of 16
7/29/2019 Reatining WAll With HORZONTAL Bach Fill
1/16
RCC design B.C.Punmia
18.2 TYPE OF RETAINING WALLS
1 Gravity walls
2 Cantilever retaining walls a. T- shaped b. L- shaped
3 Counterfort retainig walls.
4 Buttresssed walls.
The cantilever retaining wall resist the horizontal earth pressure as well as other vertical pressure by w
A gravity retaining wall shown in fig 1 is the one in which the earth pressure exrted by the
back fill is resisted by dead weight of wall, which is either made of masonry or of mass concrete . The
stress devlop in the wall is very low ,These walls are no proportioned that no tension is devloped any
where, and the resultant of forces remain withen the middle third of the base.
A retaining wall or retaining structure is used for maintaining the ground surfgaces at defrent
elevations on either side of it. Whenever embankments are involed in construction ,retaining wall are
usually necessary. In the construction of buildins having basements, retaining walls are mandatory.
Similsrly in bridge work, the wing walls and abutments etc. are designed as retaining walls , to resist
earth pressure along with superimposed loads. The material retained or supported by a retaining wall
is called backfill lying above the horizontal plane at the elevation of the top of a wall is called the
surcharge, and its inclination to horizontal is called the surcharge angle b
In the design of retaining walls or other retaining structures, it is necessary to compute the
lateral earth pressure exerted bythe retaining mass of soil. The equation of finding out the lateral earth
pressure against retaining wall is one of the oldest in Civil Engineering field. The plastic state of
strees, when the failure is imminent, was invetigated by Rankine in1860. A Lot of theoretical
experiment work has been done in this field and many theory and hypothesis heve benn proposed.
RETAINING WALL
Retaining walls may be classified according to their mode of resisting the earth pressure,and
according to their shape. Following are some of commen types of retaining walls (Fig)
7/29/2019 Reatining WAll With HORZONTAL Bach Fill
2/16
y of beending of varios components acting as cantilever s.A coomon form of cantilever retaining waal
7/29/2019 Reatining WAll With HORZONTAL Bach Fill
3/16
12 mm f@
400 mm c/c
1 Hieght of cantilever wall from ground level = 3.00 m 8 mm f @ 12 mm f@
2 Unit weight of Earth = 18 KN/m3 300 mm c/c 200 mm c/c
3 Angle of repose = 30 Degree4 Safe Bearing capacity of soil = 100 KN/m
3 8 mm f @ 12 mm f@
5 Coffiecent of friction = 0.5 300 mm c/c 100 mm c/c
6 Concrete M- 20
m = 13.33 wt. of concrete 25000 N/m3 8 mm f @ 10 mm f@7 Steel fe = 415 N/mm st = 230 N/mm 160 mm c/c 120 mm c/c
cbc = 7 N/mm2
8 Nominal cover = 30 mm 10 mm f@
9 Foundation depth = 1.00 m 310 130 mm c/c
10 Stem thickness At footing 300 mm At top 200 mmToe width 900 mm Heel width 1200 mm 900
11 Footing width 2400 mm Key 300 x 300 mm 8 mm f @
180 mm c/c 300
12 Reinforcement Summary 8 mm F @ 160 `
STEM :-Main mm f@
2.58 12 mm F@ 100 mm c/c mm c/c1.94 12 mm F@ 200 mm c/cTop 12 mm F@ 400 mm c/c
mm f@Distribution 8 mm F@ 160 mm c/c 2.58 mm c/cTamprecture 8 mm F@ 300 mm c/c
TOE :-Main 10 mm F@ 130 mm c/c mm f@Distribution 8 mm F@ 180 mm c/c mm c/c
HEEL:-Main 10 mm F@ 120 mm c/cDistribution 8 mm F@ 180 mm c/c Out side Earth side
DESIGN SUMMARY
100% Reinforcement upto m
50% Reinforcement upto m
25% Reinforcement upto m
DESIGN OF T SHAPED CANTILEVER RETAINING WALL
Horizontal back fill
1.94
200
1000
200
1200
200
940
7/29/2019 Reatining WAll With HORZONTAL Bach Fill
4/16
Hieght of cantilever wall from ground level = 3.00 m
Unit weight of Earth g = 18 kN/m = N/m
Angle of repose = 30 Degree
Safe Bearing capacity of soil q0 = 100 kN/m3
Coffiecent of friction m = 0.5 = 25 N/mmConcrete = M 20
Steel fe = 415
Nominal cover = 30 mm
Foundation depth = 1.00 m
1 Design Constants:-For HYSD Bars = 20
st = = 230 N/mm2
= #### N/mm2
cbc = = 7 N/mm3
m = 13.33x
13.33 x 7 + 230
j=1-k/3 = 1 - 0.289 / 3 = 0.904
R=1/2xc x j x k = 0.5 x 7 x 0.904 x 0.289 = 0.913
2 Diamension of base:-
height of wall above base, H = 3.00 + 1.00 = meter
The ratio of length of slabe (DE) to base width b is given by eq.
