+ All Categories
Home > Documents > Raw Water Master Plan Update - San Jacinto River Authority · Group for incorporation into the...

Raw Water Master Plan Update - San Jacinto River Authority · Group for incorporation into the...

Date post: 22-Jul-2020
Category:
Upload: others
View: 0 times
Download: 0 times
Share this document with a friend
12
1 Raw Water Master Plan Update The last edition of the RWE Newsletter discussed the ongoing development of a Raw Water Supply Master Plan. The goals of the Master Plan are: 1) to estimate expected shortages and select appropriate strategies for providing raw water supplies required by Montgomery County and Highlands Raw Water Systems; and 2) to develop an overall plan for timely and economically delivering future raw water supplies to the service area. SJRA has continued development of the Master Plan through August 2017, and is now evaluating Selected Strategies shown here. Technical memos were developed by the SJRA’s Project Consultant for each of the selected strategies which provide details for implementing the strategies, identify potential issues such as environmental constraints, and present estimated costs. These memos are currently in the process of being finalized. In order to engage interested stakeholders in this planning process, meetings involving representatives of local government agencies, utilities, economic development, and other groups, have been held to present progress results and these meetings will continue in the future. The next meeting is scheduled for October 10, 2017, at which SJRA’s project consultant will present the results of the technical memos they have created for each of the selected raw water supply strategies. The next and final step in the Master Plan process is development of a comprehensive 50-year plan for implementation of the most appropriate strategies. The final Master Plan document is scheduled to be completed in early 2018. In order to qualify for various low interest State funding options, projects must be included in the TWDB’s State Water Plan. Therefore, the final Master Plan will be submitted to the Texas Region H Planning Group for incorporation into the Region H Water Plan. Montgomery County Highlands Water Supply Transfer (via Pumping & Pipelines) from Lake Livingston to Lake Conroe Catahoula Aquifer Well Development Capture of Treated Wastewater that has returned to Natural Channels (Regional Return Flows) Enhancing Water Conservation Efforts SELECTED STRATEGIES Regional Return Flows Water Supply Transfer (via Bed and Banks) from Lake Livingston to Highlands Service Area Above: Strategies Selected for Detailed Evaluation
Transcript
Page 1: Raw Water Master Plan Update - San Jacinto River Authority · Group for incorporation into the Region H Water Plan. ... Turbulence (surfactant), Aqua-King (surfactant), Droplex (drift

1

Raw Water Master Plan Update

The last edition of the RWE Newsletter discussed

the ongoing development of a Raw Water Supply

Master Plan. The goals of the Master Plan are: 1)

to estimate expected shortages and select

appropriate strategies for providing raw water

supplies required by Montgomery County and

Highlands Raw Water Systems; and 2) to develop

an overall plan for timely and economically

delivering future raw water supplies to the service

area.

SJRA has continued development of the Master

Plan through August 2017, and is now evaluating

Selected Strategies shown here. Technical memos

were developed by the SJRA’s Project Consultant

for each of the selected strategies which provide

details for implementing the strategies, identify

potential issues such as environmental constraints,

and present estimated costs. These memos are

currently in the process of being finalized.

In order to engage interested stakeholders in this

planning process, meetings involving

representatives of local government agencies,

utilities, economic development, and other

groups, have been held to present progress results

and these meetings will continue in the future.

The next meeting is scheduled for October 10,

2017, at which SJRA’s project consultant will

present the results of the technical memos they

have created for each of the selected raw water

supply strategies.

The next and final step in the Master Plan process

is development of a comprehensive 50-year plan

for implementation of the most appropriate

strategies. The final Master Plan document is

scheduled to be completed in early 2018. In order

to qualify for various low interest State funding

options, projects must be included in the TWDB’s

State Water Plan. Therefore, the final Master Plan

will be submitted to the Texas Region H Planning

Group for incorporation into the Region H Water

Plan.

Montgomery County Highlands

Water Supply Transfer (via Pumping & Pipelines)

from Lake Livingston to Lake Conroe

Catahoula Aquifer Well Development

Capture of Treated Wastewater that has returned

to Natural Channels (Regional Return Flows)

Enhancing Water Conservation Efforts

SELECTED STRATEGIES

Regional Return Flows

Water Supply Transfer (via Bed

and Banks) from Lake Livingston

to Highlands Service Area

Above: Strategies Selected for Detailed Evaluation

Page 2: Raw Water Master Plan Update - San Jacinto River Authority · Group for incorporation into the Region H Water Plan. ... Turbulence (surfactant), Aqua-King (surfactant), Droplex (drift

