+ All Categories
Home > Documents > Red Earth Chapter Aug 11, 2005 - Earned Schedule - an...– Boeing Dreamliner , Lockheed Martin, US...

Red Earth Chapter Aug 11, 2005 - Earned Schedule - an...– Boeing Dreamliner , Lockheed Martin, US...

Date post: 25-Jul-2020
Category:
Upload: others
View: 1 times
Download: 0 times
Share this document with a friend
48
Earned Schedule Earned Schedule …an extension to EVM …an extension to EVM Copyright © 2005 Lipke Presented by Walt Lipke Red Earth Chapter – PMI Aug 11, 2005 [email protected]
Transcript
Page 1: Red Earth Chapter Aug 11, 2005 - Earned Schedule - an...– Boeing Dreamliner , Lockheed Martin, US State Department, Secretary of the Air Force – Several Countries – Australia,

Earned ScheduleEarned Schedule…an extension to EVM…an extension to EVM

Copyright © 2005 Lipke

Presented by Walt LipkeRed Earth Chapter – PMI

Aug 11, [email protected]

Page 2: Red Earth Chapter Aug 11, 2005 - Earned Schedule - an...– Boeing Dreamliner , Lockheed Martin, US State Department, Secretary of the Air Force – Several Countries – Australia,

2

OverviewOverview

• Introduction • Earned Value Management• Extension of EVM …Earned Schedule• Further Information

– Bridges EVM to Network Schedule• Summary

Page 3: Red Earth Chapter Aug 11, 2005 - Earned Schedule - an...– Boeing Dreamliner , Lockheed Martin, US State Department, Secretary of the Air Force – Several Countries – Australia,

Introduction Introduction

Page 4: Red Earth Chapter Aug 11, 2005 - Earned Schedule - an...– Boeing Dreamliner , Lockheed Martin, US State Department, Secretary of the Air Force – Several Countries – Australia,

4

• Created in Summer 2002• Published March 2003, The Measurable News• Australian, Kym Henderson – first adopter• Presentations made

– IPMC, CPM (2003, 2004, 2005)– Australia, UK, Japan, Sweden, Belgium

• Several Papers available (references)• “Emerging Practice” in new EVM Practice

Standard• CPM plans to create ES area on website

http://www.pmi-cpm.org/

About Earned Schedule

Page 5: Red Earth Chapter Aug 11, 2005 - Earned Schedule - an...– Boeing Dreamliner , Lockheed Martin, US State Department, Secretary of the Air Force – Several Countries – Australia,

5

• CPM 2005 keynote address– Blaise Durante, SAF Acquisition Executive– Air Force application to quarterly reviews– Incorporation into Department of Defense

schools– EVM Tool Vendor incorporation

About Earned Schedule

Page 6: Red Earth Chapter Aug 11, 2005 - Earned Schedule - an...– Boeing Dreamliner , Lockheed Martin, US State Department, Secretary of the Air Force – Several Countries – Australia,

6

• Early Adopters– EVM Instructors – PMA, Mgmt-Technologies..– Boeing Dreamliner, Lockheed Martin, US

State Department, Secretary of the Air Force– Several Countries – Australia, Belgium,

Sweden, …– Applications across weapons programs,

construction, software development, …– Range of project size from very small and

short to extremely large and long duration

About Earned Schedule

Page 7: Red Earth Chapter Aug 11, 2005 - Earned Schedule - an...– Boeing Dreamliner , Lockheed Martin, US State Department, Secretary of the Air Force – Several Countries – Australia,

Earned Value Management Earned Value Management

Page 8: Red Earth Chapter Aug 11, 2005 - Earned Schedule - an...– Boeing Dreamliner , Lockheed Martin, US State Department, Secretary of the Air Force – Several Countries – Australia,

8

What’s Necessary to Implement What’s Necessary to Implement EVM?EVM?

