+ All Categories
Home > Documents > Rajkumar Project Report Copy

Rajkumar Project Report Copy

Date post: 06-Mar-2016
Category:
Upload: crystal-king
View: 57 times
Download: 8 times
Share this document with a friend
Description:
Report

of 60

Transcript
  • A Project Report Entitled

    Design, Optimizationand Calibration of 6-Component External

    Wind Tunnel Balance

    Submitted to

    VISVESVARAYA TECHNOLOGICAL UNIVERSITY, BELGAUM

    In partial fulfilment of requirements for the award of the degree of

    MASTER OF TECHNOLOGY

    In

    MACHINE DESIGN

    By

    RajkumarKhot

    (USN: 1BM13MMD10)

    Project work carried out at

    Indian Institute of Science Bangalore 560012

    Under the guidance of

    POST GRADUATE AND RESEARCH CENTRE

    DEPARTMENT OF MECHANICAL ENGINEERING

    B. M. S. COLLEGE OF ENGINEERING

    BANGALORE- 560019

    July, 2015

    Internal Guide

    Dr. J. SharanaBasavaraja

    Associate Professor

    Dept. of Mechanical Engineering

    BMS College of Engineering

    Bangalore

    External Guide

    Dr. S B Kandgal Principal Research Scientist

    Dept. of Aerospace Engineering

    Indian Institute of Science

    Bangalore

  • POST GRADUATE AND RESEARCH CENTRE

    DEPARTMENT OF MECHANICAL ENGINEERING

    B. M. S. COLLEGE OF ENGINEERING

    BANGALORE- 560019

    July, 2015

    CERTIFICATE

    Certified that the project work entitled Design, Optimization and Calibration of 6-

    Component External Wind Tunnel Balancecarried out atIndian Institute of

    Science, Bangaloreby Mr.RajkumarKhotbearing the University Seat Number

    1BM13MMD10, a bonafide student of B M S College of Engineering is in partial fulfilment

    for the award of Master of Technology in Machine Design of Visvesvaraya Technological

    University, Belgaum during the year 2014-2015. It is certified that all correction/suggestions

    indicated for the internal assessment have been incorporated in the report deposited in the

    departmental library. The project report has been approved as it satisfies the academic

    requirement in respect of project work prescribed for the said Degree.

    Dr. J. SharanaBasavaraja

    Associate Professor

    Dept. of Mechanical Engineering

    BMS College of Engineering

    Bangalore -560019

    Dr. L Ravikumar

    Professor and Head

    Dept. of Mechanical Engineering

    BMS College of Engineering

    Bangalore -560019

    Dr. K MallikarjunBabu

    Principal

    BMS College of Engineering

    Bangalore -560019

    External Viva

    Name of the Examiner Signature with date

    1.

    2.

  • DECLARATION

    I, RajkumarKhot (1BM13MMD10), student of IV semester M.Tech Machine Design, B

    M S College of Engineering, Bangalore, hereby declare that the work being presented in the

    dissertation entitled Design, Optimization and Calibration of 6-Component

    External Wind Tunnel Balancesubmitted to the Visvesvaraya Technological

    University during the academic year 2014-15, is an authentic record of the work done under

    the academic guidance of Dr. J. SharanaBasavaraja, Associate Professor, Department of

    Mechanical Engineering, B M S College of Engineering, Bangalore. This project work is

    submitted in partial fulfilment of the requirements for the award of the degree Master of

    Technology in Machine Design. The work contained in thesis has not been submitted to any

    other University or Institute for the award of any degree.

    Place: Bangalore

    Date: (RajkumarKhot)

  • ACKNOWLEDGEMENT

    While bringing out this thesis to its final form, I came across a number of people whose

    contributions in various ways helped my field of research and they deserve special thanks. It is a

    pleasure to convey my gratitude to all of them.

    First and foremost, I would like to express my deep sense of gratitude and indebtedness to my

    supervisors Dr. S B Kandagal(External guide) Principal Research Scientist,Dept. of Aerospace

    Engineering,IISc, Bangalore and Dr. J. SharanaBasavaraja(Internal guide)Associate

    ProfessorBMS College of EngineeringBangalore. And for their invaluable encouragement,

    suggestions and support from an early stage of this research and providing me extraordinary

    experiences throughout the work. Above all, their priceless and meticulous supervision at each

    and every phase of work inspired me in innumerable ways

    I specially acknowledge them for their advice, supervision, and the vital contribution as and

    when required during this research. Their involvement with originality has triggered and

    nourished my intellectual maturity that will help me for a long time to come. I am proud to

    record that I had the opportunity to work with an exceptionally experienced Professors like them.

    I am highly grateful to Dr. S B Kandagaland Dr. D. Ghose, Chairman, Aerospace Engineering

    Dept. IISc Bangalore for giving me opportunity to carry out my thesis work at this reputed

    institute, which has given me exposure various methodologies of research. I also thank Mr. V

    Surendranath and Staff of OCWT, IISc, Bangalore for giving their valuable suggestion and

    time whenever asked for.

    I am greatly indebted to Dr. B. S. Suresh, Professor and Co-ordinator, PG (Machine Design),

    B. M. S. College of Engineering, Bangalore for theencouragement he has given during the

    course of this project work.

    I wish to express my sincere thanks to Dr. L Ravi Kumar, Professor & Head, Department of

    Mechanical Engineering, B. M. S. College of Engineering, Bangalore for supporting throughout

    the duration of project.

  • I take immense pleasure in thanking Dr. K. MallikharjunaBabu, Principal, B. M. S. College

    of Engineering, Bangalore, for providing the right kind of milieu.

    I extend my thanks to my friendsManjunathMelagiri, Vishal G.P, Ramesh

    Sarangamath,Guru Brahmam, Shiva Shankar, Guru Raja, at Vibration and Acoustics lab,

    Aerospace department, IISc, Bangalore, for supporting and tolerating me for the past one year

    Finally, I extend my thanks to the entire faculty of the Department of MechanicalEngineering,

    BMSCE, Bangalore, for their continued co-operation and support during the tenure of this

    project work.

    RajkumarKhot

  • ABSTRACT

    A six component platform balance was designed and fabricated in the dept. of Aerospace

    Engineering, IISc, Bangalore, for measuring aerodynamic forces and moments on models. This

    balance utilizes load cells for transducing forces into electrical signals. The platform balance

    consists of a leveled platform constrained by six load cells for measuring forces in vertical, axial

    and sideward directions. The project work includes the detailed study of wind tunnel balance

    types, mounting methods, design concepts, materials used for fabrication of external strain gauge

    balances, derivation for calibration, transformation and user matrices.

    Project work also includes the FEM analysis of 6-component external force balance,

    optimization of force measuring elements and load cells. To study the static and dynamic

    coupling of balance when model is attached to force balance by studying individual and coupled

    behavior and finally Validating the dynamic characteristics in wind tunnel for a typical model

    and study the error in responses of individual components with increased loads. The present

    study uses the CATIA to modeling the force balance configuration, Finite Element Analysis

    (FEA) extensively to find forces developed in the load cells and optimization of force measuring

    elements. MATLAB used during the generation of calibration, transformation and user matrices.

