+ All Categories
Home > Documents > Recent Results From ITER Conductor Tests 240711 Reduced

Recent Results From ITER Conductor Tests 240711 Reduced

Date post: 06-Apr-2018
Category:
Upload: odormicchi
View: 217 times
Download: 0 times
Share this document with a friend

of 29

Transcript
  • 8/2/2019 Recent Results From ITER Conductor Tests 240711 Reduced

    1/29

    A.D.

    SULTANT

    estResults

    240711

    113/141

    Appendix:TF SULTAN Sample Assembly

    Procedure at CRPP

  • 8/2/2019 Recent Results From ITER Conductor Tests 240711 Reduced

    2/29

    A.D.

    SULTANT

    estResults

    240711

    114/1

    41

    Conductors and empty tubes are

    inspected upon delivery at CRPP.

    (Courtesy

    of P. Bruzzone,

    CRPP)

    Conductor Inspection

  • 8/2/2019 Recent Results From ITER Conductor Tests 240711 Reduced

    3/29

    A.D.

    SULTANT

    estResults

    240711

    115/1

    41

    Whenever required, the conductors are straightened using a jack (asin the case of TFJA4).

    (Courtesy

    of P. Bruzzone,

    CRPP)

    Conductor Straightening

  • 8/2/2019 Recent Results From ITER Conductor Tests 240711 Reduced

    4/29A.D.

    SULTANT

    estResults

    240711

    116/1

    41

    The jacket is dismantled from both ends of the conductor section (420mm at the upper termination side and 440 mm at the bottom joint side).

    Dismantling procedure starts with a radial indent by lathing machine,

    followed by two longitudinal milling passes. The two jacket halves are pulled apart with the help of welded grips once

    the thickness of the jacket is milled down to few hundredths of millimetre.

    (Courtesy

    of P. Bruzzone,

    CRPP)

    Jacket Dismantling

  • 8/2/2019 Recent Results From ITER Conductor Tests 240711 Reduced

    5/29A.D.

    SULT

    ANT

    estResults

    240711

    117/1

    41

    The outer wrap is removed anda clamp is applied to the end ofthe cable to prevent untwisting.

    The sub-cable wraps are cut atthe cable surface and pulled outfrom inside the cable by slightlyuntwisting the cable.

    Cr plating is removed by dippingthe cable for 3 min in a HClsolution placed in an ultrasound

    bath; nitrogen gas is blown fromthe other end to preventpenetration of corrosive vaporinto the conductor.

    The solution turns dark blue andthe cable is rinsed 3 times inwater in the ultra-sound bath.

    (Courtesy of P. Bruzzone, CRPP)

    Un-Wrapping & Cr Plating Removal

  • 8/2/2019 Recent Results From ITER Conductor Tests 240711 Reduced

    6/29A.D.

    SULT

    ANT

    estResults

    240711

    118/1

    41

    (Courtesy of P. Bruzzone, CRPP)

    At the upper crimping rings, a 100 mm long steel pipe (welded shut) is placed bythe same method. The distance between the jacket edge and the start of the plug is 19 mm.

    A 855 mm long steel pipe,welded shut at one end andwith a thread machined at the

    other end, is placed at the HFZand lower crimping rings by athreaded rod; once theposition is reached, the

    threaded rod is removed.

    Central Channel Plugging

    The central channel is plugged underneath the crimping rings (to prevent a localcollapse of the central spiral) and in the High Field Zone (to force the helium inthe bundle region and restrain the temperature gradient over the cable crosssection), but it must not be plugged in the termination sections where the bundle

    region is solder filled.

  • 8/2/2019 Recent Results From ITER Conductor Tests 240711 Reduced

    7/29A.D.

    SULT

    ANT

    estResults

    240711

    119/1

    41

    The crimping rings are compacted.

    (Courtesy of P. Bruzzone, CRPP)

    Crimping Rings

  • 8/2/2019 Recent Results From ITER Conductor Tests 240711 Reduced

    8/29A.D.

    SULT

    ANT

    estResults

    240711

    120/1

    41

    A pre-fabricated copper sleeve with electron beam welded stainless

    steel end caps is carefully slid over the cable.

    (Courtesy of P. Bruzzone,CRPP)

    Cu Sleeve Insertion

  • 8/2/2019 Recent Results From ITER Conductor Tests 240711 Reduced

    9/29A.D.

    SULT

    ANT

    estResults

    240711

    121/1

    41

    The assembly is compacted in a crimping device.

    Opposite to a swaging device with rotating heads, the crimping

    device causes negligible elongation to the termination, but thestepwise action of the crimping device leaves imprints on the coppersurface, which is no longer smooth and perfectly round.

    During compaction, the inner cable diameter is reduced from

    nominal to 38 mm; assuming that the central channel is notreduced, the void fraction in the annular region changes from theoriginal ~29% to ~23%.

