+ All Categories
Home > Documents > R. Akre RF / Timing [email protected] August 11, 2004 LCLS Drive Laser Timing Stability...

R. Akre RF / Timing [email protected] August 11, 2004 LCLS Drive Laser Timing Stability...

Date post: 03-Jan-2016
Category:
Upload: aron-park
View: 214 times
Download: 0 times
Share this document with a friend
25
R. Akre RF / Timing Design [email protected] du August 11, 2004 LCLS Drive Laser Timing Stability Measurements Department of Energy Review of the Linac Coherent Light Source (LCLS) Project Breakout - SC5 Control Systems August 11, 2004 Ron Akre
Transcript

R. Akre

RF / Timing Design [email protected]

August 11, 2004

LCLS Drive Laser Timing Stability MeasurementsDepartment of Energy Review of the

Linac Coherent Light Source (LCLS) Project

Breakout - SC5 Control Systems

August 11, 2004

Ron Akre

R. Akre

RF / Timing Design [email protected]

August 11, 2004

LCLS Machine Stability Tolerance BudgetLCLS Machine Stability Tolerance Budget

X-bandX-band XX--

RMS tolerance budget for <12% rms peak-current jitter or

<0.1% rms final e− energy jitter. All tolerances are rms levels and the voltage and

phase tolerances per klystron for L2 and L3 are Nk larger,

assuming uncorrelated errors, where Nk is the number of

klystrons per linac.

P. Emma

Lowest Noise Floor Requirement 0.5deg X-Band = 125fSStructure Fill time = 100nSNoise floor = -108dBc/Hz @ 11GHz 5MHz BW-134dBc/Hz @ 476MHz

R. Akre

RF / Timing Design [email protected]

August 11, 2004

LINAC RF and Timing System

PEP PHASE SHIFT ON MAIN DRIVE LINE MDL RF with TIMING Pulse – Sync to DR

Master Oscillator is located 1.3 miles

from LCLS Injector

1.3 Miles to LCLS Injector

LCLS must be compatible with the existing linac operation including PEP timing shifts

R. Akre

RF / Timing Design [email protected]

August 11, 2004

Linac Phase Reference SystemMain Drive Line - 3 1/8 Rigid Coax Anchored to Concrete Floor Every SectorPhase Reference Line - Each Sector Independent 1/2 “ HeliaxMust not introduce noise over 2 miles

R. Akre

RF / Timing Design [email protected]

August 11, 2004

Linac Phase Reference SystemMain Drive LineMain Drive Line

3 1/8 inch Rigid Coax with 3 1/8 inch Rigid Coax with 30watts input power 30mW out30watts input power 30mW out

Length = 31 Sectors, 15.5 Length = 31 Sectors, 15.5 furlongs 2miles, 3km : Velocity = furlongs 2miles, 3km : Velocity = 0.98c0.98c

Anchored at each sector next to Anchored at each sector next to coupler and expansion jointcoupler and expansion joint

Purged with dry nitrogenPurged with dry nitrogen

Phase Length Range 100Phase Length Range 100S/YearS/Year

Phase Length Range 40Phase Length Range 40S/DayS/Day

Accuracy Based on SLC Fudge Accuracy Based on SLC Fudge FactorFactor

0.50.5S/Sector Total VariationS/Sector Total Variation

0.2S rms / Sector

Phase Reference LinePhase Reference Line

½ inch Heliax Cable with 1.2 Watts½ inch Heliax Cable with 1.2 Watts

Phase Reference for 8 PADs (Klystrons) Phase Reference for 8 PADs (Klystrons) in the sectorin the sector

Length = 1 Sector, 0.5 furlongs, 332ft, Length = 1 Sector, 0.5 furlongs, 332ft, 400k400kS in ½” HeliaxS in ½” Heliax

Temperature Coefficient 4ppm/Temperature Coefficient 4ppm/CC

Waveguide Water Waveguide Water T = 0.1T = 0.1C rmsC rms

85% of the cable is regulated to 0.185% of the cable is regulated to 0.1C C rmsrms