  • CONTENTS

    List of Figures

    List of tables

    Notations

    1 Introduction ............................................................................................................................. 9

    1.1 Wind Tunnels ................................................................................................................... 9

    1.2 Working method of Wind Tunnel .................................................................................... 9

    1.3 Types of Wind Tunnel.................................................................................................... 10

    1.3.1 Based on Flow Speed .............................................................................................. 10

    1.3.2 Based on Shape: ...................................................................................................... 11

    1.4 Balance Types ................................................................................................................ 13

    1.4.1 External balances .................................................................................................... 13

    1.4.2 Internal balances ..................................................................................................... 15

    1.5 Advantages of external balance over internal balance ................................................... 16

    1.6 Drawbacks of external balance over internal balance .................................................... 16

    1.7 Model Mounts ................................................................................................................ 16

    2 Literature Review .................................................................................................................. 19

    3 Platform Balance Description ................................................................................................ 22

    4 Load Cell ............................................................................................................................... 24

    4.1 What is a Load Cell? ...................................................................................................... 24

    4.2 Working of Load Cell .................................................................................................... 25

    Load Cells - How They Work? .............................................................................................. 25

    5 Calibration of the platform balance ....................................................................................... 27

    5.1 Objectives of the calibration .......................................................................................... 27

    5.2 Force and moment concepts ........................................................................................... 31

    5.3 Calibration procedure ..................................................................................................... 32

    5.3.1 Negative normal force: ........................................................................................... 32

    5.3.2 Positive rolling moment: ......................................................................................... 32

  • 5.3.3 Negative axial force: ............................................................................................... 33

    5.3.4 Positive pitching moment: ...................................................................................... 33

    5.3.5 Positive side force: .................................................................................................. 34

    5.3.6 Positive yawing moment: ........................................................................................ 34

    6 Derivation of Calibration Matrix, Transformation Matrix and User matrix of the platform

    balance .......................................................................................................................................... 36

    7 Balance calibration data and errors ....................................................................................... 40

    8 The Concept of I-Beam and Spring Element ......................................................................... 43

    8.1 I-Beam ............................................................................................................................ 43

    8.2 FE Analysis of Force Measuring element without and with I-beam.............................. 44

    8.3 Spring Element in place of Load cell ............................................................................. 45

    9 FEM analysis of external force balance ................................................................................ 46

    9.1 Normal Force, Rolling moment and pitching moment measurement ............................ 46

    9.2 Side Force and Yawing moment measurement .............................................................. 47

    9.3 Axial Force Measurement .............................................................................................. 48

    9.4 Combined forces and Moments: .................................................................................... 49

    9.5 Stress and Deformation plot ........................................................................................... 50

    10 Conclusions and Recommendations .................................................................................. 51

    10.1 Conclusions .................................................................................................................... 51

    10.2 Recommendations .......................................................................................................... 51

    11 References .......................................................................................................................... 52

    12 Appendix ............................................................................................................................ 54

    12.1 Appendix A .................................................................................................................... 54

  • LIST OF FIGURES

    FIGURE 1-1SCHEMATIC REPRESENTATION OF A WIND TUNNEL....................................................... 10

    FIGURE 1-2SCHEMATIC REPRESENTATION OF AN OPEN CIRCUIT WIND TUNNEL ............................. 11

    FIGURE 1-3SCHEMATIC REPRESENTATION OF A CLOSED CIRCUIT WIND TUNNEL ............................ 12

    FIGURE 1-46-COMPONENT EXTERNAL BALANCE AND SUPPORT SYSTEM AT IISC OPEN CIRCUIT

    WIND TUNNEL. ........................................................................................................................ 13

    FIGURE 1-5TYPICAL SCALED MODELS INSIDE THE WIND TUNNEL ................................................... 14

    FIGURE 1-6TYPICAL INTERNAL BALANCE USED IN LOW SPEED WIND TUNNELS .......................... 15

    FIGURE 1-7STING AND STRUT MOUNTING METHODS ...................................................................... 16

    FIGURE 1-8TYPICAL MODELS INSIDE THE WIND TUNNEL TEST SECTION ......................................... 18

    FIGURE 3-1DIFFERENT VIEWS OF PLATFORM BALANCE .................................................................. 22

    FIGURE 4-1TYPICAL LOAD CELL USED IN PLATFORM BALANCE AT IISC OPEN CIRCUIT WIND TUNNEL

    ............................................................................................................................................... 24

    FIGURE 4-2SPECIFICATION OF LOAD CELL ..................................................................................... 25

    FIGURE 4-3WHEATSTONE BRIDGE NETWORK ................................................................................ 26

    FIGURE 5-1PLATFORM BALANCE WITH CALIBRATION SETUP (A) .................................................... 28

    FIGURE 5-2PLATFORM BALANCE WITH CALIBRATION SETUP (B).................................................... 29

    FIGURE 5-3AXES SYSTEM .............................................................................................................. 30

    FIGURE 5-4FORCE AND MOMENT CONCEPT .................................................................................... 31

    FIGURE 5-5CALIBRATION FOR NF AND RM .................................................................................... 32

    FIGURE 5-6CALIBRATION FOR AF AND PM ..................................................................................... 33

    FIGURE 5-7CALIBRATION FOR SF AND YM ..................................................................................... 34

    FIGURE 6-1FORCE AND MOMENT VECTORS AT CC AND BC ........................................................... 38

    FIGURE 8-1CONCEPT OF I-BEAM.................................................................................................... 43

    FIGURE 8-2FORCE MEASURING ELEMENT WITHOUT AND WITH I-BEAM .......................................... 44

    FIGURE 8-3FE ANALYSIS OF FORCE MEASURING ELEMENTS ........................................................... 44

    FIGURE 8-4FE ANALYSIS OF FORCE MEASURING ELEMENT BY REPLACING SRING INPLACE OF LOAD

    CELL ....................................................................................................................................... 45

    FIGURE 9-1NF, RM, PM MEASUREMENT ......................................................................................... 46

    FIGURE 9-2SF, YM MEASUREMENT ............................................................................................... 47

    FIGURE 9-3AF MEASUREMENT ....................................................................................................... 48

    FIGURE 9-4COMBINED FORCES AND MOMENTS MEASUREMENTS ................................................... 49

    FIGURE 9-5STRESS AND DEFORMATION PLOT ................................................................................ 50

  • LIST OF TABLES

    TABLE 3-1 THE RATING OF THE BALANCE IS GIVEN IN THE ABOVE TABLE. .................................... 23

    TABLE 7-1CALIBRATION DATA (1) TABLE 7-2 CALIBRATION DATA (2) ......... 40

    TABLE 7-3 CALIBRATION DATA (3) TABLE 7-4CALIBRATION DATA (4) ......... 41

    TABLE 7-5CALIBRATION DATA (5) TABLE 7-6 CALIBRATION DATA (6) .............. 42

    TABLE 9-1NF MEASUREMENT ........................................................................................................ 46

    TABLE 9-2SF MEASUREMENTS ....................................................................................................... 47

    TABLE 9-3AF MEASUREMENT ........................................................................................................ 48

    TABLE 9-4COMBINED FORCES AND MOMENTS MEASUREMENTS..................................................... 49

    TABLE 9-5EN24 STEEL PROPERTIES ............................................................................................... 50

  • NOTATIONS

    E..Youngs modulus

    G..Shear modulus

    ..Poissons ratio

    x, y, z Cartesian coordinates

    Fx, Fy, Fz Forces in Cartesian coordinate system

    Mx, My, Mz Moments in Cartesian coordinate system

    AF.Axial force

    NF.Normal force

    SfSide force

    Mx..Rolling moment

    My..Pitching moment

    Mz .Yawing Moment

    Stress at a point

    Strain at a point

    M ............Mach number

    [C].Calibration Matrix

    [T].Transformation matrix

    [U].User Matrix

    RPerpendicular distance between CC and BC

    CC.Calibration centre

    BC....Balance centre

    a..Eccentricity

    F.....Force

  • Design, Optimization and Calibration of 6-Component External Wind Tunnel Balance

    Department of Mechanical Engineering, B M S College of Engineering, Bangalore. Page 9

    1 Introduction

    The aim of wind tunnel tests is the simulation of the flow around bodies or their scaled models.

    In aeronautical applications, the measurement of aerodynamic loads in a wind tunnel, forces and

    momentums, is a very difficult task due to the required accuracy. The wind tunnel balances,

    comprised by several hardware and software components, provides directly the pursued

    measurements, with high accuracy and reliability. For these reasons, among others, wind tunnel

    balances have become a common tool in testing facilities.

