Recent Fundamental RF Power Coupler developments at CERN
First SLHiPP meetingCERN, Geneva, 8 & 9 December 2011
First SLHiPP meeting, 8 & 9 December 2011
2
Acknowledgements• SPL coupler review committee :
▫ Ali Nassiri, Wolf Dietrich Moeller, Mark Champion, Sergey Kazakov, Mircea Stirbet, Amos Dexter, Rama Calaga, Miguel Jimenez, Sergio Calatroni, Ofelia Capatina, Vittorio Parma
• DESY :▫ Wolf-dietrich Moeller, Axel
Matthaisen, Birte Van der Horst, and team
• CEA :▫ Stephane Chel, Guillaume Devanz,
Michel Desmond, and team• ESRF :
▫ Jorn Jacob, Vincent Serriere, Jean-Maurice Mercier, Didier Boilot, and team
• APS :▫ Ali Nassiri, Doug Horan, Gian
Tenko, Dave Brubenker, and team
• CERN :▫ Mechanical & Material
Engineering group : Ramon Folch, Francesco Bertinelli,
Serge Mathot, Agostino Vacca, Thierry Tardy, Thierry Calamand, Thierry Renaglia, Ofelia Capatina, Marc Polini, Laurent Deparis, Philippe Frichot, Jean-Marie Geisser, Jean-Marc Malzacker, Pierre Moyret, Alain Stadler, and team
▫ Vacuum, Surface & Coating group : Miguel Jimenez, Sergio Calatroni,
Wilhelmus Vollenberg, Marina Malabaila, Nicolas Zelko, and team
▫ Magnets, Superconductors & Cryostats group: Vittorio Parma, Arnaud Van de
Craene, and team▫ RF group :
Sebastien Calvo, Antoine Boucherie, Nicolas Jurado, Charles Julie, all FSU-AB03 team members
Eric Montesinos
First SLHiPP meeting, 8 & 9 December 2011
3
Contents
• SPL couplers
• ESRF/SOLEIL/APS couplers
• Linac 4 window
Eric Montesinos
First SLHiPP meeting, 8 & 9 December 2011
4
SPL coupler requirements
Eric Montesinos
Technical ChoicesSingle window couplerFixed couplerWith a Double Walled TubeMounted in clean room with its double walled tube horizontally in only one operationVertically below the cavity and will be a support for the cavity (first time worldwide)
With a HV DC biasing capacitorAir cooled
RF Characteristicsf0 704.4 MHz
Power levels
1000 kW pulsed0.4 + 1.2 + 0.4 = 2.0 ms50 Hz (20 ms)100 kW average
Cavity design gradient 19-25 MV/m
Qext of input coupler 1.2 x 106
Input line Ø 100 / 43.5 mm = 50 Ω(from the cavity design)
Waveguides WR 1150
First SLHiPP meeting, 8 & 9 December 2011
5
Two proposed designs
Eric Montesinos
First SLHiPP meeting, 8 & 9 December 2011
6
SPL coupler project• Four ‘vacuum lines’:
▫ 4 cylindrical window couplers▫ 4 planar disk window
couplers▫ 8 Double walled Tubes▫ 4 test boxes
• DESY clean process assembly▫ (Jlab also proposed to help)
• CERN LLRF measurements
• CEA RF power tests▫ (BNL also proposed to help)
Eric Montesinos
First SLHiPP meeting, 8 & 9 December 2011
7
Couplers construction• All components have been
constructed by May 2011▫ 4 cylindrical window couplers▫ 4 planar disk window couplers▫ 8 Double walled Tubes▫ 4 test boxes
• All components have been individually vacuum leak free tested
• Specific transport boxes with springs as per tetrodes have been designed to avoid any shocks
Eric Montesinos
First SLHiPP meeting, 8 & 9 December 2011
8
Test box• Test box is made with only two parts
with a helicoflex seal :▫ Upper cover with included machined
vacuum knife flanges included▫ Two covers with inner copper plated
• Advantages :▫ Easier (not easy) to copper plate▫ Easily cleanable regarding clean
room requirements for high gradient field cavity
▫ Can be used for several sets of couplers (if large series : SPL, …)
• Drawbacks :▫ Helicoflex faces have to be very well
prepared▫ Self-supporting structure : heavy
weight
• Holes for vacuum port :▫ without sharp edges▫ L = 5 x D to allow
correct RF shielding (P peak max = 1’000 kW !), helped with additional vacuum tombac
Eric Montesinos
