TPQA - NCRMP - Quarterly Progress Report 1 for the month ending June 2013
Popular Tags:
142
in Joint Venture with Consultancy Services for Third Party Quality Audit
Transcript
Page 1: Quarterly Progress Report to the end of June 2013.pdf

in JointVenture with

Consultancy Services for Third PartyQuality Audit

Page 2: Quarterly Progress Report to the end of June 2013.pdf

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

CONTENTS

1.0 Project Background 2

2.0 Major Activities and Review Meetings of the Month 3

3.0 Out Line Tasks to be carried out 3

4.0 Activities of Third Party Quality Audit Consultant 5

Page 1 of 141

Page 3: Quarterly Progress Report to the end of June 2013.pdf

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

1. Project Background

Andhra Pradesh (AP) state has one of the longest coastal belts in India. Out of 67,362 Km of roadnetwork in the state, the nine coastal districts cover 26,000 km of road length. Every year during theperiod of April-May and September-December, cyclonic situations set in to the Bay of Bengal. Withthe recent changes in climatic conditions, the catastrophic events are increasing resulting in verydevastating cyclones like Laila, Jal etc where the loss is enormous. In the 97 years ranging from 1892to 1989, there were as many as 67 cyclones within the State.

It is essential to provide safe residential accommodation to the vulnerable population during anyeventuality or disaster due to natural calamities such as cyclones and associated tidal waves andstorm surges. The project is formulated based on experiences of Government of Andhra Pradesh inmitigating such disasters during the past and also keeping in view the existing facilities available inthe project area in Andhra Pradesh.

The Government of India has applied for a credit of US$ 255 Million equivalent from the InternationalDevelopment Association (IDA) toward the cost of National Cyclone Risk Mitigation Project (NCRMP),and it intends to apply the proceeds to payments for goods, works, related services and consultingservices under this Project.

National Cyclone Risk Mitigation Project (NCRMP) – Project Implementation Unit (PIU), AndhraPradesh, headquartered at Hyderabad has invited the consultants to submit proposals for providingthe consultancy services for Third Party Quality Audit for 9 coastal districts namely Srikakulam,Vijayanagaram, Visakhapatnam, East Godavari, West Godavari, Krishna, Guntur, Prakasam andNellore. The project “Construction of Multipurpose Cyclone Shelters, Roads to CycloneShelters, Roads to habitations, Roads & Bridges and Saline Embankments under NCRMP”is funded by International Development Association and received through Government of India. Thisconsultancy is envisaged to audit the quality of works being implemented by various line departmentsworking under PIU. To provide Consulting Services of Third Party Quality Auditor for Construction ofMultipurpose Cyclone Shelters, Roads to Cyclone Shelters, Roads to habitations, and Roads andBridges under NCRMP in 9 coastal districts The Commissioner for Disaster Management & ProjectDirector, Project Implementation Unit (PIU) NCRMP has selected Egis International in JV with EgisIndia Consulting Engineers (I) Pvt. Ltd. On 15th April’13, the Contract for Consultancy Service wassigned between The Commissioner for Disaster Management & Project Director, ProjectImplementation Unit (PIU) NCRMP and the Egis International in JV with Egis India ConsultingEngineers (I) Pvt. Ltd.

Page 2 of 141

Page 4: Quarterly Progress Report to the end of June 2013.pdf

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

2. Major Activities and Review Meetings during the Quarter-1 ending June 2013

S.No Place Date Activity

1

Nellore,Prakasam,Guntur &Krishna Districts

22.04.2013 to24.04.2013

Attended World Bank ISR mission’s visits of NCRMPworks and Sites in Nellore, Prakasam, Guntur andKrishna districts along with SPIU, PMC, EPTRI and PIUofficers

2 Hyderabad 25.04.2013 Attended World Bank ISR mission’s Review meeting heldat “H” Block in AP secretariat.

3 Preparation of Inception report, Audit strategy and Quality Assurance Plan

4 Hyderabad 15.05.2013 Inception Report and Audit Strategy for NCRMP year IIworks

5 Krishna 17.05.2013

Inspection of NCRMP works by PM, TPQA in KrishnaDistrict, conveyed a review meeting with linedepartmental Officers & Contractors of the District atMachilipatnam

6 West Godavari 18.05.2013

Inspection of NCRMP works by PM, TPQA in WestGodavari District, conveyed a review meeting with linedepartmental Officers & Contractors of the District atNarsapur, followed by site inspection in East GodavariDistrict.

7 East Godavari 19.05.2013 Inspection of NCRMP works by PM, TPQA in EastGodavari District

8 Hyderabad 20.05.2013 Submission of Quality Assurance Plan (QAP)

9 Hyderabad 20.05.2013Attended NCRMP Review meeting with all SE's of CoastalDistrict review done by Commissioner, DMA in 'H' Block,AP Secretariat, Hyderabad

10 Prakasam 23.05.2013

Inspection of NCRMP works by PM, TPQA in PrakasamDistrict, conveyed a review meeting with linedepartmental Officers & Contractors of the District atOngole

11 Prakasam &Nellore 24.05.2013 Inspection of NCRMP works by PM, TPQA in Prakasam &

Nellore Districts

12 Nellore 25.05.2013 Inspection of NCRMP works by PM, TPQA in NelloreDistricts

13 Srikakulam 06.06.2013Conducted workshop for Engineers and Contractors onQuality Assurance on NCRMP works at ZP meeting hall,Srikakulam

14 Hyderabad 15.06.2013 Attended NCRMP Review meeting at 'H' Block, APSecretariat, Hyderabad

Page 3 of 141

Page 5: Quarterly Progress Report to the end of June 2013.pdf

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

3. Outline of tasks to be carried out

The scopes of services for the Third Party Quality Audit (TPQA) assignment are

A. The consultant will prepare an inception report within 30 days from signing of the contract thatdetails the method agreed during negotiations to be employed in performing the services.

B. Assist SPIU in resolving issues related to Non compliances.

C. The field testing being conducted by the implementation staff will be observed and when doubtsarise in such observations another sample will be taken and will be tested independently to verifywhether it is as per the standards or not.

D. The consultant will review civil work components of the cyclone shelters and related roads &bridges of these buildings and compliances and non-compliances will be reported regularly to PIUand line department.

E. Consultants will visit the sites for each stage of work and audit

F. The consultant will visit the construction sites randomly without prior information to theimplementing agency, along with the regular site visits. The consultant will be submitting weeklyreports before the 3rd day of the following week. Monthly reports, quarterly reports, annualreports will be submitted as per the scheduled time plan. In case of noncompliance the consultantwill be reporting the same to the concerned SPIU representative along with photo documentationand will be suggesting the corrective measures. Regular feedback will be given with regards tocompliance of suggested corrective measures. Wherever compliances are not happening, a reportshould be submitted to the SPIU and line departments and if necessary “Stop Work” notices willbe issued through the Engineer in-charge.

G. The consultant will be presenting the quarterly review status which will be giving clear idea of thequality and quantum of work in progress. It gives a clear idea of the compliances and non-compliances of the works, the remedial measured suggested & taken up for non-compliances andthe modifications needed in the work plan basing on the experiences in the lapsed quarter.

H. The consultant will assist SPIU in ensuring the works, by way of reporting, are carried out as perspecifications, quality & quantity and towards achieving the desired results. Any defective worknoticed by the consultant shall be reported immediately and suggest corrective measures to thefield engineers, for immediate rectification and give feedback to SPIU with regards to complianceof suggested corrective measures. Wherever compliances are not happening, a report will besubmitted to the SPIU& line department.

I. The consultant will participate in the workshops / trainings administrated by the PIUs / linedepartments, quarterly and also as and when called for to give their inputs and also to act asresource persons as and when needed.

Page 4 of 141

Page 6: Quarterly Progress Report to the end of June 2013.pdf

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

J. The competency of the implementation staff will be verified and reported to SPIU and suitablesuggestions will be made.

K. The work plans of the implementation agency will be observed and suitable modifications will besuggested basing on the past experiences in the sites.

L. The consultant will prescribe suitable formats for progress reporting and the same formats will beused to report regularly.

M. The consultant will advise on the required site audit procedures for individual duties andresponsibilities, including detailed inspection schedules and check lists.

N. The Third Party Quality Audit will carry out additional tests, where a prime facie doubt arisesrelated to quality of works and / or compliance of standards using mobile laboratory available withthe consultant or nearby approved laboratories. The consultant shall advise few more labs fortesting suitably, which after the approval of the SPIU / line departments, can be used for testing.

O. Review the workers’ safety standards being followed in the construction site to avoid any type oflosses / damages, as far as possible.

P. The tests shall include all common tests as specified in Terms of Reference (ToR). Consultant willtake the samples and get it tested in accredited/approved laboratories which will be firstinspected and recommended for accrediting by Consultant under the project by SPIU. Theidentification and certification of the testing agency will be specific to the tests that can be carriedout in a particular laboratory.

Q. The Consultant will establish a mobile laboratory exclusively for Embankments.

R. Surprise field visits will be carried out without advance information to the Line departments andContractors.

S. At the end of every week the Consultant will submit a report containing the details of field visitsundertaken during the week indicating the date of visit. In addition to the site level reports andweekly report, consolidated reports would be submitted every month and quarter, compiling thefindings in the site reports, summary audit opinion, corrective actions, progress of works andissues etc. The Consultant will also make presentations on audit findings at the designated forumsas and when required by the client.

4. Activities of Third Party Quality Audit Consultant.

All the activities of TPQA consultant, such as status of TPQA visits, Quality Audit reports, NCR status

reports, status of Quality Control tests and other reports are summarized in the tables and furnished

in this Quarterly Progress Report as detailed below.

Page 5 of 141

Page 7: Quarterly Progress Report to the end of June 2013.pdf

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

Status of NCRMP Year-1 works are given in Table-1

Final QCRs to be submitted for the Year-1 works statement is given in Table-2

Spillover works statement for the Year-1 works are given in Table-3

Details of Spillover works for the year-1 works are given in Table-4

Agreements communicated for NCRMP Year-2 works statement given in Table-5

Overall statement of Agreements communicated Year-2 works + Spillover Year-1 worksstatement is given in Table-6

Status of works communicated agreements and spill over works abstract is given in Table-7

Work wise status for all 9 districts are enclosed as Annexure-A

District wise NCR submitted are enclosed as Annexure-B

District wise QC tests conducted are enclosed as Annexure-C

District wise Civil Engineers, Environmental and Social staff and Electrical engineers site visitsabstract and details of visits are enclosed as Annexure-D

District wise Surprise site visits abstract and details of visits are enclosed as Annexure-E

Statement of Quality Control Audit reports submitted by TPQA Consultant during the Quarter-1 ending June-2013 is enclosed as Annexure-F.

Photographs of TPQA visits are enclosed as Annexure-G.

Page 6 of 141

Page 8: Quarterly Progress Report to the end of June 2013.pdf

RH

B

RC

S

MP

CS

Bri

dges

Roa

ds (

R&

B)

Tota

l

RH

B

RC

S

MP

CS

Bri

dges

Roa

ds (

R&

B)

Tota

l

RH

B

RC

S

MP

CS

Bri

dges

Roa

ds (

R&

B)

Tota

l

1 Srikakulam 6 8 2 4 1 21 3 8 0 3 1 15 12 3 0 2 1 0 6 0

2 Vizianagaram - - - 2 1 3 0 0 0 2 1 3 3 0 0 0 0 0 0 0

3 Visakhapatnam 8 6 7 - - 21 8 6 5 0 0 19 14 0 0 1 0 0 1 1

4 East Godavari 2 8 3 - - 13 2 7 2 0 0 11 8 0 0 1 0 0 1 1

5 West Godavari 10 - - - - 10 10 0 0 0 0 10 10 0 0 0 0 0 0 0

6 Krishna 5 3 - - - 8 5 3 0 0 0 8 8 0 0 0 0 0 0 0

7 Guntur 3 12 - 2 - 17 3 11 0 1 0 15 6 0 1 0 1 0 2 0

8 Prakasham 14 7 2 1 - 24 14 7 2 1 0 24 20 0 0 0 0 0 0 0

9 Nellore 16 10 - - - 26 16 8 0 0 0 24 23 0 2 0 0 0 2 0

Total 64 54 14 9 2 143 61 50 9 7 2 129 104 3 3 4 2 0 12 2

Total No. of works entrusted in Year-1 = 143 nos No. of works deleted = 2 nos

No. of works completed by 14.04.2013 = 129 nos Spillover works in to Year – 2 = 143 – 2 – 129 = 12 nos

No. of works for which Final QCRs submitted = 104 nos No. of works for which Final QCRs to be submitted = 25 nos

Status of NCRMP Year-1 works up to 14.04.2013S.

no District

No. of works(Under ConcludedAgreements)

No. of works Completed No. of works under Progress

No.

of

wor

ks n

otst

arte

d

No.

of

Fina

l Rep

orts

Subm

itte

dPage 7 of 141

Vijaya.B
Typewritten text
TABLE-1
Page 9: Quarterly Progress Report to the end of June 2013.pdf

s.no

DistrictCateg

oryPackages allotted under

Phase - 1s.no Names of works under each package Work Status Remarks

1 1 Road from DPN R&B road to UddandapalemWork

completedEOAT and Approval of working

estimate waited

2 2 Road from K. Umilada Junction to Koduru (Link Road)Work

completedEOAT and Approval of working

estimate waited

3 3Road from Borubhadra, Malagam to Kollipadu via Seepuram,Gantapeta

Workcompleted

EOAT and Approval of workingestimate waited

4 1 Construction of cyclone shelter at GajapathinagaramWork

completed Approval of working estimate waited

5 2 Construction of cyclone shelter at RatnayampetaWork

completed Approval of working estimate waited

6 3 Construction of cyclone shelter at PatimeedaWork

completedworking estimate approval not

received

7 4 Construction of cyclone shelter at MullaparraWork

completedworking estimate approval not

received

8 5 Construction of cyclone shelter at BangarampetaWork

completedworking estimate approval not

received

9 RCSNCRMP/B-W/AP/RCS/

PRED/04/Uppalaguptam/0031 Road from R&B Road to Chinaraghavulapeta Cyclone Shelter

Workcompleted

Approval of working estimate waited &ATRs not received

10 NCRMP/B-W /AP/MPCS/PRED/04/ Thondangi/001

2Construction of Cyclone Shelter at Lakshmanudipeta in

ThondangiWork

completedworking estimate approval not

received

11 NCRMP/B-W /AP/MPCS/PRED/04/Thondangi/001

3 Construction of Cyclone Shelter at AvulamandaWork

completedworking estimate approval not

received

12 RHBNCRMP/B-W/AP/RHB/PRED/

07/Karlapalem/0011 Road to Kesavapuri ST Colony

Workcompleted

Approval of working estimate waited

13 3 Road from R & B Road to HanumathanagarWork

completedApproval of working estimate waited

14 4 Road from R & B Road to Adarsh nagarWork

completedApproval of working estimate waited

NCRMP/B-W/AP/MPCS/PRED/03/Nakkapalli/002

Visakhapatnam

MPCS

MPCS

EastGodavari

RCS

RHBNCRMP/B-W/AP/RHB/PRED/

01/Santhabommali/003

List of Works which are completed and final QCRs to be submitted by TPQA (awaiting approval of W.E/R.E)

Srikakulam

NCRMP/B-W/AP/RCS/PRED/07/Bapatla/004

NCRMP/B-W/AP/MPCS/PRED/03/Payakaraopeta/003

Guntur

Page 8 of 141

Vijaya.B
Typewritten text
TABLE-2
Page 10: Quarterly Progress Report to the end of June 2013.pdf

s.no

DistrictCateg

oryPackages allotted under

Phase - 1s.no Names of works under each package Work Status Remarks

List of Works which are completed and final QCRs to be submitted by TPQA (awaiting approval of W.E/R.E)

15 NCRMP/B-W/AP/RCS/PRED/07/PV Palem/001

2 Road from R&B road to MandevaripalemWork

completedApproval of working estimate waited

16 5 Road from Ganapavaram R&B Road to PedamarpuvaripalemWork

completedApproval of working estimate waited &

ATR not received

17 6 Road from R&B Road to ChinapuluguvaripalemWork

completedApproval of working estimate waited &

ATR not received

18 7 From R&B road to YaramvaripalemWork

completedApproval of working estimate waited &

ATR not received

19 8 Road from R&B Road to Pedagollapalem CSWork

completedApproval of working estimate waited &

ATR not received

20 9 Pedagollapalem PR road to BonthagoralapalemWork

completedApproval of working estimate waited &

ATR not received

21 1 Road from NH5 to MulaguntapaduWork

completedApproval of working estimate waited

22 2 Road from R&B road to ChalivendradibbaWork

completedApproval of working estimate waited

23 3 Road from Pakala R&B road to MosanaladinneWork

completedApproval of working estimate waited

24 4Road from R&B road to Binginapalli Harijanawada CycloneShelter

Workcompleted

Approval of working estimate waited

25 Nellore RCSNCRMP/B-W/AP/

RCS/PRED/09/ KAVALI/0061

Road Connecting R&B Road through Voturu Village in SPSRNellore District.

Workcompleted

Approval of working estimate waited

NCRMP/B-W/AP/RHB/PRED/08/S.Konda/002

Prakasam

RCS

RHB

NCRMP/B-W/AP/RCS/PRED/07/Karlapalem/002

Guntur

Page 9 of 141

Page 11: Quarterly Progress Report to the end of June 2013.pdf

Packages Works Packages Works Packages Works Packages Works Packages Works Packages Works Packages Works

1 Srikakulam 1 2 0 0 2 3 3 5 1 1 0 0 4 6

2 Vizianagaram 0 0 0 0 0 0 0 0 0 0 0 0 0 0

3 Visakhapatnam 1 1 0 0 0 0 1 1 0 0 0 0 1 1

4 East Godavari 1 1 0 0 0 0 1 1 0 0 0 0 1 1

5 West Godavari 0 0 0 0 0 0 0 0 0 0 0 0 0 0

6 Krishna 0 0 0 0 0 0 0 0 0 0 0 0 0 0

7 Guntur 0 0 1 1 0 0 1 1 1 1 0 0 2 2

8 Prakasam 0 0 0 0 0 0 0 0 0 0 0 0 0 0

9 Nellore 0 0 1 2 0 0 1 2 0 0 0 0 1 2

3 4 2 3 2 3 7 10 2 2 0 0 9 12

Details of Spill over (NCRMP Year-1) works which are not completed by 14.04.2013

Sl.No.

District

PR R&B I & CADTOTAL

MPCS RCS RHB TOTAL Bridges Saline Embankment

Total

Page 10 of 141

Vijaya.B
Typewritten text
TABLE-3
Page 12: Quarterly Progress Report to the end of June 2013.pdf

s.no

DistrictCateg

oryPackages allotted under

Phase - 1s.no Names of works under each package

AgreementNo. / Date

Work Status Remarks

1 1Road from R&B road Mobagam toDuubakavanipeta via Gajapathinagaram

/2010-11, Dt.30.04.2011

Work inProgress

300 mts CC road completed, GSB layingcompleted, GII spreading progress,

formation width vary from 6.00mts to7.50mts

2 2Road from Talasamudram to DolaRegulator

/2010-11, Dt.30.04.2011

Work stoppeddue to

insufficientroad width.

400mts length of road was not taken up dueinsufficient road width on canal bund.

Approval of WE with alternative proposal isawaited. 1.1 KM completed

3NCRMP/B-

W/AP/RHB/PRED/01/Polaki/005

3Road from R&B road Edulavalasa - Killamto Jonnam via Talasamudram

/2011-12, Dt.30.04.2011

Work inProgress

BT layer completed from Km 5/670 to Km7/270, and WBM Gr- III metal collection is in

progress from Km 5/000 to Km 5/670

4R&B

bridge

NCRMP/B-W/AP/Br/R&B/01/Uppugedd

a/0024

Construction of High level bridge acrossUppugedda at KM 7/6 of Srikakulammuncipal limits to Pukkalapeta viaKillipalem in Srikakulam Dt, A.P.

47/2010-2011,Dt17.12.

2010

Work inProgress

Foundation completed, Shuttering forAboutment and Piers is in progress

5 5Construction of Cyclone shelter atKollipadu

G.o rt No 451dt 06.04.2010

Work inProgress

Silt floor level slab completed. First floor slabshuttering is in progress

6 6 Construction of Cyclone Shelter at RunkuG.o rt No 451dt 06.04.2010

Work inProgress

1st floor Slab Shuttering for concrete inprogress

7Visakhapatnam

MPCSNCRMP/B-

W/AP/MPCS/PRED/03/Rambilli/004

1Construction of cyclone shelter atVenkayyapalem

/2011-12, Dt.03.10.2011

work inprogress Slabs completed, brick work to be taken up

8East

GodavariMPCS

NCRMP/B-W/AP/MPCS/PRED/ 04/

Uppalaguptam/0021

Construction of Cyclone Shelter atPedaraghavulapeta of UppalaguptamMandal

78/2011-12Dt:17.10.2011

Work inProgress

Terrace floor Beam and slab Completed. Stiltfloor & First floor Plastering and Brick work is

in progress.

9 BridgesNCRMP/B-W/AP/Br/R&B/

07/Bapatla/0114

Reconstruction of HLB @Km2/4 of Bapatla-Pandurangapuram Road across perali drain

78/2010-111.12.2010

work inprogress

Approaches is in progress

10 RCSNCRMP/B-W/AP/RCS/PRED/07/PV Palem/001

6Road from R&B Road Alluru toYadavapalem

2011-20121.11.2011

work inprogress

From Km 0.071 to km 0.125 and km 0.373 tokm 1.046 CC completed. From km 0.125 km

0.373 CC road to be done

11 3Road from @ 56/8 to C.K road toPeriyavettu kuppam cyclone shelter

14.09.2012work inprogress

Sub grade work in progress

12 2Providing BT road to Pedapannamgadu inTada Mandal

14.09.2012Work

completedRoad furniture is balance

NCRMP/B-W/AP/RCS/PRED/09/TADA/009

RCSSPSR

Nellore

Guntur

SPILL OVER (NCRMP YEAR-1) WORKS STATUS

Srikaulam

RHB

NCRMP/B-W/AP/RHB/PRED/01/Polaki/006

MPCSNCRMP/B_W/AP/MPCS/PRED/01/Santhabommalli/005

Page 11 of 141

Vijaya.B
Typewritten text
TABLE-4
Page 13: Quarterly Progress Report to the end of June 2013.pdf

Packages Works Packages Works Packages Works Packages Works Packages Works Packages Works Packages Works

1 Srikakulam 11 22 4 11 4 10 19 43 0 0 0 0 19 43

2 Vizianagaram 1 1 1 5 0 0 2 6 0 0 0 0 2 6

3 Visakhapatnam 1 1 3 4 3 5 7 10 0 0 0 0 7 10

4 East Godavari 3 5 6 9 5 8 14 22 2 2 0 0 16 24

5 West Godavari 0 0 4 9 8 24 12 33 0 0 0 0 12 33

6 Krishna 0 0 7 22 8 23 15 45 0 0 0 0 15 45

7 Guntur 2 2 2 3 1 1 5 6 1 1 0 0 6 7

8 Prakasam 0 0 3 11 8 23 11 34 1 1 0 0 12 35

9 Nellore 0 0 10 18 9 19 19 37 0 0 0 0 19 37

18 31 40 92 46 113 104 236 4 4 0 0 108 240Total

Details of Agreements Communicated by SPIU to TPQA Consultant during Quarter 1 ending with June 2013

R&B I & CADTOTAL

MPCS RCS RHB

PR

TOTAL Bridges Saline EmbankmentDistrictSl.No.

Page 12 of 141

Vijaya.B
Typewritten text
TABLE-5
Page 14: Quarterly Progress Report to the end of June 2013.pdf

Packages Works Packages Works Packages Works Packages Works Packages Works Packages Works Packages Works

1 Srikakulam 12 24 4 11 6 13 22 48 1 1 0 0 23 49

2 Vizianagaram 1 1 1 5 0 0 2 6 0 0 0 0 2 6

3 Visakhapatnam 2 2 3 4 3 5 8 11 0 0 0 0 8 11

4 East Godavari 4 6 6 9 5 8 15 23 2 2 0 0 17 25

5 West Godavari 0 0 4 9 8 24 12 33 0 0 0 0 12 33

6 Krishna 0 0 7 22 8 23 15 45 0 0 0 0 15 45

7 Guntur 2 2 3 4 1 1 6 7 2 2 0 0 8 9

8 Prakasam 0 0 3 11 8 23 11 34 1 1 0 0 12 35

9 Nellore 0 0 11 20 9 19 20 39 0 0 0 0 20 39

21 35 42 95 48 116 111 246 6 6 0 0 117 252

Details of Agreements Communicated by SPIU to TPQA Consultant during Quarter 1 ending with June 2013 + Spill over works of Year-1

Sl.No.

District

PR I & CADTOTAL

MPCS SalineEmbankment

R&B

TOTAL Bridges

Total

RCS RHB

Page 13 of 141

Vijaya.B
Typewritten text
TABLE-6
Page 15: Quarterly Progress Report to the end of June 2013.pdf

PR

R&

B -

Bri

dges

I &

CA

DD

Star

ted

Not

sta

rted

Pro

gres

s

Com

plet

ed

Stop

ped

/D

elet

ed

Civ

il En

gine

ers

visi

ts

Env

& S

ocia

lvi

sits

Elec

tric

al E

ngg

visi

ts

Tota

l Vis

its

Issu

ed

Clo

sed

Pen

ding

Civ

il A

udit

Rep

orts

Soci

al &

Env

Aud

it r

epor

ts

Elec

tric

al A

udit

repo

rts

1 Srikakulam 48 1 0 30 40 5 24 0 4 138 0 0 138 106 11 0 11 14 0

2 Vizianagaram 6 0 0 6 6 0 6 0 0 19 0 0 19 28 0 0 0 1 0

3 Visakhapatnam 11 0 0 9 11 0 9 1 1 111 9 5 125 494 10 1 9 18 9 1

4 East Godavari 23 2 0 17 9 16 9 0 0 67 0 3 70 79 1 1 0 4 0

5 West Godavari 33 0 0 33 27 6 27 0 0 130 0 0 130 145 8 8 0 2 0

6 Krishna 45 0 0 45 10 35 10 0 0 32 3 0 35 42 5 2 3 3 0

7 Guntur 7 2 0 6 6 3 5 1 0 50 4 0 54 9 0 0 0 1 0

8 Prakasam 34 1 0 34 24 11 24 0 0 114 18 0 132 459 12 7 5 21 18

9 Nellore 39 0 0 37 37 2 37 0 0 128 22 0 150 955 13 6 7 17 23

246 6 0 217 170 78 151 2 5 789 56 8 853 2317 60 25 35 81 50 1Total

ABSTRACT OF NCRMP WORKS PROGRESS STATUS UP TO JUNE 2013

Sl.No.

District

Work Entrusted

Rev

iew

of

Con

trac

tD

ocum

ent

Status of WorksCummulative Visits of

TPQA

Tota

l No.

of

QC

tes

tsco

nduc

ted

NCRs By TPQACummulative AuditReports submitted

by TPQA

Page 14 of 141

Vijaya.B
Typewritten text
TABLE-7
Page 16: Quarterly Progress Report to the end of June 2013.pdf

Annexure - A

Status of Works

Page 15 of 141

Page 17: Quarterly Progress Report to the end of June 2013.pdf

First second Third

MPCS 1 Y2-001 Construction of CS in Kollipadu No G.o rt No 451dt 06.04.2010

07.03.12 07.08.12 07.01.13 Completion of entire work

Finishings is in progress, &Sump, Septic tank and

compound wall execavationcompleted

MPCS 2 Y2-002 Construction of CS in Runku No G.o rt No 451dt 06.04.2010

07.03.12 07.08.12 07.01.13 Completion of entire work

Finishings is in progress, &Sump, Septic tank anfd

compound wall execavation isin progress.

MPCS 3 Y2-005 Construction of CS in Amalpadu

MPCS 4 Y2-006 Construction of CS in Angavanipeta No Not started

MPCS 5 Y2-007Construction of CS inCh.Batsalavanipeta

MPCS 6 Y2-008 Construction of CS in Chintavanipeta

MPCS 7 Y2-009 Construction of CS in U.Narasingupalli No Not started

MPCS 8 Y2-010 Construction of CS in Bypalli NoG.o rt No 451dt 06.04.2010

18.11.13 18.04.14 18.09.14 Ground floor plinth level Earth work completed

MPCS 9 Y2-011 Construction of CS in Chinavanka NoG.o rt No 451dt 06.04.2010

18.11.13 18.04.14 18.09.14 Ground floor plinth level Earth work completed

MPCS 10 Y2-012 Construction of CS in Chinnakothuru NoG.o rt No 451dt 06.04.2010

18.11.13 18.04.14 18.09.14 Ground floor plinth level Earth work completed

MPCS 11 Y2-013Construction of CS in Chinnajittuvanipalam

4NCRMP/B-

W/AP/MPCS/PRED/01/Ranasthalam/008

MPCS 12 Y2-018Construction of A type CS inKommaravanipeta, Ranasthalammandal

NoG.o rt No 451dt 06.04.2010

14.08.13 14.12.13 14.03.14 Ground floor plinth level jungle clearence is in progress

5NCRMP/B-W/AP/MPCS/PRED/ 01/Kaviti/011

MPCS 13 Y2-023Construction of MPCS in Ch.Karrivanipalem (Type B)

No Not started

6NCRMP/B-W/AP/MPCS/PRED/ 01/Sompeta/012

MPCS 14 Y2-024Construction of MPCS inRamayyapatnam (Type B)

No Not started

MPCS 15 Y2-025Construction of MPCS in Metturu (TypeD)

NoG.o rt No 171dt 9.08.2012

14.09.12 14.02.14 14.05.14 Ground floor plinth level PCC completed

MPCS 16 Y2-026Construction of MPCS in Nuvvalarevu(Type D)

No Not started

8NCRMP/B-

W/AP/MPCS/PRED/01/Santhabommali/014

MPCS 17 Y2-027Construction of MPCS in ReddicaSunnapalli (Type C)

NoG.o rt No 171dt 9.08.2012

19.08.13 19.12.13 19.03.14 Ground floor plinth level jungle clearence is in progress

Progress w.r.t Mile stone Remarks

STATUS OF WORKS IN SRIKAKULAM DISTRICT AS ON 30.06.2013

ContractDocumentreviewed

or Not

Mile stone completiondatesSl.

No.Package Nos.

catagory

S.noProject

codeWork name Agreement

No. / Date

NCRMP/B-W/AP/MPCS/PRED/01/V.Kotturu/004

NCRMP/B-W/AP/MPCS/PRED/01/V.Kothuru/013

NCRMP/B-W/AP/MPCS/PRED/01/V.Kotturu/003

NCRMP/B-W/AP/MPCS/PRED

/01/Santhabommali/005

work cancelled

work cancelled

1

2

work cancelled

work cancelled

3

7

Page 16 of 141

Page 18: Quarterly Progress Report to the end of June 2013.pdf

First second ThirdProgress w.r.t Mile stone Remarks

STATUS OF WORKS IN SRIKAKULAM DISTRICT AS ON 30.06.2013

ContractDocumentreviewed

or Not

Mile stone completiondatesSl.