    1.1 Wind Tunnels Wind tunnel is a physical instrument used to test scale models of aircraft and spacecraft. Wind

    tunnel is used to predict the amount of forces and moments generated by the solid objects. This

    helps designers to choose the proper size for things such as wings, spoilers, and parachutes.

    Information obtained in wind tunnels is used to improve the design of anything affected by wind.

    In the tunnel; the engineer can carefully control the flow conditions which affect forces on

    the aircraft. Some wind tunnels are big enough to hold full-size versions of vehicles. Typically,

    there are sensors and instruments inside wind tunnels that give scientists hard data regarding an

    object's interaction with wind. And often, there are windows that let those same scientists

    observe experiments visually. With those data and observations, engineers grapple with variables

    of aerodynamics such as pressure, velocity, temperature and density. In addition, these tunnels

    can help engineers figure out how wind interacts with stationary objects, such as locomotives,

    buildings, missiles, spacecrafts and bridgesand find ways to make them stronger and safer.

    1.2 Working method of Wind Tunnel Most of the time, powerful fans move air through the tunnel. The object to be tested is fastened

    in the tunnel so that it will not move. The object can be a small model of a vehicle. It can be a

    full-size aircraft or spacecraft. The air moving around the still object shows what would happen

    if the object were moving through the air. How the air moves can be studied in different ways.

  • Design, Optimization and Calibration of 6-Component External Wind Tunnel Balance

    Department of Mechanical Engineering, B M S College of Engineering, Bangalore. Page 10

    Smoke or dye can be placed in the air and can be seen as it moves. Threads can be attached to the

    object to show how the air is moving. Special instruments are often used to measure the force

    and moments of the air on the object.

    1.3 Types of Wind Tunnel Wind tunnels are designed for a specific purpose and speed range. Therefore, there are many

    different types of wind tunnels and several different ways to classify wind tunnels.

    1.3.1 Based on Flow Speed

    Figure 1-1Schematic representation of a wind tunnel

    1.3.1.1 Subsonic or low speed wind tunnels

    Maximum flow speed in this type of wind tunnels can be 135m/s. Flow speed in wind tunnels is

    generally preferred in terms of Mach number which comes out to be around 0.4 for this case.

    These types of wind tunnels are most cost effective due to the simplicity of the design and low

    wind speed. Generally low speed wind tunnels are found in schools and universities because of

    low budget.

  • Design, Optimization and Calibration of 6-Component External Wind Tunnel Balance

    Department of Mechanical Engineering, B M S College of Engineering, Bangalore. Page 11

    1.3.1.2 Transonic wind tunnels

    Maximum velocity in test section of transonic wind tunnels can reach up to speed of sound i.e.

    340m/s or Mach number of 1. These wind tunnels are very common in aircraft industry as

    most aircrafts operate around this speed.

    1.3.1.3 Supersonic wind tunnels

    Velocity of air in test section of such wind tunnel can be up to Mach 5. This is accomplished

    using convergent-divergent Nozzles. Power requirements for such wind tunnels are very high.

    1.3.1.4 Hypersonic wind tunnels

    Wind velocity in test section of such type of wind tunnels can measure between Mach 5 and

    Mach 15. This is also achieved using convergent - divergentnozzles.

    1.3.2 Based on Shape:

    1.3.2.1 Open circuit wind tunnel:

    Figure 1-2Schematic representation of an open circuit wind tunnel

    This type of wind tunnel is open at both ends. The chances of dirt particles entering with air are

    more so more honeycombs (mesh to clean incoming air) are required to clean the air. Open type

    wind tunnels can further be divided into two categories:

  • Design, Optimization and Calibration of 6-Component External Wind Tunnel Balance

    Department of Mechanical Engineering, B M S College of Engineering, Bangalore. Page 12

    A) Suck down tunnel

    With the inlet open to atmosphere, axial fan or centrifugal blower is installed after test section.

    These types of wind tunnels are not preferred because incoming air enters with significant swirl.

    B) Blower tunnel

    A blower is installed at the inlet of wind tunnel which throws the air into wind tunnel. Swirl is a

    problem in this case as well but blower tunnels are much less sensitive to it.

    1.3.2.2 Closed circuit wind tunnel

    Figure 1-3Schematic representation of a closed circuit wind tunnel

    Outlet of such wind tunnel is connected to inlet so the same air circulates in the system in a

    regulated way. The chances of dirt entering the system are also very low. Closed wind tunnels

    have more uniform flow than open type. This is usually a choice for large wind tunnels as these

    are more costly than open type wind tunnels.

  • Design, Optimization and Calibration of 6-Component External Wind Tunnel Balance

    Department of Mechanical Engineering, B M S College of Engineering, Bangalore. Page 13

    1.4 Balance Types

    Balance types are distinguished by the number of force/moment components which are measured

    simultaneously one to six are possible and the location at which they are placed. If they are

    placed inside the model they are referred to as internal balancesand if they are located outside of

    the model or the wind tunnel, they are referred to as external balances. And rotary balances are

    used for propellers, helicopter blades and other rotating models.

    1.4.1 External balances

    Figure 1-46-component External Balance and Support system at IISc Open circuit wind tunnel.

  • Design, Optimization and Calibration of 6-Component External Wind Tunnel Balance

    Department of Mechanical Engineering, B M S College of Engineering, Bangalore. Page 14

    Figure 1-5Typical scaled models inside the wind tunnel

    They are placed outside the model, inside or outside the wind tunnel chamber test section, there

    are two types of external balances exist. The first is the one-piece external balance, which is

    constructed from one single piece of material and which is equipped with strain gauges. Such

    balances are also referred to as sidewallbalancesas used in half-model tests. The second type of

    external balance comprises single force transducers which are connected by a framework. Such a

    design can be built very stiff but needs more space compared to the one-piece design. However,

    there is usually plenty of space available around the wind tunnel for such a balance, and so the

    construction can be optimized with respect to measurement requirements, such as optimized

    sensitivity, stiffness and decoupling of load interactions. But they always introduce some

    interference in the wind flow. However the possibility to change test models with almost no

    effort provides a high flexibility to the wind tunnel facility. There are several degrees of

    complexity for these balances, depending mainly on the number of measurement channels, which

    can vary between 1 and 6.

  • Design, Optimization and Calibration of 6-Component External Wind Tunnel Balance

    Department of Mechanical Engineering, B M S College of Engineering, Bangalore. Page 15

    1.4.2 Internal balances

    Figure 1-6Typical Internal Balance Used in Low Speed Wind Tunnels

    They are placed inside the model, thus no interferences are introduced in the wind flow by the

    balance components, but a mechanical support for the model is always needed to maintain it in

    the test chamber and change the model orientation if desired. There is limited space inside the

    model itself, so internal balances have to be relatively small in comparison to external balances.

    There are two main types of internal balances. The monolithic type, in which the balance body

    consists of a single piece of material, is designed in a way such that certain areas are primarily

    stressed by the applied loads. The other internal balance type uses small transducers which are

    orientated with their sensing axes in the direction of the applied loads. Such a balance is

    combined into a solid structure. A balance measures the total model loads and therefore is placed

    at the center of gravity of the model and is generally constructed from one solid piece of

    material. The number of measured components can also vary between 1 and 6. Above Figure

    shows an example of internal balance.

  • Design, Optimization and Calibration of 6-Component External Wind Tunnel Balance

    Department of Mechanical Engineering, B M S College of Engineering, Bangalore. Page 16

    1.5 Advantages of external balance over internal balance 1. They are placed outside the model, inside or outside the wind tunnel chamber test section.

    2. High flexibility to the wind tunnel facility.

    3. Multi-purpose test facility (Aircrafts, automobiles, locomotives, Buildings etc.).

    4. The external balance placed outside the wind tunnel test chamber so, their dimensions

    and weight are not important.

