REGIONAL TRANSMISSION NETWORK REGIONAL TRANSMISSION NETWORK DEVELOPMENT: DEVELOPMENT: IMPLICATIONS FOR TRADE AND IMPLICATIONS FOR TRADE AND INVESTMENT INVESTMENT Turkey – Romania Undersea Cable (Feasibility Turkey – Romania Undersea Cable (Feasibility Study Support) Study Support) Razvan Purdila, Director Razvan Purdila, Director Corporate Strategy, Capital Market, Corporate Strategy, Capital Market, Communication Communication and International Relationships, Transelectrica and International Relationships, Transelectrica
Transcript
Page 1: R EGIONAL T RANSMISSION N ETWORK D EVELOPMENT : I MPLICATIONS FOR T RADE AND I NVESTMENT R EGIONAL T RANSMISSION N ETWORK D EVELOPMENT : I MPLICATIONS.

REGIONAL TRANSMISSION REGIONAL TRANSMISSION NETWORK DEVELOPMENT NETWORK DEVELOPMENT IMPLICATIONS FOR TRADE IMPLICATIONS FOR TRADE

AND INVESTMENTAND INVESTMENT

Turkey ndash Romania Undersea Cable (Feasibility Study Turkey ndash Romania Undersea Cable (Feasibility Study Support)Support)

Razvan Purdila DirectorRazvan Purdila DirectorCorporate Strategy Capital Market CommunicationCorporate Strategy Capital Market Communication

and International Relationships Transelectricaand International Relationships TranselectricaNovember 11-12 2009November 11-12 2009

USAID USEA WORKSHOPREGIONAL TRANSMISSION NETWORK DEVELOPMENT IMPLICATIONS FOR TRADE AND INVESTMENT Istanbul November 2009

Romania ndash Turkey 400 kV HVDC link

undersea cable project

Razvan Purdila Transelectrica

Why HVDC systems

HVDC is an ldquointelligent linkrdquo The power flow can be controlled and changed very quickly practically independently from frequency at the terminal busses voltage or power angle at the terminal busses like in HVAC transmission

Due to the inherent properties of the electronic equipment which forms the converter bridges the direction of the transmitted power may be also changed very quickly

The HVDC transmission has the major advantage of flexibility inpower exchange in comparison with HVAC Moreover in case oftransmission of bulk electrical energy over long distances (more than 50 km) by submarine cable the only applicable technology is theHVDC transmission

Advantages for HVDC transmission

In a HVDC system the electricity is

- Taken from a 3-phase AC network- Converted to DC in a converter station- Transmitted by DC OHL or cable (underground or sub sea)- Converted back to AC in another converter station- Injected into AC network

HVDC transmission ndash principles and characteristics

Controllable ndash power injected where neededsupplemental control frequency control- Bypass congested circuits ndash no inadvertent flow- Higher power fewer linesno intermediate SS needed- Lower losses- Facilitates integration of remotediverse resources with less impacton existing grid- Low expensive transmission line- Reactive power demand limited toterminals independent of distances- Narrower ROW no EMF constraints- No limit to underground or submarinecable length

Cable laying

The scope of this project is to install a submarine cable between the Romanian and Turkish TSOrsquos Transelectrica and TEIAS respectively

Business concept commercial interconnector separately regulated

The Project is in line with the policies of both Romanian and Turkish Governments and fits well into the EU Green Paper on Energy and EU strategy of Priority Network Projects The project also brings a significant contribution and stability to the regional electricity market in South-East Europe

The Project is ldquoon goingrdquo in the Feasibility Study phase

Project scope

Short history of the project

bull 2004 ndash April ndash energy cooperation protocol between Romania and Turkey at ministries level

ndash The first mentioning of the cable project

bull 2005 - June ndash MOU between Transelectrica and TEIAS for the HVDC link project

ndash Main scope to prepare the oportunity study by a joint project team

bull 2006 ndash November - JPP ( joint position paper ) between Transelectrica and TEIAS

ndash Approval of the opportunity study

ndash Decision to continue the study at feasibility study level

bull 2007 ndash first attempt to launch the feasibility study with minority financing of private investors ( 50 Swedish grant available )

ndash No success replacement of the private investor with Nuclearelectrica

bull 2008 ndash first tender for the FS in new financing conditions

ndash Incompatibility of the grant with open tender requirements

bull 2009 ndash secont tender contract signature in June

ELEMENT 01

TELConstanţa

NordSubstation

ELEMENT 02TEL

Converter station and

link to Constanţa

Nord substation

ELEMENT03

TELUnderground cable between

converter station and HVDC cable connection

ELEMENT04

HVDC

cable

ELEMENT05

TEIASUnderground cable between

converter station and HVDC cable connection

ELEMENT 06

TEIASConverter

station and link to

Alibeykoumly substation

ROMANIA

BLACK SEA

ELEMENT 07

TEIASAlibeykoumly Substation

TURKEY

Romania ndash Turkey HVDC interconector overview

Part 3The feasibility study

bull Connection point with Romanian Power System 400kV SS Constanţa Nordbull Connection point with Turkish Power System 400kV SS Alybeikoumly in AsiabullThe cables voltage level 400 kVbullThe capacity 600MWbullThe length about 400 kmbull Losses on the cable-

bull in 600MW transfer ~ 12MWbull in 500MW transfer ~ 9MW

Deliverables

The nominated Designer will submit the following documents

Inception Report Terms of Reference ndash Objectives for procuring the services and

works required for the seabed survey and Geological Study EIA ndash Environmental Impact Assessment Study including

environmental approval Feasibility Study (draft) including the necessary documentation for

approvals and advices Feasibility Study (final) including the approvals and advices Documentation for urbanism certificates in Romania and Turkey Technical Specifications Progress Reports Final Report

Client ConsultantFICHTNER ENGINEERING

Romania

ClientTRANSELECTRICA amp NUCLEARELECTRICA

Romania

Client DesignerVATTENFALL

Sweden

Technical ConsultantTEIAŞ Turkey

Project team members and their responsibilities

Electricity market team

Technical team

Economical institutional and legal

commercial and financial team

- Environment expert- See bead expert- Overhead

transmission line expert

- Electrical substation expert

- Converter expert- HVDC submarine

cable expert- Permits and

approvals expert

- Contract legislation expert

- Price electricity forecasting expert

- Electricity market expert

- Macroeconomic modeling expert

- Financial analyze expert

- Investment analyze expert

- Contract legislation expert

- Romanian amp international legislation expert

Environmental team

Procurement team

- Commercial expert- Overhead

transmission line expert

- Electrical substation expert

- Converter expert- HVDC submarine

cable expert- Environment expert

- Environment expert- Romanian amp

international legislation expert

- Permits and approvals expert

EXPERT TEAMS

The Feasibility Study will

Establish the design parameters capacity and cost estimation for the HVDC link including the most suitable routing based on previous studies and existing data which include geological morphological and seabed structure analyze and initial sea depth survey as well as on its own investigations

Assess the legal and environmental impediments and propose the most appropriate and viable way forward for the Project from an operational and legal framework point of view including also the EIA Study with the afferent approvals in accordance with legalstipulations from both countries and from EU (Transelectrica Nuclearelectrica and TEIAŞ will in this respect support the Designer in this process)

bullContain the necessary documentation for obtaining permits and approvals in accordance with existing legislation in Romania and in Turkey as applicable at the date of project elaboration and corresponding to this phase of the engineeringbullContain the necessary documentation to obtain the urbanism certificatebullAnalyse the financial and economical feasibility of the interconnection project considering private benefits and costs and external effects such as public benefits and costsbullAssess suitable possibilities to finance the ProjectbullPropose a time schedule for project implementation and operationbullHighlight the commercial environmental and technical conditions of direct interconnection of the national grids of Turkey and Romania through a submarine cable across the Black Sea through system studies performed in both countries

Technical Specifications for procurement and execution will include at least a minimalcontent as follows- Scope- Definitions- Standard and recommendations- Functional and technical requirements- Testing and inspections- Execution- Provision of information1048707 Terms of Reference for procuring the services and work required for the seabed survey and geological study will be established based on our experience in similar projects For the feasibility study we will perform a study based on existing materialsdocumentation related to Black Sea seabed survey and geological studies1048707

1 Inception report (within 6 weeks of commencement of the project)2 Terms of Reference for the Seabed survey and Geological Study (The draftissue to be submitted within 6 weeks of commencement of the assignment)3 Plans and Terms of Reference for the Environmental Impact assessment (Tobe submitted as an annex to the first Progress report)4 Environmental Impact Assessment (EIA) incl environmental approvals (The draftissue within 8 months and the final issue within 10 months after the commencementof the assignment)5 Feasibility Study ndash draft incl the necessary documents for approvals and advices(8 months after commencement of the assignment)6 Feasibility Study ndash final incl approvals and advices (10 months aftercommencement of the assignment)7 Documentation for urbanism certificates in Romania and Turkey (10 months aftercommencement of the assignment)8 Technical Specifications (Within 14 months after the commencement of theproject)9 Progress Reports (To be reported quarterly no later than the 10th working day afterthe reporting period)10 Final Report (The final report shall be submitted upon finalisation of the assignement

DELIVERABLES

- Costs for Submarine cables - material and installation- Costs for HVDC land cables andor HVDC OHTLs andor HVAC ndash type overhead electriclines as applicable in Romania ndash material and installations- Costs for HVDC land cables andor HVDC OHTLs andor HVAC ndash type overhead electriclines as applicable in Turkey ndash material and installations- Costs for converter station including the AC connection in Romania- Costs for converter station including the AC connection in Turkey- Telecommunication equipment based on optical fibers- Site costs in Romania- Site costs in Turkey- Engineering project management project control and commissioning- Other investments if any- Interest rates during construction calculated separately for each of the above mentionedparts of the HVDC link- Total investment costs for the HVDC link- Payment for provisional and final expropriations

Investment needs - Investments in the HVDC Link

Investments in the Romanian AC Grid- AC grid investments exclusive the breaker bay for the HVDC link- Telecommunication and remote control equipment- Interest rates calculated separately for each part- Total investments due to the HVDC link in the Romanian AC grid

Investments in the Turkish AC Grid- AC grid investments exclusive the breaker bay for the HVDC link- Telecommunication and remote control equipment- Interest rates during construction calculated separately for each part- Total investments due to the HVDC link in the Turkish AC grid

Investment needs - Investments in the Romanian and Turkish AC grids

ldquoThe price forecast has to be calculated from different perspectivesbull Long term off-take contract 60 and 80 bull Market price for the remaining 40 and 20 bull Sufficient Average Price Level (SAPL)

COMMERCIAL and FINANCIAL ANALYSIS

ldquoBased on the recommended investment and operational plan the Designer shall establish a financial model and analyse the investment over a time horizon of both 20 years operation and 30 years operation The output of the model shall be presented in nominal terms

Tranzit scenarios 1000 MW from Romania to Turkey

Tranzit scenarios 1000 MW from UCTE (PolandampSlovakia) to

Turkey

Tranzit scenarios 1000 MW from Russia (IPSUPS) to Turkey

budget

Tranzit scenarios 1000 MW from Turkey to Romania

Tranzit scenarios1000 MW from Turkey to UCTE (Serbia and

Austria)

Activities to be done in parallel with the feasibilty study

bull Preliminary business model

ndash List of main commercial regulatory and financial hypothesys

ndash Documentation on the business experience of existing commercial interconnectors in EU

ndash Discussions and clarifications with the regulatory authorities

ndash Legal due diligence for the preliminary business model

ndash TOR for the complete business study

bull Exploration and identification of potential private partners

ndash Letters of intent

ndash Develop procedure for the selection of the private investors

bull Full clarifications on TEIAS participation in the project including Turkish applicable legislation

bull Preliminary legal preparations for the project company ( SPV )

Opportunity StudyJoint Position Paper

Feasibility Study( 75 TEL- 25 NE ) Business Study

Joint Position Paper - Final

International Agreement between

Romania and Turkey

Project implementationFinancing contracting supply and instalation

MOU -1MOU -1

MOU -2 MOU -2

Selection of private investors SPV ndash the project company

2005

2008 - 2009

2009

2010

2010 - 2013

022009

First tentative road map

THANK YOU FOR YOUR ATTENTION

e-mail relatiiinvestitoritranselectricaro razvanpurdilatranselectricaro

phone +40213035923fax +40213035880web-site wwwtranselectricaro

  • Regional Transmission Network Development Implications for Trade and Investment
  • Slide 2
  • Slide 4
  • Slide 5
  • Slide 6
  • Slide 7
  • Slide 8
  • Slide 9
  • Slide 11
  • Slide 12
  • Slide 13
  • Slide 14
  • Slide 15
  • Slide 16
  • Slide 17
  • Slide 18
  • Slide 19
  • Slide 20
  • Slide 21
  • Slide 22
  • Slide 23
  • Slide 24
  • Slide 25
  • Slide 27
  • Slide 28
  • Slide 29
  • Slide 30
  • Slide 31
  • Activities to be done in parallel with the feasibilty study
  • Slide 34
  • Slide 35
Page 2: R EGIONAL T RANSMISSION N ETWORK D EVELOPMENT : I MPLICATIONS FOR T RADE AND I NVESTMENT R EGIONAL T RANSMISSION N ETWORK D EVELOPMENT : I MPLICATIONS.

USAID USEA WORKSHOPREGIONAL TRANSMISSION NETWORK DEVELOPMENT IMPLICATIONS FOR TRADE AND INVESTMENT Istanbul November 2009

Romania ndash Turkey 400 kV HVDC link

undersea cable project

Razvan Purdila Transelectrica

Why HVDC systems

HVDC is an ldquointelligent linkrdquo The power flow can be controlled and changed very quickly practically independently from frequency at the terminal busses voltage or power angle at the terminal busses like in HVAC transmission

Due to the inherent properties of the electronic equipment which forms the converter bridges the direction of the transmitted power may be also changed very quickly

The HVDC transmission has the major advantage of flexibility inpower exchange in comparison with HVAC Moreover in case oftransmission of bulk electrical energy over long distances (more than 50 km) by submarine cable the only applicable technology is theHVDC transmission

Advantages for HVDC transmission

In a HVDC system the electricity is

- Taken from a 3-phase AC network- Converted to DC in a converter station- Transmitted by DC OHL or cable (underground or sub sea)- Converted back to AC in another converter station- Injected into AC network

HVDC transmission ndash principles and characteristics

Controllable ndash power injected where neededsupplemental control frequency control- Bypass congested circuits ndash no inadvertent flow- Higher power fewer linesno intermediate SS needed- Lower losses- Facilitates integration of remotediverse resources with less impacton existing grid- Low expensive transmission line- Reactive power demand limited toterminals independent of distances- Narrower ROW no EMF constraints- No limit to underground or submarinecable length

Cable laying

The scope of this project is to install a submarine cable between the Romanian and Turkish TSOrsquos Transelectrica and TEIAS respectively

Business concept commercial interconnector separately regulated

The Project is in line with the policies of both Romanian and Turkish Governments and fits well into the EU Green Paper on Energy and EU strategy of Priority Network Projects The project also brings a significant contribution and stability to the regional electricity market in South-East Europe

The Project is ldquoon goingrdquo in the Feasibility Study phase

Project scope

Short history of the project

bull 2004 ndash April ndash energy cooperation protocol between Romania and Turkey at ministries level

ndash The first mentioning of the cable project

bull 2005 - June ndash MOU between Transelectrica and TEIAS for the HVDC link project

ndash Main scope to prepare the oportunity study by a joint project team

bull 2006 ndash November - JPP ( joint position paper ) between Transelectrica and TEIAS

ndash Approval of the opportunity study

ndash Decision to continue the study at feasibility study level

bull 2007 ndash first attempt to launch the feasibility study with minority financing of private investors ( 50 Swedish grant available )

ndash No success replacement of the private investor with Nuclearelectrica

bull 2008 ndash first tender for the FS in new financing conditions

ndash Incompatibility of the grant with open tender requirements

bull 2009 ndash secont tender contract signature in June

ELEMENT 01

TELConstanţa

NordSubstation

ELEMENT 02TEL

Converter station and

link to Constanţa

Nord substation

ELEMENT03

TELUnderground cable between

converter station and HVDC cable connection

ELEMENT04

HVDC

cable

ELEMENT05

TEIASUnderground cable between

converter station and HVDC cable connection

ELEMENT 06

TEIASConverter

station and link to

Alibeykoumly substation

ROMANIA

BLACK SEA

ELEMENT 07

TEIASAlibeykoumly Substation

TURKEY

Romania ndash Turkey HVDC interconector overview

Part 3The feasibility study

bull Connection point with Romanian Power System 400kV SS Constanţa Nordbull Connection point with Turkish Power System 400kV SS Alybeikoumly in AsiabullThe cables voltage level 400 kVbullThe capacity 600MWbullThe length about 400 kmbull Losses on the cable-

bull in 600MW transfer ~ 12MWbull in 500MW transfer ~ 9MW

Deliverables

The nominated Designer will submit the following documents

Inception Report Terms of Reference ndash Objectives for procuring the services and

works required for the seabed survey and Geological Study EIA ndash Environmental Impact Assessment Study including

environmental approval Feasibility Study (draft) including the necessary documentation for

approvals and advices Feasibility Study (final) including the approvals and advices Documentation for urbanism certificates in Romania and Turkey Technical Specifications Progress Reports Final Report

Client ConsultantFICHTNER ENGINEERING

Romania

ClientTRANSELECTRICA amp NUCLEARELECTRICA

Romania

Client DesignerVATTENFALL

Sweden

Technical ConsultantTEIAŞ Turkey

Project team members and their responsibilities

Electricity market team

Technical team

Economical institutional and legal

commercial and financial team

- Environment expert- See bead expert- Overhead

transmission line expert

- Electrical substation expert

- Converter expert- HVDC submarine

cable expert- Permits and

approvals expert

- Contract legislation expert

- Price electricity forecasting expert

- Electricity market expert

- Macroeconomic modeling expert

- Financial analyze expert

- Investment analyze expert

- Contract legislation expert

- Romanian amp international legislation expert

Environmental team

Procurement team

- Commercial expert- Overhead

transmission line expert

- Electrical substation expert

- Converter expert- HVDC submarine

cable expert- Environment expert

- Environment expert- Romanian amp

international legislation expert

- Permits and approvals expert

EXPERT TEAMS

The Feasibility Study will

Establish the design parameters capacity and cost estimation for the HVDC link including the most suitable routing based on previous studies and existing data which include geological morphological and seabed structure analyze and initial sea depth survey as well as on its own investigations

Assess the legal and environmental impediments and propose the most appropriate and viable way forward for the Project from an operational and legal framework point of view including also the EIA Study with the afferent approvals in accordance with legalstipulations from both countries and from EU (Transelectrica Nuclearelectrica and TEIAŞ will in this respect support the Designer in this process)

bullContain the necessary documentation for obtaining permits and approvals in accordance with existing legislation in Romania and in Turkey as applicable at the date of project elaboration and corresponding to this phase of the engineeringbullContain the necessary documentation to obtain the urbanism certificatebullAnalyse the financial and economical feasibility of the interconnection project considering private benefits and costs and external effects such as public benefits and costsbullAssess suitable possibilities to finance the ProjectbullPropose a time schedule for project implementation and operationbullHighlight the commercial environmental and technical conditions of direct interconnection of the national grids of Turkey and Romania through a submarine cable across the Black Sea through system studies performed in both countries

Technical Specifications for procurement and execution will include at least a minimalcontent as follows- Scope- Definitions- Standard and recommendations- Functional and technical requirements- Testing and inspections- Execution- Provision of information1048707 Terms of Reference for procuring the services and work required for the seabed survey and geological study will be established based on our experience in similar projects For the feasibility study we will perform a study based on existing materialsdocumentation related to Black Sea seabed survey and geological studies1048707

1 Inception report (within 6 weeks of commencement of the project)2 Terms of Reference for the Seabed survey and Geological Study (The draftissue to be submitted within 6 weeks of commencement of the assignment)3 Plans and Terms of Reference for the Environmental Impact assessment (Tobe submitted as an annex to the first Progress report)4 Environmental Impact Assessment (EIA) incl environmental approvals (The draftissue within 8 months and the final issue within 10 months after the commencementof the assignment)5 Feasibility Study ndash draft incl the necessary documents for approvals and advices(8 months after commencement of the assignment)6 Feasibility Study ndash final incl approvals and advices (10 months aftercommencement of the assignment)7 Documentation for urbanism certificates in Romania and Turkey (10 months aftercommencement of the assignment)8 Technical Specifications (Within 14 months after the commencement of theproject)9 Progress Reports (To be reported quarterly no later than the 10th working day afterthe reporting period)10 Final Report (The final report shall be submitted upon finalisation of the assignement

DELIVERABLES

- Costs for Submarine cables - material and installation- Costs for HVDC land cables andor HVDC OHTLs andor HVAC ndash type overhead electriclines as applicable in Romania ndash material and installations- Costs for HVDC land cables andor HVDC OHTLs andor HVAC ndash type overhead electriclines as applicable in Turkey ndash material and installations- Costs for converter station including the AC connection in Romania- Costs for converter station including the AC connection in Turkey- Telecommunication equipment based on optical fibers- Site costs in Romania- Site costs in Turkey- Engineering project management project control and commissioning- Other investments if any- Interest rates during construction calculated separately for each of the above mentionedparts of the HVDC link- Total investment costs for the HVDC link- Payment for provisional and final expropriations

Investment needs - Investments in the HVDC Link

Investments in the Romanian AC Grid- AC grid investments exclusive the breaker bay for the HVDC link- Telecommunication and remote control equipment- Interest rates calculated separately for each part- Total investments due to the HVDC link in the Romanian AC grid

Investments in the Turkish AC Grid- AC grid investments exclusive the breaker bay for the HVDC link- Telecommunication and remote control equipment- Interest rates during construction calculated separately for each part- Total investments due to the HVDC link in the Turkish AC grid

Investment needs - Investments in the Romanian and Turkish AC grids

ldquoThe price forecast has to be calculated from different perspectivesbull Long term off-take contract 60 and 80 bull Market price for the remaining 40 and 20 bull Sufficient Average Price Level (SAPL)

COMMERCIAL and FINANCIAL ANALYSIS

ldquoBased on the recommended investment and operational plan the Designer shall establish a financial model and analyse the investment over a time horizon of both 20 years operation and 30 years operation The output of the model shall be presented in nominal terms

Tranzit scenarios 1000 MW from Romania to Turkey

Tranzit scenarios 1000 MW from UCTE (PolandampSlovakia) to

Turkey

Tranzit scenarios 1000 MW from Russia (IPSUPS) to Turkey

budget

Tranzit scenarios 1000 MW from Turkey to Romania

Tranzit scenarios1000 MW from Turkey to UCTE (Serbia and

Austria)

Activities to be done in parallel with the feasibilty study

bull Preliminary business model

ndash List of main commercial regulatory and financial hypothesys

ndash Documentation on the business experience of existing commercial interconnectors in EU

ndash Discussions and clarifications with the regulatory authorities

ndash Legal due diligence for the preliminary business model

ndash TOR for the complete business study

bull Exploration and identification of potential private partners

ndash Letters of intent

ndash Develop procedure for the selection of the private investors

bull Full clarifications on TEIAS participation in the project including Turkish applicable legislation

bull Preliminary legal preparations for the project company ( SPV )

Opportunity StudyJoint Position Paper

Feasibility Study( 75 TEL- 25 NE ) Business Study

Joint Position Paper - Final

International Agreement between

Romania and Turkey

Project implementationFinancing contracting supply and instalation

MOU -1MOU -1

MOU -2 MOU -2

Selection of private investors SPV ndash the project company

2005

2008 - 2009

2009

2010

2010 - 2013

022009

First tentative road map

THANK YOU FOR YOUR ATTENTION

e-mail relatiiinvestitoritranselectricaro razvanpurdilatranselectricaro

phone +40213035923fax +40213035880web-site wwwtranselectricaro

  • Regional Transmission Network Development Implications for Trade and Investment
  • Slide 2
  • Slide 4
  • Slide 5
  • Slide 6
  • Slide 7
  • Slide 8
  • Slide 9
  • Slide 11
  • Slide 12
  • Slide 13
  • Slide 14
  • Slide 15
  • Slide 16
  • Slide 17
  • Slide 18
  • Slide 19
  • Slide 20
  • Slide 21
  • Slide 22
  • Slide 23
  • Slide 24
  • Slide 25
  • Slide 27
  • Slide 28
  • Slide 29
  • Slide 30
  • Slide 31
  • Activities to be done in parallel with the feasibilty study
  • Slide 34
  • Slide 35
Page 3: R EGIONAL T RANSMISSION N ETWORK D EVELOPMENT : I MPLICATIONS FOR T RADE AND I NVESTMENT R EGIONAL T RANSMISSION N ETWORK D EVELOPMENT : I MPLICATIONS.

