thk./Rating

Heat# or ID

Spec.-Grd.

Thk./Rating

Heat# or ID

Spec.-Grd.

Thk./Rating

Heat# or ID

Spec.-Grd.

Thk./Rating

Heat# or ID

Spec.-Grd.

Thk./Rating

Heat# or ID

Spec.-Grd.

Thk./Rating

Heat# or ID

Spec.-Grd.

Thk./Rating

Heat# or ID

QUALITY CONTROL MANUAL

EDITION 1 REV 0 Revision Date July 18, 2012Section 9

PAGE 6 of 6EXHIBIT 9.3 NAME PLATE

QUALITY CONTROL MANUAL

EDITION 1 REV 0 Revision Date July 18, 2012

PAGE 1 of 6

SECTION 10 WELDING

10WELDING

10.1This section describes the system for controlling Welding Procedure Specifications, welding operations and welder/welding operator performance qualifications to ensure compliance with the ASME Code.

10.2The QCM is responsible for control of all Welding Procedures Specifications (WPS). His duties include:

a. Reviewing the job specifications, prior to the start of construction, to verify that WPS have been qualified in accordance with ASME Code and registered with ABSA for the work to be performed.

b. Ensuring that WPS requirements are detailed on the drawings.

c. Ensuring that WPS are detailed on WPS Index and Essential Variable Summary (Exhibit 10.1).10.3The QCM is responsible for developing and qualifying new WPS. His duties include:

a) Writing the WPS or delegating this to a qualified consultant.

b) Supervising the welding of the test coupon by Welders employed by Allied Vessel Fabrication Ltd. to ensure that it conforms to the WPS.

c) Recording the test data on the Procedure Qualification Record (PQR).

d) Subcontracting the testing of the coupons to a recognized material testing laboratory.

e) Reviewing the results and certifying the PQR.

f) Submitting the WPS and PQR with the test results to the ABSA in duplicate, for registration.

QUALITY CONTROL MANUAL

EDITION 1 REV 0 Revision Date July 18, 2012

PAGE 2 of 6

SECTION 10 WELDING

10.4The QCM is responsible for the welder/welding operator performance qualification testing and the maintenance of Welder / Welding Operator qualification records. Additionally the QCM shall instruct, assign and supervise Welding/Welder Operators. His duties include:

a. Verifying that welders have valid performance qualification card, issued by a Certified Welding Examiner and have qualified to Allied Vessel Fabrication Ltd.s WPS prior to start of work and assigning a welder to a specific work, based on the Welder/Welder Operator qualification records and Welders Log (Exhibit 10.2).

b. Maintaining a Welders Log detailing the process each welder is qualified for, essential variables, date of expiry of this PQ card (performance qualification card) and weld symbol assigned.

c. Supervising the welding of the test coupons and preparing and certifying the Welders Performance Record (QW 484 A/B or equivalent) for all welder/welding operators performance tests.

d. Ensuring that welding procedure requirements are followed and that copies of WPS (Welding Procedure Specification) are available to welders.

e. Visually examining all completed welds.

f. Ensuring that each welder is assigned a welder symbol and welds after completion are identified with the welders symbol once every 3 feet (0.9 meters) of weld. When die stamping of the ID symbols is prohibited by Code, the welders ID for each weld shall be recorded on a shop copy of the drawing and the QCI shall transfer this data to a copy of the drawing that is retained in the Quality Control Job file. The welder symbol can be reassigned after six months.g. Ensuring that all tack welds are made using WPS qualified to ASME Code Section IX, tack welds if left in place are done by welders qualified to ASME Code Section IX. Tack welds done by subcontractors shall be completely removed.h. Verifying tack welds which are not completely removed are properly prepared for incorporation into the final weld and examined visually for defects; if found defective they will be completely removed.

i. Ensuring that all weld repairs to materials are referred to AI for acceptance prior to the repair.

j. Updating the Continuity Log (Exhibit 10.3) by recording within the specified interval, when each welder or welding operation uses a welding process.

QUALITY CONTROL MANUAL

EDITION 1 REV 0 Revision Date July 18, 2012

PAGE 3 of 6

SECTION 10 WELDING

10.5A Welder or Welding Operator shall be re-qualified whenever any of the following criteria exists.1) He has not welded using a process he is qualified for a period of six months or more.2) Whenever, for a specific reason, the QCM or the AI may require re-qualification.3) Whenever there is a change in any of the Welders essential variable.

