Date post: | 11-Apr-2017 |
Category: |
Documents |
Upload: | nikhil-kumar |
View: | 134 times |
Download: | 0 times |
6/21/2016
Tom Burnett & Nikhil Kumar
Intertek
Risk Based Inspection for Power Plants
AWARE UGM 2016
222
Evolving Business Models
Centralized Distributed
CapEx OpExStatic/Dumb
Connected/Smart
3
Intertek Smart Platform
AWARE + CostCom
Condition Assessment
Failure Analysis/
BTFR
High Energy Piping
Flow Accelerated Corrosion
Power Plant Cycling
Fitness for Service
EconometricsLife Extension
(Risk Adjusted)
4
Why do RBI
• Improve plant and worker safety – Avoidance of catastrophic failure
• Increased availability and reliability of equipment
• Better understanding of equipment and processes
• Focus resources in correct areas
• Save money
• Improved turnaround planning
• Specific inspection and maintenance activities
• Avoid failures and downtime
• Detailed equipment inspection plans
• Follow industry best practices
• Make informed management decisions
5
Hazard versus Risk
Hazard Risk
6
What is RiskC
ost
Reliability
Reliability Analysis
Total Cost
Outage Cost
Capital & Maintenance
Cost
Risk = (Likelihood of Failure) x (Consequence of Failure)
7
What about API compliance?
API RP 580 was intended to provide guidance and provide basic elements for
developing and implementing a RBI program. It is an introduction to concepts and
principles of RBI, with the intent of producing a documented methodology.
AWARE is fully compliant with these guidelines.
API 581 has been updated over time and now includes step by step analysis
procedures similar to ASME FFS-1 as well as ASME Section VIII
8
Why was RBI Developed
• Most pressure equipment contain flaws
• Most flaws are innocuous - Don’t cause problems
• Few flaws cause catastrophic failure
• Must find (inspect) those critical flaws in high risk service - Cost effectively
• Typically 80% of the risk is associated with < 20% of the pressure
equipment
Loss of containment events resulting in major
insurance losses in petrochemical process plants.
Only about half of the causes of loss of containment
can be influenced by inspection activities (41% of
mechanical failures plus some portion of the “unknown”
failures). Other mitigation actions are required.
9
• As with other industries, the goal for
the electric generation industry as a
whole is to predict and prevent
failures before they occur.
• The implementations rely on both
Qualitative Risk Analysis, as well as
a Quantitative Risk Analysis, which
includes in-depth reliability and
financial analysis.
• Level I – Qualitative risk, simple
• Level II – Qualitative risk analysis,
supplemented with quantitative
methods
• Level III – Quantitative risk analysis,
in depth analysis
RBI – Qualitative or Quantitative?
Rank
Process
Units
Review and
Adjust COF
Rating
Identify
Consequence
Modifiers
Calculate
Preliminary
Consequence Index
Gather Data for
Consequence
Estimate
Review of
Process and
Operational Data
Consequence
of Failure
(COF)
Risk Rank = COF
x LOF
Development of Equipment
Worksheet
Equipment
Documentation
Review
Review and
Adjust LOF
Rating
Calculate Initial
Damage Rank
Identify
Failure
Modes
Identify Potential
Damage
Mechanisms
Identify Industry Specific
Unit Exp.(Interviews -
Process, Maint.
Engrs./Insp.)
Likelihood of
Failure (LOF)
Risk
Directed
Inspection
Plan -
Scope &
10
What does inspection planning involve:
• Determining risk in terms of
likelihood of failure and
consequence of failure
• Inspection scope, schedule, and
cost planning and risk reduction
estimations
• Presentation of the results in
terms of a risk matrix
• Evaluation of the costs and risk
reduction of countermeasures
Inspection Planning
11
Intertek Approach
AWARE Decision Analysis
No detection + No Repair
Equipment Failure
Equipment Risk
Assessment
No detection + No Repair
Detection + No Repair
Detection + Repair
Detection + No Repair
Equipment Failure
Equipment Risk
Assessment
No detection + No Repair
Detection + No Repair
Detection + Repair
No detection + No Repair
Equipment Failure
Equipment Risk
AssessmentDetection +
Repair
Risk Mitigation
Plan
Inspection Plan
Risk Matrix
Data Analysis
[Determine POF/COF]
Data Input in AWARE
Data Collection
12
Factors:
• Incorrect Design
• Incorrect Material (size, schedule,
metallurgy)
• Construction Defects (lay-up,
welds)
• In Service Induced Defects
(corrosion, erosion, fatigue, creep,
creep/fatigue, etc.)
• Cycling
• Operational and Maintenance
Caused Defects
• Define Damage Potential
• Identify Potential Failure Mechanisms
• Determine Potential Failure Modes for Damage Mechanisms
• Assign Damage Rank Based on:
• Possibility of Occurrence
• Failure Mode if Undetected
• Consider Mitigating/Aggravating Factors and Assign an Overall Likelihood of Failure Rank to Component Considering:
• Corrosion, erosion, fatigue, creep, creep/fatigue, etc.