Why HVDC systems

HVDC is an ldquointelligent linkrdquo The power flow can be controlled and changed very quickly practically independently from frequency at the terminal busses voltage or power angle at the terminal busses like in HVAC transmission

Due to the inherent properties of the electronic equipment which forms the converter bridges the direction of the transmitted power may be also changed very quickly

The HVDC transmission has the major advantage of flexibility inpower exchange in comparison with HVAC Moreover in case oftransmission of bulk electrical energy over long distances (more than 50 km) by submarine cable the only applicable technology is theHVDC transmission

Advantages for HVDC transmission

In a HVDC system the electricity is

- Taken from a 3-phase AC network- Converted to DC in a converter station- Transmitted by DC OHL or cable (underground or sub sea)- Converted back to AC in another converter station- Injected into AC network

HVDC transmission ndash principles and characteristics

Controllable ndash power injected where neededsupplemental control frequency control- Bypass congested circuits ndash no inadvertent flow- Higher power fewer linesno intermediate SS needed- Lower losses- Facilitates integration of remotediverse resources with less impacton existing grid- Low expensive transmission line- Reactive power demand limited toterminals independent of distances- Narrower ROW no EMF constraints- No limit to underground or submarinecable length

Cable laying

The scope of this project is to install a submarine cable between the Romanian and Turkish TSOrsquos Transelectrica and TEIAS respectively

Business concept commercial interconnector separately regulated

The Project is in line with the policies of both Romanian and Turkish Governments and fits well into the EU Green Paper on Energy and EU strategy of Priority Network Projects The project also brings a significant contribution and stability to the regional electricity market in South-East Europe

The Project is ldquoon goingrdquo in the Feasibility Study phase

Project scope

Short history of the project

bull 2004 ndash April ndash energy cooperation protocol between Romania and Turkey at ministries level

ndash The first mentioning of the cable project

bull 2005 - June ndash MOU between Transelectrica and TEIAS for the HVDC link project

ndash Main scope to prepare the oportunity study by a joint project team

bull 2006 ndash November - JPP ( joint position paper ) between Transelectrica and TEIAS

ndash Approval of the opportunity study

ndash Decision to continue the study at feasibility study level

bull 2007 ndash first attempt to launch the feasibility study with minority financing of private investors ( 50 Swedish grant available )

ndash No success replacement of the private investor with Nuclearelectrica

bull 2008 ndash first tender for the FS in new financing conditions

ndash Incompatibility of the grant with open tender requirements

bull 2009 ndash secont tender contract signature in June

ELEMENT 01

TELConstanţa

NordSubstation

ELEMENT 02TEL

Converter station and

link to Constanţa

Nord substation

ELEMENT03

TELUnderground cable between

converter station and HVDC cable connection

ELEMENT04

HVDC

cable

ELEMENT05

TEIASUnderground cable between

converter station and HVDC cable connection

ELEMENT 06

TEIASConverter

station and link to

Alibeykoumly substation

ROMANIA

BLACK SEA

ELEMENT 07

TEIASAlibeykoumly Substation

TURKEY

Romania ndash Turkey HVDC interconector overview

Part 3The feasibility study

bull Connection point with Romanian Power System 400kV SS Constanţa Nordbull Connection point with Turkish Power System 400kV SS Alybeikoumly in AsiabullThe cables voltage level 400 kVbullThe capacity 600MWbullThe length about 400 kmbull Losses on the cable-

bull in 600MW transfer ~ 12MWbull in 500MW transfer ~ 9MW

Deliverables

The nominated Designer will submit the following documents

Inception Report Terms of Reference ndash Objectives for procuring the services and

works required for the seabed survey and Geological Study EIA ndash Environmental Impact Assessment Study including

environmental approval Feasibility Study (draft) including the necessary documentation for

approvals and advices Feasibility Study (final) including the approvals and advices Documentation for urbanism certificates in Romania and Turkey Technical Specifications Progress Reports Final Report

Client ConsultantFICHTNER ENGINEERING

Romania

ClientTRANSELECTRICA amp NUCLEARELECTRICA

Romania

Client DesignerVATTENFALL

Sweden

Technical ConsultantTEIAŞ Turkey

Project team members and their responsibilities

Electricity market team

Technical team

Economical institutional and legal

commercial and financial team

- Environment expert- See bead expert- Overhead

transmission line expert

- Electrical substation expert

- Converter expert- HVDC submarine

cable expert- Permits and

approvals expert

- Contract legislation expert

- Price electricity forecasting expert

- Electricity market expert

- Macroeconomic modeling expert

- Financial analyze expert

- Investment analyze expert

- Contract legislation expert

- Romanian amp international legislation expert

Environmental team

Procurement team

- Commercial expert- Overhead

transmission line expert

- Electrical substation expert

- Converter expert- HVDC submarine

cable expert- Environment expert

- Environment expert- Romanian amp

international legislation expert

- Permits and approvals expert

EXPERT TEAMS

The Feasibility Study will

Establish the design parameters capacity and cost estimation for the HVDC link including the most suitable routing based on previous studies and existing data which include geological morphological and seabed structure analyze and initial sea depth survey as well as on its own investigations

Assess the legal and environmental impediments and propose the most appropriate and viable way forward for the Project from an operational and legal framework point of view including also the EIA Study with the afferent approvals in accordance with legalstipulations from both countries and from EU (Transelectrica Nuclearelectrica and TEIAŞ will in this respect support the Designer in this process)

bullContain the necessary documentation for obtaining permits and approvals in accordance with existing legislation in Romania and in Turkey as applicable at the date of project elaboration and corresponding to this phase of the engineeringbullContain the necessary documentation to obtain the urbanism certificatebullAnalyse the financial and economical feasibility of the interconnection project considering private benefits and costs and external effects such as public benefits and costsbullAssess suitable possibilities to finance the ProjectbullPropose a time schedule for project implementation and operationbullHighlight the commercial environmental and technical conditions of direct interconnection of the national grids of Turkey and Romania through a submarine cable across the Black Sea through system studies performed in both countries

Technical Specifications for procurement and execution will include at least a minimalcontent as follows- Scope- Definitions- Standard and recommendations- Functional and technical requirements- Testing and inspections- Execution- Provision of information1048707 Terms of Reference for procuring the services and work required for the seabed survey and geological study will be established based on our experience in similar projects For the feasibility study we will perform a study based on existing materialsdocumentation related to Black Sea seabed survey and geological studies1048707

1 Inception report (within 6 weeks of commencement of the project)2 Terms of Reference for the Seabed survey and Geological Study (The draftissue to be submitted within 6 weeks of commencement of the assignment)3 Plans and Terms of Reference for the Environmental Impact assessment (Tobe submitted as an annex to the first Progress report)4 Environmental Impact Assessment (EIA) incl environmental approvals (The draftissue within 8 months and the final issue within 10 months after the commencementof the assignment)5 Feasibility Study ndash draft incl the necessary documents for approvals and advices(8 months after commencement of the assignment)6 Feasibility Study ndash final incl approvals and advices (10 months aftercommencement of the assignment)7 Documentation for urbanism certificates in Romania and Turkey (10 months aftercommencement of the assignment)8 Technical Specifications (Within 14 months after the commencement of theproject)9 Progress Reports (To be reported quarterly no later than the 10th working day afterthe reporting period)10 Final Report (The final report shall be submitted upon finalisation of the assignement

DELIVERABLES

- Costs for Submarine cables - material and installation- Costs for HVDC land cables andor HVDC OHTLs andor HVAC ndash type overhead electriclines as applicable in Romania ndash material and installations- Costs for HVDC land cables andor HVDC OHTLs andor HVAC ndash type overhead electriclines as applicable in Turkey ndash material and installations- Costs for converter station including the AC connection in Romania- Costs for converter station including the AC connection in Turkey- Telecommunication equipment based on optical fibers- Site costs in Romania- Site costs in Turkey- Engineering project management project control and commissioning- Other investments if any- Interest rates during construction calculated separately for each of the above mentionedparts of the HVDC link- Total investment costs for the HVDC link- Payment for provisional and final expropriations

Investment needs - Investments in the HVDC Link

Investments in the Romanian AC Grid- AC grid investments exclusive the breaker bay for the HVDC link- Telecommunication and remote control equipment- Interest rates calculated separately for each part- Total investments due to the HVDC link in the Romanian AC grid

Investments in the Turkish AC Grid- AC grid investments exclusive the breaker bay for the HVDC link- Telecommunication and remote control equipment- Interest rates during construction calculated separately for each part- Total investments due to the HVDC link in the Turkish AC grid

Investment needs - Investments in the Romanian and Turkish AC grids

ldquoThe price forecast has to be calculated from different perspectivesbull Long term off-take contract 60 and 80 bull Market price for the remaining 40 and 20 bull Sufficient Average Price Level (SAPL)

COMMERCIAL and FINANCIAL ANALYSIS

ldquoBased on the recommended investment and operational plan the Designer shall establish a financial model and analyse the investment over a time horizon of both 20 years operation and 30 years operation The output of the model shall be presented in nominal terms

Tranzit scenarios 1000 MW from Romania to Turkey

Tranzit scenarios 1000 MW from UCTE (PolandampSlovakia) to

Turkey

Tranzit scenarios 1000 MW from Russia (IPSUPS) to Turkey

budget

Tranzit scenarios 1000 MW from Turkey to Romania

Tranzit scenarios1000 MW from Turkey to UCTE (Serbia and

Austria)

Activities to be done in parallel with the feasibilty study

bull Preliminary business model

ndash List of main commercial regulatory and financial hypothesys

ndash Documentation on the business experience of existing commercial interconnectors in EU

ndash Discussions and clarifications with the regulatory authorities

ndash Legal due diligence for the preliminary business model

ndash TOR for the complete business study

bull Exploration and identification of potential private partners

ndash Letters of intent

ndash Develop procedure for the selection of the private investors

bull Full clarifications on TEIAS participation in the project including Turkish applicable legislation

bull Preliminary legal preparations for the project company ( SPV )

Opportunity StudyJoint Position Paper

Feasibility Study( 75 TEL- 25 NE ) Business Study

Joint Position Paper - Final

International Agreement between

Romania and Turkey

Project implementationFinancing contracting supply and instalation

MOU -1MOU -1

MOU -2 MOU -2

Selection of private investors SPV ndash the project company

2005

2008 - 2009

2009

2010

2010 - 2013

022009

First tentative road map

THANK YOU FOR YOUR ATTENTION

e-mail relatiiinvestitoritranselectricaro razvanpurdilatranselectricaro

phone +40213035923fax +40213035880web-site wwwtranselectricaro

  • Regional Transmission Network Development Implications for Trade and Investment
  • Slide 2
  • Slide 4
  • Slide 5
  • Slide 6
  • Slide 7
  • Slide 8
  • Slide 9
  • Slide 11
  • Slide 12
  • Slide 13
  • Slide 14
  • Slide 15
  • Slide 16
  • Slide 17
  • Slide 18
  • Slide 19
  • Slide 20
  • Slide 21
  • Slide 22
  • Slide 23
  • Slide 24
  • Slide 25
  • Slide 27
  • Slide 28
  • Slide 29
  • Slide 30
  • Slide 31
  • Activities to be done in parallel with the feasibilty study
  • Slide 34
  • Slide 35
Page 4: R EGIONAL T RANSMISSION N ETWORK D EVELOPMENT : I MPLICATIONS FOR T RADE AND I NVESTMENT R EGIONAL T RANSMISSION N ETWORK D EVELOPMENT : I MPLICATIONS.

HVDC is an ldquointelligent linkrdquo The power flow can be controlled and changed very quickly practically independently from frequency at the terminal busses voltage or power angle at the terminal busses like in HVAC transmission

Due to the inherent properties of the electronic equipment which forms the converter bridges the direction of the transmitted power may be also changed very quickly

The HVDC transmission has the major advantage of flexibility inpower exchange in comparison with HVAC Moreover in case oftransmission of bulk electrical energy over long distances (more than 50 km) by submarine cable the only applicable technology is theHVDC transmission

Advantages for HVDC transmission

In a HVDC system the electricity is

- Taken from a 3-phase AC network- Converted to DC in a converter station- Transmitted by DC OHL or cable (underground or sub sea)- Converted back to AC in another converter station- Injected into AC network

HVDC transmission ndash principles and characteristics

Controllable ndash power injected where neededsupplemental control frequency control- Bypass congested circuits ndash no inadvertent flow- Higher power fewer linesno intermediate SS needed- Lower losses- Facilitates integration of remotediverse resources with less impacton existing grid- Low expensive transmission line- Reactive power demand limited toterminals independent of distances- Narrower ROW no EMF constraints- No limit to underground or submarinecable length

Cable laying

The scope of this project is to install a submarine cable between the Romanian and Turkish TSOrsquos Transelectrica and TEIAS respectively

Business concept commercial interconnector separately regulated

The Project is in line with the policies of both Romanian and Turkish Governments and fits well into the EU Green Paper on Energy and EU strategy of Priority Network Projects The project also brings a significant contribution and stability to the regional electricity market in South-East Europe

The Project is ldquoon goingrdquo in the Feasibility Study phase

Project scope

Short history of the project

bull 2004 ndash April ndash energy cooperation protocol between Romania and Turkey at ministries level

ndash The first mentioning of the cable project

bull 2005 - June ndash MOU between Transelectrica and TEIAS for the HVDC link project

ndash Main scope to prepare the oportunity study by a joint project team

bull 2006 ndash November - JPP ( joint position paper ) between Transelectrica and TEIAS

ndash Approval of the opportunity study

ndash Decision to continue the study at feasibility study level

bull 2007 ndash first attempt to launch the feasibility study with minority financing of private investors ( 50 Swedish grant available )

ndash No success replacement of the private investor with Nuclearelectrica

bull 2008 ndash first tender for the FS in new financing conditions

ndash Incompatibility of the grant with open tender requirements

bull 2009 ndash secont tender contract signature in June

ELEMENT 01

TELConstanţa

NordSubstation

ELEMENT 02TEL

Converter station and

link to Constanţa

Nord substation

ELEMENT03

TELUnderground cable between

converter station and HVDC cable connection

ELEMENT04

HVDC

cable

ELEMENT05

TEIASUnderground cable between

converter station and HVDC cable connection

ELEMENT 06

TEIASConverter

station and link to

Alibeykoumly substation

ROMANIA

BLACK SEA

ELEMENT 07

TEIASAlibeykoumly Substation

TURKEY

Romania ndash Turkey HVDC interconector overview

Part 3The feasibility study

bull Connection point with Romanian Power System 400kV SS Constanţa Nordbull Connection point with Turkish Power System 400kV SS Alybeikoumly in AsiabullThe cables voltage level 400 kVbullThe capacity 600MWbullThe length about 400 kmbull Losses on the cable-

bull in 600MW transfer ~ 12MWbull in 500MW transfer ~ 9MW

Deliverables

The nominated Designer will submit the following documents

Inception Report Terms of Reference ndash Objectives for procuring the services and

works required for the seabed survey and Geological Study EIA ndash Environmental Impact Assessment Study including

environmental approval Feasibility Study (draft) including the necessary documentation for

approvals and advices Feasibility Study (final) including the approvals and advices Documentation for urbanism certificates in Romania and Turkey Technical Specifications Progress Reports Final Report

Client ConsultantFICHTNER ENGINEERING

Romania

ClientTRANSELECTRICA amp NUCLEARELECTRICA

Romania

Client DesignerVATTENFALL

Sweden

Technical ConsultantTEIAŞ Turkey

Project team members and their responsibilities

Electricity market team

Technical team

Economical institutional and legal

commercial and financial team

- Environment expert- See bead expert- Overhead

transmission line expert

- Electrical substation expert

- Converter expert- HVDC submarine

cable expert- Permits and

approvals expert

- Contract legislation expert

- Price electricity forecasting expert

- Electricity market expert

- Macroeconomic modeling expert

- Financial analyze expert

- Investment analyze expert

- Contract legislation expert

- Romanian amp international legislation expert

Environmental team

Procurement team

- Commercial expert- Overhead

transmission line expert

- Electrical substation expert

- Converter expert- HVDC submarine

cable expert- Environment expert

- Environment expert- Romanian amp

international legislation expert

- Permits and approvals expert

EXPERT TEAMS

The Feasibility Study will

Establish the design parameters capacity and cost estimation for the HVDC link including the most suitable routing based on previous studies and existing data which include geological morphological and seabed structure analyze and initial sea depth survey as well as on its own investigations

Assess the legal and environmental impediments and propose the most appropriate and viable way forward for the Project from an operational and legal framework point of view including also the EIA Study with the afferent approvals in accordance with legalstipulations from both countries and from EU (Transelectrica Nuclearelectrica and TEIAŞ will in this respect support the Designer in this process)

bullContain the necessary documentation for obtaining permits and approvals in accordance with existing legislation in Romania and in Turkey as applicable at the date of project elaboration and corresponding to this phase of the engineeringbullContain the necessary documentation to obtain the urbanism certificatebullAnalyse the financial and economical feasibility of the interconnection project considering private benefits and costs and external effects such as public benefits and costsbullAssess suitable possibilities to finance the ProjectbullPropose a time schedule for project implementation and operationbullHighlight the commercial environmental and technical conditions of direct interconnection of the national grids of Turkey and Romania through a submarine cable across the Black Sea through system studies performed in both countries

Technical Specifications for procurement and execution will include at least a minimalcontent as follows- Scope- Definitions- Standard and recommendations- Functional and technical requirements- Testing and inspections- Execution- Provision of information1048707 Terms of Reference for procuring the services and work required for the seabed survey and geological study will be established based on our experience in similar projects For the feasibility study we will perform a study based on existing materialsdocumentation related to Black Sea seabed survey and geological studies1048707

1 Inception report (within 6 weeks of commencement of the project)2 Terms of Reference for the Seabed survey and Geological Study (The draftissue to be submitted within 6 weeks of commencement of the assignment)3 Plans and Terms of Reference for the Environmental Impact assessment (Tobe submitted as an annex to the first Progress report)4 Environmental Impact Assessment (EIA) incl environmental approvals (The draftissue within 8 months and the final issue within 10 months after the commencementof the assignment)5 Feasibility Study ndash draft incl the necessary documents for approvals and advices(8 months after commencement of the assignment)6 Feasibility Study ndash final incl approvals and advices (10 months aftercommencement of the assignment)7 Documentation for urbanism certificates in Romania and Turkey (10 months aftercommencement of the assignment)8 Technical Specifications (Within 14 months after the commencement of theproject)9 Progress Reports (To be reported quarterly no later than the 10th working day afterthe reporting period)10 Final Report (The final report shall be submitted upon finalisation of the assignement

DELIVERABLES

- Costs for Submarine cables - material and installation- Costs for HVDC land cables andor HVDC OHTLs andor HVAC ndash type overhead electriclines as applicable in Romania ndash material and installations- Costs for HVDC land cables andor HVDC OHTLs andor HVAC ndash type overhead electriclines as applicable in Turkey ndash material and installations- Costs for converter station including the AC connection in Romania- Costs for converter station including the AC connection in Turkey- Telecommunication equipment based on optical fibers- Site costs in Romania- Site costs in Turkey- Engineering project management project control and commissioning- Other investments if any- Interest rates during construction calculated separately for each of the above mentionedparts of the HVDC link- Total investment costs for the HVDC link- Payment for provisional and final expropriations

Investment needs - Investments in the HVDC Link

Investments in the Romanian AC Grid- AC grid investments exclusive the breaker bay for the HVDC link- Telecommunication and remote control equipment- Interest rates calculated separately for each part- Total investments due to the HVDC link in the Romanian AC grid

Investments in the Turkish AC Grid- AC grid investments exclusive the breaker bay for the HVDC link- Telecommunication and remote control equipment- Interest rates during construction calculated separately for each part- Total investments due to the HVDC link in the Turkish AC grid

Investment needs - Investments in the Romanian and Turkish AC grids

ldquoThe price forecast has to be calculated from different perspectivesbull Long term off-take contract 60 and 80 bull Market price for the remaining 40 and 20 bull Sufficient Average Price Level (SAPL)

COMMERCIAL and FINANCIAL ANALYSIS

ldquoBased on the recommended investment and operational plan the Designer shall establish a financial model and analyse the investment over a time horizon of both 20 years operation and 30 years operation The output of the model shall be presented in nominal terms

Tranzit scenarios 1000 MW from Romania to Turkey

Tranzit scenarios 1000 MW from UCTE (PolandampSlovakia) to

Turkey

Tranzit scenarios 1000 MW from Russia (IPSUPS) to Turkey

budget

Tranzit scenarios 1000 MW from Turkey to Romania

Tranzit scenarios1000 MW from Turkey to UCTE (Serbia and

Austria)

Activities to be done in parallel with the feasibilty study

bull Preliminary business model

ndash List of main commercial regulatory and financial hypothesys

ndash Documentation on the business experience of existing commercial interconnectors in EU

ndash Discussions and clarifications with the regulatory authorities

ndash Legal due diligence for the preliminary business model

ndash TOR for the complete business study

bull Exploration and identification of potential private partners

ndash Letters of intent

ndash Develop procedure for the selection of the private investors

bull Full clarifications on TEIAS participation in the project including Turkish applicable legislation

bull Preliminary legal preparations for the project company ( SPV )

Opportunity StudyJoint Position Paper

Feasibility Study( 75 TEL- 25 NE ) Business Study

Joint Position Paper - Final

International Agreement between

Romania and Turkey

Project implementationFinancing contracting supply and instalation

MOU -1MOU -1

MOU -2 MOU -2

Selection of private investors SPV ndash the project company

2005

2008 - 2009

2009

2010

2010 - 2013

022009

First tentative road map

THANK YOU FOR YOUR ATTENTION

e-mail relatiiinvestitoritranselectricaro razvanpurdilatranselectricaro

phone +40213035923fax +40213035880web-site wwwtranselectricaro

  • Regional Transmission Network Development Implications for Trade and Investment
  • Slide 2
  • Slide 4
  • Slide 5
  • Slide 6
  • Slide 7
  • Slide 8
  • Slide 9
  • Slide 11
  • Slide 12
  • Slide 13
  • Slide 14
  • Slide 15
  • Slide 16
  • Slide 17
  • Slide 18
  • Slide 19
  • Slide 20
  • Slide 21
  • Slide 22
  • Slide 23
  • Slide 24
  • Slide 25
  • Slide 27
  • Slide 28
  • Slide 29
  • Slide 30
  • Slide 31
  • Activities to be done in parallel with the feasibilty study
  • Slide 34
  • Slide 35
Page 5: R EGIONAL T RANSMISSION N ETWORK D EVELOPMENT : I MPLICATIONS FOR T RADE AND I NVESTMENT R EGIONAL T RANSMISSION N ETWORK D EVELOPMENT : I MPLICATIONS.

