+ All Categories
Home > Documents > Regulatory Challenges in Reforming Indian Power System

Regulatory Challenges in Reforming Indian Power System

Date post: 10-Feb-2016
Category:
Upload: senwe
View: 28 times
Download: 0 times
Share this document with a friend
Description:
Regulatory Challenges in Reforming Indian Power System. by Vijay L Sonavane Member, MERC Mumbai NPTI Nagpur , Date: 25 th FEB 2011 . Reform Agenda… . Indian Power System Open access in T&D Parallel Licensing Cross Subsidy Reduction . Edison’s Dream . - PowerPoint PPT Presentation
82
Regulatory Challenges in Reforming Indian Power System by Vijay L Sonavane Member, MERC Mumbai NPTI Nagpur , Date: 25 th FEB 2011
Transcript
Page 1: Regulatory Challenges in  Reforming  Indian Power System

Regulatory Challenges in Reforming

Indian Power System

byVijay L Sonavane

Member, MERC Mumbai NPTI Nagpur , Date: 25th FEB 2011

Page 2: Regulatory Challenges in  Reforming  Indian Power System

Reform Agenda… • Indian Power System• Open access in T&D • Parallel Licensing • Cross Subsidy Reduction

Page 3: Regulatory Challenges in  Reforming  Indian Power System

Edison’s Dream

“We will make Electricity so cheap that only the rich

will burn candles”

- Thomas Alva Edison(1847 - 1931)

3

Page 4: Regulatory Challenges in  Reforming  Indian Power System

History of Indian Power System 18th Nov.1897 first generating station in India (Asia)

commissioned at Sidrapong (Darjeeling) .

Installed capacity on 15th Aug 1947: 1362 MW.

Electricity: Prime mover for economic

development, Industrial & Green Revolution.

Installed capacity :1,67,077 MW (30 /11/2010)• AI Energy & Peak Load Shortages: 11.1% & 11.9% • Per capita: 734 U/year (FY 08) Target: 1000 U (Mar 12)

Page 5: Regulatory Challenges in  Reforming  Indian Power System

Indian Power Sector • Total No. of consumers: Over 130 million.• Revenue: Rs 350,000 CR/year • T&D losses: 18 to 62% in various states.• 35% of Indians do not have access to Electricity.

• Use: Industries: 42%, Domestic: 25%, AG: 24%, RLY: 3%• As on 31/10/10: 5,08,992 villages electrified ( 85.7%)• 1,68,33,575 Nos (85.2%) of AG pumps energized

• India is 6th Largest electricity utilizing country next to USA, China, Japan, UK & France. By 2014 we will be fourth

5

Page 6: Regulatory Challenges in  Reforming  Indian Power System

Indian Power System – Challenges in Transition Stage

• To Reduce Distribution Losses.

• Reduce Shortage of power by

effective Load Management .

•Promote and Develop Competition

• Promote DSM/EE activities.

•Promote RE Generation

6

Page 7: Regulatory Challenges in  Reforming  Indian Power System

Highlights of Indian Gen Sector

• Coal/ Gas/ Diesel: 108,362 MW : (64.9%)• Nuclear: 4,560 MW : ( 2.7%)• Hydro: 37367 : (22.4%)• RES : 16,799 : (10.0%)• Total: 1,67,077 MW (MU: 8,30,757 in FY 2010-11)

• AI PLF: 2009-10: 77.48%• Coal: 2009-10: 341 MT • Growth: 31/03/85: 42,584 31/03/97: 85,795 MW 31/03/2007: 132,329 MW 31/11/2010: 167,077 MW

Page 8: Regulatory Challenges in  Reforming  Indian Power System

Renewable Generation RE Source: Wind/ Solar/ Bio-Gas/ Small Hydro (Mini, Micro Run

Of River Projects)/ Baggase/ Bio mass: Infirm sources

Issues in RE Sources: • Site Selection/ • Grid Connectivity / Storage• Non Schedulable resource/ • Low Plant load factor

Satara, Maharashtra

Page 9: Regulatory Challenges in  Reforming  Indian Power System

AI Transmission Network… • 400 KV Lines: 102,166 Km, 220 KV Lines: 196,355 KM• 400KV S/S: 124,676 MVA 220KV: 196,355 KM• 765KV Lines: 3910 KM & S/S: 4500 MVA

• EHV: 765 KV/ 400KV/ 220 KV/ 132 KV/ 110 KV /(+/-) 500 KV HVDC

• In 11th Plan JV/Private Sector Transmission projects (1200KV/765 /400/ 220KV) are being developed

• During 2009-10, 765KV Seoni-Bina S/s line & second circuit of Bina- Gwailor have been commissioned.