q0
2.2 y H 2.2 x 18 x 4.00
Keep = 0.37 Eq (1)
The width of base is given by Eq. sin = 0.5
1 - 0.5
1 + 0.5
( 1 - 0.37 )x( 1 + 1.11 )
x 4.00 x 0.33
( 1 - 0.37 )x 0.5
0.6 b = 0.60 x 4.00 = m
Hence Provided b = m
Width of toe slab = a x b = 0.37 x 2.40 = 0.89 m mLet the thickness of stem = H/12 = 4.00 / 12 = 0.33 or say = 0.30 m
= 2.40 - 0.30 - 0.90 = 1.20 m
4 Thickness of stem:-
= 4.00 - 0.30 = 3.70 m consider 1 m length of retaining wall
K x y x H13 0.33 x 18 x( 3.70 )
3
BM 50.65 x 10 6
Rxb 0.913 x 1000
= 240 mm and total thickness = 240 + 60 = 300 mm
Assuming that 12 mm F bar will be used. a nominal cover of = 60 - 6 = 54 mm= 200 mm at top so that effective depth of = 140 mm
DESIGN OF T SHAPED CANTILEVER RETAINING WALL with horizontal back fill
30
=
m*c+sst
=x
(1-a) m=
0.369
=0.7HKa
=
=
k=
b 2.96
This width is excessive. Normal practice is to provide b between 0.4 to 0.6 H .
Taking maximum value of H = 2.40
=
m*c
Provided toe slab =
1.90
Cocrete M
wt. of concrete
13.33 7
b
=
Keep d
0.7
2.40
mm
0.333
=
=Effective depth required
1-sin F0.95 H
6
Hence width of heel slab
The wall will be unsafe against sliding. This will be made safe by providing a shear Key at base .
Ka =
-1=
18000
100=
= 0.289
-
= 0.95
=
4.00
Ka
4.00
(1- a)x(1+3 a) 1+sinF
m
=
The base width from the considration of sliding is given by Eq.
.
Reduce the total thickness
Heigth AB
Maximum Bending momentat B =
236=
=
m
0.90
for design
purpose
50.65 Kn-m
a
6
b
x
1
0.33
7/29/2019 Reatining WAll With HORZONTAL Bach Fill
5/16
5
Full dimension wall is shown in fig 1a
Let W1 = weight of rectangular portion of stem
w2 = weight of triangular portion of stem
w3 = weight of base slab
w4 = weight of soil on heel slab.