    (Courtesy of P. Bruzzone, CRPP)

    Cu Sleeve Compaction

  • 8/2/2019 Recent Results From ITER Conductor Tests 240711 Reduced

    10/29A.D.

    SULT

    ANT

    estResults

    240711

    122/1

    41

    The steel end cap of the sleeve is vacuum tight welded to thejacket.

    (Courtesy of P. Bruzzone, CRPP)

    Cu Sleeve Welding

  • 8/2/2019 Recent Results From ITER Conductor Tests 240711 Reduced

    11/29A.D.

    SULT

    ANT

    estResults

    240711

    123/1

    41

    To improve quality of the sleeve surface and allow a good solderingwith the matching parts after the heat treatment, the termination is

    lathed to remove the imprints of the crimping machine.

    (Courtesy of P. Bruzzone, CRPP)

    Cu Sleeve Lathing

  • 8/2/2019 Recent Results From ITER Conductor Tests 240711 Reduced

    12/29

    A.D.

    SULT

    ANT

    estResults

    240711

    124/1

    41

    Heat treatment is carriedout in a Thermcraft tubefurnace in vacuum, with a

    residual pressure smallerthan 3.8 10-6 mbar. During the entire HT, a

    flow of high-purity argon

    (0.05 li/min) purges thesample of any developinggases or fumes.

    The furnace control system

    regulates the temperatureof the inside furnace wall.

    The furnace temperatureand the temperature of 5

    sensors attached to theconductors are recorded ina PC.

    (Courtesy of

    P. Bruzzone, CRPP)

    Heat Treatment

  • 8/2/2019 Recent Results From ITER Conductor Tests 240711 Reduced

    13/29

    A.D.

    SULT

    ANT

    estResults

    240711

    125/1

    41

    A siphon is pre-assembled by a steel cap, a 500 mmlong Teflon rod (to keep the central channel freeduring solder filling) and a copper pipe.

    First the copper pipe is brazed to the steel cap, then,the Teflon is squeezed into the hole of the steel cap.

    Finally, the assembled siphon is welded to the steelend cap of the sample termination.

    (Courtesy of

    P. Bruzzone, CRPP)

    Siphon Assembly

  • 8/2/2019 Recent Results From ITER Conductor Tests 240711 Reduced

    14/29

    A.D.

    SULT

    ANT

    estResults

    240711

    126/1

    41

    A hole is drilled in the steel part of the termination welded to the jacket

    as an outlet of the cooling gas injected during flux and solder filling fromthe opposite side of the conductor.

    (Courtesy ofP. Bruzzone, CRPP)

    Outlet Hole Drilling

  • 8/2/2019 Recent Results From ITER Conductor Tests 240711 Reduced

    15/29

    A.D.

    SULT

    ANT

    estResults

    240711

    127/1

    41

    The conductor is lowered into the fluxagent placed in a retort in an ultra soundsbath.

    (Courtesy ofP. Bruzzone, CRPP)

    Solder Filling (1/4)

  • 8/2/2019 Recent Results From ITER Conductor Tests 240711 Reduced

    16/29

    A.D.

    SULT

    ANT

    estResults

    240711

    128/1

    41

    The termination and its siphon pipe arelowered into a bath of PbSn alloy, heated at260 C (above the melting temperature of

    SnAg5 used for solder filling). The PbSn bath is in an aluminum container

    sandwiched between two heaters,

    (Courtesy of

    P. Bruzzone, CRPP)

    Solder Filling (2/4)

    S ld illi (3/ )

  • 8/2/2019 Recent Results From ITER Conductor Tests 240711 Reduced

    17/29

    A.D.

    SULT

    ANT

    estResults

    240711

    129/1

    41

    SnAg rods are inserted and melted in thecopper siphon till the siphon is full.

    (Courtesy of

    P. Bruzzone, CRPP)

    Solder Filling (3/4)

    S ld Filli (4/4)

  • 8/2/2019 Recent Results From ITER Conductor Tests 240711 Reduced

    18/29

    A.D.

    SULT

    ANT

    estResults

    240711

    130/1

    41

    (Courtesy ofP. Bruzzone, CRPP)

    Once the filling is completed, thetermination is lifted from the bath.

    In the case of TFJA4, the terminations

    stayed ~8 minutes in the bath and theamount of SnAg solder, including the fillingof the siphon pipe, was 1450/1490 g for the upper termination, 1064/901 g for the lower termination.

    Solder Filling (4/4)

    Fi l P (1/2)

  • 8/2/2019 Recent Results From ITER Conductor Tests 240711 Reduced

    19/29

    A.D.

    SULT

    ANT

    estResults

    240711

    131/1

    41

    (Courtesy of

    P. Bruzzone, CRPP)

    After solidification of the solder,the copper pipe is cut away andthe solder filled steel cap is

    carefully sawed (without cuttingthe Teflon rod).

    The Teflon rod is pulled out lettingfree the central channel in the

    termination.