First SLHiPP meeting, 8 & 9 December 2011
9
Waveguides• Six parts waveguide
• Easy mounting
• Easily exchangeable shims and allows post machining of internal step for matching if needed
• Knife contacts all along to suppress any gap at intersections in order to avoid any arcing (DESY difficulties with brazed WG)
• No mechanical stress given to the ceramic, fixed point onto the body only
• Capacitor self centered around the ceramic and designed to symmetrically air cool the ceramic
Eric Montesinos
First SLHiPP meeting, 8 & 9 December 2011
10
Planar disk inner line• As the coupler must be air
cooled to avoid any water leak
• Specific trick to ensure inner RF contact :▫ Inner line on top of the
ceramic▫ Springs are compressed▫ Air cane inside the inner line▫ Screw to the inner ceramic▫ Release springs to ensure
RF contacts▫ Absolutely no stress to the
ceramic
Eric Montesinos
1 MWRFcontact
First SLHiPP meeting, 8 & 9 December 2011
11
Clean room assembly (DESY)• Test box assembly not easy
because of specific surfaces roughness needed for helicoflex
• Couplers assembly was also not easy because :▫ Couplers are heavy▫ Last connection has to be
done manually▫ Ok for few prototypes, not
for a large series
• Two cavities were sent to CERN, but…
Eric Montesinos
First SLHiPP meeting, 8 & 9 December 2011
12
Double walled Tube (DT)• Despite a previous long
experience with LEP and LHC DT, a difficulty occurred in the construction process :▫ An additional machining has
erased all the care put into the preparation of DT
• Copper sputtering was removed with a simple water Ultra Sonic cleaning process
• Decision to condition the two first vacuum lines with NOT copper coated DT
Eric Montesinos
First SLHiPP meeting, 8 & 9 December 2011
13
Low Power measurements (CERN)
Eric Montesinos
• S11 with 2 x N/WG adaptors + 2 couplers + 2 DT + test box :▫ Cylindrical = -26.5 dB▫ Planar disk = -18 dB
• Even with -16 dB, 1 MW corresponds to 25 kW reverse power
• Ok for first tests
First SLHiPP meeting, 8 & 9 December 2011
14
RF tests (CEA premises)• Tests started with cylindrical
window couplers
• Not baked out, static vacuum~ 2 x 10 -7 mbar▫ Wanted to check RF▫ Size of the test box 250 mm x
600 mm▫ Helicoflex
• Pulse mode process
• After 3 weeks,50 kW 20 us / 20 Hz
• We stopped the test
Eric Montesinos
First SLHiPP meeting, 8 & 9 December 2011
15
RF tests• In the meantime, second test box
with two planar disk window coupler has been baked out
• No helicoflex leak▫ Very slow heating up and heating
down ramps 10 C / hour▫ Maximum temperature was only
150 C during three days▫ Nitrogen onto copper rings to
avoid any oxidization
• Very good static vacuum after the process:▫ ~ 1 x 10 -9 mbar▫ Was 2 x 10-5 mbar before
starting the bake out
Eric Montesinos
First SLHiPP meeting, 8 & 9 December 2011
16
RF tests
• Restarted the tests with the planar disk window couplers
• Pulse mode process starting with 20 µs pulses / 8 Hz
• After 10 days : 1000 kW 2 ms / 8 Hz
Eric Montesinos
First SLHiPP meeting, 8 & 9 December 2011
17
RF tests• Still some out gazing around
three power levels :▫ 20 kW▫ 140 kW▫ 300 kW
• No more vacuum activity above 300 kW
• Processing around these values is under way and vacuum decreases ramp after ramp
• Tests ongoing to reach 1000 kW 2ms / 50 Hz (uncoated DT limitation)
Eric Montesinos
First SLHiPP meeting, 8 & 9 December 2011
18
Next steps• While testing the planar disk
window couplers, we baked out cylindrical couplers (already seen RF) :▫ Initial static vacuum
~ 1.0 x 10-6 mbar▫ After bake out, static vacuum
~ 1 x 10-10 mbar
• Once planar disk window coupler tests finished, restart cylindrical window coupler tests