The calculation are arrenged in Table
force(kN) Moment about toe (KN-m)
w1 1 x 0.20 x 3.70 x 25 =w2 1/2 x 0.10 x 3.70 x 25 =
w3 1 x 2.40 x 0.30 x 25 =
w4 1 x 1.20 x 3.70 x 18 =
Sw =Total resisting moment = kN-m ..(1)
0.33 x 18 x( 4.00 )2
2 2
4
3
- 64 = kN-m
\ Distance x of the point of application of resultant, from toe isSM 126.20 b 2.40Sw 121.05 6 6
b 2.40
2 2
SW 6 e 121.05 6x 0.16 70.28 < 100b b 2.40
SW 6 e 121.05 6x 0.16 30.59 < 100b b 2.40
70.28 - 30.59
70.28 - 30.59
6
(1) (2) Down ward weight of slab
= 0.30 x 1 x 1.00 x 25 = 7.50 kN-m2
= 70.28 - 7.50 = 62.8 kN-m2
underD
55.40 - 7.50 = 47.90 kN-m2
= 0.50 x( 62.78 + 47.9 ) x 0.90 = kN
47.90 + 2.00 x 62.78 0.9047.90 + 3
\ B.M. at E = 49.81 x 0.47 = kN-m
BM 23.42 x 10 6
Rxb 0.913 x 1000
= 200 mm and total thickness = 200 + 60 = 260 mm
= 200 mm or m at edge say = 0.26 mx
230 x 0.904 x 200
= 1/2 x 1131 = mm2
=
1.04 ==
x 1 +
Stability of wall:-
Design of toe slab:-
190.20
21.6
143.86
4.39
Hence safe
Hence safe
0.4
160
x
Pressure p at the junction of stem with toe slab is
p =
And at underE =
Total force = S.F. at E
lever arm
Hence net pressure intensities will be
Pressure distribution net moment SM =
Over turning
\ F.S. against over turning
Eccenticity e
= =x
Pressure p1 at
Heel= 1 -
Earth pressure
p=
Ka x y x H2
23.42
= =
Reduce the total thickness to
1.2
1.8
=
190.20
>
126.20
1.1
Detail
18.54.63 0.95
20.35
190.20
total MR121.05
18
79.92
kN ..(2)
Over turning moment Mo = 64 kN-m
= 48
x48
==
2Hence
safe
To make safe against sliding. Ew will have provid a shea Key .
190.20
64= 2.97=
= - x 0.16
1.04 m=
- 0.4
2.40=
m 450 Hence safe
0.12 260 + 200100
P D2 3.14 x ( 8 )4
1000 x 50
7 Design of heel slab :-
3.70 m high 2 eight of heel slab 3 upward soil pressure
1.20 x 3.70 x 1 x 18 = 79.9 = kN
Acting at 0.60 m from B.
= 1.20 x 0.26 x 1 x 25 = kN
Acting at 0.60 m from B.
= 1/2 x( 50 + 31 )x 1.20 = kN50 + 2 x 31 1.20
+ 3
\ Total force = = 80 + 7.80 - 49 = kN
\ B.M.at B =( 80 x 0.60 )+( 8 x 0.60 )-( 49 x 0.55 )
= 25.9 x 10'6
BM x 10 6
Rxb x
= 200 mm and total thickness = 200 + 60 = 260 mm
= 200 mm or m at edge (as that of toe slab)
x
230 x 0.904 x 200
P D2 3.14 x ( 10 )'2
4
1000 x 79
120 mm c/c at the top of keep slab. Take the reinforcement into toe
45 x D = 45 x 10 = 450 mm to the left ofB
0.12 260 + 200100
P D2 3.14 x ( 8 )'2
4
1000 x 50
Ast/A = 623 / 79 = 7.94 say = 8 No.8 bars of mm F at Bottom
8 x 79
1000 x 260
39 x 1000
Beam Ht.x beam wt. 1000 x 200
0.24 % = 0.21 (See Table 3.1)
Safe if tv< tc Here 0.20 < 0.21
8 Reinforcement in the stem:-
We had earliar assume the thickeness of heel slab as = 0.30 m
Total weight of soil =
Hence safe
Total weight of heel slab
Acting at
Effective depth required =
Hence provided these @
from a distance of
Using
Distribution steel
=Ausing 10 mm bars
39.18S.F. at B
Total upward soil pressure 48.62
7.80
Three force act on it
1. down ward weight of soil =
80.00
130
= 50
=50.44 30.59
KN say
1000
Reduce the total thickness to 0.20
=
N-mm2
0.55x = m from B
130
168=25.89
0.913 1000
Keep effective depth d
mm
Ast =25.89 10
6
sst x j x DBM x 10
6
= = 623 mm2
mm2
623= 126 mm say =
=4
mm F bars, Area = = 79
Spacing =
10