Page 10: Regulatory Challenges in  Reforming  Indian Power System

Evolution of National Grid

• State grids ( 1948+)• Regional Grids (1970+)• National Grid (2003+)

What are the advantages of Interconnections?• Higher Moment of Inertia (Stable system)• Higher Power Number • Mumbai (60MW/HZ) /Maharashtra (400MW/HZ)/

Western Region (800 MW/HZ)/ India (2100 MW/HZ)

Page 11: Regulatory Challenges in  Reforming  Indian Power System

Regional Grids of India

Merging of markets along with synchronization of regions

NEW Grid

SouthGrid

South

West

NorthEast

Northeast

Five Regional GridsFive Frequencies

October 1991East and Northeast

synchronized

March 2003West synchronized

With East & Northeast

August 2006North synchronized

With Central Grid

Central Grid

11

Page 12: Regulatory Challenges in  Reforming  Indian Power System

1 2 3 4 5 6 7 8 910

11

12

13

14

15

16

17

18

19

20

21

22

23

24

BASE LOAD

BASE LOAD

MW

Base Load – Managed through Long Term PPA’s

Daily Variations – Managed through 1) Day ahead Power Exchange or 2) UI Balancing

Seasonal Variations – Managed through Short Term trades, by1) Traders, 2) Bilateral Contracts or 3) Banking Arrangements

Maharashtra Load Curve and Demand Management 141210864

Hours

12

Page 13: Regulatory Challenges in  Reforming  Indian Power System

Mumbai Load curve as on 10/05/2010

1:002:00

3:004:00

5:006:00

7:008:00

9:0010:00

11:0012:00

13:0014:00

15:0016:00

17:0018:00

19:0020:00

21:0022:00

23:0024:00

100200300400500600700800900

100011001200130014001500160017001800190020002100220023002400250026002700280029003000 REL-D

TPC-D

BEST

Mumbai

TIME BLOCK

DEM

AND

in M

W

13

Page 14: Regulatory Challenges in  Reforming  Indian Power System

14

Functions of Distribution Utilities

To Give

– Good quality supply / services

– Continuous Supply

– At an Affordable Cost

Issues

– We cannot store electricity in bulk

– Control switches with consumers

– Payment Afterwards

Page 15: Regulatory Challenges in  Reforming  Indian Power System

Main issues with Distribution System

• Distribution Losses: Technical ( I Square R) & Non-Technical (Commercial) losses (Theft, faulty/ Slow meters)

• Solution to Theft: Areal Bunched Conductors (ABC)/ High Voltage Distribution Systems (HVDS)

• High Distribution Transformer failure rate (13.4%)

• Consumer Metering:Automated Meter Reading (AMR) systemTime of Day (TOD)/ Time of Use (TOU) metering

• Challenge: Demand Side Management (DSM)/ Energy Conservation

Page 16: Regulatory Challenges in  Reforming  Indian Power System

Aggregate Revenue Requirement Sr.No

.

Paerticulars Approved ARR (Rs Cr)

% of total ARR

1 Power Purchase 24213 76.3%

2 Employee Expenses 2591 8.2%

3 A&G and R&M 772 2.4%

4 Depreciation 458 1.4%

56

InterestOther Exp

640661

2.0%2.1%

7 Transmission charges 1879 5.91

78

Total expensesROE

31214533

98.3%1.7%

9 Total ARR 31747 100.0%

10 Non-Tariff Income 1450

11 ARR from Tariff 30297

Page 17: Regulatory Challenges in  Reforming  Indian Power System

17

Tariff Setting• Consider a Utility purchasing 8000 MUs from Genco

– (Rs 1.50 P.U.) & 2000 MUs from Traders (Rs 4.0 P.U.)

• P.P. Cost = 8000 * 1.5 + 2000 * 4 = 1200 + 800 = Rs. 2000 Cr. for 10,000 MU

– i.e. P.U. input cost = Rs 2 / Unit

• Consider the Utility has Fixed Expenditure = Rs. 800 Cr.– i.e. Total Input Cost = Rs. 2800 Cr. for 10000 MU input– (i.e. Per unit Cost = Rs 2.80)

Page 18: Regulatory Challenges in  Reforming  Indian Power System

18

• If Distribution loss is 30% ,One unit of Input means, 0.7 Unit Sold.• i.e. Rs 2.80 have to be recovered from 0.7 Unit sale• i.e. P.U. Sale Cost = 2.8 / 0.7 = Rs 4 P.U. at consumer end

• If the losses are 20%, i.e. 0.8 P.U. sold per unit Input• i.e. P.U. Sale Cost = 2.8 / 0.8 = Rs 3.50

• If Losses are 40%, i.e. 0.6 unit sold per unit Input• P.U Sale Cost = 2.8 / 0.6 = Rs 4.58

• Distribution loss is Integral Component of Retail Tariff

Tariff Setting...

