1
Region 8 Lower Westchester Bridge Bundle
PIN 8101.46, Contract No. D900049
Draft Request for Proposals
Informational Meeting
September 20, 2019
2
Presentation Staff
Jeff Moryl, PMO Project Manager
Mark Tiano, R8 Project Manager
George CrimiVaroli, R8 Project Manager
Mark Kruk, R8 Project Manager
3Region 8 Lower Westchester Bridge Bundle
Design-Build Project (PIN 8101.46; D900049)
Lower Westchester Bridge Bundle
PIN 8101.46, Contract No. D900049
Department’s Designated Representative for this
Procurement is:
Suzan Ibrahim
Attn: Lower Westchester Bridge Bundle
Contract Management Bureau
New York State Department of Transportation
50 Wolf Road, 6th Floor
Albany, New York 12232, USA
email: [email protected]
4Region 8 Lower Westchester Bridge Bundle
Design-Build Project (PIN 8101.46; D900049)
Agenda
Project Overview & Need
RFP Content
Project’s Goals & Scope of Work (Part 3)
General Contract Information (ITP)
Alternative Technical Concepts (ITP)
Procurement Schedule (ITP)
One-on-One Meetings (ITP)
Quality Control & Quality Assurance
Evaluation and Selection
Additional Information and Submission Guidelines
Questions and Answers
5Region 8 Lower Westchester Bridge Bundle
Design-Build Project (PIN 8101.46; D900049)
Location The project involves Design-Build services for five bridge
replacements in Westchester County
Two Bridges located in the Town of Mt. Pleasant, two bridges are
connecting the Village of Pelham to the City of Mt Vernon and the
fifth bridge is located in the Village of Mamaroneck
Village of Mamaroneck
Bridge
Town of Mt. Pleasant
Bridges
Village of Pelham/City
of Mt Vernon Bridges
6Region 8 Lower Westchester Bridge Bundle
Design-Build Project (PIN 8101.46; D900049)
Town of Mt. Pleasant Bridges:
BIN Carried Crossed Spans Existing
Bridge
Length
Bridge
Roadway
Width
Existing Type of
Bridge
5500859 Saw Mill
River Pkwy
Sawmill
River
1 27 ft 61 ft Stringer/Multi-Beam
Girder, Steel
5500839 Saw Mill
River Pkwy
Sawmill
River
1 29 ft 61 ft Stringer/Multi-Beam
Girder, Steel
Full replacement is needed because of hydraulic
vulnerability, roadway flooding and potential scour
which could lead to the failure of these bridges
7Region 8 Lower Westchester Bridge Bundle
Design-Build Project (PIN 8101.46; D900049)
Village of Pelham / City of Mt Vernon Bridges:
BIN Carried Crossed Spans Existing
Bridge
Length
Bridge
Roadway
Width
Existing Type of
Bridge
5500100 Lincoln
Ave.
Hutchinson
River
Parkway
1 63 ft 46 ft Concrete
3348300 Lincoln
Ave.Hutchinson
River
1 35 ft 44 ft Concrete
Full replacement is needed due to:
➢ Hydraulic vulnerability, roadway flooding and potential scour
which could lead to the failure of the bridge
➢Existing bridge restricts the HRP to an elevation that floods
during a 1-year storm event and a vertical clearance less than
11 feet over the parkway
8Region 8 Lower Westchester Bridge Bundle
Design-Build Project (PIN 8101.46; D900049)
Village of Mamaroneck Bridge:
BIN Carried Crossed Spans Existing
Bridge
Length
Bridge
Roadway
Width
Existing Type of
Bridge
1000040 US Route 1Mamaroneck
River
1 50 ft 53 ft Concrete Arch
Full replacement is needed because of hydraulic
vulnerability and potential scour which could lead to
the failure of the bridge.
9Region 8 Lower Westchester Bridge Bundle
Design-Build Project (PIN 8101.46; D900049)
Project Goals
Provide solutions that prevent/reduce flooding frequencies
within the project limits that compromise the public’s ability to
use the State’s infrastructure.
Ensure the safety of the traveling public;
Deliver the Project safely, on schedule and within budget.
Ensure coordination with utility owners, third parties, the
surrounding residential community, Project stakeholders and
any adjacent construction projects.
Ensure the Project is compliant with the project’s environmental
commitments and conditions.
10Region 8 Lower Westchester Bridge Bundle
Design-Build Project (PIN 8101.46; D900049)
Project Goals
Maximize the impact of the public investment project by:
❑ Providing cost-effective solutions that maximizes value over the
lifespan of the project;
❑ Sequencing construction to minimize effects on vehicular traffic
operations;
❑ Reducing future maintenance requirements;
❑ Minimizing effects on residential neighborhoods and business
communities; and
❑ Minimizing impacts on the environment.
Provide best value to the Department.