No.Package Nos.

catagory

S.noProject

codeWork name Agreement

No. / Date

MPCS 18 Y2-028Construction of MPCS in Calingapatnam(Type D)

NoG.o rt No 171dt 9.08.2012

14.09.13 14.02.14 14.06.14 Ground floor plinth level PCC completed

MPCS 19 Y2-029Construction of MPCS in Bandravanipeta(Type D)

NoG.o rt No 171dt 9.08.2012

14.09.13 14.02.14 14.06.14 Ground floor plinth level PCC completed

10NCRMP/B-

W/AP/MPCS/PRED/01/Polaki/018

MPCS 20 Y2-030Construction of MPCS in Akkuvaram(Type B)

NoG.o rt No 171dt 9.08.2012

14.08.12 14.12.12 14.03.14 Ground floor plinth level Earth work completed

MPCS 21 Y2-031Construction of MPCS inJaganadhapuram (Type B)

NoG.o rt No 171dt 9.08.2012

14.09.13 14.02.13 14.06.13 Ground floor plinth level jungle clearence is in progress

MPCS 22 Y2-032Construction of MPCS in Kothamukkam(Type A)

NoG.o rt No 171dt 9.08.2012

14.09.13 14.02.13 14.06.13 Ground floor plinth level jungle clearence is in progress

MPCS 23 Y2-036Construction of MPCS inBonthalakoduru (Type B)

NoG.o rt No 171dt 9.08.2012

2.10.13 2.03.14 2.06.13 Ground floor plinth level jungle clearence is in progress

MPCS 24 Y2-037Construction of MPCS inPathadibbalapalem (Type A)

NoG.o rt No 171dt 9.08.2012

2.10.13 2.03.14 2.06.13 Ground floor plinth level Earth work is in progress

RCS 25 Y2-145Road from Chinnavanka toGopaladavooru

YesG.o rt No 451dt 06.04.2010

15.08.13 15.11.13 14.03.14 Earth work & GSB Road widening is in progress

RCS 26 Y2-146Road from MN peta Road toKondavooru and to CS

YesG.o rt No 451dt 06.04.2010

15.08.13 15.11.13 14.03.14 Earth work & GSB Road widening is in progress

RCS 27 Y2-147 Road from R&B Road to S.J. Puram YesG.o rt No 451dt 06.04.2010

15.08.13 15.11.13 14.03.14 Earth work & GSB GSb layer completed

RCS 28 Y2-148Road from Kothapeta Road to SainooruCS

YesG.o rt No 451dt 06.04.2010

15.08.13 15.11.13 14.03.14 Earth work & GSB Road widening is in progress

14NCRMP/B-

W/AP/RCS/PRED/01/Santhabommali/008

RCS 29 Y2-150Borubhadra - Meghavaram Road to M.Maruvada

YesG.o rt No 192dt 13.08.2012

14.07.13 14.10.13 14.12.13 Earth work & GSBRoad widening work is in

progress

RCS 30 Y2-154Road from Yeeramukkam – Rati R&Broad to Dunnavooru

YesG.o rt No 171dt 09.08.2012

15.08.13 15.11.13 14.03.14 Earth work & GSB jungle clearence is in progress

RCS 31 Y2-155Road from Yeeramukkam – Rati R&Broad Geddavooru

YesG.o rt No 171dt 09.08.2012

15.08.13 15.11.13 14.03.14 Earth work & GSB jungle clearence is in progress

RCS 32 Y2-156Road from R&B road Ganguwada toroad to Sigalaputtuga

YesG.o rt No 171dt 09.08.2012

15.08.13 15.11.13 14.03.14 Earth work & GSB jungle clearence is in progress

RCS 33 Y2-157 Road from R&B road to Akkuvaram YesG.o rt No 171dt 09.08.2012

15.08.13 15.11.13 14.03.14 Earth work & GSB GSB completed

RCS 34 Y2-158Road from R&B road toPathadibbalapalem

YesG.o rt No 171dt 09.08.2012

15.08.13 15.11.13 14.03.14 Earth work & GSB Road widening is in progress

RCS 35 Y2-159Road from R & B road to PothayyapetaCS

YesG.o rt No 171dt 09.08.2012

15.08.13 15.11.13 14.03.14 Earth work & GSB Road widening is in progress

17NCRMP/B-W/AP/RHB/PRED/01/Polaki/005

RHB 36 Y1-096Road from R&B road Edulavalasa -

Killam to Jonnam via TalasamudramYes

/2011-12, Dt.30.04.2011

31.07.11 31.10.11 31.01.12First Milestone i.e Earthwork &

Cd works &GSB

BT layer completed from Km5/100 to Km 7/270 andretaining wall work is in

progress

13

15

16

NCRMP/B-W/AP/RCS/PRED/01/Mandasa/010

NCRMP/B-W/AP/RCS/PRED/

01/Etcherla &Ranasathalam/012

NCRMP/B-W/AP/MPCS/PRED/

01/Ranasthalam/016

NCRMP/B-W/AP/MPCS/PRED/01/Etcherla/017A

12

NCRMP/B-W/AP/RCS/PRED/01/V.Kottoru/001

9

11

NCRMP/B-W/AP/MPCS/PRED/

01/Gara/015

Page 17 of 141

Page 19: Quarterly Progress Report to the end of June 2013.pdf

First second ThirdProgress w.r.t Mile stone Remarks

STATUS OF WORKS IN SRIKAKULAM DISTRICT AS ON 30.06.2013

ContractDocumentreviewed

or Not

Mile stone completiondatesSl.

No.Package Nos.

catagory

S.noProject

codeWork name Agreement

No. / Date

RHB 37 Y1-097Road from R&B road Mobagam to

Duubakavanipeta via GajapathinagaramYes

/2010-11, Dt.30.04.2011

30.08.11 31.12.11 30.04.12First Milestone i.e Earthwork &

Cd works &GSB

300 mts CC road completed,GSB, WBM GR-II & III

completedand OGPC+ Sealcoat laying is in progress

RHB 38 Y1-098Road from Talasamudram to Dola

RegulatorYes

/2010-11, Dt.30.04.2011

30.08.11 31.12.11 30.04.12First Milestone i.e Earthwork &

Cd works &GSBBT layer completed

RHB 39 Y2-265Road from B.M ( R&B ) Road toSimmayyapeta

YesNo 1549 dt13.10.2011

14.09.13 14.02.14 14.06.14 First Milestone i.e Earthwork &Cd works &GSB Road widening is in progress

RHB 40 Y2-266 Road from R&B road to Marripadu YesNo 1549 dt13.10.2011

14.09.13 14.02.14 14.06.14 First Milestone i.e Earthwork &Cd works &GSB Road widening is in progress

RHB 41 Y2-267 Road from R&B Road to Kakarapalli YesNo 1549 dt13.10.2011

14.09.13 14.02.14 14.06.14 First Milestone i.e Earthwork &Cd works &GSB Road widening is in progress

RHB 42 Y2-268 Road from R&B road to Marripadu YesNo 1549 dt13.10.2011

14.09.13 14.02.14 14.06.14 First Milestone i.e Earthwork &Cd works &GSB Road widening is in progress

RHB 43 Y2-269Road from R&B road toPethalingapuram

YesNo 1549 dt13.10.2011

14.09.13 14.02.14 14.06.14 First Milestone i.e Earthwork &Cd works &GSB jungle clearence is in progress

20NCRMP/B-

W/AP/RHB/PRED/01/Santhabommali/001B

RHB 44 Y2-270Road from DPN road to GangaramVillage via Palatalagam,Srikrishnapuram

YesNo 1549 dt13.10.2011 20.10.13 20.4.14 19.09.14 Earth work & GSB, Bridge

foundation

Road widening is in progressand bridge earth work is in

progress.

RHB 45 Y2-273DPN road to D.L.Puram jn. via Koduru,Magathapadu , Guppidipeta

YesG.o rt No 201dt 22.09.2012 20.08.13 20.11.13 19.03.14 Earth work & GSB Road widening and culverts

work is in progress

RHB 46 Y2-274 Guppidipeta road to Chinnakoviripeta YesG.o rt No 201dt 22.09.2012 20.08.13 20.11.13 19.03.14 Earth work & GSB GSB layer completed

RHB 47 Y2-275K.C. Road to Rajarampuram viaAmpalem Revuamplam

YesG.o rt No 171dt 9.08.2012

24.08.13 24.12.13 24.03.14 First Milestone i.e Earthwork &Cd works &GSB

Road widening and culvertswork is in progress

RHB 48 Y2-276KC road to Amplam (via) Urjam,Nandigam

YesG.o rt No 171dt 9.08.2012

24.08.13 24.12.13 24.03.14 First Milestone i.e Earthwork &Cd works &GSB

Road widening and culvertswork is in progress

NCRMP/B-W/AP/Br/R&B/01/Uppugedda/002

R&B- Br 49 Y2-438

Construction of High level bridge acrossUppugedda at KM 7/6 of Srikakulammuncipal limits to Pukkalapeta viaKillipalem

Yes47/2010-11,Dt17.12.10

17.06.11 17.12.11 17.06.12 Completion of entire work

Slabs completed and finishingwork is in progress andApproach road work not

started

NCRMP/B-W/AP/RHB/PRED/ 01/Polaki/008

19

21

22

NCRMP/B-W/AP/RHB/PRED/

01/Santhabommali/001A

NCRMP/B-W/AP/RHB/PRED/

01/Polaki/007

NCRMP/B-W/AP/RHB/PRED/01/Polaki/006

18

Page 18 of 141

Page 20: Quarterly Progress Report to the end of June 2013.pdf

First second Third

1NCRMP/B-

W/AP/MPCS/PRED/02/Pusapatirega/003

MPCS 1 Y2-041Construction of MPCS inBoddugurayyapeta (Type A)

yes/2012-2013

Dt.14.03.2013

13.08.13 13.12.13 13.03.14Earthwork Excavation and

PCC work completed.Footings work is in progress.

Within the Milestone

RCS 2 Y2-160Road from R & B Road toGudepuvalasa CS

yes/2012-2013

Dt.14.03.2013

13.08.13 13.12.13 13.03.14 Earthen widening work is inprogress. Within the Milestone

RCS 3 Y2-161Road from R&B road to KavulawadaCS

yes/2012-2013

Dt.14.03.2013

13.08.13 13.12.13 13.03.14 Earthen widening work is inprogress. Within the Milestone

RCS 4 Y2-162Road from R & B Road toRoluchappidi CS

yes/2012-2013

Dt.14.03.2013

13.08.13 13.12.13 13.03.14 Earthen widening work is inprogress. Within the Milestone

RCS 5 Y2-163Road from R&B road toChinapathiwada CS

yes/2012-2013

Dt.14.03.2013

13.08.13 13.12.13 13.03.14 Earthen widening work is inprogress. Within the Milestone

RCS 6 Y2-164 Road from R&B road to BV peta yes/2012-2013

Dt.14.03.2013

13.08.13 13.12.13 13.03.14 Earthen widening work is inprogress. Within the Milestone

2

STATUS OF WORKS IN VIZIANAGARAM DISTRICT AS ON 30.06.2013

Sl.No.

Package Nos.catago

ryS.no

Projectcode

Work nameMile stone completion dates

Progress w.r.t Mile stone Remarks

ContractDocumentreviewed

or Not

NCRMP/B-W/AP/RCS/PRED/

02/Bhogapuram/001

Page 19 of 141

Page 21: Quarterly Progress Report to the end of June 2013.pdf

First second Third

1NCRMP/B-W/AP/MPCS/PRED/

03/Rambillii/004MPCS 1 Y2-048

Construction of cyclone shelter atVenkayyapalem

/2011-12,03.10.2011

Yes 02.01.12 02.04.12 02.07.12

Plinth Beam, stilt floor Ramp and staircase, stilt floor slab completed. Ist floorcolumns upto roof level completed. Istfloor stair case work completed. Ist floorslab and Head Room slabs arecompleted.Stilt floor slab and Ist floorslab ceiling plastering works arecompleted. Ist floor Brick masonry workcompleted. Inside and outside plasteringwork completed. Flooring completed.wood joiner completed.

Progress is Slow

1NCRMP/B-W/AP/MPCS/PRED/

03/S. Rayavaram/009MPCS 2 Y2-057

Construction of CS atBangarampalem I & II H/o Vakadu.(Type D)

/2013-14,20.04.2013

Yes 19.09.13 19.01.14 19.04.14Earthwork excavation started and stopdue to site dispute

Stopped

RCS 3 Y2-165Road from R & B road toChinanagamayyapalem CS

/2012-13,11.03.2013

Yes 10.07.13 10.10.13 10.12.13

WBM Gr-II From KM 0/0 to Km 0/8completed, CD works completed. WBMGr-III From KM 0/0 to Km 0/8 work isin progress.

Within the Milestone

RCS 4 Y2-166Road from R & B road to AnnavaramCS

/2012-13,11.03.2013

Yes 10.07.13 10.10.13 10.12.13WBM Gr-II and CC Road workcompleted . WBM Gr-III work is inprogress.

Within the Milestone

3NCRMP/B-W/AP/RCS/PRED/

03/S.Rayavaraam/006RCS 5 Y2-167

Road from R & B road toRevupolavaram CS

/2012-13,07.03.2013

Yes 06.07.13 06.10.13 06.12.13CC Road completed and Shoulders workis in progress

Within the Milestone

4NCRMP/B-W/AP/RCS/PRED/

03/Rambilli/007RCS 6 Y2-168

Road fromR & B road toKothapatnam CS

/2012-13,11.03.2013

Yes 10.06.13 10.08.13 10.09.13GSB,CC Road work completed andShoulders work to be progress.

Within the Milestone

RHB 7 Y2-280 Road from R & B road to Rajavaram/2012-13,

07.03.2013Yes 06.10.13 06.04.13 06.06.14 Work is completed Within the Milestone

RHB 8 Y2-281Road from Rajala R & B Road toRajaraidupalem

/2012-13,07.03.2013

Yes 06.10.13 06.04.13 06.06.14 Earthen widening work is in progress Within the Milestone

RHB 9 Y2-282Road from R & B road toGajareddipalem via Venkaypalem

/2012-13,07.03.2013

Yes 06.10.13 06.04.13 06.06.14

From Km.0/106 to Km 1/600 and fromkm 2/0 to km 2/620 GSB,WBM Gr-II,Grade-III completed and OGPC +Seal coat completed. From 1/600 to Km2/0 and From KM 2/620 to KM 2/720GSB work is in progress.

Within the Milestone

6NCRMP/B-W/AP/RHB/PRED/

03/Payakaraopeta/008RHB 10 Y2-283

Road from Z.P Road Palmanpeta toKorlayyapeta

/2012-13,0703.2013

Yes 06.07.13 06.10.13 06.12.13GSB,and CD works completed and CCRoad and Retaining wall work is inprogress.

Within the Milestone

7NCRMP/B-W/AP/RHB/PRED/

03/Atchuta puram/009RHB 11 Y2-284

Road from R & B Road toVadapalem

/2012-13,07.03.2013

Yes 06.06.13 06.08.13 06.09.13CC Road completed. Shoulders work isin progress.

Within the Milestone

STATUS OF WORKS IN VISAKHAPATNAM DISTRICT AS ON 30.06.2013

Sl.No.

Package Nos.catago

ryS.no

Projectcode

Work nameMile stone completion dates

Progress w.r.t Mile stone RemarksAgreemen

t No. /Date

NCRMP/B-W/AP/RCS/PRED/03/Bheemili/005

NCRMP/B-W/AP/RHB/PRED/03/Payakaraopeta/005

2

5

ContractDocumentreviewed

or Not

Page 20 of 141

Page 22: Quarterly Progress Report to the end of June 2013.pdf

First second Third

1NCRMP/B-W/AP/MPCS/PRED/

04/ Uppalaguptam/002MPCS 1 Y2-062

Construction of Cyclone Shelter atPedaraghavulapeta ofUppalaguptam Mandal

Yes78/2011-12Dt:17.10.2011

3 months16.01.2012

3 months16.04.2012

3 months16.07.2012(EOT up to30.06.2013)

1st floor & 2nd floor Flooringwork is in progress.

MPCS 2 Y2-074Construction of CS atKesavadasupalem (Type D)

Yes Not started

MPCS 3 Y2-075Construction of CS at Pallipalem(Type D)

Yes Not started

MPCS 4 Y2-076Construction of CS atPadamatapalem (Type D)

Yes 22.10.2013 22.03.2014 22.07.2014 PCC in Progress

MPCS 5 Y2-077Construction of CS at Kesanapalli(Type D)

Yes Not started

4NCRMP/B-W/AP/MPCS/PRED/04/Mamidikuduru/012

MPCS 6 Y2-078Construction of CS at Karavaka(Type B)

Yes Not started

5NCRMP/B-W/AP/RCS/PRED/04/U. Kothapalli/002

RCS 7 Y2-169Road from R&B road toSamanthkurru Pallepalem CS

Yes Not started

RCS 8 Y2-170Approach Road from R & B Roadto Turupupalem CS

Yes Not started

RCS 9 Y2-171Road from R & B Road toKesanapalli (New) CS

Yes Not started

RCS 10 Y2-172Road from R & B Road toPadamatipalem CS

Yes 03.09.2013 03.01.2014 03.04.2014 Earth work in progress

RCS 11 Y2-173Road from R & B Road toKatrenipadu Lanka CS

Yes 30.06.2013 30.09.2013 30.10.2013OGPC + Seal coat completedfrom Km. 0.000 to Km 0.500.

RCS 12 Y2-174Road from R & B road toKesavadasupalem (New) CS

Yes Not started

8NCRMP/B-W/AP/RCS/PRED/04/Mamidikuduru/013

RCS 13 Y2-175Road from R&B road to KaravakaCS

Yes Not started

9NCRMP/B-W/AP/RCS/PRED/04/Katrenikona/015

RCS 14 Y2-176CC Road from main proposed roadto Neellarevu II CS in Neellarevu

Yes Not started

10NCRMP/B-W/AP/RCS/PRED/04/Allavaram/016

RCS 15 Y2-177Road from R&B road toSamanthakurru CS

Yes 30.06.2013 30.10.2013Retaining wall is underprogress

RHB 16 Y2-289Road from R&B road toKorukondavari Group

Yes 29.07.2013 29.11.2013 29.03.2014 Earth work in progress

RHB 17 Y2-290Road from R&B road to GondiKodapa

Yes 29.07.2013 29.11.2013 29.03.2014 Earth work in progress

RHB 18 Y2-293BT road from Komaragiripatnam toKadadari and to CS

Yes 29.08.2013 29.12.2013 29.03.2013 Earth work in progress

RHB 19 Y2-294Road from R&B roadSamanthakurru to ChakkavaripetaRameswaram

Yes Not started

ContractDocumentreviewed

or Not

STATUS OF WORKS IN EAST GODAVARI DISTRICT AS ON 30.06.2013

Sl.No.

Package Nos.catago

ryS.no

Projectcode

Work nameMile stone completion dates

Progress w.r.t Mile stone RemarksAgreemen

t No. /Date

2

3

6

7

11

12

NCRMP/B-W/AP/RCS/PRED/04/Razole & Sakhinetipalli/010

NCRMP/B-W/AP/RHB/PRED/04/Sakhinetipalli/008

NCRMP/B-W/AP/RHB/PRED/04/Allavaram/012

NCRMP/B-W/AP/MPCS/PRED/04/Sakhinetipally/010

NCRMP/B-W/AP/MPCS/PRED/04/Malikipuram/011

NCRMP/B-W/AP/RCS/PRED/04/Malikipuram/009

Page 21 of 141

Page 23: Quarterly Progress Report to the end of June 2013.pdf

First second Third

ContractDocumentreviewed

or Not

STATUS OF WORKS IN EAST GODAVARI DISTRICT AS ON 30.06.2013

Sl.No.

Package Nos.catago

ryS.no

Projectcode

Work nameMile stone completion dates

Progress w.r.t Mile stone RemarksAgreemen

t No. /Date

RHB 20 Y2-295Road from Guthena deevi toGogullanka

Yes Not started

RHB 21 Y2-296Road from R&B road toRamalayampeta Pallamkurru (v)

Yes Not started

14NCRMP/B-W/AP/RHB/PRED/04/Katrenikona/016

RHB 22 Y2-297Road from N. Kothapalli to G.Porain Katrenikone (v)

Yes Not started

15NCRMP/B-W/AP/RHB/PRED/04/Razole/020

RHB 23 Y2-298 Road from R&B road to Aravapalem Yes Not started

16NCRMP/B-W/AP/Br/R&B/04/Pampa Yeru-1/015

Bridge 24 Y2-444Construction of Bridge at Km 43/10of Vakalapudi - Edatam road acrossPampa Yeru in EG District.

Yes 25.12.2013 25.05.2014 25.09.2014Pier 1,2,3 and 4 cutting edgeconcrete in progress.

17NCRMP/B-W/AP/Br/R&B/04/Pampa Yeru-2/016

Bridge 25 Y2-445Construction of Bridge at Km 43/6of Vakalapudi - Edatam road acrossPampa Yeru in EG District.

Yes Not started

NCRMP/B-W/AP/RHB/PRED/04/Katrenikona/014

13

Page 22 of 141

Page 24: Quarterly Progress Report to the end of June 2013.pdf

First second Third

1NCRMP/B-W/AP/RCS/PRED/

05/Achanta/002RCS 1 Y2-178

Road from R&B road to Ayodya lankaMarrimula CS. (CC Road)

Yes63/2012-13Dt.30.03.2013

30.03.201329.08.2013

30.08.201329.12.2013

30.12.201329.03.2014

Sub grade completed.

2NCRMP/B-W/AP/RCS/PRED/

05/Bhimavaram/004RCS 2 Y2-181

Construction of approach road to CS in Losariof Bhimavaram Mandal.

Yes37/2012-13Dt.08.03.2013

08.03.201307.06.2013

08.06.201307.09.2013

- Earth Work is in Progress

RCS 3 Y2-182 Road from R&B road to Kothakayalathippa CS YesSub grade completed. GSB

Material collection.

RCS 4 Y2-183Road from Narsapur Perupalem R&B road toMandavarithota

YesSub grade & CD works

completed.

RCS 5 Y2-184Road from Mollaparru R & B road toMollaparru Patha Colony

YesSub grade completed. CD

works is in Progress.

RCS 6 Y2-185Road from K.P Palem (N) Panchayat office toMetturevu Palli palem

Yes Not Started

RCS 7 Y2-186 R&B road to Chinamynavanilanka Yes Not Started

RCS 8 Y2-187 PR road to Ramanujapuram Yes Not Started

RCS 9 Y2-188 Road from P.R road to Prakasapuram Yes Not Started

5NCRMP/B-W/AP/RHB/PRED/

05/Kalla/004RHB 10 Y2-299 K.G. R&B Road to Mamidipudi of Kalawapudi. Yes

38 /2012-13Dt.08.03.2013

08.03.201307.06.2013

08.06.201307.09.2013

08.09.201307.12.2013

GSB Material collection.

6NCRMP/B-W/AP/RHB/PRED/

05/Mogaltur/006RHB 11 Y2-302 Khalipatnam R&B Road to Khalipatnam ferry Yes

52 /2012-13Dt.21.03.2013

21.03.201320.07.2013

21.07.201320.10.2013

21.10.201320.12.2013

Scarifying completed. EarthWork is in Progress.

RHB 12 Y2-306Road from Narsapur Perupalem R&B Road toMelamvaripalem Perupalem (S)

YesSub grade completed. CD

works is in Progress.

RHB 13 Y2-307Road from Perupalem Mollaparru R&B roadvia Sattinenivarimeraka to K.D. Pallavapalem

YesSub grade completed. CD

works is in Progress.

RHB 14 Y2-308Road from Perupalem – DibbalapallipalemR&B road to Mellapallavapalem

YesSub grade & CD Works is in

Progress.

RHB 15 Y2-309Road from Perupalem beach R&B Road toChallavarimeraka via Mucherlavarimeraka

YesSub grade & CD Works is in

Progress.

RHB 16 Y2-310 Road from Perupalem R&B road to Dindla YesSub grade completed. CD

works is in Progress.

RHB 17 Y2-311Road from Narsapur Perupalem R&B road toNellipallipalem via Ambedkar colonyHarijanapeta

YesSub grade completed. CD

works is in Progress.

RHB 18 Y2-312Road from Perupalem R&B Road toKouruvaripalem

YesSub grade completed. CD

works is in Progress.

3

4

7

8NCRMP/B-W/AP/RHB/PRED/

05/Mogaltur/009

NCRMP/B-W/AP/RCS/PRED/05/Mogaltur/005

NCRMP/B-W/AP/RCS/PRED/05/Narsapur/006

NCRMP/B-W/AP/RHB/PRED/05/Mogaltur/008

STATUS OF WORKS IN WEST GODAVARI DISTRICT AS ON 30.06.2013

Sl.No.

Package Nos.catagory

S.noProject

codeWork name

Mile stone completion datesProgress w.r.t Mile stone Remarks

ContractDocumentreviewed

or Not

AgreementNo. / Date

20.03.201319.09.2013

20.02.201429.06.2014

50 /2012-13Dt.20.03.2013

20.09.201319.02.2014

21.03.201320.08.2013

21.12.201320.03.2014

53 /2012-13Dt.21.03.2013

21.08.201320.12.2013

33 /2012-13Dt.06.03.2013

06.09.201305.02.2014

18.03.201317.09.2013

18.02.201417.06.2014

46 /2012-13Dt.18.03.2013

18.09.201317.02.2014

06.03.201305.09.2013

06.02.201405.06.2014

Page 23 of 141

Page 25: Quarterly Progress Report to the end of June 2013.pdf

First second Third

STATUS OF WORKS IN WEST GODAVARI DISTRICT AS ON 30.06.2013

Sl.No.

Package Nos.catagory

S.noProject

codeWork name

Mile stone completion datesProgress w.r.t Mile stone Remarks

ContractDocumentreviewed

or Not

AgreementNo. / Date

RHB 19 Y2-313 Road from SP R&B road to Pasaladeevi YesSub grade & CD works

completed.

RHB 20 Y2-314 LT R&B road to Modi Yes Sub grade completed..

RHB 21 Y2-315SP R&B road to Gannabathulavari palem ofChamakuripalem

YesSub grade & CD works

completed.

RHB 22 Y2-316Road from R&B road to SC Colony ofPedalanka

Yes Not Started

RHB 23 Y2-317 R&B road to Rajeev Nagar of Darbharevu Yes Not Started

RHB 24 Y2-318 SP R&B road to Pedathota of Turputallu YesSub grade, GSB, CD Workscompleted.WMM Work is in

progress.

RHB 25 Y2-319 R&B road to Peta of Turputallu YesScarifying completed. EarthWork & Sub grade work is in

Progress.

RHB 26 Y2-320 R&B road to Pedathota of Turputallu YesSub grade, GSB, CD Workscompleted.WMM Work is in

progress.

RHB 27 Y2-321 R&B road to Guttulavarimeraka Yes Sub grade & GSB completed.

RHB 28 Y2-322 Road from R & B Road to Pulaparthivaripalem Yes Sub grade completed.

RHB 29 Y2-323 R&B road to Pedaedigapalem YesSub grade, GSB, CD Works

completed.

RHB 30 Y2-324 R&B road to Evanivarimeraka Yes Sub grade is in Progress.

RHB 31 Y2-325Road from PR Road to Prakashpuram SCcolony of Vemuladeevi (E)

Yes Sub grade is in Progress.

RHB 32 Y2-326Road from PR road to Vemuladeevi (E) colony(Via) Ralla cheruvu of Vemuladeevi (E)

Yes

Scarifying, WMM & SDBCCompleted From Km 0.00 tokm 2.484. Shoulders work is

in is in Progress.

RHB 33 Y2-327Road from PR road to Addalavarimeraka ofVemuladeevi (E)

Yes Sub grade is in Progress.

11

12

NCRMP/B-W/AP/RHB/PRED/05/Narsapur/013

NCRMP/B-W/AP/RHB/PRED/05/Narsapur/014

9

10

NCRMP/B-W/AP/RHB/PRED/05/Narsapur/010

NCRMP/B-W/AP/RHB/PRED/05/Narsapur/012

14.03.201313.09.2013

14.02.201413.06.2014

44 /2012-13Dt.14.03.2013

14.09.201313.02.2014

62/2012-13Dt.27.03.2013

27.03.201326.09.2013

27.09.201326.02.2014

27.02.201426.06.2014

25.03.2013to

24.08.2013

25.12.2013to

24.03.2014

58 /2012-13Dt.25.03.2013

25.08.201324.12.2013

36/2012-13Dt. 8.03.2013

08.03.2013to

07.08.2013

08.08.2013to

07.12.2013

08.12.2013to

07.03.2014

Page 24 of 141

Page 26: Quarterly Progress Report to the end of June 2013.pdf

First second Third

RCS 1 Y2-189 Road from R&B road to CS @ Ullipalem Yes 21-03-201322.03.13-21.08.13

22.08.13-21.12.13

22.12.13-21.03.14

CD work&GSB completed.

RCS 2 Y2-190Road from R & B Road to CS atJaruguvanipalem

Yes 21-03-201322.03.13-21.08.13

22.08.13-21.12.13

22.12.13-21.03.14

Work not started

RCS 3 Y2-191 Road from R&B road to CS @ Utagundam Yes 21-03-201322.03.13 -21.08.13

22.08.13-21.12.13

22.12.13-21.03.14

Work not started

RCS 4 Y2-192Road from R&B road to CS @ Ramakrishnapuram

Yes 21-03-201322.03.13 -21.08.13

22.08.13-21.12.13

22.12.13-21.03.14

GSB completed

RCS 5 Y2-193 Road from R&B road to CS @ Chintakolla Yes 21-03-201321-03-13 -20-09-13

21-09-13 -20-02-14

21-02-14 -20-06-14

Work not started

RCS 6 Y2-194Road from R&B road to CS @Padalavaripalem

Yes 21-03-201321-03-13 -20-09-13

21-09-13 -20-02-14

21-02-14 -20-06-14

Work not started

RCS 7 Y2-195 Road from R&B road to CS @ Mandapakala Yes 21-03-201321-03-13 -20-09-13

21-09-13 -20-02-14

21-02-14 -20-06-14

GSB & WMM collection is inprogress.