• Define the project– Understand the Requirements– Apply WBS & OBS– Breakdown to Tasks

• Estimate Duration & Effort• Schedule the Tasks (defines interdependencies)

• Allocate the Budgets (defines what & who)

• Create the Performance Management Baseline

Page 9: Red Earth Chapter Aug 11, 2005 - Earned Schedule - an...– Boeing Dreamliner , Lockheed Martin, US State Department, Secretary of the Air Force – Several Countries – Australia,

9

What’s Necessary to Implement What’s Necessary to Implement EVM?EVM?

FundingReserve

ScheduleR

eserve

Time Phased Planned Value

Planned Project Cost“Budget at Completion”

Total Funding Available

PlannedProject

Completion

NegotiatedCompletion

Date

Time

Cos

t

Page 10: Red Earth Chapter Aug 11, 2005 - Earned Schedule - an...– Boeing Dreamliner , Lockheed Martin, US State Department, Secretary of the Air Force – Several Countries – Australia,

10

Anything Else?Anything Else?

• Assign the Work• Level the Work/Reduce the Gaps

– If at all possible, eliminate Gaps– Gaps add expense with no benefit

• Iterate Estimate ⇔ Leveling until satisfied • Evaluate the Risk

– Estimate = 50% probable execution– Reserves = 90% probable execution

Page 11: Red Earth Chapter Aug 11, 2005 - Earned Schedule - an...– Boeing Dreamliner , Lockheed Martin, US State Department, Secretary of the Air Force – Several Countries – Australia,

11

Then What?Then What?

• Record the time-phased Cost and Earned Value

• Evaluate & Report Progress Periodically• Take Appropriate Management Action

Page 12: Red Earth Chapter Aug 11, 2005 - Earned Schedule - an...– Boeing Dreamliner , Lockheed Martin, US State Department, Secretary of the Air Force – Several Countries – Australia,

What does an EVM System What does an EVM System Look Like? Look Like?

Page 13: Red Earth Chapter Aug 11, 2005 - Earned Schedule - an...– Boeing Dreamliner , Lockheed Martin, US State Department, Secretary of the Air Force – Several Countries – Australia,

13

EVM System DiagramEVM System Diagram

WBS Dictionary

Schedule Planned Values(Budgeted Costs) Actual Costs Earned Value

Integrated Project Status(Earned Value) Reports

The concept is to align project activities defined in the WBS into boththe schedule and financial accounting and time recording systems.

Page 14: Red Earth Chapter Aug 11, 2005 - Earned Schedule - an...– Boeing Dreamliner , Lockheed Martin, US State Department, Secretary of the Air Force – Several Countries – Australia,

Evaluating Project Performance Evaluating Project Performance using EVMusing EVM

Page 15: Red Earth Chapter Aug 11, 2005 - Earned Schedule - an...– Boeing Dreamliner , Lockheed Martin, US State Department, Secretary of the Air Force – Several Countries – Australia,

15

How Do I Evaluate Performance?How Do I Evaluate Performance?

• Assess Earned Value– What Has Been Accomplished?

• Performance Versus Plan– Is the Project performing as Planned?

• Remaining Work versus Resources– Can the Project Complete within Negotiated

Cost and Completion Date?– Are Reserves Being Used?

Page 16: Red Earth Chapter Aug 11, 2005 - Earned Schedule - an...– Boeing Dreamliner , Lockheed Martin, US State Department, Secretary of the Air Force – Several Countries – Australia,

16

Project Status using EVProject Status using EV

Time

$

PVEVSPI=

ACEVCPI=

BACPV

AC

EV

SVCV

PD

PV = Planned ValueEV = Earned ValueAC = Actual CostBAC = Budget at CompletionPD = Planned Duration

Page 17: Red Earth Chapter Aug 11, 2005 - Earned Schedule - an...– Boeing Dreamliner , Lockheed Martin, US State Department, Secretary of the Air Force – Several Countries – Australia,

17

Project StatusProject Status

• Present Values of Variances or Indexes• Variances

– Cost Variance (CV)

CV = EV - AC– Schedule Variance (SV)

SV = EV - PV• Indexes

– Cost Performance Index (CPI)

CPI = EV / AC– Schedule Performance Index (SPI)