15% may see variations of 215% may see variations of 2C rmsC rms

Average Temperature Variation = 0.4Average Temperature Variation = 0.4C C rmsrms

= 0.64= 0.64S rmsS rms

R. Akre

RF / Timing Design [email protected]

August 11, 2004

Phase Noise of SLAC Main Drive Line

Noise Floor -120dBc/38Hz = -136dBc/Hz = 120fS rms Jitter in 5MHz BW

Old Oscillator New Oscillator

New Oscillators Have a noise floor of -157dBc/Hz @ 476MHz11fS rms Jitter in 5MHz BW or 31fS rms Jitter in 40MHz BWAbove plots give upper limits, much of which could be from measurement system

Noise Floor -133dBc/38Hz = -149dBc/Hz < 60fS rms Jitter in 5MHz BW

R. Akre

RF / Timing Design [email protected]

August 11, 2004

Phase Noise of SLAC Main Drive Line

New Oscillators Have a noise floor of -157dBc/Hz @ 476MHz11fS rms Jitter in 5MHz BW or 31fS rms Jitter in 40MHz BWAbove plots give upper limits, much of which could be from

measurement system

10 100 1 103

1 104

1 105

1 106

1 107

0

0.05

0.1

0.15

0.2Timing Jitter

Frequency Hz - Start of Integration

Pico

seco

nds

rms

Linac MDL Sector 0 7-13-04 (mdl-20mF.dat)

Old Oscillator New Oscillator

R. Akre

RF / Timing Design [email protected]

August 11, 2004

SLAC Linac RF

The PAD measures phase noise between the reference RF and the

high power system. The beam sees 3.5uS of RF from SLED cavity which the klystron fills and is then dumped

into the accelerator structure.

R. Akre

RF / Timing Design [email protected]

August 11, 2004

LINAC RF MEETS ALL LCLS SPECIFICATIONSfor 2 Seconds when running well

Amplitude fast time plots show pulse to pulse variation at 30Hz. Standard deviation in percent of average amplitude over 2 seconds are 0.026% for 22-6 and 0.036% for 22-7.

Phase fast time plots show pulse to pulse variation at 30Hz. Standard deviation in degrees of 2856MHz over 2 seconds for the three stations are 0.037 for 22-6 and 0.057 for 22-7.

R. Akre

RF / Timing Design [email protected]

August 11, 2004

LINAC RF is Out of LCLS Specs in 1 Minute

14 minutes data taken using the SCP correlation plot Note that 22-6 and 22-7 are correlated in phase and amplitude

They also track the temperature of the water system

Amplitude

22-6

0.20%pp

Amplitude

22-7

0.43%pp

Phase

22-6

1.2 Deg pp

Phase

22-7

1.2 Deg pp

R. Akre

RF / Timing Design [email protected]

August 11, 2004

Phase as Seen by Electron is Difficult to MeasureAccelerator Water Temperature Effects on SLED Phase[1]

The tuning angle of the SLED cavity goes as: = tan -1 (2QLT), Where T = L/L = -/QL= 17000 = 10-5 / F Thermal expansion of copper.

=tan -1 (0.34T) Where T is in F.For small T, (S)= 20T(F)

The relation between the tuning angle and the measured output phase of the klystron varies with the time after PSK with about the following relation:

/ = 0.35 just after PSK (S)= 7T(F) / = 0.50 800nS after PSK (S)= 10T(F)

/ T~ +8.5 S / F for SLED Cavity

Accelerator Water Temperature Effects on the Accelerator Phase[2]

The phase change of the structure goes as follows: = f Where = phase through structure

= Angular frequencyf = Filling time of structure

= f = / x f / = -L/L = -T = -10-5 T / F for copper

= -10-5 T / F22856MHz0.84S = -0.15 T rad/F = -8.6 T S / F

/ T = -8.6 S / F for Accelerator StructureWater / Accelerator Temperature Variation is 0.1F rms through structure is 0.86F rms