In a HVDC system the electricity is

- Taken from a 3-phase AC network- Converted to DC in a converter station- Transmitted by DC OHL or cable (underground or sub sea)- Converted back to AC in another converter station- Injected into AC network

HVDC transmission ndash principles and characteristics

Controllable ndash power injected where neededsupplemental control frequency control- Bypass congested circuits ndash no inadvertent flow- Higher power fewer linesno intermediate SS needed- Lower losses- Facilitates integration of remotediverse resources with less impacton existing grid- Low expensive transmission line- Reactive power demand limited toterminals independent of distances- Narrower ROW no EMF constraints- No limit to underground or submarinecable length

Cable laying

The scope of this project is to install a submarine cable between the Romanian and Turkish TSOrsquos Transelectrica and TEIAS respectively

Business concept commercial interconnector separately regulated

The Project is in line with the policies of both Romanian and Turkish Governments and fits well into the EU Green Paper on Energy and EU strategy of Priority Network Projects The project also brings a significant contribution and stability to the regional electricity market in South-East Europe

The Project is ldquoon goingrdquo in the Feasibility Study phase

Project scope

Short history of the project

bull 2004 ndash April ndash energy cooperation protocol between Romania and Turkey at ministries level

ndash The first mentioning of the cable project

bull 2005 - June ndash MOU between Transelectrica and TEIAS for the HVDC link project

ndash Main scope to prepare the oportunity study by a joint project team

bull 2006 ndash November - JPP ( joint position paper ) between Transelectrica and TEIAS

ndash Approval of the opportunity study

ndash Decision to continue the study at feasibility study level

bull 2007 ndash first attempt to launch the feasibility study with minority financing of private investors ( 50 Swedish grant available )

ndash No success replacement of the private investor with Nuclearelectrica

bull 2008 ndash first tender for the FS in new financing conditions

ndash Incompatibility of the grant with open tender requirements

bull 2009 ndash secont tender contract signature in June

ELEMENT 01

TELConstanţa

NordSubstation

ELEMENT 02TEL

Converter station and

link to Constanţa

Nord substation

ELEMENT03

TELUnderground cable between

converter station and HVDC cable connection

ELEMENT04

HVDC

cable

ELEMENT05

TEIASUnderground cable between

converter station and HVDC cable connection

ELEMENT 06

TEIASConverter

station and link to

Alibeykoumly substation

ROMANIA

BLACK SEA

ELEMENT 07

TEIASAlibeykoumly Substation

TURKEY

Romania ndash Turkey HVDC interconector overview

Part 3The feasibility study

bull Connection point with Romanian Power System 400kV SS Constanţa Nordbull Connection point with Turkish Power System 400kV SS Alybeikoumly in AsiabullThe cables voltage level 400 kVbullThe capacity 600MWbullThe length about 400 kmbull Losses on the cable-

bull in 600MW transfer ~ 12MWbull in 500MW transfer ~ 9MW

Deliverables

The nominated Designer will submit the following documents

Inception Report Terms of Reference ndash Objectives for procuring the services and

works required for the seabed survey and Geological Study EIA ndash Environmental Impact Assessment Study including

environmental approval Feasibility Study (draft) including the necessary documentation for

approvals and advices Feasibility Study (final) including the approvals and advices Documentation for urbanism certificates in Romania and Turkey Technical Specifications Progress Reports Final Report

Client ConsultantFICHTNER ENGINEERING

Romania

ClientTRANSELECTRICA amp NUCLEARELECTRICA

Romania

Client DesignerVATTENFALL

Sweden

Technical ConsultantTEIAŞ Turkey

Project team members and their responsibilities

Electricity market team

Technical team

Economical institutional and legal

commercial and financial team

- Environment expert- See bead expert- Overhead

transmission line expert

- Electrical substation expert

- Converter expert- HVDC submarine

cable expert- Permits and

approvals expert

- Contract legislation expert

- Price electricity forecasting expert

- Electricity market expert

- Macroeconomic modeling expert

- Financial analyze expert

- Investment analyze expert

- Contract legislation expert

- Romanian amp international legislation expert

Environmental team

Procurement team

- Commercial expert- Overhead

transmission line expert

- Electrical substation expert

- Converter expert- HVDC submarine

cable expert- Environment expert

- Environment expert- Romanian amp

international legislation expert

- Permits and approvals expert

EXPERT TEAMS

The Feasibility Study will

Establish the design parameters capacity and cost estimation for the HVDC link including the most suitable routing based on previous studies and existing data which include geological morphological and seabed structure analyze and initial sea depth survey as well as on its own investigations

Assess the legal and environmental impediments and propose the most appropriate and viable way forward for the Project from an operational and legal framework point of view including also the EIA Study with the afferent approvals in accordance with legalstipulations from both countries and from EU (Transelectrica Nuclearelectrica and TEIAŞ will in this respect support the Designer in this process)

bullContain the necessary documentation for obtaining permits and approvals in accordance with existing legislation in Romania and in Turkey as applicable at the date of project elaboration and corresponding to this phase of the engineeringbullContain the necessary documentation to obtain the urbanism certificatebullAnalyse the financial and economical feasibility of the interconnection project considering private benefits and costs and external effects such as public benefits and costsbullAssess suitable possibilities to finance the ProjectbullPropose a time schedule for project implementation and operationbullHighlight the commercial environmental and technical conditions of direct interconnection of the national grids of Turkey and Romania through a submarine cable across the Black Sea through system studies performed in both countries

Technical Specifications for procurement and execution will include at least a minimalcontent as follows- Scope- Definitions- Standard and recommendations- Functional and technical requirements- Testing and inspections- Execution- Provision of information1048707 Terms of Reference for procuring the services and work required for the seabed survey and geological study will be established based on our experience in similar projects For the feasibility study we will perform a study based on existing materialsdocumentation related to Black Sea seabed survey and geological studies1048707

1 Inception report (within 6 weeks of commencement of the project)2 Terms of Reference for the Seabed survey and Geological Study (The draftissue to be submitted within 6 weeks of commencement of the assignment)3 Plans and Terms of Reference for the Environmental Impact assessment (Tobe submitted as an annex to the first Progress report)4 Environmental Impact Assessment (EIA) incl environmental approvals (The draftissue within 8 months and the final issue within 10 months after the commencementof the assignment)5 Feasibility Study ndash draft incl the necessary documents for approvals and advices(8 months after commencement of the assignment)6 Feasibility Study ndash final incl approvals and advices (10 months aftercommencement of the assignment)7 Documentation for urbanism certificates in Romania and Turkey (10 months aftercommencement of the assignment)8 Technical Specifications (Within 14 months after the commencement of theproject)9 Progress Reports (To be reported quarterly no later than the 10th working day afterthe reporting period)10 Final Report (The final report shall be submitted upon finalisation of the assignement

DELIVERABLES

- Costs for Submarine cables - material and installation- Costs for HVDC land cables andor HVDC OHTLs andor HVAC ndash type overhead electriclines as applicable in Romania ndash material and installations- Costs for HVDC land cables andor HVDC OHTLs andor HVAC ndash type overhead electriclines as applicable in Turkey ndash material and installations- Costs for converter station including the AC connection in Romania- Costs for converter station including the AC connection in Turkey- Telecommunication equipment based on optical fibers- Site costs in Romania- Site costs in Turkey- Engineering project management project control and commissioning- Other investments if any- Interest rates during construction calculated separately for each of the above mentionedparts of the HVDC link- Total investment costs for the HVDC link- Payment for provisional and final expropriations

Investment needs - Investments in the HVDC Link

Investments in the Romanian AC Grid- AC grid investments exclusive the breaker bay for the HVDC link- Telecommunication and remote control equipment- Interest rates calculated separately for each part- Total investments due to the HVDC link in the Romanian AC grid

Investments in the Turkish AC Grid- AC grid investments exclusive the breaker bay for the HVDC link- Telecommunication and remote control equipment- Interest rates during construction calculated separately for each part- Total investments due to the HVDC link in the Turkish AC grid

Investment needs - Investments in the Romanian and Turkish AC grids

ldquoThe price forecast has to be calculated from different perspectivesbull Long term off-take contract 60 and 80 bull Market price for the remaining 40 and 20 bull Sufficient Average Price Level (SAPL)

COMMERCIAL and FINANCIAL ANALYSIS

ldquoBased on the recommended investment and operational plan the Designer shall establish a financial model and analyse the investment over a time horizon of both 20 years operation and 30 years operation The output of the model shall be presented in nominal terms

Tranzit scenarios 1000 MW from Romania to Turkey

Tranzit scenarios 1000 MW from UCTE (PolandampSlovakia) to

Turkey

Tranzit scenarios 1000 MW from Russia (IPSUPS) to Turkey

budget

Tranzit scenarios 1000 MW from Turkey to Romania

Tranzit scenarios1000 MW from Turkey to UCTE (Serbia and

Austria)

Activities to be done in parallel with the feasibilty study

bull Preliminary business model

ndash List of main commercial regulatory and financial hypothesys

ndash Documentation on the business experience of existing commercial interconnectors in EU

ndash Discussions and clarifications with the regulatory authorities

ndash Legal due diligence for the preliminary business model

ndash TOR for the complete business study

bull Exploration and identification of potential private partners

ndash Letters of intent

ndash Develop procedure for the selection of the private investors

bull Full clarifications on TEIAS participation in the project including Turkish applicable legislation

bull Preliminary legal preparations for the project company ( SPV )

Opportunity StudyJoint Position Paper

Feasibility Study( 75 TEL- 25 NE ) Business Study

Joint Position Paper - Final

International Agreement between

Romania and Turkey

Project implementationFinancing contracting supply and instalation

MOU -1MOU -1

MOU -2 MOU -2

Selection of private investors SPV ndash the project company

2005

2008 - 2009

2009

2010

2010 - 2013

022009

First tentative road map

THANK YOU FOR YOUR ATTENTION

e-mail relatiiinvestitoritranselectricaro razvanpurdilatranselectricaro

phone +40213035923fax +40213035880web-site wwwtranselectricaro

  • Regional Transmission Network Development Implications for Trade and Investment
  • Slide 2
  • Slide 4
  • Slide 5
  • Slide 6
  • Slide 7
  • Slide 8
  • Slide 9
  • Slide 11
  • Slide 12
  • Slide 13
  • Slide 14
  • Slide 15
  • Slide 16
  • Slide 17
  • Slide 18
  • Slide 19
  • Slide 20
  • Slide 21
  • Slide 22
  • Slide 23
  • Slide 24
  • Slide 25
  • Slide 27
  • Slide 28
  • Slide 29
  • Slide 30
  • Slide 31
  • Activities to be done in parallel with the feasibilty study
  • Slide 34
  • Slide 35
Page 6: R EGIONAL T RANSMISSION N ETWORK D EVELOPMENT : I MPLICATIONS FOR T RADE AND I NVESTMENT R EGIONAL T RANSMISSION N ETWORK D EVELOPMENT : I MPLICATIONS.

Cable laying

The scope of this project is to install a submarine cable between the Romanian and Turkish TSOrsquos Transelectrica and TEIAS respectively

Business concept commercial interconnector separately regulated

The Project is in line with the policies of both Romanian and Turkish Governments and fits well into the EU Green Paper on Energy and EU strategy of Priority Network Projects The project also brings a significant contribution and stability to the regional electricity market in South-East Europe

The Project is ldquoon goingrdquo in the Feasibility Study phase

Project scope

Short history of the project

bull 2004 ndash April ndash energy cooperation protocol between Romania and Turkey at ministries level

ndash The first mentioning of the cable project

bull 2005 - June ndash MOU between Transelectrica and TEIAS for the HVDC link project

ndash Main scope to prepare the oportunity study by a joint project team

bull 2006 ndash November - JPP ( joint position paper ) between Transelectrica and TEIAS

ndash Approval of the opportunity study

ndash Decision to continue the study at feasibility study level

bull 2007 ndash first attempt to launch the feasibility study with minority financing of private investors ( 50 Swedish grant available )

ndash No success replacement of the private investor with Nuclearelectrica

bull 2008 ndash first tender for the FS in new financing conditions

ndash Incompatibility of the grant with open tender requirements

bull 2009 ndash secont tender contract signature in June

ELEMENT 01

TELConstanţa

NordSubstation

ELEMENT 02TEL

Converter station and

link to Constanţa

Nord substation

ELEMENT03

TELUnderground cable between

converter station and HVDC cable connection

ELEMENT04

HVDC

cable

ELEMENT05

TEIASUnderground cable between

converter station and HVDC cable connection

ELEMENT 06

TEIASConverter

station and link to

Alibeykoumly substation

ROMANIA

BLACK SEA

ELEMENT 07

TEIASAlibeykoumly Substation

TURKEY

Romania ndash Turkey HVDC interconector overview

Part 3The feasibility study

bull Connection point with Romanian Power System 400kV SS Constanţa Nordbull Connection point with Turkish Power System 400kV SS Alybeikoumly in AsiabullThe cables voltage level 400 kVbullThe capacity 600MWbullThe length about 400 kmbull Losses on the cable-

bull in 600MW transfer ~ 12MWbull in 500MW transfer ~ 9MW

Deliverables

The nominated Designer will submit the following documents

Inception Report Terms of Reference ndash Objectives for procuring the services and

works required for the seabed survey and Geological Study EIA ndash Environmental Impact Assessment Study including

environmental approval Feasibility Study (draft) including the necessary documentation for

approvals and advices Feasibility Study (final) including the approvals and advices Documentation for urbanism certificates in Romania and Turkey Technical Specifications Progress Reports Final Report

Client ConsultantFICHTNER ENGINEERING

Romania

ClientTRANSELECTRICA amp NUCLEARELECTRICA

Romania

Client DesignerVATTENFALL

Sweden

Technical ConsultantTEIAŞ Turkey

Project team members and their responsibilities

Electricity market team

Technical team

Economical institutional and legal

commercial and financial team

- Environment expert- See bead expert- Overhead

transmission line expert

- Electrical substation expert

- Converter expert- HVDC submarine

cable expert- Permits and

approvals expert

- Contract legislation expert

- Price electricity forecasting expert

- Electricity market expert

- Macroeconomic modeling expert

- Financial analyze expert

- Investment analyze expert

- Contract legislation expert

- Romanian amp international legislation expert

Environmental team

Procurement team

- Commercial expert- Overhead

transmission line expert

- Electrical substation expert

- Converter expert- HVDC submarine

cable expert- Environment expert

- Environment expert- Romanian amp

international legislation expert

- Permits and approvals expert

EXPERT TEAMS

The Feasibility Study will

Establish the design parameters capacity and cost estimation for the HVDC link including the most suitable routing based on previous studies and existing data which include geological morphological and seabed structure analyze and initial sea depth survey as well as on its own investigations

Assess the legal and environmental impediments and propose the most appropriate and viable way forward for the Project from an operational and legal framework point of view including also the EIA Study with the afferent approvals in accordance with legalstipulations from both countries and from EU (Transelectrica Nuclearelectrica and TEIAŞ will in this respect support the Designer in this process)

bullContain the necessary documentation for obtaining permits and approvals in accordance with existing legislation in Romania and in Turkey as applicable at the date of project elaboration and corresponding to this phase of the engineeringbullContain the necessary documentation to obtain the urbanism certificatebullAnalyse the financial and economical feasibility of the interconnection project considering private benefits and costs and external effects such as public benefits and costsbullAssess suitable possibilities to finance the ProjectbullPropose a time schedule for project implementation and operationbullHighlight the commercial environmental and technical conditions of direct interconnection of the national grids of Turkey and Romania through a submarine cable across the Black Sea through system studies performed in both countries

Technical Specifications for procurement and execution will include at least a minimalcontent as follows- Scope- Definitions- Standard and recommendations- Functional and technical requirements- Testing and inspections- Execution- Provision of information1048707 Terms of Reference for procuring the services and work required for the seabed survey and geological study will be established based on our experience in similar projects For the feasibility study we will perform a study based on existing materialsdocumentation related to Black Sea seabed survey and geological studies1048707

1 Inception report (within 6 weeks of commencement of the project)2 Terms of Reference for the Seabed survey and Geological Study (The draftissue to be submitted within 6 weeks of commencement of the assignment)3 Plans and Terms of Reference for the Environmental Impact assessment (Tobe submitted as an annex to the first Progress report)4 Environmental Impact Assessment (EIA) incl environmental approvals (The draftissue within 8 months and the final issue within 10 months after the commencementof the assignment)5 Feasibility Study ndash draft incl the necessary documents for approvals and advices(8 months after commencement of the assignment)6 Feasibility Study ndash final incl approvals and advices (10 months aftercommencement of the assignment)7 Documentation for urbanism certificates in Romania and Turkey (10 months aftercommencement of the assignment)8 Technical Specifications (Within 14 months after the commencement of theproject)9 Progress Reports (To be reported quarterly no later than the 10th working day afterthe reporting period)10 Final Report (The final report shall be submitted upon finalisation of the assignement

DELIVERABLES

- Costs for Submarine cables - material and installation- Costs for HVDC land cables andor HVDC OHTLs andor HVAC ndash type overhead electriclines as applicable in Romania ndash material and installations- Costs for HVDC land cables andor HVDC OHTLs andor HVAC ndash type overhead electriclines as applicable in Turkey ndash material and installations- Costs for converter station including the AC connection in Romania- Costs for converter station including the AC connection in Turkey- Telecommunication equipment based on optical fibers- Site costs in Romania- Site costs in Turkey- Engineering project management project control and commissioning- Other investments if any- Interest rates during construction calculated separately for each of the above mentionedparts of the HVDC link- Total investment costs for the HVDC link- Payment for provisional and final expropriations

Investment needs - Investments in the HVDC Link

Investments in the Romanian AC Grid- AC grid investments exclusive the breaker bay for the HVDC link- Telecommunication and remote control equipment- Interest rates calculated separately for each part- Total investments due to the HVDC link in the Romanian AC grid

Investments in the Turkish AC Grid- AC grid investments exclusive the breaker bay for the HVDC link- Telecommunication and remote control equipment- Interest rates during construction calculated separately for each part- Total investments due to the HVDC link in the Turkish AC grid

Investment needs - Investments in the Romanian and Turkish AC grids

ldquoThe price forecast has to be calculated from different perspectivesbull Long term off-take contract 60 and 80 bull Market price for the remaining 40 and 20 bull Sufficient Average Price Level (SAPL)

COMMERCIAL and FINANCIAL ANALYSIS

ldquoBased on the recommended investment and operational plan the Designer shall establish a financial model and analyse the investment over a time horizon of both 20 years operation and 30 years operation The output of the model shall be presented in nominal terms

Tranzit scenarios 1000 MW from Romania to Turkey

Tranzit scenarios 1000 MW from UCTE (PolandampSlovakia) to

Turkey

Tranzit scenarios 1000 MW from Russia (IPSUPS) to Turkey

budget

Tranzit scenarios 1000 MW from Turkey to Romania

Tranzit scenarios1000 MW from Turkey to UCTE (Serbia and

Austria)

Activities to be done in parallel with the feasibilty study

bull Preliminary business model

ndash List of main commercial regulatory and financial hypothesys

ndash Documentation on the business experience of existing commercial interconnectors in EU

ndash Discussions and clarifications with the regulatory authorities

ndash Legal due diligence for the preliminary business model

ndash TOR for the complete business study

bull Exploration and identification of potential private partners

ndash Letters of intent

ndash Develop procedure for the selection of the private investors

bull Full clarifications on TEIAS participation in the project including Turkish applicable legislation

bull Preliminary legal preparations for the project company ( SPV )

Opportunity StudyJoint Position Paper

Feasibility Study( 75 TEL- 25 NE ) Business Study

Joint Position Paper - Final

International Agreement between

Romania and Turkey

Project implementationFinancing contracting supply and instalation

MOU -1MOU -1

MOU -2 MOU -2

Selection of private investors SPV ndash the project company

2005

2008 - 2009

2009

2010

2010 - 2013

022009

First tentative road map

THANK YOU FOR YOUR ATTENTION

e-mail relatiiinvestitoritranselectricaro razvanpurdilatranselectricaro

phone +40213035923fax +40213035880web-site wwwtranselectricaro

  • Regional Transmission Network Development Implications for Trade and Investment
  • Slide 2
  • Slide 4
  • Slide 5
  • Slide 6
  • Slide 7
  • Slide 8
  • Slide 9
  • Slide 11
  • Slide 12
  • Slide 13
  • Slide 14
  • Slide 15
  • Slide 16
  • Slide 17
  • Slide 18
  • Slide 19
  • Slide 20
  • Slide 21
  • Slide 22
  • Slide 23
  • Slide 24
  • Slide 25
  • Slide 27
  • Slide 28
  • Slide 29
  • Slide 30
  • Slide 31
  • Activities to be done in parallel with the feasibilty study
  • Slide 34
  • Slide 35
Page 7: R EGIONAL T RANSMISSION N ETWORK D EVELOPMENT : I MPLICATIONS FOR T RADE AND I NVESTMENT R EGIONAL T RANSMISSION N ETWORK D EVELOPMENT : I MPLICATIONS.

