DOCUMENT TITLE Potable Water System Tie-
in(TP-PI-07A&B) andassociated pipe work
between the RGA LQ and ALQ module
DOCUMENT Number
BRZ-QT-WP-PN-0002
PROJPAGE
2 of 19
REVISION
0BRZ
CHANGE RECORD
REVISION
NUMBER
ITEM
NUMBER
DESCRIPTION OF CHANGE
A ALL Issued for IDC
B Issued for Approval (IFA)
C Re- IFA
0 Approved for construction
8/18/2019 Ras Gas Work pack
4/30
DOCUMENT TITLE Potable Water System Tie-
in(TP-PI-07A&B) and
associated pipe workbetween the RGA LQ and ALQ module
DOCUMENT Number
BRZ-QT-WP-PN-0002
PROJPAGE
3 of 19
REVISION
0BRZ
TABLE OF CONTENTS
1.0 SUMMARY ......................................................................................................................... 5
1.1 Justification ......................................................................................................................... 5
1.2 Corresponding eMOC Number ........................................................................................... 5
1.3 Outline Scope of Work ........................................................................................................ 5
1.3.1 Disciplines ........................................................................................................................... 5
1.4 Equipment / System Affected / Impacts to Operations ....................................................... 6
1.5 Related Workpacks ............................................................................................................. 6
1.6 Shutdown Content .............................................................................................................. 6
1.7 Engineering Queries ........................................................................................................... 6
1.8
Special Requirements ......................................................................................................... 7
1.9 Isolations ............................................................................................................................. 8
1.9.1 Workpack Isolations ............................................................................................................ 8
1.10 Work excludes from this workpack ..................................................................................... 8
2.0 SCOPE OF WORK ............................................................................................................. 9
2.1 Offshore Construction ......................................................................................................... 9
2.1.1 Pipe Activities………………………………………………………………………………………9
2.2 Tie ins ................................................................................................................................. 9
2.2.1 Pipe Tie-ins ………………………………………………………………………………………..9
3.0 DRAWING & DOCUMENTS ............................................................................................. 10
R f &
8/18/2019 Ras Gas Work pack
5/30
DOCUMENT TITLE Potable Water System Tie-
in(TP-PI-07A&B) and
associated pipe workbetween the RGA LQ and ALQ module
DOCUMENT Number
BRZ-QT-WP-PN-0002
PROJPAGE
4 of 19
REVISION
0BRZ
5.3 Safety Checklist……………………………………………………………………..…………..12
5.4 Accident / Incident Reporting………………………………………………………..…………12
5.5 Special Requirements………………………………………………………………..…………13
5.6 Habitats………………………………………………………………………………..………….13
5.7 Scaffolding………………………………………………………………………………..………13
6.0 MATERIALS…………………………………………………………………...…………………14
6.1 Key/Critical items of equipment……………………………………………..…………………14
6.2 MTO by Workpack………………………………………………………………..……………..14
6.3 Equipment & Consumables……………………………………………………..……………...14
6.4 Materials Queries………………………………………………..……………………………....14
7.0 CONSTRUCTION METHOD STATEMENT……..……………………………………………15
7.1
Subcontractor / Vendor Assistance .................................................................................. 15
8.0
JOBCARDS ...................................................................................................................... 15
9.0 INSPECTION AND TEST CETIFICATION REQUIREMENTS ......................................... 15
9.1 Completion / Handover Certificates .................................................................................. 15
9.2 Inspection & Test Summary Requirements Matrix ........................................................... 16
9.3 Test Packs ........................................................................................................................ 16
10.0
TECHNICAL QUERIES .................................................................................................... 17
11.0 AS BUILDING…………………………………………………………………………………….20
12.0 ATTACHMENTS…………………………………………………………………………………21
8/18/2019 Ras Gas Work pack
6/30
DOCUMENT TITLE Potable Water System Tie-
in(TP-PI-07A&B) and
associated pipe workbetween the RGA LQ and ALQ module
DOCUMENT Number
BRZ-QT-WP-PN-0002
PROJ
PAGE
5 of 19
REVISION
0BRZ
1.0 SUMMARY
1.1 Justification
The existing potable water system on the RGA LQ will be tied into and combined with the new
potable water system on the ALQ. This will provide greater capacity and flexibility.
