+ All Categories
Home > Documents > Reliability_Calculations.ppt

Reliability_Calculations.ppt

Date post: 17-Jan-2016
Category:
Upload: ekofujisyahmaulwanto
View: 6 times
Download: 1 times
Share this document with a friend
35
© 2002 Eaton Corporation. All rights reserved. Designing for System Reliability Dave Loucks, P.E. Eaton Corporation
Transcript
Page 1: Reliability_Calculations.ppt

© 2002 Eaton Corporation. All rights reserved.

Designing for System Reliability

Dave Loucks, P.E.

Eaton Corporation

Page 2: Reliability_Calculations.ppt

“Reliability is achieved through sound design, the proper application of parts, and an understanding of failure mechanisms. It is not achieved by estimating it or calculating it. Estimation and calculation are, however necessary to help determine feasibility, assess progress and provide failure probabilities and frequencies to spares calculations and other analyses.”

US Army TM 5-698-1 B-1

Page 3: Reliability_Calculations.ppt

Reliability ABCs

Gold Book (IEEE Std. 493-1997) Annual Risk - The calculated financial losses of

production due to an electrical system failure divided by the frequency (MTBF) of the failure.

Availability - A ratio that describes the percentage of time a component or system can perform its function.

Failure - The termination of the ability of an item to perform a required function.

Failure rate - The mean number of failures of a component per unit exposure time.

Page 4: Reliability_Calculations.ppt

Reliability ABCs cont’d Forced downtime - The average time per year a system is

unavailable in between failures and expressed in hours per year.

Lambda - Failure Rate () - The inverse of the mean exposure time between consecutive failures. Lambda is typically in either years per failure or millions of hours per failure.

MTBF - The mean exposure time between consecutive failures of a component or system in either failures per year or failures per million hours. For some applications measurement of mean time between repairs (MTBR) rather than mean time between failures may provide more statistically correct information.

Page 5: Reliability_Calculations.ppt

Designing for Reliability

Sound Design Proper Application of Parts (Components,

Systems) Understanding of Failure Mechanisms

Page 6: Reliability_Calculations.ppt

What Reliability Is Seen At The Load?

Utility UPS Breaker Load

For example, if power flows to load as below: Assume outage duration exceeds battery capacity

Page 7: Reliability_Calculations.ppt

Series Components

Utility UPS Breaker Load

99.9% 99.99% 99.99%

For example, if power flows to load as below: Assume outage duration exceeds battery capacity

Page 8: Reliability_Calculations.ppt

Series Components For example, if power flows to load as below:

Assume outage duration exceeds battery capacity

Utility UPS Breaker Load

99.9%(8.7 hr/yr)

99.99%(0.87 hr/yr)

99.99%(0.87 hr/yr)

x+

x+

==

99.88%(10.5 hr/yr)

Overall reliability is poorer than any component reliability

Page 9: Reliability_Calculations.ppt

Series Components For example, if power flows to load as below:

Assume outage duration exceeds battery capacity

Utility UPS Breaker Load

99.9%(8.7 hr/yr)PF* = 0.1%

99.99%(0.87 hr/yr)

0.01%

99.99%(0.87 hr/yr)

0.01%

x++

x++

===

99.88%(10.5 hr/yr)

0.12%

PF = (1 – Reliability) = 1 – R(t)

* PF = probability of failure

Page 10: Reliability_Calculations.ppt

Series Components For example, if power flows to load as below:

If outage duration less than battery capacity

UPS Breaker Load

99.99%(0.87 hr/yr)

0.01%

99.99%(0.87 hr/yr)

0.01%

x++

===

99.98%(1.74 hr/yr)

0.02%*PF =

Batteries Depleted 99.88% reliable Batteries Not Depleted 99.98% reliable

Page 11: Reliability_Calculations.ppt

Parallel Components What if power flows to load like this:

Assume outage duration exceeds battery capacity

Utility

UPS

StaticATS

Load

UPS

Page 12: Reliability_Calculations.ppt

Parallel Components

Utility

UPS

StaticATS

Load

UPS99.9%

99.99%

99.99%

99.99%

?? %

What if power flows to load like this: Assume outage duration exceeds battery capacity

Page 13: Reliability_Calculations.ppt

Parallel Components

Utility Load

99.9%

99.99%

99.99%

99.99%PF* = 0.1% PF(a or b)+ + = ?? %

?? %

UPS

StaticATS

UPS

0.01%

What if power flows to load like this: Assume outage duration exceeds battery capacity

Page 14: Reliability_Calculations.ppt

Parallel Components

99.99%

99.99%PF(a or b) = 0.01 % x = 0.000001 %

99.99 %

UPSa

UPSb

0.01%

What if power flows to load like this: Solve each path independently

99.99%

99.99%

UPSa

UPSb

99.99 %

R(t) = 1 - PF(a or b) = 99.999999%

Page 15: Reliability_Calculations.ppt

Parallel Components

Utility Load

99.9%99.99%

99.999999%

99.89 %

UPSa

orUPSb

StaticATS

Multiply the two Probabilities of Failure, PF(a) and PF(b) and subtract from 1

PF(total) = PF(u) + PF(a or b) + PF(s)= 0.1% + 0.000001% + 0.01% = 0.110001%

Page 16: Reliability_Calculations.ppt

Parallel Components

Load

99.99%

99.999999%

99.99 %

UPSa

orUPSb

StaticATS

Multiply the two Probabilities of Failure, PF(a) and PF(b) and subtract from 1

PF(total) = PF(a or b) + PF(s)= 0.000001% + 0.01% = 0.010001%

Page 17: Reliability_Calculations.ppt

Summary Table

Configuration Reliability

Single UPS system (long term outage) 99.88%

Single UPS system (short term outage) 99.98%

Redundant UPS system (long term outage) 99.89%

Redundant UPS system (short term outage) 99.99%

Comments?