RCS 8 Y2-196Road from R&B road to Ramakrishna puram R& B Road via Pathaupakali

Yes 23-03-201321-03-13 -20-08-13

21-08-13 -20-12-13

21-12-13 -20-03-14

Work not started

RCS 9 Y2-197 R & B Road to CS at Kothaupakali Yes 23-03-201321-03-13 -20-08-13

21-08-13 -20-12-13

21-12-13 -20-03-14

Work not started

RCS 10 Y2-198 Road from Uppu Canal drain to CS at Nali Yes 25-03-201325-03-13 -24-09-13

25-09-13 -24-02-14

25-02-14 -24-06-14

Work not started

RCS 11 Y2-199 Road from Nali R & B Road to Barrankula CS Yes 25-03-201325-03-13 -24-09-13

25-09-13 -24-02-14

25-02-14 -24-06-14

Work not started

RCS 12 Y2-200 From R&B road to Bhavadevarapalli Yes 25-03-201325-03-13 -24-09-13

25-09-13 -24-02-14

25-02-14 -24-06-14

Work not started

RCS 13 Y2-201 Road from R&B road to CS at Pedapalem Yes 20-03-201320-03-13 -19-09-13

20-09-13 -19-02-14

20-02-14 -19-06-14

Work not started

RCS 14 Y2-202 Road from Gullalamoda R&B road to Etimoga Yes 20-03-201320-03-13 -19-09-13

20-09-13 -19-02-14

20-02-14 -19-06-14

Work not started

RCS 15 Y2-203 Road from R&B to CS at China Etimoga Yes 20-03-201320-03-13 -19-09-13

20-09-13 -19-02-14

20-02-14 -19-06-14

Work not started

RCS 16 Y2-204Road from R & B Road to CS at ChinaKammavaripalem

Yes 20-03-201320-03-13 -19-09-13

20-09-13 -19-02-14

20-02-14 -19-06-14

Work not started

RCS 17 Y2-205Road from China Zinkapalem to Gollamandavia Peda Zinkapalem

Yes 22-03-201322.03.13 -21.09.13

22.09.13 -21.02.14

22.02.14 -21.06.14

Work not started

RCS 18 Y2-206 Road from R&B road to CS at Gollamanda Yes 22-03-201322.03.13 -21.09.13

22.09.13 -21.02.14

22.02.14 -21.06.14

Work not started

RCS 19 Y2-207 Road from ZP Road to CS at Natchugunta Yes 22-03-201322.03.13 -21.09.13

22.09.13 -21.02.14

22.02.14 -21.06.14

Work not started

RCS 20 Y2-208 Road from Krishna River to Elichetladibba CS Yes 22-03-201322.03.13 -21.09.13

22.09.13 -21.02.14

22.02.14 -21.06.14

Work not started

1

2

3

4

5

6

NCRMP/B-W/AP/RCS/PRED/06/koduru/001

NCRMP/B-W/AP/RCS/PRED/06/koduru/002

NCRMP/B-W/AP/RCS/PRED/

06/Nagayalanka/003

STATUS OF WORKS IN KRISHNA DISTRICT AS ON 30.06.2013

Sl.No.

Package Nos.catagory

S.noProject

codeWork name

Mile stone completion datesProgress w.r.t Mile stone Remarks

ContractDocumentreviewed

or Not

Agreement No. /Date

NCRMP/B-W/AP/RCS/PRED/

06/Nagayalanka/004

NCRMP/B-W/AP/RCS/PRED/

06/Nagayalanka/005

NCRMP/B-W/AP/RCS/PRED/

06/Nagayalanka/006

Page 25 of 141

Page 27: Quarterly Progress Report to the end of June 2013.pdf

First second Third

STATUS OF WORKS IN KRISHNA DISTRICT AS ON 30.06.2013

Sl.No.

Package Nos.catagory

S.noProject

codeWork name

Mile stone completion datesProgress w.r.t Mile stone Remarks

ContractDocumentreviewed

or Not

Agreement No. /Date

RCS 21 Y2-211Road from Kammavanicheruvu R&B road toVenkata durgambapuram in MachilipatnamMandal

Yes 22-03-201322.03.13 -21.08.13

22.08.13 -21.12.13

22.12.13 -21.03.14

Earth work started and GSBmaterial collection in progress

RCS 22 Y2-212Road from R&B Road Pedayadara toHarijanawada

Yes 22-03-201322.03.13 -21.08.13

22.08.13 -21.12.13

22.12.13 -21.03.14

Work not started

8NCRMP/B-W/AP/RHB/PRED/ 06/Koduru/004

RHB 23 Y2-328 Road from R&B Road to Narsimhapuram Yes 22-03-201322.03.13 -21.08.13

22.08.13 -21.12.13

22.12.13 -21.03.14

CD work&GSB completed.

RHB 24 Y2-329 Road from R&B Road to Krishnapuram Yes 22-03-201322.03.13 -21.08.13

22.08.13 -21.12.13

22.12.13 -21.03.14

Work not started

RHB 25 Y2-330 Road from R&B road to Pedagudumotu Yes 22-03-201322.03.13 -21.08.13

22.08.13 -21.12.13

22.12.13 -21.03.14

CD work is in progress.

RHB 26 Y2-335 Road from R&B Road to Parra chivara Yes 25-03-201325.03.13 -24.09.13

25.09.13 -24.02.14

25.02.14 -24.06.14

Work not started

RHB 27 Y2-336 Road from R&B road to Pedagowdapalem Yes 25-03-201325.03.13 -24.09.13

25.09.13 -24.02.14

25.02.14 -24.06.14

Work not started

RHB 28 Y2-337 Road from R & B Road to Mulapalem Yes 25-03-201325.03.13 -24.09.13

25.09.13 -24.02.14

25.02.14 -24.06.14

Work not started

RHB 29 Y2-338Road from Ganapeswaram R&B Road toPullaiahgaridibba

Yes 25-03-201325.03.13 -24.09.13

25.09.13 -24.02.14

25.02.14 -24.06.14

Work not started

RHB 30 Y2-343Road from R & B Road to Indiramma Tank inGullalamoda

Yes 22-03-201322.03.13 -21.09.13

22.09.13 -21.02.14

22.02.14 -21.06.14

Work not started

RHB 31 Y2-344Construction of road from ST colony to Uppudrain in Dindi.

Yes 22-03-201322.03.13 -21.09.13

22.09.13 -21.02.14

22.02.14 -21.06.14

Work not started

RHB 32 Y2-345 Road from Z.P.road to Sorlagondi Yes 22-03-201322.03.13 -21.09.13

22.09.13 -21.02.14

22.02.14 -21.06.14

Work not started

RHB 33 Y2-346Road from R & B road to MPUP School inSangameswaram

Yes 22-03-201322.03.13 -21.09.13

22.09.13 -21.02.14

22.02.14 -21.06.14

Work not started

RHB 34 Y2-347Road from Matlam Z.P road toGovindarajuladibba in Kruthivennu mandal

Yes 14-03-201314.03.13 -13.09.13

14.09.13 -13.02.14

14.02.14 -13.06.14

Work not started

RHB 35 Y2-348Road from R&B road to Amudalapalli(Pennamdibba) in Kruthivennu mandal

Yes 14-03-201314.03.13 -13.09.13

14.09.13 -13.02.14

14.02.14 -13.06.14

CD works is in progress.

RHB 36 Y2-349Road from Seethannapalli R&B Road toGollagudem in Kruthivennu mandal

Yes 14-03-201314.03.13 -13.09.13

14.09.13 -13.02.14

14.02.14 -13.06.14

CD works is in progress.

RHB 37 Y2-350Road from R&B Road to Bolugondi inKruthivennu mandal

Yes 14-03-201314.03.13 -13.09.13

14.09.13 -13.02.14

14.02.14 -13.06.14

CD works is in progress.

RHB 38 Y2-351 Road from R&B Road to Ramapuram Yes 19-03-201318.03.13 -17.09.13

18.09.13 -17.02.14

18.02.14 -17.06.14

Work not started

RHB 39 Y2-352Road from Chinapandraka R&B Road toUppuluru

Yes 19-03-201318.03.13 -17.09.13

18.09.13 -17.02.14

18.02.14 -17.06.14

Work not started

7

9

10

11

12

13NCRMP/B-

W/AP/RHB/PRED/06/Kruthivennu/013

NCRMP/B-W/AP/RCS/PRED/

06/Machilipatnam/008

NCRMP/B-W/AP/RHB/PRED/06/Koduru/005

NCRMP/B-W/AP/RHB/PRED/

06/Nagayalanka/008

NCRMP/B-W/AP/RHB/PRED/

06/Nagayalanka/010

NCRMP/B-W/AP/RHB/PRED/

06/Kruthivennu/011

Page 26 of 141

Page 28: Quarterly Progress Report to the end of June 2013.pdf

First second Third

STATUS OF WORKS IN KRISHNA DISTRICT AS ON 30.06.2013

Sl.No.

Package Nos.catagory

S.noProject

codeWork name

Mile stone completion datesProgress w.r.t Mile stone Remarks

ContractDocumentreviewed

or Not

Agreement No. /Date

RHB 40 Y2-353 Road from B.L road to Matlam Yes 26-03-201326.03.13 -25.09.13

26.09.13 -25.02.14

26.02.14 -25.06.14

Gravel collection is in progressfor Sub Base

RHB 41 Y2-354 Road from Interu R&B road to Parvathipuram Yes 26-03-201326.03.13 -25.09.13

26.09.13 -25.02.14

26.02.14 -25.06.14

Work not started

RHB 42 Y2-366Road from Gokavaram R & B road toVodarevupalem

Yes 18-03-201318.03.13 -17.09.13

18.09.13 -17.02.14

17.01.14 -16.04.14

Work not started

RHB 43 Y2-367Road from Gokavaram R & B road toBaduguvaripalem

Yes 18-03-201318.03.13 -17.09.13

18.09.13 -17.02.14

17.01.14 -16.04.14

Work not started

RHB 44 Y2-368Road from R&B Road Thallapalem toRayapalli

Yes 18-03-201318.03.13 -17.09.13

18.09.13 -17.02.14

17.01.14 -16.04.14

Work not started

RHB 45 Y2-369Road from Manginapudi R & B Road toPathareddypalem

Yes 18-03-201318.03.13 -17.09.13

18.09.13 -17.02.14

17.01.14 -16.04.14

Work not started

NCRMP/B-W/AP/RHB/PRED/

06/Kruthivennu/014

NCRMP/B-W/AP/RHB/PRED/

06/Machilipatnam/020

14

15

Page 27 of 141

Page 29: Quarterly Progress Report to the end of June 2013.pdf

First second Third

1NCRMP/B-W/AP/MPCS/PRED/07/Nizampatham/003

MPCS 1 Y2-097Construction of CS in Sanjeevanagar ofKothapalem (Type B)

YesC.R. No./2012-1322.03.2013

21.08.2013 21.12.2013 21.03.2014 Work not Started

2NCRMP/B-W/AP/MPCS/PRED/07/Repalle/005

MPCS 2 Y2-101 Construction of CS in Lankavanidibba (Type D) YesC.R. No./2012-1322.03.2013

21.08.2013 21.12.2013 21.03.2014 Work not Started

3NCRMP/B-W/AP/RCS/PRED/07/Nizampatnam/005

RCS 3 Y2-225Road from R&B Koosureiyuvaripalem Road toMarakavaripalem

Yes/2012-201321.03.2013

20.7.2013 20.10.2013 20.12.2013 GSB is in progress As per mile stone.

4NCRMP/B-W/AP/RCS/PRED/07/PV Palem/001

RCS 4 Y2-219 Road from R&B Road Alluru to Yadavapalem Yes/2011-20121.11.2011

31.01.2012 30.04.2012 31.07.2012 Work completed

RCS 5 Y2-226Road from Adavipallipalem R& B road to NewTsunami colony (via) Krupanagar Colony, AdaviVillage

Yes/2013-20141.04.2013

31.08.2013 31.12.2013 31.03.2013 Work not Started

RCS 6 Y2-227 Road from R & B road to Pattapupalem Yes/2013-20141.04.2013

31.08.2013 31.12.2013 31.03.2013 Earth work is in progress As per mile stone.

6NCRMP/B-W/AP/RHB/PRED/07/Nagaram/007

RHB 7 Y2-379 Road from R&B road to Gattuvaripalem Yes/2012-201321.03.2013

20.8.2013 20.12.2013 20.3.2014 Earth work is in progress As per mile stone.

7NCRMP/B-W/AP/Br/R&B/07/Bapatla/011

Bridge 8 Y2-450Reconstruction of HLB @Km2/4 of Bapatla-Pandurangapuram Road across perali drain

Yes78/2010-

20111.12.2010

31.5.2011 30.11.2011 31.5.2012Bridge completed

Approaches Pending

8NCRMP/B-W/AP/Br/R&B/07/Peddapalli/022

Bridge 9 Y2-453Reconstruction of bridge across Peddapalli drainat km 14/6 of Chandole bridge to Nizampatnamroad

Yes109/2012-

2013/12.3.13

11.7.13 11.11.13 11.3.14 Earth work is in progress As per mile stone.

5

STATUS OF WORKS IN GUNTUR DISTRICT AS ON 30.06.2013

Sl.No.

Package Nos.catagory

S.noProject

codeWork name

Mile stone completion datesProgress w.r.t Mile

stoneRemarks

ContractDocumentreviewed

or Not

NCRMP/B-W/AP/RCS/PRED/07/Bapatla/006

Agreement No. /Date

Page 28 of 141

Page 30: Quarterly Progress Report to the end of June 2013.pdf

First second Third

RCS 1 Y2-228 Road from R&B road to Motupalli CS yes

RCS 2 Y2-229Road from Km1/2+186 of ChinaganjamRailway gate-Bapaianagar ZP Road toRamachandranagar H/o Kothapalem

yes

RCS 3 Y2-230Road from Motupalli R&B Road toNirikshanagiri (via) Rudramambapuram CS inMotupalli G.P.

yes

RCS 4 Y2-231 Road from R&B road to Mattigunta CS yes

RCS 5 Y2-232Vedullapalli Vodarevu R&B road to CS atVijayalakshmipuram

yes

RCS 6 Y2-233Road from Pakala PR Road toChellammagaripattapupalem CS

yesEarthwork Widening inProgress, Culvert Work inProgress

As per milestone

RCS 7 Y2-234Road from Pakala PR road toPotthaiahgaripalem CS, Kranthinagar Revu.

yesEarthwork Widening inProgress,

As per milestone

RCS 8 Y2-235Road from Woollapalem R&B road toDevalampallipalem CS

yesEarthwork Widening inProgress,

As per milestone

RCS 9 Y2-236 Road from Tangutur to Ananthavaram yesEarthwork Widening inProgress,

As per milestone

RCS 10 Y2-238 Road from Z.P. road to Srirampattapupalem yes GSB Completed, CC in Progress As per milestone

RCS 11 Y2-239Road from ZP road to Pallipalem ofChakicharala

yes

GSB Completed, CC CompletedCD Completed & WBM Gr-IICompleted. WBM Gr-IIICompleted, OGPC + SCCompleted, CD WorksCompleted Shoulders inProgress.

As per milestone

RHB 12 Y2-387 R&B Road to Pulavaripalem yesEarthwork Widening inProgress,

As per milestone

RHB 13 Y2-388Road from Chinnaganjam Rly gate toBapaiahnagar

yesGSB Completed, WBM Gr-IICollection in Progress

As per milestone

RHB 14 Y2-389 Road from R & B road to Kothaplem yes GSB In Progress As per milestone

RHB 15 Y2-390Road from Motupalli R & B Road to KrishnaNagar

yes

RHB 16 Y2-391 Road from R & B Road to Yanadi Sangam yes

RHB 17 Y2-392Road from Jeedichetlapalem R&B road toKunkuduchetlapalem

yes

Not Started

Not Started

Not Started

Agt.No.60/2012-13,Dated11.03.2013

August2013, EarthWork & GSB

January-2014-WBM, CD &CC works

May-2014 -BT & RoadFurniture

Agt.No. 65/2012-13,Dated19.03.2013

July-2013Clearing &GrubbingScarifying,Earth work& GSB

Nov-2013WBM, CDWorks & CC

March-2014BT & RoadFurniture

C.R. No./2013-14Dated14.03.2013

July-2013Clearing &GrubbingScarifying,Earth work& GSB

Dec-2013WBM Gr-II,

CC & CDWorks

May-2014WBM Gr-III,BT,Shoulders,Earth work& RoadFurniture

Agt.No.58/2012-13,Dated11.03.2013

Earth Work,CD Works

GSB, WBMGr-II, CC-1km

CC-1.390km,BT,Shoulders,Earth Work& RoadFurniture

Agt.No.67/2012-13,Dated25.03.2013

August-2013 Earthwork, GSB,WBM

January-2014, CC,WBM,Shoulders

May-2014CC,Shoulders,BT & RoadFurniture

Not Started

Not Started

Not Started

Not Started

Not Started

ContractDocumentreviewed

or Not

STATUS OF WORKS IN PRAKASAM DISTRICT AS ON 30.06.2013

Sl.No.

Package Nos.catago

ryS.no

Projectcode

Work nameMile stone completion dates

Progress w.r.t Mile stone RemarksAgreemen

t No. /Date

NCRMP/B-W/AP/RHB/PRED/

08/Chinaganjam/012

NCRMP/B-W/AP/RHB/PRED/

08/Chinaganjam/013

NCRMP/B-W/AP/RCS/PRED/08/Chinaganjam &

Chirala/006

NCRMP/B-W/AP/RCS/PRED/

08/S.Konda&Tangutur/010

NCRMP/B-W/AP/RCS/PRED/08/Ulavapadu/009

1

2

3

4

5

Page 29 of 141

Page 31: Quarterly Progress Report to the end of June 2013.pdf

First second Third

ContractDocumentreviewed

or Not

STATUS OF WORKS IN PRAKASAM DISTRICT AS ON 30.06.2013

Sl.No.

Package Nos.catago

ryS.no

Projectcode

Work nameMile stone completion dates

Progress w.r.t Mile stone RemarksAgreemen

t No. /Date

RHB 18 Y2-397Road from KEM R & B road toChinapattapupalem

yes GSB Completed As per milestone

RHB 19 Y2-398Salt Road from Madnur ZP road toPedapattapupalem

yesGSB Completed, CC inProgress, WBM Grade-II & CCPavement Completed

As per milestone

RHB 20 Y2-399Road from Madnur ZP road toSwarnandhrapattapupalem

yesGSB Completed, CCCompleted.

As per milestone

RHB 21 Y2-400Road from Madnur ZP road to Bapujiyanadicolony

yes GSB Completed, CC Progress As per milestone

RHB 22 Y2-401Salt Road from Madnur ZP road to Namburiyanadi colony

yesGSB Completed & WBM Grade-II Progress

As per milestone

RHB 23 Y2-402Salt Road from Madnur ZP road to Thotaguntayanadi colony

yes GSB Completed As per milestone

7NCRMP/B-

W/AP/RHB/PRED/08/Tangutur/021

RHB 24 Y2-403Road from Tangutur to Tallapalem (via)Velagapudi (Km 4/5 to 7/465)

yes

Agt.No./2012-13,Dated02.04.2013

July-2013-Clearing &GrubbingScarifying,Earth work,GSB

Nov-2013 -WBM Gr-II,CD Works &CC.

March-2014- CC-,Shoulders,BT & RoadFurniture

Retaining Wall 145mCompleted. Earth workwidening Completed & GSBCompleted

As per milestone

8NCRMP/B-

W/AP/RHB/PRED/08/Tangutur/022

RHB 25 Y2-404Road from Tangutur-Ravivaripalem road @1/2KM to Pasukuduru.

yes

Agt.No./2012-13,Dated14.03.2013

Aug-2013-Clearing &GrubbingScarifying,Earth work,GSB

Dec-2013 -WBM Gr-II,CD Works &CC.

March-2014- CC-,Shoulders,BT & RoadFurniture

Earthwork Widening inProgress,

As per milestone

RHB 26 Y2-405 Road from Kanuparthy to Kukkalavaripalem yes

RHB 27 Y2-406 Road from Kanuparthy to Yanadi Sangam yes

RHB 28 Y2-407 Road from Kanuparthy to MS Pattapupalem yes

RHB 29 Y2-409Road from KEM R&B Road to Vajjireddypalem -Pattapupalem

yes GSB Completed As per milestone

RHB 30 Y2-410 KEM R & B road to Pinnivaripalem yes

GSB Completed, WBM Gr-IICompleted, CC Completed,WBM Grade-III collection inprogress

As per milestone

RHB 31 Y2-411Salt Road from Madnur ZP road toChinnapattapupalem

yes

GSB Completed, WBM Gr-IICompleted, CC 100mCompleted, WBM Grade-IIIcollection in progress

As per milestone

RHB 32 Y2-412 KEM R & B road to E. Pallipalem yesGSB Completed, CCCompleted.

As per milestone

9

NCRMP/B-W/AP/RHB/PRED/

08/Kothapatnam/019

Agt.No./2012-13,

Dated15.03.2013

August-2013

Clearing &GrubbingScarifying,Earth work,

GSB

January-2014 WBMGr-II, WBMGr-II, CC-50% & CD

Works

NCRMP/B-W/AP/RHB/PRED/08/N.G.Padu/011

10

May-2014CC-50%,

Shoulders,BT & RoadFurniture

Not Started

Not Started

Agt.No./2012-13,Dated20.03.2013

August-2013Clearing &GrubbingScarifying,Earth work,GSB

January-2014 WBMGr-II, WBMGr-III & CDWorks

May-2014CC-,Shoulders,BT & RoadFurniture

Not Started

Agt.No./2012-13,Dated11.03.2013

Oct-2013-Clearing &GrubbingScarifying,Earth work,GSB

April-2014-WBM Gr-II,WBM Gr-III& CD Works

Sep-32014-CC-,Shoulders,BT & RoadFurniture

6NCRMP/B-

W/AP/RHB/PRED/08/Kothapatnam/020

Page 30 of 141

Page 32: Quarterly Progress Report to the end of June 2013.pdf

First second Third

ContractDocumentreviewed

or Not

STATUS OF WORKS IN PRAKASAM DISTRICT AS ON 30.06.2013

Sl.No.

Package Nos.catago

ryS.no

Projectcode

Work nameMile stone completion dates

Progress w.r.t Mile stone RemarksAgreemen

t No. /Date

NCRMP/B-W/AP/RHB/PRED/08/Kothapatnam/019

RHB 33 Y2-413 Road from KEM R & B road toChenchupapayapalem

yes

GSB Completed, WBM Gr-IICompleted & Grade-IIIcollection in progress & CC inProgress

As per milestone

11NCRMP/B-

W/AP/RHB/PRED/08/Ulavapadu/016

RHB 34 Y2-414Road From M.C road to West ST colony ofVeerapalli

yes

Agt.No./2012-13,Dated11.03.2013

July-2013 -Clearing &GrubbingScarifying,Earth work,GSB

Nov-2013WBM Gr-II,WBM Gr-III,& CD Works

March-2014CC-Shoulders,BT & RoadFurniture

WBM Gr-II & Gr-III Completed,Earth Work Completed, 3m3vSlab Culvert Completed &1000mm dia Single row 3 noscompleted, OGPC + SCcompleted from 3/386 to5/380, Side drains in progress,Retaining wall 250mcompleted. 11 Culverts inprogress

As per milestone

12NCRMP/B-W/AP/Br/R&B/

08/Ongole/023Bridge 35 Y2-455

Reconstruction of High level bridge at Km.11/10 of Ongole - Kothapatnam road

yes

C.R. No.10/2013-14Dated12.04.2013

August-2013ComplitionofFoundationsupto SillLevel

Dec-2013Complitionupto belowDeck Salb

April-2014Complitionof entireworeincludingapproaches

Mobilization of Equipment As per milestone

Page 31 of 141

Page 33: Quarterly Progress Report to the end of June 2013.pdf

First second Third

1 RCS 1 Y2-240Road from @ 56/8 to C.K road to Periyavettukuppam cyclone shelter

Yes 14.09.2012 13.2.13 13.06.13 13.09.13 WBM Gr-II progress As Per mile stone

2 RCS 2 Y2-241Providing BT road to Pedapannamgadu in TadaMandal

Yes 14.09.2012 13.2.13 13.06.13 13.09.13 BT completed As Per mile stone

3NCRMP/B-W/AP/RCS/PRED/09/Alluru/012

RCS 3 Y2-242 Approach road to Labbipalem Yes49/2012-201318.03.13

17.06.13 17.08.13 17.09.13CC pavementcompletd

As Per mile stone

4NCRMP/B-W/AP/RCS/PRED/09/Bogole/013

RCS 4 Y2-243 Road from R & B road to Pathakadapalem Yes54/2012-1320.03.13

19.07.13 19.10.13 19.12.13Earth work isprogress

As Per mile stone

RCS 5 Y2-244Road from Ramudupalem on R&B road toPallipalem

Yes59/2012-201320.03.13

19.09.13 19.02.14 19.06.14 GSB is progress As Per mile stone

RCS 6 Y2-245 Road from Korutur to Pattapupalem Yes59/2012-201320.03.13

19.09.13 19.02.14 19.06.14 CD works progress As Per mile stone

6NCRMP/B-W/AP/RCS/PRED/09/Kavali/020

RCS 7 Y2-246Road from 230/6 Km of M.C Raod toPedapattapupalem

Yes46/2012-20 13Date:28.02.13

27.07.13 27.11.13 27.2.14 GSB progress As Per mile stone

RCS 8 Y2-247 Road from R&B road to Utukuru Pallipalem Yes58/2012-201320.03.13

19.09.13 19.02.14 19.06.14Eath work inprogress

As Per mile stone

RCS 9 Y2-248Road Ponnapudi R&B Road toRamachendrapuram.

Yes58/2012-201320.03.13

19.09.13 19.02.14 19.06.14 GSB completed As Per mile stone

RCS 10 Y2-249 Ponnapudi R&B road to Busagadipalem Yes58/2012-201320.03.13

19.09.13 19.02.14 19.06.14 GSB progress As Per mile stone

RCS 11 Y2-250Road from Ponnapudi R&B Road toLakshimipuram

Yes58/2012-201320.03.13

19.09.13 19.02.14 19.06.14Eath work inprogress

As Per mile stone

RCS 12 Y2-251 Road from R&B Road to Ramalingapuram Yes58/2012-201320.03.13

19.09.13 19.02.14 19.06.14Eath work inprogress

As Per mile stone

8NCRMP/B-W/AP/RCS/PRED/09/Chillakur/ 014

RCS 13 Y2-252Road from R&B Road Lingavaram toNarravaripalem

Yes63/2012-201321.03.13

20.09.13 20.12.13 19.03.14 GSB Progress As Per mile stone

9NCRMP/B-W/AP/RCS/PRED/09/Chillakur/015

RCS 14 Y2-253Road from R&B road (via) Narravaripalrm toSrinivasa Satram

Yes64/2012-201321.03.13

20.08.13 20.12.13 20.03.14 GSB is progress As Per mile stone

10NCRMP/B-W/AP/RCS/PRED/09/Kota/016

RCS 15 Y2-254Road from R&B Road to Doruvukatta road (via)Allmpadu, Deyyaladibba

Yes55/2012-201320.03.13

19.08.13 18.12.13 19.03.14 BT completed As Per mile stone

RCS 16 Y2-255Road from Kotha Kudur – Katepalli road toPatha Pattapupalem

Yes51/2012-201318.03.13

17.09.13 17.02.14 17.06.14 Not started

RCS 17 Y2-256 Road from C.S. Puram to Edurupalem Yes51/2012-201318.03.13

17.09.13 17.02.14 17.06.14 GSB progress As Per mile stone

RCS 18 Y2-257Road from Mahlakshmi puram to SagaraSangamam (via) Muthyalathopu Pattapupalem

Yes51/2012-201318.03.13

17.09.13 17.02.14 17.06.14 WMM completed As Per mile stone

RCS 19 Y2-258Road from R&B road Nelaturu to AnanthavaramCS

Yes51/2012-201318.03.13

17.09.13 17.02.14 17.06.14 Not started

5

7

11

NCRMP/B-W/AP/RCS/PRED/09/I. Pet/018

NCRMP/B-W/AP/RCS/PRED/09/Vidavaluru/ 021

NCRMP/B-W/AP/RCS/PRED/09/T.P.Gudur& Muthukur/019

NCRMP/B-W/AP/RCS/PRED/09/TADA/009

AgreementNo. / Date

STATUS OF WORKS IN SPSR NELLORE DISTRICT AS ON 30.06.2013

Sl.No.

Package Nos.catagory

S.noProject

codeWork name

Mile stone completion datesProgress w.r.t Mile

stoneRemarks

ContractDocumentreviewed

or Not

Page 32 of 141

Page 34: Quarterly Progress Report to the end of June 2013.pdf

First second Third

AgreementNo. / Date

STATUS OF WORKS IN SPSR NELLORE DISTRICT AS ON 30.06.2013

Sl.No.

Package Nos.catagory

S.noProject

codeWork name

Mile stone completion datesProgress w.r.t Mile

stoneRemarks

ContractDocumentreviewed

or Not

12NCRMP/B-W/AP/RCS/PRED/09/Tada/024

RCS 20 Y2-259Road from @ Km 65/4 of CK Road to TadaKuppam CS

Yes65/2012-201322.03.13

21.07.13 21.10.13 21.12.13 GSB progress As Per mile stone

13NCRMP/B-W/AP/RHB/PRED/09/Allur/018

RHB 21 Y2-419Road from R.I Road to C.R. Palem (via)Sambhunipalem

Yes48/2012-201318.03.13

17.08.13 17.12.13 17.03.14Eath work inprogress

As Per mile stone

RHB 22 Y2-420Salt Road from Iskapalli to Salt fields at KothaKurrupattapupalem

Yes50/2012-201318.03.13

17.08.13 17.12.13 17.03.14 WMM progress As Per mile stone

RHB 23 Y2-421 Road from R&B road to Zuvvagu Lakshmipuram Yes50/2012-201318.03.13

17.08.13 17.12.13 17.03.14 GSB progress As Per mile stone

RHB 24 Y2-422 Road from R&B Road to Zuvvagu Yes50/2012-201318.03.13

17.08.13 17.12.13 17.03.14 WMM progress As Per mile stone

RHB 25 Y2-423Road from Annagaripalem R&B road toPedanattu Pattapupalem

Yes47/2012-201304.03.13

03.8.13 03.12.13 03.03.14Eath work inprogress

As Per mile stone

RHB 26 Y2-424 Road from Pedapattapupalem to Nandempuram Yes47/2012-201304.03.13

03.8.13 03.12.13 03.03.14 WMM progress As Per mile stone

RHB 27 Y2-425 Ponnapudi-Utukur road to Pattapupalem Yes62/2012-201321.03.13

20.8.13 20.12.13 20.03.14Eath work inprogress

As Per mile stone

RHB 28 Y2-426 Road from R&B road to Venkatareddypalem Yes62/2012-201321.03.13

20.8.13 20.12.13 20.03.14Eath work inprogress

As Per mile stone

RHB 29 Y2-427 Ponnapudi R&B road to Anjanayapuram Yes62/2012-201321.03.13

20.8.13 20.12.13 20.03.14Eath work inprogress

As Per mile stone

RHB 30 Y2-428 Ponnapudi – Utukur road to Srigowripuram Yes60/2012-2013Dated21.03.13

20.09.13 20.02.14 20.06.14 Jungle clearance As Per mile stone

RHB 31 Y2-429Road from Ponnapudi – Utukur R&B road ToKothuru

Yes60/2012-2013Dated21.03.13

20.09.13 20.02.14 20.06.14 GSB progress As Per mile stone

RHB 32 Y2-430Road from Ponnapudi – Utukur R&B road toPrasanthi giri colony

Yes60/2012-2013Dated21.03.13

20.09.13 20.02.14 20.06.14 WMM progress As Per mile stone

RHB 33 Y2-431Ponnapudi R & B road toVenkatanarayanapuram

Yes60/2012-2013Dated21.03.13

20.09.13 20.02.14 20.06.14 WMM progress As Per mile stone

RHB 34 Y2-432 Road from Ponnapudi R & B road to Ponnapudi Yes60/2012-2013Dated21.03.13

20.09.13 20.02.14 20.06.14CC pavementcompletd

As Per mile stone

RHB 35 Y2-433Road from Mypadu R&B Road toKollimittapalem

Yes61/2012-2013Dated21.03.13

20.08.13 20.12.13 20.03.14 GSB progress As Per mile stone

RHB 36 Y2-434Road from Nellore – Mypadu R&B Road to WestPattapupalem

Yes61/2012-2013Dated21.03.13

20.08.13 20.12.13 20.03.14Eath work inprogress

As Per mile stone

19NCRMP/B-W/AP/RHB/PRED/09/V.Chalam/021

RHB 37 Y2-435Road from Thirumalammapalem R&B Road toGajulapalli Koneru

Yes40/2012-2013Dated 08.02.13

07.07.13 07.11.13 07.02.14 BT completed As Per mile stone

20NCRMP/B-W/AP/RHB/PRED/09/Kota/022

RHB 38 Y2-436Road from R&B road Kothapatnam toYamadinnepalem (via) Srinivasasatram

Yes53/2012-2014Dated19.03.13

18.09.13 18.02.14 18.06.14 GSB completed As Per mile stone

21NCRMP/B-W/AP/RHB/PRED/09/Kota/023

RHB 39 Y2-437Road from at km 22/5 of Yamadinne palemroad to Gunnampadia

Yes41/2012-2013Dated 08.02.13

07.06.13 07.09.13 07.11.13 BT completed As Per mile stone

17

18

NCRMP/B-W/AP/RHB/PRED/09/Vidavaluru/026

NCRMP/B-W/AP/RHB/PRED/09/I.Peta/027

14

15

16

NCRMP/B-W/AP/RHB/PRED/09/Allur/019

NCRMP/B-W/AP/RHB/PRED/09/Kavali/024

NCRMP/B-W/AP/RHB/PRED/09/Vidavaluru/025

Page 33 of 141

Page 35: Quarterly Progress Report to the end of June 2013.pdf

Annexure - B

NCR Status of Works

Page 34 of 141

Page 36: Quarterly Progress Report to the end of June 2013.pdf

Sl.No.