1.2 Corresponding eMOC Number
This will be supplied by RG eMOC initiator in a later revision.
1.3 Outline Scope of Work
1. Install all new required pipe supports (pipe supports are detailed in the pipe support
workpack).
2. Under the guidance of RG Operations& PMT conduct all required shutdowns (QT-Y-9402Potable water Press. Set), isolations and LOTOs (5 valves total, see section 1.9.1).
3. Depressurise as required.
4. Remove blind at TP-PI-07A
5. Install tie in tee piece (including new isolation valve HV393 NC in closed position).
6. Carry out any required testing
7. Under the guidance of RG Operations & PMT remove all isolations and LOTOs.
8. RG Operations to bring QT-Y-9402 Potable Water Press Set back into service.
9. Install piping (new line QT-WPT-840-4”-DBS1) between tie in location TP-PI-07B and ALQ
closure spool location
8/18/2019 Ras Gas Work pack
7/30
DOCUMENT TITLE Potable Water System Tie-
in(TP-PI-07A&B) and
associated pipe workbetween the RGA LQ and ALQ module
DOCUMENT Number
BRZ-QT-WP-PN-0002
PROJ
PAGE
6 of 19
REVISION
0BRZ
The tie in TP-PI-07 will require the potable water press set to be shut down. This will restrict
the potable water supply. Review the best time to execute this work with Operations
(potentially night shift work).
HHI piping engineering & construct ion to consider installation of the new pipe spools. There
is limited crane access in this area.
1.3.1 Disciplines
Disciplines Included In Work Scope:
Piping Structural Electrical Instruments Rigging Scaffolding Vendor Other
Pipe
supports 1
1.4 Equipment / System Affected / Impacts to Operations
The potable water maker and associated systems will require to be shut down during thispiping modification. To be assessed with, and confirmed by, RGA Operations.
This work scope will be planned so that potable water supply will still be available from
the water stored in the storage tanks.
1.5 Related Workpacks
There are no workpacks related to this scope of work.
1.6 Shutdown Content
The potable water maker and associated systems will require to be shut down during this
8/18/2019 Ras Gas Work pack
8/30
DOCUMENT TITLE Potable Water System Tie-
in(TP-PI-07A&B) and
associated pipe workbetween the RGA LQ and ALQ module
DOCUMENT Number
BRZ-QT-WP-PN-0002
PROJ
PAGE
7 of 19
REVISION
0BRZ
HHI DCC DCC TBC
All Engineering Queries are to be accompanied by a standard HHI engineering Query
Form.
1.8 Special Requirements
The below table highlights activities for the attention of RasGas Operations.
Activity Yes No
Hot Work Yes
Stress Relieving No
Lifting Yes
Blocked Access/Egress Yes
Scaffolding Yes
Use of Existing Facilities Yes
External Working Hours / Shift Pattern No
SIMOPS No
Overboard Work No
HYDM Test No
Pressure Testing using N2 No
Radiographic test No
8/18/2019 Ras Gas Work pack
9/30
DOCUMENT TITLE Potable Water System Tie-
in(TP-PI-07A&B) and
associated pipe workbetween the RGA LQ and ALQ module
DOCUMENT Number
BRZ-QT-WP-PN-0002
PROJ
PAGE
8 of 19
REVISION
0BRZ
1.9 Isolations
Isolation information will be updated in later revisions.