11Region 8 Lower Westchester Bridge Bundle
Design-Build Project (PIN 8101.46; D900049)
RFP Documents:
❑ Instructions to Proposers
❑ Part 1: D-B Agreement
❑ Part 2: General Provisions, Section DB 100
❑ Part 3: Project Requirements (Scope of Work)
❑ Part 4: Utility Requirements
❑ Part 5: Special Provisions
❑ Part 6: RFP Plans (Directive and Indicative)
❑ Part 7: Engineering Data
❑ Part 8: Special Specifications
❑ Part 9: The Design-Builder’s Proposal
❑ Part 10: RFP Addenda
Reference Documents: On Department’s website
(Not Part of the Contract Documents)
Request For Proposals Content
12Region 8 Lower Westchester Bridge Bundle
Design-Build Project (PIN 8101.46; D900049)
RFP Documents:
Instructions to Proposers (ITP)
• General Instructions
• Appendix A – Project Information
• Appendix B – Administrative Submittal Requirements
• Appendix C – Technical Submittal Requirements
• Appendix D – Price Proposal Submittal Requirements
• Appendix E – Forms
• Appendix F – Conflicts of Interest Policy
Request For Proposals Content
13Region 8 Lower Westchester Bridge Bundle
Design-Build Project (PIN 8101.46; D900049)
DB Agreement(Part 1)
Changes from pre D900047 Contracts – Agreement removed,
now in Part 2 DB 100
14Region 8 Lower Westchester Bridge Bundle
Design-Build Project (PIN 8101.46; D900049)
DB Section 100(Part 2)
Changes from pre D900047 Contracts
DB Section number aligned with Standard Specifications
Provisions associated with Construction Quality Control,
Construction Quality Assurance moved to Part 3
15Region 8 Lower Westchester Bridge Bundle
Design-Build Project (PIN 8101.46; D900049)
General Scope of Work(Part 3, Section 1.3)
Hutchinson River Parkway at E. Lincoln Ave.
BINs 5500100 & 3348300
16Region 8 Lower Westchester Bridge Bundle
Design-Build Project (PIN 8101.46; D900049)
General Scope of WorkHutchinson River Parkway at E. Lincoln Ave.
BINs 5500100 & 3348300
Replacement of the existing E. Lincoln Ave. bridges with a single, two
span bridge; including new foundations, substructure, superstructure
and approach slabs.
Replacement of the culvert that carries the HRP NB off-ramp (Ramp R)
over the HR (CIN 890715) to a bridge sized structure with a minimum
span of 30 feet.
Reconstruct the Hutchinson River Parkway to withstand 50-year storm
events
Replacement of existing traffic signals
17Region 8 Lower Westchester Bridge Bundle
Design-Build Project (PIN 8101.46; D900049)
General Scope of WorkHutchinson River Parkway at E. Lincoln Ave.
BINs 5500100 & 3348300
Reconstruct the Hutchinson River Parkway ramps to tie in to the
reconstructed parkway.
Reconstruct the East Lincoln Ave approaches and local streets and
intersections to tie into the newly reconstructed bridge elevations and
construction stages
Develop WZTC plan for the site.
Remediate and dispose of all asbestos containing materials.
Complete and/or coordinate all utility work outlined in Part 4.
Coordinate with the local community and municipalities to inform them of
all potential impacts and mitigations during various construction stages.
18Region 8 Lower Westchester Bridge Bundle
Design-Build Project (PIN 8101.46; D900049)
General Scope of Work(Part 3, Section 1.3)
SMRP NY Route 987D
BIN 5500839, BIN 5500859
19Region 8 Lower Westchester Bridge Bundle
Design-Build Project (PIN 8101.46; D900049)
General Scope of WorkSMRP NY Route 987D
BIN 5500839, BIN 5500859
Replacement of the existing bridges, including new
foundations, substructures, superstructures, approach
slabs, and high approaches within the existing ROW.
Reconstruct the Saw Mill River Parkway above the Q100
flood elevation
Subgrade stabilizations to prevent pavement settlement of
the Saw Mill River Parkway from approximately STA 933+50
to STA 948+50.
Replacement of existing traffic signals.
20Region 8 Lower Westchester Bridge Bundle
Design-Build Project (PIN 8101.46; D900049)
General Scope of WorkSMRP NY Route 987D
BIN 5500839, BIN 5500859
Remove an existing RCP elliptical culvert on the east side of
the Saw Mill River Parkway and replace with a graded ditch.
Develop WZTC plan for the site.
Remediate and disposal of all asbestos containing materials
Complete and/or coordinate all utility work outlined in Part 4.
Coordinate with the local community and municipalities to
inform them of all potential impacts and mitigations during
various construction stages.
21Region 8 Lower Westchester Bridge Bundle
Design-Build Project (PIN 8101.46; D900049)
General Scope of Work(Part 3, Section 1.3)
Route 1 over the Mamaroneck River
BIN 1000040
22Region 8 Lower Westchester Bridge Bundle
Design-Build Project (PIN 8101.46; D900049)
General Scope of WorkRoute 1 over the Mamaroneck River
BIN 1000040
Replacement of the existing bridge; including new foundations,
substructures, superstructures, approach slabs, and highway
approaches within the existing ROW.
Reconstruction of the park at the southeast quadrant of the
intersection of Route 1 and Mamaroneck Ave.