= x 1000 x 276
= 182 mm say =
=Using 8 mm F bars, Area =
2=
Spacing =
mm2
4= 50
276
Nomber of Bars =Hence Provided 10
% of steel provided =
mm c/c
mm c/c180
120
mm2
x 100
= 0.20 N/mm2
%= 0.24
Permissible shear stress for steel provided tc N/mm2
Shear stress tv =shear force
=
180 mm c/c
x = 276 mm2
2
276
=mm F bars, Area = mm24
= 182 mm say =
Distribution steel = x
Spacing =
Using 8
7/29/2019 Reatining WAll With HORZONTAL Bach Fill
7/16
0.26 m only. Hence revised H1= 4.00 - 0.26 = 3.74 m
H1 0.33 x 18 x( 3.74 )3
6
BM xRxb x
= 250 mm and total thickness = 250 + 60 = 310 mm
= 200 mm or m at edge
x
230 x 0.904 x 250P D2 3.14 x ( 12 )'2
4
1000 x 113
113
100
Continue alternate bars in the toe slabto serve as tensile reinforcement ther.Discontinue the remaining
45 x 12 = 540 mm beyond B, In th etoe slab.
250 - 140
250 - 140
H3
d'
h Ast' d'1/3
H1 Ast d
where Ast' = reinforcement at depth h Ast = reinforcement at depth H1
d' = effective depthat depth h d = effective depthat depth H1Ast' 1 h 1 d'
Ast 2 H1 2 d
Subsituting d = 250 =( 140 + 29.4 x h ) we get
140 + 29.4 x h 1/3
x
140 x 29.4 x h 1/3
x
h = 0.471 x ( 140 + 29.4 x h )1/3 ..(3)
h = 2.83 m 0.471 x ( 140 + 29.4 x h)
- h =
H1 H1
(2)1/3
2.83 m.Thus half bars can be curtailed can be curtailed at this point
.Howerver, the bars should be extented by a distance of 12 F = 12 x 12 = 144 mmOr d = 250 mm whichever is more beyond the point.
\ h = 2.83 - 0.25 = 2.58 m. Hence curtailed half bars at at height of2.58 m below the top . If we wish to curtailed half of the remaining bars so that remaining
Ast' 1
Ast 4
h 1 x d' 140 + 29.4 x h 1/3
H1 4 d x
x 140 x 29.4 x h4 x
h = 0.374 x ( 140 + 29.4 x h )1/3 ..(4)
h = 2.19 m 0.374 x ( 140 + 29.4 x h) - h =
H1
(4)1/3
+
1000
106
kN-m
= = 239 mm
=6
=
52.31
= = 0.63H1
x=250
x 3.741.59
This can be solved bytrial and error, Noting that if the effective thickness of stem w=are constant,
h would have been equal to
Hence from .(2)
0.79 x
2.36
\
h = 3.74
\ h
=
h = H1
m
1.26
Solving (3) by trial, we get h =
=
2.97 m
4
3.74 =
1/2 Ast
Effective depth required =0.913
than
2
=
x
if Ast =
h = 3.74
=\
2 250
mm and d'
x
250
x
52.31=M Kay x
While it has now been fixed as
Keep effective depth d
Reduce the total thickness to 0.20
Ast =52.31 10
6
=sst x j x D
BM x 100= 1007 mm2
Using 12 mm F bars, Area = = = 113 mm24
Spacing = = 112 mm say = 100 mm c/c1007
Actual AS provided = 1000 x x 1131 mm2
H =( Ast dNow As Ast
=
half bars after a distance of 45 F =Between A and B some of bars can be curtailed. Cosider a section at depth below the top of stem
)1/3
,,,'(1)
(where h In meter)
29.41
hx
or
= 140
Hence
d' +
This can be solved by trial and error, Noting that if the effective thickness of stem are constant,
h would have been equal to = =
he effective depth d' at section is 140
x h )=( 140 +
H
3.74 x h
0.02
0.04
250
= H1
remaining reinforcement is one forth of that provided arB, we have
7/29/2019 Reatining WAll With HORZONTAL Bach Fill
8/16
2.19 m.Thus half bars can be curtailed can be curtailed at this point
.Howerver, the bars should be extented by a distance of 12 F = 12 x 12 = 144 mmOr d = 250 mm whichever is more beyond the point.