Package No.catago

ryProject

codeWork name

Date ofIssued

NCRNo.

Observations Remedial meassures Present status of NCR

1NCRMP/B-W/AP/RCS/PRED/01/Polaki/006.

RCS Y1-098Road from Talasamudram to

Dola regulator08.06.13 57

aggrement Time completed on 31.05.13,Work continued without sanctioned EOAT,WBM Gr-III layer laid without any intimationot TPQA

NCR-57 Issued and the contractor/LineDepartment is requested to take suitableremedial action .

pending

2NCRMP/B-W/AP/MPCS/

PRED/01/Gara/015.MPCS Y2-028

Construction of Cycloneshelter at Calingapatnam

15.06.13 1 Cyclone shelter site located in village limits,Insistsed to provide strong barrication.

NCR-1 Issued and the contractor/LineDepartment is requested to take suitableremedial action .

pending

3NCRMP/B-W/AP/MPCS/

PRED/01/Gara/015.MPCS Y2-029

Construction of Cycloneshelter at bandaruvanipeta

15.06.13 2 Cyclone shelter site located in village limits,Insistsed to provide strong barrication.

NCR-2 Issued and the contractor/LineDepartment is requested to take suitableremedial action .

pending

4NCRMP/B-W/AP/RCS/

PRED/01/V.Kotturu/001.RCS Y2-147

Road from R&B road tyo SJpuram

17.06.13 3At Some locations, in shoulder portionelectrical poles are observed, insist to shiftthe electrical poles

NCR-3 Issued and the contractor/LineDepartment is requested to take suitableremedial action .

pending

5NCRMP/B-W/AP/MPCS/PRED/01/V.kotturu/013.

MPCS Y2-25Construction of Cyclone

shelter at Metturu17.06.13 4 Cyclone shelter site located in School premisis

, Insistsed to provide strong barrication.

NCR-4 Issued and the contractor/LineDepartment is requested to take suitableremedial action .

pending

6NCRMP/B-W/AP/MPCS/PRED/01/V.kotturu/004.

MPCS Y2-010Construction of Cyclone

shelter at Bypalli17.06.13 5 Cyclone shelter site located in School premisis

, Insistsed to provide strong barrication.

NCR-5 Issued and the contractor/LineDepartment is requested to take suitableremedial action .

pending

7NCRMP/B-W/AP/MPCS/PRED/01/V.kotturu/004.

MPCS Y2-011Construction of Cycloneshelter at Chinavanka

17.06.13 6 Cyclone shelter site located in School premisis, Insistsed to provide strong barrication.

NCR-6Issued and the contractor/LineDepartment is requested to take suitableremedial action .

pending

8NCRMP/B-W/AP/MPCS/PRED/01/V.kotturu/004.

MPCS Y2-012Construction of Cycloneshelter at ChinaKotturu

17.06.13 7 Cyclone shelter site located in School premisis, Insistsed to provide strong barrication.

NCR-7Issued and the contractor/LineDepartment is requested to take suitableremedial action .

pending

9NCRMP/B-W/AP/RHB/

PRED/01/Santhabommali/001B.

RHB Y2-270Road from DPN road togangaram village via

Srikrishnapuram, palatalagam17.06.13 8

bridge portion execavated and barrication notprovided, Insisted to Provide strongbarrication.

NCR-8Issued and the contractor/LineDepartment is requested to take suitableremedial action .

pending

10NCRMP/B-W/AP/MPCS/PRED/01/Polaki/018.

MPCS Y2-030Construction of Cycloneshelter at Akkuvaram

17.06.13 9 Cyclone shelter site located in School premisis, Insistsed to provide strong barrication.

NCR-9Issued and the contractor/LineDepartment is requested to take suitableremedial action .

pending

11NCRMP/B-W/AP/RHB/PRED/01/Polaki/007.

RHB Y2-274Road from Guppidipeta to

Chinnakovvaripeta29.06.13 10

the GSB layer thickness verified at Km0/045,0/360,0/600 and observed thicknessare 90mm, 95mm, and 92mm respectivelyinstead of 100 mm as specified drawing.Insisted to rectify the same.

NCR-10Issued and the contractor/LineDepartment is requested to take suitableremedial action .

pending

NCR STATUS OF SRIKAKULAM DISTRICT AS ON 30.06.2013

Page 35 of 141

Page 37: Quarterly Progress Report to the end of June 2013.pdf

Sl.No.

Package No.catago

ryProject

codeWork name

Date ofIssued

NCRNo.

Observations Remedial meassures Present status of NCR

1 NCRMP/B-W/AP/RCS/PRED/03/Bheemili/005

RCS Y2-165 Road from R&B road toChinanagamayyapalemcyclone shelter

20.05.2013 1 WBM Gr-III sample collected and condut thesive analysis test .The test results are IS sieve45mm size at percentage of 96.13 as agaist of60% to 90%. The mateial is under size in ISsieve 45mm size.

NCR-1 Issued to take suitable remedial actionbefore proceding with further work. The rejectedmaterial to be removed from the site andreplaced with suitable material

NCR pending

2 NCRMP/B-W/AP/RHB/PRED/03/Payakaraopeta/005

RHB Y2-282 Road from R&B road toGajareddypalem

25.05.13 2 Right side compound wall is in obstructionKm2/652 to 2/658 approximaty 1mt.leftsideformers place is there.no contractor and linedepartment are tackling the land acqusitionissue at Km1/6 to Km1/9 (at stretch 400mts)shoulders not widths

NCR-2 Issued to take suitable remedial actionbefore proceding with further work.

NCR pending

3 NCRMP/B-W/AP/RHB/PRED/03/Payakaraopeta/005

RHB Y2-280 Road from R&B Roadto Rajavaram

12.06.13 3 At some locations in shoulder portion ElectricalPoles prevents formation/ Compaction ofShoulders.Insisteed to shift the Electrical Poles.

NCR-3 Issued to take suitable remedial actionbefore proceding with further work. The fieldofficer are informed that they collected thedemand note from AP Transco and sent fromapproval

NCR pending

4 NCRMP/B-W/AP/RHB/PRED/03/Payakaraopeta/008

RHB Y2-283 Road from ZP RoadPalmanpeta toKorlayyapeta

12.06.13 4 At some locations in shoulder portion ElectricalPoles prevents formation/ Compaction ofShoulders.Insisteed to shift the Electrical Poles.

NCR-4 Issued to take suitable remedial actionbefore proceding with further work. The fieldofficer are informed that they collected thedemand note from AP Transco and sent fromapproval.

NCR pending

5 NCRMP/B-W/AP/RCS/PRED/03/S.Rsyavaram/006

RCS Y2-167 Road from R&B Roadto Revu polavaramcyclone sheler

12.06.13 5 At some locations in shoulder portion ElectricalPoles prevents formation/ Compaction ofShoulders.Insisteed to shift the Electrical Poles.

NCR-5 Issued to take suitable remedial actionbefore proceding with further work. The fieldofficer are informed that they collected thedemand note from AP Transco and sent fromapproval.

NCR pending

6 NCRMP/B-W/AP/RCS/PRED/03/Rambilli/007

RCS Y2-168 Road from R&B Roadto Kothapatnamcyclone shelter

12.06.13 6 At some locations in shoulder portion ElectricalPoles prevents formation/ Compaction ofShoulders.Insisteed to shift the Electrical Poles.

NCR-6 Issued to take suitable remedial actionbefore proceding with further work. The fieldofficer are informed that they collected thedemand note from AP Transco and sent fromapproval.

NCR pending

7 NCRMP/B-W/AP/RCS/PRED/03/Bheemili/005

RCS Y2-165 Road from R&B road toChinanagamayyapalemcyclone shelter

12.06.13 7 At some locations in shoulder portion ElectricalPoles prevents formation/ Compaction ofShoulders.Insisteed to shift the Electrical Poles.

NCR-7Issued to take suitable remedial actionbefore proceding with further work. The fieldofficer are informed that they collected thedemand note from AP Transco and sent fromapproval.

NCR pending

8 NCRMP/B-W/AP/RCS/PRED/03/Bheemili/005

RCS Y2-166 Road from R&B Roadto Annavaram cycloneshelter

12.06.13 8 At some locations in shoulder portion ElectricalPoles prevents formation/ Compaction ofShoulders.Insisteed to shift the Electrical Poles.

NCR-8 Issued to take suitable remedial actionbefore proceding with further work. The fieldofficer are informed that they collected thedemand note from AP Transco and sent fromapproval.

NCR pending

NCR STATUS OF VISAKHAPATNAM DISTRICT AS ON 30.06.2013

Page 36 of 141

Page 38: Quarterly Progress Report to the end of June 2013.pdf

Sl.No.

Package No.catago

ryProject

codeWork name

Date ofIssued

NCRNo.

Observations Remedial meassures Present status of NCR

NCR STATUS OF VISAKHAPATNAM DISTRICT AS ON 30.06.2013

9 NCRMP/B-W/AP/RHB/PRED/03/Atchuthapuram/009

RHB Y2-284 Road from R&B Roadto Vadapalem

12.06.13 9 At some locations in shoulder portion ElectricalPoles prevents formation/ Compaction ofShoulders.Insisteed to shift the Electrical Poles.

NCR-9 Issued to take suitable remedial actionbefore proceding with further work. The fieldofficer are informed that they collected thedemand note from AP Transco and sent fromapproval.

NCR pending

10 NCRMP/B-W/AP/RHB/PRED/03/Payakar

aopeta/005

RHB Y2-282 Road from R&B road toGajareddypalem

17.06.13 10 Sieve analysis conducted on the coarseaggregate used for seal coat the results are

beyond the specified limits i.e is the percentagepassing through I.S Sieve 2.36mm is 10.20

NCR-10 Issued to take suitable remedial actionbefore proceding with further work.

The seal coat materialhas been seived beforeuse and test results arefound to be within thespecified limits. Hence

NCR closed

Page 37 of 141

Page 39: Quarterly Progress Report to the end of June 2013.pdf

Sl.No.

Package No.catago

ryProject

codeWork name

Date ofIssued

NCRNo.

Observations Remedial meassures Present status of NCR

1NCRMP/B-W/AP/RCS/

PRED/04/Razole &Sakhinetipalli/010

RCS Y2-173Road from R&B road to

Katrenipadu Lanka CycloneShelter

19.06.2013 1

1.Temparature of OGOC mix is 50 degres Conly as againest required temparature of 150to 160 C2. Rolling shall be completed before the mixreached 100c here the mix temparature is50c hence STOP THE WORK.

NCR-1 Issued to take suitable remedialaction before proceeding with furtherwork.

Temparature are maintaineas required verify and foundthat temparature of mix areas required. Hence StopWork order is revoked. Workis allowed to procced as ondate 28.06.2013.

NCR STATUS OF EAST GODAVARI DISTRICT AS ON 30.06.2013

Page 38 of 141

Page 40: Quarterly Progress Report to the end of June 2013.pdf

Sl.No.

Package No.catago

ryProject

codeWork name

Date ofIssued

NCRNo.

Observations Remedial meassuresPresent status of

NCR

1NCRMP/B-W/AP/RHB/PRED/ 05/Narsapur/012

RHB Y2-318SP R&B road to Pedathotaof Turputallu

01.06.2013 1

FDD test is conducted for the shoulder portion andrelative compaction is < 100 % (Compaction ofmin.100% of lab MDD )as per the agreementclause requirements

NCR-1 Issued and the contractor/LineDepartment is requested to take suitableremedial action before proceeding withfurther work.

Verified, Requiredrelative compactionachived. Hence NCRClosed.

2NCRMP/B-W/AP/RHB/PRED/ 05/Narsapur/012

RHB Y2-320R&B road to Pedathota ofTurputallu

01.06.2013 2

FDD test is conducted for the shoulder portion andrelative compaction is < 100 % (Compaction ofmin.100% of lab MDD )as per the agreementclause requirements

NCR-2 Issued and the contractor/LineDepartment is requested to take suitableremedial action before proceeding withfurther work.

Verified, Requiredrelative compactionachived. Hence NCRClosed.

3NCRMP/B-W/AP/RHB/PRED/ 05/Narsapur/013

RHB Y2-321R&B road toGuttulavarimeraka

01.06.2013 3

FDD test is conducted for the shoulder portion andrelative compaction is < 100 % (Compaction ofmin.100% of lab MDD )as per the agreementclause requirements

NCR-3 Issued and the contractor/LineDepartment is requested to take suitableremedial action before proceeding withfurther work.

Verified, Requiredrelative compactionachived. Hence NCRClosed.

4 NCRMP/B-W/AP/RHB/PRED/ 05/Narsapur/013

RHB Y2-322Road from R & B Road toPulaparthivaripalem

01.06.2013 4

FDD test is conducted for the shoulder portion andrelative compaction is < 100 % (Compaction ofmin.100% of lab MDD )as per the agreementclause requirements

NCR-4 Issued and the contractor/LineDepartment is requested to take suitableremedial action before proceeding withfurther work.

Verified, Requiredrelative compactionachived. Hence NCRClosed.

5NCRMP/B-W/AP/RHB/PRED/ 05/Narsapur/010

RHB Y2-313Road from SP R&B road toPasaladeevi

03.06.2013 5

FDD test is conducted for the shoulder portion andrelative compaction is < 100 % (Compaction ofmin.100% of lab MDD )as per the agreementclause requirements

NCR-5 Issued and the contractor/LineDepartment is requested to take suitableremedial action before proceeding withfurther work.

Verified, Requiredrelative compactionachived. Hence NCRClosed.

6 NCRMP/B-W/AP/RHB/PRED/ 05/Narsapur/010

RHB Y2-315SP R&B road toGannabathulavari palem ofChamakuripalem

03.06.2013 6

FDD test is conducted for the shoulder portion andrelative compaction is < 100 % (Compaction ofmin.100% of lab MDD )as per the agreementclause requirements

NCR-6 Issued and the contractor/LineDepartment is requested to take suitableremedial action before proceeding withfurther work.

Verified, Requiredrelative compactionachived. Hence NCRClosed.

7NCRMP/B-W/AP/RHB/PRED/ 05/Narsapur/009

RHB Y2-311

Road from NarsapurPerupalem R&B road toNellipallipalem viaAmbedkar colonyHarijanapeta

03.06.2013 7

FDD test is conducted for the shoulder portion andrelative compaction is < 100 % (Compaction ofmin.100% of lab MDD )as per the agreementclause requirements

NCR-7 Issued and the contractor/LineDepartment is requested to take suitableremedial action before proceeding withfurther work.

Verified, Requiredrelative compactionachived. Hence NCRClosed.

8NCRMP/B-W/AP/RHB/PRED/ 05/Narsapur/009

Y2-312Road from Perupalem R&BRoad to Kouruvaripalem

03.06.2013 8

FDD test is conducted for the shoulder portion andrelative compaction is < 100 % (Compaction ofmin.100% of lab MDD )as per the agreementclause requirements

NCR-8 Issued and the contractor/LineDepartment is requested to take suitableremedial action before proceeding withfurther work.

Verified, Requiredrelative compactionachived. Hence NCRClosed.

NCR STATUS OF WEST GODAVARI DISTRICT AS ON 30.06.2013

Page 39 of 141

Page 41: Quarterly Progress Report to the end of June 2013.pdf

Sl.No.

Package No.catago

ryProject

codeWork name

Date ofIssued

NCRNo.

Observations Remedial meassures Present status of NCR

1NCRMP/B-W/AP/RCS/PRED/06/Machilipatnam/008

RCS Y2-211

Road fromkammavanicheruvu R&B roadto Venkata durgambapuram inBandar Mandal

12.06.13 3

Electrical poles and Service wire is in-convinent for laying of road. So please takenecessary action and For GSB and Cartingearth work Test reports are not submitted.

NCR-3 Issued and the contractor/LineDepartment is requested to take suitableremedial action before proceeding withfurther work.

Pending

2NCRMP/B-W/AP/RCS/PRED/06/koduru/001

RCS Y2-189Road from R&B road toCyclone Shelter @ Ullipalem

26.06.13 4Electrical pole @ 375 is in the shoulderportion. So please take necessary action forfurther work,

NCR-4 issued please shift the electricalpole as soon as possible for further work.

Pending

3NCRMP/B-W/AP/RHB/PRED/06/Koduru/004

RHB Y2-328Road from R&B Road toNarsimhapuram

26.06.13 5Electrical pole 12 No's are existing in theshoulder portion.

NCR-5 issued please shift the electricalpole as soon as possible for furthur work.

Pending

4NCRMP/B-W/AP/RCS/PRED/06/Nagayalanka/005

RCS Y2-203Road from R&B to cycloneshelter at China Etimoga

01.06.13 120 mm metal tested and it is not satisfyingthe limits as per IS:383

NCR-1 Issued for not satisfying the limits ,the contractor/Line Department isrequested to take suitable remedial actionbefore proceeding with further work.

It has been rectified .Hence NCR is closed

5NCRMP/B-W/AP/RCS/PRED/06/Machilipatnam/008

RCS Y2-211

Road fromkammavanicheruvu R&B roadto Venkata durgambapuram inBandar Mandal

06.06.13 2

GSB material Sample collected from the stockyard and sieve analysis conducted forGrading -III and it is not satisfying theSpecification as per table 400.1 of Mord Theresult is found beyond the specified limits.

NCR-2 Issued and the contractor/LineDepartment is requested to take suitableremedial action before proceeding withfurther work.

It has been rectified andresults are with in limitsHence Ncr closed

NCR STATUS OF KRISHNA DISTRICT AS ON 30.06.2013

Page 40 of 141

Page 42: Quarterly Progress Report to the end of June 2013.pdf

Sl.No.

Package No.catago

ryProject

codeWork name

Date ofIssued

NCRNo.

Observations Remedial meassures Present status of NCR

1NCRMP/B-W/AP/RHB/PRED/08/Tangutur/021

RHB Y2-403Road from Tangutur toTallapalem (via) Velagapudi

04.06.2013 4Under size material is observed in GSBmaterial which was collected from the stackin KM 6/500 to KM 6/600.

NCR-4 Issued and the contractor/LineDepartment is requested to take suitableremedial action before proceeding withfurther work.

Pending

2NCRMP/B-W/AP/RHB/PRED/08/Kothapatnam/019

RHB Y2-410Road from KEM R&B Road toPinnivaripalem

05.06.2013 5 Contraction Joints are not Provided as perMORD CLAUSE 1501.8.3

NCR-5 Issued and the contractor/LineDepartment is requested to take suitableremedial action before proceeding withfurther work.

Pending

3NCRMP/B-W/AP/RHB/PRED/08/Chinaganjam/012

RHB Y2-388Road from ChinaganjamRailway Gate to BapaiahNagar

17.06.2013 10

From km 2/500 to km 2/700, WBM grade-IIMaterial is collected at site. Sieve analysistests are conducted on Random samples.Thegradation of the material collected is notsatisfying the grading requirements given inMORD TABLE 400.8

NCR-10 Issued and the contractor/LineDepartment is requested to take suitableremedial action before proceeding withfurther work.

Pending

4NCRMP/B-W/AP/RHB/PRED/08/Ulavapadu/016

RHB Y2-414 Road from M.C road to WestS.T Colony of Veerepalli

25.06.2013 11 11 Culverts are going on ,No safety measuresare taken.

NCR-11 Issued and the contractor/LineDepartment is requested to take suitableremedial action before proceeding withfurther work.

Pending

5NCRMP/B-W/AP/RCS/PRED/08/Ulavapadu/009

RCS Y2-239 Road from Pallepalem ofChakicherla

25.06.2013 12A Carved stone of a temple is in obstructionin carriage way at chainage 0/675 km ,Protection is not provided.

NCR-12 Issued and the contractor/LineDepartment is requested to take suitableremedial action before proceeding withfurther work.

Pending

6NCRMP/B-W/AP/RHB/PRED/08/Kothapatnam/019

RHB Y2-413Road from KEM R&B Road toChenchupapayapalem

22.05.2013 1

WBM Gr-II material Sample collected fromthe stack from KM 0/000 to Km 0/200 andsieve analysis conducted ,The material isoversized.

NCR-1 Issued and the contractor/LineDepartment is requested to take suitableremedial action before proceeding withfurther work.

The TPQA again testedand the result found within the specified limits.Hence it is rectified on(03.06.13)

7NCRMP/B-W/AP/RHB/PRED/08/Kothapatnam/019

RHB Y2-411Salt Road from Madnur ZPRoad to Chinnapattupalem

22.05.2013 2

WBM Gr-II material Sample collected fromthe stack from KM 0/600 to 0/700 Km andsieve analysis conducted ,oversize metal isobserved.

NCR-2 Issued and the contractor/LineDepartment is requested to take suitableremedial action before proceeding withfurther work.

The TPQA again testedand the result found within the specified limits.Hence it is rectified on(03.06.13)

8NCRMP/B-W/AP/RHB/PRED/08/Chinaganjam/012

RHB Y2-388Road from ChinaganjamRailway Gate to BapaiahNagar

24.05.2013 3The Thickness of GSB varying from 85 mm to90 mm as against of 100 mm in the stretchfrom km 5/100 to 5/450 km .

NCR-3 Issued and the contractor/LineDepartment is requested to take suitableremedial action before proceeding withfurther work.

The TPQA again testedand the result found within the specified limits.Hence it is rectified on(26.06.13)

9NCRMP/B-W/AP/RHB/PRED/08/Kothapatnam/019

RHB Y2-411Salt Road from Madnur ZPRoad to Chinnapattupalem

14.06.2013 6

From km 0/350 to km 0/700, WBM grade-IIIMaterial is collected at site, Sieve analysistests are conducted on Random samples .Thegradation of the material collected is notsatisfying the grading requirements given inMORD TABLE 400.8

NCR-6 Issued and the contractor/LineDepartment is requested to take suitableremedial action before proceeding withfurther work.

The TPQA again testedand the result found within the specified limits.Hence it is rectified on(20.06.13)

10NCRMP/B-W/AP/RHB/PRED/08/Kothapatnam/020

RHB Y2-401Salt Road from Madnur ZPRoad to Namburi YanadiColony

14.06.2013 7

WBM Gr-II material Sample collected fromthe stack from KM 0/700 to 0/800 Km andGradation test conducted ,The material isundersized .

NCR-7 Issued and the contractor/LineDepartment is requested to take suitableremedial action before proceeding withfurther work.

The TPQA again testedand the result found within the specified limits.Hence it is rectified on(20.06.13)

NCR STATUS OF PRAKASAM DISTRICT AS ON 30.06.2013

Page 41 of 141

Page 43: Quarterly Progress Report to the end of June 2013.pdf

Sl.No.

Package No.catago

ryProject

codeWork name

Date ofIssued

NCRNo.

Observations Remedial meassures Present status of NCR

NCR STATUS OF PRAKASAM DISTRICT AS ON 30.06.2013

11NCRMP/B-W/AP/RHB/PRED/08/Kothapatnam/020

RHB Y2-400Salt Road from Madnur ZPRoad to Bapuji Yanadi Colony

14.06.2013 8

The Thickness of GSB varying from 80 mm to85 mm as against of 100 mm in the stretchfrom km 0/200 to 0/285 km ,This shall berectified immediately.

NCR-8 Issued and the contractor/LineDepartment is requested to take suitableremedial action before proceeding withfurther work.

The TPQA again testedand the result found within the specified limits.Hence it is rectified on(20.06.13)

12NCRMP/B-W/AP/RHB/PRED/08/Kothapatnam/020

RHB Y2-400Salt Road from Madnur ZPRoad to Bapuji Yanadi Colony

14.06.2013 9GSB material Sample collected from the stackfrom Km 0/000 to 0/285 Km and Gradationtest conducted The material is under sized.

NCR-9 Issued and the contractor/LineDepartment is requested to take suitableremedial action before proceeding withfurther work.

The TPQA again testedand the result found within the specified limits.Hence it is rectified on(20.06.13)

Page 42 of 141

Page 44: Quarterly Progress Report to the end of June 2013.pdf

Sl.No.

Package No.catago

ryProject

codeWork name

Date ofIssued

NCRNo.

Observations Remedial meassures Present status of NCR

1NCRMP/B-W/AP/RCS/PRED/09/KAVALI/020

RCS Y2-426Road from 230/6Km of M.CRoad to Pedapattapupalem ofKavali Mandal

07.06.2013 6Contractor fails to provide personal protectiveeqipement to the Workers

NCR-6Issued and the contractor/LineDepartment is requested to take suitableremedial action before proceeding withfurther work.

NCR PENDING

2NCRMP/BW/AP/RHB/PRED/09/Vidavalur/026

RHB Y2-432Road from Ponnapudi R & Broad to Ponnapudi in vidavalurmandal

07.06.2013 7

Contractor fails to provide personal protectiveeqipement like Helthes,shoes and safetyjackets during the worke progress to theworkers.

NCR-7Issued and the contractor/LineDepartment is requested to take suitableremedial action before proceeding withfurther work.

NCR PENDING

3NCRMP/B-W/AP/RHB/PRED/09/Allur/019

RHB Y2-420

Salt road from Iskapalli toSalt fields at KothaKurrupattapupalem of Allurmadal

07.06.2013 8

The site condition worse. Contractor fails toprovide personal protective eqipement andtemperory shelters to the workers. Workersdo not have shelter to eat.

NCR-8 Issued and the contractor/LineDepartment is requested to take suitableremedial action before proceeding withfurther work.

NCR PENDING

4NCRMP/B-W/AP/RHB/PRED/09/Kavali/024

RHB Y2-424Road from Pedapattapupalemto Nandempuram

07.06.2013 9

From km1/8 to km2/0, the camber of WMM isnot as specified. It requires immediaterectification. It shall be scarified and re-pavedto the required uniform profile. TPQAengineers shall be informed after therectification for verification.

NCR-9 issued and the contractor/LineDepartment is requested to take suitableremedial action before proceeding withfurther work.

NCR PENDING

5NCRMP/B-W/AP/RCS/PRED/09/T.P.Gudur &Muthukur/019

RCS Y2-257Road from Mahlakshmipuramto sagara sangamam(via)muthyalathopu

06.06.2013 10

From km1/4 to km1/6, the camber of WMM isnot as specified. It requires immediaterectification. It shall be scarified and re-pavedto the required uniform profile. TPQAengineers shall be informed after therectification for verification.With Regards

NCR-10 Issued and the contractor/LineDepartment is requested to take suitableremedial action before proceeding withfurther work.

NCR PENDING

6NCRMP/B-W/AP/RCS/ PRED/09/T.P.Gudur &Muthukur/019

RCS Y2-256Road from C.S Puram toEdurupalem

13.06.2013 12

From km 1/8 to km 2/2 no.of electric polesare to be shifted 11 no of Electric poles.4.Action shall be taken to shift water pipelines, two water sumps and a pressurerelease valve in the carriageway From km1/8 to km 2/2.

NCR-12 Issued and the contractor/LineDepartment is requested to take suitableremedial action before proceeding withfurther work.

NCR PENDING

7NCRMP/B-W/AP/RHB/PRED/09/Allur/019

RHB Y2-420

Salt road from Iskapalli toSalt fields at KothaKurrupattapupalem of Allurmadal

27.06.2013 13

Honey combs are observed at no.of places onthe body walls of vented road dam inKm2/10.They should be finished neatly. AsperMORD clause 811. Further proper shutteringshould be done.

NCR-13 Issued and the contractor/LineDepartment is requested to take suitableremedial action before proceeding withfurther work.

NCR PENDING

8NCRMP/B-W/AP/RHB/PRED/09/Allur/019

RHB Y2-420

Salt road from Iskapalli toSalt fields at KothaKurrupattapupalem of Allurmadal

03.05.2013 1

Sand collected for pipe culvert in km 2/6 issea sand. It is not suitable for concrete

works ,Hence rejected. The sand, has to beremoved from site immediatery.

NCR-1 issued. The sand shall be removedimediately

Rejected sand is removedfrom site. Hence NCR

Closed.

9NCRMP/B-W/AP/RHB/PRED/09/Allur/019

RHB Y2-422Road from R&B road toZuvvagu

03.05.2013 2

Sand collected for pipe culvert in km 1/8 issea sand. It is not suitable for concrete

works ,Hence rejected the sand, has to beremoved from site.

NCR-2 issued. the sand shall be removedimediately

Rejected sand is removedfrom site. Hence NCR

Closed.

10NCRMP/B-W/AP/RCS/PRED/09/KOTA/016

RCS Y2-254

Road from R&B Road toDoruvukatta road (via)Allmpadu, Deyyaladibba ofKota mandal

15.05.2013 3

20mm graded material as per mix designproportion is not satisfy the specified gradinggiven in MORD Table 800.1 .NCR-03 issued.Suitable remidial action shall be taken before

proceding with further work.

NCR-3 Issued and the contractor/LineDepartment is requested to take suitableremedial action before proceeding withfurther work.

Remediel action is taken.Hence Closed

NCR STATUS OF SPSR NELLORE DISTRICT AS ON 30.06.2013

Page 43 of 141

Page 45: Quarterly Progress Report to the end of June 2013.pdf

Sl.No.

Package No.catago

ryProject

codeWork name

Date ofIssued

NCRNo.

Observations Remedial meassures Present status of NCR

NCR STATUS OF SPSR NELLORE DISTRICT AS ON 30.06.2013

11NCRMP/BW/AP/RHB/PRED/09/I.Peta/027

RHB Y2-433 Road from Mypadu R&B Roadto Kollimittapalem

20.05.2013 4

20mm graded material as per mix designproportion is not satisfy the specified gradinggiven in MORD Table 800.1 .NCR-04 issued.Suitable remidial action shall be taken before

proceding with further work.

NCR-4 Issued and the contractor/LineDepartment is requested to take suitableremedial action before proceeding withfurther work.

Remediel action is taken.Hence Closed

12NCRMP/B-W/AP/RHB/PRED/09/Kota/022

RHB Y2-436

Road from R&B roadKothapatnam toYamadinnepalem (via)Srinivasasatram

21.05.2013 5

GSB (HBG) material collected is notsatisfying the gradation requrement ofgrading III of the MORD table 400.1.It

requires the addition of higher size material(retained of 4.75mm size seive). Suitable

remidial action shall be taken beforeproceding with further work.