[1] Info from D. Farkas[2] Info from P. Wilson

R. Akre

RF / Timing Design [email protected]

August 11, 2004

Phase as Seen by Electron is Difficult to Measure

Accelerator Water Temperature Effects on the Phase Through the Accelerator -8.6 S / F

SLAC Linac Accelerator Water Temperatures T< .08Frms

Phase Variations Input to Output of Accelerator > 0.5ºS-Band rms

Single Measurement Can’t Determine the Phase the Beam Sees Passing Through the Structure to LCLS Specifications

Feedback on Input Phase, Output Phase, Temperature, Beam Based Parameters (Energy and Bunch Length) is Required to Meet LCLS Specifications

Accelerator Water Temperature Effects on the Phase Through the Accelerator -8.6 S / F

SLAC Linac Accelerator Water Temperatures T< .08Frms

Phase Variations Input to Output of Accelerator > 0.5ºS-Band rms

Single Measurement Can’t Determine the Phase the Beam Sees Passing Through the Structure to LCLS Specifications

Feedback on Input Phase, Output Phase, Temperature, Beam Based Parameters (Energy and Bunch Length) is Required to Meet LCLS Specifications

R. Akre

RF / Timing Design [email protected]

August 11, 2004

LINAC SECTOR 20 – LCLS INJECTOR

RF Stability < 50fS rms : Timing/Trigger Stability 30pS rmsUsing LASER as LCLS RF OSCILLATOR is UNDER CONCIDERATION

R. Akre

RF / Timing Design [email protected]

August 11, 2004

LCLS RF System – Sector 20 Layout

100ft ½” Heliax = 0.3ºS/ºF

Tunnel Temperature < 0.1deg F rms

R. Akre

RF / Timing Design [email protected]

August 11, 2004

SPPS Laser Phase Noise Measurement

R. Akre, A. CavalieriR. Akre, A. Cavalieri

R. Akre

RF / Timing Design [email protected]

August 11, 2004

SPPS Laser Phase Noise Measurements

Phase Noise of Output of Oscillator with Respect to InputMeasurement done at 2856MHz with External Diode

Need to verify these results and check calibrationR. Akre, A. CavalieriR. Akre, A. Cavalieri

R. Akre

RF / Timing Design [email protected]

August 11, 2004

SPPS Laser Amplitude of Phase Transfer FunctionSPPS Laser Oscillator Amplitude Transfer Function

-25.0

-20.0

-15.0

-10.0

-5.0

0.0

5.0

10.0

0 5000 10000 15000 20000 25000 30000 35000

Frequency Hz

Am

plitu

de

dB

Phase Modulation placed on RF Reference and measured on Diode at Laser output.

During the Blue part of the curve the modulation amplitude was reduced by 12dB to prevent laser from unlocking. Data taken 10/22/03 R. Akre, A. CavalieriR. Akre, A. Cavalieri

R. Akre

RF / Timing Design [email protected]

August 11, 2004

SPPS Laser Phase Jump Tracking

R. Akre, A. CavalieriR. Akre, A. Cavalieri

R. Akre

RF / Timing Design [email protected]

August 11, 2004

SPPS Laser Phase Jump Trackingk1 0

kpts 12

143.7 143.8 143.9 144 144.1 144.2 144.3 144.40.4

0.2

0

0.2

0.4

0.6

milliseconds

pico

seco

nds

- ph

ase

erro

r

SPPS LASER 1 Hz Phase Oscillation Square Wave 0.25pS pk (Phase Shift In 400k 2mVT.dat) 400k SPS

k1 0kpts 1

2

643.8 643.9 644 644.1 644.2 644.3 644.40.5

0.4

0.3

0.2

0.1

0

0.1

milliseconds

pic

ose

cond

s -

ph

ase

err

or

SPPS LASER 1 Hz Phase Oscillation Square Wave 0.25pS pk (Phase Shift In 400k 2mVT.dat) 400k SPS

