+ All Categories
Home > Documents > RAFT.ppt2

RAFT.ppt2

Date post: 04-Jun-2018
Category:
Upload: ajsanyal259
View: 213 times
Download: 0 times
Share this document with a friend

of 24

Transcript
  • 8/13/2019 RAFT.ppt2

    1/24

    FIRSTLY, LAYOUT IS

    TO BE GIVEN AT

    SITE ACCORDING

    TO PLAN W.R.T.

    WHICH

    EXCAVATION IS

    CARRIED OUT WITH

    THE HELP OF LANDEXCAVATOR AND

    PREFERABLY

    SHOULD BE

    DISMENTLED AS

    PER SITE

    CONDITION.

  • 8/13/2019 RAFT.ppt2

    2/24

  • 8/13/2019 RAFT.ppt2

    3/24

    A LAYER OF SAND

    BED IS LAYED OVER

    THE EXCAVATED

    SURFACE AREA

    (APPROX.- 75mm) OVER

    WHICH PCC BED OF

    RECOMMENDED

    THICKNESS IS LAYED

    SAY- 1:4:8. THESURFACE SHOULD BE

    PROPERLY FINISHED

    AND LEVELED AFTER

    THE PCC COURSE.

  • 8/13/2019 RAFT.ppt2

    4/24

  • 8/13/2019 RAFT.ppt2

    5/24

  • 8/13/2019 RAFT.ppt2

    6/24

  • 8/13/2019 RAFT.ppt2

    7/24

  • 8/13/2019 RAFT.ppt2

    8/24

  • 8/13/2019 RAFT.ppt2

    9/24

    AFTER COMPLETING THE

    PCC COURSE BOTTOM

    REINFOCEMENT IS PLACED

    AS PER STRUCTURAL

    DESIGN OF THE RAFT SLAB.

    THE M/S RODS SHOULD BE

    PLACED PREFERABLY

    EQUALLY PARALEL TO EACH

    OTHER.

  • 8/13/2019 RAFT.ppt2

    10/24

  • 8/13/2019 RAFT.ppt2

    11/24

  • 8/13/2019 RAFT.ppt2

    12/24

  • 8/13/2019 RAFT.ppt2

    13/24

    AFTER COMPLETING

    THE BOTTOM

    REINFORCEMENT,

    COLUMNS ARE

    PLACED ACCORDING

    TO THE LAYOUT

    PLAN AND

    SIMULTANEOUSLY

    CHAIRS ARE ALSO

    TIED TO THE

    BOTTOM

    REINFORCEMENT.

  • 8/13/2019 RAFT.ppt2

    14/24

  • 8/13/2019 RAFT.ppt2

    15/24

  • 8/13/2019 RAFT.ppt2

    16/24

    FIXING OF CHAIRS OVER BOTTOM RODS

  • 8/13/2019 RAFT.ppt2

    17/24COLUMN & BOTTOM REINFORCEMENT JUNCTION

  • 8/13/2019 RAFT.ppt2

    18/24

  • 8/13/2019 RAFT.ppt2

    19/24

    TOP

    REINFORCEMENT OF

    RAFT SLAB

  • 8/13/2019 RAFT.ppt2

    20/24

    PROVIDING TOP REINFORCEMENT

  • 8/13/2019 RAFT.ppt2

    21/24

    AFTER COMPLETING

    ALL THE

    REINFORCEMENT

    WORKS,

    CEMENT

    CONCRETING IS TOBE DONE OF

    RECOMMENDED

    MIX.PROPER

    GROUTING SHOULD

    BE DONE.

  • 8/13/2019 RAFT.ppt2

    22/24

    RAFT SLAB CASTING

  • 8/13/2019 RAFT.ppt2

    23/24

  • 8/13/2019 RAFT.ppt2

    24/24

    THANK -YOU