+ All Categories
Home > Documents > Questions & Issues Raised at October & November Public Hearings

Questions & Issues Raised at October & November Public Hearings

Date post: 23-Jan-2016
Category:
Upload: lazar
View: 30 times
Download: 0 times
Share this document with a friend
Description:
Questions & Issues Raised at October & November Public Hearings. Brushy Creek Regional Utility Authority Board Meeting December 10, 2007. OVERVIEW – Public Hearing Questions & Issues. Overview of Public Hearings Questions & Issues Raised Related To: - PowerPoint PPT Presentation
Popular Tags:
26
Questions & Issues Raised at October & November Public Hearings Brushy Creek Regional Utility Authority Board Meeting December 10, 2007
Transcript
Page 1: Questions & Issues Raised  at  October & November Public Hearings

Questions & Issues Raised at

October & November Public Hearings

Brushy Creek Regional Utility Authority

Board Meeting

December 10, 2007

Page 2: Questions & Issues Raised  at  October & November Public Hearings

OVERVIEW – Public Hearing Questions & Issues

I. Overview of Public Hearings

II. Questions & Issues Raised Related To:

A. PHASE 1 Raw Water Delivery System (Trails End)

B. PHASE 2A Raw Water Delivery System (Volente)

C. Impacts to Lake Travis

D. Water Conservation

Page 3: Questions & Issues Raised  at  October & November Public Hearings

PHASE 1 RAW WATER DELIVERY SYSTEM

Phase 1 - Overview:

Floating intake – 30 mgd

29,000 l.f. of 78-inch Raw Water Pipeline

Design is approximately 45% complete

Begin construction in summer 2008 and finish spring 2010.

Page 4: Questions & Issues Raised  at  October & November Public Hearings

PHASE 1 RAW WATER DELIVERY SYSTEM

1. Why did you choose Trails End for the route?

Four alternative routes evaluated in detail

Over 15 evaluation criteria considered for each route

Alternative B (Trails End) was selected because of a fatal flaw environmental impact on Alternative A route

Sandy Creek route was not evaluated because: Increased cost Environmental Permitting Permanent easement requirements

Page 5: Questions & Issues Raised  at  October & November Public Hearings

Not Considered

Not Consi

dered

Page 6: Questions & Issues Raised  at  October & November Public Hearings
Page 7: Questions & Issues Raised  at  October & November Public Hearings

PHASE 1 RAW WATER DELIVERY SYSTEM

2. What is in this project for the Trails End residents?

New road with widened shoulders

Potential drainage improvements

Tunneling under Trails End HOA Park

Mitigation of impacts to best extent possible

Page 8: Questions & Issues Raised  at  October & November Public Hearings

PHASE 1 RAW WATER DELIVERY SYSTEM

3. What are the potential impacts along Trails End Road and how will they be mitigated?

Potential

Impact Mitigation

Construction Noise Limited work hours

Mufflers

Traffic Maintain two-way traffic for most of length

Driveways/ fences/ mailboxes

Keep in service and restore back to original condition following construction.

Groundwater Trench dams

Dust Water spray system on trencher and periodic watering

Trees Tree replacement inside ROW. Compensation for trees removed in Temp Const Easement

Page 9: Questions & Issues Raised  at  October & November Public Hearings

PHASE 1 RAW WATER DELIVERY SYSTEM

Two-Lane Traffic

One-Lane Traffic

Page 10: Questions & Issues Raised  at  October & November Public Hearings
Page 11: Questions & Issues Raised  at  October & November Public Hearings

PHASE 1 RAW WATER DELIVERY SYSTEM

3. What are the potential impacts along Trails End Road and how will they be mitigated?

Potential

Impact Mitigation

Construction Noise Limited work hours

Mufflers

Traffic Maintain two-way traffic for most of length

Driveways/ fences/ mailboxes

Keep in service and restore back to original condition following construction.

Groundwater Trench dams

Dust Water spray system on trencher and periodic watering

Trees Tree replacement inside ROW. Compensation for trees removed in Temp Const Easement

Page 12: Questions & Issues Raised  at  October & November Public Hearings

PHASE 1 RAW WATER DELIVERY SYSTEM

4. What are the critical design issues associated with this line?

Pipe Sizing – per generally accepted design standards - max 300 psi.

Coordination with LCRA on existing pipeline along Trails End Rd.