Replacement of Traffic Signal W-16 located at the intersection
of Route 1 and Mamaroneck Ave.
Remediate and disposal of all asbestos containing materials
Develop WZTC plan for the site.
23Region 8 Lower Westchester Bridge Bundle
Design-Build Project (PIN 8101.46; D900049)
General Scope of WorkRoute 1 over the Mamaroneck River
BIN 1000040
Complete and/or coordinate all utility work outlined in Part 4.
❑ Support 66” Sewer Main and maintain service through duration of project.
Coordinate with the local community and municipalities to inform them of all
potential impacts and mitigations during various construction stages.
Acquisition of U.S. Army Corps of Engineers permit for in-water work.
Acquisition of an Individual Section 401 Water Quality Certification and Article
25 Tidal Wetlands Permit from NYSDEC and an individual concurrence
consistency determination from NYS Department of State for in-water work.
24Region 8 Lower Westchester Bridge Bundle
Design-Build Project (PIN 8101.46; D900049)
Project Coordination (Part 3, Section 1.4)
Reconstruction of the Hutchinson Elementary School in the
Town of Pelham
25Region 8 Lower Westchester Bridge Bundle
Design-Build Project (PIN 8101.46; D900049)
Project Manager
Design Manager
Quality Manager
Resident Engineer
Lead Structural Engineer
Lead Civil Engineer
Lead Hydraulic Engineer
Lead Geotechnical Engineer
Project Superintendent
Other Personnel:
❑ Environmental Compliance Manager
❑ MWBE/Civil Rights Compliance Manager
Key Personnel (Part 3, Section 3.2)
26Region 8 Lower Westchester Bridge Bundle
Design-Build Project (PIN 8101.46; D900049)
The Department has determined that the work at all 3 sites are
NEPA Class II Categorical Exclusion. Since there is no individual
or cumulative Environmental Impact they are excluded from the
requirement to prepare an Environmental Impact Statement or
Environmental Assessment.
The Department has determined that the work on the SMRP is a
SEQRA Type II Action in accordance with 17 NYCRR, Part 15.
No further SEQRA processing is required.
Environmental Approvals(Part 3, Section 7.2)
27Region 8 Lower Westchester Bridge Bundle
Design-Build Project (PIN 8101.46; D900049)
The Department has determined that the work at the HRP and
Route 1 sites are SEQRA Non-Type II Actions in accordance with
17 NYCRR, Part 15. The Design Reports serve as the EA under
SEQRA. No further SEQRA processing is required.
It is the Design-Builder’s responsibility to obtain all environmental
permits associated with the Project.
Environmental Approvals(Part 3, Section 7.2)
28Region 8 Lower Westchester Bridge Bundle
Design-Build Project (PIN 8101.46; D900049)
The Department will own all Right-of-Way needed for the Project by the anticipated
date of availability provided in Part 3 Section 10.
Permanent Easements will be acquired from the County of Westchester at the HRP
site. Additional Temporary Easements will be acquired at the HRP and Rte. 1 sites.
ROW Maps are included in Part 7 and the properties are listed in Part 3 Section 10.
❑ Permanent and Temporary easement have projection dates
❑ Property releases for driveway reconnections or other work that is required are
the responsibility of the Design-Builder.
❑ Any ROW fencing that has been damaged or removed due to construction shall
be replaced by the Design-Builder.
❑ The Design Builder shall not enter any listed properties without written
notification from the Department.
Right-of-Way(Part 3, Section 10)
29Region 8 Lower Westchester Bridge Bundle
Design-Build Project (PIN 8101.46; D900049)
The Design-Builder shall be responsible for the acquisition and all
costs associated therewith for any temporary land or other property
required for the Design-Builder’s convenience outside the ROW
limits (i.e. staging, lay-down, access, etc.)
Right-of-Way(Part 3, Section 10)
30Region 8 Lower Westchester Bridge Bundle
Design-Build Project (PIN 8101.46; D900049)
Work Zone Traffic Control(Part 3, Section 19)
Hutchinson River Parkway at E. Lincoln Ave.
BINs 5500100 and 3348300
31Region 8 Lower Westchester Bridge Bundle
Design-Build Project (PIN 8101.46; D900049)
Work Zone Traffic ControlHutchinson River Parkway at E. Lincoln Ave.
BINs 5500100 & 3348300
Design Builder shall implement Work Zone Traffic Control and
Closures Restrictions in accordance with Section 19 of Part-3
Project Requirement.
E. Lincoln Ave
❑ Vehicular traffic shall be maintained in both directions at all times.
◼ Temporary bridge detour south of existing BINs illustrated in indicative plans
Pedestrian traffic shall be maintained through the Project area at all
times at all locations where pedestrian access currently exists.
The Design-Builder shall be responsible for developing a plan to
provide an ADA compliant route for pedestrians.
32Region 8 Lower Westchester Bridge Bundle
Design-Build Project (PIN 8101.46; D900049)
Work Zone Traffic ControlHutchinson River Parkway at E. Lincoln Ave.