NCR-5Issued and the contractor/LineDepartment is requested to take suitableremedial action before proceeding withfurther work.

Remediel action is taken.Hence Closed

13NCRMP/BW/AP/RHB/PRED/09/I.Peta/027

RHB Y2-433Road from Mypadu R&B Roadto Kollimittapalem

12.06.2013 11

GSB layer thickness is verified from km0/240 to km 0/250. The thickness varying

from 90mm to 96mm as against the specifiedthickness of 100mm. It shall be rectified and

intimated for verification.

NCR-11 Issued and the contractor/LineDepartment is requested to take suitableremedial action before proceeding withfurther work.

Remediel action is taken.Hence Closed

Page 44 of 141

Page 46: Quarterly Progress Report to the end of June 2013.pdf

Annexure - C

QC Tests conducted by TPQA

Page 45 of 141

Page 47: Quarterly Progress Report to the end of June 2013.pdf

Done in thisQuarter months

Passed in thisQuarter months

Failed in thisQuarter months

1 Embankment 0 0 0 Nil 0 -

2 Shoulders -

3 Granular Sub Base 12 12 0 0 0 -

4 Base Course (WBM) 0 0 0 0 0 -

5 TACK COAT/ SDBC/ OGPC 0 0 0 0 0 _

6 Sand 24 24 0 0 0

7 Coarse Agreegate 20 20 0 0 0

8 Cement 2 2 0 0 0

9 Steel 6 6 0 0 0

10 CC cubes 8 sets 8 sets 0 0 0

11 Slump test 32 32 0 0 0

12 Water test 2 2 0 0 0

13 core cutting test 0 0 0 0 0

Total 106 106 0 0 0 -

Tests on Materials (CD Works)

Summary of QC Tests done by TPQA during Quarter-1 ending June-2013 in Srikakulam District

Sl.No

Layer/Component of Road

No. of testsNo. of tests

rectified in thisQuarter months

CumulativeRectifications

PendingRemarks

Page 46 of 141

Page 48: Quarterly Progress Report to the end of June 2013.pdf

Done in thisQuarter months

Passed in thisQuarter months

Failed in thisQuarter months

1 Embankment 0 0 0 0 0 -

2 Soil /Shoulders/SGD 0 0 0 0 0 -

3 Granular Sub Base 0 0 0 0 0 -

4 Base Course (WMM) 0 0 0 0 0 -

5 SDBC 0 0 0 0 0 -

6 Sand 4 4 0 0 0 -

7 Coarse Agreegate 8 8 0 0 0

8 Cement 1 1 0 0 0 -

9 Steel & Water 0 0 0 0 0 -

10 pH Values 2 2 0 0 0 -

11 CC cubes 1 1 0 0 0 -

12 Workability 12 12 0 0 0 -

Total 28 28 0 0 0 -

Tests on Materials (CD Works)

Summary of QC Tests done by TPQA during Quarter-1 ending June-2013 in Vizianagaram District

Sl.No

Layer/Component of RoadNo. of tests No. of tests

rectified in thisQuarter months

CumulativeRectifications

PendingRemarks

Page 47 of 141

Page 49: Quarterly Progress Report to the end of June 2013.pdf

Done in thisQuarter months

Passed in thisQuarter months

Failed in thisQuarter months

1 Embankment 0 0 0 0 0 -

2 Soil 4 4 0 0 0 -

3 Granular Sub Base/ Shoulders 24 24 0 0 0 -

4 Base Course (WBM) 74 73 1 0 1 -

5 OGPC 14 13 1 1 0 -

6 Sand 56 56 0 0 0 -

7 Coarse Agreegate 66 66 0 0 0 -

8 Cement 9 9 0 0 0 -

9 Steel & Water 0 0 0 0 0 -

10 pH Value 24 24 0 0 0 -

11 CC cubes 57 57 0 0 0 -

12 Workability 151 151 0 0 0 -

13 Bricks 7 7 0 0 0 -

14 Rebound Hammer 8 8 0 0 0 -

Total 494 492 2 1 1 -

Tests on Materials (CD Works)

Summary of QC Tests done by TPQA during Quarter-1 ending June-2013 in Visakhapatnam District

Sl.No

Layer/Component of Road

No. of testsNo. of tests

rectified in thisQuarter months

CumulativeRectifications

PendingRemarks

Page 48 of 141

Page 50: Quarterly Progress Report to the end of June 2013.pdf

Done in thisQuarter months

Passed in thisQuarter months

Failed in thisQuarter months

1 Embankment 0 0 0 0 0 0

2 Shoulders 0 0 0 0 0 0

3 Granular Sub Base 0 0 0 0 0 0

4 Base Course (WBM) 5 5 0 0 0 0

5 OGPC 6 6 0 0 0 0

6 Sand 10 10 0 0 0 0

7 Coarse Aggregate 16 16 0 0 0 0

8 Cement 8 8 0 0 0 0

9 Steel 0 0 0 0 0 0

10 CC cubes 8Set 8Set 0 0 0 0

11 Slump test 34 34 0 0 0 0

Total 79 79 0 0 0 0

Tests on Materials (CD Works) for Pipe Culverts, slab Culvert, CC Pavement, R&B Bridge and MPCS

Summary of QC Tests done by TPQA during Quarter-1 ending June-2013 in East Godavari District

Sl.No

Layer/Component of Road

No. of testsNo. of tests

rectified in thisQuarter months

CumulativeRectifications

PendingRemarks

Page 49 of 141

Page 51: Quarterly Progress Report to the end of June 2013.pdf

Done in thisQuarter months

Passed in thisQuarter months

Failed in thisQuarter months

1 Embankment - - - - -

2 Shoulders - - - - -

3 Sub Grade 59 43 16 16 -

4 Granular Sub Base 15 15 - - -

5 Base Course (WMM) 15 15 - - -

6 SDBC 6 6 - - -

7 Sand 13 13 - - -

8 Coarse Aggregate 13 13 - - -

9 Cement 2 2 - - -

10 Steel - - - - -

11 CC cubes 9 9 - - -

12 Slump test 13 13 - - -

Total 145 129 16 16 0 0

Tests on Materials (CD Works)

Summary of QC Tests done by TPQA during Quarter-1 ending June-2013 in West Godavari District

Sl.No

Layer/Component of Road

No. of testsNo. of tests

rectified in thisQuarter months

CumulativeRectifications

PendingRemarks

Page 50 of 141

Page 52: Quarterly Progress Report to the end of June 2013.pdf

Done in thisQuartermonths

Passed in thisQuartermonths

Failed in thisQuartermonths

1 Embankment 0 0 0 0 0 0

2 Shoulders 0 0 0 0 0 0

3 Sub grade 0 0 0 0 0 0

3 Granular Sub Base 6 5 1 1 0 0

4 Base Course (WMM) 4 4 0 0 0 0

5 SDBC 0 0 0 0 0 0

6 Sand 8 8 0 0 0 Nil

7 Coarse Aggregate 14 13 1 0 0 0

8 Cement 0 0 0 0 0 0

9 Steel 0 0 0 0 0 0

10 CC cubes 1 1 0 0 0 0

11 CC Cores 0 0 0 0 0 0

12 Slump test 0 0 0 0 0 0

13 Field density by core cutter method 0 0 0 0 0 0

14 Field density test by sand replacement method 9 9 0 0 0 0

Total 42 40 2 1 0 0

Tests on Materials (CD Works)

Summary of QC Tests done by TPQA during Quarter-1 ending June-2013 in Krishna District

Sl.No

Layer/Component of Road

No. of tests No. of testsrectified in this

Quartermonths

CumulativeRectifications

PendingRemarks

Page 51 of 141

Page 53: Quarterly Progress Report to the end of June 2013.pdf

Done in thisQuarter months

Passed in thisQuarter months

Failed in thisQuarter months

1 Embankment 0 0 0 0 0 -

2 Sub Grade 0 0 0 0 0 -

3 Granual Sub Base

Gradation 1 1 0 0 0 -

Relative Compaction (FDD) 0 0 0 0 0 -

4 WBM Grade-II

Gradation 0 0 0 0 0 -

Volumetric Analysis 0 0 0 0 0 -

Aggregate Impact Value 0 0 0 0 0 -

Water Absorption 0 0 0 0 0 -

Screenings 0 0 0 0 0 -

5 WBM Grade-III

Gradation 0 0 0 0 0 -

Volumetric Analysis 0 0 0 0 0 -

Aggregate Impact Value 0 0 0 0 0 -

Water Absorption 0 0 0 0 0 -

Screenings 0 0 0 0 0 -

6 Prime Coat

Rate of spread of Binder 0 0 0 0 0 -

7 Tack Coat

Rate of spread of Binder 0 0 0 0 0 -

8 OGPC

Grading of 13.2mm & 11.2mm chips 0 0 0 0 0 -

Summary of QC Tests done by TPQA during Quarter-1 ending June-2013 in Guntur District

Sl.No

Layer/Component of Road

No. of testsNo. of tests

rectified in thisQuarter months

CumulativeRectifications

PendingRemarks

Page 52 of 141

Page 54: Quarterly Progress Report to the end of June 2013.pdf

Done in thisQuarter months

Passed in thisQuarter months

Failed in thisQuarter months

Sl.No

Layer/Component of Road

No. of testsNo. of tests

rectified in thisQuarter months

CumulativeRectifications

PendingRemarks

Temperature 0 0 0 0 0 -

% of BT Content 0 0 0 0 0 -

9 Seal Coat

Temperature 0 0 0 0 0 -

% of BT Content 0 0 0 0 0 -

10 OGPC + SC

Bitumen Extraction Test 0 0 0 0 0 -

11 Shoulder

Sand Replacement (FDD) 0 0 0 0 0 -

12 Concrete

Cement 1 1 0 0 0 -

Combined Gradation 1 1 0 0 0 -

FA-Silt Content 1 1 0 0 0 -

CA-Gradation

CA-AIV 1 1 0 0 0 -

CA-Water Absorption

Water pH Test 1 1 0 0 0 -

Slump 2 2 0 0 0 -

Concrete Cubes 1 1 0 0 0 -

Concrete Core 0 0 0 0 0 -

Rebound Hammer 0 0 0 0 0 -

9 9 0 0 0Total

Page 53 of 141

Page 55: Quarterly Progress Report to the end of June 2013.pdf

Done in thisQuarter months

Passed in thisQuarter months

Failed in thisQuarter months

1 Embankment 0 0 0 0 0

2 Sub Grade 0 0 0 0 0

3 Granual Sub Base

Gradation 55 54 1 1 0

Relative Compaction(FDD) 37 37 0 0 0

4 WBM Grade-II

Gradation 20 19 1 0 1

Volumetric Analysis 6 6 0 0 0

Aggregate Impact Value 6 6 0 0 0

Water Absorption 10 10 0 0 0

Screenings 20 20 0 0 0

5 WBM Grade-III

Gradation 10 9 1 1 0

Volumetric Analysis 2 2 0 0 0

Aggregate Impact Value 2 2 0 0 0

Water Absorption 4 4 0 0 0

Screenings 8 8 0 0 0

6 Prime Coat

Rate of spread of Binder 6 6 0 0 0

7 Tack Coat

Rate of spread of Binder 6 6 0 0 0

Summary of QC Tests done by TPQA during Quarter-1 ending June-2013 in Prakasam District

Sl.No

Layer/Component of RoadNo. of tests No. of tests

rectified in thisQuarter months

CumulativeRectifications

PendingRemarks

Page 54 of 141

Page 56: Quarterly Progress Report to the end of June 2013.pdf

Done in thisQuarter months

Passed in thisQuarter months

Failed in thisQuarter months

Sl.No

Layer/Component of RoadNo. of tests No. of tests

rectified in thisQuarter months

CumulativeRectifications

PendingRemarks

8 OGPC

Grading of 13.2mm & 11.2mm chips 12 12 0 0 0

Temperature 6 6 0 0 0

% of BT Content 6 6 0 0 0

9 Seal Coat

Temperature 6 6 0 0 0

% of BT Content 6 6 0 0 0

10 OGPC + SC

Bitumen Extraction Test 12 12 0 0 0

11 Shoulder

Sand Replacement (FDD) 0 0 0 0 0

12 Concrete

Cement 11 11 0 0 0

Combined Gradation 29 29 0 0 0

FA-Silt Content 21 21 0 0 0

CA-Gradation 21 21 0 0 0

CA-AIV 10 10 0 0 0

CA-Water Absorption 11 11 0 0 0

Water pH Test 30 30 0 0 0

Slump 42 42 0 0 0

Concrete Cubes 44 44 0 0 0

Concrete Core

Rebound Hammer

459 456 3 2 1Total

Page 55 of 141

Page 57: Quarterly Progress Report to the end of June 2013.pdf

Done in thisQuarter months

Passed in thisQuarter months

Failed in thisQuarter months

1 Embankment 96 96 0 0 0 0

2 Sub Grade 93 93 0 0 0 0

3 Granual Sub Base 203 202 1 0 0 0

4 WMM 69 69 0 0 0 0

5 MSS 45 45 0 0 0 0

6 Sand 77 75 2 0 0 0

7 Coarse Agreegate 44 42 2 0 0 0

8 Cement 57 57 0 0 0 0

9 Steel 0 0 0 0 0 0

10 CC cubes 133 133 0 0 0 0

11 Cores 4 4 0 0 0 0

12 Slump 110 110 0 0 0 0

13 Water ph 24 24 0 0 0 0

Total 955 950 5 0 0 0

Summary of QC Tests done by TPQA during Quarter-1 ending June-2013 in SPSR Nellore District

Tests on Materials

CumulativeRectifications

PendingRemarks

Sl.No

Layer/Component of Road

No. of testsNo. of tests

rectified in thisQuarter months

Page 56 of 141

Page 58: Quarterly Progress Report to the end of June 2013.pdf

Annexure - D

Visits by TPQA Consultants

Page 57 of 141

Page 59: Quarterly Progress Report to the end of June 2013.pdf

Wor

ks

Vis

it m

ade

inth

is Q

uart

erm

onth

s

Wor

ks

Vis

it m

ade

inth

is Q

uart

erm

onth

s

Wor

ks

Vis

it m

ade

inth

is Q

uart

erm

onth

s

Wor

ks

Vis

it m

ade

inth

is Q

uart

erm

onth

s

Wor

ks

Vis

it m

ade

inth

is Q

uart

erm

onth

s

1 Srikakulam 24 63 11 34 13 26 1 15 0 0 138

2 Vizianagaram 1 7 5 12 0 0 0 0 0 0 19

3 Visakhapatnam 2 33 4 40 5 38 0 0 0 0 111

4 East Godavari 6 35 9 10 8 12 2 10 0 0 67

5 West Godavari 0 0 9 25 24 105 0 0 0 0 130

6 Krishna 0 0 22 15 23 17 0 0 0 0 32

7 Guntur 2 12 4 15 1 8 2 15 0 0 50

8 Prakasam 0 0 11 25 23 87 1 2 0 0 114

9 Nellore 0 0 20 59 19 69 0 0 0 0 128

35 150 95 235 116 362 6 42 0 0 789Total

Sl.No.

District

MPCS RCS

Tota

l Vis

its

NCRMP WORKS - ABSTRACT OF TPQA (CIVIL ENGG) INSPECTIONS FOR QUARTER 1 ENDING WITH JUNE-2013

PR R&B I & CADD

SALINE EMBANKMENTSRHB BRIDGES

Page 58 of 141

Page 60: Quarterly Progress Report to the end of June 2013.pdf

1 Y2-001 MPCSConstruction of Cyclone shelter at Kollipadu inSanthabommali Mandal.

Finishings is in progress, & Sump, Septictank and compound wall execavation is in

progress.

04.04.1322.04.1305.06.1314.06.13

4

2 Y2-002 MPCSConstruction of Cyclone shelter at Runku inSanthabommali Mandal.

Finishings is in progress, & Sump, Septictank and compound wall execavation

completed

04.04.1301.05.13

14.05.13(S)05.06.1314.06.1326.06.13

6

3 Y2-010 MPCS Construction of Cyclone shelter at Bypalli Earth work completed

20.05.1321.05.1303.06.1305.06.13

21.06.13(S)22.06.13

6

4 Y2-011 MPCS Construction of Cyclone shelter at Chinavanka Earth work completed

20.05.1321.05.133.06.135.06.1321.06.1322.06.13

6

5 Y2-012 MPCS Construction of Cyclone shelter at Chinakotturu Earth work completed

29.05.135.06.1321.06.1322.06.13

4

6 Y2-018 MPCSConstruction of Cyclone shelter atKomaravanipeta

jungle clearence is in progress18.06.1328.06.13

2

7 Y2-023 MPCSConstruction of cyclone shelter inCH.Karrivanipalem

Jungle clearence is in progress 09.06.13 1

8 Y2-024 MPCSConstruction of cyclone shelter inRamayyapatnam

Jungle clearence is in progress 09.06.13 1

9 Y2-025 MPCS Construction of Cyclone shelter at Metturu PCC completed

20.05.1321.05.1303.06.1305.06.13

21.06.13(S)22.06.1325.06.13

7

10 Y2-027 MPCSConstruction of Cyclone shelter at ReddicaSunnapalli

jungle clearence is in progress 26.06.13 1

11 Y2-028 MPCS Construction of cyclone shelter at Calingapatnam PCC completed

17.05.1330.05.135.06.137.06.1315.06.1321.06.1327.06.13

7

12 Y2-029 MPCSConstruction of Cyclone shelter atBandaruvanipeta

PCC completed

17.5.1330.05.13

06.1307.06.13(S)

15.06.1321.06.1327.06.13

7

13 Y2-030 MPCSConstruction of cyclone shelter at Akkuvaram inpolaki mandal

Earth work completed

17.04.133.05.1321.05.135.06.1321.06.13

5

14 Y2-031 MPCSConstruction of Cyclone shelter atJaganadhapuram

jungle clearence is in progress18.06.13

28.06.13(S)2

TPQA (CIVIL ENGG) SITE INSPECTIONS FROM APRIL-13 TO JUNE-13

Name of the District: SRIKAKULAM

Sl.No

ProjectCode

catagory

Name of work visited Work stage Date of visitTotal visits

till date

Page 59 of 141

Page 61: Quarterly Progress Report to the end of June 2013.pdf

Name of the District: SRIKAKULAM

Sl.No

ProjectCode

catagory

Name of work visited Work stage Date of visitTotal visits

till date

15 Y2-032 MPCS Construction of Cyclone shelter at Kottamukkam jungle clearence is in progress18.06.1328.06.13

2

16 Y2-036 MPCSConstruction of Cyclone shelter atBonthalakoduru

jungle clearence is in progress 28.06.13 1

17 Y2-037 MPCSConstruction of Cyclone shelter atpatadibbalapalem

Earth work is in progress 28.06.13 1

18 Y2-145 RCS Road from Chinavanka to Gopaladavooru Road widening is in progress

18.04.1320.04.1321.04.135.06.13

4

19 Y2-146 RCSRoad from MN peta Road to Kondavooru and toCS

Road widening is in progress

18.04.1320.04.1321.04.1329.06.13

4

20 Y2-147 RCS Road from R&B road to S.J.puram GSb layer completed

18.04.1320.04.13

21.04.13(S)3.06.13

13.06.13(S)21.06.13(S)

6

21 Y2-148 RCS Road from Kothapeta Road to Sainooru CS Road widening is in progress

18.04.1320.04.1321.04.133.06.1329.06.13

5

22 Y2-154 RCSRoad from Yerramukkam Rati R&B road toDonnuvooru

Jungle clearence is in progress 29.04.13 1

23 Y2-155 RCSRoad from Yerramukkam Rati R&B road toGeddavooru

Jungle clearence is in progress 29.04.13 1

24 Y2-156 RCSRoad from R&B road Ganguwada toSingalaputtuga

Jungle clearence is in progress 29.04.13 1

25 Y2-157 RCS Road from R&B road to Akkuvaram GSB completed

17.04.1303.05.1321.05.1305.06.1308.06.13

21.06.13(S)29.06.13

7

26 Y2-158 RCS Road from R&B road to Pathadibbapalem Road widening is in progress27.04.13

19.06.13(S)29.06.13

3

27 Y2-159 RCS Road from R&B road to Pothayyapeta Road widening is in progress27.04.13

29.06.13(S)2

28 Y2-266 RHB Road from DPN R&B road to Marripadu Road widening is in progress30.05.1321.06.13

2

29 Y2-267 RHB Road from DPN R&B road to Kakarapalli Road widening is in progress30.05.1321.06.13

2

30 Y2-268 RHB Road from DPN R&B road to Marripadu Adl Road widening is in progress30.05.1321.06.13

2

31 Y2-269 RHB Road from Mulapeta BT road patalingudu jungle clearence is in progress30.05.1321.06.13

2

32 Y2-270 RHBRoad from DPN road to gangaram village ViaPalatalagam, Srikrishnapuram

Road widening is in progress and bridgeearth work is in progress.

17.04.133.05.1321.05.135.06.13

4

33 Y2-272 RHBRoad from Mabagam R&B road toDubbakavanipeta via gajapathinagaram.

300 mts CC road completed, GSB, WBMGR-II & III completedand OGPC+ Seal

coat laying is in progress 8.06.13 1

34 Y2-273 RHBDPN road to DL purtam jn via Koduru,magathapadu, Guppidipeta

Road widening and culverts work is inprogress

17.04.133.05.13

21.05.13(S)5.06.1313.06.1321.06.1329.06.13

7

Page 60 of 141

Page 62: Quarterly Progress Report to the end of June 2013.pdf

Name of the District: SRIKAKULAM

Sl.No

ProjectCode

catagory

Name of work visited Work stage Date of visitTotal visits

till date

35 Y2-274 RHB Guppidipeta road to Chinnakoviripeta GSB layer completed

17.04.133.05.13

21.05.13(S)13.06.1321.06.1329.06.13

6

36 Y2-438 R&B BrConstruction of HLB across uppugedda at Km7/6 of Srikakulam municipal limits toPukkalapeta

Slabs completed, Wing walls work is inprogress, Approach road work not started.

6.04.13,8.04.13,20.4.13,23.04.13,26.04.13,27.04.13

30.04.13(S)2.05.1310.05.1313.05.1317.05.1321.05.133.06.136.06.13

15.06.13(S)

15

138

Page 61 of 141

Page 63: Quarterly Progress Report to the end of June 2013.pdf

1 Y2-160 RCS Road from R &B Road to Gudepuvalasa cyclone shelter Earthen widening work isin progress.

30.04.1326.05.13

2

2 Y2-161 RCS Road from R &B Road to Kavulawada Cyclone Shelter Earthen widening work isin progress.

30.04.1326.05.13

2

3 Y2-162 RCS Road from R&B Road to Roluchappidi cyclone shelter Earthen widening work isin progress.

30.04.1302.05.1326.05.1318.06.13

4

4 Y2-163 RCS Road from R&B road to Chinapathiwada Cyclone shelter. Earthen widening work isin progress.

30.04.1326.05.13

2

5 Y2-164 RCS Road from R&B road to B.V.Peta cyclone shelter Earthen widening work isin progress.

30.04.1318.06.13

2

6 Y2-041 MPCS Construction of cyclone shelter at Buddugurayyapeta

Earthwork Excavationand PCC work

completed. Footings workis in progress.

30.04.1326.05.1318.06.1320.06.1322.06.1327.06.1328.06.13

7

19

TPQA (CIVIL ENGG) SITE INSPECTIONS FROM APRIL-13 TO JUNE-13

Name of the District: VIZIANAGARAM

Sl.No

ProjectCode

catagory

Name of work visited Work stage Date of visit Total visits

Page 62 of 141

Page 64: Quarterly Progress Report to the end of June 2013.pdf

Name of the District: VISAKHAPATNAM

Sl.No

ProjectCode

catagory

Name of work visited Work stageDate of

visitTotalvisits

1 Y2-048 MPCSConstruction of cyclone shelter atVenkayyapalem in Rambilli Mandal

Plinth Beam, stilt floor Ramp and stair case, stilt floor slabcompleted. Ist floor columns upto roof level completed. Istfloor stair case work completed. Ist floor slab and HeadRoom slabs are completed.Stilt floor slab and Ist floor slabceiling plastering works are completed. Ist floor Brickmasonry work completed. Inside and outside plasteringwork completed. Flooring completed. wood joinercompleted.

02.04.1306.04.1318.04.1324.04.1307.05.1310.05.1313.05.1315.05.1316.05.1321.05.1325.05.1330.05.1307.06.1315.06.13

14

2 Y2-057 MPCSConstruction of Cyclone shelter atBangarampalem I&II H/O Vakadu

stopped

03.04.1312.04.1313.04.1318.04.1303.05.1325.05.1306.05.1304.06.13

8

3 Y2-043 MPCSConstruction of Cyclone shelter atPatimeda

Work completed20.04.1327.04.13

2

4 Y2-044 MPCSConstruction of Cyclone shelter atMullaparra

Work completed20.04.1327.04.13

2

5 Y2-045 MPCSConstruction of Cyclone shelter atBangarampeta

Work completed20.04.1327.04.13

2

6 Y2-046 MPCSConstruction of Cyclone shelter atGajapathinagaram

Work completed02.04.1306.04.1309.04.13

3

7 Y2-047 MPCSConstruction of Cyclone shelter atRatnayampeta

Work completed02.04.1306.04.13

2

8 Y2-165 RCSRoad from R&B road toChinanagamayyapalem cycloneshelter

WBM Gr-II From KM 0/0 to Km 0/8 completed, CD workscompleted. WBM Gr-III From KM 0/0 to Km 0/8 work is inprogress.

23.04.1325.04.1329.04.1330.04.1302.05.1311.05.1318.05.1322.05.1324.05.1326.05.1304.06.13

11

9 Y2-166 RCSRoad from R&B road to Annavaramcyclone shelter

WBM Gr-II and CC Road work completed . WBM Gr-IIIwork is in progress.

23.04.1325.04.1329.04.1330.04.1302.05.1311.05.1318.05.1322.05.1324.05.1326.05.1304.06.13

11

10 Y2-167 RCS Road from R&B Road toRevupolavaram Cyclone shelter .

CC Road completed and Shoulders work is in progress

01.04.1303.04.1312.04.1313.04.1318.04.1303.05.1306.05.1313.05.1315.05.1325.05.1304.06.13

11

TPQA (CIVIL ENGG) SITE INSPECTIONS FROM APRIL-13 TO JUNE-13

Page 63 of 141

Page 65: Quarterly Progress Report to the end of June 2013.pdf

Name of the District: VISAKHAPATNAM

Sl.No

ProjectCode

catagory

Name of work visited Work stageDate of

visitTotalvisits

11 Y2-168 RCS Road from R&B road to KothapatnamGSB,CC Road work completed and Shoulders work to beprogress.

24.04.1307.05.1310.05.1313.05.1315.05.1325.05.1307.06.13

7

12 Y2-280 RHB Road from R&B road to Rajavaram Work is completed

02.04.1306.04.1309.04.1312.04.1320.04.1316.05.1325.05.1304.06.1312.06.13

9

13 Y2-281 RHBRoad from Rajala R&B road toRajarayyudupalem

02.04.13 1

14 Y2-282 RHBRoad from R&B road toGajareddipalem

From Km.0/106 to Km 1/600 and from km 2/0 to km2/620 GSB,WBM Gr-II,Grade-III completed and OGPC +Seal coat completed. From 1/600 to Km 2/0 and From KM2/620 to KM 2/720 GSB work is in progress.

02.04.1306.04.1318.04.1324.04.1307.05.1316.05.1325.05.1329.05.1303.06.1307.06.1315.06.1317.06.1318.06.1326.06.13

14

15 Y2-283 RHBRoad from ZP Road Palamanpeta toKorlayyapeta.

GSB,and CD works completed and CC Road and Retainingwall work is in progress.

04.06.1308.06.1312.06.1317.06.1318.06.1322.06.13

6

16 Y2-284 RHB Road from R&B road to Vadapalem CC Road completed. Shoulders work is in progress.

16.04.1318.04.1322.04.1303.05.1313.05.1319.05.1325.05.1304.06.13

8

111

Page 64 of 141

Page 66: Quarterly Progress Report to the end of June 2013.pdf

Sl.No

ProjectCode

catagory

Name of work visited Work stageDate of

visitTotalvisits

1 Y2-060 MPCS Cyclone Shelter at Avulamanda Work completion stage

05.04.2013,11.04.2013,20.04.2013,25.04.2013,30.04.2013,09.05.2013,13.05.2013,19.05.2013,22.05.2013,28.05.2013,02.06.2013,12.06.2013

12

2 Y2-061 MPCS Cyclone Shelter at Lakshmanudipeta Work completion stage

05.04.2013,11.04.2013,20.04.2013,25.04.2013,30.04.2013,09.05.2013,13.05.2013,19.05.2013,22.05.2013,28.05.2013,02.06.2013,12.06.2013

12

3 Y2-062 MPCS Cyclone Shelter at Pedaraghavulapeta1st floor & 2nd floor Flooring work is in

progress.

16.04.2013,24.04.2013,30.04.2013,03.05.2013,10.05.2013,25.05.2013,29.05.2013,07.06.2013

8

4 Y2-076 MPCSConsruction of Cyclone Shelter at Padamatipalem( Type - D)

Earth work in progress19.06.2013,28.06.2013

2

5 Y2-078 MPCSConsruction of Cyclone Shelter at Karavaka ( Type- B)

Not started 19.06.2013 1

6 Y2-289 RHB Road from R&B Road to Korukondavari Group Earth work in progress

02.05.2013,10.05.2013,18.05.2013,03.06.2013,08.06.2013,19.06.2013

6

7 Y2-290 RHB Road from R&B Road to Gondi Kodapa Earth work in progress

02.05.2013,10.05.2013,18.05.2013,03.06.2013,08.06.2013,19.06.2013

6

8 Y2-173 RCSRoad from R&B road to Katrenipadu Lanka

Cyclone ShelterOGPC + Seal coat completed from Km.0.000 to Km 0.500.

02.05.2013,10.05.2013,18.05.2013,03.06.2013,08.06.2013,19.06.2013,28.06.2013

7

9 Y2-173 RCSRoad from R&B road to Kesavadasupalem (New)

Cyclone ShelterNot started

02.05.2013,03.06.2013,08.06.2013

3

10 Y2-444 R&B BrConstruction of Bridge at Km.43/10 of Vakalapudi-Edatam road acrros Pampa Yeru in EG DT.

Pier 1,2,3 and 4 cutting edge concrete inprogress.

19.05.2013,28.05.2013,02.06.2013,12.06.2013,27.06.2013

5

11 Y2-445 R&B BrConstruction of Bridge at Km.43/6of Vakalapudi-Edatam road acrros Pampayeru in EG DT.

Not started

19.05.2013,28.05.2013,02.06.2013,12.06.2013,27.06.2013

5

67

TPQA (CIVIL ENGG) SITE INSPECTIONS FROM APRIL TO JUNE 2013

Name of the District: EAST GODAVARI

Page 65 of 141

Page 67: Quarterly Progress Report to the end of June 2013.pdf

Sl.No

ProjectCode

catagory

Name of work visited Work stageDate of

visitTotalvisits

1 Y2-178 RCSRoad from R&B road to Ayodya lanka Marrimulacyclone shelter.

Sub grade completed.