10.6The Purchasing Manager is responsible for ordering welding consumables based on inventory levels. His duties include:

a) Verifying that all Purchase Orders for welding consumables specify SFA specifications and AWS classifications.

b) Issue purchase order as per Section 8.3

10.7The Shipper/Receiver is responsible for receiving welding consumables. His duties includea) Verifying that welding consumables are identified with the correct SFA specifications and AWS classifications.b) Sign Purchase Order and Pack Memo, initial and date all boxes. 10.8The Shop Manager is responsible for:

a) Ensuring that low hydrogen and alloy electrodes are kept in heated storage in accordance with the Electrode Manufacturers specifications (typically between 200 F and 300 F) after the container seal is broken.

b) Ensuring that welders are issued with sufficient electrodes for no longer than two hours work period and that electrodes removed from the oven for more than four hours will not be used for Code work; those electrodes will be placed in a container marked: NON - CODE.c) Ensuring that submerged arc welding flux is stored in accordance with the manufacturers recommendation Hoppers, and temporary storage containers if used, shall be labeled to indicate the type of flux they contain.

10.9 The AI shall have the right, at any time, to call for a witness re-qualification

tests of the Welding Procedure Specification or any Welder / Welder Operator. APPLICABLE DOCUMENTS/FORMS

WPS Index and Essential Variable Summary, Exhibit 10.1

Welders Log,

Exhibit 10.2

Continuity Log, Exhibit 10.3

QUALITY CONTROL MANUAL

EDITION 1 REV 0 Revision Date July 18, 2012

PAGE 4 of 6

SECTION 10 WELDINGEXHIBIT 10.1 WPS INDEX & ESSENTIAL VARIABLE SUMMARY

WPS INDEX & ESSENTIAL VARIABLE SUMMARYComments

WPS Consumables

Position

P No.

Impact Tested & Temp.

PWHT

Base Metal Thickness Range

Process &Weld Deposit Thickness

W.P.S. Identifier & Revision No.

QUALITY CONTROL MANUAL

EDITION 1 REV 0 Revision Date July 18, 2012

PAGE 5 of 6

SECTION 10 WELDINGEXHIBIT 10.2 WELDERS LOG

WELDERS LOGEXPIRY DATE P.Q. CD.

GMAWX-FER

GTAWCURRENT

BACKING GAS

INSERT

CORED / SOLID

UPHILL / DOWNHILL

POSITIONS

DEPOSITTHICKNESS(In)

MINIMUMOD (In)

BACKING

FILLER METAL F NUMBER(S)

BASE METALS

PROCESS/METHOD

SYMBOL

WELDERS NAME / FILE NUMBER

QUALITY CONTROL MANUAL

EDITION 1 REV 0 Revision Date July 18, 2012

PAGE 6 of 6

SECTION 10 WELDINGEXHIBIT 10.3 CONTINUITY LOG

CONTINUITY LOG YEAR:

WELDERS NAME FILE NUMBERSYMBOLPROCESS/METHODJAN. - MAR.

APR. - JUN.JUL. - SEPT.OCT. - DEC.

Note:There must be confirmation of welding process use (i.e., continuity) in every three-month period in order to ensure that a six-month gap in continuity has not occurredQUALITY CONTROL MANUAL

EDITION 1 REV 0 Revision Date July 18, 2012

PAGE 1 OF 3

SECTION 11 NONCONFORMITIES11NON-CONFORMITIES

11.1This section describes the system for identifying, documenting and resolving non-conformities found at receiving, construction, examination or testing. 11.2 A non-conformity is any condition, which does not meet the requirements of the Code, job specifications or this Quality Control Manual. Repairs to weld metal that are identified by planned quality control examination shall be completed in accordance with the Code, this Manual, and the job specifications but need not be documented on a Non-Conformity Report (Exhibit 11.1). .