2

Highlands SCADA System Implementation: Moving into the 21st Century

Historically, all pumps and control gates for the

Highlands Division canal system have been

monitored and controlled manually. As customer

demands for water have increased in recent years,

monitoring and control of the system have

become more important to ensure that the

necessary hydraulic flow and

capacity requirements are

continually being met. There

are a variety of concerns with a

manually operated system. For

example, there are currently no

alarms or notifications to alert

staff of low levels in the canal or

that water in the canal may be in

danger of overtopping the

levee. To prevent these type of

operational irregularities from

occurring, the Technical Services

Department and the SCADA/I&C

Department are working with the

Highlands Division to develop a

SCADA system to provide these

improved functions.

Project Implementation Plan

This improvement project is scheduled

to be completed in four phases

spanning several years. Phase 0

involves four sites that will include the placement

of instrumentation to allow for flow and level data

to be collected and sent back to the Emergency

Operations Center (EOC). In Phase 0, this data

will be transmitted via cellular communications.

Phase 1 will include additional improvements to

the original four sites, and will add an additional

three sites. The particular equipment installed at

each location will address the specific operational

needs at that site. Also included in Phase 1, will

be a conversion from cellular communication to a

more secure radio communications protocol.

With the recent attacks from malware and

ransomware around the world, SJRA staff

recognizes that network security is of upmost

importance.

Currently, staff are working on both Phase 0 and

Phase 1 project. The ongoing work involves:

Acquisition of the necessary

property easements,

Erection of the shelters at the

site,

The construction of the

control panels,

The procurement and

installation of instruments,

The development of a secure

network, and

Programming of PLC’s and

the SCADA system software.

Construction plans for the

conduit placement, concrete pads, and

shelters was completed in August and

the Highlands Division staff will begin

construction of the concrete pads,

placement of conduit, and the erection

of the shelters in September.

SCADA staff is in the process of

completing surveys and acquiring the

metes and bounds for land that will be

required to move forward with Phase 1 of the

project. Although SJRA has easements for every

location where a siphon is located, not all areas

include enough space for placement of the needed

instruments, Programmable Logic Controller

(PLC) panel placement, and shelter. Additional

easements are also needed for any major

communications equipment built on the siphons,

including any larger antenna towers located

designed to withstand 129 MPH winds.

Flow Measurement

A new type of flow meter is going to be used in

the Highlands Division that has not been used in

Page 3: Raw Water Master Plan Update - San Jacinto River Authority · Group for incorporation into the Region H Water Plan. ... Turbulence (surfactant), Aqua-King (surfactant), Droplex (drift

3

any other location in the SJRA. In most operating

plant environments, non-pressurized flows are

measured within a channel by utilizing a flume or

V-notch weir. However, this requires introducing

a head loss that is not desirable within the canal

system of the Highlands Division. The

instrument that is currently earmarked for use in

the Highlands is called an “Acoustic Doppler”

flow meter and is designed specifically for use in

large channels or canals.

This type of meter utilizes sound to determine the

speed of the water within the canal. A separate

tool (which can be moved and used at many

locations) is used to measure the cross-sectional

area of the canal. Those two pieces of information

together will provide a calculated rate of flow in

the canal.

Communications Network

For the communications system, necessary

cellular devices, servers, and network appliances

(routers and firewalls) will also be purchased for

the System.

SCADA software that is to be used in the

Highlands Division will be the Wonderware,

same software that is being used in the other three

SJRA operating divisions. The SCADA/I&C

Department is working closely with the

Highlands Division to ensure that the end product

is one that will meet the division’s needs and

expectations. Staff will ensure that the same

standards developed for other divisions will be

used in the Highlands project to allow for easy

development of databases and the user interface

screens.

Above: Flow Meter to be used in the Canal

Above: Servers to be transferred and reutilized

Above: Cellular Communication Device

Page 4: Raw Water Master Plan Update - San Jacinto River Authority · Group for incorporation into the Region H Water Plan. ... Turbulence (surfactant), Aqua-King (surfactant), Droplex (drift

4

Invasive Vegetation Control in the Highlands

The Raw Water System in the Highlands includes

the Highlands Reservoir and approximately 27

miles of canals, all of which requires attentive

effort to minimize the growth of invasive aquatic

and shoreline vegetation along the System. The

Highlands staff are trained and licensed by the

State of Texas Department of Agriculture (TDA)

to properly use appropriate herbicides and other

specialized tools in their maintenance activities.

