+ All Categories
Home > Documents > Rate Analysis

Rate Analysis

Date post: 26-Nov-2014
Category:
Upload: nikhil
View: 64 times
Download: 5 times
Share this document with a friend
Description:
its a rate analysis of construction item.
20
Rate Analysis Sheet I.Material Cost Analysis : Material Quantity Rate Per Amount Rs. P. Rs. P. - - - - - Nil - Total Rs. - II.Labour Cost Analysis : Labour No. Rate Per Amount Rs. P. Rs. P. Male 1/3 60 0 day 20 0 Female 1/3 50 0 day 16 66 Total Rs. 36.66 III.Equipment Cost Analysis : Equipment Hire Charge Rs. P. 36 66 Add Water Charges 1.5 % 0 55 Add Sundaries 1 % 0 37 Total Cost Rs. 37 58 Total Cost for the item : a. Material cost - - b. Labour cost 36 66 Add Water Charges 1.5 % and Sundaries 1 c. Equipment cost 0 92 10% of Total Cost d. Contractor's profit 3 76 Total Rs. 41.34 Cost Rs. 41.30 per Rate Analysis Sheet I.Material Cost Analysis : Material Quantity Rate Per Amount Rs. P. Rs. P. - - - - - Nil - Excavation for foundation upto 1.5 m depth including disposal excavated material upto 50 m m 3 Excavation for foundation 1.5 m to 3 m depth including disposal excavated material upto 50 m
Transcript
Page 1: Rate Analysis

Rate Analysis Sheet

I.Material Cost Analysis :

Material QuantityRate

PerAmount

Rs. P. Rs. P.- - - - - Nil -

Total Rs. -II.Labour Cost Analysis :

Labour No.Rate

PerAmount

Rs. P. Rs. P.Male 1/3 60 0 day 20 0

Female 1/3 50 0 day 16 66

Total Rs. 36.66III.Equipment Cost Analysis :

EquipmentHire ChargeRs. P.36 66

Add Water Charges 1.5 % 0 55Add Sundaries 1 % 0 37

Total Cost Rs. 37 58Total Cost for the item :

a. Material cost - -b. Labour cost 36 66

Add Water Charges 1.5 % and Sundaries 1% c. Equipment cost 0 9210% of Total Cost d. Contractor's profit 3 76

Total Rs. 41.34Cost Rs. 41.30 per

Rate Analysis Sheet

I.Material Cost Analysis :

Material QuantityRate

PerAmount

Rs. P. Rs. P.- - - - - Nil -

Excavation for foundation upto 1.5 m depth including disposal excavated material upto 50 m

m3

Excavation for foundation 1.5 m to 3 m depth including disposal excavated material upto 50 m

Page 2: Rate Analysis

Total Rs. -II.Labour Cost Analysis :

Labour No.Rate

PerAmount

Rs. P. Rs. P.Male 11/30 60 0 day 22 0

Female 11/30 50 0 day 18 33

Total Rs. 40.33III.Equipment Cost Analysis :

EquipmentHire ChargeRs. P.40 33

Add Water Charges 1.5 % 0 60Add Sundaries 1 % 0 40

Total Cost Rs. 41 33Total Cost for the item :

a. Material cost - -b. Labour cost 40 33

Add Water Charges 1.5 % and Sundaries 1% c. Equipment cost 1 010% of Total Cost d. Contractor's profit 4 13

Total Rs. 45.46Cost Rs. 45.5 per

Rate Analysis Sheet

Providing and laying P.C.C.(1:4:8) and curing excluding formwork

I.Material Cost Analysis :

Material QuantityRate

PerAmount

Rs. P. Rs. P.Cement 1/13*1.54*28.8 3.41 145 0 bag 494.45

Sand 4/13*1.54 0.473 150 0 70.95

Aggregate 8/13*1.54 0.947 400 0 378.8

Total Rs. 944.2II.Labour Cost Analysis :

Labour No.Rate

PerAmount

Rs. P. Rs. P.Male 3/4 60 0 day 45 0

m3

m3

m3

Page 3: Rate Analysis

Female 1/2 50 0 day 25 0

Bhisti 1/5 60 0 day 12 0

Total Rs. 82.00III.Equipment Cost Analysis :

EquipmentHire ChargeRs. P.