BINs 5500100 & 3348300
Lane Closures will be permitted on the Hutchinson River
Parkway during non-peak hours without penalty.
Peak Hours Restricted times are defined as:
❑ 5:00 AM (0500 Hrs) to 11:00 PM (2300 Hrs), Monday through Friday
❑ No Restricted Hours on non-holiday weekends
HRP Lane Closures shall be restricted to 320 Hours Maximum
(Each Direction). Short term traffic stoppages as defined in the
RFP shall not count toward the 320 Hr. restriction.
33Region 8 Lower Westchester Bridge Bundle
Design-Build Project (PIN 8101.46; D900049)
Work Zone Traffic Control(Part 3, Section 19)
SMRP NY Route 987D
BINs 5500839 and 5500859
34Region 8 Lower Westchester Bridge Bundle
Design-Build Project (PIN 8101.46; D900049)
Work Zone Traffic ControlSMRP NY Route 987D
BINS 5500839 and 5500859
The Design-Builder shall maintain 1 lane of traffic in each
direction at all times on the SMRP
35Region 8 Lower Westchester Bridge Bundle
Design-Build Project (PIN 8101.46; D900049)
Work Zone Traffic Control(Part 3, Section 19)
Route 1 over the Mamaroneck River
BIN 1000040
36Region 8 Lower Westchester Bridge Bundle
Design-Build Project (PIN 8101.46; D900049)
Work Zone Traffic ControlRoute 1 over the Mamaroneck River
BIN 1000040
Route 1
❑ Full closure of Route 1 is permitted for a maximum duration of 10 weeks.
❑ Vehicular and pedestrian traffic shall be maintained at all times via off
site detours.
The Design-Builder shall be responsible for developing a plan to
provide an ADA compliant route for pedestrians.
❑ Design-Builder shall be responsible for upgrading any features on the
detour route that do not meet ADA standards.
37Region 8 Lower Westchester Bridge Bundle
Design-Build Project (PIN 8101.46; D900049)
Utility Coordination – Existing Utilities(Part 4)
In accordance with Part 4 – Utility Requirements, the Design-Builder is
responsible for:
❑ Verifying utility facility locations
❑ Identifying and resolving any conflicts not yet documented
❑ Coordinating with utility owners for utility relocations
❑ Providing stakeout and final layout of utility relocations
❑ Protecting existing utilities
❑ Cost to repair damages to utilities caused by the Design-Builder
❑ Informing the Department of all meetings and correspondence with
utility owners
38Region 8 Lower Westchester Bridge Bundle
Design-Build Project (PIN 8101.46; D900049)
Utility Requirements(Part 4)
Hutchinson River Parkway at E. Lincoln
Ave.
BINs 5500100 & 3348300
39Region 8 Lower Westchester Bridge Bundle
Design-Build Project (PIN 8101.46; D900049)
Utility InventoryHutchinson River Parkway at E. Lincoln Ave.
BINs 5500100 & 3348300
Aerial Communication Utilities (south side of bridge)
❑ Crown Castle
❑ Altice USA / Cablevision
❑ AT&T
❑ Extenet Systems
❑ FirstLight Fiber
❑ Zayo
Verizon Communications
❑ Abandoned underground wood conduits on the north side of the bridge.
◼ Can be removed during bridge demolition
40Region 8 Lower Westchester Bridge Bundle
Design-Build Project (PIN 8101.46; D900049)
Utility InventoryHutchinson River Parkway at E. Lincoln Ave.
BINs 5500100 & 3348300
Con Ed (Electric)
❑ Aerial lines along the south side of the E. Lincoln Ave. bridge.
❑ Oil-O-Static
◼ (2) 5” and (1) 4” conduits underneath the south sidewalk
◼ (2) 5” conduits approximately 140 LF south of the bridge crossing
underneath the HRP and Hutchinson River.
❑ Underneath the north sidewalk, there is a concrete encased duct bank.
Con Ed (Gas) has a 12” Gas Main on the north side of the
bridge
41Region 8 Lower Westchester Bridge Bundle
Design-Build Project (PIN 8101.46; D900049)
Utility InventoryHutchinson River Parkway at E. Lincoln Ave.
BINs 5500100 & 3348300
SUEZ
❑ (1) 16” diameter steel water line runs north-south under First Ave.
❑ (1) 8” diameter steel water line tees off the 16” line at the intersection of
First Ave and East Lincoln Ave and runs east under East. Lincoln Ave.
❑ According to record plans, no water lines appear to be on BINs 5500100
and 3348300.
Mt Vernon Department of Public Work
❑ 16” cast iron sewer on northbound side of the Hutchinson River Parkway
and connects to a 20” cast iron sewer at a manhole between the two
bridges. The 20” sewer line continues west to east and crosses under the
HRP and the Hutchinson River.
42Region 8 Lower Westchester Bridge Bundle
Design-Build Project (PIN 8101.46; D900049)
Utility InventoryHutchinson River Parkway at E. Lincoln Ave.