The scope of this project is to install a submarine cable between the Romanian and Turkish TSOrsquos Transelectrica and TEIAS respectively

Business concept commercial interconnector separately regulated

The Project is in line with the policies of both Romanian and Turkish Governments and fits well into the EU Green Paper on Energy and EU strategy of Priority Network Projects The project also brings a significant contribution and stability to the regional electricity market in South-East Europe

The Project is ldquoon goingrdquo in the Feasibility Study phase

Project scope

Short history of the project

bull 2004 ndash April ndash energy cooperation protocol between Romania and Turkey at ministries level

ndash The first mentioning of the cable project

bull 2005 - June ndash MOU between Transelectrica and TEIAS for the HVDC link project

ndash Main scope to prepare the oportunity study by a joint project team

bull 2006 ndash November - JPP ( joint position paper ) between Transelectrica and TEIAS

ndash Approval of the opportunity study

ndash Decision to continue the study at feasibility study level

bull 2007 ndash first attempt to launch the feasibility study with minority financing of private investors ( 50 Swedish grant available )

ndash No success replacement of the private investor with Nuclearelectrica

bull 2008 ndash first tender for the FS in new financing conditions

ndash Incompatibility of the grant with open tender requirements

bull 2009 ndash secont tender contract signature in June

ELEMENT 01

TELConstanţa

NordSubstation

ELEMENT 02TEL

Converter station and

link to Constanţa

Nord substation

ELEMENT03

TELUnderground cable between

converter station and HVDC cable connection

ELEMENT04

HVDC

cable

ELEMENT05

TEIASUnderground cable between

converter station and HVDC cable connection

ELEMENT 06

TEIASConverter

station and link to

Alibeykoumly substation

ROMANIA

BLACK SEA

ELEMENT 07

TEIASAlibeykoumly Substation

TURKEY

Romania ndash Turkey HVDC interconector overview

Part 3The feasibility study

bull Connection point with Romanian Power System 400kV SS Constanţa Nordbull Connection point with Turkish Power System 400kV SS Alybeikoumly in AsiabullThe cables voltage level 400 kVbullThe capacity 600MWbullThe length about 400 kmbull Losses on the cable-

bull in 600MW transfer ~ 12MWbull in 500MW transfer ~ 9MW

Deliverables

The nominated Designer will submit the following documents

Inception Report Terms of Reference ndash Objectives for procuring the services and

works required for the seabed survey and Geological Study EIA ndash Environmental Impact Assessment Study including

environmental approval Feasibility Study (draft) including the necessary documentation for

approvals and advices Feasibility Study (final) including the approvals and advices Documentation for urbanism certificates in Romania and Turkey Technical Specifications Progress Reports Final Report

Client ConsultantFICHTNER ENGINEERING

Romania

ClientTRANSELECTRICA amp NUCLEARELECTRICA

Romania

Client DesignerVATTENFALL

Sweden

Technical ConsultantTEIAŞ Turkey

Project team members and their responsibilities

Electricity market team

Technical team

Economical institutional and legal

commercial and financial team

- Environment expert- See bead expert- Overhead

transmission line expert

- Electrical substation expert

- Converter expert- HVDC submarine

cable expert- Permits and

approvals expert

- Contract legislation expert

- Price electricity forecasting expert

- Electricity market expert

- Macroeconomic modeling expert

- Financial analyze expert

- Investment analyze expert

- Contract legislation expert

- Romanian amp international legislation expert

Environmental team

Procurement team

- Commercial expert- Overhead

transmission line expert

- Electrical substation expert

- Converter expert- HVDC submarine

cable expert- Environment expert

- Environment expert- Romanian amp

international legislation expert

- Permits and approvals expert

EXPERT TEAMS

The Feasibility Study will

Establish the design parameters capacity and cost estimation for the HVDC link including the most suitable routing based on previous studies and existing data which include geological morphological and seabed structure analyze and initial sea depth survey as well as on its own investigations

Assess the legal and environmental impediments and propose the most appropriate and viable way forward for the Project from an operational and legal framework point of view including also the EIA Study with the afferent approvals in accordance with legalstipulations from both countries and from EU (Transelectrica Nuclearelectrica and TEIAŞ will in this respect support the Designer in this process)

bullContain the necessary documentation for obtaining permits and approvals in accordance with existing legislation in Romania and in Turkey as applicable at the date of project elaboration and corresponding to this phase of the engineeringbullContain the necessary documentation to obtain the urbanism certificatebullAnalyse the financial and economical feasibility of the interconnection project considering private benefits and costs and external effects such as public benefits and costsbullAssess suitable possibilities to finance the ProjectbullPropose a time schedule for project implementation and operationbullHighlight the commercial environmental and technical conditions of direct interconnection of the national grids of Turkey and Romania through a submarine cable across the Black Sea through system studies performed in both countries

Technical Specifications for procurement and execution will include at least a minimalcontent as follows- Scope- Definitions- Standard and recommendations- Functional and technical requirements- Testing and inspections- Execution- Provision of information1048707 Terms of Reference for procuring the services and work required for the seabed survey and geological study will be established based on our experience in similar projects For the feasibility study we will perform a study based on existing materialsdocumentation related to Black Sea seabed survey and geological studies1048707

1 Inception report (within 6 weeks of commencement of the project)2 Terms of Reference for the Seabed survey and Geological Study (The draftissue to be submitted within 6 weeks of commencement of the assignment)3 Plans and Terms of Reference for the Environmental Impact assessment (Tobe submitted as an annex to the first Progress report)4 Environmental Impact Assessment (EIA) incl environmental approvals (The draftissue within 8 months and the final issue within 10 months after the commencementof the assignment)5 Feasibility Study ndash draft incl the necessary documents for approvals and advices(8 months after commencement of the assignment)6 Feasibility Study ndash final incl approvals and advices (10 months aftercommencement of the assignment)7 Documentation for urbanism certificates in Romania and Turkey (10 months aftercommencement of the assignment)8 Technical Specifications (Within 14 months after the commencement of theproject)9 Progress Reports (To be reported quarterly no later than the 10th working day afterthe reporting period)10 Final Report (The final report shall be submitted upon finalisation of the assignement

DELIVERABLES

- Costs for Submarine cables - material and installation- Costs for HVDC land cables andor HVDC OHTLs andor HVAC ndash type overhead electriclines as applicable in Romania ndash material and installations- Costs for HVDC land cables andor HVDC OHTLs andor HVAC ndash type overhead electriclines as applicable in Turkey ndash material and installations- Costs for converter station including the AC connection in Romania- Costs for converter station including the AC connection in Turkey- Telecommunication equipment based on optical fibers- Site costs in Romania- Site costs in Turkey- Engineering project management project control and commissioning- Other investments if any- Interest rates during construction calculated separately for each of the above mentionedparts of the HVDC link- Total investment costs for the HVDC link- Payment for provisional and final expropriations

Investment needs - Investments in the HVDC Link

Investments in the Romanian AC Grid- AC grid investments exclusive the breaker bay for the HVDC link- Telecommunication and remote control equipment- Interest rates calculated separately for each part- Total investments due to the HVDC link in the Romanian AC grid

Investments in the Turkish AC Grid- AC grid investments exclusive the breaker bay for the HVDC link- Telecommunication and remote control equipment- Interest rates during construction calculated separately for each part- Total investments due to the HVDC link in the Turkish AC grid

Investment needs - Investments in the Romanian and Turkish AC grids

ldquoThe price forecast has to be calculated from different perspectivesbull Long term off-take contract 60 and 80 bull Market price for the remaining 40 and 20 bull Sufficient Average Price Level (SAPL)

COMMERCIAL and FINANCIAL ANALYSIS

ldquoBased on the recommended investment and operational plan the Designer shall establish a financial model and analyse the investment over a time horizon of both 20 years operation and 30 years operation The output of the model shall be presented in nominal terms

Tranzit scenarios 1000 MW from Romania to Turkey

Tranzit scenarios 1000 MW from UCTE (PolandampSlovakia) to

Turkey

Tranzit scenarios 1000 MW from Russia (IPSUPS) to Turkey

budget

Tranzit scenarios 1000 MW from Turkey to Romania

Tranzit scenarios1000 MW from Turkey to UCTE (Serbia and

Austria)

Activities to be done in parallel with the feasibilty study

bull Preliminary business model

ndash List of main commercial regulatory and financial hypothesys

ndash Documentation on the business experience of existing commercial interconnectors in EU

ndash Discussions and clarifications with the regulatory authorities

ndash Legal due diligence for the preliminary business model

ndash TOR for the complete business study

bull Exploration and identification of potential private partners

ndash Letters of intent

ndash Develop procedure for the selection of the private investors

bull Full clarifications on TEIAS participation in the project including Turkish applicable legislation

bull Preliminary legal preparations for the project company ( SPV )

Opportunity StudyJoint Position Paper

Feasibility Study( 75 TEL- 25 NE ) Business Study

Joint Position Paper - Final

International Agreement between

Romania and Turkey

Project implementationFinancing contracting supply and instalation

MOU -1MOU -1

MOU -2 MOU -2

Selection of private investors SPV ndash the project company

2005

2008 - 2009

2009

2010

2010 - 2013

022009

First tentative road map

THANK YOU FOR YOUR ATTENTION

e-mail relatiiinvestitoritranselectricaro razvanpurdilatranselectricaro

phone +40213035923fax +40213035880web-site wwwtranselectricaro

  • Regional Transmission Network Development Implications for Trade and Investment
  • Slide 2
  • Slide 4
  • Slide 5
  • Slide 6
  • Slide 7
  • Slide 8
  • Slide 9
  • Slide 11
  • Slide 12
  • Slide 13
  • Slide 14
  • Slide 15
  • Slide 16
  • Slide 17
  • Slide 18
  • Slide 19
  • Slide 20
  • Slide 21
  • Slide 22
  • Slide 23
  • Slide 24
  • Slide 25
  • Slide 27
  • Slide 28
  • Slide 29
  • Slide 30
  • Slide 31
  • Activities to be done in parallel with the feasibilty study
  • Slide 34
  • Slide 35
Page 8: R EGIONAL T RANSMISSION N ETWORK D EVELOPMENT : I MPLICATIONS FOR T RADE AND I NVESTMENT R EGIONAL T RANSMISSION N ETWORK D EVELOPMENT : I MPLICATIONS.

Short history of the project

bull 2004 ndash April ndash energy cooperation protocol between Romania and Turkey at ministries level

ndash The first mentioning of the cable project

bull 2005 - June ndash MOU between Transelectrica and TEIAS for the HVDC link project

ndash Main scope to prepare the oportunity study by a joint project team

bull 2006 ndash November - JPP ( joint position paper ) between Transelectrica and TEIAS

ndash Approval of the opportunity study

ndash Decision to continue the study at feasibility study level

bull 2007 ndash first attempt to launch the feasibility study with minority financing of private investors ( 50 Swedish grant available )

ndash No success replacement of the private investor with Nuclearelectrica

bull 2008 ndash first tender for the FS in new financing conditions

ndash Incompatibility of the grant with open tender requirements

bull 2009 ndash secont tender contract signature in June

ELEMENT 01

TELConstanţa

NordSubstation

ELEMENT 02TEL

Converter station and

link to Constanţa

Nord substation

ELEMENT03

TELUnderground cable between

converter station and HVDC cable connection

ELEMENT04

HVDC

cable

ELEMENT05

TEIASUnderground cable between

converter station and HVDC cable connection

ELEMENT 06

TEIASConverter

station and link to

Alibeykoumly substation

ROMANIA

BLACK SEA

ELEMENT 07

TEIASAlibeykoumly Substation

TURKEY

Romania ndash Turkey HVDC interconector overview

Part 3The feasibility study

bull Connection point with Romanian Power System 400kV SS Constanţa Nordbull Connection point with Turkish Power System 400kV SS Alybeikoumly in AsiabullThe cables voltage level 400 kVbullThe capacity 600MWbullThe length about 400 kmbull Losses on the cable-

bull in 600MW transfer ~ 12MWbull in 500MW transfer ~ 9MW

Deliverables

The nominated Designer will submit the following documents

Inception Report Terms of Reference ndash Objectives for procuring the services and

works required for the seabed survey and Geological Study EIA ndash Environmental Impact Assessment Study including

environmental approval Feasibility Study (draft) including the necessary documentation for

approvals and advices Feasibility Study (final) including the approvals and advices Documentation for urbanism certificates in Romania and Turkey Technical Specifications Progress Reports Final Report

Client ConsultantFICHTNER ENGINEERING

Romania

ClientTRANSELECTRICA amp NUCLEARELECTRICA

Romania

Client DesignerVATTENFALL

Sweden

Technical ConsultantTEIAŞ Turkey

Project team members and their responsibilities

Electricity market team

Technical team

Economical institutional and legal

commercial and financial team

- Environment expert- See bead expert- Overhead

transmission line expert

- Electrical substation expert

- Converter expert- HVDC submarine

cable expert- Permits and

approvals expert

- Contract legislation expert

- Price electricity forecasting expert

- Electricity market expert

- Macroeconomic modeling expert

- Financial analyze expert

- Investment analyze expert

- Contract legislation expert

- Romanian amp international legislation expert

Environmental team

Procurement team

- Commercial expert- Overhead

transmission line expert

- Electrical substation expert

- Converter expert- HVDC submarine

cable expert- Environment expert

- Environment expert- Romanian amp

international legislation expert

- Permits and approvals expert

EXPERT TEAMS

The Feasibility Study will

Establish the design parameters capacity and cost estimation for the HVDC link including the most suitable routing based on previous studies and existing data which include geological morphological and seabed structure analyze and initial sea depth survey as well as on its own investigations

Assess the legal and environmental impediments and propose the most appropriate and viable way forward for the Project from an operational and legal framework point of view including also the EIA Study with the afferent approvals in accordance with legalstipulations from both countries and from EU (Transelectrica Nuclearelectrica and TEIAŞ will in this respect support the Designer in this process)

bullContain the necessary documentation for obtaining permits and approvals in accordance with existing legislation in Romania and in Turkey as applicable at the date of project elaboration and corresponding to this phase of the engineeringbullContain the necessary documentation to obtain the urbanism certificatebullAnalyse the financial and economical feasibility of the interconnection project considering private benefits and costs and external effects such as public benefits and costsbullAssess suitable possibilities to finance the ProjectbullPropose a time schedule for project implementation and operationbullHighlight the commercial environmental and technical conditions of direct interconnection of the national grids of Turkey and Romania through a submarine cable across the Black Sea through system studies performed in both countries

Technical Specifications for procurement and execution will include at least a minimalcontent as follows- Scope- Definitions- Standard and recommendations- Functional and technical requirements- Testing and inspections- Execution- Provision of information1048707 Terms of Reference for procuring the services and work required for the seabed survey and geological study will be established based on our experience in similar projects For the feasibility study we will perform a study based on existing materialsdocumentation related to Black Sea seabed survey and geological studies1048707

1 Inception report (within 6 weeks of commencement of the project)2 Terms of Reference for the Seabed survey and Geological Study (The draftissue to be submitted within 6 weeks of commencement of the assignment)3 Plans and Terms of Reference for the Environmental Impact assessment (Tobe submitted as an annex to the first Progress report)4 Environmental Impact Assessment (EIA) incl environmental approvals (The draftissue within 8 months and the final issue within 10 months after the commencementof the assignment)5 Feasibility Study ndash draft incl the necessary documents for approvals and advices(8 months after commencement of the assignment)6 Feasibility Study ndash final incl approvals and advices (10 months aftercommencement of the assignment)7 Documentation for urbanism certificates in Romania and Turkey (10 months aftercommencement of the assignment)8 Technical Specifications (Within 14 months after the commencement of theproject)9 Progress Reports (To be reported quarterly no later than the 10th working day afterthe reporting period)10 Final Report (The final report shall be submitted upon finalisation of the assignement

DELIVERABLES

- Costs for Submarine cables - material and installation- Costs for HVDC land cables andor HVDC OHTLs andor HVAC ndash type overhead electriclines as applicable in Romania ndash material and installations- Costs for HVDC land cables andor HVDC OHTLs andor HVAC ndash type overhead electriclines as applicable in Turkey ndash material and installations- Costs for converter station including the AC connection in Romania- Costs for converter station including the AC connection in Turkey- Telecommunication equipment based on optical fibers- Site costs in Romania- Site costs in Turkey- Engineering project management project control and commissioning- Other investments if any- Interest rates during construction calculated separately for each of the above mentionedparts of the HVDC link- Total investment costs for the HVDC link- Payment for provisional and final expropriations

Investment needs - Investments in the HVDC Link

Investments in the Romanian AC Grid- AC grid investments exclusive the breaker bay for the HVDC link- Telecommunication and remote control equipment- Interest rates calculated separately for each part- Total investments due to the HVDC link in the Romanian AC grid

Investments in the Turkish AC Grid- AC grid investments exclusive the breaker bay for the HVDC link- Telecommunication and remote control equipment- Interest rates during construction calculated separately for each part- Total investments due to the HVDC link in the Turkish AC grid

Investment needs - Investments in the Romanian and Turkish AC grids

ldquoThe price forecast has to be calculated from different perspectivesbull Long term off-take contract 60 and 80 bull Market price for the remaining 40 and 20 bull Sufficient Average Price Level (SAPL)

COMMERCIAL and FINANCIAL ANALYSIS

ldquoBased on the recommended investment and operational plan the Designer shall establish a financial model and analyse the investment over a time horizon of both 20 years operation and 30 years operation The output of the model shall be presented in nominal terms

Tranzit scenarios 1000 MW from Romania to Turkey

Tranzit scenarios 1000 MW from UCTE (PolandampSlovakia) to

Turkey

Tranzit scenarios 1000 MW from Russia (IPSUPS) to Turkey

budget

Tranzit scenarios 1000 MW from Turkey to Romania

Tranzit scenarios1000 MW from Turkey to UCTE (Serbia and

Austria)

Activities to be done in parallel with the feasibilty study

bull Preliminary business model

ndash List of main commercial regulatory and financial hypothesys

ndash Documentation on the business experience of existing commercial interconnectors in EU

ndash Discussions and clarifications with the regulatory authorities

ndash Legal due diligence for the preliminary business model

ndash TOR for the complete business study

bull Exploration and identification of potential private partners

ndash Letters of intent

ndash Develop procedure for the selection of the private investors

bull Full clarifications on TEIAS participation in the project including Turkish applicable legislation

bull Preliminary legal preparations for the project company ( SPV )

Opportunity StudyJoint Position Paper

Feasibility Study( 75 TEL- 25 NE ) Business Study

Joint Position Paper - Final

International Agreement between

Romania and Turkey

Project implementationFinancing contracting supply and instalation

MOU -1MOU -1

MOU -2 MOU -2

Selection of private investors SPV ndash the project company

2005

2008 - 2009

2009

2010

2010 - 2013

022009

First tentative road map

THANK YOU FOR YOUR ATTENTION

e-mail relatiiinvestitoritranselectricaro razvanpurdilatranselectricaro

phone +40213035923fax +40213035880web-site wwwtranselectricaro

  • Regional Transmission Network Development Implications for Trade and Investment
  • Slide 2
  • Slide 4
  • Slide 5
  • Slide 6
  • Slide 7
  • Slide 8
  • Slide 9
  • Slide 11
  • Slide 12
  • Slide 13
  • Slide 14
  • Slide 15
  • Slide 16
  • Slide 17
  • Slide 18
  • Slide 19
  • Slide 20
  • Slide 21
  • Slide 22
  • Slide 23
  • Slide 24
  • Slide 25
  • Slide 27
  • Slide 28
  • Slide 29
  • Slide 30
  • Slide 31
  • Activities to be done in parallel with the feasibilty study
  • Slide 34
  • Slide 35
Page 9: R EGIONAL T RANSMISSION N ETWORK D EVELOPMENT : I MPLICATIONS FOR T RADE AND I NVESTMENT R EGIONAL T RANSMISSION N ETWORK D EVELOPMENT : I MPLICATIONS.

ELEMENT 01

TELConstanţa

NordSubstation

ELEMENT 02TEL

Converter station and

link to Constanţa

Nord substation

ELEMENT03

TELUnderground cable between

converter station and HVDC cable connection

ELEMENT04

HVDC

cable

ELEMENT05

TEIASUnderground cable between

converter station and HVDC cable connection

ELEMENT 06

TEIASConverter

station and link to

Alibeykoumly substation

ROMANIA

BLACK SEA

ELEMENT 07

TEIASAlibeykoumly Substation

TURKEY

Romania ndash Turkey HVDC interconector overview

Part 3The feasibility study

bull Connection point with Romanian Power System 400kV SS Constanţa Nordbull Connection point with Turkish Power System 400kV SS Alybeikoumly in AsiabullThe cables voltage level 400 kVbullThe capacity 600MWbullThe length about 400 kmbull Losses on the cable-

bull in 600MW transfer ~ 12MWbull in 500MW transfer ~ 9MW

Deliverables

The nominated Designer will submit the following documents

Inception Report Terms of Reference ndash Objectives for procuring the services and

works required for the seabed survey and Geological Study EIA ndash Environmental Impact Assessment Study including

environmental approval Feasibility Study (draft) including the necessary documentation for

approvals and advices Feasibility Study (final) including the approvals and advices Documentation for urbanism certificates in Romania and Turkey Technical Specifications Progress Reports Final Report

Client ConsultantFICHTNER ENGINEERING

Romania

ClientTRANSELECTRICA amp NUCLEARELECTRICA

Romania

Client DesignerVATTENFALL

Sweden

Technical ConsultantTEIAŞ Turkey

Project team members and their responsibilities

Electricity market team

Technical team

Economical institutional and legal

commercial and financial team

- Environment expert- See bead expert- Overhead

transmission line expert

- Electrical substation expert

- Converter expert- HVDC submarine

cable expert- Permits and

approvals expert

- Contract legislation expert

- Price electricity forecasting expert

- Electricity market expert

- Macroeconomic modeling expert

- Financial analyze expert

- Investment analyze expert

- Contract legislation expert

- Romanian amp international legislation expert

Environmental team

Procurement team

- Commercial expert- Overhead

transmission line expert

- Electrical substation expert

- Converter expert- HVDC submarine

cable expert- Environment expert

- Environment expert- Romanian amp

international legislation expert

- Permits and approvals expert

EXPERT TEAMS

The Feasibility Study will

Establish the design parameters capacity and cost estimation for the HVDC link including the most suitable routing based on previous studies and existing data which include geological morphological and seabed structure analyze and initial sea depth survey as well as on its own investigations

Assess the legal and environmental impediments and propose the most appropriate and viable way forward for the Project from an operational and legal framework point of view including also the EIA Study with the afferent approvals in accordance with legalstipulations from both countries and from EU (Transelectrica Nuclearelectrica and TEIAŞ will in this respect support the Designer in this process)

bullContain the necessary documentation for obtaining permits and approvals in accordance with existing legislation in Romania and in Turkey as applicable at the date of project elaboration and corresponding to this phase of the engineeringbullContain the necessary documentation to obtain the urbanism certificatebullAnalyse the financial and economical feasibility of the interconnection project considering private benefits and costs and external effects such as public benefits and costsbullAssess suitable possibilities to finance the ProjectbullPropose a time schedule for project implementation and operationbullHighlight the commercial environmental and technical conditions of direct interconnection of the national grids of Turkey and Romania through a submarine cable across the Black Sea through system studies performed in both countries

Technical Specifications for procurement and execution will include at least a minimalcontent as follows- Scope- Definitions- Standard and recommendations- Functional and technical requirements- Testing and inspections- Execution- Provision of information1048707 Terms of Reference for procuring the services and work required for the seabed survey and geological study will be established based on our experience in similar projects For the feasibility study we will perform a study based on existing materialsdocumentation related to Black Sea seabed survey and geological studies1048707

1 Inception report (within 6 weeks of commencement of the project)2 Terms of Reference for the Seabed survey and Geological Study (The draftissue to be submitted within 6 weeks of commencement of the assignment)3 Plans and Terms of Reference for the Environmental Impact assessment (Tobe submitted as an annex to the first Progress report)4 Environmental Impact Assessment (EIA) incl environmental approvals (The draftissue within 8 months and the final issue within 10 months after the commencementof the assignment)5 Feasibility Study ndash draft incl the necessary documents for approvals and advices(8 months after commencement of the assignment)6 Feasibility Study ndash final incl approvals and advices (10 months aftercommencement of the assignment)7 Documentation for urbanism certificates in Romania and Turkey (10 months aftercommencement of the assignment)8 Technical Specifications (Within 14 months after the commencement of theproject)9 Progress Reports (To be reported quarterly no later than the 10th working day afterthe reporting period)10 Final Report (The final report shall be submitted upon finalisation of the assignement