• These tests are scheduled beginning 2012
• Corrected DT copper coating under way
• Cryostat flanges to be added prior to new clean room assembly
• Mounting of chosen design at DESY clean room:▫ Two tests cavities▫ Four copper coated DT with
cryostat flanges▫ Four couplers
• RF tests at Saclay premises of the four chosen couplers
Eric Montesinos
First SLHiPP meeting, 8 & 9 December 2011
19
Key RF items
• Ceramic and waveguide as a whole matching system
• Waveguides:▫ ‘Plug and Play’ ▫ No doorknob▫ Reduced height▫ Screwed waveguide▫ No mechanical stress to
the ceramic
• Test cavity in two parts, easier to copper plate and easy to clean
• Inner line of planar disk window with RF contacts ensured by compression of springs
• Only air cooled couplers
Eric Montesinos
First SLHiPP meeting, 8 & 9 December 2011
20
ESRF/SOLEIL/APS coupler requirements
RF Characteristics
f0 352.2 MHz
Power levels 200 kW cw
Technical choices Single window, fixed coupler
Waveguides WR 2300 half height
Mechanical constraintsMust match with previous design without any infrastructure modification
Eric Montesinos
First SLHiPP meeting, 8 & 9 December 2011
21
Kovar vs copper window• LEP Kovar® brazed window :
▫ Kovar ® rings on both ends▫ Body and Antenna with Stainless Steel
rings brazed onto copper▫ TIG welding under mechanical
pressure ensuring RF contact▫ Easy Kovar ® brazing process▫ Weakness of the design : RF contact▫ High field between two Kovar ®
‘antennas’, arcing
• LHC copper brazed window :▫ Massive copper ring for high power▫ No RF contact, fully continuous RF
path▫ Spherical ends of copper rings for no
arcing▫ Very difficult brazing process (6 years
to be finalized)▫ Advantage of the design: extremely
powerful
Eric Montesinos
LEP kovar collar
RF contact via compression
while TIG welding
LHC copper collars
EB welded
Metallic continuity
Ceramic
Ceramic
First SLHiPP meeting, 8 & 9 December 2011
22
Kovar vs copper window• APS coupler with kovar/copper
misalignment :▫ RF contact lost▫ kovar has metalized ceramic (grey)▫ Thermal losses▫ Vacuum leak
• CERN Kovar vs CERN copper with a LHC test :▫ kovar RF losses▫ Thermal overheating▫ Burnt kapton and peek (> 250 C)
• Copper ceramic window is not only a simple upgrade, it is a very new design really stronger than kovar window ceramic
Eric Montesinos
First SLHiPP meeting, 8 & 9 December 2011
23
ESRF coupler project• LEP I style coupler became ESRF
trouble maker (five unexplained vacuum leaks in 2008)
• Proposal of a new coupler to fit into existing premises with NO infrastructure modification
• Coupling loop :▫ Water cool to be sure there will be no
mechanical stress given to the ceramic
• Three vacuum ports for conditioning process:▫ Vacuum gauge close to the ceramic▫ Glass window for arc detection▫ e- antenna
• First prototype delivered September 2011
Eric Montesinos
First SLHiPP meeting, 8 & 9 December 2011
24
ESRF coupler tests• Bake out onto cavity process
• CERN pulsed mode conditioning process under vacuum feedback
• Off tune, 200 kWpulsed 5 ms / 50 Hz in 22 hours
• On tune, 200 kW cw in 60 hours
• Qualified for ESRF needs
• Last week, on tune 300 kW cw
Eric Montesinos
20 us / 20 ms pulses
50 us / 20 ms pulses
500 us / 20 ms pulses CW
Pulse length of 20us - 50us - 100us - 200us - 500us - 1ms - 2ms - 5ms - 10mswith fixed repetition time of 20 ms and finally CW
time
Power
First SLHiPP meeting, 8 & 9 December 2011
25
ESRF/SOLEIL next steps• Further tests to higher
power levels, up to maximum test bench capability, i.e. 350 kW cw
• Two additional ESRF ‘series couplers’
• Two SOLEIL couplers:▫ Electrical antenna, air