Page 19: Regulatory Challenges in  Reforming  Indian Power System

What is Success?“

“In 1988 Tendulkar failed in English in 10th standard

Now, in 2011 for 10th Standard English book

the first lesson is about Sachin Tendulkar…..”

This is Real SUCCESS!!!!

Page 20: Regulatory Challenges in  Reforming  Indian Power System

Open Access, Parallel Licensee

Page 21: Regulatory Challenges in  Reforming  Indian Power System

Electricity Act 2003 Mandate for Reform

• Promoting competition/ Protecting consumers’ interest / Providing power to All

• Consolidation of Laws in G/T/D/ Trading• Gen is decentralized but Regulatory freedom

needed for accessing the market• Transmission: Licensed activity. Regulatory

framework necessary for competitive & transparent operation

Page 22: Regulatory Challenges in  Reforming  Indian Power System

Buying/Selling commodity named Electricity…..

• Which cannot be seen, counted in numbers, or measured in Kilos, liters or meters

• Which cannot be put into container with forwarding address, on a particular truck taking a particular route, but flows as per laws of Physics

• Which cannot be stored and whose availability and cost keep changing widely

Page 23: Regulatory Challenges in  Reforming  Indian Power System

Buying /Selling of Electricity….• Which intermingles with other supplies in an

inevitable pool & cannot have an owner’s name tag

• Buyer has no control over what seller supplies &seller has no control over what buyer draws from the pool & the two may not match all time

• Thus, it is necessary to have mechanism for commercial handling of mismatches

Page 24: Regulatory Challenges in  Reforming  Indian Power System

Solution ????• Power trading has to be notional : the buyer

has to pay the agreed amount to the supplier for scheduled quantum of power

• Payment for variations from the schedule through a common mechanism called UI (Unscheduled Interchange)

Page 25: Regulatory Challenges in  Reforming  Indian Power System

Drawl from CS 2500 MW

Gen 10000 MW

State Load 12500 MW

CS Schedule 2000 MW

CS UI 500 MW

If System frequency is 49.5 Hz, the State has to pay ar Rs 8.73 PU is Rs.10,18,250 in 15 minutes! (500 MW: Rs. 1.018M)

Cost of 12000 MW scheduled generation for 15Min at Rs 3 PU is

Rs. 12000/4 X 3 i.e. 90,00,000 in 15 minutes! (12000 MW: Rs.9.0 M)

(For only 4% Energy: Price is over 10% : Avoid overdrawing)

Concept of Unscheduled Interchange

25

Page 26: Regulatory Challenges in  Reforming  Indian Power System

0.000

2.000

4.000

6.000

8.000

10.000

12.000

14.000

16.000

18.000

20.000Revised UI Curve w.e.f 3rd May 2010

Freq in Hzs

UI rate 15.50 paisa for each step of 0.02 Hz.

UI rate 47 paisa for each step of 0.02 Hz.

50.20 Hz.

Rs.12.22

Rs.17.46

UI rate 15.50 paisa for each step of 0.02 Hz.

UI rate 47 paisa for each step of 0.02 Hz.

50.20 Hz.

49.70 Hz.

49.50 Hz.

Rs.12.22

Rs.17.46

UI rate 15.50 paisa for each step of 0.02 Hz.

UI rate 47 paisa for each step of 0.02 Hz.

50.20 Hz.

Rs.12.22

Rs.17.46

UI rate 15.50 paisa for each step of 0.02 Hz.

UI rate 47 paisa for each step of 0.02 Hz.

50.20 Hz.

.

49.50 Hz.

49.20 Hz.Rs.3.88

Rs.17.46

Rs.8.73

UI rate in Paisa

26

Page 27: Regulatory Challenges in  Reforming  Indian Power System

Electricity Markets • More private sector participation needed• Need to unbundle supply system & start

multi-seller, multi-buyer model • Basic need: consensus building in various

stake holders Competition:• Open access (using existing DL’s wires & paying

wheeling charges)• Parallel Licensing (New DL to lay the network &

give supply) We should see competition as an opportunity &

not as a threat

Page 28: Regulatory Challenges in  Reforming  Indian Power System

Open Access • OA means that customer can pick & choose their supplier &

any supplier can use existing lines to reach any customer.

• On payment of wheeling charges, CS surcharge & additional surcharge wherever applicable. (S 42(2), 42 (4))

• Open access means enabling Sale/ purchase of energy between two parties utilizing the system of an (in-between) third party & not blocking it on any unreasonable grounds.