11.3Any non-conforming material found the QCM will decide if the item is to be rejected (e.g. by returning to the supplier) or if the item is to be reworked or repaired to bring it into conformance. If a decision is made to repair the material or item, a repair procedure will be developed. This repair procedure shall be approved by the QCM and the method and extent of the repair must be accepted by the AI before the start of the repair, by signature and date on the Non-Conformity report disposition section. The QCM shall prepare additional inspection functions on the Travel Sheet when applicable.11.4When non-conformity is found during construction an immediate hold shall be placed on that portion of work affected, and the QCM shall be informed immediately. The non-conformity item will be identified with a Hold Tag (Exhibit 11.2).11.5The QCM will prepare a Non-Conformity Report with details of the non-conformity and a hold notation shall be made on the Travel Sheet listing the Non-Conformity Report number. All proposed Non-Conformity Report dispositions shall have QCM approval. The Designer shall approve all proposed dispositions involving design changes. The Designer will prepare revised design calculations and drawings as outlined in Section 7 of this Manual. After receiving the specified approvals, all Nonconformity Reports indicating design changes, repairs, re-work, material substitution, or use as is dispositions shall be submitted to the AI for acceptance of the proposed disposition.11.6During any repair or re-work the QCM will ensure that the specified examinations are completed, and that the AI is notified sufficiently in advance of any additional inspection or hold points.11.7The Hold Tag shall only be removed after the non-conformity has been resolved to the satisfaction of the QCM, AI and the Owners Inspector, and they have indicated acceptance by signing off the Non-Conformity Report and Travel Sheet when applicable.

11.8The Non-Conformity Report shall be retained in the job file and in a separate Non-Conformity Report File. The QCM will periodically review all the reports and indicate corrective action if required.

APPLICABLE DOCUMENTS/FORMS

Nonconformity Report, Exhibit 11.1

Hold Tag,

Exhibit 11.2

QUALITY CONTROL MANUAL

EDITION 1 REV 0 Revision Date July 18, 2012

PAGE 2 OF 3

SECTION 11 NONCONFORMITIES

EXHIBIT 11.1 NONCONFORMITY REPORT

NCR #0005NONCONFORMITY REPORT

JOB NUMBER: SER#

DESCRIPTION OF NONCONFORMANCE:

SIGNATURE OF ORIGINATOR:

DATE:

PROPOSED DISPOSITION:

DESIGNER APPROVAL:

DATE:

QCM APPROVAL:

DATE:

AUTHORIZED INSPECTOR ACCEPTANCE:

DATE:

OWNERS INSPECTORS ACCEPTANCE:

DATE:

NONCONFORMANCE RECTIFIED: DATE:

QCM APPROVAL:

DATE:

AUTHORIZED INSPECTOR ACCEPTANCE:

DATE:

OWNERS INSPECTORS ACCEPTANCE:

DATE:

QUALITY CONTROL MANUAL

EDITION 1 REV 0 Revision Date July 18, 2012

PAGE 3 OF 3

SECTION 11 HOLD TAGEXHIBIT 11.2

HOLD

DO NOT USE

SIGNATURE:

DATE:

JOB NO.:

THIS ITEM OR PART IS NOT TO BE

USED FOR THE REASONLISTED ON

THE NONCONFORMITY REPORT:

NONCONFORMITY REPORT NO.:

WHEN THE NONCONFORMITY HAS

BEEN RESOLVED IN ACCORDANCE

WITH SECTION 11 OF THE QUALITY

CONTROL MANUAL THIS TAG MAY

ONLY BE REMOVED BY THE QUALITY

CONTROL DEPARTMENT

HOLD TAG COLOR RED

QUALITY CONTROL MANUAL

EDITION 1 REV 0 Revision Date July 18, 2012

PAGE 1 OF 3

SECTION 12 NONDESTRUCTIVE EXAMINATION

12 NONDESTRUCTIVE EXAMINATION

12.1This section describes the system of ensuring that nondestructive examination are completed in accordance with the Construction Code and ASME Code Section V as referenced by the applicable Construction Code.12.2The QCM is responsible for appointing all NDE subcontractors. His duties include:

a) Reviewing the subcontractors personnel qualifications and certifications, Written Practice and NDE procedures that are approved by a Level III Examiner for compliance with the Code and the latest Construction Code accepted Edition/Addenda of SNT-TC-1A. He shall ensure that these are available to AI at his request.

