Quarterly Transportation Report
2nd Quarter 2012April 17, 2012
Thomas Blaser – DirectorDepartment of Transportation
|2|Quarterly Transportation Report | Tuesday, April 17, 2012
Transportation Headlines
Location & Design Public HearingRoute 28 (Linton Hall Road to Fitzwater Drive)
Wednesday, April 25, 20127:00 pm to 9:00 pmPatriot High School
10504 Kettle Run RoadNokesville, VA 20181
|3|Quarterly Transportation Report | Tuesday, April 17, 2012
University Boulevard PPTA(Prince William Parkway to Sudley Manor Drive)
Accomplishments Hornbaker Road design has been completed and
approved by VDOT University Boulevard design has been approvedIssues R-O-W negotiations with adjacent developmentsTimeline Construction activities began in January 2012 on
Hornbaker Road with majority of activities starting in the Spring of 2012
Construction to be complete by December 26, 2013
|4|Quarterly Transportation Report | Tuesday, April 17, 2012
University Boulevard PPTA(Prince William Parkway to Sudley Manor Drive)
|5|Quarterly Transportation Report | Tuesday, April 17, 2012
Route 1 – Joplin to Bradys Hill
Accomplishments Project activities and billing are 89%
complete Median work with stamped concrete
and grass is 60% complete Paving is ongoing and is 70% complete
Issues Timing of Inn Street connection
Timeline Construction on-schedule for
completion June 2012
|6|Quarterly Transportation Report | Tuesday, April 17, 2012
Route 28 (Linton Hall Road to Fitzwater Drive)
Accomplishments Design has initiated with survey work underway Citizen Information Meeting held on October 11, 2011 Project Value Engineering has been completed Environmental Assessment Document approvedIssues Construction phasing to expedite completion Impacts to septic fields and R-O-W acquisitionTimeline Public Hearing scheduled for April 25, 2012 Anticipated Final Construction Plans – January 2013 Construction Advertisement for Phase I (Linton Hall Road to Realigned
Vint Hill Road) anticipated for Spring 2013 Phase II to follow contingent on funding availability
|7|Quarterly Transportation Report | Tuesday, April 17, 2012
Route 28 (Linton Hall Road to Fitzwater Drive)
|8|Quarterly Transportation Report | Tuesday, April 17, 2012
Fuller Rd./Fuller Heights Rd. (Quantico Marine Corps Base Entrance)
Accomplishments Coordination with Marine Corps Base Quantico (MCBQ) regarding design
concerns has been concluded Environmental Permitting is completed R-O-W and easement requested from MCBQ on 3/30/12 R-O-W plans submitted to VDOT for authorizationIssues Maintenance of traffic during construction Access Management waivers Flood Plain and CLOMR/LOMR RequirementsTimeline R-O-W authorization from VDOT anticipated by Summer 2012
|9|Quarterly Transportation Report | Tuesday, April 17, 2012
Fuller Rd./Fuller Heights Rd. (Quantico Marine Corps Base Entrance)
|10|Quarterly Transportation Report | Tuesday, April 17, 2012
Telegraph Road Commuter Lot
Accomplishments Final grading activities ongoing for Phase I (Commuter Lot) Temporary SWM activity is complete Demolition of pavement is complete Storm sewer pipes are 90% completeIssues Coordinate with adjacent developers Utility Relocations Opening of Phase ITimeline Lot construction (Phase I) scheduled for completion – August 31, 2012 Final R-O-W plan approval for road improvements – February 2012 Construction advertisement for road improvements (Phase II) – May 2012 Construction for road improvements anticipated to be complete –
Summer 2013
|11|Quarterly Transportation Report | Tuesday, April 17, 2012
Telegraph Road Commuter Lot
|12|Quarterly Transportation Report | Tuesday, April 17, 2012
Old Bridge Road Pedestrian Improvements (Mohican Road to Dillingham Square)
AccomplishmentsDesign of the project incorporating the VDOT
Safety Project is in progressProject is in coordination with VDOT Safety
ProjectIssuesNoneTimelineConstruction is anticipated to start Fall 2012
|13|Quarterly Transportation Report | Tuesday, April 17, 2012
Prince William Parkway (Old Bridge Road to Minnieville Road)
Accomplishments Preliminary Design/Build Plans completed by AMT Project to be financed through Bond funding and use
of State Revenue Sharing funds RFP advertised – February 2012Issues R-O-W Impacts Utility relocationTimeline Bid opening on May 23, 2012 Award Design/Build contract Summer of 2012
|14|Quarterly Transportation Report | Tuesday, April 17, 2012
Rollins Ford Road
Accomplishments Design for roadway extension has been submitted to VDOT
for approvalIssues Project construction will include two phases and two Notice
To Proceeds (NTPs) Improvements at Vint Hill Road to meet current standards Coordination with Park ProjectTimeline Advertisement for construction for roadway extension
anticipated for Spring 2012
|15|Quarterly Transportation Report | Tuesday, April 17, 2012
Route 1 – Dale Blvd. to Featherstone Rd.