Total Material and Labour Cost 1026.20 0Concrete Mixer 500 Rs. *1/20 day 25.00 0

Total 1051.20Add Water Charges 1.5 % 15.77 0

Total 1066.97Add Sundaries 1 % 10.66968 0

Total Cost Rs. 1077.64 0Total Cost for the item :

a. Material cost 944.2 0b. Labour cost 82.00 0

Add Water Charges 1.5 % and Sundaries 1% c. Equipment cost 51.44 010% of Total Cost d. Contractor's profit 107.7638 0

Total Rs. 1185.40Cost Rs. 1186.00 per

Rate Analysis Sheet

R.C.C.(1:2:4) Footing including formwork (1 mx 1 m) , excluding reinforcement

I.Material Cost Analysis :

Material QuantityRate

PerAmount

Rs. P. Rs. P.Cement 1/7*1.54*28.8 6.336 145 0 bag 918.72

Sand 2/7*1.54 0.44 150 0 66.00

Aggregate 4/7*1.54 0.88 400 0 352.00

Total Rs. 1336.72II.Labour Cost Analysis :

Labour No.Rate

PerAmount

Rs. P. Rs. P.Male 3/4 60 0 day 45 0

Female 1/2 50 0 day 25 0

Bhisti 1/5 60 0 day 12 0

m3

m3

m3

Page 4: Rate Analysis

Total Rs. 82.00III.Equipment Cost Analysis :

EquipmentHire ChargeRs. P.

Total Material and Labour Cost 1418.72 0Concrete Mixer 600 Rs. *1/30 day 20.00 0

160.00 0

Total 1598.72Add Water Charges 1.5 % 23.98 0

Total 1622.70Add Sundaries 1 % 16.22701 0

Total Cost Rs. 1638.93 0Total Cost for the item :

a. Material cost 1336.72 0b. Labour cost 82.00 0

Add Water Charges 1.5 % and Sundaries 1% c. Equipment cost 220.21 010% of Total Cost d. Contractor's profit 163.8928 0

Total Rs. 1802.82Cost Rs. 1803.00 per

Rate Analysis Sheet

R.C.C.(1:2:4) Column (400 mm * 250 mm) and their formwork excluding reinforcement

I.Material Cost Analysis :

Material QuantityRate

PerAmount

Rs. P. Rs. P.Cement 1/7*1.54*28.8 6.336 140 0 bag 887.04

Sand 2/7*1.54 0.44 200 0 88.00

Aggregate 4/7*1.54 0.88 400 0 352.00

Total Rs. 1327.04II.Labour Cost Analysis :

Labour No.Rate

PerAmount

Rs. P. Rs. P.Male 3/4 60 0 day 45 0

Female 1/2 50 0 day 25 0

Bhisti 1/5 60 0 day 12 0

Total Rs. 82.00III.Equipment Cost Analysis :

EquipmentHire ChargeRs. P.

Cost of Centering ( 80.00 Rs. Per Sq.m)* 2 m2 (Total 4 m length * 0.5 m height)

m3

m3

m3

Page 5: Rate Analysis

Total Material and Labour Cost 1409.04 0Concrete Mixer 600 Rs.*1/30 day 20.00 0

1040.00 0

Total 2469.04Add Water Charges 1.5 % 37.04 0

Total 2506.08Add Sundaries 1 % 25.06076 0

Total Cost Rs. 2531.14 0Total Cost for the item :

a. Material cost 1327.04 0b. Labour cost 82.00 0

Add Water Charges 1.5 % and Sundaries 1% c. Equipment cost 1122.10 010% of Total Cost d. Contractor's profit 253.1136 0

Total Rs. 2784.25Cost Rs. 2784.00 per

Rate Analysis Sheet

R.C.C.(1:2:4) Beam (250 mm * 300 mm) and their formwork excluding reinforcement

I.Material Cost Analysis :

Material QuantityRate

PerAmount

Rs. P. Rs. P.Cement 1/7*1.54*28.8 6.336 140 0 bag 887.04

Sand 2/7*1.54 0.44 200 0 88.00

Aggregate 4/7*1.54 0.88 400 0 352.00

Total Rs. 1327.04II.Labour Cost Analysis :

Labour No.Rate

PerAmount

Rs. P. Rs. P.Male 3/4 60 0 day 45 0

Female 1/2 50 0 day 25 0

Bhisti 1/5 60 0 day 12 0

Total Rs. 82.00III.Equipment Cost Analysis :

EquipmentHire ChargeRs. P.