BINs 5500100 & 3348300
Westchester Department of Environmental Facilities
❑ 20” cast iron sewer on the northbound side of Hutchinson River Parkway
43Region 8 Lower Westchester Bridge Bundle
Design-Build Project (PIN 8101.46; D900049)
Utility Relocations (Performed by Others)
Hutchinson River Parkway at E. Lincoln Ave.
BINs 5500100 & 3348300
Telecommunication
❑ Crown Castle, Altice USA/Cablevision, AT&T, Extenet Systems,
FirstLight Fiber, and Zayo
Con Edison (Electric)
Con Edison (Gas)
44Region 8 Lower Westchester Bridge Bundle
Design-Build Project (PIN 8101.46; D900049)
Utility Relocations (Performed by Design-Builder)
Hutchinson River Parkway at E. Lincoln Ave.
BINs 5500100 & 3348300
Telecommunications
❑ Verizon
❑ Crown Castle / Altice USA / AT&T / Extenet Systems/
FirstLight Fiber / Zayo
Con Edison (Electric)
❑ Preserve, support, protect and maintain the (2)-5” and (1)-4” Oil-O-
Static transmission lines crossing the E. Lincoln Ave. bridge during
construction.
45Region 8 Lower Westchester Bridge Bundle
Design-Build Project (PIN 8101.46; D900049)
Utility Relocations (Performed by Design-Builder)
Hutchinson River Parkway at E. Lincoln Ave.
BINs 5500100 & 3348300
Con Edison (Natural Gas)
❑ The Design-Builder is responsible for keeping a 12” gas main in service
throughout construction and relocating it to the new structure.
Sanitary Sewer
❑ The Design-Builder is responsible for any modification or relocation of
sanitary sewers owned by Westchester County Department of
Environmental Facilities or Mt Vernon Department of Public Work.
Water
❑ The Design-Builder is responsible for any modification or relocation to
SUEZ water main.
46Region 8 Lower Westchester Bridge Bundle
Design-Build Project (PIN 8101.46; D900049)
Utility Requirements(Part 4)
Route 1 over Mamaroneck River
BIN 1000040
47Region 8 Lower Westchester Bridge Bundle
Design-Build Project (PIN 8101.46; D900049)
Utility InventoryRoute 1 over Mamaroneck River
BIN 1000040
Verizon Communications
❑ Concrete encased ductbank consisting of 16-4” wrought iron conduits
❑ Concrete encased ductbank consisting of 11-4” tile conduits.
Crown Castle
❑ 288 Fiber cable located in one conduit of the Verizon conduit system
48Region 8 Lower Westchester Bridge Bundle
Design-Build Project (PIN 8101.46; D900049)
Utility InventoryRoute 1 over Mamaroneck River
BIN 1000040
Con Ed (Electric)
❑ Concrete encased duct bank consisting of 6-4” iron conduits on west
side of bridge
❑ Concrete encased duct bank consisting of 3-4” fiber conduits on east
side of bridge
Con Ed (Gas)
❑ 12” cast iron and steel low pressure distribution main parallel to Rte. 1
❑ 20” steel high pressure main that runs parallel to Route 1 and manifolds
to 3-12” steel pipes on each side of the bridge.
49Region 8 Lower Westchester Bridge Bundle
Design-Build Project (PIN 8101.46; D900049)
Utility InventoryRoute 1 over Mamaroneck River
BIN 1000040
Westchester County Sewer
❑ 66” concrete sewer main runs parallel to Route 1 under the existing north
sidewalk. Between manholes on either side of the bridge, the sewer main
consists of a reinforced concrete structure specially constructed to span
over the river and integrate with the existing arch bridge.
Village of Mamaroneck Sewer
❑ 8” cast iron sewer main runs parallel to Route 1 hanging from the bottom
of the existing bridge arch
Westchester Joint Water Works (WJWW)
❑ 10” cast iron water main runs parallel to Route 1 that transitions to 1-8” on
either side of the bridge to cross over the arch.
50Region 8 Lower Westchester Bridge Bundle
Design-Build Project (PIN 8101.46; D900049)
Utility Relocations (Performed by Others)
Route 1 over Mamaroneck River
BIN 1000040
Telecommunications
❑ Verizon
❑ Crown Castle
Con Ed (Electric)
Con Ed (Gas)
51Region 8 Lower Westchester Bridge Bundle
Design-Build Project (PIN 8101.46; D900049)
Utility Relocations (Performed by Design-Builder)
Route 1 over Mamaroneck River
BIN 1000040
Telecommunications
❑ Verizon- Install new conduit system consisting of 16-4” conduits.
Con Edison (Electric)
❑ The Design-Builder is responsible for relocating the electric system to
the new structure.
Con Edison (Gas)
❑ The Design-Builder is responsible for installing a new 12” gas
distribution main and a 20” gas transmission main on the replacement
structure.
52Region 8 Lower Westchester Bridge Bundle
Design-Build Project (PIN 8101.46; D900049)
Utility Relocations (Performed by Design-Builder)
Route 1 over Mamaroneck River
BIN 1000040
Westchester County Sewer
❑ Preserve, protect and maintain the existing 66” county sewer structure
crossing the Mamaroneck River during construction.