b) Certifying that all personnel performing NDE shall be qualified and certified in accordance with their employers written practice and appointing, using the Certifying Statement and Appointment Letter (Exhibit 12.1) kept on file, the NDE Subcontractors Level III Examiner to act as the Level III Examiner for Allied Vessel Fabrication Ltd. There shall be evidence that the Level III Examiner has accepted the appointment. c) Ensuring that all examinations are done under the supervision of a Level II or Level III Examiner.

d) Ensuring that all interpretations are done by a Level II or Level III Examiner.e) Ensuring and certifying on the Certifying Statement and Appointment Letter that all qualified NDE procedures for Code required Ultrasonic Examination (UT), Magnetic Particle (MT), and Liquid Penetrant (PT) are demonstrated to the satisfaction of the AI prior to use. Any change in NDE procedure essential variables shall require re-qualification of the procedure and demonstration to the satisfaction of the AI prior to the use of the revised procedure. 12.3The QCI is responsible for liaison with the NDE subcontractor. His duties include:

a) Reviewing the qualifications of the NDE Examiners for conformance to this Quality Control

System.

b) Notifying the NDE Examiners of NDE requirements

QUALITY CONTROL MANUAL

EDITION 1 REV 0 Revision Date July 18, 2012

PAGE 2 OF 3

SECTION 12 NONDESTRUCTIVE EXAMINATION

12.3c) identifying the welds to be examined.

d) Maintaining traceability of reports to their locations on the vessel by stamping the weld number

on the vessel or by recording on a weld map or as built drawings and retain in job file.

e) Reviewing and accept all NDE reports and radiographic film by signature and making these

available to the AI for review and acceptance.

f) Filing all NDE reports and forwarding these to the QCM when the job is completed.

12.4The AI may require re-qualification of NDE Personnel or procedure for cause.

APPLICABLE DOCUMENTS/FORMS

Certifying Statement And Appoint Letter, Exhibit 12.1

QUALITY CONTROL MANUAL

EDITION 1 REV 0 Revision Date July 18, 2012

PAGE 3 OF 3

EXHIBIT 12.1 CERTIFYING STATEMENT

AND APPOINTMENT LETTER

I have reviewed the:Written Practice

(Edition Number and Revision Number of Written Practice)

NDE Procedures

(Method and Edition Number and / or Revision Number of Written Procedures)

And personal certification records and vision Examination records of all examiners that will perform NDE at Allied Vessel Fabrication Ltd.

For:_____________________________________________________________________________________

(Name and Address of NDE Company)It is my opinion that the specified NDE procedures are in accordance with ASME Section V Requirements as referenced by the applicable construction Code and that the Written Practice complies in all respects with the requirements of the construction Code accepted Edition/ addenda of SNT-TC-1A. Based Upon my review of the above referenced documents I hereby certify that personnel performing and evaluating NDE have been qualified and certified in accordance with their employers written practice and that the demonstration of the procedure(s) to the satisfaction of the AI, as required by the ASME Code, Section V, paragraph T-150, has been completed as specified within the (Name of Company) written Quality system. Therefore:_________________________________________

______________________________________

(Name of NDE Company) are hereby appointed (RT, UT, PT, MT, ET, VT, and or LT)

to perform

For:

______________________________________________________________________________________________________

(Name of the Manufacturer)

Appointment of Level III Examiner

_________________________________________is by this statement appointed to act as the Level III Examiner on behalf of:

(Name of Level III Examiner)_________________________________________ in the following methods: _______________________________________

(Name of the Manufacturer)

(RT,UT,PT,MT,ET,VT, and/orLT)

_________________________________________ (Date) ________________________________________

(Signature of QCM

(Appointment Expiry Date)

Level III Examiner Acceptance of Appointment

I hereby accept the appointment as indicated above

________________________________________

QUALITY CONTROL MANUAL

EDITION 1 REV 0 Revision Date July 18, 2012

PAGE 1 OF 2

SECTION 13 HEAT TREATMENT13HEAT TREATMENT

13.1This section describes the procedure that will be used to ensure that heat treatment is performed in accordance with Code and job specifications.13.2Heat Treatment of Code items will be subcontracted.13.3The QCM will review and accept the subcontractors facilities and written procedures and ensure that the furnace instrumentation is properly calibrated. The acceptance and approval of facilities and procedures shall be documented on a copy of the subcontractors procedures that are maintained on file.13.4The QCM will issue the written Heat Treatment Instructions (Exhibit 13.1) to the subcontractor specifying holding time, holding temperature, heating rate, cooling rate, and any special instructions.