Total Material and Labour Cost 1409.04 0Concrete Mixer 600.00 Rs.*1/30 day 20.00 0

917.60 0

Cost of Centering ( 80.00 Rs. Per Sq.m)* 13 m2 (Total (2*0.4+2*0.25)1.3 m length * 10 m height)

m3

m3

m3

Cost of Centering (80.00 Rs Per m2)* 11.47 m2 [(length= volume(1m3) /(c/s area(0.25*0.3) m]=13.50 m * 0.85 m (0.3+0.3+0.25) m length

Page 6: Rate Analysis

Total 2346.64Add Water Charges 1.5 % 35.20 0

Total 2381.84Add Sundaries 1 % 23.8184 0

Total Cost Rs. 2405.66 0Total Cost for the item :

a. Material cost 1327.04 0b. Labour cost 82.00 0

Add Water Charges 1.5 % and Sundaries 1% c. Equipment cost 996.62 010% of Total Cost d. Contractor's profit 240.5658 0

Total Rs. 2646.22Cost Rs. 2647.00 per

Rate Analysis Sheet

Yellow soil or Earth Filling in Plinth

I.Material Cost Analysis :

Material QuantityRate

PerAmount

Rs. P. Rs. P.Yellow soil or Earth 1 125 0 125.00

Total Rs. 125.00II.Labour Cost Analysis :

Labour No.Rate

PerAmount

Rs. P. Rs. P.Male 1/10 60 0 day 6 0

Female 1/10 50 0 day 5 0

Total Rs. 11.00III.Equipment Cost Analysis :

EquipmentHire ChargeRs. P.

Total Material and Labour Cost 136.00 0Add Sundaries 1 % 1.36 0

Total Cost Rs. 137.36 0Total Cost for the item :

a. Material cost 125.00 0b. Labour cost 11.00 0

Sundaries 1% c. Equipment cost 1.36 010% of Total Cost d. Contractor's profit 13.736 0

m3

m3

Page 7: Rate Analysis

Total Rs. 151.10Cost Rs. 151.00 per

Rate Analysis Sheet

R.C.C.(1:2:4) Slab and their formwork excluding reinforcement

I.Material Cost Analysis :

Material QuantityRate

PerAmount

Rs. P. Rs. P.Cement 1/7*1.54*28.8 6.336 145 0 bag 918.72

Sand 2/7*1.54 0.44 150 0 66.00

Aggregate 4/7*1.54 0.88 400 0 352.00

Total Rs. 1336.72II.Labour Cost Analysis :

Labour No.Rate

PerAmount

Rs. P. Rs. P.Male 3/4 60 0 day 45 0

Female 1/2 50 0 day 25 0

Bhisti 1/5 60 0 day 12 0

Mason 1/4 200 0 day 50 0Total Rs. 132.00

III.Equipment Cost Analysis :

EquipmentHire ChargeRs. P.

Total Material and Labour Cost 1468.72 0Concrete Mixer 500.00 Rs.*1/20 day 25.00 0

560.00 0Total 2053.72

Add Water Charges 1.5 % 30.81 0Total 2084.53

Add Sundaries 1 % 20.84526 0Total Cost Rs. 2105.37 0

Total Cost for the item :a. Material cost 1336.72 0b. Labour cost 132.00 0

Add Water Charges 1.5 % and Sundaries 1% c. Equipment cost 636.65 010% of Total Cost d. Contractor's profit 210.5371 0

Total Rs. 2315.91Cost Rs. 2316.00 per

Rate Analysis Sheet

m3

m3

m3

Cost of shuttering (80.00 Rs Per m2)* 7 m2

m3

Page 8: Rate Analysis

12 mm thick smooth plastering ( 1 : 4 )

I.Material Cost Analysis :

Material QuantityRate

PerAmount

Rs. P. Rs. P.

add 30 % fill joint or even surfaces=0.3*0.12=0.036add 25 % Dry Volume = 0.25 * 0.12 = 0.03Total = 0.12+0.036+0.03 = 0.186 = 0.2

Cement 1/5*0.2*28.8=1.15+0.5 1.65 145 0 bag 239.25

Sand 4/5*0.2 0.16 150 0 24.00Total Rs. 263.25

II.Labour Cost Analysis :

Labour No.Rate

PerAmount

Rs. P. Rs. P.Male 3/4 60 0 day 45.00 0

Female 3/4 50 0 day 37.50 0

Bhisti 1/20 60 0 day 3.00 0

Mason 1 200 0 day 200.00 0Total Rs. 285.50

III.Equipment Cost Analysis :

EquipmentHire ChargeRs. P.