SPI = EV / PV

Page 18: Red Earth Chapter Aug 11, 2005 - Earned Schedule - an...– Boeing Dreamliner , Lockheed Martin, US State Department, Secretary of the Air Force – Several Countries – Australia,

18

Project OutcomeProject Outcome

• Prediction of Project Outcome– Trend of Periodic Values– Performance to Achieve Planned Cost

To Complete Performance Index (TCPI)

TCPI = (BAC – EV) / (BAC – AC)– Performance to Achieve Estimated Cost

TCPI = (BAC – EV) / (EAC – AC)where EAC is Estimate at Completion

Page 19: Red Earth Chapter Aug 11, 2005 - Earned Schedule - an...– Boeing Dreamliner , Lockheed Martin, US State Department, Secretary of the Air Force – Several Countries – Australia,

19

Project Outcome PredictionProject Outcome Prediction

PV

Time

Cos

t

AC EV

Cost Variance

ScheduleVariance

Cost Overrun

ScheduleSlippage

EAC

BAC

PlannedCompletion

ECD

Now

Cost and Schedule AnalysisCost and Schedule Analysis

Page 20: Red Earth Chapter Aug 11, 2005 - Earned Schedule - an...– Boeing Dreamliner , Lockheed Martin, US State Department, Secretary of the Air Force – Several Countries – Australia,

20

PredictionPrediction

• Independent Estimate at Completion (IEAC)– IEAC1 = BAC / CPI– IEAC2 = AC + (BAC – EV) / PF

where PF = Performance FactorBAC – EV = BCWR

where BCWR = Budgeted Cost for Work Remaining

• Performance Factors– CPI– SPI– wt1 ∗ CPI + wt2 ∗ SPI, where (wt1 + wt2 = 1)– CPI ∗ SPI– CPIx, a moving average over x months

Page 21: Red Earth Chapter Aug 11, 2005 - Earned Schedule - an...– Boeing Dreamliner , Lockheed Martin, US State Department, Secretary of the Air Force – Several Countries – Australia,

21

Anything Peculiar?Anything Peculiar?

• Where are the predictors for schedule? …None Exist

• Why? …Experts believe EVM cannot be used to predict schedule…Schedule indicators exhibit erratic behavior

• Then Why is SPI Used in the PFs? …Good question

Page 22: Red Earth Chapter Aug 11, 2005 - Earned Schedule - an...– Boeing Dreamliner , Lockheed Martin, US State Department, Secretary of the Air Force – Several Countries – Australia,

Earned Value Management Earned Value Management LimitationsLimitations

Page 23: Red Earth Chapter Aug 11, 2005 - Earned Schedule - an...– Boeing Dreamliner , Lockheed Martin, US State Department, Secretary of the Air Force – Several Countries – Australia,

23

EVM LimitationsEVM Limitations

• EVM is a wonderful management method– Uniquely connects cost, schedule, and

requirements– Facilitates scientific approach to project

management– Fosters project planning from historical

performance– Provides project status described by

numerical evidence

Page 24: Red Earth Chapter Aug 11, 2005 - Earned Schedule - an...– Boeing Dreamliner , Lockheed Martin, US State Department, Secretary of the Air Force – Several Countries – Australia,

24

EVM LimitationsEVM Limitations

• However, EVM has deficiencies– Schedule indicators are flawed for late

projects• EVM practitioners pay attention to Cost and

ignore Schedule data• Has caused EVM to be focused in financial

management• Schedule management is segregated

– Indicators are not directly connected to deliverables …or management action

Page 25: Red Earth Chapter Aug 11, 2005 - Earned Schedule - an...– Boeing Dreamliner , Lockheed Martin, US State Department, Secretary of the Air Force – Several Countries – Australia,

25

Extensions to EVMExtensions to EVM

• resolves schedule indicators

flaw• Concept of addresses

connection to deliverables (which is an extension of ES)

• Development of has evolved to

improved management methods

Earned Schedule

Schedule Adherence

PM indicators

Page 26: Red Earth Chapter Aug 11, 2005 - Earned Schedule - an...– Boeing Dreamliner , Lockheed Martin, US State Department, Secretary of the Air Force – Several Countries – Australia,