The Highlands staff diligently monitor, budget for

treatment, and ensure that maintenance to

eliminate or control the various species is

adequate to ensure the uninterrupted flow of

water supplies for this System. Through monthly

canal inspections, staff records all locations of

invasive species and areas requiring treatment.

Work orders are then issued to further address the

areas of concern. In order to prevent clogging at

the intakes of customers from the dead vegetation

and the change in water quality due to the

breakdown of the dead vegetation, staff must

ensure timely and open communication occurs on

scheduled application activities with industrial,

municipal, and irrigation customers.

Application Process

In order to obtain an approved herbicide license,

staff must pass several tests, including those on:

General Knowledge, Rules and Regulations,

Aquatic Herbicides, and Right-of-Ways. After all

tests are initially passed, staff must complete five

hours of continuing education yearly to maintain

their license. Additionally, the Highlands must

keep on file a specific and updated inventory of

all herbicides purchased and stored for future

application, a daily log of products sprayed, and

the specific location that spraying was required.

The responsibility to manage the availability of

the herbicide products and safe application lies

with the licensed staff members.

In order to properly apply aquatic herbicides, staff

must have access to the necessary application

equipment and proper personal protective

equipment. Depending on the particular method

of application used, staff must follow the

directions on the label for personal protection,

including wearing: long sleeve shirts, long pants,

hats, safety glasses, rubber aprons, and protective

rubber gloves. Application equipment includes:

an all-terrain vehicle equipped with a spray rig

and a hand spray nozzle, a broadcaster for

granulated formulations, and a boom sprayer that

will reach the side or rear to further distribute the

product.

Above: Product Storage area for the ongoing treatment of

invasive plant species along the Raw Water System

Page 5: Raw Water Master Plan Update - San Jacinto River Authority · Group for incorporation into the Region H Water Plan. ... Turbulence (surfactant), Aqua-King (surfactant), Droplex (drift

5

Other equipment that may also be used includes

back-pack sprayers, hand-held pump sprayers,

and a trailer mounted spray rig for handgun

applications. Proper personal protective

equipment and application equipment allows for

a safe and more effective application in the

targeted areas.

Invasive Plants

There are several invasive plant species that are

located and treated along the Raw Water System.

Treatment for each species may vary and require

herbicides with different active ingredients or

methods for removal depending on the season

and location of the infestation. Some of the

species found along the System include:

Alligatorweed, Primrose, Hyacinth, Smartweed,

Hydrilla, American Pondweed, Coontail Moss,

American Lotus, Tallow Trees, Johnson Grass,

Bloodweed, Giant Reed (cane), Common

Duckweed, Cattails, Pennywort (Highlands

Reservoir area specifically), and other

miscellaneous grasses along the canal banks.

Commonly used products include: Rodeo,

Polaris, Streamline, Clearcast, Garlon 3A,

Turbulence (surfactant), Aqua-King (surfactant),

Droplex (drift control), Mystic Dye, Aqua Master,

Garlon 4 Ultra, Clipper, Fastbreak, Diluent Blue,

and Spike. Additives are incorporated for drift

control, anti-foaming, and dyes for visibility to

ensure the targeted area is achieved and over-

spray is minimized. Various surfactants are used

to enhance the product bonding to the surface of

the invasive vegetation. Each mixture is

comprised of different major ingredients. When

possible, blending of ingredients is required to

achieve the optimum desired results against some

vegetation. Products used for treatment along the

Raw Water System in the Highlands are

environmentally friendly and have been

designated in Texas for aquatic use. Careful

consideration for each application is given for the

appropriate method and substances utilized for

removal.

Past experience with invasive vegetation on the

Raw Water System has shown that other methods

beyond spray application must also be used to

achieve successful control, including: 1) the

Above: Licensed Herbicide Operator spraying a

fence line using a hand-sprayer from an all-terrain

vehicle

Above: Licensed Herbicide Operator spraying

the edge of the canal from the levee with a hand

sprayer

Page 6: Raw Water Master Plan Update - San Jacinto River Authority · Group for incorporation into the Region H Water Plan. ... Turbulence (surfactant), Aqua-King (surfactant), Droplex (drift

6

introduction of biologically-modified grass carp,

and 2) the use of a drip-application system to

inject aquatic herbicides during periods when

cooler water temperatures exist. The drip-

injection method has been used for the north area

of the Highlands Reservoir, along with occasional

boom and nozzle spraying and the broadcasting

of granulated formulations. With assistance of the

Texas Parks and Wildlife Department, grass carp

were recently introduced to help in the control of

Hydrilla, American Pondweed, and Coontail

throughout the System and these plants are now

under control. Staff carefully considers the

methods available and applies the most feasible

and cost-effective approach for targeting the areas

identified.