❑ Sewer line to remain in service for the entirety of the contract.
Village of Mamaroneck Dept. of Public Works
❑ Connect the existing 8” Village sewer into the 66” County sewer trunk line
to the east of the existing bridge.
53Region 8 Lower Westchester Bridge Bundle
Design-Build Project (PIN 8101.46; D900049)
Utility Requirements(Part 4)
SMRP NY Route 987D
BINs 5500839 and 5500859
54Region 8 Lower Westchester Bridge Bundle
Design-Build Project (PIN 8101.46; D900049)
Utility InventorySMRP NY Route 987D
BINs 5500839 and 5500859
Westchester Dept. of Environmental Facilities
❑ 39” sanitary sewer line runs parallel to the Saw Mill River Parkway north
of Marble Avenue. The sewer line changes to 48” south of Marble
Avenue.
55Region 8 Lower Westchester Bridge Bundle
Design-Build Project (PIN 8101.46; D900049)
There are no anticipated utility relocations required by others
for BIN 5500839 & BIN 5500859 Saw Mill River Parkway
Site.
Utility Relocations (Performed by Others)
SMRP NY Route 987D
BINs 5500839 and 5500859
56Region 8 Lower Westchester Bridge Bundle
Design-Build Project (PIN 8101.46; D900049)
There are no anticipated utility relocations required by the
Design-Builder for the Saw Mill River Parkway site.
The Design-Builder shall be responsible for any relocations
caused by their Design Solution.
Utility Relocations (Performed by Design-Builder)
SMRP NY Route 987D
BINs 5500839 and 5500859
57Region 8 Lower Westchester Bridge Bundle
Design-Build Project (PIN 8101.46; D900049)
4.2.2 Utility Coordination Manager
The Design-Builder shall utilize a single dedicated person responsible for managing
all utility coordination. This person shall be referred to as the Utility Coordination
Manager. The Design-Builder’s Utility Coordination Manager shall be responsible for
managing all utility coordination.
Utility Coordinator Roles and Responsibilities(Part 4 – Section 4.2.2)
58Region 8 Lower Westchester Bridge Bundle
Design-Build Project (PIN 8101.46; D900049)
• Primary Shift: The DB is required to furnish no less than 5 Full Time Construction Inspectors,
FTCI, (not including the Resident Engineer or the Office Engineer). Upon commencement of the
project (NTP), it is understood that the FTCIs will be logically increased to the inspection staff
incrementally consistent with the project’s schedule. The DB shall ensure adequate inspection
staff is present on site, no less than two weeks prior to the need for the additional FTCI staff
persons to allow for advance study and familiarization with the project. In any case, the 10 FTCI
staff shall be on site for deployment no later than 180 calendar days from NTP. Subsequent to
achieving the project substantial completion, as defined by the contract, the DB firm may similarly
ramp down the inspection staff to align with the work remaining to complete the project and
consistent with the project schedule, with the written approval of the Department’s Project
Manager. During project operations, the number of FTCI should be consistent with the Design
Builder’s planned operations and Table “Construction Inspection Requirements”.
• Secondary or Multiple Shift: In the event the DB elects to perform work in Secondary or
Multiple shifts, the operations occurring during the secondary or multiple shift shall be staffed at
the same staffing level pattern as the primary shift operations.
Quality Control and Construction Inspection
Requirements(Part 5)
59Region 8 Lower Westchester Bridge Bundle
Design-Build Project (PIN 8101.46; D900049)
Notes and Plans Sheets are included for all 3 sites.
Plans for Harbour Island Park are included.
Typical Sections are forthcoming.
Directive Plans(Part 6)
60Region 8 Lower Westchester Bridge Bundle
Design-Build Project (PIN 8101.46; D900049)
Indicative Plans are forthcoming which detail preliminary design of
the Preferred Solutions as stated in the Design Reports. Will
include plans and typical sections.
Indicative Plans(Part 6)
61Region 8 Lower Westchester Bridge Bundle
Design-Build Project (PIN 8101.46; D900049)
Changes from Draft to Final RFP
Ongoing Activities
❑ ITP – Form SCD
❑ Part 4 Appendix C – Executed HC 140s
❑ Part 7 OCMC Permit for HRP
62Region 8 Lower Westchester Bridge Bundle
Design-Build Project (PIN 8101.46; D900049)
General Contract Information&
Instructions to Proposers (ITP)
63Region 8 Lower Westchester Bridge Bundle
Design-Build Project (PIN 8101.46; D900049)
General Contract Information
Lump Sum Design-Build Contract
Best Value Selection Process (50% Price, 50% Quality)
Project Completion Date shall be the earlier of:
October 14, 2022 or
The number of days past NTP proposed by the successful Proposer on
Form SCD (ITP Appendix E)
Escrow Submission of Bid Documents for Successful Proposer
The Department has determined, through a due diligence study, that there
is a public benefit to implementing a Project Labor Agreement for this
project. The Department is in the process of preparing an Agreement and
obtaining signatures from the appropriate trade unions.