1.9.1 Workpack Isolations
The following lines and/or equipment require isolation in accordance with the above prior
to work commencing under this workpack
Isolation
Number
SystemLine and/or
Equipment No.Scope
Description
P&ID
1 Existing Potable
Water
Valve BBFS8 HV0031 Close valve and
LOTO
4950-QT-PR-4104
2 Existing Potable
Water
Valve BBFS8 HV0035 Close valve and
LOTO
4950-QT-PR-4104
3 Existing Potable
Water
Valve BBFS8 HV0039 Close valve and
LOTO
4950-QT-PR-4104
4 Existing Potable
Water
QT-P-9401A, Valve
HV0112
Close valve and
LOTO
4950-QT-PR-4104
5 Existing Potable
Water
QT-P-9401A, Valve
HV0113
Close valve and
LOTO
4950-QT-PR-4104
6 Existing Potable
Water
BBFS8 HV393NC Close valve and
LOTO
4950-QT-PR-4104
Refer to Attachment No. 03) for P&ID mark-up of isolations to facilitate tie-ins.to be
completed for 1st issue.
8/18/2019 Ras Gas Work pack
10/30
DOCUMENT TITLE Potable Water System Tie-
in(TP-PI-07A&B) and
associated pipe workbetween the RGA LQ and ALQ module
DOCUMENT Number
BRZ-QT-WP-PN-0002
PROJ
PAGE
9 of 19
REVISION
0BRZ
2.0 SCOPE OF WORK
2.1 Offshore Construct ion
HHI will provide a scope of work detailing all construction activities required during the
execution of this workpack.
2.1.1 Piping Act ivi ties
1. Install all required scaffolding required for this workpack (see the construction method
statement for details).
2. Install all new required pipe supports (locations to be confirmed by HHI piping post
piping-survey). (Note: If the installation of supports requires Hot Work then installation
of appropriate welding habitat (pressurised or non-pressurised) shall be done prior to
starting the work.)
3. Make all required isolations and LOTOs required to install the tie in spool (see section1.9.1).
4. Make tie in. Remove LOTOs.
5. Install new piping from ALQ to tie in location.
6. Isolate and LOTO new valve BBFS8 HV393NC
7. Make tie in at TP-PI-07B
8. Remove isolations.
2.2 Tie ins
2 2 1 Pi i Ti i
8/18/2019 Ras Gas Work pack
11/30
DOCUMENT TITLE Potable Water System Tie-
in(TP-PI-07A&B) andassociated pipe work
between the RGA LQ and ALQ module
DOCUMENT Number
BRZ-QT-WP-PN-0002
PROJ
PAGE
10 of 19
REVISION
0BRZ
3.0 DRAWING & DOCUMENTS
3.1 Reference Drawing & Documents
Included in this section are the following reference document types (as required) :
Tie-in Register
Marked up Drawings
Isometric Drawings
3.1.1 Tie-in Register
Document No. Title Rev
BRZ-QT-L-PN-0001TIR COMBINED ALQ & RGA A
3.1.2 Marked up drawings
Drawing No. Title Rev
49450-QT-PR-4104 QUARTERS PLATFORM PIPING &
INSTRUMENTATION DIAGRAM POTABLE
WATER MAKER.
7D
49450-QT-PR-4108 QUARTERS PLATFORM PIPING &
INSTRUMENTATION DIAGRAM WASHDOWN
SYSTEM
9D
49450-QT-PR-4104 P&ID marked up to show isolation points.
8/18/2019 Ras Gas Work pack
12/30
DOCUMENT TITLE Potable Water System Tie-
in(TP-PI-07A&B) andassociated pipe work
between the RGA LQ and ALQ module
DOCUMENT Number
BRZ-QT-WP-PN-0002
PROJ
PAGE
11 of 19
REVISION
0BRZ
Note all pip ing destruct and construct Isometrics are to be included and attached in
this workpack.
4.0 PROCEDURES / SPECIFICATIONS / REFERENCES
The following RasGas documents will be adhered to during the execution of this workpack.
TO BE INCLUDED IN LATER REVISIONS.