Total Material and Labour Cost 548.75 0Add Water Charges 1.5 % 8.23 0

Total 556.98Add Sundaries 1 % 5.569813 0

Total Cost Rs. 562.55 0Total Cost for the item :

a. Material cost 263.25 0b. Labour cost 285.50 0

Add Water Charges 1.5 % and Sundaries 1% c. Equipment cost 13.80 010% of Total Cost d. Contractor's profit 56.25511 0

Total Rs. 618.81Cost Rs. 619.00 per

Rate Analysis Sheet

I.Material Cost Analysis :

Material QuantityRate

PerAmount

Rs. P. Rs. P.30 30 0 Kg 900.00

20 30 0 Kg 600.00

wet mix volume=10 x 0.012 = 0.12 m3

m3

m2

Snowcem Painting for 100 m2

Indocem 1 st Coat

2 nd Coat

Page 9: Rate Analysis

Total Rs. 1500.00II.Labour Cost Analysis :

Labour No.Rate

PerAmount

Rs. P. Rs. P.Painter 5 100 0 day 500.00 0

Helper 5 60 0 day 300.00 0

Total Rs. 800.00III.Equipment Cost Analysis :

EquipmentHire ChargeRs. P.

Total Material and Labour Cost 2300.00 0Add Water Charges 1.5 % 34.50 0

Total 2334.50Add Sundaries 1 % 23.345 0

Total Cost Rs. 2357.85 0Total Cost for the item :

a. Material cost 1500.00 0b. Labour cost 800.00 0

Add Water Charges 1.5 % and Sundaries 1% c. Equipment cost 57.85 010% of Total Cost d. Contractor's profit 235.7845 0

Total Rs. 2593.63Cost Rs. 2593.63 per

Cost Rs. 26 per

Rate Analysis Sheet

9" thick Brickwork with ( 1 : 6 ) Cement mortar

I.Material Cost Analysis :

Material QuantityRate

PerAmount

Rs. P. Rs. P.Bricks 500 1100 0 1000 no. 550.00 0

Cement 1/7*0.32*28.8 1.32 145 0 bag 190.90 0

Sand 6/7*0.32 0.27 150 0 41.14 0

Total Rs. 782.05II.Labour Cost Analysis :

Labour No.Rate

PerAmount

Rs. P. Rs. P.( Helper ) Male 1/3 60 0 day 20 0

( Helper ) Female 1/3 50 0 day 16.67 0

100 m2

m2

m3

Page 10: Rate Analysis

Bhisti 1/10 50 0 day 5.00 0

Mason 1/3 200 0 day 66.67 0Total Rs. 108.33

III.Equipment Cost Analysis :

EquipmentHire ChargeRs. P.

Total Material and Labour Cost 890.38 0Add Water Charges 1.5 % 13.36 0

Total 903.73 0Add Sundaries 1 % 9.037347 0

Total Cost Rs. 912.77 0Total Cost for the item :

a. Material cost 782.05 0b. Labour cost 108.33 0

Add Water Charges 1.5 % and Sundaries 1% c. Equipment cost 22.39 010% of Total Cost d. Contractor's profit 91.27721 0

Total Rs. 1004.05Cost Rs. 1004.00 per

Rate Analysis Sheet

I.Material Cost Analysis :

Material QuantityRate

PerAmount

Rs. P. Rs. P.Polished kotah stone 10 225 0 2250.00 0

Cement 1/7*1.42*28.8*0.29 1.69 145 0 bag 245.67 0

Sand 6/7*0.29 0.25 150 0 37.29 0

Total Rs. 2532.95II.Labour Cost Analysis :

Labour No.Rate

PerAmount

Rs. P. Rs. P.( Helper ) Male 1/2 60 0 day 30.00 0

( Helper ) Female 1/2 50 0 day 25.00 0

Bhisti 1/5 60 0 day 12.00 0

Mason 1/2 200 0 day 100.00 0Total Rs. 167.00

III.Equipment Cost Analysis :

EquipmentHire ChargeRs. P.