Any provision in the RFP inconsistent with the provisions of an approved PLA
shall be superseded by the PLA to the greatest extent permitted by federal or
state law.
64Region 8 Lower Westchester Bridge Bundle
Design-Build Project (PIN 8101.46; D900049)
General Contract Information
Liquidated Damages will be assessed for:
Failure to achieve Project Completion by the Project Completion Date (as
determined by the number of calendar days after NTP indicated in Table
SCD-1 on Form SCD)
65Region 8 Lower Westchester Bridge Bundle
Design-Build Project (PIN 8101.46; D900049)
General Contract Information
A Schedule of Prices and a Work Payment Schedule are provided in the RFP.
❑ Schedule of Prices (Form SP)
◼ Construction Work
◼ Design Services
◼ Construction Inspection Services
◼ Quality Control Services (Material Testing)
◼ Utility Work
◼ Force Account Work ($5,000,000)
◼ Site Mobilization - % of Construction + Force Account (4% max)
66Region 8 Lower Westchester Bridge Bundle
Design-Build Project (PIN 8101.46; D900049)
General Contract Information
❑ Work Payment Schedule (Form WPS)
◼ Breakdown of Construction Work Items
◼ Input by Proposer (100% max)
◼ Construction Progress Payments subject to DB 109-01 A and 109-01 B
67Region 8 Lower Westchester Bridge Bundle
Design-Build Project (PIN 8101.46; D900049)
Contract Information
Stipend to Unsuccessful Proposers
❑ 50% of Qualified Costs, $250K max
Must satisfy criteria in ITP General Instructions:
❑ Pass all Pass/Fail Factors
❑ Achieve at least 60 points on Quality Factors
❑ Proposal must be competitive and reasonable
❑ Proposal was not selected by the Department as providing the
Best Value
There is a Buy America Clause
There is an Iran Divestment Act Clause
There is a DBE Participation Goal of 14%
Environmental and construction related permits by Design-Builder
68Region 8 Lower Westchester Bridge Bundle
Design-Build Project (PIN 8101.46; D900049)
ATCs
Alternative Technical Concepts (ATCs) are proposals from
the Proposers to design and construct the Project in a manner
that is different from the Contract Requirements and which:
❑ are submitted to the Department for review, consideration and
approval prior to Proposal submittal;
❑ have significant savings in time, and/or reduction of traffic impacts,
and/or community disruption, and/or project costs, and/or
environmental impacts, and/or other beneficial impacts to Project
parameters; and
❑ offer, in the Department’s judgment, an equal or superior Project.
69Region 8 Lower Westchester Bridge Bundle
Design-Build Project (PIN 8101.46; D900049)
ATCs
Proposers may submit on a confidential basis any number of ATCs for
the Department’s approval using Form ATC.
The Department may provide ‘Conditional Approval’ of an ATC.
The Design-Builder is solely responsible for obtaining approvals from
any local municipality, public agency or permit issuing agency for ATC
concepts which would affect their facilities, operations or issued
permit.
November 25, 2019 is the final date to submit ATCs for consideration
and December 13, 2019 is the final date for Proposers to respond to
Conditional Approval of ATCs.
70Region 8 Lower Westchester Bridge Bundle
Design-Build Project (PIN 8101.46; D900049)
Anticipated Procurement Schedule
Activity Due Date
Draft RFP Informational Meeting September 20, 2019
Final RFP to Shortlisted Firms October 4, 2019
Date Proposers may start submitting ATCs for review October 7, 2019
Proposal period one-on-one meetings with all Proposers, specific dates to be
determined. October 16, 2019 to November 14, 2019
Final date for Proposers to submit ATC’s for review November 25, 2019
Final date for Department’s responses to ATCs submitted for review December 9, 2019
Final date for receipt of Proposer questions December 9, 2019
Final Date for proposers to respond to conditional approval of ATC’s December 13, 2019
Issue Date for Final Addendum and/or answers to Proposer questions December 18, 2019
Proposal Due January 8, 2020
Post Proposal meetings (if required) January 22-23, 2020
Selection of Best Value February 12, 2020
Contract Award April, 2020
Notice to Proceed April, 2020
71Region 8 Lower Westchester Bridge Bundle
Design-Build Project (PIN 8101.46; D900049)
One-On-One Meetings
One-On-One Meetings: At least three meetings will be offered to
each Proposer, Dates have been set aside for:
❑ October 16-17; October 29-30; November 13-14, 2019
❑ Note: First meeting will be 2 hours, successive meetings will be 1-1/2
The Department reserves the right to disclose to all Proposers
any issues raised during the meetings that may materially affect
the project.
The Department will not disclose information pertaining to an
individual Proposer’s technical concepts, proposal or ATCs.
Additional One-on-One Meetings may be held if required to review
ATCs, or if the Department believes it is warranted.
72Region 8 Lower Westchester Bridge Bundle
Design-Build Project (PIN 8101.46; D900049)
Quality Control is the Design-Builder’s responsibility.
The Design-Builder shall appoint a QC Manager responsible for QC
Plans for both Design and Construction.
