+ All Categories
Home > Documents > Reliability and Safety Assessment in Offshore and Process ... · reliability modelling The IEC...

Reliability and Safety Assessment in Offshore and Process ... · reliability modelling The IEC...

Date post: 17-Mar-2020
Category:
Upload: others
View: 12 times
Download: 1 times
Share this document with a friend
33
Reliability and Safety Assessment in Offshore and Process Industries PSAM 7 / ESREL ´04 Berlin, Germany Lars Bodsberg SINTEF, Trondheim, Norway 1
Transcript

Reliability and Safety Assessment in Offshore and Process Industries

PSAM 7 / ESREL ´04Berlin, Germany

Lars BodsbergSINTEF, Trondheim, Norway

1

”All models are wrong! Some are useful.”

(G.E. Box)

2

Empirical Safety Control:Traffic and work safety

Evolutionary Safety Control:Air craft crashes,

train collision

Analytical Safety Control:e.g., Major nuclear and

chemical hazards(CEC Seveso directive)

1

2

3

Control of accidentprocess based onpredicitive analysis ofpossible accidents

Control of accident processitself from reaction to individualpast accidents

Control of conditions andcauses from epidemiologicalanalysis of past accidents

HighLow Consequence of accident

Num

ber o

f acc

iden

ts c

ontri

butin

g to

tota

l los

s

Few

Many

Adapted from J. Rasmussen

Safety Management Principles

3

© Norsk Hydro

4

IEC 61508 and IEC 61511

The International standard IEC 61508: Functional safety of electrical/-electronic/programmable electronic (E/E/PE) safety-related systems“(7 parts)

Generic standard

The International standard IEC 61511: Functional safety –Safety instrumented systems for the process industry sector (3 parts)

Sector specific standard

5

Widespread use of IEC 61508 and IEC 61511 in the Norwegian Petroleum Industry

The Petroleum Safety Authority Norway recommends the use of IEC 61508

The Norwegian Oil Industry Association (OLF) provides financial support to a joint industry project between operators and the various suppliers of services and equipment to establish a guideline

Guideline published at: www.itk.ntnu.no/sil

6

IEC 61508: Functional safety of electrical/-electronic/programmable electronic (E/E/PE) safety-related systems“

Generic standard, i.e.:Providing general framework, covering a wide range of complexity, hazards and risk potentialsConceived with a rapidly developing technology in mind - framework sufficiently robust and comprehensive

Major objective:Facilitate development of sector specific standardsProvide consistency within and across application sectorsProvide a generic approach for all lifecycle activitiesProvide qualitative and quantitative safety requirements to safety systems

7

IEC 61508 Overall

life cycle

Safety-relatedsystems:E/E/PES

Realisation

9

Concept1

Hazard & RiskAnalysis

3

Overall SafetyRequirements

4

Safety RequirementsAllocation

5

Overall Installation &Commissioning

12

OverallSafety Validation

13

Overall Operation &Maintenance

14

Decommissioning16

External RiskReductionFacilities

Realisation

11Safety-relatedSystems:

OtherTechnology

Realisation

10

Overall Modification& Retrofit

15

Back to appropriateOverall Safety Lifecycle

phase

Overall ScopeDefinition

2

OverallOperation&

MaintenancePlanning

OverallValidationPlanning

OveralIInstallation& Commis-

sioningPlanning

Overall Planning

7 86

8

Development of Safety System Requirements

Isolate and depressurize vessel

9999 out of 10000times

EUC Hazard

Risk

EUCrisk

Overpressure

Tolerablerisk

Safety requirements&

Safety Integrity Level

E/E/PES

OtherSafety-relatedsystems

Externalfacilities

Not part ofIEC 61508

Allocation

R

Design, etc

Req.

h/w s/w

9

Risk reduction in IEC 61508 - General concept

Tolerable risk

EUC risk

Necessary risk reduction

Actual risk reduction

Increasingrisk

Residualrisk

Partial risk covered by E/E/PE

safety-related systems

Partial risk covered by other technology

safety-related systems

Partial risk covered by external risk

reduction facilities

Risk reduction achieved by all safety-relatedsystems and external risk reduction facilities