m3

Polished kotah stone ( 10 m2 ) with ( 1 : 6 ) Cement mortar

m2

m3

Page 11: Rate Analysis

Total Material and Labour Cost 2699.95 0Add Water Charges 1.5 % 40.50 0

Total 2740.45 0Add Sundaries 1 % 27.40453 0

Total Cost Rs. 2767.86 0Total Cost for the item :

a. Material cost 2532.95 0b. Labour cost 167.00 0

Add Water Charges 1.5 % and Sundaries 1% c. Equipment cost 67.90 010% of Total Cost d. Contractor's profit 276.7858 0

Total Rs. 3044.64Cost Rs. 3045.00 per

Cost Rs. 304.50 per

Rate Analysis Sheet

I.Material Cost Analysis :

Material QuantityRate

PerAmount

Rs. P. Rs. P.Tiles 10 60 0 600.00 0

Cement 1/7*1.42*28.8*0.29 1.69 145 0 bag 245.67 0

Sand 6/7*0.29 0.25 150 0 37.29 0

Total Rs. 882.95II.Labour Cost Analysis :

Labour No.Rate

PerAmount

Rs. P. Rs. P.( Helper ) Male 3/4 60 0 day 45.00 0

( Helper ) Female 3/4 50 0 day 37.50 0

Bhisti 1/20 60 0 day 3.00 0

Mason 1 200 0 day 200.00 0Total Rs. 285.50

III.Equipment Cost Analysis :

EquipmentHire ChargeRs. P.

Total Material and Labour Cost 1168.45 060.00 0

Total 1228.45 0Add Water Charges 1.5 % 18.43 0

Total 1246.88 0Add Sundaries 1 % 12.46881 0

Total Cost Rs. 1259.35 0

10 m2

m2

Mosaic flooring ( 10 m2 ) with ( 1 : 6 ) Cement mortar

m2

m3

Polishing 10 m2 ( 6 Rs. Per m2 )

Page 12: Rate Analysis

Total Cost for the item :a. Material cost 882.95 0b. Labour cost 285.50 0

Add Water Charges 1.5 % and Sundaries 1% c. Equipment cost 90.90 010% of Total Cost d. Contractor's profit 125.9349 0

Total Rs. 1385.28Cost Rs. 1385.28 per

Cost Rs. 138.53 per

Rate Analysis Sheet

I.Material Cost Analysis :

Material QuantityRate

PerAmount

Rs. P. Rs. P.Glazed Tiles 37 70 0 dozen 2590.00 0

Cement 1/7*1.42*28.8*0.29 1.55 145 0 bag 224.75 0

Sand 6/7*0.29 0.10 150 0 15.00 0

Total Rs. 2829.75II.Labour Cost Analysis :

Labour No.Rate

PerAmount

Rs. P. Rs. P.( Helper ) Male 60 0 day 90.00 0

( Helper ) Female 1.5 50 0 day 75.00 0

Bhisti 3/4 60 0 day 45.00 0

Mason 1.5 200 0 day 300.00 0Total Rs. 510.00

III.Equipment Cost Analysis :

EquipmentHire ChargeRs. P.

Total Material and Labour Cost 3339.75 0Add Water Charges 1.5 % 50.10 0

Total 3389.85 0Add Sundaries 1 % 33.89846 0

Total Cost Rs. 3423.74 0Total Cost for the item :

a. Material cost 2829.75 0b. Labour cost 510.00 0

Add Water Charges 1.5 % and Sundaries 1% c. Equipment cost 83.99 010% of Total Cost d. Contractor's profit 342.3745 0

Total Rs. 3766.12Cost Rs. 3766.12 per

10 m2

m2

White Glazed Tiles ( 10 m2 ) with ( 1 : 6 ) Cement mortar

m3

1.5

10 m2

Page 13: Rate Analysis

Cost Rs. 376.61 per

Rate Analysis Sheet

I.Material Cost Analysis :

Material QuantityRate

PerAmount

Rs. P. Rs. P.Glazed Tiles 37 90 0 dozen 3330.00 0

Cement 1/5*0.2*28.8 1.75 145 0 bag 253.75 0

Sand 4/5*0.20 0.13 150 0 19.50 0

Total Rs. 3603.25II.Labour Cost Analysis :

Labour No.Rate

PerAmount

Rs. P. Rs. P.( Helper ) Male 3 60 0 day 180.00 0

( Helper ) Female 3 50 0 day 150.00 0

Bhisti 3/4 60 0 day 45.00 0

Mason 3 200 0 day 600.00 0Total Rs. 975.00

III.Equipment Cost Analysis :

EquipmentHire ChargeRs. P.