8/18/2019 Ras Gas Work pack
13/30
DOCUMENT TITLE Potable Water System Tie-
in(TP-PI-07A&B) andassociated pipe work
between the RGA LQ and ALQ module
DOCUMENT Number
BRZ-QT-WP-PN-0002
PROJ
PAGE
12 of 19
REVISION
0BRZ
5.0 SAFETY
Refer to JSA attachment 7.
5.1 General
All construction activities shall comply with the RasGas Safety Management System.
5.2 Permit to Work System
The RasGas Permit To Work system has been designed to assist CONTRACTOR and
operating personnel working on RasGas offshore installations to carry out work in
accordance with safe working practices.
The PTW system includes regulations, procedures, documentation and guidance notes
laying down the conditions of work and precautions which must be taken by HHI during
the execution of any work to ensure safety of both personnel and plant. The permit to
work system has been designed as both a working and reference document.
The permits issued for work in this workpack will be discussed at the permit meeting prior
to the commencement of the work.
All permits must be applied for by HHI PTW trained personnel a minimum of 24 hours in
advance of commencing the work.
5.3 Safety Checklist
The following activities will be carried out :
a. Discuss work scope permits with the production / discipline supervisors
b Tool box talk with foreman / charge-hand
8/18/2019 Ras Gas Work pack
14/30
DOCUMENT TITLE Potable Water System Tie-
in(TP-PI-07A&B) andassociated pipe work
between the RGA LQ and ALQ module
DOCUMENT Number
BRZ-QT-WP-PN-0002
PROJ
PAGE
13 of 19
REVISION
0BRZ
RasGas will be informed of all hot work requirements after the site verification study.
5.6 Habitats
Consultation is required with RasGas operations before establishing temporary habitatrequirements prior to construction work commencing. HHI is to supply and install the
necessary material for the habitats.
5.7 Scaffolding
HHI will ensure Scaffolding erected for installation activities does not inhibit F&G
detection or deluge system.
Plans for Scaffolding will be submitted by HHI to RasGasOperations30 days in advance
of any planned erection.
8/18/2019 Ras Gas Work pack
15/30
DOCUMENT TITLE Potable Water System Tie-
in(TP-PI-07A&B) andassociated pipe work
between the RGA LQ and ALQ module
DOCUMENT Number
BRZ-QT-WP-PN-0002
PROJ
PAGE
14 of 19
REVISION
0BRZ
6.1 Key/Crit ical items of equipment
POS for Key/Critical items of equipment identified by workpack and by tie-in, will be
included in the 1st revision of each workpack.
Item PO Number Vendor Supplied by
BULK ITEM XXX XXX HHI Offshore
VALVE XXX XXX HHI Offshore
6.2 Workpack MTO4” Bolt/Nut & gasket. See attached isometric drawing.
6.3 Equipment & Consumables
Construction Information to be included in later revisions.
6.4 Materials Queries
Refer all materials queries to HHI Materials Coordination focal point
Name e-mail Telephone Number
TBC
Material for this work scope is held at HHI onshore materials storage facility, in Ulsan andwill be shipped directly to the platform after being checked and confirmed by HHI
Brownfield Engineer.
• All materials are to be checked on arrival to the platform to ensure that there has
8/18/2019 Ras Gas Work pack
16/30
DOCUMENT TITLE Potable Water System Tie-
in(TP-PI-07A&B) andassociated pipe work
between the RGA LQ and ALQ module
DOCUMENT Number
BRZ-QT-WP-PN-0002
PROJ
PAGE
15 of 19
REVISION
0BRZ
All required work to complete this workpack will be executed under the RG PTW system. All PTW will
be completed and submitted to RG Operations the day before the planned work.
HHI will only perform LOTO and Isolations under the guidance of RG Operations & RG PMT.
All bolts will be hot bolted before proceeding with tie-in work.
Testing will be as per the line list.
Prefabrication of pipe spools will be maximized.
This work will be completed in stages as per the level 3 schedule. This workpack can only be
completed after the ALQ installation.