Source: IEC 61508

10

Safety Integrity Level - SIL

SAFETYINTEGRITY

LEVEL- SIL

4

3

2

1

DEMAND MODE OFOPERATION

(Probability of Failureon Demand - PFD)

≥10-5 to < 10-4

≥ 10-4 to < 10-3

≥ 10-3 to < 10-2

≥ 10-2 to < 10-1

CONTINUOUS/HIGHDEMAND MODE OF

OPERATION(Probability of a dangerous

failure per hour)

≥ 10-9 to < 10-8

≥ 10-8 to < 10-7

≥ 10-7 to < 10-6

≥ 10-6 to < 10-5

11

IEC 61508 implications on safety and reliability modelling

The IEC 61508 standard sets out a risk-based approach for deciding the Safety Integrity Level (SIL) for systems performingsafety functions

On-going R&D to improve QRAs in Norway.

The IEC 61508 standard requires evaluation of reliability performance of the safety instrumented systems

The PDS method

12

13

Comparison PRA vs. QRATopic PRA QRA

Initiating events Root cause analysis of initiating events presented in fault trees. Identification of common cause initiators (CCIs). Predefined lists and handbooks.

No root cause analysis No CCI assessment Predefined categories of leakage Frequencies based on counting leakage point, or platform data.

Fault tree/ event tree analysis (system modeling)

Detailed modeling Support systems explicitly modeled. Link between event trees and fault trees. (Time-dependent models for living PSA).

Rough model Support systems not included Only partly use of fault trees No linking of event and fault trees.

Data and parameter estimation

Best estimates and confidence intervals. Classical and Bayesian framework. ‘Weighted’ plant-specific data

Best estimates Generic data and separate plant-specific data

Human reliability

Thorough analysis of important human actions (e.g. by THERP, SHARP, etc.).

Almost non-existing

Dependencies Partly inherent in models Separate dependency analysis Regarded as crucial

Partly inherent in models No separate analysis

Uncertainty Always included, at least qualitatively. Regarded as important

Absent

External events Covers some external events Linked to the ‘internal’ event

Covers many external events Separate analysis (Limited modeling effort)

Results Best estimate and uncertainty in short and long term fatalities. Cumulative distribution functions.

Single best estimate FAR-, and PLL-values

Reliability Assessment of Safety Instrumented Systems – the PDS Method

14

15

16

Balance between production and protection

Reason (1998)

Protection

Production

High Integrity Pressure Protection System (HIPPS)

RedundantLogic

PT2

PT1

V 2V 1

PT3

17

Safety performance – voting logic

0.006

0.005

0.004

0.003

0.002

0.001

Probability of failure on demand

Primary Investment2oo2 voting

1oo1 voting

2oo3 voting

1oo2 voting

18

Safety vs. LCC –Low Unavailability Cost pr Trip

Acceptance criteria

0.006

0.005

0.004

0.003

0.002

0.001

Probability of failure on demand

100 200 300 400 500

Primary Investment

Operation and maintenance cost

Unavailability cost pr trip

LCC in 1 000 Norwegian kroner

2oo2 voting

1oo1 voting

2oo3 voting

1oo2 voting

19

Safety vs. LCC –High Unavailability Cost pr Trip

Acceptance criteria

0.006

0.005

0.004

0.003

0.002

0.001

100 200 300 400 500

LCC in 1 000 Norwegian kroner

Probability of failure on demand

Primary Investment

Operation and maintenance cost

Unavailability cost pr trip

2oo2 voting

1oo1 voting

2oo3 voting1oo2 voting

20

Gareth Morgan

21

Failure Mode Classification in PDS and IEC

Safe (S)

Failure

Dangerous (D)

Spurious Trip (ST)

IEC

PDS

Non-critical(NONC)

22

Main Failure Modes in PDS

Dangerous (D)Safety system/module does not operate on demand(e.g. sensor stuck upon demand)

Spurious Trip (ST)Safety system/module operates without demand(e.g. sensor provides signal without demand)

Non-Critical (NONC)Main functions not affected(e.g. sensor imperfection which has no direct effect on control path)

The IEC standard does not distinguish between ST and NONC failures; both are referred to as Safe failures

