+ All Categories
Home > Documents > RELIANCE PETROCHEMICAL PLANT - sarens.com · Jamnagar - Gujarat - India ... Sarens executed all the...

RELIANCE PETROCHEMICAL PLANT - sarens.com · Jamnagar - Gujarat - India ... Sarens executed all the...

Date post: 10-Dec-2018
Category:
Upload: phungliem
View: 221 times
Download: 0 times
Share this document with a friend
2
NOTHING TOO HEAVY, NOTHING TOO HIGH RELIANCE PETROCHEMICAL PLANT OIL AND GAS LOCATION Jamnagar - Gujarat - India CLIENT Reliance Industries Limited PROJECT SUMMARY Sarens executed all the superheavy lifts for the new refinery expansion at the Reliance Petrochemical Plant. Reliance claims to own the biggest petrochemical plant (30.000.000 m 2 ) in the world and to be in possession of over 1.000 cranes. At the project’s peak, there was an on- site workforce in excess of 110.000 per day.
Transcript
Page 1: RELIANCE PETROCHEMICAL PLANT - sarens.com · Jamnagar - Gujarat - India ... Sarens executed all the superheavy lifts for the new refinery expansion at the Reliance Petrochemical Plant.

NOTHING TOO HEAVY, NOTHING TOO HIGH

THE SECOND SARENS GENERATION, CIRCA 1960S

RELIANCE PETROCHEMICAL PLANT

OIL AND GAS

• LOCATION

Jamnagar - Gujarat - India

• CLIENT

Reliance Industries Limited

• PROJECT SUMMARY

Sarens executed all the superheavy lifts for

the new refinery expansion at the Reliance

Petrochemical Plant. Reliance claims to

own the biggest petrochemical plant

(30.000.000 m2) in the world and to be in

possession of over 1.000 cranes.

At the project’s peak, there was an on-

site workforce in excess of 110.000 per day.

Page 2: RELIANCE PETROCHEMICAL PLANT - sarens.com · Jamnagar - Gujarat - India ... Sarens executed all the superheavy lifts for the new refinery expansion at the Reliance Petrochemical Plant.

SGC PROJECT SUCCESS

ENGINEERING IS THE CLOSEST THING

TO MAGIC THAT EXISTS IN THE WORLD.

ELON MUSK, CIRCA 2015.

NOTHING TOO HEAVY, NOTHING TOO HIGH

• OBJECTIVE

- The SGC-120 performed five critical lifts and

about seven structural modules. The operation

required working in four locations with one

Benny” alias for the SGC-120, (named after late

Executive Board member, Benny Sarens, who

was the group’s driving force behind the design,

development, and construction of the crane).

- The primary challenge was to assemble the

crane in the shortest time possible.

• SOLUTIONS

- The project required three crane relocations.

- Thanks to the joint efforts of the Engineering

department and the site team, Sarens was able

to move larger crane parts among different

crane positions, in order to minimize relocation

time.

• RESULTS

- Safe and secure execution

- No accidents or incidents


Recommended