Cost of Control

Over the last decade, the average annual cost for

herbicides used along the Raw Water System in

the Highlands has been approximately $30,000.

For FY2017, $50,000 was budgeted for herbicides

and supplies for the management of all the

invasive species along the Raw Water System.

Training and improved resources have effectively

reduced the costs of herbicide for the System.

Through the procurement of specialized

equipment such as spray booms, the quantity of

herbicide utilized has been reduced compared to

using hand-held spray nozzles. Collaboration

with herbicide product representatives has

provided further guidance to staff to increase

their knowledge on more effective approaches

and the best use of appropriate herbicide products

at the various locations. Products procured and

used today are also of higher quality and have a

greater impact to the targeted areas.

After treatment occurs, staff must still monitor

and manage the impact of the applications. This

sometimes includes the removal of dead

vegetation that breaks loose and can potentially

be a risk for blockages at the headwalls of the

siphon structures. Depending on the size of the

infestation, decomposition of the dead vegetation

can have an impact on water quality. If localized

blooms are not spotted and treated quickly, the

amount of vegetation can increase geometrically

and create significant problems for our customers.

Through careful planning and diligent use of all

the control tools and resources, the Highlands

staff efforts will continue to provide safe and

reliable raw water supplies to all customers along

the System.

Above: Approximately 5,000 grass carp were released

into the System to help reduce the invasive vegetation

Page 7: Raw Water Master Plan Update - San Jacinto River Authority · Group for incorporation into the Region H Water Plan. ... Turbulence (surfactant), Aqua-King (surfactant), Droplex (drift

7

Monitoring System Provides Dam Operators with Extra “ALERT’s”

In August, 2016, the SJRA, along with its partners,

the City of Conroe and Montgomery County,

received a grant of $460,000 for flood protection

planning and for improvements to the SJRA’s

flood early warning system along the West Fork

of the San Jacinto River in Montgomery County.

Texas. This is a 50% matching-funds grant with

50% to be provided by SJRA and its partners in

the project.

One important element of the project includes

enhancements to SJRA’s existing

hydrometerological monitoring network that

covers the Lake Conroe watershed and

immediate surrounding area.

The first step, completed in February, 2017, was

an engineering analysis of the network resulting

in recommendations for improvements which are

now underway and are further explained below.

SJRA has operated a radio-telemetry monitoring

network since the 1980’s which relied on

technology trademarked as “Automated Local

Evaluation in Real Time (ALERT)” protocol. This

system transmitted rainfall and related data from

sites located throughout the Lake Conroe

watershed to a control station at the Lake Conroe

dam for use by the SJRA operators to pass storm

flows safely through the spillway gates. Data

from this system is simultaneously repeated in

real time to a regional network of weather

monitoring partners that is managed by the

Harris County Flood Control District. This

ALERT system has performed its intended

function very well for over three decades but was

limited in its ability to expand its coverage of the

County and remain reliable. By converting to the

next generation of new and improved

transmission protocol, called ALERT2, the SJRA

has now gained significant advantages, including:

Improved the reliability of data capture

during high intensity events when the

frequency of transmissions is greatest

and the need for accurate data is most

important.

Greater room and abilities to

accommodate system expansion.

Faster transmission speed

Larger transmission packet size

Error detection and correction

The graphic below illustrates the proposed

architecture of the improved network.

Page 8: Raw Water Master Plan Update - San Jacinto River Authority · Group for incorporation into the Region H Water Plan. ... Turbulence (surfactant), Aqua-King (surfactant), Droplex (drift

8

SJRA’s existing repeater tower has been

damaged over the years from freezing water

contained within the tubular tower structure.

Thus the tower, which was originally 100 feet

tall, had to be lowered several times to remove

damaged sections. By relocating the new

antennas to a 100-foot tall water storage tank

which is a part of the SJRA’s Groundwater

Reduction Program, the antennas’ elevation is

now some 100 feet higher than the previous

tower. This location also has fiber optic cable

running to the Lake Conroe campus making it

an ideal place to mount the receiving antennas.

With this new system in place, data

transmission can be sent via internet protocol

(IP) which is more reliable than radio. Backup

redundancy via radio signal will remain in

place in case of loss of internet service.