23

Failure Cause Classification in PDS and IEC

Failure

Systematic(Non-physical)

Ageing Stress Interaction Design

Naturalageing(within designenvelope)

SandblastingHumidityOverheating

Software errorSensor doesnot distinguishtrue and falsedemandWrong locationof sensor

Examples Random Test/periodic

Scaffoldingcover upsensor

Leave inby-passCover upsensor

Random Hardware(Physical)

IEC

PDS

24

Loss of Safety Quantification in PDS and IEC

Failure

Systematic(Non-physical)

Ageing Stress Interaction Design

Random Hardware(Physical)

IEC

PDS

25

Reliability Performance MeasuresLoss of safety.

Critical Safety Unavailability (CSU):“The probability that the safety system will fail to automatically carry out a successful safety action on the occurrence of a hazardous/-accidental event”Probability of Failure on Demand (PFD):That part of CSU which is caused by random hardware failures

Loss of production regularity.Spurious Trip Rate (STR):“The mean number of spurious activations of the safety system per unit time”

Maintenance activity.Mean Corrective Maintenance (MCM):“The mean number of man-hours spent on CM per year”Mean Preventive Maintenance (MPM):“The mean number of man-hours spent on PM per year”

IECIEC

26

Loss of Safety Calculations - Example

Component PFD Random hardware

PSF Systematic

CSU Total

PT (1oo2) 1.1 ⋅10-5 3.6 ⋅10-5 4.7⋅10-5

Logic (1oo2) 0.2 ⋅10-5 2.5 ⋅10-5 2.7⋅10-5

V (1oo2) 11.8⋅10-5 0.03⋅10-5 11.8⋅10-5

Total 13.1⋅10-5 6.1⋅10-5 19.2⋅10-5

27

Safety require-ments allocation5

Overall operation andmaintenance planning6

RAMS targets andtradeoff values

Updated Relia-bility parameters

Followup plan

Maintenanceplan

Work Ordersystem

Overall operation,mainteance and repair14

Actual PM& CM

Follow upactions

Op. restrict.Budget allocation

Resource allocationInfrom regulator (NPD)

Data-base

DataAnalysis

Overall modifica-tion and retrofit15

Reporting

Generic Relia-bility parameters

Trends, Pareto, CCF, FCA etcExtended reliability databases

Manufactures and vendorsInfrom regulator (NPD)

Inprovementmeasures Failures

BacklogPM & CM

28

Summary

Risk-based approach adopted in Norwegian offshore productionWidespread application of the IEC 61508 standardRequirements to safety functions can normally not be obtained directly from the Quantitative Risk Analysis (QRA) as it is performed today. Cooperation between regulatory authorites, industry and R&D to establish guideline document for IEC 61508Ongoing research to improve QRAReliability analysis should support the balance betweenproduction and protection

29

IEC 61508 and 61511 – Lessons learned

Provides good framework for design, implementation and operation of safety-related systems

Sensible risk-based approach, however in an area, and at a level of detail, which is not yet very mature

Difficult to apply for systems involving several vendors“global functions”

30

”All models are wrong! Some are useful.”

(G.E. Box)

31

References

Reliability Prediction Method for Safety Instrumented Systems; PDS Method Handbook, 2003 EditionPublished by SINTEF (www.sintef.no/pds) and distributed by Sydvest(www.sydvest.com)

Reliability Data for Safety Instrumented Systems;PDS Data Handbook, 2003 EditionPublished by SINTEF (www.sintef.no/pds) and distributed by Sydvest(www.sydvest.com)

Application of IEC 61508 and IEC 61511 in the Norwegian Petroleum IndustryPublished at www.itk.ntnu.no/sil

32

Lars BodsbergPh.D - Research Director

Lars BodsbergPh.D - Research Director

SINTEF, Safety and ReliabilityN-7465 Trondheim

Telephone: +47 73 59 27 58Telefax: +47 73 59 28 96

http://www.sintef.no

SINTEF, Safety and ReliabilityN-7465 Trondheim

Telephone: +47 73 59 27 58Telefax: +47 73 59 28 96

http://www.sintef.no33


Recommended