    Introduction to RDAP

    Getting Started

  • 7/28/2019 r Dap Introduction

    2/32

    Opening RDAP will give you this window. For the first

    time user you must create a system. Click on

    File/System Selection

  • 7/28/2019 r Dap Introduction

    3/32

    This window appears. Under Select System, type in

    First System. Hit enter

  • 7/28/2019 r Dap Introduction

    4/32

    Click Yes to save the system created

  • 7/28/2019 r Dap Introduction

    5/32

    Since this is the first system, the only answer you can give

    is No. In the future as you create new systems you

    probably will want to answer Yes.

  • 7/28/2019 r Dap Introduction

    6/32

    On the new window, click File/Sub/Feeder Selection.

    Hit enter

  • 7/28/2019 r Dap Introduction

    7/32

    Type in the name First under Substation and hit enter.

  • 7/28/2019 r Dap Introduction

    8/32

    Click on Yes

  • 7/28/2019 r Dap Introduction

    9/32

    Type in 12.47 under Feeder Bus. That is all that you

    need to do at this point. Click on Okay

  • 7/28/2019 r Dap Introduction

    10/32

    Type in Feeder 1 under Feeder. Hit enter and answer

    Yes to the question.

  • 7/28/2019 r Dap Introduction

    11/32

    Type in F1 in the blank. Be careful that you dont put

    any spaces in the name. Click Okay

  • 7/28/2019 r Dap Introduction

    12/32

    You should now have this window showing that you have

    created First System with Substation First and

    Feeder 1. Now click on Z-Models

  • 7/28/2019 r Dap Introduction

    13/32

    Listed here are the basic data that will be input for a

    given feeder. Conductors lists all of the standard

    conductors. At this point click on Spacings

  • 7/28/2019 r Dap Introduction

    14/32

    The upper window shows the spacings that have been

    created. At this point there arent any. Hit enter to drop

    down to the lower window.

  • 7/28/2019 r Dap Introduction

    15/32

    Type in the Description, select Feet and then type in the

    x,y coordinates for the four positions as shown. Hit Okay.

    Note that you could enter more data. Hit Quit and

    answer Yes.

  • 7/28/2019 r Dap Introduction

    16/32

    Click on Z-Models/Configurations to get this screen.

    As before the left window shows configurations that have

    been built. At this point there arent any. Hit enter to

    move to the right side (input) window.

  • 7/28/2019 r Dap Introduction

    17/32

    Type in the Description, hit enter and then the down

    arrow to scroll through the conductors. Stop on 450,000

    AA and hit enter to move to the Neutral Conductor

    selection.

  • 7/28/2019 r Dap Introduction

    18/32

    Continue entering the data using the pop up windows to

    select Spacing in Feet and Phasing. Set the Distance

    from Grd to 0. Hit Okay. More data could be entered,

    but hit Quit and then Yes.

  • 7/28/2019 r Dap Introduction

    19/32

    From the main screen click on Z-Models/Configurations.

    The window appears and now click on View Zs to see

    the computed phase and admittance matrices for this

    configuration.

  • 7/28/2019 r Dap Introduction

    20/32

    Get back to the main window by hitting Okay,Quit

    and Yes. You are now ready to enter data for your

    Feeder 1. Select Data/Segments

  • 7/28/2019 r Dap Introduction

    21/32

    This window displays the data window on the left and the

    input window on the right. Hit enter to get to the data

    input window.

  • 7/28/2019 r Dap Introduction

    22/32

    Enter the data for the 6000 ft. segment. I usually select

    the Node B name as the Segment name. From the pop

    up menu select DEMO. Hit Quit and answer Yes

  • 7/28/2019 r Dap Introduction

    23/32

    Select Spot Loads to bring up the data window for the

    spot loads.

  • 7/28/2019 r Dap Introduction

    24/32

    As before the left window shows the nodes that have been

    created. Select F2 and hit enter. Now input the necessary

    data. Hit Quit and Yes.

  • 7/28/2019 r Dap Introduction

    25/32

    Your feeder can now be analyzed selecting

    Analysis/Interactive Flow Analysis

  • 7/28/2019 r Dap Introduction

    26/32

    This is the menu for the analysis routines. Select

    Results to run the analysis.

  • 7/28/2019 r Dap Introduction

    27/32

    Right away the pop up menu shown will appear. This

    lists the various outputs that you can look at. Look at

    each one of them.

  • 7/28/2019 r Dap Introduction

    28/32

    Summary

    Click on the three horizontal lines on the top left to get

    back to the menu. Note the top right of the screen is

    WRITE. Click on that and this window will be writtento rdap.txt in the RDAP30 subdirector.

  • 7/28/2019 r Dap Introduction

    29/32

    Node Voltages on 120 volt base

  • 7/28/2019 r Dap Introduction

    30/32

    Dont look at voltage profile yet. Select power flow. A

    new pop-ups shows the nodes in the feeder. Select all and

    then toggle to get flow in Amps/Degs.

  • 7/28/2019 r Dap Introduction

    31/32

    Continue to look at the various outputs. To get back to

    the data preparation menu hit File/Return

  • 7/28/2019 r Dap Introduction

    32/32