05.04.2013,23.04.2013,01

.06.2013,07.06.2013

4

2 Y2-181 RCSConstruction of approach road to cyclone shelter inLosari of Bhimavaram Mandal.

Earth Work is in Progress

29.05.2013,28.05.2013,05.06.2013,27.06.2013

4

3 Y2-182 RCSRoad from R&B road to Kothakayalathippa cycloneshelter

Sub grade completed. GSB Materialcollection.

09.04.2013,22.04.2013,06.06.2013,09.06.2013,22.06.2013

5

4 Y2-183 RCSRoad from Narsapur Perupalem R&B road toMandavarithota

Sub grade & CD works completed.

03.04.2013,22.04.2013,06.06.2013,09.06.2013,22.06.2013

5

5 Y2-184 RCSRoad from Mollaparru R & B road to MollaparruPatha Colony

Sub grade completed. CD works isin Progress.

09.04.2013,22.04.2013,06.06.2013,09.06.2013,22.06.2013

5

6 Y2-306 RHBRoad from Narsapur PerupalemR & B Road to Melamvaripalem Perupalem(S)

Sub grade completed. CD works isin Progress.

15.04.2013,22.04.2013,04.06.2013,08.06.2013,23.06.2013

5

7 Y2-307 RHBRoad from Perupalem Mollaparru R & B road viaSattinenivarimeraka to K.D.Pallavapalem

Sub grade completed. CD works isin Progress.

15.04.2013,22.04.2013,04.06.2013,08.06.2013,23.06.2013

5

8 Y2-310 RHBRoad from perupalem -Diddalapalem R & B road tomelapallavapalem

Sub grade and CD works is inProgress.

15.04.2013,22.04.2013

2

9 Y2-309 RHBRoad from Perupalem beach R & B Road toChallavarimeraka via Mucherlavarimeraka

Sub grade & CD Works is inProgress.

15.04.2013,22.04.2013,18

.05.2013,28.05.2013

4

10 Y2-310 RHB Road from Perupalem R&B road to DindlaSub grade completed. CD works inProgress.

15.04.2013,22.04.2013,18.05.2013,28.05.2013,03.06.2013,10.06.2013,24.06.2013

7

11 Y2-311 RHBRoad from Narsapur Perupalem R & B road toNellipallipalem via Ambedkar colony Harijanapeta

Sub grade completed. CD works isin Progress.

22.04.2013,18.05.2013,25.05.2013,03.06.2013,10.06.2013,

5

12 Y2-312 RHBRoad from Perupalem R & B Road toKouruvaripalem

Sub grade completed. CD works isin Progress.

22.04.2013,18.05.2013,25.05.2013,03.06.2013,10.06.2013,

5

13 Y2-313 RHB Road from SP R&B road to Pasaladeevi Sub grade & CD works completed.

22.04.2013,18.05.2013,27.05.2013,03.06.2013,08.06.2013,20.06.2013

6

14 Y2-314 RHB LT R&B road to Modi Sub grade completed..

22.04.2013,03.06.2013,08.06.2013,10.06.2013

4

TPQA (CIVIL ENGG) SITE INSPECTIONS FROM APRIL TO JUNE 2013

Name of the District: WEST GODAVARI

Page 66 of 141

Page 68: Quarterly Progress Report to the end of June 2013.pdf

Sl.No

ProjectCode

catagory

Name of work visited Work stageDate of

visitTotalvisits

Name of the District: WEST GODAVARI

15 Y2-315 RHBSP R&B road to Gannabathulavari palem ofChamakuripalem

Sub grade & CD works completed.

22.04.2013,18.05.2013,25.05.2013,03.06.2013,08.06.2013,20.06.2013

6

16 Y2-318 RHB SP R&B road to Pedathota of TurputalluSub grade, GSB, CD Workscompleted.WMM Work is inprogress.

15.04.2013,30.04.2013,14.05.2013,01.06.2013,08.06.2013,17.06.2013,18.06.2013,28.06.2013

8

17 Y2-319 RHB SP R&B road to Peta of Turputallu Sub grade work is in progress.15.04.2013,30.04.2013,20.05.2013

3

18 Y2-320 RHB R&B road to Pedathota of TurputalluSub grade, GSB, CD Workscompleted.WMM Work is inprogress.

06.04.2013,30.04.2013,18.05.2013,01.06.2013,08.06.2013,17.06.2013,18.06.2013,28.06.2013

8

19 Y2-321 RHB R&B road to Guttulavarimeraka Sub grade & GSB completed.

18.04.2013,30.04.2013,14.05.2013,18.05.2013,01.06.2013,08.06.2013,14.06.2013

7

20 Y2-322 RHB Road from R & B Road to Pulaparthivaripalem Sub grade completed.

18.04.2013,30.04.2013,14.05.2013,01.06.2013,08.06.2013

5

21 Y2-323 RHB R&B road to PedaedigapalemSub grade, GSB, CD Workscompleted.

30.04.2013,18.05.2013,03.06.2013,08.06.2013,13.06.2013,18.06.2013

6

22 Y2-324 R&B road to Evanivarimerka Sub grade is in progress18.04.2013,30.04.2013,25.05.2013

3

23 Y2-325Road from PR road Prakashpuram SC colony ofVemuladeevi(E)R&B road to Evanivarimerka

Sub grade is in progress18.04.2013,30.04.2013,18.05.2013

3

24 Y2-326 RHBRoad from PR road to Vemuladeevi (E) colony(Via)Ralla cheruvu of Vemuladeevi (E)

Scarifying, WMM & SDBCCompleted From Km 0.00 to km2.484. Shoulders work is in is inProgress.

18.04.2013,27.04.2013,02.05.2013,03.05.2013,04.05.2013,05.05.2013,06.05.2013,18.05.2013,03.06.2013,08.06.2013,09.06.2013,10.06.2013

12

25 Y2-327Road from PR road to Addalavarimerka ofVemuladeevi(E)

Sub grade is in progress18.04.2013,27.04.2013,18.05.2013

3

130

Page 67 of 141

Page 69: Quarterly Progress Report to the end of June 2013.pdf

1 Y2-328 RHB Road from R&B Road to Narsimhapuram CD work & GSB completed.

19.04.2013,20.04.2013,23.04.2013,02.05.2013,17.05.201326.06.2013

6

2 Y2-329 RHB Road from R&B Road to Krishnapuram Work not started19.04.2013,23.04.2013,17.05.2013

3

3 Y2-330 RHB Road From R&B road to Pedagudumotu CD work is in progress.19.04.2013,17.05.2013,18.06.2013

3

4 Y2-349 RHBRoad from Seethannapalli R&B Road to Gollagudem

CD works is in progress. 03.06.13 1

5 Y2-347 RHB Road from Matlam ZP road to Govindarajuladibba Work not started 03.06.13 1

6 Y2-348 RHBRoad from R & B road to Amudalapalli(Pennammadibba)

CD works is in progress. 03.06.13 1

7 Y2-350 RHB Road from R&B Road to Boligondi CD works is in progress. 17.06.13 1

8 Y2-353 RHB Road from B.L road to MatlamGravel collection is in progressfor Sub Base

17.06.13 1

9 Y2-189 RCS Road from R&B road to Cyclone Shelter @ Ullipalem CD work&GSB completed.18.05.2013,27.05.2013,26.06.2013

3

10 Y2-190 RCSRoad from R & B Road to Cyclone Shelter atJaruguvanipalem

Work not started 18.05.2013 1

11 Y2-191 RCS Road from R&B road to Cyclone Shelter @ Utagundam Work not started 18.05.2013 1

12 Y2-192 RCSRoad from R&B road to Cyclone Shelter @ Ramakrisnapuram

GSB completed18.05.201326.06.2013

2

13 Y2-193 RCS Road from R&B road to Cyclone shelter @ Chintakolla Work not started 17.05.2013 1

14 Y2-194 RCSRoad from R&B road to Cyclone Shelter @Padalavaripalem

Work not started 17.05.2013 1

15 Y2-195 RCS Road from R&B road to Cyclone Shelter @ MandapakalaGSB & WMM collection inprogress

17.05.2013,27.05.2013

2

16 Y2-203 RCS Road from R&B to cyclone shelter at China Etimoga Material collected for CD works 01.05.2013 1

17 Y2-211 RCSRoad from kammavanicheruvu R&B road to Venkatadurgambapuram in Bandar Mandal

Earth work started and GSBmaterial collection in progress

13.04.2013,06.06.2013,12.06.2013

3

32

TPQA (CIVIL ENGG) SITE INSPECTIONS FOR the QUARETER 1 ENDING WITH JUNE 2013

Name of the District: KRISHNA

Sl.No

ProjectCode

catagory Name of work visited Work stageDate of

visitTotal visits

Page 68 of 141

Page 70: Quarterly Progress Report to the end of June 2013.pdf

Sl.No

ProjectCode

catagory

Name of work visited Work stageDate of

visitTotalvisits

1 Y2-453 R&B BrConstruction of HLB across Pedapalli No-2 Drain@km 14/6 of Chandolu bridge to Nizampatnamroad

Earth work is in progress

20.4.2013,6.5.2013,9.5.2013,18.5.2013,28.5.2013,3.6.2013,13.6.2013,18.6.2013,21.6.2013,26.6.2013

10

2 42-219 RCS Road from R&B Road Allur to Yadavapalemwork completed shouldercompaction to be done.

6.4.2013,30.4.2013,6.5.2013,29.5.2013

4

3 Y2-225 RCSRoad from R&B Krosurivariplam road toMarkavaripalem

GSB is in progress

3.6.2013,13.6.13,18.6.13,21.6.13,26.6.13

5

4 Y2-227 RCS Road from R & B road to Pattapupalem Earth work is in progress21.6.13,26.6.13.

2

5 Y2-379 RHB Road from R&B road to Gattuvaripalem Earth work is in progress

9.5.13,18.5.13,28.5.13,3.6.13,13.6.13,18.6.13,21.6.13,26.6.13

8

6 Y2-450 R&B BrRe construction of HLB @km 2/4 of Bapatla -Pandurangapuram road across perali drain

Bridge completed ApproachesPending

21.6.1326.6.13

2

7 Y2-094 MPCSConstruction of MPCS at Harbour of Nizampatnamvillage

Agreement not concluded06.5.13,28.6.13

2

8 Y2-098 MPCSConstruction of CS in Fisherman colony ofNizampatnam village (Type C)

Agreement not concluded06.5.13,28.6.13

2

9 Y2-099 MPCSConstruction of CS in Near MRO office of NizamPatnam (Type B)

Agreement not concluded06.5.13,26.6.13,28.6.13

3

10 Y2-097 MPCSConstruction of CS in Sanjeevanagar ofKothapalem (Type B)

Agreement concluded12.04.1306.05.1318.5.13

3

11 Y2-100 MPCSConstruction of CS in Padamativeedhi ofNizampatnam village (Type C)

Agreement not concluded 28.6.13 1

12 Y2-224 RCS Road from R&B Road to Adarsh Nagar. work completed20.04.13,24.0413,29.06.13

3

13 Y2-223 RCS Road from R&B Road to Hanumanth Nagger work completed20.04.13,24.0413,29.06.13

3

14 Y2-450 R&B BrReconstruction of HLB@km 5/2 of Bapatla-Suryalanka road across perali drain.

work completed20.04.13,24.0413,

2

50

TPQA (CIVIL ENGG) SITE INSPECTIONS FROM APRIL TO JUNE 2013

Name of the District: GUNTUR

Page 69 of 141

Page 71: Quarterly Progress Report to the end of June 2013.pdf

Sl.No

ProjectCode

catagory

Name of work visited Work stage Date of visitTotalvisits

1 Y2-238 RCSRoad from ZP road toSriramapattapupalem in Ulavapadu Mandal

GSB Completed, CC in Progress

02.04.201322.04.201307.05.201322.05.201324.05.201304.06.201320.06.201325.06.2013

8

2 Y2-239 RCSRoad from ZP road to Pallipalem ofChakicharala in Ulavapadu Mandal

GSB Completed, CC Completed CD Completed & WBMGr-II Completed. WBM Gr-III Completed, OGPC + SCCompleted, CD Works Completed & Shoulders inProgress.

03.05.201307.05.201308.05.201314.05.201317.05.201322.05.201324.05.201304.06.201306.06.201307.06.201320.06.201325.06.2013

12

3 Y2-414 RHBRoad from MC Road to Veerapalli inUlavapadu mandal.

WBM Gr-II & Gr-III Completed, Earth WorkCompleted, 3m3v Slab Culvert Completed & 1000mmdia Single row 3 nos completed, OGPC + SCcompleted from 3/386 to 5/380, Side drains inprogress, Retaining wall 250m completed. 11 Culvertsin progress

04.04.201321.04.201307.05.201308.05.201320.05.201322.05.201324.05.201304.06.201306.06.201307.06.201320.06.201325.06.2013

12

4 Y2-397 RHBRoad from KEM R&B road toChinnapattapupalem

GSB Completed

13.04.201321.04.201330.04.201321.05.201323.05.201314.06.2013

6

5 Y2-398 RHBSalt road from Madanur ZP road toPedapattapupalem

GSB Completed, CC in Progress, WBM Grade-II & CCPavement Completed

14.04.201321.05.201323.05.201314.06.2013

4

6 Y2-399 RHBRoad from Madanur ZP road toSwarnandhrapattapupalem

GSB Completed, CC Completed.

08.04.201307.05.201313.05.201318.05.201320.05.201321.05.201323.05.201314.06.2013

8

7 Y2-400 RHBRoad from Madanur ZP road toBapujiyanadi Colony

GSB Completed, CC Progress

13.04.201314.06.201320.06.201325.06.2013

4

8 Y2-401 RHBSalt road from Madanur ZP road toNamburi Yanadi Colony

GSB Completed & WBM Grade-II Progress

14.04.201313.05.201323.05.201314.06.201320.06.2013

5

9 Y2-402 RHBSalt road from Madanur ZP road toThotaguntayanadi Colony

GSB Completed

08.04.201314.06.201320.06.201325.06.2013

4

10 Y2-409 RHBRoad from KEM R&B road toVajjireddypalem - Pattapupalem

GSB Completed, WBM Gr-II collection in progress &CC Completed.

21.04.201330.04.201313.05.201323.05.2013

4

TPQA (CIVIL ENGG) SITE INSPECTIONS FROM APRIL TO JUNE 2013

Name of the District: PRAKASAM

Page 70 of 141

Page 72: Quarterly Progress Report to the end of June 2013.pdf

Sl.No

ProjectCode

catagory

Name of work visited Work stage Date of visitTotalvisits

Name of the District: PRAKASAM

11 Y2-412 RHB KEM R&B road to E.Pallipalem GSB Completed, CC Completed.

21.04.201330.04.201305.05.201308.05.201313.05.201321.05.201323.05.2013

7

12 Y2-413 RHBRoad from KEM R&B road toChenchupapayapalem

GSB Completed, WBM Gr-II Completed & Grade-IIIcollection in progress & CC in Progress

21.04.201330.04.201313.05.201323.05.201303.06.201305.06.201314.06.2013

7

13 Y2-411 RHB Salt road Madnur ZP road to ChinnapattupalemGSB Completed, WBM Gr-II Completed, CC 100mCompleted, WBM Grade-III collection in progress

13.05.201323.05.201303.06.201305.06.201314.06.201320.06.2013

6

14 Y2-410 RHB KEM R&B road to PinnivaripalemGSB Completed, WBM Gr-II Completed, CCCompleted, WBM Grade-III collection in progress

13.05.201321.05.201323.05.201331.05.201305.06.201314.06.2013

6

15 Y2-403 RHBRoad from Tangutur to Tallapalem (via)velagapudi (km 4/5 to 7/465)

Retaining Wall 145m Completed. Earth work wideningCompleted & GSB Completed

04.06.201320.06.201325.06.201328.06.2013

4

16 Y2-388 RHB Road from Chinaganjam Railway Gate to Bapaiah nagarGSB Completed, WBM Gr-II Collection in Progress

15.05.201324.05.201317.06.201326.06.2013

4

17 Y2-389 RHB Road from R&B Road to Kothapalem GSB In Progress15.05.201317.06.201326.06.2013

3

18 Y2-387 RHB Road from R&B Road to Pulavaripalem Earthwork Widening in Progress,15.05.201317.06.201326.06.2013

3

19 Y2-455 R&B BrReconstruction of high level bridge at km11/10 of ongole kothapatnam road inprakasam district

Mobilization of Equipment05.06.201314.06.2013

2

20 Y2-404 RHBRoad from Tangutur-Ravivaripalem road@1/2 km to Pasukuduru

Earthwork Widening in Progress, 28.06.2013 1

21 Y2-236 RCS Road from Tangutur to Ananthavaram Earthwork Widening in Progress, 28.06.2013 1

22 Y2-233 RCSRoad from Pakala PR Road toChellammagaripattapupalem CS

Earthwork Widening in Progress, Culvert Work inProgress

28.06.2013 1

23 Y2-234 RCSRoad from Pakala PR road toPotthaiahgaripalem CS, Kranthinagar Revu. Earthwork Widening in Progress, 28.06.2013 1

24 Y2-235 RCSRoad from Woollapalem R&B road toDevalampallipalem CS Earthwork Widening in Progress, 28.06.2013 1

114

Page 71 of 141

Page 73: Quarterly Progress Report to the end of June 2013.pdf

Sl.No

ProjectCode

catagory

Name of work visited Work stageDate of

visitTotalvisits

1 Y2-419 RHBRoad from R.I Road to C.R. Palem (via)Sambhunipalem

Eath work in progress24.05.1327.06.13

2

2 Y2-436 RHBRoad from R&B road Kothapatnam toYamadinnepalem (via) Srinivasasatram

GSB completed

15.05.1325.05.1304.06.1306.06.1321.06.13

5

3 Y2-423 RHBRoad from Annagaripalem R&B road to PedanattuPattapupalem

Eath work in progress24.05.1327.06.13

2

4 Y2-424 RHB Road from Pedapattapupalem to Nandempuram WMM progress

03.05.1310.05.1324.05.1307.06.1320.06.13

5

5 Y2-242 RCS Approach road to Labbipalem CC pavement completd24.05.1307.06.1320.06.13

3

6 Y2-243 RCS Road from R & B road to Pathakadapalem Earth work is progress24.05.1324.05.1327.06.13

3

7 Y2-256 RCS Road from C.S Puram to Edurupalem GSB progress

13.05.1324.05.1331.05.1306.06.13

4

8 Y2-257 RCSRoad from Mahlakshmi puram to SagaraSangamam (via) Muthyalathopu Pattapupalem

WMM completed

13.05.1324.05.1331.05.1306.06.13

4

9 Y2-246 RCSRoad from 230/6 Km of MC road toPedapattapupalem

GSB progress

13.04.1303.05.1310.05.1307.06.1324.05.1320.06.13

6

10 Y2-259 RCSRoad from @ Km 65/4 of C K Road to TadaKuppam Cyclone Shelter

GSB completed25.05.1330.05.1307.06.13

3

11 Y2-241 RCSProviding BT road to Peda Pannam Gadu in TadaMandal of Nellore Dt.

BT completed 20.04.13 1

12 Y2-240 RCSRoad from @ km 56/8 to CK Road to PeriyavettuKuppam Cyclone Shelter

GSB completed 20.04.13 1

13 Y2-420 RHBSalt Road from Iskapalli to Salt fields at KothaKurru pattapupalem

WMM completed

10.04.1313.04.1303.05.1309.05.1324.05.1320.06.1327.06.1329.06.13

7

14 Y2-421 RHB Road from R&B road to Zuvvagu Lakshmipuram GSB progress

10.04.1313.04.1303.05.1324.05.1320.06.13

5

15 Y2-422 RHB Road from R&B Road to Zuvvagu WMM progress

10.04.1313.04.1303.05.1309.05.1324.05.1320.06.1329.06.13

7

16 Y2-430 RHBRoad from Ponnapudi – Utukur R&B road toPrasanthigiri colony

WMM progress

03.05.1309.05.1318.05.1325.05.1307.06.1320.06.13

6

TPQA (CIVIL ENGG) SITE INSPECTIONS FROM APRIL TO JUNE 2013

Name of the District: SPSR NELLORE

Page 72 of 141

Page 74: Quarterly Progress Report to the end of June 2013.pdf

Sl.No

ProjectCode

catagory

Name of work visited Work stageDate of

visitTotalvisits

Name of the District: SPSR NELLORE

17 Y2-431 RHBPonnapudi R & B road to Venkata narayanapuram

WMM progress

03.05.1309.05.1318.05.1325.05.1307.06.1320.06.13

6

18 Y2-432 RHB Road from Ponnapudi R & B road to Ponnapudi CC pavement completd

03.05.1309.05.1318.05.1325.05.1301.06.1307.06.1320.06.13

7

19 Y2-433 RHB Road from Mypadu R&B Road to Kollimittapalem WMM completed

24.05.1312.06.1321.06.1326.06.13

3

20 Y2-437 RHBRoad from At km 22/5 of Yamadinne palem roadto Gunnampadia

BT completed25.05.1315.04.13,20.04.13

3

21 Y2-435 RHBRoad from Thirumalammapalem R&B Road toGajulapalli Koneru in V.Chalam mandal

BT completed15.04.13,20.04.1325.05.13

3

22 Y2-252 RCSRoad from R&B Road Lingavaram toNarravaripalem

GSB Progress16.05.1325.05.1321.06.13

3

23 Y2-253 RCSRoad from R&B road (via) Narravaripalrm toSrinivasa Satram

GSB is progress16.05.1325.05.1321.06.13

3

24 Y2-254 RCSRoad from R&B Road to Doruvukatta road (via)Allmpadu, Deyyaladibba

BT completed

15.05.1325.05.1304.06.1306.06.1321.06.13

5

25 Y2-244 RCSRoad from Ramudupalem on R&B road toPallipalem

GSB is progress

17.04.13,29.04.1302.05.1325.05.1321.06.1326.06.13

6

26 Y2-248 RCS Road Ponnapudi R&B Road to Ramachendrapuram GSB completed18.05.1325.05.1301.06.13

3

27 Y2-249 RCS Ponnapudi R&B road to Busagadipalem GSB progress25.05.1312.04.1320.06.13

3

28 Y2-250 RCS Road from Ponnapudi R&B Road to Lakshimipuram Eath work in progress25.05.1320.06.13

2

29 Y2-251 RCS Road from R&B Road to Ramalingapuram Eath work in progress25.05.1301.06.13

2

30 Y2-247 RCS Road from R&B road to Utukuru Pallipalem Jungle clearence25.05.1312.04.13

2

31 Y2-425RHB

Ponnapudi-Utukur road to Pattapup[alem Jungle clearence12.04.1325.05.13

2

32 Y2-245 RCSRoad from Korutur to Pattapupalem in Nellore

DistrictEart work is progress

25.05.1317.04.13,29.04.13

3

33 Y2-255 RCSRoad from Kotha Kudur-Katepalli road to PathaPattapupalem in Nellore District

Eart work is progress 24.05.13 1

34 Y2-258 RCSRoad from R&B road Nelaturu to AnanthavaramCyclone shelter in Nellore District

Not started 24.05.20131

35 Y2-426 RHBRoad from R&B road to Venkata reddy palem inNellore District

Eart work is progress03.05.13,25.5.13

2

36 Y2-427 RHBPonnapudi R&B road to Anjanaya puram in NelloreDistrict

Eart work is progress 25.5.2013 1

37 Y2-428 RHBPonnapudi – Utukur road to Srigowri puram inNellore District

Eart work is progress 25.5.2013 1

Page 73 of 141

Page 75: Quarterly Progress Report to the end of June 2013.pdf

Sl.No

ProjectCode

catagory

Name of work visited Work stageDate of

visitTotalvisits

Name of the District: SPSR NELLORE

38 Y2-429 RHBRoad from Ponnapudi – Utukur R&B road toKothuru in Nellore District

Eart work is progress 25.5.2013 1

39 Y2-434 RHBRoad from Nellore – Mypadu R&B Road to WestPattapupalem in Nellore District

Eart work is progress 24.05.2013 1

Total 128

Page 74 of 141

Page 76: Quarterly Progress Report to the end of June 2013.pdf

Wor

ks

Vis

it m

ade

inth

is Q

uart

erm

onth

s

Wor

ks

Vis

it m

ade

inth

is Q

uart

erm

onth

s

Wor

ks

Vis

it m

ade

inth

is Q

uart

erm

onth

s

Wor

ks

Vis

it m

ade

inth

is Q

uart

erm

onth

s

Wor

ks

Vis

it m

ade

inth

is Q

uart

erm

onth

s

1 Srikakulam 24 0 11 0 13 0 1 0 0 0 0

2 Vizianagaram 1 0 5 0 0 0 0 0 0 0 0

3 Visakhapatnam 2 0 4 4 5 5 0 0 0 0 9

4 East Godavari 6 0 9 0 8 0 2 0 0 0 0

5 West Godavari 0 0 9 0 24 0 0 0 0 0 0

6 Krishna 0 0 22 3 23 0 0 0 0 0 3

7 Guntur 2 0 4 4 1 0 2 0 0 0 4

8 Prakasam 0 0 11 2 23 16 1 0 0 0 18

9 Nellore 0 0 20 18 19 4 0 0 0 0 22

35 0 95 31 116 25 6 0 0 0 56Total

NCRMP WORKS - ABSTRACT OF TPQA (SOCIAL & ENV) INSPECTIONS FOR QUARTER-1 ENDING WITH JUNE-2013

Sl.No.

District

PR R&B I & CADD

Tota

l Vis

itsMPCS RCS RHB BRIDGES SALINE EMBANKMENTS

Page 75 of 141

Page 77: Quarterly Progress Report to the end of June 2013.pdf

Sl.No

DistrictMPCS/ RHB/ RCS / R&B

/ I&CADD

ProjectCode

Work stageDate of

visit

Totalvisits till

dateObservations / Remarks

1 RCS Y-2-166 GSM Stage 25.05.2013 1 Electrical poles are in obstruction in the shoulders on both sides of the road.The line department told that they are pursuing this matter with the APCPDCL.

2 RCS Y--165 GSM Stage 25.05.2013 1

1. Electrical poles are close to the carriageway. The line department told thatthey are pursuing this matter with the APCPDCL.2. The area from Km 0/860 to Km 1/525 falls under Gilma reserve forest land.The line department officials are pursuing this matter with forest department

3 RCS Y-2-168 Sub grade stage 25.05.2013 1

1. Electrical poles and a water tap are in obstruction adjoining the road. Theline department told that they are pursuing this matter with the APCPDCL &RWS authorities.2. Necessary action shall be taken for the compound wall and steps of thehouse adjoining the carriageway of the road.

4 RCS Y-2-167 Sub grade stage 25.05.2013 1 Electrical poles and a transformer are in obstruction in the shoulder of theroad. The line department told that they are pursuing this matter with theAPCPDCL authorities

5 RHB Y-2-282 GSM Stage 25.05.2013 1

1. A stretch of 300 mtrs. of road (from Km 1/6 to Km 1/9) is not taken up dueto obstruction of two thatched houses, some trees and electrical poles. Theline department officers informed that they are pursuing the matter with landowners.2. A compound wall on the right side and farmers land in the left side are inobstruction in the shoulder of the road between Km 2/652 and Km 2/658.3. Helmets and shoes are provided to the workers.4. The project information board with details was kept at the site.During summer season, working hours shall be avoided during mid-noon. Theyshall be adjusted between 8.00 AM to 11.00 AM and 3.00 PM to 6.00 PM

6 RHB Y-2-281 Sub grade stage 25.05.2013 1Electrical poles are in obstruction in the shoulders on both sides of the road.The line department told that they are pursuing this matter with the APCPDCLauthorities.

7 RHB Y-2-283 Sub grade stage 26.05.2013 1 No issues

8 RHB Y-2-280 GSM Stage 26.05.2013 1 No issues

9 RHB Y2-284 GSM stage 26.05.2013 1 No issues

TPQA SITE INSPECTIONS FROM APRIL-13 TO JUNE-13

Name of work visited

Road from R&B Road to Annavararmcyclone shelter

Road from R&B Road toChinanagamayyapalem )

Road from R&B Road to Kothapatnam

Road from R&B Road to Revupolavaram

Road from R&B Road to Gajareddipalemvia Venkaypalem

NCR Issued

Road from Rajala R&B Road toRajaraidupalem

Road from Z.P.Road Palmanpeta toKorlayyapeta

Vish

akha

patn

am

Road from R&B Road to Vadapalem

Road from R&B Road to Rajavaram

Page 76 of 141

Page 78: Quarterly Progress Report to the end of June 2013.pdf

Sl.No

DistrictMPCS/ RHB/ RCS / R&B

/ I&CADD

ProjectCode

Work stageDate of

visit

Totalvisits till

dateObservations / RemarksName of work visited

10 RCS Y-2-244 GSB stage 06.06.2013 1

1. Necessary action shall be taken for shifting the seven electrical poles in theshoulder and an electrical pole in the carriageway at Km 2/6. Action shall betaken for the electrical cables crossing the road in the entire stretch of theroad.2. Safety measures shall be taken for the culvert under construction

11 RCS Y-2-255 Sub-grade stage 06.06.2013 1 Necessary action shall be taken for the Trees in obstruction in the shoulderson both sides of the road to avoid accidents.

12 RCS Y-2-256 GSB stage 06.06.2013 1

1. Necessary action shall be taken to for the three neem trees in thecarriageway on RHS of the road from Km. 1/3 to Km. ¼.2. Safety measures shall be provided to the workers.3. Action shall be taken to shift two water pipe lines, two water sumps and apressure release valve of RWS department in the carriageway on RHS fromKm. 1/1 to Km. ½.4. Guard posts shall be installed for the side drain on both sides of the road inentire stretch of the road

13 RCS Y-2-257 Sub-grade stage 06.06.2013 1 One Electrical pole on the LHS and two electrical poles on the RHS inobstruction in the shoulders of the road shall be shifted to avoid accidents atKm.0/3.

14 RCS Y-2-254 GSB stage 06.06.2013 1

1. Electrical poles & Transformers which are in obstruction in the shoulders onLHS of the road shall be shifted to avoid accidents. The Electrical poles inobstruction in the carriageway shall be shifted immediately at Km. 1/8 and atKm. 2/8.2. Necessary action shall be taken for the trees in obstruction in the shoulderson both the sides of the road.

15 RCS Y-2-428 GSB stage 07.06.2013 1 No issues till date

16 RCS Y-2-249 Sub-grade stage 07.06.2013 1 Temporary walls are in obstruction on either side of the Road at Km 1/6 to 1/8

17 RHB Y-2-432 GSB stage 06.06.2013 1

1. Two village platforms are in obstruction at Km 1/3 and at 1/8.2. Electic poles are all along the way on the eitherside of the Road. The fieldofficers informed that they are pursuing the matter with the APCPDCLauthorities.3. The contractor has to provide the Personal Protective Equipment to theworkers

18 RCS Y-2-250 GSB stage 06.06.2013 1

One eletric pole is located on the carriageway at Km 0/6 . On the LHS of theshoulder of the road a tranformer is in obstrcution at Km 0/100. The fieldofficers informed that they are pursuing the matter with the APCPDCLauthorities.