• Implications: Competitors may cherry pick high revenue customers but Cross Subsidy & Stand by issues

Page 29: Regulatory Challenges in  Reforming  Indian Power System

More clear definition

• Open access means enabling non-discriminatory Sale/ purchase of electrical energy between two parties

utilizing the system of an (in-between) third party

& not blocking it on any unreasonable grounds

Page 30: Regulatory Challenges in  Reforming  Indian Power System

Example of OA

Tata Power wants to sell 100 MW to Discom A in Andhra

• TPC & Discom A agree on terms & conditions of sale

• TPC to get consent from MSETCL /STU & no objection from SLDC Kalwa

• Discom A to get consent from APTRANSCO and APSTU and no objection from AP SLDC

Page 31: Regulatory Challenges in  Reforming  Indian Power System

Example (contd)

• Both SLDCs after ascertaining transmission adequacy agree to arrange for necessary metering, scheduling, EA, UI settlement

• All concerned to have a common understanding about treatment/ sharing of transmission losses, levy of transmission/ wheeling charges for use of intra-state & inter-state system

Page 32: Regulatory Challenges in  Reforming  Indian Power System

OA REGULATIONS OF MERC

• MERC has formulated two Regulations: Transmission OA 2005 & Distribution OA , 2005

• Distribution OA Regulations permit consumers with contract demand >= 1 MVA are eligible to avail OA from by 1st April 2007

• Draft for OA Regulations were finalized & uploaded on MERC website for comments by stakeholders & consumers up to 11th Feb.2011.Final Version is getting ready

Page 33: Regulatory Challenges in  Reforming  Indian Power System

Categorization of OA Customers

Long term Open Access customers• OA for a period >= 12 years but not exceeding 25 years

Medium term Open Access customers OA for a period < 3 years & > 3 months Short -term Open Access customer• OA for a period up to one month, at a time.

“Limited Short term OA customer” means consumer, who has a supply agreement with the DL & avails OA only during pre-scheduled LS period”

Page 34: Regulatory Challenges in  Reforming  Indian Power System

Open Access: issues

• Cross subsidy: To compensate full/partial revenue loss of existing DL

• Apportionment of losses• Shortage scenario: load shedding• State of Art Energy metering & EA system

Despite none of these issues, most countries took over ten years to implement full OA

Page 35: Regulatory Challenges in  Reforming  Indian Power System

Charges for Open Access Customer

Charges payable by OA customers:• Transmission charges & Wheeling charges• Cross Subsidy Surcharge (CSS)• Additional Surcharge (ASC)• Standby Support charges (SBSC)• Scheduling & System Operation Charges

payable to SLDC

Page 36: Regulatory Challenges in  Reforming  Indian Power System

Why Cross Subsidy Surcharge(CSS)?

• In current tariff orders, CSS & ASC are identified as NIL from 1st April 2007 (due to negative values)

• Study Committee re-examined approach towards CSS & ASC.

• By identifying a value for CSS & ASC, prospective OA applicant would share burden of Cross Subsidy.

Page 37: Regulatory Challenges in  Reforming  Indian Power System

Cross Subsidy Surcharge NTP formula

S = T – [ C (1+ L / 100) + D ]

• S: Surcharge • T: Tariff payable by relevant category of consumers; • C: Weighted average cost of PP of top 5% at the margin excluding

liquid fuel based Gen. & renewable power • D: Wheeling charge • L: % System Losses for applicable voltage level

( In case the formula gives negative value of surcharge, ‘C’ in the formula needs to be redefined (????))

Page 38: Regulatory Challenges in  Reforming  Indian Power System

Cross subsidy surcharge

• Surcharge formula (NTP)S = T – [C (1+L/100) + D]

C Costliest long term contracted PP cost excluding liquid fuel generation may be considered

Example:If C Rs.4.26 PU (for costliest LTPP) then S = 67 PS/Unit for IND consumer @ 33KV & above

Page 39: Regulatory Challenges in  Reforming  Indian Power System

OA CSS IN Various States

State

Punjab

Haryana

Uttrakhand

Himachal Pradesh

Madhya Pradesh

Rajasthan

Cross Subsidiary in Paise/Unit

0

72

38

20

84 at 66/33 KV and 62 at 132 KV

13

Page 40: Regulatory Challenges in  Reforming  Indian Power System

Additional Surcharge: Stranded costs

• OA customer, receiving supply from a person other than DL of his area of supply, shall pay to the DL, an additional surcharge, in addition to wheeling charges & CSS, to meet out the fixed cost of such DL, arising out of his obligation to supply as provided under Section 42(4) of EA 2003.

• Additional surcharge shall become applicable only if, the obligation of DL in terms of LTPP commitments has been stranded.

• Fixed costs related to network assets are recovered through wheeling charges.

Page 41: Regulatory Challenges in  Reforming  Indian Power System

Additional Surcharge (ASC)

• DL should be required to demonstrate stranded cost, if any, every six months to SERC.

• On being satisfied, SERC would determine additional surcharge (Ps/KWH)

• Such ASC should be levied only on new open access applicants.