    1.6 Drawbacks of external balance over internal balance 1. Drawback is always introduces some interference in the wind flow, interference problem

    doesnt arise in internal balance as the balance placed inside the model.

    2. Aerodynamic interference between the model support system and the model itself

    3. Interference between tunnel and model.

    4. Inertia loads on the balance.

    1.7 Model Mounts

    Figure 1-7Sting and strut mounting methods

  • Design, Optimization and Calibration of 6-Component External Wind Tunnel Balance

    Department of Mechanical Engineering, B M S College of Engineering, Bangalore. Page 17

    There are several different methods for mounting the model inside the test section. The choice of

    mounting system in a particular wind tunnel is often driven by the type of balance being

    employed. For an external balance, measuring devices are located outside of the model and the

    tunnel. For an external balance, the mount must transmit the aerodynamic loads on the model to

    the external balance, and hold the model securely at the desired flight condition of angle of

    attack and angle of yaw. For an internal balance, the measuring devices are located inside the

    model. The mount does not have to transmit forces, but must provide a path for information to be

    passed from the model to data recording devices.

    On the above figure, four different methods for mounting a fighter aircraft model in a tunnel and

    for all of the mounting systems, the struts are normally shielded from the air in the tunnel so that

    the drag of the struts themselves is not included in the drag of the aircraft. At the upper right, we

    have a three strut mount that connects to the model near both wing tips and at the aft end. The

    three strut mount is used most often with external balances; the bottom of the three struts

    connects to a platform that is instrumented with strain gages. With three movable struts,

    the angle of attack and roll angle can be accurately set and sustained while yaw is provided by

    turning the model on the circular section of the platform. The disadvantage of this system is the

    expense, complexity and maintenance for three movable struts. Aerodynamic interference

    between the struts and the model and flow blockage in the tunnel are also concerns for a three

    strut mount. Less expense, interference, and blockage can be obtained by the two strut mount at

    the upper left. But the two strut mount is less rigid than the three strut in pitch and roll. Even less

    expensive and with a minimum of interference and blockage is the single strut mounting system

    shown at the bottom. The single strut can be attached to the top or bottom of the model as shown

    at the left bottom, or it can be attached to the rear of the model, as a sting mount, as shown at the

    right bottom. The sting mount has less interference with the model flow field than the one strut

    mount, but the aft end of the model may be distorted to accept the sting mount. Single strut

    mounts are less rigid than multiple strut mounts. The single strut mounts works very well with

    internal balances and flow diagnostics.

  • Design, Optimization and Calibration of 6-Component External Wind Tunnel Balance

    Department of Mechanical Engineering, B M S College of Engineering, Bangalore. Page 18

    Figure 1-8Typical models inside the wind tunnel test section

    We now focus our attention in the 6 components external balances, as they provide 3 forces and

    3 momentums measurement and a high flexibility for a multi test wind tunnel.

  • Design, Optimization and Calibration of 6-Component External Wind Tunnel Balance

    Department of Mechanical Engineering, B M S College of Engineering, Bangalore. Page 19

    2 Literature Review

    Miguel A. Gonzalez, Jose Miguel Ezquerro, Victoria Lapuerta, Ana Laveron,

    and Jacobo Rodriguez [1]

    This paper gives the general description of wind tunnel balances. The number of measuring

    components and the position of the balance with relation to the model and wind tunnel chamber

    determines the wind tunnel balances designs. The most flexible ones in terms of usability are the

    six components external balances, so these will be referenced for introducing the calibration

    process; this is one of the key points to achieve the required aerodynamic tests results accuracy

    and reliability. Because of its influence on the drag measurement accuracy, the coupling effect

    between lift and drag measurements is analyzed very deeply as well. The analysis of the non-

    stationary effects are finally done taking into account the wind tunnel balance requirements and

    constraints, with special attention on an issue not commonly mentioned, the inertia forces

    generated on the balance by the model vibrations, and their influence on the aerodynamic forces

    to be measured. Several mentions to signal processing and acquisition are done, as this is the

    other key point on the measurements accuracy. However, it is easy to extrapolate these

    procedures to other types of balances, as the main intention is to shows which are the critical

    points that make wind tunnel balances such a special and complex hardware. They do not intend

    here to describe the design and calibration procedures of the industrial manufacturers. This is the

    result of a work done in the University Polytechnica de Madrid (UPM), and the

    InstitutoTechnologico y de EnergiasRenovables (ITER, Tenerife, Canary Island, Spain,

    www.iter.es).

    AnkitSoni&PankajPriyadarshi[2]

    The important design principles were learnt during the study of this paper, which are described in

    this paper. Measurement of forces and moments on aerodynamic models has always been an

    important part of wind tunnel experiments. A study was carried out on various beam type load

    cells using Finite Element Analysis. It was found that a parallelogram beam type load cell met all

  • Design, Optimization and Calibration of 6-Component External Wind Tunnel Balance

    Department of Mechanical Engineering, B M S College of Engineering, Bangalore. Page 20

    requirements and was found to be sensitive only to the normal loading and insensitive to all other

    loads and moments. The final configuration of the load cell was arrived at by carrying out a non-

    linear constrained optimization of the configuration parameters for two materials, namely

    Aluminum and Stainless Steel. These load cells were used to configure different designs of six

    components External Strain Gauge Balance. Static FE analysis of the complete assembly was

    carried out. An attempt was made to reduce the coupling between various forces & moments and

    to make the components sensitive only to their respective normal loads.

    HosseinNabipour[3]

    This paper aims to fully put the wind tunnel of Memorial University back into service which

    requires equipping the tunnel with its old force balance and flow visualization equipment. The

    major part of the project will be the calibration and modernization of the force balance for force

    and moment measurements on the test model. The balance will be equipped with a data

    acquisition system and a computer to monitor and analyze the test results simultaneously. Also

    there will be some flow measurements across the test section and finally the smoke generator

    needs to be prepared and installed in the tunnel.

    Marin SANDU, Adriana SANDU [4]

    This paper describes the design of a six-component force/moment sensor which is compact, has

    high measuring sensitivities, and can be used either as internal or as external balance in the

    aerodynamic testing. The measurement of steady and fluctuating forces acting on a body in a

    flow is one of the main tasks in wind-tunnel experiments. Usually, a multi-component strain

    gauge force and moment sensor (also known as balance) is used to generate signals which are

    processed by means of an adequate instrumentation. To design a wind-tunnel balance, the

    specifications of the load ranges and the available space (for the placement of the balance inside

    or outside the model) are required. The main challenge is to conceive the elastic element of the

    sensor as a monolithic part with a relative simple geometry and to identify the adequate

  • Design, Optimization and Calibration of 6-Component External Wind Tunnel Balance

    Department of Mechanical Engineering, B M S College of Engineering, Bangalore. Page 21

    placement of strain gauges to maximize the measuring sensitivities and to diminish the inter-

    influence of the components.

    S. M. GORLIN and I. I. SLEZINGER [5]

    Some of the measuring techniques and instruments are described in this book. In this textbook

    for advanced measuring techniques and instruments are described. R. C. Pankhurst and D. W.

    Holder discuss a wide range of experimental problems in their textbook "Wind -Tunnel

    Technique" (1952), but the treatment is general and sometimes superficial. Since the publication

    of these works the technology of aerodynamics has advanced greatly. In this book systematically

    certain modern techniques of aerodynamic measurement are described. They have made wide

    use of experience in the USSR and abroad, selecting material to enable readers with knowledge

    of theoretical aerodynamics to become familiar with experimental practice and with the

    instruments and apparatus used in practice. The book is intended mainly for experimental-

    research works in aerodynamics and for those using their results and also for students of fluid

    dynamics. This book is useful for engineers and technicians designing and constructing

    aerodynamic installations, and developing measuring equipment.

