By Loh Chu Bian
1
REDHA INSTITUTE SEMINAR SERIESSeminar on Malaysian Land Law:Recent Development & Controversies
CONTENTS
Statutory provisions
When does the time to deliver VP start
running?
Manner of delivery VP
Conclusion
2
STATUTORY PROVISIONS
3
Governing provisions Description
Rule 11 of the Housing
Development (Control
and Licensing)
Regulations 1989
Schedule G & Schedule H for
contract of sale for the sale
and purchase of a housing
accommodation
Clause 24 of Schedule G 24 months from the date of
the Agreement
Clause 25 of Schedule H 36 months from the date of
the Agreement
What is the “Date of the Agreement”?
4
When does the time to deliver vacant
possession start running?
The change of the legal
position
5
The time to deliver vacant possession start
from the date of the payment of booking fee
Factual matrix and surrounding
circumstances
The case of Premier Green
Faber Union ought not be taken as a scientific of technical formula without having any regards to:
i. factual matrix of the case;
ii. current practices in the industry; and
iii. terms of the SPA.
6
Purchaser is bound by the statutory SPA where, based on Clauses 25(1) and 25(2)
of the SPA, time starts to run from the date of the SPA, not booking fee .
Premier Green Sdn Bhd V Tribunal Tuntutan Pembeli Rumah & Anor
Factual matrix or surrounding circumstances
7
Hoo See Sen & Anor v Public
Bank Bhd & Anor
•Appellants purchased a house for $145,000.
•Appellants paid a booking fee of $1,000 on 18.08.1982.
•SPA was signed on 18.03.1983.
•House was not completed and no delivery had taken
place. 2nd respondent was therefore liable to pay LAD
to the appellants.
Facts
•Time for delivery of vacant possession is 24 months from the date of payment of the booking fee.Decision
•SPA stated that VP to be given within 24 months from the date of payment of the booking fee.
Analysis
8
Faber Union Sdn Bhd v. Chew Nyat
Shong & Anor
9
•The purchaser bought a unit of property from the
developer and paid deposit on 17.02.1984.
•The SPA was signed on 27.06.1984.
•The developer failed to complete the property
within the stipulated time, and the purchaser sued
for LAD.
Facts
•Court relied and followed Supreme Court’sdecision in Hoo See Sen & Anor v Public Bank Bhd& Anor [1988] 2 MLJ 170 as they “find no goodreason to disagree” with the earlier decision.
•Time starts to run from the date on which thepurchaser paid the booking fee.
Judgment
The "Faber Union Rule”
“For the purpose of ascertaining the date
of delivery of VP the relevant date when
time starts to run is the date on which the
purchaser paid the booking fee and not
the date of the signing of the sale and
purchase agreement.”
10
Lim Eh Fah & Ors v. Seri Maju
Padu
11
•The first appellant bought one unit of the condominium at
RM 75,300 and deposited 10% of the purchase price to the
respondent on 17.07.1992.
•The developer failed to complete the property within the
stipulated time, and the purchaser sued for LAD.
•The respondent argued that the damages ought to be
calculated from the date the deed of assignment was
signed.
Facts
•The Court followed Faber Union and Hoo See Sen, which held that the date to take into consideration for purposes of calculating the damages on late delivery of VP is the date when the deposit was paid.
Decision
•The long period between the date the purchaser paid deposit and the date the deed of assignment was signed.
•The Court feels a need to protect the right of the purchaser.
Analysis
Lim Eh Fah - The need to
protect purchaser’s interest
“If the date of the signing of the S&P
agreement were to be taken as the
relevant date, when time started to run
for the delivery of the vacant possession,
the respondent could willy-nilly pick any
dates it favoured to execute the S&P
agreement, which would certainly
prejudice the interest of the purchaser.”
12
Faber Union Sdn Bhd v. Tribunal Tuntutan
Pembeli Rumah, Kementerian Perumahan
dan Kerajaan Tempatan & Ors
13
•Application for judicial review for an order of certiorari to
quash the award of the Tribunal. The Tribunal allowed the
claim of the 2nd – 10th respondents for LAD for late delivery of
VP under SPA.
•The SPAs were signed and VP was delivered within the time
stipulated in SPA.
•The respondents contend that notwithstanding the SPA,
based on the applicant’s brochures and representations
made by the applicant’s sales representatives, VP was to be
delivered earlier.
Facts
•The Court held that the Tribunal was right to follow the principle laid down in Faber Union and Lim Eh Fah, which held that the relevant date for the purpose of calculating the amount of damages is the date the respondents paid the deposits.
Decision
•The representation made by applicant through its brochures and sales representatives that VP could be delivered earlier than was stated in SPA; and the letter to all purchasers informing that there was a delay in completion.
Analysis
Nippon Express (M) Sdn Bhd v. CheKiang Realty Sdn Bhd & Another Appeal
14
•The appellants signed two purchase forms to purchase two
pieces of industrial land from respondent. It was agreed that
the respondent shall construct the infrastructures for the two
lands and deliver vacant possession within 30 months from
the date of the agreements.
•Subsequently, dispute arose between the parties as the
Nippon has insufficient funds to purchase both of the lands.
Facts
•The Court followed the principles laid down in Faber Union and held that the relevant date when time start to run is the date on which the purchaser paid the booking fee.
Decision
•This is not a case under HDA, but Contracts Act.Analysis
Lembaman Development Sdn
Bhd v. Ooi Lai Yin & Anor and
Other Cases
15
•The applicant, a developer of a housing project had
applied by way of a judicial review for an order of certiorari
to quash decision of the Tribunal.
•The applicant argued that there cannot be a concluded
contract on that date because the amount paid only
amounts to 1% of the purchase price.
•The respondent argued that the time start to run not from
the settlement of 10% deposit, but from the date of
payment of booking fee. Furthermore, there is a document
dated 17.02.2010 which stated “I/We have agreed to
purchase the above captioned property from the above
named vendor...”
Facts
•“…based on the aforesaid authority, the relevant date is the date when the booking fee was paid…”
Decision
Reiteration of Lim Eh Fah in
Lembaman
“The Lim Eh Fah case clearly stipulatedthat where the position otherwise,developers could arbitrarily fix any date tohave the SPA executed to the prejudiceof the purchasers. If this were to be thecase, then developers would obviouslychoose a date later in time with theintention of potentially having to bear lessdamages for late delivery of vacantpossession.”
16
Manner of delivery of vacant
possessionSc
he
du
le G
• the issuance of a certificate of completion and compliance
• water and electricity supply ready for connection
• all monies due and payable paid
• the completion of any alteration or additional work
Sc
he
du
le H
• the issuance of a certificate of completion and compliance
• water and electricity supply ready for connection
• all monies due and payable paid
• the separate strata title has been issued
• the completion of any alteration or additional work
17
Conclusion In light of the recent High Court decision in
Premier Green, the principles set out by the
Supreme Court in Faber Union is not a
scientific or technical formulae. The factual
matrix or surrounding circumstances of each
case must be taken into account.
In ascertaining the date of delivery of the VP in
an LAD claim, the developer has a reasonable
and valid legal ground to argue that time start
running from the date of the execution of the
SPA.
18
Q & A
19
Thank you
20