Any pipe work that is pre-installed before the ALQ installation will have a cap end installed to protect
the pipe.
Scaffolding will be set up so all workers have a safe working platform.
This work will be conducted by the following team: 1 supervisor, 5 pipefitters & 1 safety.
7.1 Subcontractor / Vendor Assistance
No need any subcontractor / Vendor because HHI will perform.
8.0 JOBCARDS
CONSTRUCTION INFORMATION TO BE INCLUDED IN LATER REVISIONS.
8/18/2019 Ras Gas Work pack
17/30
DOCUMENT TITLE Potable Water System Tie-
in(TP-PI-07A&B) andassociated pipe work
between the RGA LQ and ALQ module
DOCUMENT Number
BRZ-QT-WP-PN-0002
PROJ
PAGE
16 of 19
REVISION
0BRZ
9.2 Inspection & Test Summary Requirements Matrix
The following Discipline Inspection and Test Summary’s are applicable to this workpack
Discipline Platform System Ref. MC-1 Ref.
Electrical / Mechanical
Note: Discipline, Inspection and Test Summary’s detail minimum certification
Examples of additional certification.
Calibration, NDT, Leak Testing, Coating, Load Testing or Bolt Tensioning
Punch list.
Discipline punch lists are included within each ITS. Record outstanding items according
to original work scope at handover stage
9.3 Test Packs
8/18/2019 Ras Gas Work pack
18/30
DOCUMENT TITLE Potable Water System Tie-
in(TP-PI-07A&B) andassociated pipe work
between the RGA LQ and ALQ module
DOCUMENT Number
BRZ-QT-WP-PN-0002
PROJ
PAGE
17 of 19
REVISION
0BRZ
10.0 TECHNICAL QUERIES
8/18/2019 Ras Gas Work pack
19/30
DOCUMENT TITLE Potable Water System Tie-
in(TP-PI-07A&B) andassociated pipe work
between the RGA LQ and ALQ module
DOCUMENT Number
BRZ-QT-WP-PN-0002
PROJ
PAGE
18 of 19
REVISION
0BRZ
11.0 AS BUILDING
HHI will follow the BARZAN Project as-building procedure.
The contractor shall be responsible for preparing redline as built mark-ups for any agreed
deviation to the AFC design during installation, pre-commissioning and commissioning.
During installation, all design changes must be marked-up / as-built on the relevant
drawings and collated onto the designated RasGas workpack set of documents. Upon
completion of mechanical completion / commissioning / system hand-over, all drawings
must be stamped “As-Built”, signed and dated (including those drawings that have no
changes). Contractor to prepare field sketch for any obstruction / clashing occur as per project design
document and shall obtain RasGas PMT Operations approval prior to start with the work.
8/18/2019 Ras Gas Work pack
20/30
DOCUMENT TITLE Potable Water System Tie-
in(TP-PI-07A&B) andassociated pipe work
between the RGA LQ and ALQ module
DOCUMENT Number
BRZ-QT-WP-PN-0002
PROJ
PAGE
19 of 19REVISION
0BRZ
12.0 ATTACHMENTS
1) 49450-QT-PR-4104 QT Platform piping & instrumentation potable water maker.
2) 49450-QT-PR-4108 QT Platform piping & instrumentation wash down system.
3) 49450-QT-PR-4104 P & ID Isolation Mark Up.
4) Isometrics to be attached in a subsequent revision.
5) Model shots and Photographs.
6) Model shot for interconnecting line between ALQ and QT.