19 RCS Y-2-251 GSB stage 07.06.2013 1 No issues till dateRoad from R & B Road from

Ramalingapuram

Road from Ramudupalem on R&B Roadto Pallipalem

Road from Kotha Kudur-Katepalli road toPatha Pattapupalem

Nellore

Ponnapudi R&B Road to Busagadipalem

Road from Ponnapudi R & B road toPonnapudi -NCR Issued

Road from Ponnapudi R&B road toLakshmipuram

Road from Mahalakshmipuram to SagaraSangamam (via) Muthyalathopu

Pattapupalem

Road from R&B Road to Doruvukattaroad (via) Allmpadu, Deyyaladibba

Ponnapudi-Utukur road to srigowripuram

Road from C.S.Puram to Edurupalem

Page 77 of 141

Page 79: Quarterly Progress Report to the end of June 2013.pdf

Sl.No

DistrictMPCS/ RHB/ RCS / R&B

/ I&CADD

ProjectCode

Work stageDate of

visit

Totalvisits till

dateObservations / RemarksName of work visited

20 RHB Y-2-430 GSB stage 07.06.2013 1One Electric pole is obstruction on the LHS of the Road. The field officersinformed that they are pursuing the matter with the APCPDCL authorities

21 RCS Y-2-248 Sub-grade stage 07.06.2013 1Seven eletric poles are in obstruction on either side of the road between at Km0/600 to Km 0/900. The field officers informed that they are pursuing thematter with the APCPDCL authorities

22 RHB Y-2-431 Sub-grade stage 06.06.2013 1One Electric pole is obstruction on the LHS of the Road. The field officersinformed that they are pursuing the matter with the APCPDCL authorities.

23 RHB Y-2-427 GSB stage 06.06.2013 1Electric poles are obstruction on either side of the road. The field officersinformed that they are pursuing the matter with the APCPDCL authorities.

24 RHB Y-2-420 GSB stage 06.06.2013 1 Contractor has to provide temporary shelter for the workers. Women workerstaking shelter under water tanker

25 RHB Y-2-422 Sub-grade stage 07.06.2013 1Two Electric poles are obstruction on either side of the road. The field officersinformed that they are pursuing the matter with the APCPDCL authorities.

26 RHB Y-2-421 Sub-grade stage 07.06.2013 1 No issues till date

27 RCS Y-2-246 GSM stage 07.06.2013 1 Contractor has to provide personal protective equipment like shoe and Jacketsto the workers.

28 RHB Y-2-424 Sub-grade stage 07.06.2013 1 No issues till date

29 RCS Y-2-252 GSM stage 06.06.2013 1 No issues till date

30 RCS Y-2-253 GSB stage 06.06.2013 11. One electric pole at Km 2/6 is in obstruction on LHS of the shoulder of theroad.2. Two water taps are in obstruction on LHS of the road at Km 2/6 to 2/8.

31 RHB Y-2-426 Sub-grade stage 07.06.2013 1 No issues till date

32 RHB Y-2-436 GSB stage 06.06.2013 1At Km 6/0 to 6/4 a stretch of 400 mts reserve forest is passing atkothapatnam. The line department yet to take the permission from the forestdepartment.

33 RHB Y-2-437 GSB stage 06.06.2013 1 No issues

34 RCS Y-2-238 GSB stage 25.06.2013 1 The four electrical poles on the shoulder on the LHS of the road shall beshifted to avoid accidents from Km. 1/350 to Km. 2/040.

35 RCS Y-2-239 GSB stage 25.06.2013 1Necessary action shall be taken for the temple in obstruction in thecarriagewayat Km.0/675

36 RHB Y-2-387 Sub grade stage 25.06.2013 1

1. Road width is not adequate for the formation of the road. 2. Necessaryaction shall be taken for the temple in obstrcution in the carriageway in theRHS of the road. 3. Necessary action shall be taken for the openwell in theRHS of the road to avoid accidents.

Road from Z.P. road toSrirampattapupalem

Road from R&B road (via) Narravaripalrmto Srinivasa Satram

Road from R&B road Kothapatnam toYamadinnepalem (via) Srinivasasatram

Road from at km 22/5 of Yamadinnepalem road to Gunnampadia

Road from R&B road to Venkatreddypalem

Road from ZP road to Pallipalem ofChakicharala

Prak

asam

Road from R&B Road Lingavaram toNarravaripalem

Ponnapudi R &B road road toVenkatanarayanapuram

R&B Road to Pulavaripalem

Ponnapudi R &B rod road toAnjaneyapuram

Salt Road from Iskapalli to salt fields atKothakurrupattapupalem-NCR Issued

Road from R &B road to Zuvvagu

Road from R &B road to ZuvvaguLakshmipuram

Road from 230/6 Km of M.C road toPedapattupalem

Road from Pedapattapupalem toNandempuram

Road from Ponnapudi-Utukur R&B road toPrasanthigiri colony

Road from Ponnapudi R&B road toRamachendrapuram

Page 78 of 141

Page 80: Quarterly Progress Report to the end of June 2013.pdf

Sl.No

DistrictMPCS/ RHB/ RCS / R&B

/ I&CADD

ProjectCode

Work stageDate of

visit

Totalvisits till

dateObservations / RemarksName of work visited

37 RHB Y-2-388 Sub grade stage 26.06.2013 1

1) The electrical pole in the carriageway on the RHS of the road shall beshifted to avoid accidents at Km. 5.120.2)Necessary action shall be taken forthe electrical lines crossing the road from Km. 5.120 to Km. 5.800 .3) Guardstones with relflective stickers shall be provided on both the sides of thecauseway to avoid accidents at Km. 0/800

38 RHB Y-2-389 GSB stage 26.06.2013 1

1) Four electrical polesare near the carriageway and in obstruction in the RHSof the road from Km. 1.825 to Km.1.925. Suggestion was made to remove thetemporary compound walls and other structures in the LHS of the road.2)Necessary action shall be taken for the school bathroom wall in obstruction inthe RHS in the shoulder of the road at Km.1.800.

39 RHB Y-2-397 GSB stage 07.06.2013 1

1. Electric lines are crossing at Km 0.100 to Km 0.200. It is dangerous if anyheavy loaded vehicle passes through these lines. The field officers informedthat they are pursuing the matter with the APCPDCL authorities.2. Trees are obstruction at Km 0.200 to at Km 0.250. The field officersinformed that they are perusing the matter with the concerned authorities.3. Two electric poles are obstruction at Km 0.820 to at Km 0.850. The fieldofficers informed that they are pursuing the matter with the APCPDCLauthorities.Electric lines are crossing at Km 0.100 to Km 0.200. It is dangerous if anyheavy loaded vehicle passes through these lines. The field officers informedthat they are pursuing the matter with the APCPDCL authorities.2. Trees are obstruction at Km 0.200 to at Km 0.250. The field officersinformed that they are perusing the matter with the concerned authorities.3. Two electric poles are obstruction at Km 0.820 to at Km 0.850. The fieldofficers informed that they are pursuing the matter with the APCPDCLauthorities.

40 RHB Y-2-398 Sub grade stage 07.06.2013 1 Ten eletric poles are in obstruction in the shoulders of the road.

41 RHB Y-2-399 Sub grade stage 07.06.2013 1Two Electric poles are obstruction on either side of the road. The field officersinformed that they are pursuing the matter with the APCPDCL authorities.

42 RHB Y-2-400 GSB stage 25.06.2013 1 No issues

43 RHB Y-2-401 GSB stage 07.06.2013 1Three electric poles and compound wall are in obstruction on the shoulder on

the LHS and eletric pole on the RHS of the road in Km.0/1.

44 RHB Y-2-402 GSB stage 25.06.2013 1Reflective stickers shall be pasted to the trees on both sides of the road in theshoulders to avoid accidents.

45 RHB Y-2-403 GSB stage 26.06.2013 1Caution boards shall be provided to the " S" curves in the entire stretch of theroad.

Road from Madnur ZP road toBapujiyanadi colony

Salt Road from Madnur Z.P Road toNamburi Yanadi Colony

Salt Road from Madnur ZP road toThotagunta yanadi colonyRoad from Tangutur to Tallapalem (via)Velagapudi (Km 4/5 to 7/465)

Prak

asam

Salt Road from Madnur Z.P Road toPedapattapupalem

Salt Road from Madnur Z.P Road toSwarnandrapattapupalem

Road from Chinnaganjam Rly gate toBapaiahnagar

Road from R & B road to Kothaplem

Road from KEM R&B road tochinappattapupalem

Page 79 of 141

Page 81: Quarterly Progress Report to the end of June 2013.pdf

Sl.No

DistrictMPCS/ RHB/ RCS / R&B

/ I&CADD

ProjectCode

Work stageDate of

visit

Totalvisits till

dateObservations / RemarksName of work visited

46 RHB Y-2-409 Sub grade stage 07.06.2013 1Electric lines are crossing at Km 0.100 to Km 0.200. It is dangerous if anyheavy loaded vehicle passes through these lines. The field officers informedthat they are persuing the matter with the APCPDCL authorities.

47 RHB Y-2-410 GSB stage 07.06.2013 1 No issues

48 RHB Y-2-411 Sub grade stage 07.06.2013 1Six trees are obstruction on LHS of the shoulder at Km 0.175 to Km 0.200. Thefield officers informed that they are persuing the matter with the concerneddepartment.

49 RHB Y-2-412 GSB stage 07.06.2013 1 No issues

50 RHB Y-2-413 Sub grade stage 07.06.2013 1

Two Electric poles are obstruction on RHS of the road. The field officersinformed that they are pursuing the matter with the APCPDCL authorities. 2)Guard stones with reflective stickers shall be provided to the Road Dam on theLHS to avoid accidents from Km.3/6 to Km.3/8. 3) Guard stones with relflectivestickers shall be provided on both the sides of the culvert to avoid accidents atKm. 3/150.

51 RHB Y-2-414 GSB stage 25.06.2013 1

1) Seven electrical poles in the shoulder on the RHS of the road in obstructionshall be shifted to avoid accidents from Km. 3/400 to Km. 3/950.2) Guardstones with reflective stickers shall be provided to the Road Dam on the LHS toavoid accidents from Km.3/6 to Km.3/8. 3) Guard stones with relflectivestickers shall be provided on both the sides of the culvert to avoid accidents atKm. 3/150.4) A temple is in obstruction on the RHS of the Road and a House isin obstruction on the LHS of the road. The road width is not adequate at Km.2/2. 5) All the 11 culverts under construction shall be properly barricaded toavoid accidents in the entire stretch of the road.

Prak

asam

Road from KEM R&B road toVajjireddypalem-Pattapupalem

KEM R&B road to Pinnivaripalem

Salt road Madnur ZP road toChinnapattapupalem

KEM Road to E.Pallipalem

Road from KEM R&B road toChenchupapayapalem

Road From M.C road to West ST colony ofVeerapalli

Page 80 of 141

Page 82: Quarterly Progress Report to the end of June 2013.pdf

WorksVisit made in thisQuarter months

1 Srikakulam 24 0

2 Vizianagaram 1 0

3 Visakhapatnam 2 5

4 East Godavari 6 3

5 West Godavari 0 0

6 Krishna 0 0

7 Guntur 2 0

8 Prakasam 0 0

9 Nellore 0 0

35 8Total

NCRMP WORKS - ABSTRACT OF TPQA (Electrical ENGG) INSPECTIONS FOR QUARTER 1ENDING WITH JUNE-2013

Sl.No.

District

PR

MPCS

Page 81 of 141

Page 83: Quarterly Progress Report to the end of June 2013.pdf

Sl.No

DistrictProjectCode

Name of work visited Work stage Date of visit Remarks if any

1 Y2-043 Construction of MPCS at patimeda Finishing stage 15/05/2013

2 Y2-044 Construction of MPCS at Mullaparra Finishing stage 15/05/2013

3 Y2-045 Construction of MPCS at Bangaranpeta Finishing stage 15/05/2013

4 Y2-046 Construction of MPCS at Gajapathi Nagaram Finishing stage 15/05/2013

5 Y2-047 Construction of MPCS at Ratnayampeta Finishing stage 15/05/2013

6 Y2-060 Construction of MPCS at Avulamanda Finishing stage 22/05/2013

7 Y2-061 Construction of MPCS at Laxmanudipeta Finishing stage 22/05/2013

8 Y2-062 Construction of MPCS at Pedaraghavulupeta progress 22/05/2013

TPQA (Electrical ENGG) SITE INSPECTIONS FROM APRIL-13 TO JUNE-13

Visakhapatnam

East Godavari

Page 82 of 141

Page 84: Quarterly Progress Report to the end of June 2013.pdf

Annexure - E

Surprise Visits by TPQA

Page 83 of 141

Page 85: Quarterly Progress Report to the end of June 2013.pdf

Sl. No. District Number of surprise inspections

1 Srikakulam 14

2 Vizianagaram 3

3 Visakhapatnam 16

4 East Godavari 3

5 West Godavari 6

6 Krishna 15

7 Guntur 9

8 Prakasam 19

9 Nellore 22

107

Abstract Details of surprise inspections carried out by TPQA Consultant upto June2013

Total

Page 84 of 141

Page 86: Quarterly Progress Report to the end of June 2013.pdf

District : SRIKAKULAM

Sl.No Date Habitation Name of Work Package No. Visited by Remarks

1 30.04.13 BridgeConstruction ofHLB across Uppigedda at KM 7/6 of SrikakulamMuncipal Limits to Pukkalapeta via killipalem

NCRMP/B-W/AP/Br/R&B/01/Uppugedda/002

SE

2 14.05.13 MPCS Construction of Cyclone shelter at RunkuNCRMP/B-W/AP/MPCS/PRED/01/Santhabommalli/005

SE

3 21.05.13 RCS Road from R&B road SJ puramNCRMP/B-W/AP/RCS/PRED/01/V.Kotturu/001

DPM

4 21.05.13 RHB KC road to Rajarampuram via AmplamNCRMP/B-W/AP/RHB/PRED/01/Polaki/008

DPM

5 21.05.13 RHB KC road to Amplam via Urjam, nandigamNCRMP/B-W/AP/RHB/PRED/01/Polaki/008

DPM

6 21.05.13 RHBDPN road to DL puram junction via koduru maghatapaduGuppidipeta

NCRMP/B-W/AP/RHB/PRED/01/Polaki/007

DPM

7 21.05.13 RHB Guppidipeta road to ChinnakovaripetaNCRMP/B-W/AP/RHB/PRED/01/Polaki/007

SE

8 7.06.13 MPCS Construction of Cyclone shelter at bandaruvanipetaNCRMP/B-W/AP/MPCS/PRED/01/Gara/015

SE

9 13.06.13 RCS Road from R&B road SJ puramNCRMP/B-W/AP/RCS/PRED/01/V.Kotturu/001

SE

10 15.06.13 BridgeConstruction ofHLB across Uppigedda at KM 7/6 of SrikakulamMuncipal Limits to Pukkalapeta via killipalem

NCRMP/B-W/AP/Br/R&B/01/Uppugedda/002

SE

11 19.06.13 RCS Road from Bonthalakoduru to patadibbalapalemNCRMP/B-W/AP/RCS/PRED/01/Etcherla/012

SE

12 29.06.13 RCS Road from R&B road to pothayyapetaNCRMP/B-W/AP/RCS/PRED/01/Etcherla/012

DPM

13 29.06.13 MPCS Construction of Cyclone shelter at jaganadhapuramNCRMP/B-W/AP/MPCS/PRED/01/ranastalam/016

DPM

14 8.07.13 MPCS Construction of Cyclone shelter at CalingapatnamNCRMP/B-W/AP/MPCS/PRED/01/Gara/015

SE, Socialexpert

SURPRISE VISITS UP TO END OF JUNE 2013

Page 85 of 141

Page 87: Quarterly Progress Report to the end of June 2013.pdf

District : VIZIANAGARAM

Sl.No Date Habitation Name of Work Package No. Visited by Remarks

1 20.06.13 MPCS Construction of cyclone shelter at BuddugurayyapetaNCRMP/B-W/AP/MPCS/PRED/02/Pusapatirega/003

SE

2 22.06.13 MPCS Construction of cyclone shelter at BuddugurayyapetaNCRMP/B-W/AP/MPCS/PRED/02/Pusapatirega/003

DPM

3 27.06.13 MPCS Construction of cyclone shelter at BuddugurayyapetaNCRMP/B-W/AP/MPCS/PRED/02/Pusapatirega/003

DPM

SURPRISE VISITS UP TO END OF JUNE 2013

Page 86 of 141

Page 88: Quarterly Progress Report to the end of June 2013.pdf

District : VISAKHAPATNAM

Sl.No Date Habitation Name of Work Package No. Visited by Remarks

1 18.04.13 RCS Road from R&B Road to Revupolavaram Cyclone shelterNCRMP/B-W/AP/RCS/PRED/03/S.Rayavaram/006

DPM

2 29.04.13 RCS Road from R&B road to Chinanagamayyapalem cyclone shelterNCRMP/B-W/AP/RCS/PRED/03/Bheemili/005

DPM

3 29.4.13 RCS Road from R&B road to Annavaram cyclone shelterNCRMP/B-W/AP/RCS/PRED/03/Bheemili/005

DPM

4 24.4.13 RHB Road from R&B road to GajareddipalemNCRMP/B-W/AP/RHB/PRED/03/Payakaraopeta/005

SE

5 18.04.13 RHB Road from R&B road to VadapalemNCRMP/B-W/AP/RHB/PRED/03/Atchutapuram/009

SE

6 18.5.13 RCS Road from R&B road to Chinanagamayyapalem cyclone shelterNCRMP/B-W/AP/RCS/PRED/03/Bheemili/005

DPM

7 18.5.13 RCS Road from R&B road to Annavaram cyclone shelterNCRMP/B-W/AP/RCS/PRED/03/Bheemili/005

DPM

8 22.5.13 RCS Road from R&B road to Annavaram cyclone shelterNCRMP/B-W/AP/RCS/PRED/03/Bheemili/005

SE

9 13.05.13 RCS Road from R&B road to KothapatnamNCRMP/B-W/AP/RCS/PRED/03/Atchutapuram/007

DPM

10 16.05.13 RHB Road from R&B road to GajareddipalemNCRMP/B-W/AP/RHB/PRED/03/Payakaraopeta/005

DPM

11 13.5.13 RHB Road from R&B road to VadapalemNCRMP/B-W/AP/RHB/PRED/03/Atchutapuram/009

DPM

12 07.06.13 RCS Road from R&B road to KothapatnamNCRMP/B-W/AP/RCS/PRED/03/Atchutapuram/007

PM

13 07.06.13 RHB Road from R&B road to GajareddipalemNCRMP/B-W/AP/RHB/PRED/03/Payakaraopeta/005

PM

14 07.06.13 MPCSConstruction of Cyclone shelter at Venkayyapalem in RambilliMandal

NCRMP/B-W/AP/MPCS/PRED/03/Rambilli/004

PM

15 17.06.13 RHB Road from R&B road to GajareddipalemNCRMP/B-W/AP/RHB/PRED/03/Payakaraopeta/005

DPM

16 22.06.13 RHB Road from ZP Road Palamanpeta to KorlayyapetaNCRMP/B-W/AP/RHB/PRED/03/Payakaraopeta/008

SE

SURPRISE VISITS UP TO END OF JUNE 2013

Page 87 of 141

Page 89: Quarterly Progress Report to the end of June 2013.pdf

District : EAST GODAVARI

Sl.No Date Habitation Name of Work Package No. Visited by Remarks

1 10.05.2013 RCS Road from R & B Road to Katrenipadu Lanka CSNCRMP/B-W/AP/RCS/PRED/04/Razole & Sakhinetipalli/010

SE

2 02.06.2013 CSCyclone Shelter at Lakshmanudipeta of Thondangi Mandal,E.G.Dt.

NCRMP/B-W/ AP/MPCS/PRED/04/Thondangi/001

SE

3 19.06.2013 RCS Road from R & B Road to Katrenipadu Lanka CSNCRMP/B-W/AP/RCS/PRED/04/Razole & Sakhinetipalli/010

DPM

SURPRISE VISITS UP TO END OF JUNE 2013

Page 88 of 141

Page 90: Quarterly Progress Report to the end of June 2013.pdf

District : WEST GODAVARI

Sl.No Date Habitation Name of Work Package No. Visited by Remarks

1 06.05.2013 RHBRoad from PR road to Vemuladeevi (E) colony (Via)Ralla cheruvu of Vemuladeevi (E)

NCRMP/B-W/AP/RHB/ PRED/05/Narsapur/014

DPM

2 14.05.2013 RHBRoad from R & B Road toPulaparthivaripalem

NCRMP/B-W/AP/RHB/PRED/05/Narsapur/013

SE

3 18.05.2013 RHBRoad from Perupalem beach R & B Road to Challavarimerakavia Mucherlavarimeraka

NCRMP/B-W/AP/RHB/PRED/05/ Mogaltur/008

PM

4 27.05.2013 RHBRoad from SP R&B road toPasaladeevi

NCRMP/B-W/AP/ RHB/PRED/05/ Narsapur /010

SE

5 01.06.2013 RCSRoad from R&B road to Ayodya lanka Marrimula cycloneshelter.

NCRMP/B-W/AP/RCS/PRED/05/Achanta/002

SE

6 05.06.2013 RCSConstruction of approach road to cyclone shelter in Losari ofBhimavaram Mandal.

NCRMP/B-W/AP/RCS/PRED/05/Bhimavaram/004

SE

7 06.06.2013 RCS Road from Narsapur Perupalem R&B road to MandavarithotaNCRMP/B-W/AP/RCS/PRED/05/ Mogaltur /005

SE

8 07.06.2013 RHB SP R&B road to Pedathota of TurputalluNCRMP/B-W/AP/RHB/PRED/05/Narsapur/012

SE

9 09.06.2013 RCS Road from Narsapur Perupalem R&B road to MandavarithotaNCRMP/B-W/AP/RCS/PRED/05/ Mogaltur /005

SE

10 13.06.2013 RHB R&B road to PedaedigapalemNCRMP/B-W/AP/RHB/PRED/05/Narsapur/013

SE

11 14.06.2013 RHB R&B road to GuttulavarimerakaNCRMP/B-W/AP/RHB/PRED/05/Narsapur/013

SE

12 10.06.2013 RHBRoad from Narsapur Perupalem R & B road to Nellipallipalemvia Ambedkar colony Harijanapeta

NCRMP/B-W/AP/RHB/ PRED/05/Mogaltur /009

SE

13 22.06.2013 RCSRoad from R&B road toKothakayalathippa cyclone shelter

NCRMP/B-W/AP/RCS/PRED/05/ Mogaltur /005

SE

14 23.06.2013 RHBRoad from Perupalem Mollaparru R & B road viaSattinenivarimeraka to K.D.Pallavapalem

NCRMP/B-W/AP/RHB/PRED/05/ Mogaltur/008

SE

15 24.06.2013 RHB Road from Perupalem R&B road to DindlaNCRMP/B-W/AP/RHB/ PRED/05/Mogaltur /009

SE

SURPRISE VISITS UP TO END OF JUNE 2013

Page 89 of 141

Page 91: Quarterly Progress Report to the end of June 2013.pdf

District : KRISHNA

Sl.No Date Habitation Name of Work Package No. Visited by Remarks

1 17.05.2013 RHB Road from R&B Road to NarsimhapuramNCRMP/B-W/AP/RHB/PRED/06/Koduru/004

SE

2 27.05.2013 RCS Road from R&B road to Cyclone Shelter @ UllipalemNCRMP/B-W/AP/RCS/PRED/06/koduru/001

SE

3 27.05.2013 RCS Road from R&B road to Cyclone Shelter @ MandapakalaNCRMP/B-W/AP/RCS/PRED/06/koduru/002

SE

4 06.06.2013 RCSRoad from kammavanicheruvu R&B road to Venkatadurgambapuram in Bandar Mandal

NCRMP/B-W/AP/RCS/PRED/06/Machilipatnam/008

DPM

5 26.06.2013 RCS Road from R&B road to Cyclone Shelter @ Ramakrisna puramNCRMP/B-W/AP/RCS/PRED/06/koduru/001

DPM

6 26.06.2013 RCS Road from R&B road to Cyclone Shelter @ UllipalemNCRMP/B-W/AP/RCS/PRED/06/koduru/001

DPM

SURPRISE VISITS UP TO END OF JUNE 2013

Page 90 of 141

Page 92: Quarterly Progress Report to the end of June 2013.pdf

District : GUNTUR

Sl.No Date Habitation Name of Work Package No. Visited by Remarks

1 06.05.2013 BRIDGEConstruction of HLB across Pedapalli No-2 Drain @km 14/6 ofChandolu bridge to Nizampatnam road

NCRMP/B-W/AP/Br/R&B/07/Repalle/020

DPM

2 06.05.2013 MPCS Construction of MPCS at Harbour of Nizampatnam villageNCRMP/B-W/AP/MPCS/PRED/ 07/Nizampatnam/001

DPM

3 06.05.2013 MPCSConstruction of CS in Near MRO office of Nizam Patnam (TypeB)

DPM

4 06.05.2013 MPCSConstruction of CS in Near MRO office of Nizam Patnam (TypeB

DPM

5 29.05.2013 RCS Road from R&B Road Allur to Yadavapalem.NCRMP/B-W/AP/RCS/PRED/07/PVPalem/001

DPM

6 26.06.2013 RCS Road from R&B Krosurivariplam road to MarkavaripalemNCRMP/B-W/AP/RCS/PRED/07/NIZAMPATNAM/005

DPM

7 26.06.2013 RCS Road from R & B road to PattapupalemNCRMP/B-W/AP/RCS/PRED/07/Bapatla/006

DPM

8 26.06.2013 RHBRe construction of HLB @km 2/4 of Bapatla -Pandurangapuram road across peralidrain in Guntur Dt.

NCRMP/B-W/AP/Br/R&B/07/Bapatla/011

DPM

9 26.06.2013 RHB Road from R&B road to GattuvaripalemNCRMP/B-W/AP/RHB/PRED/07/Nagaram/007

DPM

SURPRISE VISITS UP TO END OF JUNE 2013

NCRMP/B-W/AP/MPCS/ PRED/ 07/Nizampatham/004

Page 91 of 141

Page 93: Quarterly Progress Report to the end of June 2013.pdf

District : PRAKASAM

Sl.No Date Habitation Name of Work Package No. Visited by Remarks

1 23.05.2013 BridgeReconstruction of High level bridge at Km. 11/10 of Ongole -Kothapatnam road in Prakasam District

NCRMP/B-W/AP/Br/R&B/08/Ongole/023

PM

2 20.06.2013 RHB Road From M.C road to West ST colony of VeerapalliNCRMP/B-W/AP/RHB/PRED/08/Ulavapadu/016

DPM

3 20.06.2013 RCS Road from Z.P. road to SrirampattapupalemNCRMP/B-W/AP/RCS/PRED/08/Ulavapadu/009

DPM

4 20.06.2013 RCS Road from ZP road to Pallipalem of ChakicharalaNCRMP/B-W/AP/RCS/PRED/08/Ulavapadu/009

DPM

5 20.06.2013 RHB Salt Road from Madnur ZP road to Namburi yanadi colonyNCRMP/B-W/AP/RHB/PRED/08/Kothapatnam/020

DPM

6 20.06.2013 RHB Salt Road from Madnur ZP road to ChinnapattapupalemNCRMP/B-W/AP/RHB /PRED/08/Kothapatnam/019

DPM

7 20.06.2013 RHB Salt Road from Madnur ZP road to Thotagunta yanadi colonyNCRMP/B-W/AP/RHB/PRED/08/Kothapatnam/020

DPM

8 20.06.2013 RHBRoad from Tangutur to Tallapalem (via) Velagapudi (Km 4/5to 7/465)

NCRMP/B-W/AP/RHB/PRED/08/Tangutur/021

DPM

9 02.07.2013 RHB Road from KEM R & B road to ChinapattapupalemNCRMP/B-W/AP/RHB/PRED/08/Kothapatnam/020

SE

10 02.07.2013 RHB Salt Road from Madnur ZP road to PedapattapupalemNCRMP/B-W/AP/RHB/PRED/08/Kothapatnam/020

SE

11 02.07.2013 RHB Road from Madnur ZP road to SwarnandhrapattapupalemNCRMP/B-W/AP/RHB/PRED/08/Kothapatnam/020

SE

12 02.07.2013 RHB Road from Madnur ZP road to Bapujiyanadi colonyNCRMP/B-W/AP/RHB/PRED/08/Kothapatnam/020

SE

13 02.07.2013 RHB Salt Road from Madnur ZP road to Namburi yanadi colonyNCRMP/B-W/AP/RHB/PRED/08/Kothapatnam/020

SE

14 02.07.2013 RHB Salt Road from Madnur ZP road to Thotagunta yanadi colonyNCRMP/B-W/AP/RHB/PRED/08/Kothapatnam/020

SE

15 02.07.2013 RHB Road from KEM R&B Road to Vajjireddypalem -PattapupalemNCRMP/B-W/AP/RHB /PRED/08/Kothapatnam/019

SE

SURPRISE VISITS UP TO END OF JUNE 2013

Page 92 of 141

Page 94: Quarterly Progress Report to the end of June 2013.pdf

District : PRAKASAM

Sl.No Date Habitation Name of Work Package No. Visited by Remarks

SURPRISE VISITS UP TO END OF JUNE 2013

16 02.07.2013 RHB KEM R & B road to PinnivaripalemNCRMP/B-W/AP/RHB /PRED/08/Kothapatnam/019

SE

17 02.07.2013 RHB Salt Road from Madnur ZP road to ChinnapattapupalemNCRMP/B-W/AP/RHB /PRED/08/Kothapatnam/019

SE

18 02.07.2013 RHB KEM R & B road to E. PallipalemNCRMP/B-W/AP/RHB /PRED/08/Kothapatnam/019

SE

19 02.07.2013 RHB Road from KEM R & B road to ChenchupapayapalemNCRMP/B-W/AP/RHB /PRED/08/Kothapatnam/019

SE

Page 93 of 141

Page 95: Quarterly Progress Report to the end of June 2013.pdf

District : SPSR NELLORE

Sl.No Date Habitation Name of Work Package No. Visited by Remarks

1 29.04.2013 RCSRoad from Ramudupalem on R&B road to Pallipalem inNellore District

NCRMP/BW/AP/RCS/PRED/09/I.Pet/018

SE

2 29.04.2013 RCS Road from Korutur to Pattapupalem in Nellore DistrictNCRMP/BW/AP/RCS/PRED/09/I.Pet/018

SE

3 24.05.2013 RHBSalt Road from Iskapalli to Salt fields at Kotha Kurrupattapupalem in Nellore District

NCRMP/BW/AP/RHB/PRED/09/Allur/019

PM

4 24.05.2013 RHB Road from R&B Road to Zuvvagu in Nellore DistrictNCRMP/BW/AP/RHB/PRED/09/Allur/019

PM

5 25.05.2013 RCSRoad from R&B Road to Doruvukatta road (via) Allmpadu,Deyyaladibba in Nellore District

NCRMP/BW/AP/RCS/PRED/09/Kota/016

PM

6 25.05.2013 RCSRoad from Narravaripalem to Yamadinnepalem in NelloreDistrict

NCRMP/BW/AP/RCS/PRED/09/Chillakur/015

PM

7 10.5.13 RHBRoad from Pedapattapupalem to Nandempuram in NelloreDistrict

NCRMP/B-W/AP/RHB/PRED/09/Kavali/024

SE

8 10.5.13 RCSRoad from 230/6 Km of MC road to Pedapattapupalem inNellore District

NCRMP/B-W/AP/RCS/PRED/09/Kavali/020

SE

9 03.05.2013 RHB Road from R&B road to Venkata reddy palem in Nellore DistrictNCRMP/BW/AP/RHB/PRED/09/Vidaval uru/025

DPM

10 03.05.2013 RHBPonnapudi R & B road to Venkata narayana puram in NelloreDistrict

NCRMP/BW/AP/RHB/PRED/09/Vidaval uru/025

DPM

11 03.05.2013 RHBRoad from Ponnapudi R & B road to Ponnapudi in NelloreDistrict

NCRMP/BW/AP/RHB/PRED/09/Vidaval uru/025

DPM

12 03.05.2013 RHBRoad from Pedapattapupalem to Nandempuram in NelloreDistrict

NCRMP/B-W/AP/RHB/PRED/09/Kavali/024

DPM

13 03.05.2013 RHBRoad from 230/6 Km of MC road to Pedapattapupalem inNellore District

NCRMP/B-W/AP/RCS/PRED/09/Kavali/020

DPM

14 4.06.2013 RHBRoad from R&B road Kothapatnam to Yamadinnepalem (via)Srinivasasatram in Nellore District

NCRMP/B-W/AP/RHB/PRED/09/Kota/022

SE

15 6.6.2013 RCSRoad from Mahlakshmi puram to Sagara Sangamam (via)Muthyalathopu Pattapupalem in Nellore District

NCRMP/B-W/AP/RCS/ PRED/09/T.P.Gudur & Muthukur/019

SE

SURPRISE VISITS UP TO END OF JUNE 2013

Page 94 of 141

Page 96: Quarterly Progress Report to the end of June 2013.pdf

District : SPSR NELLORE

Sl.No Date Habitation Name of Work Package No. Visited by Remarks

SURPRISE VISITS UP TO END OF JUNE 2013

16 21.06.2013 RHBRoad from Mypadu R&B Road to Kollimittapalem in NelloreDistrict

NCRMP/BW/AP/RHB/PRED/09/I.Peta/027

SE

17 21.06.2013 RCSRoad from Ramudupalem on R&B road to Pallipalem inNellore District

NCRMP/BW/AP/RCS/PRED/09/I.Pet/018

DPM

18 21.06.2013 RHBRoad from R&B road Kothapatnam to Yamadinnepalem (via)Srinivasasatram in Nellore District

NCRMP/B-W/AP/RHB/PRED/09/Kota/022

DPM

19 21.06.2013 RHBRoad from R&B Road Lingavaram to Narravaripalem inNellore District

NCRMP/BW/AP/RCS/PRED/09/Chillakur/014

DPM

20 21.06.2013 RHBRoad from R&B Road to Doruvukatta road (via) Allmpadu,Deyyaladibba in Nellore District

NCRMP/BW/AP/RCS/PRED/09/Kota/016

SE

21 29.06.2013 RHBSalt Road from Iskapalli to Salt fields at Kotha Kurrupattapupalem in Nellore District

NCRMP/BW/AP/RHB/PRED/09/Allur/019

SE

22 29.06.2013 RHB Road from R&B Road to Zuvvagu in Nellore DistrictNCRMP/BW/AP/RHB/PRED/09/Allur/019

SE

Page 95 of 141

Page 97: Quarterly Progress Report to the end of June 2013.pdf

Annexure - F

Audit Reports submitted byTPQA Consultant

Page 96 of 141

Page 98: Quarterly Progress Report to the end of June 2013.pdf

Package Number Name of Work District

NCRMP/BW/AP/BR/R&B/01/Uppugedda/002

Construction of Minor Bridge across Uppugedda at KM7/6 of Srikakulam Municipal limits to Pukkalapeta viaKillipalem in Srikakulam District.