• No ASC for captive GEN plant for carrying electricity to destination of his own use.

Page 42: Regulatory Challenges in  Reforming  Indian Power System

Treatment of S/B Supply (Our Views)

• In case consumer meets part of his demand through OA & if the supplier defaults to supply power or

• In case of failure by OA supplier & the consumer meeting all his requirement from DL,

Energy settlement would be at highest of the following : • UI charge• At SMP levied under Intra State ABT mechanism• Temporary tariff as permitted in NTP

Page 43: Regulatory Challenges in  Reforming  Indian Power System

Unscheduled Interchange

• If an OA consumer is unable to draw scheduled energy due to failure of InSTS &/or network of DL, power injected may be treated as Banked Power & OA consumer may be allowed to draw the same within a period of 3 months with an advance notice of 24 hours to DL.

• Beyond 3 months, energy would be treated as lapsed.

Page 44: Regulatory Challenges in  Reforming  Indian Power System

Metering For OA consumer having load of >= 10 MW & all Gen Stations

irrespective of capacity, Special Energy Meters shall be installed by STU or DL as the case may be, for & at the cost of the customer.

SEM can be inspected by any person authorized by STU/ SLDC.

As regards OA consumers having load < 10 MW, the TOD meter shall be installed by DL concerned.

All OA customers shall follow Metering Standards of CEA.

Page 45: Regulatory Challenges in  Reforming  Indian Power System

States Allowing OA Power Procurement through Power Exchanges

• Punjab• Haryana• Uttarakhand• Himachal Pradesh• Madhya Pradesh• Rajasthan• Tamil Nadu

Page 46: Regulatory Challenges in  Reforming  Indian Power System

Volume on Power Exchanges

Jan'10 Feb'10 Mar'10 Apr'10 May'10 Jun'10 Jul'10 Aug'10 Sep'10 Oct'10 Nov'10 Dec'100.00

5.00

10.00

15.00

20.00

25.00

30.00

35.00

40.00

45.00

50.00

Average Volume(MUs)

Page 47: Regulatory Challenges in  Reforming  Indian Power System

Price on Power Exchange

Jan'10 Feb'10 Mar'10 Apr'10 May'10 Jun'10 Jul'10 Aug'10 Sep'10 Oct'10 Nov'10 Dec'100.00

1.00

2.00

3.00

4.00

5.00

6.00

7.00

8.00

9.00

Market Clearing Price(Rs/Unit)

Page 48: Regulatory Challenges in  Reforming  Indian Power System

BENEFITS OF OPEN ACCESS• Maharashtra is facing peak & energy deficits, even after

subsequent reforms programs, the utilities are not unable to bridge the gap and provide quality & reliable power supply to consumers.

• With OA, consumers are will get alternative sources of power from Market, may be, at a lower cost, & can have assured availability of power on demand

• Purchase of costly power to meet demand can be avoided, which will actually result in lower PP cost for DL, leading to lower tariffs for remaining utility consumers.

• However, Revenue of DL will get affected (CSS/ASC/SBC)

Page 49: Regulatory Challenges in  Reforming  Indian Power System

“If it is to be It is up to me!!”

Thanks!! (Contact me [email protected])

49

Page 50: Regulatory Challenges in  Reforming  Indian Power System

Parallel Distribution Licensee • MERC can grant distribution license to more

than one persons for distribution through their own networks in same area (6thproviso of S14)

• Implications: DL will face Competition in its HT & High Revenue Customers.

Page 51: Regulatory Challenges in  Reforming  Indian Power System

Determination of tariff Section 62 (1) proviso 1 (d)

• The appropriate Commission may determine tariff in accordance with provisions of this Act for (a) Generation (b) Transmission (c) Wheeling (d) retail sale of electricity

PROVIDED that, in case of distribution of electricity in the same area by two or more DL, the Commission may, for the purpose of promoting competition, among DLs, fix only maximum ceiling of tariff for retail sale of electricity.

Page 52: Regulatory Challenges in  Reforming  Indian Power System

Competition through parallel licensee

• SERC to grant License if investment meets GoI stipulated norms (S 14/Proviso 6)

• Tariff ceiling may be set by Regulator(S 62(1d))

• No time frame issue unlike OA: Commencement of operation by time & cost of roll out plan

Competition in retail through parallel network is an immediate possibility.

Page 53: Regulatory Challenges in  Reforming  Indian Power System

Main Difference

• OA: On incumbent licensee’s Network

• CSS/SB-Charges/ASC to be decided as the network of incumbent Licensee is used

• Parallel Licensee: DL will have to lay the network.

• Ceiling Tariff concept.