Design QC shall be the Design-Builder’s responsibility and shall be
performed in accordance with the QC Plan.
The QC Plan is a living document and will be further developed and
updated throughout the Project, as described in RFP Part 3.
Construction Inspection shall be performed by an Independent
Engineering Firm (hired by the Design-Builder).
Materials Testing shall be performed by an Independent Materials
Testing Firm or Laboratory (hired by the Design-Builder).
Offsite Plant Quality Control will be performed by the Department.
Quality Control (QC)(Part 3 Appendices)
73Region 8 Lower Westchester Bridge Bundle
Design-Build Project (PIN 8101.46; D900049)
Design and Construction Quality Assurance is the Department’s
responsibility.
The Department may perform QA on any of the Design-Builder’s
design and construction activities.
The Department will establish and maintain its own staff, or utilize an
independent consultant, to perform QA of the Design-Builder’s design
and construction work.
Offsite plant Quality Assurance will be performed by the Department.
RFP Part 3 describes in detail the Department’s QA role for the Project.
Quality Assurance (QA)(Part 3 Appendices)
74Region 8 Lower Westchester Bridge Bundle
Design-Build Project (PIN 8101.46; D900049)
Pass/Fail Evaluation Factors
Legal – Financial – Administrative – DBE Compliance - Price Proposal (Bond/Conformance)
Quality Evaluation Factors (50%)
Design-Build Organization and Process (25 Points)
◼ Key Personnel (15 points)
◼ Overall Design-Build Team Organization (10 points)
Design-Build Approach to the Project (45 points)
◼ Project Understanding (5 points)
◼ Design Solutions (25 points)
◼ Construction Approach (Means and Methods) (15 points)
Schedule (30 points)
◼ CPM Schedule with Gantt Chart (10 points)
◼ Project Completion / Duration Calendar Days (20 points)
Price (50%)
Design-Builder
must obtain a
minimum score of
60 points on
Quality Evaluation
Factors
Best Value Selection and Evaluation(ITP, Appendix A)
75Region 8 Lower Westchester Bridge Bundle
Design-Build Project (PIN 8101.46; D900049)
Proposers shall comply with all formatting requirements stated in the ITP in
Appendices A, B, C, and D, including page size, section length, and font size. In
addition, all Proposers shall comply with the following format requirements:
The inside and outside surfaces of all binders, and both sides of all dividers,
shall be solid and shall contain only text; no pictures, renderings or graphics
shall be included.
All narrative pages, Initial Management Plan components and forms shall
contain text only and shall contain no pictures, renderings or graphics.
Proposal Format Compliance(ITP Appendices)
76Region 8 Lower Westchester Bridge Bundle
Design-Build Project (PIN 8101.46; D900049)
If requested in the ITP, photographs, visualizations, and/or renderings shall not
contain any text, other than text limited to feature labels.
All drawings submitted as part of the Proposal shall include no narratives or
text other than notes or call-outs which would typically be included on design
drawings.
External web links are not to included anywhere in the Proposal.
Failure by a Proposer to follow the formatting requirements stated in the ITP
will result in the particular page(s) being deleted from the Proposal before
technical evaluation.
A Proposal may receive a lower score as a result of any pages removed.
Proposal Format Compliance(ITP Appendices)
77Region 8 Lower Westchester Bridge Bundle
Design-Build Project (PIN 8101.46; D900049)
Submit ALL Forms required:
❑ Do not alter any Form unless indicated on the Form.
❑ Do not add any appendices or attachments to the Forms.
❑ Do not include photographs or illustrations unless specifically indicated.
❑ Do not submit the following with Proposal:
◼ Form SA (Stipend Agreement) => 20 Days after Proposal Due Date
◼ Form BDEA (Bid Document Escrow Agreement)
◼ PAB (Payment Bond (Labor and Material Bond))
◼ PEB (Performance Bond (Faithful Performance Bond))
Proposal Format Compliance(ITP Appendices)
78Region 8 Lower Westchester Bridge Bundle
Design-Build Project (PIN 8101.46; D900049)
Responses to Proposer Questions will be posted on the Department’s
Project Web Site.
Reference Documents are Posted on the Department’s Project Web Site:
https://www.dot.ny.gov/main/business-center/designbuildproject49
Reference Documents include but not limited to:
Final Design Approval Reports
Bridge Inspection Reports
Record Plans of Roadways and Structures within the Project Limits
Subsurface Exploration Boring Logs
Additional Information
79Region 8 Lower Westchester Bridge Bundle
Design-Build Project (PIN 8101.46; D900049)
Lower Westchester Bridge Bundle
PIN 8101.46, Contract No. D900049
Department’s Designated Representative for this
Procurement is:
Suzan Ibrahim
Attn: Lower Westchester Bridge Bundle
Contract Management Bureau
New York State Department of Transportation
50 Wolf Road, 6th Floor
Albany, New York 12232, USA
email: [email protected]
80Region 8 Lower Westchester Bridge Bundle
Design-Build Project (PIN 8101.46; D900049)
Questions ?