    Tropea C, Yarin A L, Foss J F [6]

    The aim of this paper is to give an impression of the possibilities, advantages and limitations

    offered by the use of piezoelectric balances. Several types of external balances are discussed for

    wall mounted models, which can be suspended one-sided or twin-sided. Additionally an internal

    sting balance is described, which is usually applied inside the model. Reports are given on

    selected measurements performed in very different wind tunnels, ranging from low-speed to

    transonic; from short- to continuous running time and encompassing cryogenic and high pressure

    principles. The projects span from a wing/engine combination in a low-speed wind tunnel to

    flutter tests with a swept-wing performed in a Transonic Wind Tunnel, and include bluff

    bodiesin a high pressure and cryogenic wind tunnel, as well. These tests serve as examples for

    discussing the fundamental aspects that are essential in developing and applying piezo balances.

  • Design, Optimization and Calibration of 6-Component External Wind Tunnel Balance

    Department of Mechanical Engineering, B M S College of Engineering, Bangalore. Page 22

    3 Platform Balance Description

    A six component platform balance was designed and fabricated in the dept. of Aerospace

    Engineering, IISc, Bangalore, for measuring aerodynamic forces and moments on models. This

    balance utilizes load cells for transducing forces into electrical signals. The platform balance

    consists a leveled platform constrained by six load cells for measuring forces in vertical, axial

    and sideward directions. Fig.1to Fig. 4 shows the different views of the balance. In Fig.1 two

    load cells (H1, H2) are indicated which were used for measuring side force and yawing moment.

    In Fig.2 one load cell (H3) is indicated to measure axial force. In fig.3 three load cells (V1, V2,

    and V3) are fixed to measure normal force, rolling moment and pitching moment. In Fig.4 all

    the six load cells are fixed to form the complete platform balance system.

    Figure 3-1Different views of platform balance

  • Design, Optimization and Calibration of 6-Component External Wind Tunnel Balance

    Department of Mechanical Engineering, B M S College of Engineering, Bangalore. Page 23

    A hexagonal shaped rigid plate (Fig.4) is used as the metric platform. A circular flange fitting is

    bolted at the center of this platform (Fig.4) for the purpose of fixing the model support adopter.

    The center of the flange coincides with the vertical center line of the platform balance.

    The vertical components of the load on the model are sensed by the three load cells fitted

    vertically as indicated in the Fig.3. These loads cells are designated as V1, V2 and V3. For

    sensing side force and yawing moment, there are two load cells fitted horizontally. In the same

    plane for sensing axial force one load cell is provided. These load cells are designated as H1, H2

    and H3. From these six load cells the six-components of forces and moments are obtained.

    With the direction of axial force aligned parallel to the tunnel axis, we have the following main

    components referred to the balance Centre.

    1. Normal Force (NF) = V1+V2 +V3

    2. Rolling Moment (RM) = (V1-V2)*a

    3. Pitching Moment (PM) = V3*a

    4. Side Force (SF) = H1+H2

    5. Yawing Moment (YM) = (H1-H2)*b

    6. Axial Force (AF) = H3

    Where a and b are the corresponding length of the moment arm.

    Table 3-1The rating of the balance is given in the above Table.

    Axial force 136 kg

    Side force 250 kg

    Normal force 700 kg

    Rolling moment 200 kgm

    Pitching moment 50 kgm

    Yawing moment 70 kgm

  • Design, Optimization and Calibration of 6-Component External Wind Tunnel Balance

    Department of Mechanical Engineering, B M S College of Engineering, Bangalore. Page 24

    4 Load Cell Load: The word loadwill be used to describe both the applied forces and moments. The task of a

    balance is to measure the aerodynamic loads, which act on the model or on components of the

    model itself. In total there are six different components of aerodynamic loads, three forces in the

    direction of the coordinate axes, and the moments around these axes themselves.

    Thesecomponents are measured in a certain coordinate systemwhich can be either fixed to the

    model or to the wind tunnel.

    4.1 What is a Load Cell? A load cell is a sensor or a transducer that converts a load or force acting on it into an electronic

    signal. This electronic signal can be a voltage change, current change or frequency change

    depending on the type of load cell and circuitry used.

    Figure 4-1Typical load cell used in Platform balance at IISc open circuit wind tunnel

    Load cells or Load sensors as they are commonly called - can be made using resistive,

    capacitive, inductive or other techniques. Most commonly available load cells are based on the

  • Design, Optimization and Calibration of 6-Component External Wind Tunnel Balance

    Department of Mechanical Engineering, B M S College of Engineering, Bangalore. Page 25

    principle of change of resistance in response to an applied load. This is termed piezo-resistive

    i.e. something that changes in response to an applied pressure (or squeezed).

    One of the most popularly used types of the load cells is the strain gauge load cell. In fact

    amongst all the types of load cells, the strain gauge type ones are used most commonly. These

    load cells are used for the measurement of very large compressive and tensile forces. This load

    cell is the special application of the strain gauges.

    4.2 Working of Load Cell

    Load Cells - How They Work?

    Load cells are traditionally built using resistive bonded foil strain gauges (as shown in the picture

    below). Strain gauges are essentially resistors built using standard semiconductor etching

    techniques and are bonded to a metallic member such as a cantilever beam or diaphragm.

    Figure 4-2 Specification of load cell

  • Design, Optimization and Calibration of 6-Component External Wind Tunnel Balance

    Department of Mechanical Engineering, B M S College of Engineering, Bangalore. Page 26

    Usually at least four strain gauges are configured in a Wheatstone Bridge configuration with four

    separate resistors connected as shown below in what is called a Wheatstone Bridge Network. An

    excitation voltage - usually 10V is applied to one set of corners and the voltage difference is

    measured between the other two corners. At equilibrium with no applied load, the voltage output

    is zero or very close to zero when the four resistors are closely matched in value. That is why it

    is referred to as a balanced bridge circuit.

    Figure 4-2Wheatstone bridge Network

    When the metallic member to which the strain gauges are attached, is stressed by the application

    of a force, the resulting strain - leads to a change in resistance in one (or more) of the resistors.

    This change in resistance results in a change in output voltage. This small change in output

    voltage can be measured and digitized after careful amplification of the small milli-volt level

    signals to a higher amplitude 0-5V or 0-10V signal.

  • Design, Optimization and Calibration of 6-Component External Wind Tunnel Balance

    Department of Mechanical Engineering, B M S College of Engineering, Bangalore. Page 27

    5 Calibration of the platform balance

    The goal of calibration is to minimize any measurement uncertainty by ensuring the accuracy of

    test equipment. Calibration quantifies and controls errors or uncertainties within measurement

    processes to an acceptable level.

    5.1 Objectives of the calibration

    1. To determine the interaction components

    2. To check accuracy, repeatability and linearity.

    3. To determine the calibration constant for each component.

    For calibration purpose a vertical tubular column with suitable fittings on its both ends need to

    fabricate. One end of the bar will have a flange fitting and will be bolted on the platform balance

    to the corresponding holes provided for the purpose. The other end of the bar will also have

    flange fitting clamped to the vertical column by a pinch fitting thus permitting rotation about a

    vertical axis. This will be used for supporting the loading bar and pans. Fig shows a typical

    arrangement made for calibration. The loading bar and pans can be aligned with the axial or

    lateral directions to calibrate respective components. This arrangement is used for calibration of

    the following components.

  • Design, Optimization and Calibration of 6-Component External Wind Tunnel Balance

    Department of Mechanical Engineering, B M S College of Engineering, Bangalore. Page 28

    Figure 5-1Platform balance with calibration setup (a)

  • Design, Optimization and Calibration of 6-Component External Wind Tunnel Balance

    Department of Mechanical Engineering, B M S College of Engineering, Bangalore. Page 29

    Figure 5-2Platform balance with Calibration setup (b)

  • Design, Optimization and Calibration of 6-Component External Wind Tunnel Balance

    Department of Mechanical Engineering, B M S College of Engineering, Bangalore. Page 30

    Axes System

    Figure 5-3Axes system

    For the platform balance, we choose the balance centre to be at the centre of the mounting flange

    which mates with the model/calibration column. The directions of axes are chosen as follows:

    Axial force direction coincides with wind direction and is horizontal (X direction).