\ h = 2.19 - 0.25 = 1.94 m. Hence stop half bars the remaining barsby 1.94 m below the top of the stem . Continue rest of the bars to the top of the stem
Check for shear:-
Shear force = 182
41.96 x 1000
1000 x 250
Distribution and temprechure reinforcement:-
= 310 + 200
0.12
100
P D2 3.14 x ( 8 )4
1000 x 50
= 8 = 300 mm c/cboth way in outer face
9 Design of shear key:-
Pp = KpP = 3.00 x 55.40 = kN/m3 Kp=1/ka = 3.00
Pp x a = a
18
2.00
or PH = 3.00 x( 4 + a )2
= 2.40 ax 18 = 43.20 a
\ W = 121.05 + 43.20 a Refer force calculation table=
mSw+Pp 0.5 x ( 121.05 + 43.20 a) 166.19 a3 x( 4 + a
2 )
0.5 x ( 121.05 + 43.20 a) 166.19 a
1.5
( 4 + a)2 = 60.52 + 21.6 a+ 166.19 a
4.5
( 4 + a)2 = 13.45 + 41.7 a
16 + 8 a + a2 = 41.73 a- 8 a + 13.45 - 16
a2 = 33.73 a -2.55
or a = a2 - 33.73 a +
or a = 0.076 m say = 80 mm
= 300 mm. Keep width of key 300 mm (equal to stem width)
F where (45 + F/2) =2 shearing angle of passive resistance
\ a1 = 0.3 x ( 3.00 )1/2
a1 = 0.52 m = DE = 0.90 m
Hence satisfactory.
Now size of key = 300 x 300 mm
PH = 3.00 x( 4.00 + a )2
= 3.00 x( 4.00 + 0.30 )2
PH = kN
0.17 < Permissible shear stress table 3.1
45 +a tan F = a tan x
55.47
it should be noted that passive pressure taken into account above will be devloped only when lengtha1 given below is avilable in front of key ;
However, provided minimum value of a
2.55
Actual length of the slab available
= a kpa1 =
1.5
+
Hence equilibrium of wall, permitting F.S. 1.5 against sliding we have
PH=1.5
x3
=
.(2)Weight of the soil between bottom of the base and D 1C1
0.33 x x( 4Sliding force at level D1C1 = a )2
mm2
Using 8 mm F bars, Area
164 mm say =
\ total passive pressure Pp = 166.19
166.19
mm bars
mm c/cat the inner face of
wall,along its length160
for tempreture reinforcement provide
\ spacing306
= = = 50.24
The wall is in unsafe in sliding, and hence shear key will be provided below the stem as shown in fig.