Page 54: Regulatory Challenges in  Reforming  Indian Power System

Case study: TPC-D and R Infra-D

• M/s Tata Cos had four licenses: 1907/1919/ 1921/ 1953 for sell, supply & distribute power to Bulk as well as retail consumers. GOM on 12/07/2001 transferred these to Tata Power.

• M/s BSES Ltd had license from 29/05/1926 & 13/05/1926 as DL in suburban Mumbai. R-Infra has taken over BSES.

• In Mumbai City: Four DLs : TPC-D (bulk Consumers & few Retail) /R-Infra-D (North Mumbai up to Vikhroli /BEST (South Mumbai )/MSEDCL (Mulund/Bhandup)

Page 55: Regulatory Challenges in  Reforming  Indian Power System

Case study: TPC-D and R Infra-D• Hon. Supreme Court Order dated 8th July 2008 allowing

supply of electrical energy in retail by TPC-D utilizing distribution network of the other licensee present in the area.

• “and allow these three appeals upon holding that under the Terms & Conditions of the licenses held by it ‘Tata Power Co. Ltd. Is entitled to effect supply of electrical energy in retail directly to consumers, whose MD is less than 1000 KVA, apart from its entitlement to supply energy to other licensees for their own purpose, and in bulk, within its area of supply as stipulated in its licenses.”

Page 56: Regulatory Challenges in  Reforming  Indian Power System

TPC Petition dated 30th August 2009

• R-Infra’s area of supply forms the part of TPC’s area of supply. Both have common areas to the extent of R-Infra’s area of supply .

• TPC proposes to use R-Infra’s existing Dist network system to ensure smooth Change over.

• Public Hearing on TPC’s petition 30th Sept 2009 & 8th Oct 2009 (136 persons present)

Page 57: Regulatory Challenges in  Reforming  Indian Power System

• Noting the consumer interest & their keenness to exercise the choice of supplier on immediate basis, MERC decided to issue interim order.

• Order issued on 15th Oct 2009 as per powers vested under Section 94(2) of EA 2003:

• “The appropriate Commission shall have powers to pass such interim order in any proceeding, hearing or matter before the Commission, as that Commission may consider appropriate.”

• No reference has been drawn to Section 42 of EA 2003 & Regulations issued there under, to avoid the applicability of Section 86(1)(a).

MERC Order..

Page 58: Regulatory Challenges in  Reforming  Indian Power System

Some issues about change over

• Period for change over: shall not exceed 30 days from the date of receipt of complete change over application form by TPC.

• Past Dues/liabilities & disconnection: As per Section 56 of EA. (Disconnection of supply in default of payment).

• Migration is not allowed to consumer who is in arrears, without clearing his dues or for a disconnected consumer (in arrears)

Page 59: Regulatory Challenges in  Reforming  Indian Power System

Shifting : Energy Meter Issues • Ownership of Energy Meters: Consumers have a

choice to continue with the existing meter of R-Infra/ Opt for meter from TPC / Purchase his own meter from third party

• Joint testing of meter at the time of migration• Meter for changeover consumers

to have downloadable capability • Common meter specifications

for third party meter purchase

Page 60: Regulatory Challenges in  Reforming  Indian Power System

• Meter reading for consumers to be done by TPC . As TPC will be responsible for Billing/ Collection & meter reading is an integral part of bill preparation.

• TPC will provide meter reading info to R-infra on daily basis along with the date& time

• TPC shall pay R-Infra wheeling charges within 21 days from date of bills raised on changeover consumers ,irrespective of payment of WC by consumers.

Shifting of consumers from RIL To TPC

Page 61: Regulatory Challenges in  Reforming  Indian Power System

• Security Deposit: Last month bill will be issued by RIL In case of non-payment of dues, RIL after deducting the SD available with them can disconnect the consumer, if the consumer does not pay the balance amount in time

• Theft & inspection: Any theft by meter tampering or bypassing meter leads to increased distribution losses for R-Infra and requires R-Infra to pay for this energy, in intra State pool at System Marginal price. To ensure that wheeling DL is able to manage distribution losses, it should have the RIGHT TO INSPECT and READ Consumer METER from time to time for detection & investigation of theft by way of meter tampering or bypassing the meter

Security Deposit & Theft detection

Page 62: Regulatory Challenges in  Reforming  Indian Power System

Retail tariffs (Energy Charges in PS/ per Unit)

Category Consumption TPC-D R-Infra-D BEST

LT Res 0-100 105 296 155

101-300 250 556 330

301-500 440 916 530

>500 530 1061 680

LT Com 0-20 KW 425 795 400-760

20-50 KW 480 1026 730

>50 KW 505 1091 755

LT IND 0-20KW 450 776 370-595

> 20 KW 460 1077 640-700

HT IND 500 756 505

HT Com 485 841 715

Page 63: Regulatory Challenges in  Reforming  Indian Power System

Calculation of tariff forChange-over consumers

• Tariff for Change-Over consumers = Charges based on tariff of supply DL (-) Wheeling Charges of Supply DL [a]