13.5The QCI will ensure that all items to be sent out for heat treatment are properly identified by die stamping or heat resistant marker.

13.6The QCI will notify the subcontractor when the vessel is ready for heat treatment and will review the procedures used by the subcontractor.

13.7After completion of heat treatment, the QCI will inspect the vessel for proper identification and any damage, and review all time temperature charts for legibility and compliance with written instructions. The charts will be identified with the vessel (or item) serial number and shall be signed and dated by the subcontractors representative and the QCI.

13.8The QCI will file the instructions and time temperature charts in the vessel file which will be made available for the AI for review.

APPLICABLE DOCUMENTS/FORMS

Heat Treatment Instructions, Exhibit 13.1

QUALITY CONTROL MANUAL

EDITION 1 REV 0 Revision Date July 18, 2012

PAGE 2 OF 2

SECTION 13 HEAT TREATMENT

EXHIBIT 13.1 HEAT TREATMENT INSTRUCTIONS

HEAT TREATMENT INSTRUCTIONS

Heat Treatment Company__________________________ P.O.___________

Vessel Description________________________________ Job#___________

Diameter____________ Length______________________ Weight_________

Shell Thickness_____________________ Head Thickness_______________

1) Temperature to be raised from_____F to______ F (_____C to_____C)

at a maximum rate of __________F (___________C) per hour divided by the maximum metal thickness of the shell or head in inches.2) Temperature to be held at ________F plus_______F, minus_________F

(at______C plus______C, minus_______C) for_________minutes.

3) Temperature to be lowered from__________F to____________F

(_______C to_______C) at a max. rate of _____F (_________C) per hour divided by the maximum metal thickness of the shell or head in inches.

4) Additional requirements___________________________________________

___________________________________________________________________________________________________________________________________________________________

Heat Number:_____________________________________________________

Operators signature_____________________ Date__________________

QCM___________________________ Date__________________

***************************************************************************************************************Comments:_______________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________QUALITY CONTROL MANUAL

EDITION 1 REV 0 Revision Date July 18, 2012

PAGE 1 OF 2

SECTION 14 MEASURING AND TESTING EQUIPMENT14.MEASURING AND TESTING EQUIPMENT14.1The purpose of this section describes the control and calibration of measuring and testing equipment to ensure Code compliance.

14.2The QCM is responsible for the control of measuring the test equipment. His/Her duties include:

a. Ensuring that all gauges and recorders are identified with a serial number and calibration date.

b. Maintaining calibration records pertaining to measuring and test equipment which will include a list of all measuring and test equipment for Code use, and an Equipment Calibration Log (Exhibit 14.1) and calibration reports for each item. (Pressure gauges must be calibrated against a dead weight tester that has a calibration record, traceable to National standard.) The maximum interval between calibrations shall be twelve months. If the item has not been used since the last calibration, the QCM upon satisfactory examination of the gauge will change the calibration date to one year, from the date of use.

14.3The QCI is responsible for the use of test equipment. His/Her duties include:

a) Examining the equipment for visible damage and calibration status.

b) Recording the date of first use of equipment after calibrations, on the Equipment Calibration Log.c) Ensuring that the range of the gauge is between 1.5 and 4 times the test pressure.

d) Returning all equipment to the storage area after the test.a) Identifying any equipment that requires recalibration.14.4 Code items that are inspected or tested with measuring and test equipment found to be out of calibration shall be re-inspected or re-tested, and documented as nonconformity in accordance with Section 11 of this Quality Control Manual.a) In the event the Code Item has left our possession, the QCM would notify the owner of the nonconformance and the item would be re-inspected or retested, and documented in accordance with Section 11 of this Quality Control Manual.APPLICABLE DOCUMENTS/FORMS

Equipment Calibration Log, Exhibit 14.1

QUALITY CONTROL MANUAL

EDITION 1 REV 0 Revision Date August 05, 2009 SECTION 14 Page 2 of 2

EXHIBIT 14.1 EQUIPMENT CALIBRATION LOG

EQUIPMENT CALIBRATION LOG

EQUIPMENT DESCRIPTION:

IDENTIFICATION NO.:CALIBRATION INTERVAL:

Calibration Date Calibration Record VerifiedDate of First Use Calibration Expiry Date

Calibration Requirements And Instructions:

QUALITY CONTROL MANUAL

EDITION 1 REV 0 Revision Date July 18, 2012

PAGE 1 OF 3 SECTION 15 PRESSURE TESTS

15PRESSURE TESTS

15.1This section describes the system for conducting all pressure tests including hydrostatic, pneumatic, services and leak. Pneumatic test procedures will be submitted to ABSA Design Survey Section for acceptance prior to testing. (See Exhibit 15.1 for guidelines for pneumatic test procedure).

15.2 The QCM is responsible for the implementation of this system in accordance with the following procedures:

a) All hydrostatic tests performed in the shop/field will be undertaken with maximum regard to personnel safety. All unauthorized personnel will stay clear of the area where the test is being performed.

b) The AI will witness the hydrostatic test.

c) Air will be vented from the vessel as it is filled.

d) The metal temperature should be at least 30 F above the MDMT but not exceed 120 F for ASME Code Section VIII Division 1 pressure vessels.

e) The pressure will be increased gradually to the test pressure as stated on the accepted drawings and held1) for a minimum of 15 minutes for an item without nozzle reinforcing pads, or

2) for a minimum of 60 minutes when the item has nozzle reinforcing pads.f) Following the application of the hydro test pressure an inspection shall be made of all joints and connections. This inspection shall be made at a pressure not less than required by the applicable construction Code. The pressure will be held for a sufficient time for the AI to complete the inspection

g) Two pressure gauges will be used. They will be graduated to no less than 1.5 times and no more than 4 times the test pressure.h) Results of all pressure tests, including a record of pressure gauges used, shall be documented on the Travel Sheet and the Hydrostatic Test Report (Exhibit 15.2)APPLICABLE DOCUMENTS/FORMS

Guidelines for The Preparation of Pneumatic Test Procedure, Exhibit 15.1 Hydrostatic Test Report

Exhibit 15.2

QUALITY CONTROL MANUAL

EDITION 1 REV 0 Revision Date July 18, 2012

PAGE 2 OF 3 SECTION 15 EXHIBITS

EXHIBIT 15.1

GUIDELINES FOR THE PREPARATION OF PNEUMATIC TEST PROCEDURE

Due to the large energy storage in compressed gas and hence the potential hazard of a sudden release of this energy, pneumatic testing should be avoided if at all possible.

The testing procedure has to be submitted to the ABSA for acceptance before any testing can be carried out.

The testing procedure must be accompanied by detailed justifications why a standard hydrostatic test is not feasible.

In addition to strict adherence to the respective Code Sections (e.g. ASME Section VIII Division 1, Para UG-100 or ASME B 31.3, Para 345.5), the testing procedure should contain as a minimum the following information:

1)List of all personnel within the testing area and designated personnel in charge of testing.

2)Test boundaries of the pressure system with specified maximum pressure x volume (PV) limits, including listings of piping and/or equipment to be included in the test.

3)Test site preparations and related precautions undertaken including removal of unauthorized personnel, isolation of test site, etc.

4)Test media, pressure source and pressure and temperature ranges of testing.

5)Provision of Safety Relief Valves which must be sized to handle the maximum output of the pressure source to avoid excessive testing pressure.

6)Material specification involved in the test. For materials whose resistance to brittle fracture at low temperature has not been enhanced, test temperature above 60 F (16 C) may be considered in reducing the risk of brittle fracture during a pneumatic testing.

7)Exposure of all joints including weld joints, threaded/flanged connections, etc. All post-weld heat treatment shall be completed. Should a piping system be tested, all equipment and pressure vessels shall be disconnected from the piping or isolated by blinds or other safe means.

8)Method of testing with details of pressure steps, holding time inspection methods etc.

9)Precautions taken to prevent gas expansion temperature drop and thermal stresses due to temperature gradients.

10)Reference should be made to the Canadian Registration Numbers (CRN) of the system/vessel to be

tested.