Total Material and Labour Cost 4578.25 0Add Water Charges 1.5 % 68.67 0

Total 4646.92 0Add Sundaries 1 % 46.46924 0

Total Cost Rs. 4693.39 0Total Cost for the item :

a. Material cost 3603.25 0b. Labour cost 975.00 0

Add Water Charges 1.5 % and Sundaries 1% c. Equipment cost 115.14 010% of Total Cost d. Contractor's profit 469.3393 0

Total Rs. 5162.73Cost Rs. 5162.73 per

Cost Rs. 516.27 per

Rate Analysis Sheet

Refilling of material

I.Material Cost Analysis :

m2

Coloured Glazed Tiles ( 10 m2 ) with ( 1 : 4 ) Cement mortar

m3

10 m2

m2

Page 14: Rate Analysis

Material QuantityRate

PerAmount

Rs. P. Rs. P.Nil - - - - - -

Total Rs. NilII.Labour Cost Analysis :

Labour No.Rate

PerAmount

Rs. P. Rs. P.( Helper ) Male 1/8 60 0 day 7.50 0

( Helper ) Female 1/8 50 0 day 6.25 0

Total Rs. 13.75III.Equipment Cost Analysis :

EquipmentHire ChargeRs. P.

Total Material and Labour Cost 13.75 0Add Sundaries 1 % 0.14 0

Total Cost Rs. 13.89 0Total Cost for the item :

a. Material cost Nil 0b. Labour cost 13.75 0

Add Water Charges 1.5 % and Sundaries 1% c. Equipment cost 0.14 010% of Total Cost d. Contractor's profit 1.39 0

Total Rs. 15.28Cost Rs. 15.50 per

Rate Analysis Sheet

Tor Steel

I.Material Cost Analysis :

Material QuantityRate

PerAmount

Rs. P. Rs. P.Tor Steel 1000 15.8 0 Kg 15800.0 -

Add 5% towards westage 50 15.8 0 Kg 790.00

Total Rs. 16590.00

m3

Page 15: Rate Analysis

II.Labour Cost Analysis :

Labour No.Rate

PerAmount

Rs. P. Rs. P.Labour charge 1 1500.00 0 Kg 1500.00 0

Total Rs. 1500.00III.Equipment Cost Analysis :

EquipmentHire ChargeRs. P.

Total Material and Labour Cost 18090.00 0Add Sundaries 1 % 180.90 0

Total Cost Rs. 18270.90 0Total Cost for the item :

a. Material cost 16590.00 0b. Labour cost 1500.00 0

Add Water Charges 1.5 % and Sundaries 1% c. Equipment cost 180.90 010% of Total Cost d. Contractor's profit 1827.09 0

Total Rs. 20097.99Cost Rs. 20098.00 per 1000 Kg

Cost Rs. 20.09 per Kg

Rate Analysis Sheet

4.5" thick Brickwork ( Partition wall ) with ( 1 : 6 ) Cement mortar

I.Material Cost Analysis :

Material QuantityRate

PerAmount

Rs. P. Rs. P.Bricks 50 1000 0 1000 no. 50.00 0

Cement 1/7*0.32*28.8 0.23 145 0 bag 33.35 0

Sand 6/7*0.32 0.024 150 0 3.60 0

Steel 0.88 15.5 0 Kg. 13.64Total Rs. 86.95

II.Labour Cost Analysis :

Labour No.Rate

PerAmount

Rs. P. Rs. P.( Helper ) Male 1/20 60 0 day 3 0

( Helper ) Female 1/20 50 0 day 2.50 0

Bhisti 1/20 60 0 day 3.00 0

m3

Page 16: Rate Analysis

Mason 1/20 200 0 day 10.00 0Total Rs. 18.50

III.Equipment Cost Analysis :

EquipmentHire ChargeRs. P.