Page 18: Reliability_Calculations.ppt

Value AnalysisIs going from this:

Utility UPS Breaker

Utility

UPS

StaticATS

99.89%(only battery) 99.99%

UPS

99.88%(only battery) 99.89%

to this

worth it?

0.01%difference

Page 19: Reliability_Calculations.ppt

Value Analysis

99.98% x 8760 = 8752 hours on and 8 hours off 99.99% x 8760 = 8759 hours on and 1 hour off With the second solution you are on 7 more

hours per year What is 7 hours worth? What is the second UPS worth?

Page 20: Reliability_Calculations.ppt

Breakeven Analysis

Total Economic Value (TEV) Simple Return (no time value of money) TEVS = (Annual Value of Solution x Years of Life of

Solution) – Cost of Solution

Assume 1 hour of downtime worth $10000 Assume cost of solution is $30000 Assume life of solution is 10 years

Page 21: Reliability_Calculations.ppt

Breakeven Analysis

Total Economic Value (TEV) Simple Return (no time value of money) TEVS = (Annual Value of Solution x Years of Life of

Solution) – Cost of SolutionTEVS = (($10000 x 7) x 10) – $30000

TEVS = $700000 - $30000 = $670000

Discounting cash flow at 10% cost of money TEVD = NPV($70000/yr, 10 yrs) – $30000

TEVD = $430120 – $30000 = $400120

Page 22: Reliability_Calculations.ppt

Reliability Tools

Eaton Spreadsheet Tools IEEE PCIC Reliability Calculator Commercially Available Tools Financial Tools (web calculators)

Page 23: Reliability_Calculations.ppt

Web Based Financial Analysis

www.eatonelectrical.com search for “calculators” Choose “Life Extension

ROI Calculator”

Page 24: Reliability_Calculations.ppt

Web Based Financial Analysis

Report provides financial data

Provides Internal Rate of Return

Use this to compare with other projects competing for same funds

Evaluates effects due to taxes, depreciation

Based on IEEE Gold Book data

Page 25: Reliability_Calculations.ppt

Uncertainty – Heart of Probability

Probability had origins in gambling What are the odds that …

We defined mathematics resulted based on: Events

• What are the possible outcomes?

Probability• In the long run, what is the relative frequency that an event

will occur?

• “Random” events have an underlying probability function

Page 26: Reliability_Calculations.ppt

Normal Distribution of Probabilities

From absolutely certain to absolutely impossible to everything in between

AbsolutelyCertain

100%

0%AbsolutelyImpossible

Most likely value

Page 27: Reliability_Calculations.ppt

Distribution System Reliability How do you predict when something is going to

fail? One popular method uses exponential curve

AbsolutelyCertain

37% of them are working

50% of them are working

69%

50%

Page 28: Reliability_Calculations.ppt

Mean Time Between Failures

The ‘mean time’ is not the 50-50 point (1/2 are working, 1/2 are not), rather…

When device life (t) equals MTBF (1/), then:

368011

.)(

eeetRt

MTBFt

The ‘mean time’ between failures when 37% devices are still operating

Page 29: Reliability_Calculations.ppt

MTBF Review

Remember, MTBF doesn’t say that when the operating time equals the MTBF that 50% of the devices will still be operating, nor does it say that 0% of the devices will still be operating. It says 37% (e-1) of them will still be working.

Said another way; when present time of operation equals the mean (1/2 maximum life), the reliability is 37%

Page 30: Reliability_Calculations.ppt

Exponential Probability

Assumes (1/MTBF) is constant with age For components that are not refurbished, we

know that isn’t true. Reliability decreases with age ( gets bigger)

However, for systems made up of many parts of varying ages and varying stages of refurbishment, exponential probability math works well.

Page 31: Reliability_Calculations.ppt

Reliability versus MTBF

Assume at time = 0 Reliability equals 100% (you left it running)

At time > 0, Reliability is less than 100%

tMTBFt eetR

1

)(

Page 32: Reliability_Calculations.ppt

Converting MTBF to Reliability

Unknown Reliability = ?

Known MTBF (40000 hrs) t (8760 hrs = 1 year)

tMTBFt eetR

1

)(

UPS

%.

)(

.

380

21908760

40000

1

1

ee

eetRt

MTBFt

Page 33: Reliability_Calculations.ppt

Availability

Increase Mean Time Between Failures (MTBF) Decrease Mean Time To Repair (MTTR)

%100

MTTRMTBF

MTBFAi

i

i

A

AMTBFMTTR

)(

100

Page 34: Reliability_Calculations.ppt

0.65

0.7

0.75

0.8

0.85

0.9

0.95

1

0 10 20 30 40 50 60 70 80 90 100

MTTR (Hours)

Av

aila

bili

ty

1000 hrs800 hrs600 hrs

400 hrs

200 hrs

MTBF

Page 35: Reliability_Calculations.ppt

0.65

0.7

0.75

0.8

0.85

0.9

0.95

1

0 10 20 30 40 50 60 70 80 90 100

MTTR (Hours)

Av

aila

bili

ty

1000 hrs800 hrs600 hrs

400 hrs

200 hrs

MTBF

10.5 21.1 31.6 42.1 52.6