DELIVERABLES

- Costs for Submarine cables - material and installation- Costs for HVDC land cables andor HVDC OHTLs andor HVAC ndash type overhead electriclines as applicable in Romania ndash material and installations- Costs for HVDC land cables andor HVDC OHTLs andor HVAC ndash type overhead electriclines as applicable in Turkey ndash material and installations- Costs for converter station including the AC connection in Romania- Costs for converter station including the AC connection in Turkey- Telecommunication equipment based on optical fibers- Site costs in Romania- Site costs in Turkey- Engineering project management project control and commissioning- Other investments if any- Interest rates during construction calculated separately for each of the above mentionedparts of the HVDC link- Total investment costs for the HVDC link- Payment for provisional and final expropriations

Investment needs - Investments in the HVDC Link

Investments in the Romanian AC Grid- AC grid investments exclusive the breaker bay for the HVDC link- Telecommunication and remote control equipment- Interest rates calculated separately for each part- Total investments due to the HVDC link in the Romanian AC grid

Investments in the Turkish AC Grid- AC grid investments exclusive the breaker bay for the HVDC link- Telecommunication and remote control equipment- Interest rates during construction calculated separately for each part- Total investments due to the HVDC link in the Turkish AC grid

Investment needs - Investments in the Romanian and Turkish AC grids

ldquoThe price forecast has to be calculated from different perspectivesbull Long term off-take contract 60 and 80 bull Market price for the remaining 40 and 20 bull Sufficient Average Price Level (SAPL)

COMMERCIAL and FINANCIAL ANALYSIS

ldquoBased on the recommended investment and operational plan the Designer shall establish a financial model and analyse the investment over a time horizon of both 20 years operation and 30 years operation The output of the model shall be presented in nominal terms

Tranzit scenarios 1000 MW from Romania to Turkey

Tranzit scenarios 1000 MW from UCTE (PolandampSlovakia) to

Turkey

Tranzit scenarios 1000 MW from Russia (IPSUPS) to Turkey

budget

Tranzit scenarios 1000 MW from Turkey to Romania

Tranzit scenarios1000 MW from Turkey to UCTE (Serbia and

Austria)

Activities to be done in parallel with the feasibilty study

bull Preliminary business model

ndash List of main commercial regulatory and financial hypothesys

ndash Documentation on the business experience of existing commercial interconnectors in EU

ndash Discussions and clarifications with the regulatory authorities

ndash Legal due diligence for the preliminary business model

ndash TOR for the complete business study

bull Exploration and identification of potential private partners

ndash Letters of intent

ndash Develop procedure for the selection of the private investors

bull Full clarifications on TEIAS participation in the project including Turkish applicable legislation

bull Preliminary legal preparations for the project company ( SPV )

Opportunity StudyJoint Position Paper

Feasibility Study( 75 TEL- 25 NE ) Business Study

Joint Position Paper - Final

International Agreement between

Romania and Turkey

Project implementationFinancing contracting supply and instalation

MOU -1MOU -1

MOU -2 MOU -2

Selection of private investors SPV ndash the project company

2005

2008 - 2009

2009

2010

2010 - 2013

022009

First tentative road map

THANK YOU FOR YOUR ATTENTION

e-mail relatiiinvestitoritranselectricaro razvanpurdilatranselectricaro

phone +40213035923fax +40213035880web-site wwwtranselectricaro

  • Regional Transmission Network Development Implications for Trade and Investment
  • Slide 2
  • Slide 4
  • Slide 5
  • Slide 6
  • Slide 7
  • Slide 8
  • Slide 9
  • Slide 11
  • Slide 12
  • Slide 13
  • Slide 14
  • Slide 15
  • Slide 16
  • Slide 17
  • Slide 18
  • Slide 19
  • Slide 20
  • Slide 21
  • Slide 22
  • Slide 23
  • Slide 24
  • Slide 25
  • Slide 27
  • Slide 28
  • Slide 29
  • Slide 30
  • Slide 31
  • Activities to be done in parallel with the feasibilty study
  • Slide 34
  • Slide 35
Page 10: R EGIONAL T RANSMISSION N ETWORK D EVELOPMENT : I MPLICATIONS FOR T RADE AND I NVESTMENT R EGIONAL T RANSMISSION N ETWORK D EVELOPMENT : I MPLICATIONS.

Part 3The feasibility study

bull Connection point with Romanian Power System 400kV SS Constanţa Nordbull Connection point with Turkish Power System 400kV SS Alybeikoumly in AsiabullThe cables voltage level 400 kVbullThe capacity 600MWbullThe length about 400 kmbull Losses on the cable-

bull in 600MW transfer ~ 12MWbull in 500MW transfer ~ 9MW

Deliverables

The nominated Designer will submit the following documents

Inception Report Terms of Reference ndash Objectives for procuring the services and

works required for the seabed survey and Geological Study EIA ndash Environmental Impact Assessment Study including

environmental approval Feasibility Study (draft) including the necessary documentation for

approvals and advices Feasibility Study (final) including the approvals and advices Documentation for urbanism certificates in Romania and Turkey Technical Specifications Progress Reports Final Report

Client ConsultantFICHTNER ENGINEERING

Romania

ClientTRANSELECTRICA amp NUCLEARELECTRICA

Romania

Client DesignerVATTENFALL

Sweden

Technical ConsultantTEIAŞ Turkey

Project team members and their responsibilities

Electricity market team

Technical team

Economical institutional and legal

commercial and financial team

- Environment expert- See bead expert- Overhead

transmission line expert

- Electrical substation expert

- Converter expert- HVDC submarine

cable expert- Permits and

approvals expert

- Contract legislation expert

- Price electricity forecasting expert

- Electricity market expert

- Macroeconomic modeling expert

- Financial analyze expert

- Investment analyze expert

- Contract legislation expert

- Romanian amp international legislation expert

Environmental team

Procurement team

- Commercial expert- Overhead

transmission line expert

- Electrical substation expert

- Converter expert- HVDC submarine

cable expert- Environment expert

- Environment expert- Romanian amp

international legislation expert

- Permits and approvals expert

EXPERT TEAMS

The Feasibility Study will

Establish the design parameters capacity and cost estimation for the HVDC link including the most suitable routing based on previous studies and existing data which include geological morphological and seabed structure analyze and initial sea depth survey as well as on its own investigations

Assess the legal and environmental impediments and propose the most appropriate and viable way forward for the Project from an operational and legal framework point of view including also the EIA Study with the afferent approvals in accordance with legalstipulations from both countries and from EU (Transelectrica Nuclearelectrica and TEIAŞ will in this respect support the Designer in this process)

bullContain the necessary documentation for obtaining permits and approvals in accordance with existing legislation in Romania and in Turkey as applicable at the date of project elaboration and corresponding to this phase of the engineeringbullContain the necessary documentation to obtain the urbanism certificatebullAnalyse the financial and economical feasibility of the interconnection project considering private benefits and costs and external effects such as public benefits and costsbullAssess suitable possibilities to finance the ProjectbullPropose a time schedule for project implementation and operationbullHighlight the commercial environmental and technical conditions of direct interconnection of the national grids of Turkey and Romania through a submarine cable across the Black Sea through system studies performed in both countries

Technical Specifications for procurement and execution will include at least a minimalcontent as follows- Scope- Definitions- Standard and recommendations- Functional and technical requirements- Testing and inspections- Execution- Provision of information1048707 Terms of Reference for procuring the services and work required for the seabed survey and geological study will be established based on our experience in similar projects For the feasibility study we will perform a study based on existing materialsdocumentation related to Black Sea seabed survey and geological studies1048707

1 Inception report (within 6 weeks of commencement of the project)2 Terms of Reference for the Seabed survey and Geological Study (The draftissue to be submitted within 6 weeks of commencement of the assignment)3 Plans and Terms of Reference for the Environmental Impact assessment (Tobe submitted as an annex to the first Progress report)4 Environmental Impact Assessment (EIA) incl environmental approvals (The draftissue within 8 months and the final issue within 10 months after the commencementof the assignment)5 Feasibility Study ndash draft incl the necessary documents for approvals and advices(8 months after commencement of the assignment)6 Feasibility Study ndash final incl approvals and advices (10 months aftercommencement of the assignment)7 Documentation for urbanism certificates in Romania and Turkey (10 months aftercommencement of the assignment)8 Technical Specifications (Within 14 months after the commencement of theproject)9 Progress Reports (To be reported quarterly no later than the 10th working day afterthe reporting period)10 Final Report (The final report shall be submitted upon finalisation of the assignement

DELIVERABLES

- Costs for Submarine cables - material and installation- Costs for HVDC land cables andor HVDC OHTLs andor HVAC ndash type overhead electriclines as applicable in Romania ndash material and installations- Costs for HVDC land cables andor HVDC OHTLs andor HVAC ndash type overhead electriclines as applicable in Turkey ndash material and installations- Costs for converter station including the AC connection in Romania- Costs for converter station including the AC connection in Turkey- Telecommunication equipment based on optical fibers- Site costs in Romania- Site costs in Turkey- Engineering project management project control and commissioning- Other investments if any- Interest rates during construction calculated separately for each of the above mentionedparts of the HVDC link- Total investment costs for the HVDC link- Payment for provisional and final expropriations

Investment needs - Investments in the HVDC Link

Investments in the Romanian AC Grid- AC grid investments exclusive the breaker bay for the HVDC link- Telecommunication and remote control equipment- Interest rates calculated separately for each part- Total investments due to the HVDC link in the Romanian AC grid

Investments in the Turkish AC Grid- AC grid investments exclusive the breaker bay for the HVDC link- Telecommunication and remote control equipment- Interest rates during construction calculated separately for each part- Total investments due to the HVDC link in the Turkish AC grid

Investment needs - Investments in the Romanian and Turkish AC grids

ldquoThe price forecast has to be calculated from different perspectivesbull Long term off-take contract 60 and 80 bull Market price for the remaining 40 and 20 bull Sufficient Average Price Level (SAPL)

COMMERCIAL and FINANCIAL ANALYSIS

ldquoBased on the recommended investment and operational plan the Designer shall establish a financial model and analyse the investment over a time horizon of both 20 years operation and 30 years operation The output of the model shall be presented in nominal terms

Tranzit scenarios 1000 MW from Romania to Turkey

Tranzit scenarios 1000 MW from UCTE (PolandampSlovakia) to

Turkey

Tranzit scenarios 1000 MW from Russia (IPSUPS) to Turkey

budget

Tranzit scenarios 1000 MW from Turkey to Romania

Tranzit scenarios1000 MW from Turkey to UCTE (Serbia and

Austria)

Activities to be done in parallel with the feasibilty study

bull Preliminary business model

ndash List of main commercial regulatory and financial hypothesys

ndash Documentation on the business experience of existing commercial interconnectors in EU

ndash Discussions and clarifications with the regulatory authorities

ndash Legal due diligence for the preliminary business model

ndash TOR for the complete business study

bull Exploration and identification of potential private partners

ndash Letters of intent

ndash Develop procedure for the selection of the private investors

bull Full clarifications on TEIAS participation in the project including Turkish applicable legislation

bull Preliminary legal preparations for the project company ( SPV )

Opportunity StudyJoint Position Paper

Feasibility Study( 75 TEL- 25 NE ) Business Study

Joint Position Paper - Final

International Agreement between

Romania and Turkey

Project implementationFinancing contracting supply and instalation

MOU -1MOU -1

MOU -2 MOU -2

Selection of private investors SPV ndash the project company

2005

2008 - 2009

2009

2010

2010 - 2013

022009

First tentative road map

THANK YOU FOR YOUR ATTENTION

e-mail relatiiinvestitoritranselectricaro razvanpurdilatranselectricaro

phone +40213035923fax +40213035880web-site wwwtranselectricaro

  • Regional Transmission Network Development Implications for Trade and Investment
  • Slide 2
  • Slide 4
  • Slide 5
  • Slide 6
  • Slide 7
  • Slide 8
  • Slide 9
  • Slide 11
  • Slide 12
  • Slide 13
  • Slide 14
  • Slide 15
  • Slide 16
  • Slide 17
  • Slide 18
  • Slide 19
  • Slide 20
  • Slide 21
  • Slide 22
  • Slide 23
  • Slide 24
  • Slide 25
  • Slide 27
  • Slide 28
  • Slide 29
  • Slide 30
  • Slide 31
  • Activities to be done in parallel with the feasibilty study
  • Slide 34
  • Slide 35
Page 11: R EGIONAL T RANSMISSION N ETWORK D EVELOPMENT : I MPLICATIONS FOR T RADE AND I NVESTMENT R EGIONAL T RANSMISSION N ETWORK D EVELOPMENT : I MPLICATIONS.

bull Connection point with Romanian Power System 400kV SS Constanţa Nordbull Connection point with Turkish Power System 400kV SS Alybeikoumly in AsiabullThe cables voltage level 400 kVbullThe capacity 600MWbullThe length about 400 kmbull Losses on the cable-

bull in 600MW transfer ~ 12MWbull in 500MW transfer ~ 9MW

Deliverables

The nominated Designer will submit the following documents

Inception Report Terms of Reference ndash Objectives for procuring the services and

works required for the seabed survey and Geological Study EIA ndash Environmental Impact Assessment Study including

environmental approval Feasibility Study (draft) including the necessary documentation for

approvals and advices Feasibility Study (final) including the approvals and advices Documentation for urbanism certificates in Romania and Turkey Technical Specifications Progress Reports Final Report

Client ConsultantFICHTNER ENGINEERING

Romania

ClientTRANSELECTRICA amp NUCLEARELECTRICA

Romania

Client DesignerVATTENFALL

Sweden

Technical ConsultantTEIAŞ Turkey

Project team members and their responsibilities

Electricity market team

Technical team

Economical institutional and legal

commercial and financial team

- Environment expert- See bead expert- Overhead

transmission line expert

- Electrical substation expert

- Converter expert- HVDC submarine

cable expert- Permits and

approvals expert

- Contract legislation expert

- Price electricity forecasting expert

- Electricity market expert

- Macroeconomic modeling expert

- Financial analyze expert

- Investment analyze expert

- Contract legislation expert

- Romanian amp international legislation expert

Environmental team

Procurement team

- Commercial expert- Overhead

transmission line expert

- Electrical substation expert

- Converter expert- HVDC submarine

cable expert- Environment expert

- Environment expert- Romanian amp

international legislation expert

- Permits and approvals expert

EXPERT TEAMS

The Feasibility Study will

Establish the design parameters capacity and cost estimation for the HVDC link including the most suitable routing based on previous studies and existing data which include geological morphological and seabed structure analyze and initial sea depth survey as well as on its own investigations

Assess the legal and environmental impediments and propose the most appropriate and viable way forward for the Project from an operational and legal framework point of view including also the EIA Study with the afferent approvals in accordance with legalstipulations from both countries and from EU (Transelectrica Nuclearelectrica and TEIAŞ will in this respect support the Designer in this process)

bullContain the necessary documentation for obtaining permits and approvals in accordance with existing legislation in Romania and in Turkey as applicable at the date of project elaboration and corresponding to this phase of the engineeringbullContain the necessary documentation to obtain the urbanism certificatebullAnalyse the financial and economical feasibility of the interconnection project considering private benefits and costs and external effects such as public benefits and costsbullAssess suitable possibilities to finance the ProjectbullPropose a time schedule for project implementation and operationbullHighlight the commercial environmental and technical conditions of direct interconnection of the national grids of Turkey and Romania through a submarine cable across the Black Sea through system studies performed in both countries

Technical Specifications for procurement and execution will include at least a minimalcontent as follows- Scope- Definitions- Standard and recommendations- Functional and technical requirements- Testing and inspections- Execution- Provision of information1048707 Terms of Reference for procuring the services and work required for the seabed survey and geological study will be established based on our experience in similar projects For the feasibility study we will perform a study based on existing materialsdocumentation related to Black Sea seabed survey and geological studies1048707

1 Inception report (within 6 weeks of commencement of the project)2 Terms of Reference for the Seabed survey and Geological Study (The draftissue to be submitted within 6 weeks of commencement of the assignment)3 Plans and Terms of Reference for the Environmental Impact assessment (Tobe submitted as an annex to the first Progress report)4 Environmental Impact Assessment (EIA) incl environmental approvals (The draftissue within 8 months and the final issue within 10 months after the commencementof the assignment)5 Feasibility Study ndash draft incl the necessary documents for approvals and advices(8 months after commencement of the assignment)6 Feasibility Study ndash final incl approvals and advices (10 months aftercommencement of the assignment)7 Documentation for urbanism certificates in Romania and Turkey (10 months aftercommencement of the assignment)8 Technical Specifications (Within 14 months after the commencement of theproject)9 Progress Reports (To be reported quarterly no later than the 10th working day afterthe reporting period)10 Final Report (The final report shall be submitted upon finalisation of the assignement

DELIVERABLES

- Costs for Submarine cables - material and installation- Costs for HVDC land cables andor HVDC OHTLs andor HVAC ndash type overhead electriclines as applicable in Romania ndash material and installations- Costs for HVDC land cables andor HVDC OHTLs andor HVAC ndash type overhead electriclines as applicable in Turkey ndash material and installations- Costs for converter station including the AC connection in Romania- Costs for converter station including the AC connection in Turkey- Telecommunication equipment based on optical fibers- Site costs in Romania- Site costs in Turkey- Engineering project management project control and commissioning- Other investments if any- Interest rates during construction calculated separately for each of the above mentionedparts of the HVDC link- Total investment costs for the HVDC link- Payment for provisional and final expropriations

Investment needs - Investments in the HVDC Link

Investments in the Romanian AC Grid- AC grid investments exclusive the breaker bay for the HVDC link- Telecommunication and remote control equipment- Interest rates calculated separately for each part- Total investments due to the HVDC link in the Romanian AC grid

Investments in the Turkish AC Grid- AC grid investments exclusive the breaker bay for the HVDC link- Telecommunication and remote control equipment- Interest rates during construction calculated separately for each part- Total investments due to the HVDC link in the Turkish AC grid

Investment needs - Investments in the Romanian and Turkish AC grids

ldquoThe price forecast has to be calculated from different perspectivesbull Long term off-take contract 60 and 80 bull Market price for the remaining 40 and 20 bull Sufficient Average Price Level (SAPL)

COMMERCIAL and FINANCIAL ANALYSIS

ldquoBased on the recommended investment and operational plan the Designer shall establish a financial model and analyse the investment over a time horizon of both 20 years operation and 30 years operation The output of the model shall be presented in nominal terms

Tranzit scenarios 1000 MW from Romania to Turkey

Tranzit scenarios 1000 MW from UCTE (PolandampSlovakia) to

Turkey

Tranzit scenarios 1000 MW from Russia (IPSUPS) to Turkey

budget

Tranzit scenarios 1000 MW from Turkey to Romania

Tranzit scenarios1000 MW from Turkey to UCTE (Serbia and

Austria)

Activities to be done in parallel with the feasibilty study

bull Preliminary business model

ndash List of main commercial regulatory and financial hypothesys

ndash Documentation on the business experience of existing commercial interconnectors in EU

ndash Discussions and clarifications with the regulatory authorities

ndash Legal due diligence for the preliminary business model

ndash TOR for the complete business study

bull Exploration and identification of potential private partners

ndash Letters of intent

ndash Develop procedure for the selection of the private investors

bull Full clarifications on TEIAS participation in the project including Turkish applicable legislation

bull Preliminary legal preparations for the project company ( SPV )

Opportunity StudyJoint Position Paper

Feasibility Study( 75 TEL- 25 NE ) Business Study

Joint Position Paper - Final

International Agreement between

Romania and Turkey

Project implementationFinancing contracting supply and instalation

MOU -1MOU -1

MOU -2 MOU -2

Selection of private investors SPV ndash the project company

2005

2008 - 2009

2009

2010

2010 - 2013

022009

First tentative road map

THANK YOU FOR YOUR ATTENTION

e-mail relatiiinvestitoritranselectricaro razvanpurdilatranselectricaro

phone +40213035923fax +40213035880web-site wwwtranselectricaro

  • Regional Transmission Network Development Implications for Trade and Investment
  • Slide 2
  • Slide 4
  • Slide 5
  • Slide 6
  • Slide 7
  • Slide 8
  • Slide 9
  • Slide 11
  • Slide 12
  • Slide 13
  • Slide 14
  • Slide 15
  • Slide 16
  • Slide 17
  • Slide 18
  • Slide 19
  • Slide 20
  • Slide 21
  • Slide 22
  • Slide 23
  • Slide 24
  • Slide 25
  • Slide 27
  • Slide 28
  • Slide 29
  • Slide 30
  • Slide 31
  • Activities to be done in parallel with the feasibilty study
  • Slide 34
  • Slide 35
Page 12: R EGIONAL T RANSMISSION N ETWORK D EVELOPMENT : I MPLICATIONS FOR T RADE AND I NVESTMENT R EGIONAL T RANSMISSION N ETWORK D EVELOPMENT : I MPLICATIONS.