    Normal force direction is vertical positive upwards (Z direction).

    Side force direction is horizontal and at right angle to the tunnel axis (Y Direction).

  • Design, Optimization and Calibration of 6-Component External Wind Tunnel Balance

    Department of Mechanical Engineering, B M S College of Engineering, Bangalore. Page 31

    5.2 Force and moment concepts

    Figure 5-4Force and moment concept

    1. Axial force: The force Parallel to the wind flow and to the tunnels walls.

    2. Normal force: Upward/Downward force normal to Drag and Side force.

    3. Side force: Applied to the sides of the test model and normal to drag and lift.

    4. Yawing moment: Moment caused by Drag and Side force about an axis parallel to Lift

    5. Pitching moment: Moment caused by Drag and Lift about an axis parallel to side force

    6. Rolling moment: Moment caused by Lift and Side force about an axis parallel to Drag

  • Design, Optimization and Calibration of 6-Component External Wind Tunnel Balance

    Department of Mechanical Engineering, B M S College of Engineering, Bangalore. Page 32

    5.3 Calibration procedure

    5.3.1 Negative normal force: This is obtained by loading equal weights on both the pans.

    5.3.2 Positive rolling moment:

    In the negative normal force loading setup, rolling moment is obtained by transferring weights

    from one pan to another keeping the total weights same.

    Figure 5-5Calibration for Nf and Rm

    Normal force = Nf =Fz = F1+ F2

    Rolling moment = Rm= Mx= F1*a-F2a

    Remaining forces (fx, Fy) and moments (My, Mz) are zero

  • Design, Optimization and Calibration of 6-Component External Wind Tunnel Balance

    Department of Mechanical Engineering, B M S College of Engineering, Bangalore. Page 33

    [Nf] = [1 0 0 0 0 0] [Rm] = [0 0 1 0 0 0]

    5.3.3 Negative axial force:

    This requires pulley-string arrangement. The loading on the pan gives axial force.

    5.3.4 Positive pitching moment: The loading arm will be rotated by 90 degree to the original position and loading pans will be

    hung. Both loading pans loaded equal loads. Now transferring loads from one pan to another,

    the pitching moment is obtained.

    Figure 5-6Calibration for Af and Pm

    Axial force = Af = Fx = F

    Mz

    Fx

    Fy

    Mx

    My

    Fz

    Mz

    Fx

    Fy

    Mx

    My

    Fz

  • Design, Optimization and Calibration of 6-Component External Wind Tunnel Balance

    Department of Mechanical Engineering, B M S College of Engineering, Bangalore. Page 34

    Pitching moment = Pm = My = F*a

    Remaining forces (Fy, Fz) and moments (Mx, Mz) are zero

    [Af] = [0 0 0 0 1 0] , [Pm] = [0 1 0 0 0 0]

    5.3.5 Positive side force: This requires pulley-string setup for loading in side direction.

    5.3.6 Positive yawing moment: This is obtained by pulley-string setup, the string being tied to the loading bar at a distance from

    the center.

    Figure 5-7Calibration for Sf and Ym

    Side force = Sf = Fy = F

    a= 25cm

    F

    Mz

    Fx

    Fy

    Mx

    My

    Fz

    Mz

    Fx

    Fy

    Mx

    My

    Fz

  • Design, Optimization and Calibration of 6-Component External Wind Tunnel Balance

    Department of Mechanical Engineering, B M S College of Engineering, Bangalore. Page 35

    Yawing moment = Ym = Mz = F*a

    Remaining forces (Fx, Fz) and moments (Mx, My) are zero

    [Sf] = [0 0 0 1 0 0] [Ym] = [0 0 0 0 0 1]

    Mz

    Fx

    Fy

    Mx

    My

    Fz

    Mz

    Fx

    Fy

    Mx

    My

    Fz

  • Design, Optimization and Calibration of 6-Component External Wind Tunnel Balance

    Department of Mechanical Engineering, B M S College of Engineering, Bangalore. Page 36

    6 Derivation of Calibration Matrix, Transformation Matrix

    and User matrix of the platform balance

    Before use, any balance needs a calibration to establish the relationship between the balance

    output vector in millivolts per volt of excitation and the load vector (forces and moments relative

    to a balance centre suitably defined with respect to the balance). For the platform balance, we

    choose the balance centre to be at the centre of the mounting flange which mates with the

    model/calibration column. The directions of axes are chosen as follows: axial force direction

    coincides with wind direction and is horizontal. Normal force direction is vertical positive

    upwards and side force direction is horizontal and at right angle to the tunnel axis.

    It would be most convenient to calibrate the balance by applying one component of the load

    vector at a time and record the balance output vector for each component. However, in this

    particular case, it is difficult to apply only a single component of the load vector at a time due to

    constraints associated with the balance location. Therefore an alternative scheme using a

    generalized loading method is employed and is described below.

    Let the balance output vector (written as a row vector for convenience) be associated with a

    generalized load vector F. Assuming linearity, we may relate R to F by a calibration matrix C as,

    In the above, the calibration matrix is easily obtained by the conventional method of applying

    one component of F at a time and recording the balance output vector.

    Inverting the above relation, one obtains

    654321 RRRRRR 654321 FFFFFF

    6661

    1611

    ....

    ......

    ......

    ......

    ......

    ....

    CC

    CC

    =

  • Design, Optimization and Calibration of 6-Component External Wind Tunnel Balance

    Department of Mechanical Engineering, B M S College of Engineering, Bangalore. Page 37

    Above equation gives the components of any applied load resolved into generalized forces

    1 6 one may transform this to set of forces into forces relative to balance Centre

    (Normal force NF, Pitching moment PM, Rolling moment RM, Side force SF, Axial force AF

    and Yawing moment YM) by a simple transformation.

    We may write

    Above equation resolves the generalized forces 16 into forces relative to balance

    Centre. The transformation matrix [T] is obtained by using equilibrium considerations.

    Let CC= calibration Centre, BC= balance Centre; CC and BC are co-linear at a distance of R.

    654321 RRRRRR 654321 FFFFFF =

    6661

    1611

    ....

    ......

    ......

    ......

    ......

    ....1

    cc

    cc

    YMAFSFRMPMNF = 654321 FFFFFF

    6661

    1611

    ....

    ......

    ......

    ......

    ......

    ....

    TT

    TT

  • Design, Optimization and Calibration of 6-Component External Wind Tunnel Balance

    Department of Mechanical Engineering, B M S College of Engineering, Bangalore. Page 38

    R

    Figure 6-1Force and moment vectors at CC and BC

    Force and moment vectors at CC and BC will be

    F

    = Fxi + Fyj + Fzk; M

    = Mxi + Myj + Mzk

    Force and Moment vectors at BC wii be

    F

    = Fxi + Fyj + Fzk; M

    = Mx i + Myj + Mzk

    The procedure to evaluate forces (Fx, Fy, fz) and moments (Mx, My, Mz) at Balance centre is

    Cleary explained in calibration procedure chapter.

    Fx = Axial force (Af), Fy = Side force (Sf), Fz = Normal force (Nf)

    Mx = Rolling moment (Rm), My = Pitching moment (Pm),

    Mz = Yawing moment (Ym)

    . (4)

    YM

    AF

    SF

    RM

    PM

    NF

    aR

    R

    R

    0100

    01000

    00100

    000100

    000010

    000001

    Mz

    Fx

    Fy

    Mx

    My

    Fz

    =

  • Design, Optimization and Calibration of 6-Component External Wind Tunnel Balance

    Department of Mechanical Engineering, B M S College of Engineering, Bangalore. Page 39

    R=Column length= 101.4cm

    a= eccentricity = 25cm

    . (5)

    In equation (4) and (5) the middle 6*6 matrix is called Transfer matrix [T]

    Using above equation we have,

    . (6)

    . (7)

    Here [U] is the user matrix and is obtained by post multiplying with [T].