QUALITY CONTROL MANUAL

EDITION 1 REV 0 Revision Date July 18, 2012

PAGE 3 OF 3

SECTION 15-Hydrostatic Test Report Exhibit 15.2

ALLIED VESSEL FABRICATION LTD.HYDROSTATIC TEST REPORT

DATE

SERIAL NUMBER(S):

JOB NUMBER:

VESSEL(S) DESCRIPTION:

HOLDING TIME @ TEST PRESSURE:

GAUGE SERIAL #(S) + CALIBRATION DATE:

RESULTS + COMMENTS:

DATE

Signature of QCM

DATE

Signature of Owners Inspector.

DATE

Signature of AI

QUALITY CONTROL MANUAL

EDITION 1 REV 0 Revision Date July 18, 2012

PAGE 1 OF 4

SECTION 16-REPAIRS AND ALTERATIONS16REPAIRS AND ALTERATIONS SHOP/FIELD16.1This section describes the system for controlling the repairs and alterations of pressure vessels. All other sections of this Manual apply except as modified below.

16.2All repairs and alterations shall be in accordance with Alberta Safety Codes Act and Regulations.

16.3The QCM will develop a written procedure for all repairs and alterations containing as minimum the following information:

a) Vessel description

b) Year built

c) (A) number

d) CRN number

e) Original Manufacturer

f) Owners name

g) Location of vessel

h) Detailed description of the repair/alteration procedure

i) Weld details

j) Welding procedure number

k) Material used (specification number, grade, size)

l) NDE requirements

m) PWHT requirements

n) Pressure test requirements

The Boilers and Pressure Vessels Repair and Alteration Report, (AB-230) may be used to detail the repair/alteration procedure when suitable.

16.4The QCM shall obtain acceptance of the repair or alteration procedure from the AI and the owners approval before starting work. The AI may require that the repair procedure be submitted to Design Survey Section of ABSA for acceptance.

16.5The QCM will ensure that copies of the latest repair/alteration procedure and instructions are provided to all personnel responsible for the repair/alteration.

QUALITY CONTROL MANUAL

EDITION 1 REV 0 Revision Date July 18, 2012

PAGE 2 OF 4

SECTION 16-REPAIRS AND ALTERATIONS16.6If the vessel is still under warranty, the QCM will contact the owner to obtain acceptance of the proposed work from the manufacturer.

16.7For alterations, the Designer will prepare detailed design, calculations and drawings in accordance with applicable Code Section. The QCM will submit the alteration procedure, design calculations and drawings to the Design Survey Section of ABSA for acceptance prior to starting work.

16.8Material for the repair/alteration shall be ordered in accordance with Section 8 of this Manual.

16.9Examination and inspection will be in accordance with Section 9 of this Manual. The QCM will develop for each repair/alteration the Repair/Alteration Inspection Checklist (Exhibit 16.1) and present it to the AI prior to the repair for his/her hold and inspection points.16.10When required by the AI, an identification plate will be attached to the vessel, adjacent to the original name plate with the following information:

a) Name of repair/alteration organization

b) Date and description of repair/alteration

c) MAWP and MDMTd) Job number

e) CRN number

f) Original MFG Name & Original Vessel S/N

16.11Non-destructive examination shall be performed according to the applicable ASME Code Section and Section 12 of this Manual.

16.12Heat treatment shall be in accordance with the applicable ASME Code Section and Section 13 of this Manual.

16.13The repaired/altered vessel shall be hydrostatically tested as indicated on the Repair/Alteration Report unless specifically exempted by the AI.

QUALITY CONTROL MANUAL

EDITION 1 REV 0 Revision Date July 18, 2012

PAGE 3 OF 4

SECTION 16-REPAIRS AND ALTERATIONS16.14Upon satisfactory completion of the repair/alteration, the QCM will complete and certify the Boilers and Pressure Vessels Repair/Alteration report (AB-40) and present it to the AI for his acceptance.

16.15The QCM will assign a separate job number and file for each repaired / altered item.