Deliverables

The nominated Designer will submit the following documents

Inception Report Terms of Reference ndash Objectives for procuring the services and

works required for the seabed survey and Geological Study EIA ndash Environmental Impact Assessment Study including

environmental approval Feasibility Study (draft) including the necessary documentation for

approvals and advices Feasibility Study (final) including the approvals and advices Documentation for urbanism certificates in Romania and Turkey Technical Specifications Progress Reports Final Report

Client ConsultantFICHTNER ENGINEERING

Romania

ClientTRANSELECTRICA amp NUCLEARELECTRICA

Romania

Client DesignerVATTENFALL

Sweden

Technical ConsultantTEIAŞ Turkey

Project team members and their responsibilities

Electricity market team

Technical team

Economical institutional and legal

commercial and financial team

- Environment expert- See bead expert- Overhead

transmission line expert

- Electrical substation expert

- Converter expert- HVDC submarine

cable expert- Permits and

approvals expert

- Contract legislation expert

- Price electricity forecasting expert

- Electricity market expert

- Macroeconomic modeling expert

- Financial analyze expert

- Investment analyze expert

- Contract legislation expert

- Romanian amp international legislation expert

Environmental team

Procurement team

- Commercial expert- Overhead

transmission line expert

- Electrical substation expert

- Converter expert- HVDC submarine

cable expert- Environment expert

- Environment expert- Romanian amp

international legislation expert

- Permits and approvals expert

EXPERT TEAMS

The Feasibility Study will

Establish the design parameters capacity and cost estimation for the HVDC link including the most suitable routing based on previous studies and existing data which include geological morphological and seabed structure analyze and initial sea depth survey as well as on its own investigations

Assess the legal and environmental impediments and propose the most appropriate and viable way forward for the Project from an operational and legal framework point of view including also the EIA Study with the afferent approvals in accordance with legalstipulations from both countries and from EU (Transelectrica Nuclearelectrica and TEIAŞ will in this respect support the Designer in this process)

bullContain the necessary documentation for obtaining permits and approvals in accordance with existing legislation in Romania and in Turkey as applicable at the date of project elaboration and corresponding to this phase of the engineeringbullContain the necessary documentation to obtain the urbanism certificatebullAnalyse the financial and economical feasibility of the interconnection project considering private benefits and costs and external effects such as public benefits and costsbullAssess suitable possibilities to finance the ProjectbullPropose a time schedule for project implementation and operationbullHighlight the commercial environmental and technical conditions of direct interconnection of the national grids of Turkey and Romania through a submarine cable across the Black Sea through system studies performed in both countries

Technical Specifications for procurement and execution will include at least a minimalcontent as follows- Scope- Definitions- Standard and recommendations- Functional and technical requirements- Testing and inspections- Execution- Provision of information1048707 Terms of Reference for procuring the services and work required for the seabed survey and geological study will be established based on our experience in similar projects For the feasibility study we will perform a study based on existing materialsdocumentation related to Black Sea seabed survey and geological studies1048707

1 Inception report (within 6 weeks of commencement of the project)2 Terms of Reference for the Seabed survey and Geological Study (The draftissue to be submitted within 6 weeks of commencement of the assignment)3 Plans and Terms of Reference for the Environmental Impact assessment (Tobe submitted as an annex to the first Progress report)4 Environmental Impact Assessment (EIA) incl environmental approvals (The draftissue within 8 months and the final issue within 10 months after the commencementof the assignment)5 Feasibility Study ndash draft incl the necessary documents for approvals and advices(8 months after commencement of the assignment)6 Feasibility Study ndash final incl approvals and advices (10 months aftercommencement of the assignment)7 Documentation for urbanism certificates in Romania and Turkey (10 months aftercommencement of the assignment)8 Technical Specifications (Within 14 months after the commencement of theproject)9 Progress Reports (To be reported quarterly no later than the 10th working day afterthe reporting period)10 Final Report (The final report shall be submitted upon finalisation of the assignement

DELIVERABLES

- Costs for Submarine cables - material and installation- Costs for HVDC land cables andor HVDC OHTLs andor HVAC ndash type overhead electriclines as applicable in Romania ndash material and installations- Costs for HVDC land cables andor HVDC OHTLs andor HVAC ndash type overhead electriclines as applicable in Turkey ndash material and installations- Costs for converter station including the AC connection in Romania- Costs for converter station including the AC connection in Turkey- Telecommunication equipment based on optical fibers- Site costs in Romania- Site costs in Turkey- Engineering project management project control and commissioning- Other investments if any- Interest rates during construction calculated separately for each of the above mentionedparts of the HVDC link- Total investment costs for the HVDC link- Payment for provisional and final expropriations

Investment needs - Investments in the HVDC Link

Investments in the Romanian AC Grid- AC grid investments exclusive the breaker bay for the HVDC link- Telecommunication and remote control equipment- Interest rates calculated separately for each part- Total investments due to the HVDC link in the Romanian AC grid

Investments in the Turkish AC Grid- AC grid investments exclusive the breaker bay for the HVDC link- Telecommunication and remote control equipment- Interest rates during construction calculated separately for each part- Total investments due to the HVDC link in the Turkish AC grid

Investment needs - Investments in the Romanian and Turkish AC grids

ldquoThe price forecast has to be calculated from different perspectivesbull Long term off-take contract 60 and 80 bull Market price for the remaining 40 and 20 bull Sufficient Average Price Level (SAPL)

COMMERCIAL and FINANCIAL ANALYSIS

ldquoBased on the recommended investment and operational plan the Designer shall establish a financial model and analyse the investment over a time horizon of both 20 years operation and 30 years operation The output of the model shall be presented in nominal terms

Tranzit scenarios 1000 MW from Romania to Turkey

Tranzit scenarios 1000 MW from UCTE (PolandampSlovakia) to

Turkey

Tranzit scenarios 1000 MW from Russia (IPSUPS) to Turkey

budget

Tranzit scenarios 1000 MW from Turkey to Romania

Tranzit scenarios1000 MW from Turkey to UCTE (Serbia and

Austria)

Activities to be done in parallel with the feasibilty study

bull Preliminary business model

ndash List of main commercial regulatory and financial hypothesys

ndash Documentation on the business experience of existing commercial interconnectors in EU

ndash Discussions and clarifications with the regulatory authorities

ndash Legal due diligence for the preliminary business model

ndash TOR for the complete business study

bull Exploration and identification of potential private partners

ndash Letters of intent

ndash Develop procedure for the selection of the private investors

bull Full clarifications on TEIAS participation in the project including Turkish applicable legislation

bull Preliminary legal preparations for the project company ( SPV )

Opportunity StudyJoint Position Paper

Feasibility Study( 75 TEL- 25 NE ) Business Study

Joint Position Paper - Final

International Agreement between

Romania and Turkey

Project implementationFinancing contracting supply and instalation

MOU -1MOU -1

MOU -2 MOU -2

Selection of private investors SPV ndash the project company

2005

2008 - 2009

2009

2010

2010 - 2013

022009

First tentative road map

THANK YOU FOR YOUR ATTENTION

e-mail relatiiinvestitoritranselectricaro razvanpurdilatranselectricaro

phone +40213035923fax +40213035880web-site wwwtranselectricaro

  • Regional Transmission Network Development Implications for Trade and Investment
  • Slide 2
  • Slide 4
  • Slide 5
  • Slide 6
  • Slide 7
  • Slide 8
  • Slide 9
  • Slide 11
  • Slide 12
  • Slide 13
  • Slide 14
  • Slide 15
  • Slide 16
  • Slide 17
  • Slide 18
  • Slide 19
  • Slide 20
  • Slide 21
  • Slide 22
  • Slide 23
  • Slide 24
  • Slide 25
  • Slide 27
  • Slide 28
  • Slide 29
  • Slide 30
  • Slide 31
  • Activities to be done in parallel with the feasibilty study
  • Slide 34
  • Slide 35
Page 13: R EGIONAL T RANSMISSION N ETWORK D EVELOPMENT : I MPLICATIONS FOR T RADE AND I NVESTMENT R EGIONAL T RANSMISSION N ETWORK D EVELOPMENT : I MPLICATIONS.

Client ConsultantFICHTNER ENGINEERING

Romania

ClientTRANSELECTRICA amp NUCLEARELECTRICA

Romania

Client DesignerVATTENFALL

Sweden

Technical ConsultantTEIAŞ Turkey

Project team members and their responsibilities

Electricity market team

Technical team

Economical institutional and legal

commercial and financial team

- Environment expert- See bead expert- Overhead

transmission line expert

- Electrical substation expert

- Converter expert- HVDC submarine

cable expert- Permits and

approvals expert

- Contract legislation expert

- Price electricity forecasting expert

- Electricity market expert

- Macroeconomic modeling expert

- Financial analyze expert

- Investment analyze expert

- Contract legislation expert

- Romanian amp international legislation expert

Environmental team

Procurement team

- Commercial expert- Overhead

transmission line expert

- Electrical substation expert

- Converter expert- HVDC submarine

cable expert- Environment expert

- Environment expert- Romanian amp

international legislation expert

- Permits and approvals expert

EXPERT TEAMS

The Feasibility Study will

Establish the design parameters capacity and cost estimation for the HVDC link including the most suitable routing based on previous studies and existing data which include geological morphological and seabed structure analyze and initial sea depth survey as well as on its own investigations

Assess the legal and environmental impediments and propose the most appropriate and viable way forward for the Project from an operational and legal framework point of view including also the EIA Study with the afferent approvals in accordance with legalstipulations from both countries and from EU (Transelectrica Nuclearelectrica and TEIAŞ will in this respect support the Designer in this process)

bullContain the necessary documentation for obtaining permits and approvals in accordance with existing legislation in Romania and in Turkey as applicable at the date of project elaboration and corresponding to this phase of the engineeringbullContain the necessary documentation to obtain the urbanism certificatebullAnalyse the financial and economical feasibility of the interconnection project considering private benefits and costs and external effects such as public benefits and costsbullAssess suitable possibilities to finance the ProjectbullPropose a time schedule for project implementation and operationbullHighlight the commercial environmental and technical conditions of direct interconnection of the national grids of Turkey and Romania through a submarine cable across the Black Sea through system studies performed in both countries

Technical Specifications for procurement and execution will include at least a minimalcontent as follows- Scope- Definitions- Standard and recommendations- Functional and technical requirements- Testing and inspections- Execution- Provision of information1048707 Terms of Reference for procuring the services and work required for the seabed survey and geological study will be established based on our experience in similar projects For the feasibility study we will perform a study based on existing materialsdocumentation related to Black Sea seabed survey and geological studies1048707

1 Inception report (within 6 weeks of commencement of the project)2 Terms of Reference for the Seabed survey and Geological Study (The draftissue to be submitted within 6 weeks of commencement of the assignment)3 Plans and Terms of Reference for the Environmental Impact assessment (Tobe submitted as an annex to the first Progress report)4 Environmental Impact Assessment (EIA) incl environmental approvals (The draftissue within 8 months and the final issue within 10 months after the commencementof the assignment)5 Feasibility Study ndash draft incl the necessary documents for approvals and advices(8 months after commencement of the assignment)6 Feasibility Study ndash final incl approvals and advices (10 months aftercommencement of the assignment)7 Documentation for urbanism certificates in Romania and Turkey (10 months aftercommencement of the assignment)8 Technical Specifications (Within 14 months after the commencement of theproject)9 Progress Reports (To be reported quarterly no later than the 10th working day afterthe reporting period)10 Final Report (The final report shall be submitted upon finalisation of the assignement

DELIVERABLES

- Costs for Submarine cables - material and installation- Costs for HVDC land cables andor HVDC OHTLs andor HVAC ndash type overhead electriclines as applicable in Romania ndash material and installations- Costs for HVDC land cables andor HVDC OHTLs andor HVAC ndash type overhead electriclines as applicable in Turkey ndash material and installations- Costs for converter station including the AC connection in Romania- Costs for converter station including the AC connection in Turkey- Telecommunication equipment based on optical fibers- Site costs in Romania- Site costs in Turkey- Engineering project management project control and commissioning- Other investments if any- Interest rates during construction calculated separately for each of the above mentionedparts of the HVDC link- Total investment costs for the HVDC link- Payment for provisional and final expropriations

Investment needs - Investments in the HVDC Link

Investments in the Romanian AC Grid- AC grid investments exclusive the breaker bay for the HVDC link- Telecommunication and remote control equipment- Interest rates calculated separately for each part- Total investments due to the HVDC link in the Romanian AC grid

Investments in the Turkish AC Grid- AC grid investments exclusive the breaker bay for the HVDC link- Telecommunication and remote control equipment- Interest rates during construction calculated separately for each part- Total investments due to the HVDC link in the Turkish AC grid

Investment needs - Investments in the Romanian and Turkish AC grids

ldquoThe price forecast has to be calculated from different perspectivesbull Long term off-take contract 60 and 80 bull Market price for the remaining 40 and 20 bull Sufficient Average Price Level (SAPL)

COMMERCIAL and FINANCIAL ANALYSIS

ldquoBased on the recommended investment and operational plan the Designer shall establish a financial model and analyse the investment over a time horizon of both 20 years operation and 30 years operation The output of the model shall be presented in nominal terms

Tranzit scenarios 1000 MW from Romania to Turkey

Tranzit scenarios 1000 MW from UCTE (PolandampSlovakia) to

Turkey

Tranzit scenarios 1000 MW from Russia (IPSUPS) to Turkey

budget

Tranzit scenarios 1000 MW from Turkey to Romania

Tranzit scenarios1000 MW from Turkey to UCTE (Serbia and

Austria)

Activities to be done in parallel with the feasibilty study

bull Preliminary business model

ndash List of main commercial regulatory and financial hypothesys

ndash Documentation on the business experience of existing commercial interconnectors in EU

ndash Discussions and clarifications with the regulatory authorities

ndash Legal due diligence for the preliminary business model

ndash TOR for the complete business study

bull Exploration and identification of potential private partners

ndash Letters of intent

ndash Develop procedure for the selection of the private investors

bull Full clarifications on TEIAS participation in the project including Turkish applicable legislation

bull Preliminary legal preparations for the project company ( SPV )

Opportunity StudyJoint Position Paper

Feasibility Study( 75 TEL- 25 NE ) Business Study

Joint Position Paper - Final

International Agreement between

Romania and Turkey

Project implementationFinancing contracting supply and instalation

MOU -1MOU -1

MOU -2 MOU -2

Selection of private investors SPV ndash the project company

2005

2008 - 2009

2009

2010

2010 - 2013

022009

First tentative road map

THANK YOU FOR YOUR ATTENTION

e-mail relatiiinvestitoritranselectricaro razvanpurdilatranselectricaro

phone +40213035923fax +40213035880web-site wwwtranselectricaro

  • Regional Transmission Network Development Implications for Trade and Investment
  • Slide 2
  • Slide 4
  • Slide 5
  • Slide 6
  • Slide 7
  • Slide 8
  • Slide 9
  • Slide 11
  • Slide 12
  • Slide 13
  • Slide 14
  • Slide 15
  • Slide 16
  • Slide 17
  • Slide 18
  • Slide 19
  • Slide 20
  • Slide 21
  • Slide 22
  • Slide 23
  • Slide 24
  • Slide 25
  • Slide 27
  • Slide 28
  • Slide 29
  • Slide 30
  • Slide 31
  • Activities to be done in parallel with the feasibilty study
  • Slide 34
  • Slide 35
Page 14: R EGIONAL T RANSMISSION N ETWORK D EVELOPMENT : I MPLICATIONS FOR T RADE AND I NVESTMENT R EGIONAL T RANSMISSION N ETWORK D EVELOPMENT : I MPLICATIONS.

Electricity market team

Technical team

Economical institutional and legal

commercial and financial team

- Environment expert- See bead expert- Overhead

transmission line expert

- Electrical substation expert

- Converter expert- HVDC submarine

cable expert- Permits and

approvals expert

- Contract legislation expert

- Price electricity forecasting expert

- Electricity market expert

- Macroeconomic modeling expert

- Financial analyze expert

- Investment analyze expert

- Contract legislation expert

- Romanian amp international legislation expert

Environmental team

Procurement team

- Commercial expert- Overhead

transmission line expert

- Electrical substation expert

- Converter expert- HVDC submarine

cable expert- Environment expert

- Environment expert- Romanian amp

international legislation expert

- Permits and approvals expert

EXPERT TEAMS

The Feasibility Study will

Establish the design parameters capacity and cost estimation for the HVDC link including the most suitable routing based on previous studies and existing data which include geological morphological and seabed structure analyze and initial sea depth survey as well as on its own investigations

Assess the legal and environmental impediments and propose the most appropriate and viable way forward for the Project from an operational and legal framework point of view including also the EIA Study with the afferent approvals in accordance with legalstipulations from both countries and from EU (Transelectrica Nuclearelectrica and TEIAŞ will in this respect support the Designer in this process)

bullContain the necessary documentation for obtaining permits and approvals in accordance with existing legislation in Romania and in Turkey as applicable at the date of project elaboration and corresponding to this phase of the engineeringbullContain the necessary documentation to obtain the urbanism certificatebullAnalyse the financial and economical feasibility of the interconnection project considering private benefits and costs and external effects such as public benefits and costsbullAssess suitable possibilities to finance the ProjectbullPropose a time schedule for project implementation and operationbullHighlight the commercial environmental and technical conditions of direct interconnection of the national grids of Turkey and Romania through a submarine cable across the Black Sea through system studies performed in both countries

Technical Specifications for procurement and execution will include at least a minimalcontent as follows- Scope- Definitions- Standard and recommendations- Functional and technical requirements- Testing and inspections- Execution- Provision of information1048707 Terms of Reference for procuring the services and work required for the seabed survey and geological study will be established based on our experience in similar projects For the feasibility study we will perform a study based on existing materialsdocumentation related to Black Sea seabed survey and geological studies1048707

1 Inception report (within 6 weeks of commencement of the project)2 Terms of Reference for the Seabed survey and Geological Study (The draftissue to be submitted within 6 weeks of commencement of the assignment)3 Plans and Terms of Reference for the Environmental Impact assessment (Tobe submitted as an annex to the first Progress report)4 Environmental Impact Assessment (EIA) incl environmental approvals (The draftissue within 8 months and the final issue within 10 months after the commencementof the assignment)5 Feasibility Study ndash draft incl the necessary documents for approvals and advices(8 months after commencement of the assignment)6 Feasibility Study ndash final incl approvals and advices (10 months aftercommencement of the assignment)7 Documentation for urbanism certificates in Romania and Turkey (10 months aftercommencement of the assignment)8 Technical Specifications (Within 14 months after the commencement of theproject)9 Progress Reports (To be reported quarterly no later than the 10th working day afterthe reporting period)10 Final Report (The final report shall be submitted upon finalisation of the assignement

DELIVERABLES

- Costs for Submarine cables - material and installation- Costs for HVDC land cables andor HVDC OHTLs andor HVAC ndash type overhead electriclines as applicable in Romania ndash material and installations- Costs for HVDC land cables andor HVDC OHTLs andor HVAC ndash type overhead electriclines as applicable in Turkey ndash material and installations- Costs for converter station including the AC connection in Romania- Costs for converter station including the AC connection in Turkey- Telecommunication equipment based on optical fibers- Site costs in Romania- Site costs in Turkey- Engineering project management project control and commissioning- Other investments if any- Interest rates during construction calculated separately for each of the above mentionedparts of the HVDC link- Total investment costs for the HVDC link- Payment for provisional and final expropriations

Investment needs - Investments in the HVDC Link

Investments in the Romanian AC Grid- AC grid investments exclusive the breaker bay for the HVDC link- Telecommunication and remote control equipment- Interest rates calculated separately for each part- Total investments due to the HVDC link in the Romanian AC grid

Investments in the Turkish AC Grid- AC grid investments exclusive the breaker bay for the HVDC link- Telecommunication and remote control equipment- Interest rates during construction calculated separately for each part- Total investments due to the HVDC link in the Turkish AC grid

Investment needs - Investments in the Romanian and Turkish AC grids

ldquoThe price forecast has to be calculated from different perspectivesbull Long term off-take contract 60 and 80 bull Market price for the remaining 40 and 20 bull Sufficient Average Price Level (SAPL)

COMMERCIAL and FINANCIAL ANALYSIS

ldquoBased on the recommended investment and operational plan the Designer shall establish a financial model and analyse the investment over a time horizon of both 20 years operation and 30 years operation The output of the model shall be presented in nominal terms

Tranzit scenarios 1000 MW from Romania to Turkey

Tranzit scenarios 1000 MW from UCTE (PolandampSlovakia) to

Turkey

Tranzit scenarios 1000 MW from Russia (IPSUPS) to Turkey

budget

Tranzit scenarios 1000 MW from Turkey to Romania

Tranzit scenarios1000 MW from Turkey to UCTE (Serbia and

Austria)

Activities to be done in parallel with the feasibilty study

bull Preliminary business model

ndash List of main commercial regulatory and financial hypothesys

ndash Documentation on the business experience of existing commercial interconnectors in EU

ndash Discussions and clarifications with the regulatory authorities

ndash Legal due diligence for the preliminary business model

ndash TOR for the complete business study

bull Exploration and identification of potential private partners

ndash Letters of intent

ndash Develop procedure for the selection of the private investors

bull Full clarifications on TEIAS participation in the project including Turkish applicable legislation

bull Preliminary legal preparations for the project company ( SPV )

Opportunity StudyJoint Position Paper

Feasibility Study( 75 TEL- 25 NE ) Business Study

Joint Position Paper - Final

International Agreement between

Romania and Turkey

Project implementationFinancing contracting supply and instalation

MOU -1MOU -1

MOU -2 MOU -2

Selection of private investors SPV ndash the project company

2005

2008 - 2009

2009

2010

2010 - 2013

022009

First tentative road map

THANK YOU FOR YOUR ATTENTION

e-mail relatiiinvestitoritranselectricaro razvanpurdilatranselectricaro

phone +40213035923fax +40213035880web-site wwwtranselectricaro

  • Regional Transmission Network Development Implications for Trade and Investment
  • Slide 2
  • Slide 4
  • Slide 5
  • Slide 6
  • Slide 7
  • Slide 8
  • Slide 9
  • Slide 11
  • Slide 12
  • Slide 13
  • Slide 14
  • Slide 15
  • Slide 16
  • Slide 17
  • Slide 18
  • Slide 19
  • Slide 20
  • Slide 21
  • Slide 22
  • Slide 23
  • Slide 24
  • Slide 25
  • Slide 27
  • Slide 28
  • Slide 29
  • Slide 30
  • Slide 31
  • Activities to be done in parallel with the feasibilty study
  • Slide 34
  • Slide 35
Page 15: R EGIONAL T RANSMISSION N ETWORK D EVELOPMENT : I MPLICATIONS FOR T RADE AND I NVESTMENT R EGIONAL T RANSMISSION N ETWORK D EVELOPMENT : I MPLICATIONS.