7) JSA-PN-0002
8/18/2019 Ras Gas Work pack
21/30
8/18/2019 Ras Gas Work pack
22/30
8/18/2019 Ras Gas Work pack
23/30
1
8/18/2019 Ras Gas Work pack
24/30
N
2 2
SEE SHT
SHT 1
E 67294
N 61991
EL +29992
59
4 NPD
4X4 NPD
6
6
4
5
1
EL +29541
4 N
PD
5
8
230
STEM W 4 5 .0 S
5
7
5
5
CONN TO
QT-T-9401A/ A1
4 FFF E 150#
E 66708
N 63124
EL +29541
4
8
8
5
6
8
8
4X4 NPD
8
7
INSUL:
N
E 60655
N 61804
EL +2 9 9 9 2
INSUL:
0’ 0
TP-PI-07
5
9
CONN TO
QT-Y-9402/ II
4 F FFE 150#
E 60655
N 6 2 3 5 0
EL +29992
QT-WPT-388-DBS1-N
QTPA0112
U
QT-WPT-388-4 -DBS1-N
49450-QT-PR-4104
QT-WPT-388-DBS1 0.5000 25. 00 8.6200
48.90
0.000 DBS1
N O PA I N T 4 N
0.0
ANALY
NONE
2 2
R ASGAS OFFSHOR E EXPANSION PR OJ EC T
PDS Model Number:
PAINT
N O TES: -
I
F
N
m
e
%
CHECK ISOMETRIC
RasGas Company Limi ted
CONSULTANT/CONTRACTOR :
HEAVY INDUSTRIES CO., LTD.
402025-00546
N
FABRICATION MATERIALS
U
T SIZE
NO COMPONENT DESCRIPTION (Inch) ITEM CODE QTY
SEE ISO
QT-388
E 60655
F4 G7 B8
TP-PI-07
QT-WPT-840-4 -DBS1-N
8/18/2019 Ras Gas Work pack
25/30
U U U
1 PIPE D1784 SL-PE S/80 4 1PPP0180 7.8 M
U
2 TEE STR D1784 SW S/80 4X4 3TSP0180 1
U
3 ELBOW 90D D1784 SW S/80 4 3ELP0180 5
U
4 FLG WN D1784 FF 150 -S/80 4 2FWP0018 7
U
5 FLG BLD D1784 FF 150 4 2FBP0010 1
U
U
ERECTION MATERIALS
U
T SIZE
NO COMPONENT DESCRIPTION (Inch) ITEM CODE QTY
U
U
U
6 PIPE PE S-80 CPVC, D1784 CL 23447-B 4 PIPPPP5 1.8 M
U
7 GSKT GARLOCK-3400 FULL FACE 150#-1/16 4 5GF05J34 6
U
8 STUD B/N/PW A193B7M/A1942HM XYLAN, 110.0MM BOLT 5/8 6BN0270P 48
LENGTH
9 VALVE BALL FB CPVC FF 150# TAG NO:BBFS8 4 7VBBFS8X 1
U
PIPE SUPPORTS
U
0 PC02-4 4 PSL 2
U
1 REST 4 PSL 1
U
2 IS01 4 4 PSL 1
U
PIECE MARKS
U
SP 1 SP2 SP3 SP4
U U
CUT PIPE LENGTH
U
PIECE LENGTH NPD REMARKS PIECE LENGTH NPD REMARKS
NO (MM) (IN) NO (MM) (IN)
U
169 4 206 4
1250 4 387 4
164 4 1474 4
1722 4 327 4
3605 4 150 4
N 61975
EL +29992
*UNDEFI NED*
SP
<
>
N
P
D
*UNDEFI NED*
2
4
3
2
4X4 NPD
*UNDEFI NED*
<
>
*UNDEFI NED*
2
7
9
4 G7 B8
380
9
F4 G7 B8
*UNDEFI NED*
SP2
3
5
2
S10
3-074
<
>
*UNDEFI NED*
1
3
2
3
3
*UNDEFI NED*
<
4
>
*UNDEFI NED*
5
3
*UNDEFI NED*
<
*UNDEFI NED*
2
3
EL +29695
*UNDEFI NED*
1
1
1
4
S10
3-071
<
6
>
*UNDEFI NED*
1
6
7
3
67
*UNDEFI NED*
9
2
9
S11
3-093
<
7
>
*UNDEFI NED*
1
7
2
9
F4
F4 G7 B8
*UNDEFI NED*
3
3
3
SP3
<
8
>
*UNDEFI NED*
66
SP4
3
*UNDEFI NED*
6
4
3
S12
3-166
<
9
>
4
N
P
D
*UNDEFI NED*
3
6
7
8
F4 G7 B8
SEE ISO
QT-WPT-840-1
E 53382
N 60055
EL +29695
*UNDEFI NED*
<
1
>
*UNDEFI NED*
2
2
3
F4 G7 B8
5
Q
T
A
D
W
T
R
H
D
2
D
QT05-WPT-840-1
DBS1
QT05
QT-WPT-840-4 -DBS1-N
N
D
N
M
O
N
LINE NO.