The file will contain the following information:

a. Drawings

b. Calculations

c. Repair/alteration procedure

d. Purchase Order

e. Material Test Reports

f. NDE records

g. Heat treatment records

h. Repair/Alteration Checklisti. Boilers and Pressure Vessels Repair and Alteration Report with Manufacturers Partial Data Reportsj. Non-conformity Report

k. Nameplate stamping facsimileAPPLICABLE DOCUMENTS/FORMS

Repair / Alteration Inspection Checklist, Exhibit 16.1

QUALITY CONTROL MANUAL

EDITION 1 REV 0 Revision Date July 18, 2012

PAGE 4 OF 4

EXHIBIT 16.1 REPAIR/ALTERATION INSPECTION CHECKLIST

Boiler Vessel TitleManufacturer / Serial Number Alberta (A) Number

AI Review:Review Date

Indicate Sequence Numbers and Hold Points Which Are Applicable By *

Seq. OperationsHold PointsComments Rep OrgABSA InspOwner Insp.

1Repair/Alteration Procedure Accepted by Authorized Inspector and Owner

2Welding Procedure Specifications Registered for Welding to be done

3Welders Have Valid Alberta P.Q. Card for work to be done

4Cracks MT/PT check after removial

5aMaterial to be used - check against PO/Drawing

5bmaterial identified with corrected SA/SB specifications and examined for defects

5cmaterial test reports checked against specifications

6aFit Up Shell courses -flush patches -heads

6btubesheet/shell-firetube

6cnozzles & fittings

7Radiographic Examination

8Ultrasonic Examinmation MT/PT

9Internal Visual after welding

10External Visual after welding

11Heat Treatment

12Hardness Test

13Hydrostatic Pressure Test Gauge No.'s

14Alternative Test (Specify)

15Alberta Repair/Alteration Form AB-40 complete

16Repair/Alteration Nameplate Attached

OUTLINE SKETCHMATERIAL USED IN REPAIR / ALTERATION

(Record Welders Symbols and Heat No.'s ) Attach Separate Sketch if requiredItemMat.'l SpecPlate & Head Heat & Plate #Thk.Sch.Rating

Shell/Patches

Heads/End

Tubesheet

Firetube

Nozzles

Fittings

Flanges

QUALITY CONTROL MANUAL

EDITION 1 REV 0 Revision Date July 18, 2012

PAGE 1 OF 2

SECTION 17-RECORD RETENTION

17RECORD RETENTION

17.1This section describes the records that will be maintained in accordance with Code requirements and this Manual as stated in scope.

17.2The QCM will ensure that the following records (as applicable) are maintained in the job file, for a minimum of five (5) years.

a) Manufacturers Data Report with attachmentsb) Manufacturers Partial Data Report with attachments.c) Design specifications for design and field construction of pressure piping systems (AB-96)

d) Drawings, design calculations and any applicable proof test records in the CRN File

e) Pressure Piping Data Reports (AB-83)

f) Material Test Reports and/or material certification

g) NDE reports

h) Heat Treatment instructions and heat treatment time-temp charts

i) Physical test reports (CVN, hardness, etc.)

j) Nonconformity report and Dispositions

k) WPSs and PQRs as recorded on the construction drawing in the WPS File

l) Post Weld Heat Treatment Records

m) Hydrostatic Pressure Test records n) Material lists, spool lists, purchase orders generated by Allied Vessel Fabrication Ltd.

o) As built drawings

p) Travel Sheet

q) Completion of Construction Form (AB-81) for piping

r) Repair/Alteration Form (AB-40) for repairs and alterations

s) Repair/Alteration Inspection Checklist.

t) PhotoCopy of Name Plateu) Repair Procedures and Records not as defined in Section 16

QUALITY CONTROL MANUAL

EDITION 1 REV 0 Revision Date July 18, 2012

PAGE 2 OF 2

SECTION 17-RECORD RETENTION

17.3 Radiographic film may be disposed of after the Manufacturers Data Reports are signed and accepted by the AI.17.4 Records documenting Welder / Welder Operator performance qualification and the continuity of those qualifications shall be maintained by the QCM for as long as the qualifications remain valid, and for a minimum of three years after the qualifications have expired or the Welder / Welder Operator have left the employment of Allied Vessel Fabrication Ltd.QUALITY CONTROL MANUAL

EDITION 1 REV 0 Revision Date July 18, 2012

PAGE 1 OF 1

SECTION 18-AUTHORIZED INSPECTORS18AUTHORIZED INSPECTORS

18.1 The purpose of this section is to describe the provisions made within this Quality Control Manual to allow the AI and the AI Supervisor to perform their duties in accordance with the Code and the Alberta Safet