(+) Wheeling Charges of wheeling DL [b]

(a) HT = 18 Ps/KWH & LT = 37 Ps/KWH (b) HT = 46 Ps/KWH & LT = 88 Ps/KWH

Two DL: Supply (Tata), Wheeling: R-infra

• About 90,000 Consumers shifted from R-Infra to TPC. Applications received 50,000 (+) MIAL Case: Daily savings Rs 10.5 Lakh

• Residential (monthly bill in Rs) : Savings :13.5% to 31.2%

Page 64: Regulatory Challenges in  Reforming  Indian Power System

Conclusions • EA 2003: Engineers/Economists/Lawyers

Engineers: like to operate sophisticated PSEconomists: like to work on optimal incentivesLawyers: like to write rules & agreement Power sector reform brings all of them into close contact. But None of them can succeed at their chosen tasks, unless they work together in designing sustainable solutions for the Customers”

Page 65: Regulatory Challenges in  Reforming  Indian Power System

Important issues in Cross Subsidy Reduction

• Analysis of various MERC tariff orders: No definite pattern for CS is being followed.

• CSR plan for each utility, to be prepared, separately.

• We are in the process of finalizing the Roadmap & simultaneously preparing the draft Regulations.

Page 66: Regulatory Challenges in  Reforming  Indian Power System

ACOS for various utilities

•MSEDCL: 455 P/U•BEST: 575 P/U•TPC-D: 520 P/U•R-Infra-D: 635 P/U

Page 67: Regulatory Challenges in  Reforming  Indian Power System

Categories having >1% of total Sale AND /OR >1% of total consumers AND > 1% Revenue

Utility ACOS (Ps/Unit)

Min ABR (Ps/U) Categories

Max ABR (Ps/U) Category

MSEDCL 455 210(46%) LT V- AG

845 (186%) HT-Com

BEST 575 368 (64%) LT-Res

755 (131%) HT- Com

R-Infra (*) 706 524 (74%) LT- I- Res

952 (135%) LT-II- Com

TPC-D 520 395 (76%) LT-I- Res

551 (106%) HT-Com

Page 68: Regulatory Challenges in  Reforming  Indian Power System

Three step in Cross subsidy Reduction

• Step I: Inter category Cross subsidy Reduction based on Average cost of supply for utility

• Step II: Inter category Cross subsidy Reduction based on cost to serve for each category

• Step III: Intra category (sub-category wise) cross subsidy reduction

Page 69: Regulatory Challenges in  Reforming  Indian Power System

Tariff Subsidy by GOM (Consumers to pay at a lesser tariff than approved by

MERC)

Financial Year AG Consumers (Rs CR)

P/L Consumers (Rs CR)

Total Subsidy (Rs CR)

FY 2005-06 1309 333 1642FY 2006-07 1229 484 1713FY 2008-09 1305 471 1776FY 2009-10 1397 485 1882FY 2010-11 1865 658 2523

Page 70: Regulatory Challenges in  Reforming  Indian Power System

Important issues • Categories having Sale <1% of total Sale AND/OR Consumers <1%

of total consumers AND Revenue <1% of total Revenue are not considered in study at the initial stage

• Utilities need to carry out Cost to Serve (Cost of Service) studies for various category of consumers. (Within 24 months)

• Initially, roadmap based on ACOS (five year road map)

• After the results of Cost to Serve studies for each category, roadmap modification will be taken up. Finally, intra-category CSR can be taken up

Page 71: Regulatory Challenges in  Reforming  Indian Power System

CS IN MSEDCL (FY 2010-11)SUBSIDIZING CATEGORIES

ACOS= RS.4.55/KWH Total CS = Rs. 5020 Cr in total ARR of Rs 32056 Cr (15.7%) [64% from IND & 31% from COM]

CATEGORY SALE MU

ABR % of ACOS

CS= (ABR-ACOS)

CS IN RS. CR

% of Total CS

LT-COM 3814 686 151% (*) 231 881 18%

LT IND 4549 537 118% 82 373 7%

HT IND 25024 570 125% (*) 115 2878 57%

HT-COM 1620 845 186% (*) 390 632 13%

RLYS 1427 604 133% (*) 149 212 4%

Page 72: Regulatory Challenges in  Reforming  Indian Power System

CS IN MSEDCL (FY 2010-11) Subsidized Categories[71%to AG & 19% Domestic]

CATEGORY SALE MU ABR % of ACOS

CS= (ABR-ACOS)

CS IN RS. CR

% CS of TTL CS

LT-Res 12478 379 83% 76 948 19%

LT PWW 591 226 50% (*) 229 135 3%

LT Ag 14057 210 46% (*) 245 3444 69%

HT Ag 496 248 54% (*) 207 102 2%

HT PWW 1190 417 92% 38 45 1%

MPECS 743 296 65% (*) 159 118 2%

Page 73: Regulatory Challenges in  Reforming  Indian Power System

Other SERCs…. • Karnataka: No CSR Road map. ACOS approach in

tariff Order. No intra class CSR.