The Feasibility Study will

Establish the design parameters capacity and cost estimation for the HVDC link including the most suitable routing based on previous studies and existing data which include geological morphological and seabed structure analyze and initial sea depth survey as well as on its own investigations

Assess the legal and environmental impediments and propose the most appropriate and viable way forward for the Project from an operational and legal framework point of view including also the EIA Study with the afferent approvals in accordance with legalstipulations from both countries and from EU (Transelectrica Nuclearelectrica and TEIAŞ will in this respect support the Designer in this process)

bullContain the necessary documentation for obtaining permits and approvals in accordance with existing legislation in Romania and in Turkey as applicable at the date of project elaboration and corresponding to this phase of the engineeringbullContain the necessary documentation to obtain the urbanism certificatebullAnalyse the financial and economical feasibility of the interconnection project considering private benefits and costs and external effects such as public benefits and costsbullAssess suitable possibilities to finance the ProjectbullPropose a time schedule for project implementation and operationbullHighlight the commercial environmental and technical conditions of direct interconnection of the national grids of Turkey and Romania through a submarine cable across the Black Sea through system studies performed in both countries

Technical Specifications for procurement and execution will include at least a minimalcontent as follows- Scope- Definitions- Standard and recommendations- Functional and technical requirements- Testing and inspections- Execution- Provision of information1048707 Terms of Reference for procuring the services and work required for the seabed survey and geological study will be established based on our experience in similar projects For the feasibility study we will perform a study based on existing materialsdocumentation related to Black Sea seabed survey and geological studies1048707

1 Inception report (within 6 weeks of commencement of the project)2 Terms of Reference for the Seabed survey and Geological Study (The draftissue to be submitted within 6 weeks of commencement of the assignment)3 Plans and Terms of Reference for the Environmental Impact assessment (Tobe submitted as an annex to the first Progress report)4 Environmental Impact Assessment (EIA) incl environmental approvals (The draftissue within 8 months and the final issue within 10 months after the commencementof the assignment)5 Feasibility Study ndash draft incl the necessary documents for approvals and advices(8 months after commencement of the assignment)6 Feasibility Study ndash final incl approvals and advices (10 months aftercommencement of the assignment)7 Documentation for urbanism certificates in Romania and Turkey (10 months aftercommencement of the assignment)8 Technical Specifications (Within 14 months after the commencement of theproject)9 Progress Reports (To be reported quarterly no later than the 10th working day afterthe reporting period)10 Final Report (The final report shall be submitted upon finalisation of the assignement

DELIVERABLES

- Costs for Submarine cables - material and installation- Costs for HVDC land cables andor HVDC OHTLs andor HVAC ndash type overhead electriclines as applicable in Romania ndash material and installations- Costs for HVDC land cables andor HVDC OHTLs andor HVAC ndash type overhead electriclines as applicable in Turkey ndash material and installations- Costs for converter station including the AC connection in Romania- Costs for converter station including the AC connection in Turkey- Telecommunication equipment based on optical fibers- Site costs in Romania- Site costs in Turkey- Engineering project management project control and commissioning- Other investments if any- Interest rates during construction calculated separately for each of the above mentionedparts of the HVDC link- Total investment costs for the HVDC link- Payment for provisional and final expropriations

Investment needs - Investments in the HVDC Link

Investments in the Romanian AC Grid- AC grid investments exclusive the breaker bay for the HVDC link- Telecommunication and remote control equipment- Interest rates calculated separately for each part- Total investments due to the HVDC link in the Romanian AC grid

Investments in the Turkish AC Grid- AC grid investments exclusive the breaker bay for the HVDC link- Telecommunication and remote control equipment- Interest rates during construction calculated separately for each part- Total investments due to the HVDC link in the Turkish AC grid

Investment needs - Investments in the Romanian and Turkish AC grids

ldquoThe price forecast has to be calculated from different perspectivesbull Long term off-take contract 60 and 80 bull Market price for the remaining 40 and 20 bull Sufficient Average Price Level (SAPL)

COMMERCIAL and FINANCIAL ANALYSIS

ldquoBased on the recommended investment and operational plan the Designer shall establish a financial model and analyse the investment over a time horizon of both 20 years operation and 30 years operation The output of the model shall be presented in nominal terms

Tranzit scenarios 1000 MW from Romania to Turkey

Tranzit scenarios 1000 MW from UCTE (PolandampSlovakia) to

Turkey

Tranzit scenarios 1000 MW from Russia (IPSUPS) to Turkey

budget

Tranzit scenarios 1000 MW from Turkey to Romania

Tranzit scenarios1000 MW from Turkey to UCTE (Serbia and

Austria)

Activities to be done in parallel with the feasibilty study

bull Preliminary business model

ndash List of main commercial regulatory and financial hypothesys

ndash Documentation on the business experience of existing commercial interconnectors in EU

ndash Discussions and clarifications with the regulatory authorities

ndash Legal due diligence for the preliminary business model

ndash TOR for the complete business study

bull Exploration and identification of potential private partners

ndash Letters of intent

ndash Develop procedure for the selection of the private investors

bull Full clarifications on TEIAS participation in the project including Turkish applicable legislation

bull Preliminary legal preparations for the project company ( SPV )

Opportunity StudyJoint Position Paper

Feasibility Study( 75 TEL- 25 NE ) Business Study

Joint Position Paper - Final

International Agreement between

Romania and Turkey

Project implementationFinancing contracting supply and instalation

MOU -1MOU -1

MOU -2 MOU -2

Selection of private investors SPV ndash the project company

2005

2008 - 2009

2009

2010

2010 - 2013

022009

First tentative road map

THANK YOU FOR YOUR ATTENTION

e-mail relatiiinvestitoritranselectricaro razvanpurdilatranselectricaro

phone +40213035923fax +40213035880web-site wwwtranselectricaro

  • Regional Transmission Network Development Implications for Trade and Investment
  • Slide 2
  • Slide 4
  • Slide 5
  • Slide 6
  • Slide 7
  • Slide 8
  • Slide 9
  • Slide 11
  • Slide 12
  • Slide 13
  • Slide 14
  • Slide 15
  • Slide 16
  • Slide 17
  • Slide 18
  • Slide 19
  • Slide 20
  • Slide 21
  • Slide 22
  • Slide 23
  • Slide 24
  • Slide 25
  • Slide 27
  • Slide 28
  • Slide 29
  • Slide 30
  • Slide 31
  • Activities to be done in parallel with the feasibilty study
  • Slide 34
  • Slide 35
Page 16: R EGIONAL T RANSMISSION N ETWORK D EVELOPMENT : I MPLICATIONS FOR T RADE AND I NVESTMENT R EGIONAL T RANSMISSION N ETWORK D EVELOPMENT : I MPLICATIONS.

bullContain the necessary documentation for obtaining permits and approvals in accordance with existing legislation in Romania and in Turkey as applicable at the date of project elaboration and corresponding to this phase of the engineeringbullContain the necessary documentation to obtain the urbanism certificatebullAnalyse the financial and economical feasibility of the interconnection project considering private benefits and costs and external effects such as public benefits and costsbullAssess suitable possibilities to finance the ProjectbullPropose a time schedule for project implementation and operationbullHighlight the commercial environmental and technical conditions of direct interconnection of the national grids of Turkey and Romania through a submarine cable across the Black Sea through system studies performed in both countries

Technical Specifications for procurement and execution will include at least a minimalcontent as follows- Scope- Definitions- Standard and recommendations- Functional and technical requirements- Testing and inspections- Execution- Provision of information1048707 Terms of Reference for procuring the services and work required for the seabed survey and geological study will be established based on our experience in similar projects For the feasibility study we will perform a study based on existing materialsdocumentation related to Black Sea seabed survey and geological studies1048707

1 Inception report (within 6 weeks of commencement of the project)2 Terms of Reference for the Seabed survey and Geological Study (The draftissue to be submitted within 6 weeks of commencement of the assignment)3 Plans and Terms of Reference for the Environmental Impact assessment (Tobe submitted as an annex to the first Progress report)4 Environmental Impact Assessment (EIA) incl environmental approvals (The draftissue within 8 months and the final issue within 10 months after the commencementof the assignment)5 Feasibility Study ndash draft incl the necessary documents for approvals and advices(8 months after commencement of the assignment)6 Feasibility Study ndash final incl approvals and advices (10 months aftercommencement of the assignment)7 Documentation for urbanism certificates in Romania and Turkey (10 months aftercommencement of the assignment)8 Technical Specifications (Within 14 months after the commencement of theproject)9 Progress Reports (To be reported quarterly no later than the 10th working day afterthe reporting period)10 Final Report (The final report shall be submitted upon finalisation of the assignement

DELIVERABLES

- Costs for Submarine cables - material and installation- Costs for HVDC land cables andor HVDC OHTLs andor HVAC ndash type overhead electriclines as applicable in Romania ndash material and installations- Costs for HVDC land cables andor HVDC OHTLs andor HVAC ndash type overhead electriclines as applicable in Turkey ndash material and installations- Costs for converter station including the AC connection in Romania- Costs for converter station including the AC connection in Turkey- Telecommunication equipment based on optical fibers- Site costs in Romania- Site costs in Turkey- Engineering project management project control and commissioning- Other investments if any- Interest rates during construction calculated separately for each of the above mentionedparts of the HVDC link- Total investment costs for the HVDC link- Payment for provisional and final expropriations

Investment needs - Investments in the HVDC Link

Investments in the Romanian AC Grid- AC grid investments exclusive the breaker bay for the HVDC link- Telecommunication and remote control equipment- Interest rates calculated separately for each part- Total investments due to the HVDC link in the Romanian AC grid

Investments in the Turkish AC Grid- AC grid investments exclusive the breaker bay for the HVDC link- Telecommunication and remote control equipment- Interest rates during construction calculated separately for each part- Total investments due to the HVDC link in the Turkish AC grid

Investment needs - Investments in the Romanian and Turkish AC grids

ldquoThe price forecast has to be calculated from different perspectivesbull Long term off-take contract 60 and 80 bull Market price for the remaining 40 and 20 bull Sufficient Average Price Level (SAPL)

COMMERCIAL and FINANCIAL ANALYSIS

ldquoBased on the recommended investment and operational plan the Designer shall establish a financial model and analyse the investment over a time horizon of both 20 years operation and 30 years operation The output of the model shall be presented in nominal terms

Tranzit scenarios 1000 MW from Romania to Turkey

Tranzit scenarios 1000 MW from UCTE (PolandampSlovakia) to

Turkey

Tranzit scenarios 1000 MW from Russia (IPSUPS) to Turkey

budget

Tranzit scenarios 1000 MW from Turkey to Romania

Tranzit scenarios1000 MW from Turkey to UCTE (Serbia and

Austria)

Activities to be done in parallel with the feasibilty study

bull Preliminary business model

ndash List of main commercial regulatory and financial hypothesys

ndash Documentation on the business experience of existing commercial interconnectors in EU

ndash Discussions and clarifications with the regulatory authorities

ndash Legal due diligence for the preliminary business model

ndash TOR for the complete business study

bull Exploration and identification of potential private partners

ndash Letters of intent

ndash Develop procedure for the selection of the private investors

bull Full clarifications on TEIAS participation in the project including Turkish applicable legislation

bull Preliminary legal preparations for the project company ( SPV )

Opportunity StudyJoint Position Paper

Feasibility Study( 75 TEL- 25 NE ) Business Study

Joint Position Paper - Final

International Agreement between

Romania and Turkey

Project implementationFinancing contracting supply and instalation

MOU -1MOU -1

MOU -2 MOU -2

Selection of private investors SPV ndash the project company

2005

2008 - 2009

2009

2010

2010 - 2013

022009

First tentative road map

THANK YOU FOR YOUR ATTENTION

e-mail relatiiinvestitoritranselectricaro razvanpurdilatranselectricaro

phone +40213035923fax +40213035880web-site wwwtranselectricaro

  • Regional Transmission Network Development Implications for Trade and Investment
  • Slide 2
  • Slide 4
  • Slide 5
  • Slide 6
  • Slide 7
  • Slide 8
  • Slide 9
  • Slide 11
  • Slide 12
  • Slide 13
  • Slide 14
  • Slide 15
  • Slide 16
  • Slide 17
  • Slide 18
  • Slide 19
  • Slide 20
  • Slide 21
  • Slide 22
  • Slide 23
  • Slide 24
  • Slide 25
  • Slide 27
  • Slide 28
  • Slide 29
  • Slide 30
  • Slide 31
  • Activities to be done in parallel with the feasibilty study
  • Slide 34
  • Slide 35
Page 17: R EGIONAL T RANSMISSION N ETWORK D EVELOPMENT : I MPLICATIONS FOR T RADE AND I NVESTMENT R EGIONAL T RANSMISSION N ETWORK D EVELOPMENT : I MPLICATIONS.

Technical Specifications for procurement and execution will include at least a minimalcontent as follows- Scope- Definitions- Standard and recommendations- Functional and technical requirements- Testing and inspections- Execution- Provision of information1048707 Terms of Reference for procuring the services and work required for the seabed survey and geological study will be established based on our experience in similar projects For the feasibility study we will perform a study based on existing materialsdocumentation related to Black Sea seabed survey and geological studies1048707

1 Inception report (within 6 weeks of commencement of the project)2 Terms of Reference for the Seabed survey and Geological Study (The draftissue to be submitted within 6 weeks of commencement of the assignment)3 Plans and Terms of Reference for the Environmental Impact assessment (Tobe submitted as an annex to the first Progress report)4 Environmental Impact Assessment (EIA) incl environmental approvals (The draftissue within 8 months and the final issue within 10 months after the commencementof the assignment)5 Feasibility Study ndash draft incl the necessary documents for approvals and advices(8 months after commencement of the assignment)6 Feasibility Study ndash final incl approvals and advices (10 months aftercommencement of the assignment)7 Documentation for urbanism certificates in Romania and Turkey (10 months aftercommencement of the assignment)8 Technical Specifications (Within 14 months after the commencement of theproject)9 Progress Reports (To be reported quarterly no later than the 10th working day afterthe reporting period)10 Final Report (The final report shall be submitted upon finalisation of the assignement

DELIVERABLES

- Costs for Submarine cables - material and installation- Costs for HVDC land cables andor HVDC OHTLs andor HVAC ndash type overhead electriclines as applicable in Romania ndash material and installations- Costs for HVDC land cables andor HVDC OHTLs andor HVAC ndash type overhead electriclines as applicable in Turkey ndash material and installations- Costs for converter station including the AC connection in Romania- Costs for converter station including the AC connection in Turkey- Telecommunication equipment based on optical fibers- Site costs in Romania- Site costs in Turkey- Engineering project management project control and commissioning- Other investments if any- Interest rates during construction calculated separately for each of the above mentionedparts of the HVDC link- Total investment costs for the HVDC link- Payment for provisional and final expropriations

Investment needs - Investments in the HVDC Link

Investments in the Romanian AC Grid- AC grid investments exclusive the breaker bay for the HVDC link- Telecommunication and remote control equipment- Interest rates calculated separately for each part- Total investments due to the HVDC link in the Romanian AC grid

Investments in the Turkish AC Grid- AC grid investments exclusive the breaker bay for the HVDC link- Telecommunication and remote control equipment- Interest rates during construction calculated separately for each part- Total investments due to the HVDC link in the Turkish AC grid

Investment needs - Investments in the Romanian and Turkish AC grids

ldquoThe price forecast has to be calculated from different perspectivesbull Long term off-take contract 60 and 80 bull Market price for the remaining 40 and 20 bull Sufficient Average Price Level (SAPL)

COMMERCIAL and FINANCIAL ANALYSIS

ldquoBased on the recommended investment and operational plan the Designer shall establish a financial model and analyse the investment over a time horizon of both 20 years operation and 30 years operation The output of the model shall be presented in nominal terms

Tranzit scenarios 1000 MW from Romania to Turkey

Tranzit scenarios 1000 MW from UCTE (PolandampSlovakia) to

Turkey

Tranzit scenarios 1000 MW from Russia (IPSUPS) to Turkey

budget

Tranzit scenarios 1000 MW from Turkey to Romania

Tranzit scenarios1000 MW from Turkey to UCTE (Serbia and

Austria)

Activities to be done in parallel with the feasibilty study

bull Preliminary business model

ndash List of main commercial regulatory and financial hypothesys

ndash Documentation on the business experience of existing commercial interconnectors in EU

ndash Discussions and clarifications with the regulatory authorities

ndash Legal due diligence for the preliminary business model

ndash TOR for the complete business study

bull Exploration and identification of potential private partners

ndash Letters of intent

ndash Develop procedure for the selection of the private investors

bull Full clarifications on TEIAS participation in the project including Turkish applicable legislation

bull Preliminary legal preparations for the project company ( SPV )

Opportunity StudyJoint Position Paper

Feasibility Study( 75 TEL- 25 NE ) Business Study

Joint Position Paper - Final

International Agreement between

Romania and Turkey

Project implementationFinancing contracting supply and instalation

MOU -1MOU -1

MOU -2 MOU -2

Selection of private investors SPV ndash the project company

2005

2008 - 2009

2009

2010

2010 - 2013

022009

First tentative road map

THANK YOU FOR YOUR ATTENTION

e-mail relatiiinvestitoritranselectricaro razvanpurdilatranselectricaro

phone +40213035923fax +40213035880web-site wwwtranselectricaro

  • Regional Transmission Network Development Implications for Trade and Investment
  • Slide 2
  • Slide 4
  • Slide 5
  • Slide 6
  • Slide 7
  • Slide 8
  • Slide 9
  • Slide 11
  • Slide 12
  • Slide 13
  • Slide 14
  • Slide 15
  • Slide 16
  • Slide 17
  • Slide 18
  • Slide 19
  • Slide 20
  • Slide 21
  • Slide 22
  • Slide 23
  • Slide 24
  • Slide 25
  • Slide 27
  • Slide 28
  • Slide 29
  • Slide 30
  • Slide 31
  • Activities to be done in parallel with the feasibilty study
  • Slide 34
  • Slide 35
Page 18: R EGIONAL T RANSMISSION N ETWORK D EVELOPMENT : I MPLICATIONS FOR T RADE AND I NVESTMENT R EGIONAL T RANSMISSION N ETWORK D EVELOPMENT : I MPLICATIONS.

1 Inception report (within 6 weeks of commencement of the project)2 Terms of Reference for the Seabed survey and Geological Study (The draftissue to be submitted within 6 weeks of commencement of the assignment)3 Plans and Terms of Reference for the Environmental Impact assessment (Tobe submitted as an annex to the first Progress report)4 Environmental Impact Assessment (EIA) incl environmental approvals (The draftissue within 8 months and the final issue within 10 months after the commencementof the assignment)5 Feasibility Study ndash draft incl the necessary documents for approvals and advices(8 months after commencement of the assignment)6 Feasibility Study ndash final incl approvals and advices (10 months aftercommencement of the assignment)7 Documentation for urbanism certificates in Romania and Turkey (10 months aftercommencement of the assignment)8 Technical Specifications (Within 14 months after the commencement of theproject)9 Progress Reports (To be reported quarterly no later than the 10th working day afterthe reporting period)10 Final Report (The final report shall be submitted upon finalisation of the assignement

DELIVERABLES

- Costs for Submarine cables - material and installation- Costs for HVDC land cables andor HVDC OHTLs andor HVAC ndash type overhead electriclines as applicable in Romania ndash material and installations- Costs for HVDC land cables andor HVDC OHTLs andor HVAC ndash type overhead electriclines as applicable in Turkey ndash material and installations- Costs for converter station including the AC connection in Romania- Costs for converter station including the AC connection in Turkey- Telecommunication equipment based on optical fibers- Site costs in Romania- Site costs in Turkey- Engineering project management project control and commissioning- Other investments if any- Interest rates during construction calculated separately for each of the above mentionedparts of the HVDC link- Total investment costs for the HVDC link- Payment for provisional and final expropriations

Investment needs - Investments in the HVDC Link

Investments in the Romanian AC Grid- AC grid investments exclusive the breaker bay for the HVDC link- Telecommunication and remote control equipment- Interest rates calculated separately for each part- Total investments due to the HVDC link in the Romanian AC grid

Investments in the Turkish AC Grid- AC grid investments exclusive the breaker bay for the HVDC link- Telecommunication and remote control equipment- Interest rates during construction calculated separately for each part- Total investments due to the HVDC link in the Turkish AC grid

Investment needs - Investments in the Romanian and Turkish AC grids

ldquoThe price forecast has to be calculated from different perspectivesbull Long term off-take contract 60 and 80 bull Market price for the remaining 40 and 20 bull Sufficient Average Price Level (SAPL)

COMMERCIAL and FINANCIAL ANALYSIS

ldquoBased on the recommended investment and operational plan the Designer shall establish a financial model and analyse the investment over a time horizon of both 20 years operation and 30 years operation The output of the model shall be presented in nominal terms

Tranzit scenarios 1000 MW from Romania to Turkey

Tranzit scenarios 1000 MW from UCTE (PolandampSlovakia) to

Turkey

Tranzit scenarios 1000 MW from Russia (IPSUPS) to Turkey

budget

Tranzit scenarios 1000 MW from Turkey to Romania

Tranzit scenarios1000 MW from Turkey to UCTE (Serbia and

Austria)

Activities to be done in parallel with the feasibilty study

bull Preliminary business model

ndash List of main commercial regulatory and financial hypothesys

ndash Documentation on the business experience of existing commercial interconnectors in EU

ndash Discussions and clarifications with the regulatory authorities

ndash Legal due diligence for the preliminary business model

ndash TOR for the complete business study

bull Exploration and identification of potential private partners

ndash Letters of intent

ndash Develop procedure for the selection of the private investors

bull Full clarifications on TEIAS participation in the project including Turkish applicable legislation

bull Preliminary legal preparations for the project company ( SPV )

Opportunity StudyJoint Position Paper

Feasibility Study( 75 TEL- 25 NE ) Business Study

Joint Position Paper - Final

International Agreement between

Romania and Turkey

Project implementationFinancing contracting supply and instalation

MOU -1MOU -1

MOU -2 MOU -2

Selection of private investors SPV ndash the project company

2005

2008 - 2009

2009

2010

2010 - 2013

022009

First tentative road map

THANK YOU FOR YOUR ATTENTION

e-mail relatiiinvestitoritranselectricaro razvanpurdilatranselectricaro

phone +40213035923fax +40213035880web-site wwwtranselectricaro

  • Regional Transmission Network Development Implications for Trade and Investment
  • Slide 2
  • Slide 4
  • Slide 5
  • Slide 6
  • Slide 7
  • Slide 8
  • Slide 9
  • Slide 11
  • Slide 12
  • Slide 13
  • Slide 14
  • Slide 15
  • Slide 16
  • Slide 17
  • Slide 18
  • Slide 19
  • Slide 20
  • Slide 21
  • Slide 22
  • Slide 23
  • Slide 24
  • Slide 25
  • Slide 27
  • Slide 28
  • Slide 29
  • Slide 30
  • Slide 31
  • Activities to be done in parallel with the feasibilty study
  • Slide 34
  • Slide 35
Page 19: R EGIONAL T RANSMISSION N ETWORK D EVELOPMENT : I MPLICATIONS FOR T RADE AND I NVESTMENT R EGIONAL T RANSMISSION N ETWORK D EVELOPMENT : I MPLICATIONS.

- Costs for Submarine cables - material and installation- Costs for HVDC land cables andor HVDC OHTLs andor HVAC ndash type overhead electriclines as applicable in Romania ndash material and installations- Costs for HVDC land cables andor HVDC OHTLs andor HVAC ndash type overhead electriclines as applicable in Turkey ndash material and installations- Costs for converter station including the AC connection in Romania- Costs for converter station including the AC connection in Turkey- Telecommunication equipment based on optical fibers- Site costs in Romania- Site costs in Turkey- Engineering project management project control and commissioning- Other investments if any- Interest rates during construction calculated separately for each of the above mentionedparts of the HVDC link- Total investment costs for the HVDC link- Payment for provisional and final expropriations

Investment needs - Investments in the HVDC Link

Investments in the Romanian AC Grid- AC grid investments exclusive the breaker bay for the HVDC link- Telecommunication and remote control equipment- Interest rates calculated separately for each part- Total investments due to the HVDC link in the Romanian AC grid

Investments in the Turkish AC Grid- AC grid investments exclusive the breaker bay for the HVDC link- Telecommunication and remote control equipment- Interest rates during construction calculated separately for each part- Total investments due to the HVDC link in the Turkish AC grid

Investment needs - Investments in the Romanian and Turkish AC grids

ldquoThe price forecast has to be calculated from different perspectivesbull Long term off-take contract 60 and 80 bull Market price for the remaining 40 and 20 bull Sufficient Average Price Level (SAPL)

COMMERCIAL and FINANCIAL ANALYSIS

ldquoBased on the recommended investment and operational plan the Designer shall establish a financial model and analyse the investment over a time horizon of both 20 years operation and 30 years operation The output of the model shall be presented in nominal terms

Tranzit scenarios 1000 MW from Romania to Turkey

Tranzit scenarios 1000 MW from UCTE (PolandampSlovakia) to

Turkey

Tranzit scenarios 1000 MW from Russia (IPSUPS) to Turkey

budget

Tranzit scenarios 1000 MW from Turkey to Romania

Tranzit scenarios1000 MW from Turkey to UCTE (Serbia and

Austria)

Activities to be done in parallel with the feasibilty study

bull Preliminary business model

ndash List of main commercial regulatory and financial hypothesys

ndash Documentation on the business experience of existing commercial interconnectors in EU

ndash Discussions and clarifications with the regulatory authorities

ndash Legal due diligence for the preliminary business model

ndash TOR for the complete business study

bull Exploration and identification of potential private partners

ndash Letters of intent

ndash Develop procedure for the selection of the private investors

bull Full clarifications on TEIAS participation in the project including Turkish applicable legislation

bull Preliminary legal preparations for the project company ( SPV )

Opportunity StudyJoint Position Paper

Feasibility Study( 75 TEL- 25 NE ) Business Study

Joint Position Paper - Final

International Agreement between

Romania and Turkey

Project implementationFinancing contracting supply and instalation

MOU -1MOU -1

MOU -2 MOU -2

Selection of private investors SPV ndash the project company

2005

2008 - 2009

2009

2010

2010 - 2013

022009

First tentative road map

THANK YOU FOR YOUR ATTENTION

e-mail relatiiinvestitoritranselectricaro razvanpurdilatranselectricaro

phone +40213035923fax +40213035880web-site wwwtranselectricaro

  • Regional Transmission Network Development Implications for Trade and Investment
  • Slide 2
  • Slide 4
  • Slide 5
  • Slide 6
  • Slide 7
  • Slide 8
  • Slide 9
  • Slide 11
  • Slide 12
  • Slide 13
  • Slide 14
  • Slide 15
  • Slide 16
  • Slide 17
  • Slide 18
  • Slide 19
  • Slide 20
  • Slide 21
  • Slide 22
  • Slide 23
  • Slide 24
  • Slide 25
  • Slide 27
  • Slide 28
  • Slide 29
  • Slide 30
  • Slide 31
  • Activities to be done in parallel with the feasibilty study
  • Slide 34
  • Slide 35
Page 20: R EGIONAL T RANSMISSION N ETWORK D EVELOPMENT : I MPLICATIONS FOR T RADE AND I NVESTMENT R EGIONAL T RANSMISSION N ETWORK D EVELOPMENT : I MPLICATIONS.