k1 0kpts 1

2

26.2 26.4 26.6 26.8 27 27.2 27.41

0.5

0

0.5

1

milliseconds

pic

ose

cond

s -

ph

ase

err

or

SPPS LASER 1 Hz Phase Oscillation Square Wave 2pS pk (Phase Shift In 400k 16mV 3T.dat) 400k SPS

k1 0kpts 1

2

526.2 526.4 526.6 526.8 527 527.2 527.41

0.5

0

0.5

1

milliseconds

pic

ose

cond

s -

ph

ase

err

or

SPPS LASER 1 Hz Phase Oscillation Square Wave 2pS pk (Phase Shift In 400k 16mV 3T.dat) 400k SPS

0.25pS pk Square Wave 2.0pS pk Square Wave

Laser Phase Error – Output Phase to Input Reference - Modulated with 1 Hz Square Wave

R. Akre

RF / Timing Design [email protected]

August 11, 2004

Linac Phase Stability Estimate Based on Energy Linac Phase Stability Estimate Based on Energy Jitter in the ChicaneJitter in the Chicane

SLAC LinacSLAC Linac

1 GeV1 GeV 30 GeV30 GeV9 GeV9 GeV

ee Energy (MeV) Energy (MeV)

BPM

221/21/2< 0.1 deg (100 fs)< 0.1 deg (100 fs)

EE/E/E00 0.06% 0.06%

P. Emma

R. Akre

RF / Timing Design [email protected]

August 11, 2004

Electro-Optical SamplingElectro-Optical Sampling

170 fs rms170 fs rms

Single-ShotSingle-Shot

Timing JitterTiming Jitter(20 Shots)(20 Shots)

200 200 m thick ZnTe crystalm thick ZnTe crystal

ee

Ti:Sapphire Ti:Sapphire laserlaser

Adrian Cavalieri et al., Adrian Cavalieri et al., U. Mich.U. Mich.

<300 fs<300 fs

ee temporal information is encoded on temporal information is encoded on transverse profile of laser beamtransverse profile of laser beam

R. Akre

RF / Timing Design [email protected]

August 11, 2004

LCLS Phase Noise Associated Time Referenced to Beam Time

LCLS Laser ~200uS Off Scale BelowLCLS Gun 1.1uS SLED / Accelerator 3.5uS Phase Detector (Existing) 30nSDistribution System 200nS

1km @ c-97%c=100nS

Far Hall Trigger 2uS3km @ c-80%c=2uS

TIME

-3.5us SLED Starts to Fill

-1.1uS Gun Starts to Fill

-2uS Far Hall TrigRF Starts Trip

Beam Time 0Reference

Except for the LASER common mode noise levels below ~100kHz would not cause instabilities – the entire system would track the deviations

R. Akre

RF / Timing Design [email protected]

August 11, 2004

Beam Trigger for User Facility

Single Pulse with 30fS stability (1Hz to 3GHz BW)

Tightest Noise Tolerance of LCLS

Wide Bandwidth

Low Phase Noise 30fS Stability today

10fS Stability tomorrow

1fS The Day After

Currently users are expected to use local beam timing measurement, EO, to achieve this.

R. Akre

RF / Timing Design [email protected]

August 11, 2004

FY04 Tasks

Complete phase measurement system

Complete measurements in the SLAC front end

Preliminary design for SLAC linac RF upgrade

Complete Design of 1kW Solid State S-Band Amp

R. Akre

RF / Timing Design [email protected]

August 11, 2004

FY05 Tasks and ResourcesReady to Ramp Up

Start on X-Band systemComplete SLAC Linac Front End UpgradesComplete Design of Phase Reference SystemComplete Design of LLRF Control SystemDefine Beam Phase Cavity MonitorFurther Studies on Linac Stability

SLAC Klystron Department to Support 75% of RF manpower

Manpower available from other SLAC groups (ARDA, ARDB, NLC, and Controls) and LBNL


Recommended