• Punjab: CSR Regulations in place. ACOS approach followed. Discoms directed to carry out category wise Cost of supply. No mention of intra class CS.

• Gujrat: CSR road map not issued. Study is being taken up

Page 74: Regulatory Challenges in  Reforming  Indian Power System

Other SERCs… • AP: No specific road map & just trying CSR. COS approach to

be used. CS to be brought into +/-20 % level

• Delhi: Does have specific CSR Road map. But decided to use ACOS approach (No specific mention of intra-class CSR)

• Orissa: Tariff Policy being followed for deciding allowable level of CS. There is an intra- Discom CS. No specific mention about the method/Road map for CSR. (No mention about Intra-Class CSR)

Page 75: Regulatory Challenges in  Reforming  Indian Power System

MPERC Notification: 06/10/2010: LT(ABR as % of ACOS of that FY)

Category FY 08-09 FY 09-10 FY 10-11 FY 11-12

Dom 93 93 94 95

Non-Dom 152 140 130 120

PWW 86 90 92 95

IND 121 121 121 120

AG Met 67 67 73 80

St Light 100 100 100 100

Page 76: Regulatory Challenges in  Reforming  Indian Power System

MPERC Notification: 06/10/2010: HT(ABR as % of ACOS of that FY)

Category FY 08-09 FY 09-10 FY 10-11 FY 11-12

RLY 128 123 123 120

Coal mines 149 140 130 120

PWW 88 90 92 95

IND 125 124 122 120

Non-IND 136 131 126 120

Seasonal 179 160 140 120

Bulk-Res 97 97 97 97

Bulk supply 80 85 90 95

Page 77: Regulatory Challenges in  Reforming  Indian Power System

CS Reduction: Rs 341 CR to be reduced per year (considering ACOS remains constant for 5 years)

Category Present ABR %

Year 1 Year 2 Year 3 Year 4 Year 5

LT –COMABR

CSR in Rs Cr

151%685

145%660

-107

139%632

-107

-132% 610

-107

126%573

-107

120% 546

-107HT-IND

ABRCSR

125%570

124%565

-120

123%560

-120

122%555-12

121%550

-120

120%546

-120HT-COM

ABRCSR

186%845

173%786-97

160%727-97

147%668-97

134%609-97

120%545-97

RLYSABR

CSR

133%604

130%590-16

127%576-16

125%568-16

122%554-16

120%545-16

Page 78: Regulatory Challenges in  Reforming  Indian Power System

CS : Rs 252 CR to be increased per year (considering ACOS remains constant for 5 years)

Category Present ABR %

Year 1 Year 2 Year 3 Year 4 Year 5

LT –PWWABR

CSR in Rs Cr

50%226

56%253

16

62%280

16

68%307

16

74%334

16

80%363

17LT-AgABRCSR

46%210

49%221217

53%239217

57%257217

61%275217

65%293217

HT-AgABRCSR

54%247

58%265

9

62%284

9

66%302

9

70%321

9

74%339

9MPECSL

ABRCSR

65%295

68%309

10

71%322

10

74%336

10

77%349

10

80%363

10

Page 79: Regulatory Challenges in  Reforming  Indian Power System

Some imp issues…. • LT AG tariff: 46% to 65% in 5 years (CSR in 10 years)• HT AG tariff: 54% to 74% in 5 years (CSR in 7 years)• CSR/ Year: Rs. 340 Cr/year Rise: 252 Cr/year • Balance amount to be increased in categories with

ABR>80 & <100%, e.g. LT-I• Main issues: Fuel prices rising, sales is also rising • ACOS = Total ARR/Sale will accordingly change. • Category wise sale is also changing, ABR will accordingly

go up or down • CSR Model needs to take care of these issues & based

on the trajectory, the revised tariff needs to be fixed.

Page 80: Regulatory Challenges in  Reforming  Indian Power System

Conclusions…

• CS reduction roadmap being prepared & CSR regulations being prepared

• Final draft under preparation

• CS Surcharge for each utility will be computed & computations will be sent to stakeholders for comments.

Page 81: Regulatory Challenges in  Reforming  Indian Power System

Reforming the Existing system “Many of the

important things in the world have been

accomplished by the people,

who kept on trying, even when

there seem to be no hope at all”

Dale Carnegie

Page 82: Regulatory Challenges in  Reforming  Indian Power System

Thank You([email protected])

82


Recommended