Let the depth of key =a intensity of passive pressure Pp devloped in front of key depend upon
the soil pressure P in front of the key
=
mm2
4
mm
\ Distribution reinforcement = x 1000 x 255 = 306
Average thickness of stem
2= 255
tv\
p =kayH2
1.8=
kN3.742
=41.96
2
=
x= 0.33 x
Solving (4) by trial, we get h =
=x( 4 + a)2
7/29/2019 Reatining WAll With HORZONTAL Bach Fill
9/16
= a = x
= kN Hence
SW = 121.05 + 43.20 a
= 121.05 + 43.20 x 0.30
= kN
Actual force to be resisted by the key at F.S. 1.5 is = 1.5PH - mSW= 1.5 x 55.5 - 0.5 x
= kN
16.20 x 1000
300 x 1000
16.20 x 150 x 1000
1/6 x 1000 x( 300 )2
= N/mm2 Hence safe
Bending stress =
\ shear stress =
166.19 0.30
49.86
0.16
134.01
166.19
134.01
16.20
= 0.054 N/mm2
7/29/2019 Reatining WAll With HORZONTAL Bach Fill
10/16
A A A
m H1 m m H1= m m
toe heel
D E B C D E B C D E B
Toe Toe a1
m m
D1 e
p = pp
70.28
55.40
50.4
4
30.5
9
b = 2.40
2.40
0.90W2 1.20
W1
W20.00
2.40
70.2
8
0.30 0.30
3.00 3.70
4.00H=
1
0.20
1.20
W1
3.00
0.20 0.20
3.00 3.70
W1
P=
1.00
0.90
a b
b =
55.4
0
2.40
W2
P=
7/29/2019 Reatining WAll With HORZONTAL Bach Fill
11/16
A
Outer side face
mm F Earth side Face@ c/c `
mm F
@ C/Cm
mm F@
mm F@ c/c
mm Fmm F @
@ c/c
mm FN.S.L. @
mm F mm F
@ c/c @
Toe Heel
Reinforcement Detail Reinforcement
Foundation level
mm F mm F@ c/c @ c/c `
1000
300
1.9
4
2.5
8
10
C/C
8
160
200
C/C
740
3000
8
8
8
300
160
3740
200
4.00H=
180
60
0.20
Earth side Face
130
8
10
C/C
C/C
12
8
300
300
300
450
Outer side
180
120
400
12
200
12
100
7/29/2019 Reatining WAll With HORZONTAL Bach Fill
12/16
7/29/2019 Reatining WAll With HORZONTAL Bach Fill
13/16
7/29/2019 Reatining WAll With HORZONTAL Bach Fill
14/16
M-10 M-15 M-20 M-25 M-30 M-35 M-40
(N/mm2) Kg/m2
(N/mm2) Kg/m2
M 10 3.0 300 2.5 250
M 15 5.0 500 4.0 400
M 20 7.0 700 5.0 500
M 25 8.5 850 6.0 600
M 30 10.0 1000 8.0 800
M 35 11.5 1150 9.0 900
M 40 13.0 1300 10.0 1000
M 45 14.5 1450 11.0 1100M 50 16.0 1600 12.0 1200
M-10 M-15 M-20 M-25 M-30 M-35 M-40
Grade of concrete M-15 M-20 M-25 M-30 M-35 M-40
Modular Ratio 18.67 13.33 10.98 9.33 8.11 7.18
scbc N/mm2 5 7 8.5 10 11.5 13m scbc 93.33 93.33 93.33 93.33 93.33 93.33
kc 0.4 0.4 0.4 0.4 0.4 0.4
jc 0.867 0.867 0.867 0.867 0.867 0.867
Rc 0.867 1.214 1.474 1.734 1.994 2.254
Pc (%) 0.714 1 1.214 1.429 1.643 1.857
kc 0.329 0.329 0.329 0.329 0.329 0.329
jc 0.89 0.89 0.89 0.89 0.89 0.89
Rc 0.732 1.025 1.244 1.464 1.684 1.903
Pc (%) 0.433 0.606 0.736 0.866 0.997 1.127
kc 0.289 0.289 0.289 0.289 0.289 0.289
jc 0.904 0.904 0.904 0.904 0.904 0.904Rc 0.653 0.914 1.11 1.306 1.502 1.698
Pc (%) 0.314 0.44 0.534 0.628 0.722 0.816
kc 0.253 0.253 0.253 0.253 0.253 0.253
jc 0.916 0.916 0.916 0.914 0.916 0.916