Earned ScheduleEarned Schedule

Page 27: Red Earth Chapter Aug 11, 2005 - Earned Schedule - an...– Boeing Dreamliner , Lockheed Martin, US State Department, Secretary of the Air Force – Several Countries – Australia,

27

• Traditional schedule EVM metrics are good at beginning of project− Show schedule performance trends

• But the metrics don’t reflect real schedule performance at end− Eventually, all “budget” will be earned as the work is

completed, no matter how late you finish• SPI improves and ends up at 1.00 at end

of project• SV improves and ends up at $0 variance

at end of project

So, what’s the problem?

Page 28: Red Earth Chapter Aug 11, 2005 - Earned Schedule - an...– Boeing Dreamliner , Lockheed Martin, US State Department, Secretary of the Air Force – Several Countries – Australia,

28

• Traditional schedule metrics lose predictive ability over the last third of the project

− Impacts schedule predictions, EAC predictions

•• Project managers don’t Project managers don’t understand schedule understand schedule performance in terms of budgetperformance in terms of budget

…Like most of us!

So, what’s the problem?

Page 29: Red Earth Chapter Aug 11, 2005 - Earned Schedule - an...– Boeing Dreamliner , Lockheed Martin, US State Department, Secretary of the Air Force – Several Countries – Australia,

29

Cost and Schedule VariancesCost and Schedule Variances

+$

-$

001 02

CV = BCWP - ACWP SV = BCWP - BCWS

Note: Project completion was scheduled for Jan 02, but completed Apr 02.

J F M A M J J A S O N D J F M A

CVSV

CV = EV - AC SV = EV - PV

Page 30: Red Earth Chapter Aug 11, 2005 - Earned Schedule - an...– Boeing Dreamliner , Lockheed Martin, US State Department, Secretary of the Air Force – Several Countries – Australia,

30

Cost and Schedule Cost and Schedule Performance IndicesPerformance Indices

0.0

0.5

1.0

1.5

2.0

J F M A M J J A S O N D J F M A

CPISPI

01 02

Note: Project completion was scheduled for Jan 02, but completed Apr 02.

PVEVSPI =

IND

EX V

ALU

E

ACEVCPI =

Page 31: Red Earth Chapter Aug 11, 2005 - Earned Schedule - an...– Boeing Dreamliner , Lockheed Martin, US State Department, Secretary of the Air Force – Several Countries – Australia,

Earned Schedule ConceptEarned Schedule Concept

Page 32: Red Earth Chapter Aug 11, 2005 - Earned Schedule - an...– Boeing Dreamliner , Lockheed Martin, US State Department, Secretary of the Air Force – Several Countries – Australia,

32

Earned Schedule ConceptEarned Schedule Concept

PV

EVSPI($) =

AT

ESSPI(t) =

$

Time

PV

EV

Projection of EVonto PV

7ATPV(May) - PV(June)

PV(May) -EV 5 ES

June of Portion May of AllES

=

+=

+=

J J JF M MA A S O N

PV EV SV($) −=

AT- ES SV(t) =

Page 33: Red Earth Chapter Aug 11, 2005 - Earned Schedule - an...– Boeing Dreamliner , Lockheed Martin, US State Department, Secretary of the Air Force – Several Countries – Australia,

33

Earned Schedule: The FormulaeEarned Schedule: The Formulae

• EScum is the:Number of completed PV time increments EV exceeds + the fraction of the incomplete PV increment

• EScum = C + I where:C = number of time increments for EV ≥ PVI = (EV – PVC) / (PVC+1 – PVC)

• ESperiod(n) = EScum(n) – EScum(n-1)= ∆EScum

Page 34: Red Earth Chapter Aug 11, 2005 - Earned Schedule - an...– Boeing Dreamliner , Lockheed Martin, US State Department, Secretary of the Air Force – Several Countries – Australia,