Total Material and Labour Cost 105.45 0Add Water Charges 1.5 % 1.58 0

Total 107.03 0Add Sundaries 1 % 1.07 0

Total Cost Rs. 108.10 0Total Cost for the item :

a. Material cost 86.95 0b. Labour cost 18.50 0

Add Water Charges 1.5 % and Sundaries 1% c. Equipment cost 2.65 010% of Total Cost d. Contractor's profit 10.81 0

Total Rs. 118.91Cost Rs. 119.00 per

Rate Analysis Sheet

I.Material Cost Analysis :

Material QuantityRate

PerAmount

Rs. P. Rs. P.( I ) Prime Coating

( 1 ) Distemper primer 8 94.00 0 Lit. 752.00 0( 2 ) Putty 5 5.00 0 Kg. 25.00 0

( 3 ) Sand Paper 1 18.00 0 Dozen 18.00 0( II ) Top Coat

( 1 )Dry Distemper 10 50.00 0 Lit. 500.00 0( 2 ) Putty 5 5.00 0 Kg. 25.00 0

( 3 ) Sand Paper 1 18.00 0 Dozen 18.00 0Total Rs. 1338.00

II.Labour Cost Analysis :

Labour No.Rate

PerAmount

Rs. P. Rs. P.( I ) Prime Coat

Painter 2.5 100.00 0 day 250.00 0Mazdoor 2.5 60.00 0 day 150.00 0

( II ) Top CoatPainter 6 100.00 0 day 600.00 0

Mazdoor 3 60.00 0 day 180.00 0

Total Rs. 1180.00III.Equipment Cost Analysis :

EquipmentHire ChargeRs. P.

Total Material and Labour Cost 2518.00 0

m3

Distemper ( 100 m2 )

Page 17: Rate Analysis

Add Water Charges 1.5 % 37.77 0Total 2555.77 0

Add Sundaries 1 % 25.56 0Total Cost Rs. 2581.33 0

Total Cost for the item :a. Material cost 1338.00 0b. Labour cost 1180.00 0

Add Water Charges 1.5 % and Sundaries 1% c. Equipment cost 63.33 010% of Total Cost d. Contractor's profit 258.13 0

Total Rs. 2839.46Cost Rs. 2839.50 per

Cost Rs. 28.39 per

Rate Analysis Sheet

I.Material Cost Analysis :

Material QuantityRate

PerAmount

Rs. P. Rs. P.Teak Wood 0.1023 ### 0 3682.80 0

fitting 512.00 0

Total Rs. 4194.80II.Labour Cost Analysis :

Labour No.Rate

PerAmount

Rs. P. Rs. P.Frame

Carpenter 1 180.00 0 day 180.00 0helper 1 90.00 0 day 90.00 0

ShutterCarpenter 2 180.00 0 day 360.00 0

helper 2 90.00 0 day 180.00 0Fixers

Carpenter 0.5 180.00 0 day 90.00 0helper 0.5 90.00 0 day 45.00 0

Total Rs. 945.00III.Equipment Cost Analysis :

EquipmentHire ChargeRs. P.

Total Material and Labour Cost 5139.80 0Add Sundaries 1 % 51.40 0

Total Cost Rs. 5191.20 0Total Cost for the item :

a. Material cost 4194.80 0

100 m2

m2

Doors and Windows ( 2 m2 )

m3

Page 18: Rate Analysis

b. Labour cost 945.00 0Add Water Charges 1.5 % and Sundaries 1% c. Equipment cost 51.40 0

10% of Total Cost d. Contractor's profit 519.12 0Total Rs. 5710.32

Cost Rs. 5710.32 perCost Rs. 2855.16 per

Rate Analysis Sheet

mild Steel

I.Material Cost Analysis :

Material QuantityRate

PerAmount

Rs. P. Rs. P.mild Steel 1050 16.00 0 Kg 16800.0 -

Add 5% towards westage 20 16.00 0 Kg 320.00

Total Rs. 17120.00II.Labour Cost Analysis :

Labour No.Rate

PerAmount

Rs. P. Rs. P.Labour charge 1 1500.00 0 Tonne 1500.00 0

Total Rs. 1500.00III.Equipment Cost Analysis :

EquipmentHire ChargeRs. P.

Total Material and Labour Cost 18620.00 0Add Water Charges 1.5 % 279.30 0

Total 18899.30 0Add Sundaries 1 % 188.99 0

Total Cost Rs. 19088.29 0Total Cost for the item :

a. Material cost 17120.00 0b. Labour cost 1500.00 0

Add Water Charges 1.5 % and Sundaries 1% c. Equipment cost 468.29 010% of Total Cost d. Contractor's profit 1908.83 0

Total Rs. 20997.12Cost Rs. 20997.12 per 1050 Kg

Cost Rs. 20.00 per Kg

2 m2

m2

Page 19: Rate Analysis

19.99726


Recommended