Investments in the Romanian AC Grid- AC grid investments exclusive the breaker bay for the HVDC link- Telecommunication and remote control equipment- Interest rates calculated separately for each part- Total investments due to the HVDC link in the Romanian AC grid

Investments in the Turkish AC Grid- AC grid investments exclusive the breaker bay for the HVDC link- Telecommunication and remote control equipment- Interest rates during construction calculated separately for each part- Total investments due to the HVDC link in the Turkish AC grid

Investment needs - Investments in the Romanian and Turkish AC grids

ldquoThe price forecast has to be calculated from different perspectivesbull Long term off-take contract 60 and 80 bull Market price for the remaining 40 and 20 bull Sufficient Average Price Level (SAPL)

COMMERCIAL and FINANCIAL ANALYSIS

ldquoBased on the recommended investment and operational plan the Designer shall establish a financial model and analyse the investment over a time horizon of both 20 years operation and 30 years operation The output of the model shall be presented in nominal terms

Tranzit scenarios 1000 MW from Romania to Turkey

Tranzit scenarios 1000 MW from UCTE (PolandampSlovakia) to

Turkey

Tranzit scenarios 1000 MW from Russia (IPSUPS) to Turkey

budget

Tranzit scenarios 1000 MW from Turkey to Romania

Tranzit scenarios1000 MW from Turkey to UCTE (Serbia and

Austria)

Activities to be done in parallel with the feasibilty study

bull Preliminary business model

ndash List of main commercial regulatory and financial hypothesys

ndash Documentation on the business experience of existing commercial interconnectors in EU

ndash Discussions and clarifications with the regulatory authorities

ndash Legal due diligence for the preliminary business model

ndash TOR for the complete business study

bull Exploration and identification of potential private partners

ndash Letters of intent

ndash Develop procedure for the selection of the private investors

bull Full clarifications on TEIAS participation in the project including Turkish applicable legislation

bull Preliminary legal preparations for the project company ( SPV )

Opportunity StudyJoint Position Paper

Feasibility Study( 75 TEL- 25 NE ) Business Study

Joint Position Paper - Final

International Agreement between

Romania and Turkey

Project implementationFinancing contracting supply and instalation

MOU -1MOU -1

MOU -2 MOU -2

Selection of private investors SPV ndash the project company

2005

2008 - 2009

2009

2010

2010 - 2013

022009

First tentative road map

THANK YOU FOR YOUR ATTENTION

e-mail relatiiinvestitoritranselectricaro razvanpurdilatranselectricaro

phone +40213035923fax +40213035880web-site wwwtranselectricaro

  • Regional Transmission Network Development Implications for Trade and Investment
  • Slide 2
  • Slide 4
  • Slide 5
  • Slide 6
  • Slide 7
  • Slide 8
  • Slide 9
  • Slide 11
  • Slide 12
  • Slide 13
  • Slide 14
  • Slide 15
  • Slide 16
  • Slide 17
  • Slide 18
  • Slide 19
  • Slide 20
  • Slide 21
  • Slide 22
  • Slide 23
  • Slide 24
  • Slide 25
  • Slide 27
  • Slide 28
  • Slide 29
  • Slide 30
  • Slide 31
  • Activities to be done in parallel with the feasibilty study
  • Slide 34
  • Slide 35
Page 21: R EGIONAL T RANSMISSION N ETWORK D EVELOPMENT : I MPLICATIONS FOR T RADE AND I NVESTMENT R EGIONAL T RANSMISSION N ETWORK D EVELOPMENT : I MPLICATIONS.

ldquoThe price forecast has to be calculated from different perspectivesbull Long term off-take contract 60 and 80 bull Market price for the remaining 40 and 20 bull Sufficient Average Price Level (SAPL)

COMMERCIAL and FINANCIAL ANALYSIS

ldquoBased on the recommended investment and operational plan the Designer shall establish a financial model and analyse the investment over a time horizon of both 20 years operation and 30 years operation The output of the model shall be presented in nominal terms

Tranzit scenarios 1000 MW from Romania to Turkey

Tranzit scenarios 1000 MW from UCTE (PolandampSlovakia) to

Turkey

Tranzit scenarios 1000 MW from Russia (IPSUPS) to Turkey

budget

Tranzit scenarios 1000 MW from Turkey to Romania

Tranzit scenarios1000 MW from Turkey to UCTE (Serbia and

Austria)

Activities to be done in parallel with the feasibilty study

bull Preliminary business model

ndash List of main commercial regulatory and financial hypothesys

ndash Documentation on the business experience of existing commercial interconnectors in EU

ndash Discussions and clarifications with the regulatory authorities

ndash Legal due diligence for the preliminary business model

ndash TOR for the complete business study

bull Exploration and identification of potential private partners

ndash Letters of intent

ndash Develop procedure for the selection of the private investors

bull Full clarifications on TEIAS participation in the project including Turkish applicable legislation

bull Preliminary legal preparations for the project company ( SPV )

Opportunity StudyJoint Position Paper

Feasibility Study( 75 TEL- 25 NE ) Business Study

Joint Position Paper - Final

International Agreement between

Romania and Turkey

Project implementationFinancing contracting supply and instalation

MOU -1MOU -1

MOU -2 MOU -2

Selection of private investors SPV ndash the project company

2005

2008 - 2009

2009

2010

2010 - 2013

022009

First tentative road map

THANK YOU FOR YOUR ATTENTION

e-mail relatiiinvestitoritranselectricaro razvanpurdilatranselectricaro

phone +40213035923fax +40213035880web-site wwwtranselectricaro

  • Regional Transmission Network Development Implications for Trade and Investment
  • Slide 2
  • Slide 4
  • Slide 5
  • Slide 6
  • Slide 7
  • Slide 8
  • Slide 9
  • Slide 11
  • Slide 12
  • Slide 13
  • Slide 14
  • Slide 15
  • Slide 16
  • Slide 17
  • Slide 18
  • Slide 19
  • Slide 20
  • Slide 21
  • Slide 22
  • Slide 23
  • Slide 24
  • Slide 25
  • Slide 27
  • Slide 28
  • Slide 29
  • Slide 30
  • Slide 31
  • Activities to be done in parallel with the feasibilty study
  • Slide 34
  • Slide 35
Page 22: R EGIONAL T RANSMISSION N ETWORK D EVELOPMENT : I MPLICATIONS FOR T RADE AND I NVESTMENT R EGIONAL T RANSMISSION N ETWORK D EVELOPMENT : I MPLICATIONS.

Tranzit scenarios 1000 MW from Romania to Turkey

Tranzit scenarios 1000 MW from UCTE (PolandampSlovakia) to

Turkey

Tranzit scenarios 1000 MW from Russia (IPSUPS) to Turkey

budget

Tranzit scenarios 1000 MW from Turkey to Romania

Tranzit scenarios1000 MW from Turkey to UCTE (Serbia and

Austria)

Activities to be done in parallel with the feasibilty study

bull Preliminary business model

ndash List of main commercial regulatory and financial hypothesys

ndash Documentation on the business experience of existing commercial interconnectors in EU

ndash Discussions and clarifications with the regulatory authorities

ndash Legal due diligence for the preliminary business model

ndash TOR for the complete business study

bull Exploration and identification of potential private partners

ndash Letters of intent

ndash Develop procedure for the selection of the private investors

bull Full clarifications on TEIAS participation in the project including Turkish applicable legislation

bull Preliminary legal preparations for the project company ( SPV )

Opportunity StudyJoint Position Paper

Feasibility Study( 75 TEL- 25 NE ) Business Study

Joint Position Paper - Final

International Agreement between

Romania and Turkey

Project implementationFinancing contracting supply and instalation

MOU -1MOU -1

MOU -2 MOU -2

Selection of private investors SPV ndash the project company

2005

2008 - 2009

2009

2010

2010 - 2013

022009

First tentative road map

THANK YOU FOR YOUR ATTENTION

e-mail relatiiinvestitoritranselectricaro razvanpurdilatranselectricaro

phone +40213035923fax +40213035880web-site wwwtranselectricaro

  • Regional Transmission Network Development Implications for Trade and Investment
  • Slide 2
  • Slide 4
  • Slide 5
  • Slide 6
  • Slide 7
  • Slide 8
  • Slide 9
  • Slide 11
  • Slide 12
  • Slide 13
  • Slide 14
  • Slide 15
  • Slide 16
  • Slide 17
  • Slide 18
  • Slide 19
  • Slide 20
  • Slide 21
  • Slide 22
  • Slide 23
  • Slide 24
  • Slide 25
  • Slide 27
  • Slide 28
  • Slide 29
  • Slide 30
  • Slide 31
  • Activities to be done in parallel with the feasibilty study
  • Slide 34
  • Slide 35
Page 23: R EGIONAL T RANSMISSION N ETWORK D EVELOPMENT : I MPLICATIONS FOR T RADE AND I NVESTMENT R EGIONAL T RANSMISSION N ETWORK D EVELOPMENT : I MPLICATIONS.

Tranzit scenarios 1000 MW from UCTE (PolandampSlovakia) to

Turkey

Tranzit scenarios 1000 MW from Russia (IPSUPS) to Turkey

budget

Tranzit scenarios 1000 MW from Turkey to Romania

Tranzit scenarios1000 MW from Turkey to UCTE (Serbia and

Austria)

Activities to be done in parallel with the feasibilty study

bull Preliminary business model

ndash List of main commercial regulatory and financial hypothesys

ndash Documentation on the business experience of existing commercial interconnectors in EU

ndash Discussions and clarifications with the regulatory authorities

ndash Legal due diligence for the preliminary business model

ndash TOR for the complete business study

bull Exploration and identification of potential private partners

ndash Letters of intent

ndash Develop procedure for the selection of the private investors

bull Full clarifications on TEIAS participation in the project including Turkish applicable legislation

bull Preliminary legal preparations for the project company ( SPV )

Opportunity StudyJoint Position Paper

Feasibility Study( 75 TEL- 25 NE ) Business Study

Joint Position Paper - Final

International Agreement between

Romania and Turkey

Project implementationFinancing contracting supply and instalation

MOU -1MOU -1

MOU -2 MOU -2

Selection of private investors SPV ndash the project company

2005

2008 - 2009

2009

2010

2010 - 2013

022009

First tentative road map

THANK YOU FOR YOUR ATTENTION

e-mail relatiiinvestitoritranselectricaro razvanpurdilatranselectricaro

phone +40213035923fax +40213035880web-site wwwtranselectricaro

  • Regional Transmission Network Development Implications for Trade and Investment
  • Slide 2
  • Slide 4
  • Slide 5
  • Slide 6
  • Slide 7
  • Slide 8
  • Slide 9
  • Slide 11
  • Slide 12
  • Slide 13
  • Slide 14
  • Slide 15
  • Slide 16
  • Slide 17
  • Slide 18
  • Slide 19
  • Slide 20
  • Slide 21
  • Slide 22
  • Slide 23
  • Slide 24
  • Slide 25
  • Slide 27
  • Slide 28
  • Slide 29
  • Slide 30
  • Slide 31
  • Activities to be done in parallel with the feasibilty study
  • Slide 34
  • Slide 35
Page 24: R EGIONAL T RANSMISSION N ETWORK D EVELOPMENT : I MPLICATIONS FOR T RADE AND I NVESTMENT R EGIONAL T RANSMISSION N ETWORK D EVELOPMENT : I MPLICATIONS.

Tranzit scenarios 1000 MW from Russia (IPSUPS) to Turkey

budget

Tranzit scenarios 1000 MW from Turkey to Romania

Tranzit scenarios1000 MW from Turkey to UCTE (Serbia and

Austria)

Activities to be done in parallel with the feasibilty study

bull Preliminary business model

ndash List of main commercial regulatory and financial hypothesys

ndash Documentation on the business experience of existing commercial interconnectors in EU

ndash Discussions and clarifications with the regulatory authorities

ndash Legal due diligence for the preliminary business model

ndash TOR for the complete business study

bull Exploration and identification of potential private partners

ndash Letters of intent

ndash Develop procedure for the selection of the private investors

bull Full clarifications on TEIAS participation in the project including Turkish applicable legislation

bull Preliminary legal preparations for the project company ( SPV )

Opportunity StudyJoint Position Paper

Feasibility Study( 75 TEL- 25 NE ) Business Study

Joint Position Paper - Final

International Agreement between

Romania and Turkey

Project implementationFinancing contracting supply and instalation

MOU -1MOU -1

MOU -2 MOU -2

Selection of private investors SPV ndash the project company

2005

2008 - 2009

2009

2010

2010 - 2013

022009

First tentative road map

THANK YOU FOR YOUR ATTENTION

e-mail relatiiinvestitoritranselectricaro razvanpurdilatranselectricaro

phone +40213035923fax +40213035880web-site wwwtranselectricaro

  • Regional Transmission Network Development Implications for Trade and Investment
  • Slide 2
  • Slide 4
  • Slide 5
  • Slide 6
  • Slide 7
  • Slide 8
  • Slide 9
  • Slide 11
  • Slide 12
  • Slide 13
  • Slide 14
  • Slide 15
  • Slide 16
  • Slide 17
  • Slide 18
  • Slide 19
  • Slide 20
  • Slide 21
  • Slide 22
  • Slide 23
  • Slide 24
  • Slide 25
  • Slide 27
  • Slide 28
  • Slide 29
  • Slide 30
  • Slide 31
  • Activities to be done in parallel with the feasibilty study
  • Slide 34
  • Slide 35
Page 25: R EGIONAL T RANSMISSION N ETWORK D EVELOPMENT : I MPLICATIONS FOR T RADE AND I NVESTMENT R EGIONAL T RANSMISSION N ETWORK D EVELOPMENT : I MPLICATIONS.

budget

Tranzit scenarios 1000 MW from Turkey to Romania

Tranzit scenarios1000 MW from Turkey to UCTE (Serbia and

Austria)

Activities to be done in parallel with the feasibilty study

bull Preliminary business model

ndash List of main commercial regulatory and financial hypothesys

ndash Documentation on the business experience of existing commercial interconnectors in EU

ndash Discussions and clarifications with the regulatory authorities

ndash Legal due diligence for the preliminary business model

ndash TOR for the complete business study

bull Exploration and identification of potential private partners

ndash Letters of intent

ndash Develop procedure for the selection of the private investors

bull Full clarifications on TEIAS participation in the project including Turkish applicable legislation

bull Preliminary legal preparations for the project company ( SPV )

Opportunity StudyJoint Position Paper

Feasibility Study( 75 TEL- 25 NE ) Business Study

Joint Position Paper - Final

International Agreement between

Romania and Turkey

Project implementationFinancing contracting supply and instalation

MOU -1MOU -1

MOU -2 MOU -2

Selection of private investors SPV ndash the project company

2005

2008 - 2009

2009

2010

2010 - 2013

022009

First tentative road map

THANK YOU FOR YOUR ATTENTION

e-mail relatiiinvestitoritranselectricaro razvanpurdilatranselectricaro

phone +40213035923fax +40213035880web-site wwwtranselectricaro

  • Regional Transmission Network Development Implications for Trade and Investment
  • Slide 2
  • Slide 4
  • Slide 5
  • Slide 6
  • Slide 7
  • Slide 8
  • Slide 9
  • Slide 11
  • Slide 12
  • Slide 13
  • Slide 14
  • Slide 15
  • Slide 16
  • Slide 17
  • Slide 18
  • Slide 19
  • Slide 20
  • Slide 21
  • Slide 22
  • Slide 23
  • Slide 24
  • Slide 25
  • Slide 27
  • Slide 28
  • Slide 29
  • Slide 30
  • Slide 31
  • Activities to be done in parallel with the feasibilty study
  • Slide 34
  • Slide 35
Page 26: R EGIONAL T RANSMISSION N ETWORK D EVELOPMENT : I MPLICATIONS FOR T RADE AND I NVESTMENT R EGIONAL T RANSMISSION N ETWORK D EVELOPMENT : I MPLICATIONS.

Tranzit scenarios1000 MW from Turkey to UCTE (Serbia and

Austria)

Activities to be done in parallel with the feasibilty study

bull Preliminary business model

ndash List of main commercial regulatory and financial hypothesys

ndash Documentation on the business experience of existing commercial interconnectors in EU

ndash Discussions and clarifications with the regulatory authorities

ndash Legal due diligence for the preliminary business model

ndash TOR for the complete business study

bull Exploration and identification of potential private partners

ndash Letters of intent

ndash Develop procedure for the selection of the private investors

bull Full clarifications on TEIAS participation in the project including Turkish applicable legislation

bull Preliminary legal preparations for the project company ( SPV )

Opportunity StudyJoint Position Paper

Feasibility Study( 75 TEL- 25 NE ) Business Study

Joint Position Paper - Final

International Agreement between

Romania and Turkey

Project implementationFinancing contracting supply and instalation

MOU -1MOU -1

MOU -2 MOU -2

Selection of private investors SPV ndash the project company

2005

2008 - 2009

2009

2010

2010 - 2013

022009

First tentative road map

THANK YOU FOR YOUR ATTENTION

e-mail relatiiinvestitoritranselectricaro razvanpurdilatranselectricaro

phone +40213035923fax +40213035880web-site wwwtranselectricaro

  • Regional Transmission Network Development Implications for Trade and Investment
  • Slide 2
  • Slide 4
  • Slide 5
  • Slide 6
  • Slide 7
  • Slide 8
  • Slide 9
  • Slide 11
  • Slide 12
  • Slide 13
  • Slide 14
  • Slide 15
  • Slide 16
  • Slide 17
  • Slide 18
  • Slide 19
  • Slide 20
  • Slide 21
  • Slide 22
  • Slide 23
  • Slide 24
  • Slide 25
  • Slide 27
  • Slide 28
  • Slide 29
  • Slide 30
  • Slide 31
  • Activities to be done in parallel with the feasibilty study
  • Slide 34
  • Slide 35
Page 27: R EGIONAL T RANSMISSION N ETWORK D EVELOPMENT : I MPLICATIONS FOR T RADE AND I NVESTMENT R EGIONAL T RANSMISSION N ETWORK D EVELOPMENT : I MPLICATIONS.

Activities to be done in parallel with the feasibilty study

bull Preliminary business model

ndash List of main commercial regulatory and financial hypothesys

ndash Documentation on the business experience of existing commercial interconnectors in EU

ndash Discussions and clarifications with the regulatory authorities

ndash Legal due diligence for the preliminary business model

ndash TOR for the complete business study

bull Exploration and identification of potential private partners

ndash Letters of intent

ndash Develop procedure for the selection of the private investors

bull Full clarifications on TEIAS participation in the project including Turkish applicable legislation

bull Preliminary legal preparations for the project company ( SPV )

Opportunity StudyJoint Position Paper

Feasibility Study( 75 TEL- 25 NE ) Business Study

Joint Position Paper - Final

International Agreement between

Romania and Turkey

Project implementationFinancing contracting supply and instalation

MOU -1MOU -1

MOU -2 MOU -2

Selection of private investors SPV ndash the project company

2005

2008 - 2009

2009

2010

2010 - 2013

022009

First tentative road map

THANK YOU FOR YOUR ATTENTION

e-mail relatiiinvestitoritranselectricaro razvanpurdilatranselectricaro

phone +40213035923fax +40213035880web-site wwwtranselectricaro

  • Regional Transmission Network Development Implications for Trade and Investment
  • Slide 2
  • Slide 4
  • Slide 5
  • Slide 6
  • Slide 7
  • Slide 8
  • Slide 9
  • Slide 11
  • Slide 12
  • Slide 13
  • Slide 14
  • Slide 15
  • Slide 16
  • Slide 17
  • Slide 18
  • Slide 19
  • Slide 20
  • Slide 21
  • Slide 22
  • Slide 23
  • Slide 24
  • Slide 25
  • Slide 27
  • Slide 28
  • Slide 29
  • Slide 30
  • Slide 31
  • Activities to be done in parallel with the feasibilty study
  • Slide 34
  • Slide 35
Page 28: R EGIONAL T RANSMISSION N ETWORK D EVELOPMENT : I MPLICATIONS FOR T RADE AND I NVESTMENT R EGIONAL T RANSMISSION N ETWORK D EVELOPMENT : I MPLICATIONS.

Opportunity StudyJoint Position Paper

Feasibility Study( 75 TEL- 25 NE ) Business Study

Joint Position Paper - Final

International Agreement between

Romania and Turkey

Project implementationFinancing contracting supply and instalation

MOU -1MOU -1

MOU -2 MOU -2

Selection of private investors SPV ndash the project company

2005

2008 - 2009

2009

2010

2010 - 2013

022009

First tentative road map

THANK YOU FOR YOUR ATTENTION

e-mail relatiiinvestitoritranselectricaro razvanpurdilatranselectricaro

phone +40213035923fax +40213035880web-site wwwtranselectricaro

  • Regional Transmission Network Development Implications for Trade and Investment
  • Slide 2
  • Slide 4
  • Slide 5
  • Slide 6
  • Slide 7
  • Slide 8
  • Slide 9
  • Slide 11
  • Slide 12
  • Slide 13
  • Slide 14
  • Slide 15
  • Slide 16
  • Slide 17
  • Slide 18
  • Slide 19
  • Slide 20
  • Slide 21
  • Slide 22
  • Slide 23
  • Slide 24
  • Slide 25
  • Slide 27
  • Slide 28
  • Slide 29
  • Slide 30
  • Slide 31
  • Activities to be done in parallel with the feasibilty study
  • Slide 34
  • Slide 35
Page 29: R EGIONAL T RANSMISSION N ETWORK D EVELOPMENT : I MPLICATIONS FOR T RADE AND I NVESTMENT R EGIONAL T RANSMISSION N ETWORK D EVELOPMENT : I MPLICATIONS.

THANK YOU FOR YOUR ATTENTION

e-mail relatiiinvestitoritranselectricaro razvanpurdilatranselectricaro

phone +40213035923fax +40213035880web-site wwwtranselectricaro

  • Regional Transmission Network Development Implications for Trade and Investment
  • Slide 2
  • Slide 4
  • Slide 5
  • Slide 6
  • Slide 7
  • Slide 8
  • Slide 9
  • Slide 11
  • Slide 12
  • Slide 13
  • Slide 14
  • Slide 15
  • Slide 16
  • Slide 17
  • Slide 18
  • Slide 19
  • Slide 20
  • Slide 21
  • Slide 22
  • Slide 23
  • Slide 24
  • Slide 25
  • Slide 27
  • Slide 28
  • Slide 29
  • Slide 30
  • Slide 31
  • Activities to be done in parallel with the feasibilty study
  • Slide 34
  • Slide 35