cooled▫ CERN LEP type test cavity▫ Outer coaxial line with
corrected length▫ Tests at ESRF
Eric Montesinos
First SLHiPP meeting, 8 & 9 December 2011
26
APS coupler project• Collaboration requested during
CWRF workshop Barcelona in April 2010
• Present coupler also LEP I type limited to 100 kW cw
• Design similar to ESRF:▫ Coupling loop differs▫ Inches vs mm▫ Waveguide air cooling as
personal safety interlock
• Individual bake out of the coupler, reduced exposition to air (not under mobile clean room)
Eric Montesinos
First SLHiPP meeting, 8 & 9 December 2011
27
APS ‘picture horizontal flip’• Loop angle does not allow any
vacuum ports to be useful
• Not needed because cavity is small enough, pumping perfect (1 x 10-9 Torr without RF)
• If one additional coupler, it will be with no more vacuum ports:▫ Reduces the costs to its
minimum▫ Reduces the risk of vacuum
potential leaks▫ Cavity small enough to ensure
a correct vacuum monitoring
Eric Montesinos
First SLHiPP meeting, 8 & 9 December 2011
28
APS coupler tests and next steps• Tests started last week
• Conditioning in cw mode with a very low pressure:▫ 1 x 10-8 Torr maximum▫ interlock at 5 x 10-8 Torr
• 25 kW cw after two days
• Further tests to higher power levels, up to maximum test bench capability, i.e. 200 kW cw
• Implementation of CERN pulse mode conditioning system
Eric Montesinos
Vacuum Power
First SLHiPP meeting, 8 & 9 December 2011
29
Linac 4 window requirements
RF Characteristics
f0 352.2 MHz
Power levels 1250 kW pulsed 2ms / 50 Hz (SPL cycle)
Waveguides WR 2300
Mechanical constraints As short as possible
Eric Montesinos
First SLHiPP meeting, 8 & 9 December 2011
30
Ceramic assembly• As simple as possible :
▫ 1 : Ceramic Ø 400 mm x 25 mm▫ 2 : Inner copper ring Ø 400 mm x
1.25 mm▫ Outer copper ring▫ Stainless steel ring for Helicoflex
• Two first individually brazed sub-assemblies:▫ Brazed ceramic = ceramic + inner
copper ring▫ Outer ring for Vacuum seal = outer
copper ring + stainless steel ring
• Main ceramic = EB welding of two parts
• Ti sputtering of the vacuum side
Eric Montesinos
First SLHiPP meeting, 8 & 9 December 2011
31
LINAC 4 window project• As simple as possible
▫ 1-2-3-4 : Ceramic assembly▫ 5 : spacer▫ 6 : Helicoflex seal▫ 7-8 : Stainless Steel flanges
• Massive flanges, not copper plated
• More difficult design than it look likes because of the two shapes : cylindrical and rectangular, with incorporated screws
Eric Montesinos
1 2 437
56
8
EB1EB2
FM
First SLHiPP meeting, 8 & 9 December 2011
32
S11 < 32 dB over ~ 16 MHz
LINAC 4 window next step• First prototype with helicoflex
▫ Low Power RF ok
• Second prototype with no helicoflex but an Electron Beam Welding is under construction
• Tests of two prototypes face to face onto a vacuum waveguide line in CEA premises :▫ 1.25 MW 2 ms 50 Hz▫ Define the best design
(Helicoflex/EBW)
• Series construction of 30 windows▫ Ceramics already ordered
Eric Montesinos
First SLHiPP meeting, 8 & 9 December 2011
33
Future coupler developments• HIE-Isolde, under way
▫ 100 MHz▫ 500 W (1 kW ?)▫ Operating at 2k▫ Inside vacuum vessel
• LIU-SPS 200 MHz▫ New concept with coaxial plain
disk and capacitive coupling▫ 900 kW pulsed 50 % (ms)▫ 450 kW cw power
• SPS 800 MHz consolidation▫ Scaling of Linac 4 to 800 MHz▫ 150 kW cw
• One for all Crab Cavities coupler▫ Same window for all
cavities▫ Compatible with various
coupling system
• Whatever new coupler needed
Eric Montesinos
First SLHiPP meeting, 8 & 9 December 2011
34
Thank you very muchfor your attention
And many thanks again to all the persons involvedin all these projects
Eric Montesinos