    Final Prep (1/2)

    Fi l P (2/2)

  • 8/2/2019 Recent Results From ITER Conductor Tests 240711 Reduced

    20/29

    A.D.

    SULT

    ANT

    estResults

    240711

    132/1

    41

    The solder is removedmechanically from the end oftermination to prepare the welding

    of the inlet and outlet coolingpipes.

    The temporary venting hole iswelded shut.

    (Courtesy of

    P. Bruzzone, CRPP)

    Final Prep (2/2)

    D t ti E i ti

  • 8/2/2019 Recent Results From ITER Conductor Tests 240711 Reduced

    21/29

    A.D.

    SULT

    ANT

    estResults

    240711

    133/1

    41

    Effectiveness of solder filling procedure was checked by destructiveexamination of a solder filled termination.

    (Courtesy of

    P. Bruzzone, CRPP)

    Destructive Examination

    Inst mentation

  • 8/2/2019 Recent Results From ITER Conductor Tests 240711 Reduced

    22/29

    A.D.

    SULT

    ANT

    estResults

    240711

    134/1

    41

    Arrays of voltage taps are welded to thejacket.

    Temperature sensors are attached tomachined flats on the conductor jacket.

    (Courtesy of P. Bruzzone, CRPP)

    Instrumentation

    Upper Termination Assembly

  • 8/2/2019 Recent Results From ITER Conductor Tests 240711 Reduced

    23/29

    A.D.

    SULT

    ANT

    estResults

    240711

    135/1

    41

    A copper plate issolder to each of theupper terminations tobuild the flat contactsurface to SULTANtransformer.

    Soldering is done at190 C with SnPbeutectic alloy toprevent melting of

    the SnAg solderinside thetermination.

    (Courtesy of P. Bruzzone, CRPP)

    Upper Termination Assembly

    Bottom Joint Assembly

  • 8/2/2019 Recent Results From ITER Conductor Tests 240711 Reduced

    24/29

    A.D.

    SULT

    ANT

    estResults

    240711

    136/141

    The bottom joint is made bysoldering a copper saddle toboth lower terminations.

    As for the upperterminations, SnPb is used at190 C to prevent melting ofthe solder inside thetermination.

    The joint assembly issandwiched between twoheaters, with aluminiummatching parts to fit the flatheaters to the roundtermination.

    After completing the

    soldering, a steel clamp isapplied and the cooling pipesare welded.

    (Courtesy ofP. Bruzzone,

    CRPP)

    Bottom Joint Assembly

    Overall Assembly (1/3)

  • 8/2/2019 Recent Results From ITER Conductor Tests 240711 Reduced

    25/29

    A.D.

    SULTANT

    estResults

    240711

    137/141

    (Courtesy of

    P. Bruzzone,

    CRPP)

    After completion of termination andjoints, the assembled conductors arebolted into a segmented steel clamp.

    Electrical insulation between clampand conductors is provided by 1-mm-thick glass-epoxy half shellsmatching the diameters of the two

    conductors. A segmented glass epoxy saddle

    piece separate the two conductors.

    Overall Assembly (1/3)

    Overall Assembly (2/3)

  • 8/2/2019 Recent Results From ITER Conductor Tests 240711 Reduced

    26/29

    A.D.

    SULTANT

    estResults

    240711

    138/141

    (Courtesy of P. Bruzzone, CRPP)

    The repulsive force between the two conductors at high field isestimated up to 1 MN/m and is reacted by M10 bolts, spaced by 50

    mm (2.5 t/bolt). The bolts are pre-loaded with only 5 Nm to prevent deformation of the

    round conductor.

    Upper Termination

    Bottom Joint

    Clamp

    Overall Assembly (2/3)

    Overall Assembly (3/3)

  • 8/2/2019 Recent Results From ITER Conductor Tests 240711 Reduced

    27/29

    A.D.

    SULTANT

    estResults

    240711

    139/141

    Upper TerminationBottom Joint

    Fully assembledsample

    seen fromBottom Joint

    (Courtesy ofP. Bruzzone,

    CRPP)

    Overall Assembly (3/3)

    Connection to TRAFO

  • 8/2/2019 Recent Results From ITER Conductor Tests 240711 Reduced

    28/29

    A.D.

    SULTANT

    estResults

    240711

    140/141

    Indium wires are deposited onto the faces of the upper terminations,which are inserted and bolted to the Trafo terminations.

    (Courtesy of

    P. Bruzzone,CRPP)

    Connection to TRAFO

    Installation in SULTAN

  • 8/2/2019 Recent Results From ITER Conductor Tests 240711 Reduced

    29/29

    A.D.

    SULTANT

    estResult

    s

    240711

    141/141

    (Courtesy of

    P. Bruzzone,CRPP)

    Finally, the TRAFO/sample assembly is inserted into SULTAN.

    Installation in SULTAN


Recommended