• Operating Considerations
• Thermal Cycles, Stress Cycles, Transients and Off Normal Operations
• Inspection Considerations - Scope, Frequency, and Technique
• Quality of Documentation and Plant Experience
Likelihood of Failure
13
− Reliability Models for
certain key equipment
(High Energy Piping or
Pressure Vessels),
where damage
mechanisms and
uncertainties are well
understood and
statistical distributions
are available. In this
scenario, the model uses
the following equation to
determine POF:
• 𝑃𝑓 𝑡 = 𝑔𝑓𝑓. 𝐷𝑓 𝑡 . 𝐹𝑀,
where 𝑃𝑓 𝑡 is the function
of a generic failure
frequency 𝑔𝑓𝑓, damage
factor 𝐷𝑓(𝑡), and a
management system
factor 𝐹𝑀
− Statistical Models. These models are based on generic data collected either using frequencies available in the AWARE database or other models developed by Intertek Engineering. We will also rely on EPRI data to develop and determine the POF.
• Where appropriate, two parameter Weibull models will be used to estimate failure frequency, 𝑃𝑓 𝑡 =
1 − exp[−𝑡
𝐶𝐿′
𝐵] ; where:
CL’ is the updated characteristic life and B is the shape factor
• For some key boiler pressure parts Intertek’s probabilistic failure rate damage models such as TUBETECH or SAFESEAM, or SAFEGIRTH will be used to estimate the likelihood (i.e., probability, frequency) of failure
− Expert Judgment. will be
relied upon when the
information on likely
damage mechanism or
failure frequency is
found inadequate.
Likelihood of Failure
14
Possible Consequence:
(a) formation of a vapor cloud that could
ignite, causing injury and equipment
damage
(b) release of a toxic chemical that could
cause health problems
(c) a spill that could cause environmental
damage
(d) a rapid release of superheated steam
that could cause damage and injury
(e) a forced unit shutdown that could
have an adverse economic impact
(f) minimal safety, health, environmental,
and/or economic impact
• Calculate Consequence Value
• Worst Case Pressure & Temperature
• Volume of Contained Fluid/Gas
• Density Factor
• NFPA Factors (Flammability, Toxicity, Reactivity, Other)
• Assign Consequence Rank to Component Considering Mitigating/Aggravating Factors
• Location Relative to Other Equipment
• Location Relative to Concentrations of Personnel
• Environmental Factors (Reportable Release Quantities)
Consequence of Failure
15
• Calculate Preliminary Consequence Value (PCV)
• Product of Worst Case: Temperature, Volume, Pressure and Density factors.
• Sum of MSDS Factors: Flammability, Toxicity, Reactivity, Other (steam).
• Final Product (PCV)
• Modify PCV by considering Mitigating, Aggravating Factors
• Location Relative to Other Equipment
• Location Relative to Concentrations of Personnel
• Environmental Factors (Reportable Release Quantities)
• Fire detection and suppression devices
Estimating Consequence
Four Categories Based Consistent With Industry Approach
Consequence of Component Failure
Considerable 1
Serious 2
Some 3
Minor or No Impact on Personnel 4
Rank Consequence Based on
Potential For Harm to Site
Personnel & Environment
16
RBI pitfalls
RBI will not compensate for
• inaccurate or missing information
• inadequate design or faulty equipment
• improper installation and/or operation
• operating outside the acceptable design envelope
• not effectively implementing the inspection plan
• lack of qualified personnel or team work
• lack of sound engineering or operational judgment
• failure to promptly take corrective action or implement appropriate mitigation
strategies
17
Risk Management
Reducing likelihood of failure is not only restricted to inspections:
• Inspection and Maintenance
• Understanding damage
• Correct NDE techniques
• MOC/Record Keeping/Report
• Repair, Replace, Control
• Operational Controls
• Online Monitoring
• Materials
RBI focuses on “inspectable risk”. RBI is not intended to replace
other practices that have proven satisfactory or substitute for the
judgment of a responsible, qualified inspector or engineer.
18
Life Optimization Program
• What is Intertek’s AIM Life
Optimization Program:
• API 580 Compliant
• System Risk Analysis Tool
• Justification for future maintenance
costs and maintenance planning aid
• A Living document
• Flexible and adaptable to changing
management and operations
• Easy to use and inexpensive, with a
quick ROI.
A typical RBI implementation results in an inspection plan as the primary output. Instead, Intertek’s program
goes beyond the basic requirements of RBI and its objectives are:
• Organizing and maintaining key inspection and overhaul reports from past years
• Developing inspection and real-time data acquisition plans needed to assess equipment health
• Developing a database structure to organize the vast data in a way that is easily retrieved and
disseminated