PACKAGE No.
P&ID REF.
PWHT
PAINT SYSTEM No.
INSULATION
SPOOL DATA
PROJECT
TYPE
THK
NOTE
GAD REF.
RT MT
UT PT
E
T
A
C
T
N
D
A
T
1. ORIGIN POINTS
CODE
SUB BLOCK.
ASME B31.3
SPEC I S O D W G N O .
R E V N o
ULSAN KOREA
(Q525)
OFFSHORE & ENGINEERING DIVISION
/N
1
2
3
4
5
6
7
8
9
SPOOL NO
SHT NO
STAGE NO REV
DESIGNED
[A](E 0 mm) &
[4](N 0 mm)
CHECKED
FOR FABRICATION
RZ N
BRZ-ALQ-D-PN-
BRZ-ALQ-D-PN-
5 Attachment Model shot and Photograph
8/18/2019 Ras Gas Work pack
26/30
8/18/2019 Ras Gas Work pack
27/30
6 Model shot for interconnecting line between ALQ and QT
QT05-WPT-840-1
Appendix –JSA Form
8/18/2019 Ras Gas Work pack
28/30
Appendix JSA Form
Job Safety Analysis forPotable water tie ins TI-PI-07A/B
ActivityWorkOrder
FunctionLocation
Piping tie-ins andassociatedpipework
At minimum, the following PPE is required for task
• Approved and inspected Hard Hat
• Safety Glasses with side shields
• Long sleeves coverall
• Approved gloves to be worn at all times (no
cotton gloves)• Approved Safety foot wear
**Mandatory control measures for all steps
Reviewed by Signature Date
Notes:
1. Job start meeting is to be held on the RGA Complex. At this meetingthe Workmethod and JSA will be reviewed and signed by all personnelinvolved in the taskany additional hazards identified will beadded to this
JSA and the summary sheet.2. Emergency procedure and Rescue plan will be discussed at the Job
Startmeeting.3. Work to be completed under PTW-Conditions.PTW must be on site and
signed by all personnel involved in task.
4. This is a living document and as such may be subject to review at anytime asidentified changes in conditions / work scope may dictate.Where a change has been identified, this will be managed in line with
HHIProcedures, Instructions, Specifications and Standards and will beexecuted/interfacedin accordance with other SHE&S Systems.
Amendments to the JSA may be added (written) / removed at thework sitewhen agreement has been reached by all concerned parties. 5.
This shall beupdated in JSA summary sheet, if available
JSA No: 0136 JSA
Title:
8/18/2019 Ras Gas Work pack
29/30
System: Train:
Task description:
UncontrolledRisk
ResidualRisk
STEP ACTIVITY HAZARD H M L CONTROL MEASURES H M L1. Scaffolding A. Working at height
B. Pinch points L
A. Working at height procedure, safe working
platform
B. Correct PPE (gloves) L
2 Installation of new
piping
A. Working at height
B. Erecting scaffold platform
on grating.
C. Use of manual tools
L
A. Working at height procedure
B. Personnel tied off at all times; even when lower
than handrail.
C. Correct PPE (gloves)
L
3
Tie‐ins
A. Pressurized
lines
L A. RG LOTO and Isolation procedure L
Approved Signature Print Title: Date
Performing Party Signature Print Title: Date