    1004.0056.400

    01004.1010

    0014.10100

    000100

    000010

    000001

    YM

    AF

    SF

    RM

    PM

    NF

    Mz

    Fx

    Fy

    Mx

    My

    Fz

    =

    YMAFSFRMPMNF 654321 RRRRRR= C1 T

    U YMAFSFRMPMNF = 654321 RRRRRR

    C 1

  • Design, Optimization and Calibration of 6-Component External Wind Tunnel Balance

    Department of Mechanical Engineering, B M S College of Engineering, Bangalore. Page 40

    7 Balance calibration data and errors

    Table 7-1Calibration data (1) Table 7-2 Calibration Data (2)

    Applied Load

    (NF)(kg)

    Measured

    load (kg) % Error

    -20 -20.0185 -0.0925

    -40 -40.011 -0.0275

    -60 -59.9901 0.0165

    -80 -79.9745 0.031875

    -100 -99.9979 0.0021

    -80 -79.9973 0.003375

    -60 -59.9925 0.0125

    -40 -40.0086 -0.0215

    -20 -19.9924 0.038

    Applied

    Load (AF)

    (kg)

    Measured load

    (kg) % Error

    -5 -5.0072 -0.144

    -10 -9.9546 0.454

    -15 -14.9527 0.3153

    -20 -19.8777 0.6115

    -25 -24.9131 0.3476

    -30 -29.853 0.49

    -25 -25.2144 -0.858

    -20 -20.2068 -1.034

    -15 -15.0998 -0.665

    -10 -10.049 -0.49

    -5 -5.0138 -0.276

  • Design, Optimization and Calibration of 6-Component External Wind Tunnel Balance

    Department of Mechanical Engineering, B M S College of Engineering, Bangalore. Page 41

    Table 7-3Calibration data (3) Table 7-3Calibration Data (4)

    Applied

    Load

    (SF)(kg)

    Measured load

    (kg) % Error

    10 10.0333 -0.333

    20 19.933 0.335

    30 29.9616 0.128

    40 39.9879 0.0302

    50 49.8957 0.2086

    40 40.1149 -0.2872

    30 30.1812 -0.604

    20 20.0187 -0.0935

    10 9.9803 0.197

    Applied Load

    (RM)(kg-m)

    Measured load

    (kg-m) % Error

    10 10.0333 -0.333

    20 19.933 0.335

    30 29.9616 0.128

    40 39.9879 0.0302

    50 49.8957 0.2086

    40 40.1149 -0.2872

    30 30.1812 -0.604

    20 20.0187 -0.0935

    10 9.9803 0.197

  • Design, Optimization and Calibration of 6-Component External Wind Tunnel Balance

    Department of Mechanical Engineering, B M S College of Engineering, Bangalore. Page 42

    Table 7-4Calibration data (5) Table 7-5 Calibration Data (6)

    The calibration data shows that the balance behaves in a linear fashion in the range of loads

    applied. The transformation matrix obtained is almost a diagonal matrix as expected. Percentage

    error is less than 1% of maximum load in each component.

    Applied

    moment

    (YM)(kg-m)

    Measured

    moment

    (kg-m)

    % Error

    -2 -1.9638 1.81

    -4 -3.934 1.65

    -6 -5.9076 1.54

    -8 -7.8926 1.3425

    -6 -5.9025 1.625

    -4 -3.9642 0.895

    -2 -1.9769 1.155

    Applied moment

    (PM)(kg-m)

    Measured

    moment

    (kg-m)

    % Error

    1.2 1.1882 0.9833

    2.4 2.3997 0.0125

    3.6 3.6198 -0.55

    4.8 4.8037 -0.0771

    6 6.0227 -0.3783

    4.8 4.8202 -0.4208

    3.6 3.6155 -0.4306

    2.4 2.4208 -0.8667

    1.2 1.1992 0.0667

  • Design, Optimization and Calibration of 6-Component External Wind Tunnel Balance

    Department of Mechanical Engineering, B M S College of Engineering, Bangalore. Page 43

    8 The Concept of I-Beam and Spring Element

    8.1 I-Beam

    Figure 8-1Concept of I-Beam

    When an I-beam bends the top of the beam is in compression and the bottom is in tension. These

    forces are greatest at the very top and very bottom. So to make the stiffest beam with the least

    amount of material you would want the material to be only at the top and bottom sides. However

    still need to connect them together or they would just be two separate plates and would not be

    stiff at all. So need to put a web in the middle to connect them and make them work together.

    The idea is to remove material that is not carrying much load and concentrating the material

    where the load is highest. Its an extremely efficient shape for resisting bending.

  • Design, Optimization and Calibration of 6-Component External Wind Tunnel Balance

    Department of Mechanical Engineering, B M S College of Engineering, Bangalore. Page 44

    Figure 8-2Force measuring element without and with I-beam

    8.2 FE Analysis of Force Measuring element without and with I-

    beam

    Figure 8-3FE analysis of force measuring elements

    A study was carried out on various configurations of force measuring elements using Finite

    Element Analysis. It was found that an I- beam induced in-between type of force measuring

    element met all requirements and was found to be sensitive only to the normal loading and

    insensitive to all other loads and moments. Static FE analysis of the force measuring element was

    carried out. An attempt was made to reduce the coupling between various forces & moments and

    to make the components sensitive only to their respective normal loads and to protect the load

    cells.

  • Design, Optimization and Calibration of 6-Component External Wind Tunnel Balance

    Department of Mechanical Engineering, B M S College of Engineering, Bangalore. Page 45

    8.3 Spring Element in place of Load cell

    Figure 8-4FE analysis of force measuring element by replacing sring inplace of load cell

    The static FE analysis of the complete assembly force balance was carried out by replacing

    spring element in place of load cells, because there are no options to create and simulate load

    cells like elements in Ansys and some other available analysis softwares. When a spring is

    compressed or stretched from its initial position after applying force on an element, the force or

    reaction it exerts is approximately proportional to its change in length.

  • Design, Optimization and Calibration of 6-Component External Wind Tunnel Balance

    Department of Mechanical Engineering, B M S College of Engineering, Bangalore. Page 46

    9 FEM analysis of external force balance

    9.1 Normal Force, Rolling moment and pitching moment measurement

    Figure 9-1Nf, Rm, Pm measurement

    The vertical components of the load on the model are sensed by the three load cells fitted

    vertically. These loads cells are designated as V1, V2 and V3.

    Applied NF (N) V1 (N) V2 (N) V3 (N)

    -100 50.98 50.08 0.180

    -200 100.29 100.26 0.554

    -300 150.15 149.85 0.205

    -400 200.20 200.15 0.340

    Table 9-1Nf measurement

  • Design, Optimization and Calibration of 6-Component External Wind Tunnel Balance

    Department of Mechanical Engineering, B M S College of Engineering, Bangalore. Page 47

    9.2 Side Force and Yawing moment measurement

    Figure 9-2Sf, Ym Measurement

    For sensing side force and yawing moment, there are two load cells fitted horizontally. These

    load cells are designated as H1, H2.

    Applied SF (N) H1 (N) H2 (N)

    50 -24.99 24.99

    100 -49.99 49.99

    150 -74.99 74.99

    200 -99.99 99.99

    Table 9-2Sf measurements

  • Design, Optimization and Calibration of 6-Component External Wind Tunnel Balance

    Department of Mechanical Engineering, B M S College of Engineering, Bangalore. Page 48

    9.3 Axial Force Measurement

    Figure 9-3Af measurement

    In the horizontal plane for sensing axial force one load cell is provided in axial direction and is

    designated as H3.