Sandy Creek Park Crossing License Agreement with Travis County Public Hearing required by Travis County Easements from LCRA

Easements 40 temporary easements 9 permanent easements

Page 13: Questions & Issues Raised  at  October & November Public Hearings

PHASE 2A RAW WATER DELIVERY SYSTEM

Phase 2A - Overview:

Deep Water Intake – 142 mgd

15,000 to 20,000 l.f. of 84-inch Raw Water Pipeline

Currently performing study to pick best intake site - to be complete in Spring 2008

Complete construction between 2012 and 2016

Page 14: Questions & Issues Raised  at  October & November Public Hearings

PHASE 2A RAW WATER DELIVERY SYSTEM

5. Why do you need a deep intake in the Volente area?

To provide water during a severe drought

Volente area provides access to deep water in reasonable proximity to the existing plants and the proposed BCRUA regional plant

Alternative locations are either too remote or do not provide deep-water access

Page 15: Questions & Issues Raised  at  October & November Public Hearings

PHASE 2A RAW WATER DELIVERY SYSTEM

Page 16: Questions & Issues Raised  at  October & November Public Hearings

PHASE 2A RAW WATER DELIVERY SYSTEM

6. What sites are you considering for a deep intake and how will the final decision be made?

Seven sites in Volente area and four types intakes are being investigated (28 total combinations)

Study scheduled for completion in April, 2008

Site recommendation to BCRUA will be based on cost, social impacts, and environmental impacts

Study will be conducted with public input

Page 17: Questions & Issues Raised  at  October & November Public Hearings

PHASE 2A RAW WATER DELIVERY SYSTEM

7. Why are most of the sites in a residential neighborhood?

Areas around Lake Travis are predominately residential properties, particularly in the Volente study area

Only two commercial sites exist in the Volente area, and both are included in the study

Page 18: Questions & Issues Raised  at  October & November Public Hearings

PHASE 2A RAW WATER DELIVERY SYSTEM

8. Why can’t you partner with City of Austin in their intake?

Cost uncertainty

Schedule uncertainty

Environmental conflicts

Page 19: Questions & Issues Raised  at  October & November Public Hearings

IMPACTS TO LAKE TRAVIS

9. Why Lake Travis for a water source? Cedar Park and Leander currently use Lake Travis

Round Rock evaluated alternative supplies and selected Lake Travis as most economical

Other alternatives (BRA water, groundwater from east) are more expensive

Page 20: Questions & Issues Raised  at  October & November Public Hearings

IMPACTS TO LAKE TRAVIS

Source-Partner Plant Size (mgd)

Net Capital Cost

Total Cost

Lake Travis-City of Cedar Park 40.8 $94,211,000 $361,220,000

Lake Belton-BRALake Travis-Cedar Park

22.818

$109,923,000 $371,439,000

Lake Travis-City of Cedar Park 18+22.8 $98,800,000 $390,619,000

Groundwater-Water Texas 18+22.8 $58,024,000 $439,374,000

Groundwater-BVWA 18+22.8 $58,024,000 $477,746,000

Groundwater-Water Texas 40.8 $58,024,000 $481,812,000

Lake Travis-City of Austin 18+22.8 $120,826,000 $520,388,000

Lake Travis-City of Austin 40.8 $140,128,000 $526,081,000

Groundwater-SWWC 40.8 - $566,096,000

2005 Round Rock Water Supply Study

Page 21: Questions & Issues Raised  at  October & November Public Hearings

IMPACTS TO LAKE TRAVIS

10. Will this project empty the lake? How much will this project really drop the lake?

At build-out, BCRUA may use up to 58,000 acre-feet per year - 13% of the annual firm yield of the Highland Lakes

This is 5% of the full volume of Lake Travis

BCRUA is one of many customers of LCRA

LCRA manages the Highland Lakes pursuant to TCEQ oversight (water rights permit and water management plan)

Page 22: Questions & Issues Raised  at  October & November Public Hearings

IMPACTS TO LAKE TRAVIS

11. How will this project impact other utilities who get water from the lake?

LCRA contracts do not guarantee water availability at any specific location or time

The LCRA water management plan predicts Lake Travis may drop to elevation 576 during a severe drought

Each utility must make contingency plans - including the existing Cedar Park and Leander/LCRA water plants

Page 23: Questions & Issues Raised  at  October & November Public Hearings

WATER CONSERVATION

12. What are the three Cities doing for water conservation?

Cedar Park Adopted inverted block rates (also known as conservation

rates) earlier this year. Effluent Re-use at Avery Ranch Golf Course Voluntary water conservation measures year around Mandatory water conservations measures during drought Sell water conservation devices (low flow aerators, low flow

toilet flaps, etc.) at low prices at City Hall.

Page 24: Questions & Issues Raised  at  October & November Public Hearings

WATER CONSERVATION

12. What are the three Cities doing for water conservation (cont.)?

Round Rock Effluent Re-use at Forest Creek Golf Course Currently in planning stages for effluent re-use to Old

Settlers Park, Stony Point High School and other locations Voluntary water conservation measures during the summer Mandatory water conservation measures during drought

Page 25: Questions & Issues Raised  at  October & November Public Hearings

WATER CONSERVATION

12. What are the three Cities doing for water conservation (cont.)?

Leander Ordinances regulating water use associated with commercial

car washes, dishwashers, and clothes washers, and individual water metering for multi-family and mixed-use properties.

Ordinance that all new landscapes (non-residential and residential) are required to have a minimum of 6” of soil depth in areas planted with turf grass.

Homebuilders are required to offer a “Water Wise” landscape option to buyers.

Voluntary water conservation measures during the summer Mandatory water conservation measures during drought

Page 26: Questions & Issues Raised  at  October & November Public Hearings

Questions?


Recommended