SJRA’s monitoring gauge network currently

consists of 11 field sites spread throughout the

Lake Conroe surrounding area. As part of this

enhancement project, SJRA will add 5

additional sites to the network and move two

existing sites to more strategic locations. These

enhancements will provide water surface

elevation (stage) data at 5 critical tributaries that

flow into Lake Conroe. This data will provide

Lake Conroe reservoir operators with

additional information as to inflows into Lake

Conroe. In addition, data from these stage

gauges can be used to calibrate the models that

will be run as a part of the Flood Protection

Planning Study. The figure below depicts the

geographical layout of the enhanced

monitoring network.

SJRA staff will soon install all of the necessary

equipment for the new stations and upgrade the

existing stations from the legacy ALERT protocol

to the improved ALERT2. If all work goes

according to plan, SJRA will be fully converted to

ALERT2 by the end of the year.

Above: GIS mapping of existing weather stations, proposed weather stations, existing

repeater and new repeater location

Page 9: Raw Water Master Plan Update - San Jacinto River Authority · Group for incorporation into the Region H Water Plan. ... Turbulence (surfactant), Aqua-King (surfactant), Droplex (drift

9

Raw Water Enterprise Next Quarter Calendar

September 2017

20th Legislative Staff Briefing Austin

24th Leadership SJRA – Into, Team Building and SJRA History

25th Houston Galveston Area Council – BIG Coordination and Policy Work Group Meeting

28th San Jacinto River Authority - Board of Directors Meeting

28th Woodlands Township – Drainage Task Force Meeting

28th LSGCD - Water Efficiency Network Meeting

October 2017

4th North Houston Association – Environmental Committee Meeting

5th Texas Parks and Wildlife – 2017 Zebra Mussel Prevention and Management Partners

Meeting

10th San Jacinto River Authority - Raw Water Supply Master Plan Stakeholder Meeting

18th – 20th Texas Water Conservation Association – Fall Conference San Antonio

24th Leadership SJRA – Lake Conroe Division Meeting

25th Houston Galveston Area Council – Regional Flood Management Council

26th San Jacinto River Authority - Board of Directors Meeting

26th LSGCD - Water Efficiency Network Meeting

31st Houston Galveston Area Council – Bacteria Implementation Group Fall Meeting

November 2017

1st Region H Meeting

8th – 9th National Hydrologic Warning Council – 2017 9th Annual National Conference San Antonio

14th Leadership SJRA – Technical Services, SCADA and IT

17th Sam Houston State University Tour at the Lake Conroe Dam

23rd LSGCD - Water Efficiency Network Meeting

27th – 29th Texas Aquatic Plant Management Society – Annual Conference San Antonio

Employee Service Recognition

No Service Awards this Quarter

Page 10: Raw Water Master Plan Update - San Jacinto River Authority · Group for incorporation into the Region H Water Plan. ... Turbulence (surfactant), Aqua-King (surfactant), Droplex (drift

10

Raw Water Usage Data

Lake Level Data

**Lake Level Data: USGS Gauge at Dam, Rainfall & Temperature: SJRA Gauge at Dam, Evaporation & Discharge: Internal Calculation

80

81

82

83

84

85

86

87

0

5

10

15

20

25

30

Jun-17 Jul-17 Aug-17

Deg

rees

Far

enh

eit

Rai

nfa

ll/E

vap

ora

tio

n i

n I

nch

es

Lake Conroe - Rainfall, Evaporation, and Average Temperature

Total Rainfall Total Evaporation Average Temperature

0

50,000

100,000

150,000

200,000

250,000

300,000

199

200

201

202

Acr

e-fe

et

ft/M

SL

Lake Conroe - Average Lake Level and Discharge Totals

Lake Discharge Average Lake Level

Page 11: Raw Water Master Plan Update - San Jacinto River Authority · Group for incorporation into the Region H Water Plan. ... Turbulence (surfactant), Aqua-King (surfactant), Droplex (drift

11

Lake Conroe and Highlands Division Safety Tailgates

Highland Division Tailgates

Escaping a submerged vehicle

Hurricane safety

Weed eater safety

Train crossing safety

Driving safety

Hand safety

Tick safety

HR/Safety Coordinated Training Activities

Snake Safety

Lake Conroe Division Tailgates

Hurricane safety

Above: The Lake Conroe Division views a fictional “Hurricane Charlie” webinar, hosted by the National Weather Service on

June 6, 2017

Page 12: Raw Water Master Plan Update - San Jacinto River Authority · Group for incorporation into the Region H Water Plan. ... Turbulence (surfactant), Aqua-King (surfactant), Droplex (drift

12

Fourth Quarter Financials for the Raw Water Enterprise, Highlands

Division and Lake Conroe Division have not been provided for this

report due to end of year reconciliation


Recommended