    Table 9-3Af measurement

    Applied AF (N) H3 (N)

    25 24.99

    50 49.99

    75 74.99

    100 99.99

  • Design, Optimization and Calibration of 6-Component External Wind Tunnel Balance

    Department of Mechanical Engineering, B M S College of Engineering, Bangalore. Page 49

    9.4 Combined forces and Moments:

    Figure 9-4Combined forces and moments measurements

    From V1, V2, V3, H1, H2 and H3 load cells the six-components of forces and moments are

    obtained.

    Table 9-4Combined forces and moments measurements

    Applied

    load

    (N) V1 (N) V2 (N) V3(N) H1(N) H2(N) H3(N)

    Af 50 -0.00004 -0.0038 -0.0019 -0.0049 -0.00027 49.99

    Sf 100 -0.00035 -0.00098 -0.00037 -49.99 49.99 -

    0.00022

    Nf 200 -100.001 -100.001 0.544 -0.0002 -0.0009 -0.0003

  • Design, Optimization and Calibration of 6-Component External Wind Tunnel Balance

    Department of Mechanical Engineering, B M S College of Engineering, Bangalore. Page 50

    9.5 Stress and Deformation plot

    Figure 9-5Stress and Deformation plot

    The static FE Analysis shows that, stresses and deformations in a designed external balance are

    within the limits for specified range of forces and moments.

    Material Used: EN24 Steel.

    Table 9-5EN24 steel properties

    EN24 Mechanical Properties

    Max Stress 850-1000 MPa

    Yield Stress 680 MPa

    0.2% Proof Stress 665 Mpa

    Elongation 13%

    Hardness 248-302 Brinell

    EN24 Chemical composition

    Carbon 0.36-0.44%

    Silicon 0.10-0.35%

    Manganese 0.45-0.70%

    Sulphur 0.040 Max

    Phosphorus 0.035 Max

    Chromium 1.00-1.40%

    Molybdenum 0.20-0.35%

    Nickel 1.30-1.70%

  • Design, Optimization and Calibration of 6-Component External Wind Tunnel Balance

    Department of Mechanical Engineering, B M S College of Engineering, Bangalore. Page 51

    10 Conclusions and Recommendations

    10.1 Conclusions 1. Calibration procedure is explained in detail and data obtained is presented.

    2. The calibration data shows that the balance behaves in a linear fashion in the range of

    loads applied. The transformation matrix obtained is almost a diagonal matrix as

    expected. Percentage error is less than 1% of maximum load in each component.

    3. The balance can be utilised to determine aerodynamic loads within the specified range

    of forces and moments.

    4. The FE Analysis shows that, stresses and deformations of the designed external

    balance are within the limits as.

    10.2 Recommendations

    Recommendations for future works into developing the external force balance include:

    1. Alter the balance so that two or more struts can be used to support models which will

    allow for additional stability.

    2. Install vibration isolators that support the force balance to reduce vibration and increase

    stability

    3. Create a software program that enables easier calibration, better display, that will reduce

    the impact of vibrations on readings

    4. The present work could be extended for developing a design package for complete design

    of the balance and preparation of design data that would further help in the design of

    actual wind tunnel balances.

  • Design, Optimization and Calibration of 6-Component External Wind Tunnel Balance

    Department of Mechanical Engineering, B M S College of Engineering, Bangalore. Page 52

    11 References

    [1] Miguel A. Gonzalez, Jose Miguel Ezquerro, Victoria Lapuerta, Components of a Wind

    Tunnel Balance: Design and Calibration (2012).

    [2] AnkitSoni, PankajPriyadarshi,Finite Element Analysis and Optimization of a Beam Type

    Load cell for an External Balance design Aerospace Engg. Dept. Indian Institute of Space

    Science and Technology, Trivandrum-695547

    [3] HosseinNabipour,Wind Tunnel revitalization project, Memorial University, Mechanical

    Engg. Dept. (2006)

    [4] M. Sandu, A. Sandu, Analytic-numerical approach in a multicomponent strain gauge

    transducer design, Scientific Bulletin of University politehnica of Bucharest, vol67, no. 3,

    pp. 37- 44( 2005).

    [5] Gorlin S.M &Slezinger,Wind Tunnels and Their Instrumentation, Israel Program for

    Scientific Translations, No 1680, Israel Jerusalem (2009).

    [6] Tropea. C, Yarin.A.L, Foss.J.F,Force and Moment Measurements, Springer (2007).

    Retrived from

    [7] Frederick Francois Pieterse, Design and Development of a six Component Strain Gauge

    Wind Tunnel Balance, Rand Afrikaans University (2010).

    [8] Design of a six component External strain gage balance, NASA Website

    [9] Engler R.H, Klein C, Wind Tunnels and Wind Tunnel Test Techniques, Cambridge, UK,

    Paper 43 (1997).

    [10] Robinson, M.J. Mee, D.J Tsai, C.Y. Bakos, Measurement of three components of Force on

    a large scramjet in a shock tunnel Journal of Spacecraft and Rockets 41(2004).

    [11] J.B. Barlow, W.H. Rae Jr and A.Pope, Low-Speed wind Tunnel, 3rd Ed. John Wiley &

    Sons, New York (1999).

    [12] G. Schewe, Force measurements in aerodynamicsusingpiezo-electric multicomponent force

    transducers, Proc. 11th iciasf, 85 Record, Stanford University (1985)

  • Design, Optimization and Calibration of 6-Component External Wind Tunnel Balance

    Department of Mechanical Engineering, B M S College of Engineering, Bangalore. Page 53

    [13] Beginners Guide to Wind Tunnels, Glenn learning technologies project, NASA, Retrieved

    from

    [14] B. Ewald, Multi-component force balances for conventional and cryogenic wind tunnels,

    Meas. Sci.Technol. 11, 8194 (2000)

    [15] Tiffany. A, Wind Tunnel Instrumentation, Electronic Engg. Vol 29, No.3, (1957)

    [16] Pollok. N, The optimum design of stain gauge sting balance for wind tunnel models,

    Report 133, aeronautical research laboratories, Australia (1979)

    [16] Levvy .L.E and Saunders.C.G, A modern wind tunnel balance, J.roy.Aero.Soc. vol 57,

    512-520 (1953)

    [17] Alonpope and John.J.Harpus,Low wind tunnel testing, John Wiley & Sons N.Y (1966).

    [18] Reston, Assessment of Experimental Uncertainty with Application to Wind Tunnel

    Testing, AIAA S-071A (1999).

    [19] G Schewe, Force measurement in aerodynamics using peizo-electric multicomponent force

    transducer, 11th ICIASF 85 Record, Stanford University, (1985).

    [20] Reston, Calibration and Use of External Strain Gauge Balance with Application to Wind

    Tunnel Testing, AIAA R-091(2003)

  • Design, Optimization and Calibration of 6-Component External Wind Tunnel Balance

    Department of Mechanical Engineering, B M S College of Engineering, Bangalore. Page 54

    12 Appendix

    12.1 Appendix A

    The modeling of the external force balance with the required configuration is designed using

    CATIA V5 software. The front, top, side and isometric views of the balance is shown in the

    following figures.

  • Design, Optimization and Calibration of 6-Component External Wind Tunnel Balance

    Department of Mechanical Engineering, B M S College of Engineering, Bangalore. Page 55

  • Design, Optimization and Calibration of 6-Component External Wind Tunnel Balance

    Department of Mechanical Engineering, B M S College of Engineering, Bangalore. Page 56

  • Design, Optimization and Calibration of 6-Component External Wind Tunnel Balance

    Department of Mechanical Engineering, B M S College of Engineering, Bangalore. Page 57


Recommended