34

Earned ScheduleEarned Schedule: : The Schedule IndicatorsThe Schedule Indicators

• Schedule Variance (time):–– SV(t) = ESSV(t) = EScumcum –– ATATcumcum

where AT = actual time

−− SV(t)SV(t)periodperiod = = ∆∆ESEScumcum –– ∆∆ATATcumcumnormally ∆ATcum = 1

• Schedule Performance Index (time):–– SPI(t) = ESSPI(t) = EScumcum / AT/ ATcumcum

–– SPI(t)SPI(t)periodperiod = = ∆∆ESEScumcum / / ∆∆ATATcumcum

Earned Schedule: Earned Schedule: The Schedule IndicatorsThe Schedule Indicators

Page 35: Red Earth Chapter Aug 11, 2005 - Earned Schedule - an...– Boeing Dreamliner , Lockheed Martin, US State Department, Secretary of the Air Force – Several Countries – Australia,

35

Schedule Variance ComparisonSchedule Variance Comparison

-400

-300

-200

-100

0

J F M A M J J A S O N D J F M-3

-2

-1

0

0

20

40

60

80

100

J F M A M J J A S O N D J F M0

0.2

0.4

0.6

0.8

1

SV($) SV(t)

Early Finish Project

Late Finish Project

$ Mo

$ Mo

Page 36: Red Earth Chapter Aug 11, 2005 - Earned Schedule - an...– Boeing Dreamliner , Lockheed Martin, US State Department, Secretary of the Air Force – Several Countries – Australia,

36

Schedule Performance Index Schedule Performance Index ComparisonComparison

0.98

1.00

1.02

1.04

1.06

1.08

1.10

1.12

J F M A M J J A S O N D J F M

0.70

0.80

0.90

1.00

1.10

1.20

1.30

J F M A M J J A S O N D J F M

SPI($) SPI(t)

Early Finish Project

Late Finish Project

Page 37: Red Earth Chapter Aug 11, 2005 - Earned Schedule - an...– Boeing Dreamliner , Lockheed Martin, US State Department, Secretary of the Air Force – Several Countries – Australia,

37

The cumulative value of ES is found by using EV to identify in which increment of PV the cost value occurs. – Lipke

7 months gone by, but the project only has “Earned Schedule” to Month 5Which SV “Answers the mail?” $ behind or 2 months behind schedule?

$

5

Σ PV

Σ EV

Time Now

71 2 3 4 6 8 9 10

A

B

SVc

SVt

Earned Schedule :Earned Schedule : How it WorksHow it Works

Acknowledgement to Robert Handshuh and Lockheed Martin

Page 38: Red Earth Chapter Aug 11, 2005 - Earned Schedule - an...– Boeing Dreamliner , Lockheed Martin, US State Department, Secretary of the Air Force – Several Countries – Australia,

Schedule AnalysisSchedule Analysis

Page 39: Red Earth Chapter Aug 11, 2005 - Earned Schedule - an...– Boeing Dreamliner , Lockheed Martin, US State Department, Secretary of the Air Force – Several Countries – Australia,

39

Schedule Analysis with EVM?Schedule Analysis with EVM?

• The general belief is EVM cannot be used to predict schedule duration

• Most practitioners analyze schedule from the bottom up using the networked schedule ….“It is the only way possible.”– Analysis of the Schedule is overwhelming– Critical Path is used to shorten analysis

(CP is longest path of the schedule)

• Duration prediction using Earned Schedule provides a macro-method similar to the method for Cost – a significant advance in practice

Page 40: Red Earth Chapter Aug 11, 2005 - Earned Schedule - an...– Boeing Dreamliner , Lockheed Martin, US State Department, Secretary of the Air Force – Several Countries – Australia,

40

Schedule OutcomeSchedule Outcome

• Prediction of Project Schedule Outcome– Trend of Periodic SV(t) and SPI(t) Values– Performance to Achieve Planned Duration

To Complete Schedule Performance IndexTSPI = (PD – ES) / (PD – AT)

– Performance to Achieve Estimated Duration

TSPI = (PD – ES) / (ED – AT)where ED is Estimated Duration

Page 41: Red Earth Chapter Aug 11, 2005 - Earned Schedule - an...– Boeing Dreamliner , Lockheed Martin, US State Department, Secretary of the Air Force – Several Countries – Australia,

41

Schedule PredictionSchedule Prediction

• Independent Estimate at Completion (Time)– IEAC1(t) = PD / SPI(t)– IEAC2(t) = AT + (PD – ES) / PF(t)

where PF(t) = Performance Factor (Time)PD – ES = PDWR

where PDWR = Planned Duration for Work Remaining

• Performance Factors …??