Srikakulam

NCRMP/BW/AP/BR/R&B/01/Uppugedda/002

Construction of Minor Bridge across Uppugedda at KM7/6 of Srikakulam Municipal limits to Pukkalapeta viaKillipalem in Srikakulam District.

Srikakulam

NCRMP/BW/AP/BR/R&B/01/Uppugedda/002

Construction of High Level Bridge across Uppugedda atKM 7/6 of Srikakulam Municipal limits to Pukkalapetavia Killipalem

Srikakulam

NCRMP/B-W/AP/MPCS/PRED/01/Santhabommali/005

Construction of cyclone shelter at Kollipadu inSanthabommali Mandal.

Srikakulam

NCRMP/B-W/AP/MPCS/PRED/01/Santhabommali/005

Construction of cyclone shelter at Runku inSanthabommali Mandal.

Srikakulam

NCRMP/B-W/AP/MPCS/PRED/01/Santhabommali/005

Construction of cyclone shelter at Runku inSanthabommali Mandal.

Srikakulam

NCRMP/BW/AP/RHB/PRED/01/Polaki/005

Road from R&B Road Edulavalasa - Killam Road toJonnam via Talasamudram in Polaki Mandal

Srikakulam

NCRMP/BW/AP/BR/R&B/01/Uppugedda/002

Construction of High Level Bridge across Uppugedda atKM 7/6 of Srikakulam Municipal limits to Pukkalapetavia Killipalem

Srikakulam

NCRMP/B-W/AP/MPCS/PRED/01/Gara/015

Construction of CS at Bandaruvanipeta in Gara Mandal Srikakulam

NCRMP/B-W/AP/MPCS/PRED/01/Gara/015

Construction of CS at Calingapatnam in Gara Mandal Srikakulam

NCRMP/B-W/AP/MPCS/PRED/01/V.kotturu/013

Construction of CS at Metturu in V. Kothuru Mandal Srikakulam

NCRMP/B-W/AP/RCS/PRED/01/Mandasa/010

Road from R&B Road to Akkuvaram in Mandasa Mandal Srikakulam

NCRMP/B-W/AP/MPCS/PRED/01/V.kotturu/004

Construction of CS at Chinavanka in V. Kothuru Mandal Srikakulam

NCRMP/B-W/AP/MPCS/PRED/01/V.kotturu/004

Construction of CS at Bypalli in V. Kothuru Mandal Srikakulam

NCRMP/B-W/AP/RCS/PRED/01/V.Kottoru/001

Road from R&B Road to SJ Puram in V.Kotturu Mandal Srikakulam

NCRMP/B-W/AP/MPCS/PRED/02/Pusapatirega/003

Construction of CS at Boddugurayyapeta Village inPusapatirega Mandal

Vizianagaram

NCRMP/B-W/AP/MPCS/PRED/03/Rambilli/004

Construction of Cyclone Shelter at Venkayypalem inRambilli Mandal

Visakhapatnam

NCRMP/B-W/AP/RCS/PRED/03/Bheemili/005

Road from R&B Road to Annavaram Cyclone Shelter Visakhapatnam

NCRMP/B-W/AP/RCS/PRED/03/Bheemili/005

Road from R&B Road to Chinanagamayyapalem CycloneShelter in Bheemili Mandal

Visakhapatnam

NCRMP/B-W/AP/RCS/PRED/03/Rambilli/007

Road from R&B Road to Kothapatnam Cyclone shelterin Rambilli Mandal

Visakhapatnam

NCRMP/B-W/AP/RCS/PRED/03/S.Rayavaram/006

Road from R&B Road to Revupolavaram Cyclone Shelterin S.Rayavaram Mandal

Visakhapatnam

QCRs submitted during the Quarter-1 ending month of June-2013

Page 97 of 141

Page 99: Quarterly Progress Report to the end of June 2013.pdf

Package Number Name of Work District

NCRMP/B-W/AP/RHB/PRED/03/Atchuthapuram/009

Road from R&B Road to Vadapalem in AtchuthapuramMandal

Visakhapatnam

NCRMP/B-W/AP/RHB/PRED/03/Payakaraopeta/005

Road from R&B Road to Gajareddipalem inPayakaraopeta Mandal

Visakhapatnam

NCRMP/B-W/AP/RHB/PRED/03/Payakaraopeta/005

Road from R&B Road to Rajavaram Visakhapatnam

NCRMP/B-W/AP/RHB/PRED/03/Payakaraopeta/005

Road from R&B Road to Gajareddipalem inPayakaraopeta Mandal

Visakhapatnam

NCRMP/B-W/AP/RCS/PRED/03/S.Rayavaram/006

Road from R&B road to Revupolavaram CS Visakhapatnam

NCRMP/B-W/AP/RHB/PRED/03/Atchuthapuram/009

Road from R&B Road to Vadapalem in AtchuthapuramMandal

Visakhapatnam

NCRMP/B-W/AP/RCS/PRED/03/Rambilli/007

Road from R&B road to Kothapatnam CS in RambilliMandal

Visakhapatnam

NCRMP/B-W/AP/RHB/PRED/03/Payakaraopeta/005

Road from R&B Road to Rajavaram. Visakhapatnam

NCRMP/B-W/AP/RCS/PRED/03/Bheemili/005

Road from R&B Road to Annavaram CS in BheemiliMandal

Visakhapatnam

NCRMP/B-W/AP/RHB/PRED/03/Payakaraopeta/008

Road from ZP Road Palmanpeta to Korlayyapeta inPayakaraopeta Mandal

Visakhapatnam

NCRMP/B-W/AP/MPCS/PRED/03/Rambilli/004

Construction of CS at Venkayypalem in Rambilli Mandal Visakhapatnam

NCRMP/B-W/AP/Br/R&B/04/Pampa Yeru-1/015

Construction of Bridge at Km 43/10 of Vakalapudi-Edatam Road across Pampa Yeru

East Godavari

NCRMP/B-W/AP/MPCS/PRED/04/Thondangi/001

Construction of Cyclone Shelter at Lakshamanudipeta inThondangi Mandal

East Godavari

NCRMP/B-W/AP/MPCS/PRED/04/Thondangi/001

Construction of Cyclone Shelter at Avulamanda inThondangi Mandal

East Godavari

NCRMP/B-W/AP/RCS/PRED/04/Razolu & Sakhinetipalli/010

Road from R&B Road to Katrenipadulanka CS inSakhinetipally

East Godavari

NCRMP/B-W/AP/RHB/PRED/05/Narsapur/014

Road from PR Road to Vemuladeevi (E) Colony (via)Rallacheruvu of Vemuladeevi (E)

West Godavari

NCRMP/B-W/AP/RHB/PRED/05/Narsapur/014

Road from PR Road to Vemuladeevi(E) colony (via)Rallacheruvu of Vemuladeevi

West Godavari

NCRMP/B-W/AP/RHB/PRED/05/Koduru/004

Road from R&B Road to Narasimhapuram in KoduruMandal

Krishna

NCRMP/B-W/AP/RCS/PRED/05/Koduru/001

Road from R&B Road to Ramakrishnapuram CS inKoduru Mandal

Krishna

NCRMP/B-W/AP/RCS/PRED/05/Koduru/001

Road from R&B Road to Ullipalem CS in Koduru Mandal Krishna

NCRMP/B-W/AP/RCS/PRED/07/PV Palem/001

Road from R&B Road Alluru to Yadavapalem Guntur

NCRMP/B-W/AP/Br/R&B/08/Kanaparthy/012

Construction of High level Bridge at Km. 16/10 ofNaguluppalapadu - Kanaparthy Road

Prakasam

NCRMP/B-W/AP/RCS/PRED/08/Ulavapadu/009

Road from ZP Road to Srirampattapupalem inUlavapadu Mandal

Prakasam

Page 98 of 141

Page 100: Quarterly Progress Report to the end of June 2013.pdf

Package Number Name of Work District

NCRMP/B-W/AP/RHB/PRED/08/Kothapatnam/019

KEM R&B Road to Chenchupapayapalem inKothapatnam Mandal

Prakasam

NCRMP/B-W/AP/RHB/PRED/08/Kothapatnam/019

KEM R&B Road to Pinnivaripalem in KothapatnamMandal

Prakasam

NCRMP/B-W/AP/RHB/PRED/08/Kothapatnam/019

Road from KEM R&B Road to VajjireddypalemPattapupalem in Kothapatnam Mandal

Prakasam

NCRMP/B-W/AP/RHB/PRED/08/Kothapatnam/020

Road from Madnur ZP Road toSwarnandhrapattapupalem

Prakasam

NCRMP/B-W/AP/RHB/PRED/08/Kothapatnam/020

Road from KEM R&B Road to Chinapattapupalem inKothapatnam Mandal

Prakasam

NCRMP/B-W/AP/RHB/PRED/08/Kothapatnam/020

Salt Road from Madnur ZP Road to Pedapattapupalemin Kothapatnam Mandal

Prakasam

NCRMP/B-W/AP/RHB/PRED/08/Kothapatnam/020

Road from Madnur ZP Road toSwarnandhrapattapupalem

Prakasam

NCRMP/B-W/AP/RHB/PRED/08/Ulavapadu/016

Road from M.C Road to West ST Colony of Veerapalli ofUlavapadu Mandal

Prakasam

NCRMP/B-W/AP/RHB/PRED/08/Ulavapadu/016

Road From MC Road to West ST colony of Veerapalli Prakasam

NCRMP/B-W/AP/RHB/PRED/08/Kothapatnam/019

KEM R & B road to E. Pallipalem. Prakasam

NCRMP/B-W/AP/RHB/PRED/08/Kothapatnam/019

KEM R & B road to E. Pallipalem. Prakasam

NCRMP/B-W/AP/RHB/PRED/08/Kothapatnam/020

Salt Road from Madnur ZP Road to Namburi Yanadicolony in Kothapatnam Mandal

Prakasam

NCRMP/B-W/AP/RCS/PRED/08/Ulavapadu/009

Road from ZP road to Pallipalem of Chakicharala inUlavapadu Mandal

Prakasam

NCRMP/B-W/AP/RHB/PRED/08/Kothapatnam/019

Salt Road from Madnur ZP Road to Chinnapattapupalemin Kothapatnam Mandal

Prakasam

NCRMP/B-W/AP/RHB/PRED/08/Kothapatnam/019

KEM R&B Road to Chenchupapayapalem inKothapatnam Mandal

Prakasam

NCRMP/B-W/AP/RHB/PRED/08/Kothapatnam/019

KEM R&B Road to Pinnivaripalem in KothapatnamMandal

Prakasam

NCRMP/B-W/AP/RHB/PRED/08/Kothapatnam/019

Salt Road from Madnur ZP Road to Chinnapattapupalemin Kothapatnam Mandal

Prakasam

NCRMP/B-W/AP/RHB/PRED/08/Kothapatnam/020

Road from Madnur ZP Road to Bapujiyanadi colony inKothapatnam Mandal

Prakasam

NCRMP/B-W/AP/RCS/PRED/08/Ulavapadu/009

Road from ZP Road to Srirampattapupalem inUlavapadu Mandal

Prakasam

NCRMP/B-W/AP/RHB/PRED/08/Chinaganjam/012

Road from Chinnaganjam Railway Gate to Bapaiahnagarin Chinaganjam Mandal

Prakasam

NCRMP/B-W/AP/RCS/PRED/09/TADA/009

Road from @ km 56/8 CK Road to Periyavettu KuppamCyclone Shelter

SPSR Nellore

NCRMP/B-W/AP/RCS/PRED/09/Vidavalur/021

Road from Ponnapudi R&B Road to Ramachandrapuramin Vidavalur Mandal

SPSR Nellore

NCRMP/B-W/AP/RHB/PRED/09/Allur/019

Road from R&B Road to Zuvvagu in Allur Mandal SPSR Nellore

Page 99 of 141

Page 101: Quarterly Progress Report to the end of June 2013.pdf

Package Number Name of Work District

NCRMP/B-W/AP/RHB/PRED/09/Allur/019

Salt Road from Iskapalli to Salt fields at KothaKurrupattapupalem of Allur Mandal

SPSR Nellore

NCRMP/B-W/AP/RHB/PRED/09/Kavali/024

Road from Pedapattapupalem to Nandempuram ofKavali Mandal

SPSR Nellore

NCRMP/B-W/AP/RHB/PRED/09/V.Chalam/021

Road from Thirumalammapalem R&B Road toGajulapalli Koneru of Venkatachalam Mandal

SPSR Nellore

NCRMP/BW/AP/RHB/PRED/09/Vidavalur/026

Road from Ponnapudi R&B Road to Ponnapudi inVidavalur Mandal

SPSR Nellore

NCRMP/B-W/AP/RCS/PRED/09/Kota/016

Road from R&B Road to Doruvuketta Road viaAllampadu, Deyyaladibba of Kota mandal

SPSR Nellore

NCRMP/B-W/AP/RCS/PRED/09/Tada/024

Road from @ Km 65/4 of CK Road to Tada Kuppam CSof Tada Mandal

SPSR Nellore

NCRMP/BW/AP/RHB/PRED/09/Vidavalur/026

Road from Ponnapudi R&B Road to Ponnapudi inVidavalur Mandal

SPSR Nellore

NCRMP/BW/AP/RHB/PRED/09/Vidavalur/026

Road from Ponnapudi R&B Road toVenkatanarayanapuram in Vidavalur Mandal

SPSR Nellore

NCRMP/BW/AP/RHB/PRED/09/Vidavalur/026

Road from Ponnapudi- Utukur R&B Road toPrasanthagiri Colony in Vidavalur Mandal

SPSR Nellore

NCRMP/B-W/AP/RHB/PRED/09/I.Peta/027

Road from Mypadu R&B road to Kollimittapalem inI.Peta Mandal

SPSR Nellore

NCRMP/B-W/AP/RCS/PRED/09/I.Peta/018

Road from Ramudupalem on R&B Road to Pallipalem inI.Peta Mandal

SPSR Nellore

Page 100 of 141

Page 102: Quarterly Progress Report to the end of June 2013.pdf

Package Number Name of Work District

NCRMP/B-W/AP/RD/R&B/01/Nowpada/006

Improvements to Nowpada - Venkatapuram Road from km0/0 to 15/0

Srikakulam

NCRMP/B-W/AP/BR/R&B/01/Bendigadda/004

Construction of HLB across Bendigadda at Km 4/10 of Pundito Parlakimidi Road.

Srikakulam

NCRMP/B-W/AP/RCS/PRED/07/Nizampatnam/003

Road from R&B Road to Adavala H/O Bavajipalem inNizampatnam Mandal

Guntur

NCRMP/B-W/AP/RCS/PRED/07/Nizampatnam/003

Road from R&B Road to Atlavaripalem in NizampatnamMandal

Guntur

NCRMP/B-W/AP/RCS/PRED/07/Nagaram/002

Road from R&B Road to Mahammad Alipalem in NagaramMandal

Guntur

NCRMP/B-W/AP/RHB/PRED/07/Nagaram/002

Road from R&B Road to Katurivaripalem in Nagaram Mandal Guntur

NCRMP/B-W/AP/RCS/PRED/07/Nizampatnam/003

Road from R&B Road to Gurunadhanagar in NizampatnamMandal

Guntur

NCRMP/B-W/AP/Br/R&B/08/Kanaparthy/012

Construction of High level Bridge at Km. 16/10 ofNaguluppalapadu - Kanaparthy Road in Prakasam District

Prakasam

Final QARs submitted during the Quarter-1 ending month of June-2013

Page 101 of 141

Page 103: Quarterly Progress Report to the end of June 2013.pdf

Package Number Name of Work District

NCRMP/B-W/AP/RCS/PRED/03/Bheemili/005

Road from R&B Road to Chinanagamayyapalem CycloneShelter

Vishakhapatnam

NCRMP/B-W/AP/RCS/PRED/03/Bheemili/005

Road from R&B Road to Annavaram Cyclone Shelter Vishakhapatnam

NCRMP/B-W/AP/RCS/PRED/03/S.Rayavaraam /006

Road from R&B Road to Revupolavaram Cyclone Shelter Vishakhapatnam

NCRMP/B-W/AP/RCS/PRED/03/Rambilli/007

Road fromR&B Road to Kothapatnam Cyclone Shelter Vishakhapatnam

NCRMP/B-W/AP/RHB/PRED/03/Payakaraopeta/005

Road from R&B Road to Rajavaram Vishakhapatnam

NCRMP/B-W/AP/RHB/PRED/03/Payakaraopeta/005

Road from Rajala R&B Road to Rajaraidupalem Vishakhapatnam

NCRMP/B-W/AP/RHB/PRED/03/Payakaraopeta/005

Road from R&B Road to Gajareddipalem via Venkaypalem Vishakhapatnam

NCRMP/B-W/AP/RHB/PRED/03/Payakaraopeta/008

Road from Z.P Road Palmanpeta to Korlayyapeta Vishakhapatnam

NCRMP/B-W/AP/RHB/PRED/03/Atchutapuram/009

Road from R&B Road to Vadapalem Vishakhapatnam

NCRMP/B-W/AP/RCS/PRED/08/Ulavapadu/009

Road from Z.P. road to Srirampattapupalem Prakasam

NCRMP/B-W/AP/RCS/PRED/08/Ulavapadu/ 009

Road from ZP road to Pallipalem of Chakicharala Prakasam

NCRMP/B-W/AP/RHB/PRED/08/Chinaganjam/012

R&B Road to Pulavaripalem Prakasam

NCRMP/B-W/AP/RHB/PRED/08/Chinaganjam/012

Road from Chinnaganjam Rly gate to Bapaiahnagar Prakasam

NCRMP/B-W/AP/RHB/PRED/08/Chinaganjam/012

Road from R & B road to Kothaplem Prakasam

NCRMP/B-W/AP/RHB/PRED/08/Kothapatnam/020

Road from KEM R & B road to Chinapattapupalem Prakasam

NCRMP/B-W/AP/RHB/PRED/08/Kothapatnam/020

Salt Road from Madnur ZP road to Pedapattapupalem Prakasam

NCRMP/B-W/AP/RHB/PRED/08/Kothapatnam/020

Road from Madnur ZP road to Swarnandhrapattapupalem Prakasam

NCRMP/B-W/AP/RHB/PRED/08/Kothapatnam/020

Road from Madnur ZP road to Bapujiyanadi colony Prakasam

NCRMP/B-W/AP/RHB/PRED/08/Kothapatnam/020

Salt Road from Madnur ZP road to Namburi yanadi colony Prakasam

NCRMP/B-W/AP/RHB/PRED/08/Kothapatnam/020

Salt Road from Madnur ZP road to Thotagunta yanadicolony

Prakasam

NCRMP/B-W/AP/RHB/PRED/08/Tangutur/021

Road from Tangutur to Tallapalem (via) Velagapudi (Km4/5 to 7/465)

Prakasam

NCRMP/B-W/AP/RHB/PRED/08/Kothapatnam/019

Road from KEM R&B Road to Vajjireddypalem -Pattapupalem

Prakasam

NCRMP/B-W/AP/RHB/PRED/08/Kothapatnam/019

KEM R & B road to Pinnivaripalem Prakasam

Env & Social QCRs submitted during the Quarter-1 ending month of June-2013

Page 102 of 141

Page 104: Quarterly Progress Report to the end of June 2013.pdf

Package Number Name of Work District

NCRMP/B-W/AP/RHB/PRED/08/Kothapatnam/019

Salt Road from Madnur ZP road to Chinnapattapupalem Prakasam

NCRMP/B-W/AP/RHB/PRED/08/Kothapatnam/019

KEM R & B road to E. Pallipalem Prakasam

NCRMP/B-W/AP/RHB/PRED/08/Kothapatnam/019

Road from KEM R & B road to Chenchupapayapalem Prakasam

NCRMP/B-W/AP/RHB/PRED/08/Ulavapadu/016

Road From M.C road to West ST colony of Veerapalli Prakasam

NCRMP/B-W/AP/RCS/PRED/09/I.Pet/018

Road from Ramudupalem on R&B road to pallipalem Nellore

NCRMP/B-W/AP/RCS/PRED/09/Kavali/020

Road from 230/6 Km of MC road to Pedapattupupalem Nellore

NCRMP/B-W/AP/RCS/PRED/09/Vidavaluru/021

Road from Ponnapudi R&B road to Ramachendrapuram Nellore

NCRMP/B-W/AP/RCS/PRED/09/Vidavaluru/021

Ponnapudi R&B road to Busagadipalem Nellore

NCRMP/B-W/AP/RCS/PRED/09/Vidavaluru/021

Road from Ponnapudi R&B road to Lakshmipuram Nellore

NCRMP/B-W/AP/RCS/PRED/09/Vidavaluru/021

R&B road from Ramalingapuram Nellore

NCRMP/B-W/AP/RCS/PRED/09/Chilkuru/014

Road from R&B road Lingavaram to Narravaripalem Nellore

NCRMP/B-W/AP/RCS/PRED/09/Chilkuru/015

Road from R&B road Narravaripalem to Srinivasasatram Nellore

NCRMP/B-W/AP/RCS/PRED/09/Kota/016

Road from R&B road to Doruvukatta road to (Via)Allampadu, Deyyaladibba

Nellore

NCRMP/B-W/AP/RCS/PRED/09/TP.Gudur&Muthukur/019

Road from Kothakudur-Katepalli road toPathapattapupalem

Nellore

NCRMP/B-W/AP/RCS/PRED/09/TP.Gudur&Muthukur/019

Road from C.S.Puram to Edurupalem Nellore

NCRMP/B-W/AP/RCS/PRED/09/TP.Gudur&Muthukur/019

Road from Mahalakshmipuram to Sagarasangamam viaMuthyalathopu pattupalem

Nellore

NCRMP/B-W/AP/RHB/PRED/09/Alluru /019

Salt Road from Iskapalli to Salt fields at KothaKurrupattapupalem

Nellore

NCRMP/B-W/AP/RHB/PRED/09/Alluru /019

Road from R&B road to Zuvvagu Lakshmipuram Nellore

NCRMP/B-W/AP/RHB/PRED/09/Alluru /019

Road from R&B Road to Zuvvagu Nellore

NCRMP/B-W/AP/RHB/PRED/09/Kavali/024

Road from Pedapattapupalem to Nandempuram Nellore

NCRMP/B-W/AP/RHB/PRED/09/Vidavaluru/025

Road from R&B road to Venkatareddypalem Nellore

NCRMP/B-W/AP/RHB/PRED/09/Vidavaluru/025

Ponnapudi R&B road to Anjanayapuram Nellore

NCRMP/B-W/AP/RHB/PRED/09/Vidavaluru/026

Ponnapudi - Utukur road to Srigowripuram Nellore

NCRMP/B-W/AP/RHB/PRED/09/Vidavaluru/026

Road from Ponnapudi - Utukur R&B road to Prasanthi giricolony

Nellore

Page 103 of 141

Page 105: Quarterly Progress Report to the end of June 2013.pdf

Package Number Name of Work District

NCRMP/B-W/AP/RHB/PRED/09/Vidavaluru/026

Ponnapudi R & B road to Venkatanarayanapuram Nellore

NCRMP/B-W/AP/RHB/PRED/09/Vidavaluru/026

Road from Ponnapudi R & B road to Ponnapudi Nellore

NCRMP/B-W/AP/RHB/PRED/09/Kota/022

Road from R&B road Kothapatnam to Yamadinnepalem(via) Srinivasasatram

Nellore

NCRMP/B-W/AP/RHB/PRED/09/Kota/023

Road from at km 22/5 of Yamadinne palem road toGunnampadia

Nellore

Package Number Name of Work District

NCRMP/B-W/AP/MPCS/ PRED/03/Rambilli/004

Construction of Cyclone Shelter at Venkayyapalam inRambilli Mandal

Visakhapatnam

Electrical QCRs submitted during the Quarter-1 ending month of June-2013

Page 104 of 141

Page 106: Quarterly Progress Report to the end of June 2013.pdf

Annexure - G

Photo Documentation

Page 105 of 141

Page 107: Quarterly Progress Report to the end of June 2013.pdf

Page 106 of 141

Page 108: Quarterly Progress Report to the end of June 2013.pdf

Page 107 of 141

Page 109: Quarterly Progress Report to the end of June 2013.pdf

Page 108 of 141

Page 110: Quarterly Progress Report to the end of June 2013.pdf

Page 109 of 141

Page 111: Quarterly Progress Report to the end of June 2013.pdf

Page 110 of 141

Page 112: Quarterly Progress Report to the end of June 2013.pdf

Page 111 of 141

Page 113: Quarterly Progress Report to the end of June 2013.pdf

Page 112 of 141

Page 114: Quarterly Progress Report to the end of June 2013.pdf

Page 113 of 141

Page 115: Quarterly Progress Report to the end of June 2013.pdf

Page 114 of 141

Page 116: Quarterly Progress Report to the end of June 2013.pdf

Page 115 of 141

Page 117: Quarterly Progress Report to the end of June 2013.pdf

Vemuladeevi (E) colony (Via) Ralla cheruvu of Vemuladeevi (E). TPQA-NCRMP inspection on 04.05.2013 in West Godavari District. Checking

WMM 1st layer measurements

Vemuladeevi (E) colony (Via) Ralla cheruvu of Vemuladeevi (E). TPQA-NCRMP inspection on 04.05.2013 in West Godavari District. Checking

WMM 1st layer thickness

Vemuladeevi (E) colony (Via) Ralla cheruvu of Vemuladeevi (E). TPQA-NCRMP inspection on 04.05.2013 in West Godavari District. Sieve

analysis

Vemuladeevi (E) colony (Via) Ralla cheruvu of Vemuladeevi (E). TPQA-NCRMP inspection on 04.05.2013 in West Godavari District. WMM 1st Layer

Page 116 of 141

Page 118: Quarterly Progress Report to the end of June 2013.pdf

Page 117 of 141

Page 119: Quarterly Progress Report to the end of June 2013.pdf

Page 118 of 141

Page 120: Quarterly Progress Report to the end of June 2013.pdf

Page 119 of 141

Page 121: Quarterly Progress Report to the end of June 2013.pdf

Page 120 of 141

Page 122: Quarterly Progress Report to the end of June 2013.pdf

Page 121 of 141

Page 123: Quarterly Progress Report to the end of June 2013.pdf

Page 122 of 141

Page 124: Quarterly Progress Report to the end of June 2013.pdf

Page 123 of 141

Page 125: Quarterly Progress Report to the end of June 2013.pdf

Page 124 of 141

Page 126: Quarterly Progress Report to the end of June 2013.pdf

Page 125 of 141

Page 127: Quarterly Progress Report to the end of June 2013.pdf

Page 126 of 141

Page 128: Quarterly Progress Report to the end of June 2013.pdf

Page 127 of 141

Page 129: Quarterly Progress Report to the end of June 2013.pdf

Page 128 of 141

Page 130: Quarterly Progress Report to the end of June 2013.pdf

Page 129 of 141

Page 131: Quarterly Progress Report to the end of June 2013.pdf

Page 130 of 141

Page 132: Quarterly Progress Report to the end of June 2013.pdf

Page 131 of 141

Page 133: Quarterly Progress Report to the end of June 2013.pdf

Page 132 of 141

Page 134: Quarterly Progress Report to the end of June 2013.pdf

Page 133 of 141

Page 135: Quarterly Progress Report to the end of June 2013.pdf

Page 134 of 141

Page 136: Quarterly Progress Report to the end of June 2013.pdf

Page 135 of 141

Page 137: Quarterly Progress Report to the end of June 2013.pdf

Page 136 of 141

Page 138: Quarterly Progress Report to the end of June 2013.pdf

Page 137 of 141

Page 139: Quarterly Progress Report to the end of June 2013.pdf

Page 138 of 141

Page 140: Quarterly Progress Report to the end of June 2013.pdf

Page 139 of 141

Page 141: Quarterly Progress Report to the end of June 2013.pdf

Page 140 of 141

Page 142: Quarterly Progress Report to the end of June 2013.pdf

Page 141 of 141


Recommended