Rc 0.579 0.811 0.985 1.159 1.332 1.506
Pc (%) 0.23 0.322 0.391 0.46 0.53 0.599
Table 1.15. PERMISSIBLE DIRECT TENSILE STRESS
Grade of concrete
Tensile stress N/mm2 1.2 4.0 4.42.0 2.8 3.2 3.6
Table 1.16.. Permissible stress in concrete (IS : 456-2000)
Grade of
concrete
Permission stress in compression (N/mm2) Permissible stress in bond (Average) for
plain bars in tention (N/mm2)Bending acbc Direct (acc)
(N/mm2) in kg/m2
-- --
0.6 60
0.8 80
0.9 90
1.0 100
1.4 140
1.1 110
1.2 120
31
(31.11)
19
(18.67)
13
(13.33)
11
(10.98)
1.3 130
9
(9.33)
8
(8.11)
7
(7.18)
Table 1.18. MODULAR RATIO
Grade of concrete
Modular ratio m
Table 2.1. VALUES OF DESIGN CONSTANTS
(a) sst =140
N/mm2
(Fe 250)
(b) sst =190
N/mm2
(d) sst =275
N/mm2
(Fe 500)
(c ) sst =
230N/mm2
(Fe 415)
7/29/2019 Reatining WAll With HORZONTAL Bach Fill
15/16
M-15 M-20 M-25 M-30 M-35 M-40
0.18 0.18 0.19 0.20 0.20 0.20
0.22 0.22 0.23 0.23 0.23 0.23
0.29 0.30 0.31 0.31 0.31 0.32
0.34 0.35 0.36 0.37 0.37 0.38
0.37 0.39 0.40 0.41 0.42 0.42
0.40 0.42 0.44 0.45 0.45 0.46
0.42 0.45 0.46 0.48 0.49 0.49
0.44 0.47 0.49 0.50 0.52 0.52
0.44 0.49 0.51 0.53 0.54 0.55
0.44 0.51 0.53 0.55 0.56 0.57
0.44 0.51 0.55 0.57 0.58 0.60
0.44 0.51 0.56 0.58 0.60 0.62
0.44 0.51 0.57 0.6 0.62 0.63
300 or more 275 250 225 200 175 50 or less
1.00 1.05 1.10 1.15 1.20 1.25 1.30
M-15 M-20 M-25 M-30 M-35 M-40
1.6 1.8 1.9 2.2 2.3 2.5
Grade of concrete M-10 M-15 M-20 M-25 M-30 M-35 M-40 M-45 M-50
tbd (N / mm2) -- 0.6 0.8 0.9 1 1.1 1.2 1.3 1.4
tbd (N / mm2) tbd (N / mm2)
M 15
M 20
M 25
M 30
M 35
M 40M 45
M 50
Table 3.1. Permissible shear stress Table c in concrete (IS : 456-2000)
100As Permissible shear stress in concrete tc N/mm2
bd
< 0.15
0.25
0.50
0.75
1.00
1.25
1.50
1.75
2.00
2.25
2.50
2.75
Table 3.2. Facor k
3.00 and above
Grade of concrete
Over all depth of slab
k
Table 3.3. Maximum shear stress tc.max in concrete (IS : 456-2000)
tc.max
Table 3.4. Permissible Bond stress Table bd in concrete (IS : 456-2000)
Table 3.5. Development Length in tension
Grade of
concrete
Plain M.S. Bars H.Y.S.D. Bars
kd = LdF kd = LdF
0.6 58 0.96
0.9 39 1.44 40
1 35 1.6 36
60
0.8 44 1.28 45
27 2.08
33
1.2 29 1.92 30
1.1 32 1.76
28
1.4 25 2.24 26
1.3
7/29/2019 Reatining WAll With HORZONTAL Bach Fill
16/16
Degree sin cos tan
10 0.174 0.985 0.176
15 0.259 0.966 0.268
16 0.276 0.961 0.287
17 0.292 0.956 0.306
18 0.309 0.951 0.325
19 0.326 0.946 0.344
20 0.342 0.940 0.364
21 0.358 0.934 0.384
22 0.375 0.927 0.404
23 0.391 0.921 0.424
24 0.407 0.924 0.445
25 0.422 0.906 0.466
30 0.500 0.866 0.577
35 0.573 0.819 0.700
40 0.643 0.766 0.839
45 0.707 0.707 1.000
50 0.766 0.643 1.192
55 0.819 0.574 1.428
60 0.866 0.500 1.732
65 0.906 0.423 2.145
Value of angle