Page 42: Red Earth Chapter Aug 11, 2005 - Earned Schedule - an...– Boeing Dreamliner , Lockheed Martin, US State Department, Secretary of the Air Force – Several Countries – Australia,

And There is More …And There is More …

Page 43: Red Earth Chapter Aug 11, 2005 - Earned Schedule - an...– Boeing Dreamliner , Lockheed Martin, US State Department, Secretary of the Air Force – Several Countries – Australia,

43

Earned ScheduleEarned ScheduleBridges EVM to “Real” Schedule

$$

Time

PV

BAC

PD

EV

ES AT

SV(t)

Page 44: Red Earth Chapter Aug 11, 2005 - Earned Schedule - an...– Boeing Dreamliner , Lockheed Martin, US State Department, Secretary of the Air Force – Several Countries – Australia,

44

How Can This Be Used?How Can This Be Used?

•• Tasks behindTasks behind – possibility of impediments or constraints can be identified

•• Tasks aheadTasks ahead – a likelihood of future rework can be identified

• The identification is independent from schedule efficiency

• The identification can be automated• PMs can now have a schedule analysis PMs can now have a schedule analysis tool connected to the EVM Data!!tool connected to the EVM Data!!

Page 45: Red Earth Chapter Aug 11, 2005 - Earned Schedule - an...– Boeing Dreamliner , Lockheed Martin, US State Department, Secretary of the Air Force – Several Countries – Australia,

Earned Schedule SummaryEarned Schedule Summary

Page 46: Red Earth Chapter Aug 11, 2005 - Earned Schedule - an...– Boeing Dreamliner , Lockheed Martin, US State Department, Secretary of the Air Force – Several Countries – Australia,

46

Earned Schedule SummaryEarned Schedule Summary• Derived from EVM data … only• Provides time-based schedule indicators• Indicators do not fail for late finish projects• Application is scalable up/down, just as is EVM• Schedule prediction is better than any other

EVM method presently used– SPI(t) behaves similarly to CPI– IEAC(t) = PD / SPI(t) behaves similarly to

IEAC = BAC / CPI

•• Facilitates bridging EVM to the scheduleFacilitates bridging EVM to the schedule

Page 47: Red Earth Chapter Aug 11, 2005 - Earned Schedule - an...– Boeing Dreamliner , Lockheed Martin, US State Department, Secretary of the Air Force – Several Countries – Australia,

47

Earned Schedule ReferencesEarned Schedule References

• “Schedule is Different,” The Measurable News,March & Summer 2003 [Walt Lipke]

• “Earned Schedule: A Breakthrough Extension to Earned Value Theory? A Retrospective Analysis of Real Project Data,” The Measurable News, Summer 2003 [Kym Henderson]

• “Further Developments in Earned Schedule,”The Measurable News, Spring 2004 [Kym Henderson]

• “Connecting Earned Value to the Schedule,” The Measurable News, Winter 2004 [Walt Lipke]

• “Earned Schedule in Action”, The Measurable News, Spring 2005 [Kym Henderson]

http://sydney.pmichapters-australia.org.au/Click “Education,” then “Presentations and Papers” for .pdf copies

Page 48: Red Earth Chapter Aug 11, 2005 - Earned Schedule - an...– Boeing Dreamliner , Lockheed Martin, US State Department, Secretary of the Air Force – Several Countries – Australia,

48

• Excel spreadsheet available upon request

[email protected]

• Copyright material – treat appropriately

Earned Schedule CalculatorEarned Schedule Calculator


Recommended