Accomplishments Three unsolicited design-build proposals received for the
project Selection committee selected the firm of Lane Construction to
move forward with project negotiation
Issues Project Funding Waterline Construction
Timeline Award of design-build contract – Spring 2012
|16|Quarterly Transportation Report | Tuesday, April 17, 2012
Minnieville Road – Spriggs Rd. to Rte. 234
Accomplishments Three unsolicited design-build proposals received for the
project
Issues Selection committee rejected all PPTA proposals
Timeline Issuance of RFP for project design – Summer 2012
|17|Quarterly Transportation Report | Tuesday, April 17, 2012
Mountain Road Improvements (Revenue Sharing/TRIP)(Bear Hollow Trail to Jackson Hollow Road)
Accomplishments Notice to Proceed has been issued to NOVEC Project has been advertised for construction R-O-W and easements have been acquired Environmental Permit issued Utility Relocation is in progressIssues None Maintenance of traffic during construction – Road closure during
Summer monthsTimeline Utility relocation completion anticipated by end of Spring 2012 with
construction to follow Bid opening on April 13, 2012
|18|Quarterly Transportation Report | Tuesday, April 17, 2012
Mountain Road Improvements (Revenue Sharing/TRIP)(Bear Hollow Trail to Jackson Hollow Road)
|19|Quarterly Transportation Report | Tuesday, April 17, 2012
Logmill Road Improvements
Accomplishments Preliminary plan design is in progress Project Day meeting with VDOT, JMT and PWC DOT held in
November 2011 Meeting held with property owners concerning grade at Parnell
Court Profile to proceed with balanced cut and fill for optimum
constructionIssues Possible temporary road closure and management of traffic during
constructionTimeline Intermediate Plan submission scheduled for Summer 2012 Advertisement for construction – Spring 2013 Construction completion anticipated for Fall 2013
|20|Quarterly Transportation Report | Tuesday, April 17, 2012
Fuller Heights Rd. Sidewalk –Bethlehem Church Rd. to Potomac Crest Dr. (TRIP)
Accomplishments R-O-W acquisition is completed Construction by County forces is in progressIssues Coordination during construction of sewer line Drainage design affecting adjacent properties Project BudgetTimeline Construction completion is anticipated in Summer of
2012
|21|Quarterly Transportation Report | Tuesday, April 17, 2012
Hoadly Road Trail – Spriggs Road to Dale Boulevard (TRIP)Accomplishments Plans submitted to VDOT Comments received from VDOT and Development
Services are being addressedIssues R-O-W and easement constraints Possible design waiverTimeline Plans expected to be re-submitted to VDOT in April
2012
|22|Quarterly Transportation Report | Tuesday, April 17, 2012
Gideon Drive Sidewalk – Dale Blvd. to Opitz Blvd. (TRIP)
Accomplishments Notice to Proceed with preliminary design has been issued to
RDA Task Order to RDA has been modified to accommodate use of
Federal CMAQ funding on project for constructionIssues R-O-W and easement constraints Utility RelocationsTimeline Preliminary design scheduled for submission to VDOT – May
2012
|23|Quarterly Transportation Report | Tuesday, April 17, 2012
Glenkirk Road Sidewalk
Accomplishments County request to administer project approved by VDOT County/Sate Agreement has been received and funding
budgeted and appropriated Federal design task order has been issued to Dewberry
Issues Expedited construction schedule
Timeline Advertise for construction in Fall 2012
|24|Quarterly Transportation Report | Tuesday, April 17, 2012
Mine Road @ Van Buren Road Intersection Improvements
Accomplishments County request to administer project approved by VDOT County/Sate Agreement has been received and funding
budgeted and appropriated Federal design task order has been issued to Dewberry
Issues None
Timeline Advertise for construction in Fall 2012
|25|Quarterly Transportation Report | Tuesday, April 17, 2012
Panther Pride Drive Sidewalk
Accomplishments County request to administer project approved by VDOT County/Sate Agreement has been received and funding
budgeted and appropriated Federal design task order has been issued to Dewberry
Issues None
Timeline Advertise for construction in Fall 2012